This document discusses ensuring quality in civil construction projects. It defines quality as excellence that meets certain standards. Quality control procedures implement proper mixing, compaction, placement and curing of construction materials. Following a plan-do-check-act cycle can help assure quality. Common construction mistakes that reduce quality are also outlined, such as inadequate compaction, improper reinforcement, and poor workmanship. Causes of poor quality include ignorance, substandard materials and design, and lack of supervision. The relationship between quality, cost and value is examined.
2. Ensuring Quality in civil Construction
Presented by :
Er. P. Das,(M.Tech.Civil )A.E, Jatni.
Under the guidance of
Er. Mahendra Kumar Mohanty
EE,DRDA,KHORDA
2
3. Definition of Quality
Quality means excellence.
It is thus a philosophy rather than a mere attribute.
The difference between two objects
is judged by their qualities.
We set some standards which
determine the level of acceptability.
3
4. Quality control:-
Quality control means rational use of resources.
Quality control procedures implement:-
appropriate mixing,
proper compaction,
correct placement and
adequate curing.
Quality control prevents temptation of over
design.
4
5. Quality Controls-----
Quality control ensures:-
strict monitoring of every stage of
concrete production and
rectification of faults.
Quality control reduces maintenance
costs.
5
6. Plan, Do, Check and Act cycle
for assuring quality
6
Plan :-quality
Do :- Working
systematically
Check:-
checking with
non
conformance
Act :-Upon
the result
7. The cement sand mix in the mortar and brick
masonry is made quite early, prior to its use and in
larger quantities than required.
The construction materials like sand, bricks,
Aggregate etc are not washed and are full of
deleterious material and dust.
7
Knowing the 20 No mistakes occurr during
construction phase ( for planning purpose )
8. construction mistakes
Compaction of bottom strata in foundation
work is not carried out.
During concreting of footing, the concrete is
poured at a height greater than 1m.
Generally, trapezoidal footings are resorted
to where concrete is never vibrated.
8
9. construction mistakes
Reinforced concrete column, being an
important part of the structure are neither
mechanically vibrated nor machine mixed.
They are cast in short lifts with increased
number of joints.
Cover to reinforcement in column, beams
and slabs is insufficient.
9
10. construction mistakes
No cover to reinforcement in contact of the
ground
Misalignment of column at foundation level
and rectification at higher level, leading to
eccentric loading.
Reinforced coping at plinth level being an
important barrier to dampness is never
densely cast.
10
11. The plinth filling is never carried out
in layers nor compacted.
At the joints of Reinforced concrete
and brick masonry, either :-
the RC surface is not roughned
or filling of mortar at the joint is not
evident.
11
construction mistakes
12. The joint of brick masonry at larger
height are improperly racked.
Mixing ratio in plaster and brick
masonry is not maintained.
12
construction mistakes
13. In the case where beams are cast prior
to slabs :
In large slabs, the concrete in beams
starts setting before casting of RC slab.
The concrete spilled on the sides of
beams while casting is never removed
which gets set subsequently
13
construction mistakes
14. Reinforcement of RC column is kept
exposed above RC slab.
Hacking to concrete surface is poorly
done prior to Plastering.
Bearing to lintels on both the ends is not
sufficient.
14
construction mistakes
15. In load bearing structure ,secondary beams
are resting directly on the walls giving
point loading.
Proper care for uplift pressure in black
cotton soil is not taken in by proving with
ground beam
Combined footing
15
construction mistakes
16. The above 20 no construction mistakes may result
in
Cracks in concrete.
Improper bonding between concrete and
brick masonry.
Spillage of plaster.
Dampness of walls.
Leakage of slabs.
Cracks in brick masonry.
Settlement of foundation and walls.
Result of mistakes.
16
17. Causes for poor quality can be summarized
as ignorance, poor materials, poor design,
poor detailing, poor workmanship,
improper quantity of cement, improper
concrete mix, excess water, inadequate
compaction, substandard forms, inadequate
curing, inadequate cover, poor construction
practices, poor supervision and above all
lack of technical knowledge.
17
Causes of mistakes
19. Effectiveness of the Existing system in quality
vulnerability reduction
20
Entity
Block Development Officer
Assistant Engineer
JE
Executive Officer
Executant
Sanjojaka
only interested in profit as 10%, profit is not in estimate
Can't be believed,not accountable
Comments
Check only the progress
Monitor progress,Check quality,encourage public participation
Estimate,Execute,Check only during his presence
Does not Check quality
20. 21
With the
increase of
quality of
design, cost
increase is
exponential but
value addition
initially
increases, but
starts saturating
at of some point.
Hence the
optimum cost is
arrived when
slope of both the
curves is same .
Relation between Quality and Cost
21. 22
One can note
that with the
increase of
quality of
construction,
cost of quality
control gets
saturated.
Thus we can
arrive at
optimum
quality for
minimum cost
from total cost
of the
construction.
Economics of Quality of Conformance
22. 23
Case Study
Project : Community
Centre
Scheme : MPLAD
GP: Gangapada
Est.Cost :-3.96 Lakh
Steps taken : The
entire reinforcement
was wrong, and was
removed as per the
design requirement
Of the slab
23. CONCLUSIONS:
24
100% quality in PR Deptt. can not be
controlled it can only be managed by :-
Immediate Execution of the work
Use of machinery and technology
Experienced quality engineer
Distributing quality manuals to the
people
More no of supervision to the site