What is BOT project what all are the criteria for the viability to get the project and case study of the project. and what all risk is been faced in this project
The document discusses toll roads and provides information on various aspects of toll road projects. It defines toll roads as roads that can be used by vehicles upon payment of a toll fee. It notes the growth in vehicle numbers has led to increased use of toll roads to help fund road infrastructure projects. The document outlines key topics like the concept of toll roads, common project structures, activities involved in toll road projects, major risks, tolling aspects, and government support policies. It also briefly discusses newer developments in toll road projects.
Built operate transfer case studies in local construction Sector in PakistanMeesum Zaidi
This document discusses built operate transfer (BOT) case studies in the local construction sector of Pakistan. It provides definitions and background for BOT projects, describing their typical structure and stakeholders. The document outlines the objectives and methodology of BOT projects, including the process from building to operating to transferring ownership. It also examines trends in BOT projects in Pakistan, challenges faced, and examples of specific motorway projects. The overall aim is to review BOT project trends and increase understanding of their use for infrastructure development in Pakistan.
This document describes several common procurement models for infrastructure projects:
- Design-Build, Turn-Key, and Build-Operate-Transfer models involve private partners designing, building, financing, and sometimes operating projects before transferring ownership back to the public sector.
- Build-Lease-Transfer, Build-Own-Operate-Transfer, and Design-Build-Finance-Operate models have private partners taking on more long-term responsibilities like owning, operating and maintaining projects in addition to designing and building them.
- Build-Own-Operate models give private partners long-term ownership of projects in addition to design, build, finance, operation and maintenance responsibilities.
Each model allocates project risks
Nj future redevelopment forum 2014 financing infrastructure mc monagleNew Jersey Future
This document from Ernst & Young provides an overview of public-private partnerships (P3s) and trends in the US P3 market. It notes that P3s can be an effective tool but are not suitable for all projects. The US P3 market is growing and includes availability payment models where payments are made based on meeting performance standards. While P3s transfer some risks to private partners, they require careful screening and structuring to ensure projects are viable and risks are appropriately allocated between public and private entities. Success requires credibility in both specific projects and the broader P3 program.
The document discusses toll roads and provides information on various aspects of toll road projects. It defines toll roads as roads that can be used by vehicles upon payment of a toll fee. It notes the growth in vehicle numbers has led to increased use of toll roads to help fund road infrastructure projects. The document outlines key topics like the concept of toll roads, common project structures, activities involved in toll road projects, major risks, tolling aspects, and government support policies. It also briefly discusses newer developments in toll road projects.
Built operate transfer case studies in local construction Sector in PakistanMeesum Zaidi
This document discusses built operate transfer (BOT) case studies in the local construction sector of Pakistan. It provides definitions and background for BOT projects, describing their typical structure and stakeholders. The document outlines the objectives and methodology of BOT projects, including the process from building to operating to transferring ownership. It also examines trends in BOT projects in Pakistan, challenges faced, and examples of specific motorway projects. The overall aim is to review BOT project trends and increase understanding of their use for infrastructure development in Pakistan.
This document describes several common procurement models for infrastructure projects:
- Design-Build, Turn-Key, and Build-Operate-Transfer models involve private partners designing, building, financing, and sometimes operating projects before transferring ownership back to the public sector.
- Build-Lease-Transfer, Build-Own-Operate-Transfer, and Design-Build-Finance-Operate models have private partners taking on more long-term responsibilities like owning, operating and maintaining projects in addition to designing and building them.
- Build-Own-Operate models give private partners long-term ownership of projects in addition to design, build, finance, operation and maintenance responsibilities.
Each model allocates project risks
Nj future redevelopment forum 2014 financing infrastructure mc monagleNew Jersey Future
This document from Ernst & Young provides an overview of public-private partnerships (P3s) and trends in the US P3 market. It notes that P3s can be an effective tool but are not suitable for all projects. The US P3 market is growing and includes availability payment models where payments are made based on meeting performance standards. While P3s transfer some risks to private partners, they require careful screening and structuring to ensure projects are viable and risks are appropriately allocated between public and private entities. Success requires credibility in both specific projects and the broader P3 program.
Piyush Kumar gave a seminar on build operate and transfer (BOT) projects. In a BOT project, a private entity builds infrastructure, operates it, and then transfers it to the public sector after a certain time period. For coordinate BOT projects, the private entity builds and staffs a facility, establishes operating guidelines, manages the offshore organization, and then helps transfer the team and operations to a new subsidiary of the customer. BOT projects provide infrastructure development with no upfront investment for the customer and involve various political, technical, financing, traffic, currency, and other risks that must be considered. Piyush discussed examples of BOT projects in the highway and railway sectors in India.
The Construction Manager-General Contractor method for consctruction of trans...Angel Damian Rivera-Saez
The document discusses the Construction Manager-General Contractor (CM/GC) project delivery method for transportation projects in Puerto Rico. It provides background on Puerto Rico's transportation infrastructure needs and fiscal problems. It then summarizes the key characteristics and benefits of the CM/GC method seen in other states, including reduced risks, costs savings, and shortened project timelines. The document proposes implementing CM/GC for Puerto Rico projects like PR-18 reconstruction and bridge replacements. It outlines necessary changes to laws and regulations and provides a flowchart for selection and bidding processes to successfully adopt the CM/GC method in Puerto Rico.
A new approach to infrastructure financing in Colombiapc1619
Clemente del Valle, president of FDN, outlines Colombia's world-class infrastructure program which includes 40 projects worth USD 27 billion developing over 8,000 km of infrastructure. Corruption, inadequate infrastructure supply, and inefficient government bureaucracy are among the top problems for doing business in Colombia. FDN, Colombia's development bank, aims to mobilize USD 2.5 billion for infrastructure financing by the end of 2015 through financial products, regulatory changes, and pilot projects.
This document provides an analytical comparison of different public-private partnership (PPP) models, including BOT, BOOT, and full privatization (FP). It defines each model and outlines their key stages, advantages, and disadvantages. BOT involves private financing, construction, and operation of infrastructure that is then transferred to public ownership. BOOT is similar but includes long-term private ownership and operation. FP transfers full ownership, operation, and financing to the private sector. The document concludes that BOT and BOOT models transfer more risk to the private sector but have longer duration periods than FP. BOOT generally has the highest costs and efficiency but also the greatest private sector investment and control.
Construction Industry is one of the most booming industries in the whole world. This industry is mainly an urban based one which is concerned with preparation as well as construction of real estate properties. The repairing of any existing building or making certain alterations in the same also comes under construction Industry.
This document provides a critical review of why infrastructure projects using the public-private partnership (PPP) model have failed, with a focus on road sector projects in India. It analyzes the risk factors associated with PPP toll road projects through case studies. Key risks include delays in land acquisition, lack of external linkages to project sites, financing difficulties, inadequate planning studies, design issues, construction delays, approval delays, traffic volume shortfalls, payment collection problems, inappropriate financial structures, legal/regulatory changes, and force majeure events. The document examines three case studies of major PPP road projects in India that were awarded but could not be initiated due to problems such as lack of bidders and difficulties acquiring land
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...IRJET Journal
This document discusses public-private partnerships (PPPs) for road infrastructure projects in India. It provides an overview of different PPP models used in India, including build-operate-transfer (BOT), BOT-toll, and BOT-annuity models. It also discusses the advantages and challenges of using PPP models for road projects in India, such as risks related to land acquisition, project costs, and financing. The key PPP models currently used for national highway projects in India are BOT-toll, BOT-annuity, and the hybrid annuity model.
Financing & Managing Infrastructure Development in India, Risk Mitigation in Model Concession Agreement & Financial Implications on different Shareholders
Prepared by the students of corporate finance at the MBA program of IE Business School, this presentation provides an introduction to project finance and analyzes two case studies involving project finance.
Infrastructure Finance Fundamentals (ADN Capital Ventures)Adam Nicolopoulos
Project finance is a method of arranging financing where the lenders rely primarily on the cash flows of the project being financed, rather than the balance sheets of its sponsors. It establishes a single purpose company to develop, build, and operate an infrastructure or industrial project based on its projected cash flows. Project risks are transferred and shared among stakeholders, with lenders relying on the project's assets and cash flows for repayment rather than recourse to the sponsors. Key risks like construction, operation, maintenance, revenue, and permits are typically borne by private sector parties rather than the public sector.
The presentation elucidates the study aimed at exploring the need of PPP model in India, with respect to capacities and capabilities of municipal governments to handle finance and governance of large scale urban infrastructure projects.
A turnkey project refers to a project where a contractor is responsible for designing, building, and training personnel for a new facility. The contractor agrees to deliver a fully operational project, including training staff, and upon completion hands over the keys to the client. Turnkey projects merge design and construction responsibilities into a single contract between the client and contractor. They allow the contractor flexibility to modify the design as needed while assuming responsibility for any gaps or omissions. While turnkey projects provide economic returns, they do not establish long-term operations in the foreign country and can create future competitors.
Traditionally, infrastructure projects in India were owned by the government, but private sector participation is now encouraged due to large investment needs. Private projects are implemented through a special purpose vehicle (SPV) corporate entity. Key parties include project sponsors, the SPV, contractors, lenders, and the government. Infrastructure projects face various risks during construction and operation that must be managed, such as construction risks, market risks, and regulatory risks.
The document provides a project plan for regenerating the railway at Berzozil. Key points include:
- The project aims to develop a new 21st century railway station that regenerates the local community and rationalizes existing sidings to provide development land for future projects.
- A stakeholder analysis identifies internal and external stakeholders that will be impacted by the project.
- Concept proposals show plans for the site including regenerating industrial land and maintaining a strong community hub.
- The project plan outlines the work breakdown structure, risk analysis, program of work, procurement strategy, and review and closure processes to deliver the project objectives.
This document provides an overview of public-private partnerships (PPPs) for toll road projects. It discusses key elements for evaluating BOT project economics, including country environment, concession environment, public-private risk sharing, sponsor ability, and financial market environment. It also covers different tolling models and concepts, as well as critical risks and success factors for tolled PPP projects. The document aims to outline effective collaboration between the public and private sectors for delivering tolled bridge and highway projects.
Construction involves the building or assembling of infrastructure through a complex, multistep process. It requires effective planning and coordination between design teams, financial advisors, and contractors to ensure projects are completed safely, on budget, and meet environmental standards. There are two main types of construction - building construction which includes homes and commercial buildings, and industrial construction for specialized facilities. Large projects require managing numerous interdependent tasks and integrating input from various experts.
Demystifying The Public Private Partnershipphilippduffy
This document provides an overview of public-private partnerships (P3s) with a focus on their application in Quebec. It defines P3s, explains how they work through an output-based design-build-finance-maintain-operate model, discusses their benefits and drawbacks, and outlines Quebec's experience with P3s for infrastructure projects. Key projects in Quebec like the Maison Symphonique concert hall have seen success through on-time and on-budget delivery using a P3 model. Municipal infrastructure also presents opportunities for future P3 projects in Quebec.
This document discusses turnkey projects, which involve a company taking responsibility for the entire design and construction of a project in exchange for payment upon completion. Some key advantages of turnkey projects are reduced schedule and costs compared to separate contracting of design, construction, etc. Turnkey projects also allow countries to gain technological know-how by partnering with companies from other countries. However, there is a risk of creating new competitors by sharing proprietary technology in this way. The document provides examples of American and other foreign companies that have completed large turnkey infrastructure projects in various countries.
Public-private partnerships (PPPs) are agreements between governments and the private sector to provide public infrastructure like highways. Under a PPP model, a private sector special purpose vehicle constructs, maintains, and operates the infrastructure while collecting tolls. The private investor funds the construction, operation, and maintenance costs. There are risks if construction costs are underestimated, but quality incentives and supervision help mitigate this. PPPs provide infrastructure through private funding and expertise while transferring the asset back to the government upon completion of the contract period.
This document discusses infrastructure development through public-private partnerships (PPPs) like build-operate-transfer (BOT) models. It provides details on BOT structuring, including that a private company builds and operates an infrastructure asset for a set concession period before transferring it to the public sector. The document also examines options for PPPs ranging from short-term service contracts to long-term divestitures. As a case study, it outlines plans for Mumbai's first metro rail corridor to address public transportation needs through a PPP.
Piyush Kumar gave a seminar on build operate and transfer (BOT) projects. In a BOT project, a private entity builds infrastructure, operates it, and then transfers it to the public sector after a certain time period. For coordinate BOT projects, the private entity builds and staffs a facility, establishes operating guidelines, manages the offshore organization, and then helps transfer the team and operations to a new subsidiary of the customer. BOT projects provide infrastructure development with no upfront investment for the customer and involve various political, technical, financing, traffic, currency, and other risks that must be considered. Piyush discussed examples of BOT projects in the highway and railway sectors in India.
The Construction Manager-General Contractor method for consctruction of trans...Angel Damian Rivera-Saez
The document discusses the Construction Manager-General Contractor (CM/GC) project delivery method for transportation projects in Puerto Rico. It provides background on Puerto Rico's transportation infrastructure needs and fiscal problems. It then summarizes the key characteristics and benefits of the CM/GC method seen in other states, including reduced risks, costs savings, and shortened project timelines. The document proposes implementing CM/GC for Puerto Rico projects like PR-18 reconstruction and bridge replacements. It outlines necessary changes to laws and regulations and provides a flowchart for selection and bidding processes to successfully adopt the CM/GC method in Puerto Rico.
A new approach to infrastructure financing in Colombiapc1619
Clemente del Valle, president of FDN, outlines Colombia's world-class infrastructure program which includes 40 projects worth USD 27 billion developing over 8,000 km of infrastructure. Corruption, inadequate infrastructure supply, and inefficient government bureaucracy are among the top problems for doing business in Colombia. FDN, Colombia's development bank, aims to mobilize USD 2.5 billion for infrastructure financing by the end of 2015 through financial products, regulatory changes, and pilot projects.
This document provides an analytical comparison of different public-private partnership (PPP) models, including BOT, BOOT, and full privatization (FP). It defines each model and outlines their key stages, advantages, and disadvantages. BOT involves private financing, construction, and operation of infrastructure that is then transferred to public ownership. BOOT is similar but includes long-term private ownership and operation. FP transfers full ownership, operation, and financing to the private sector. The document concludes that BOT and BOOT models transfer more risk to the private sector but have longer duration periods than FP. BOOT generally has the highest costs and efficiency but also the greatest private sector investment and control.
Construction Industry is one of the most booming industries in the whole world. This industry is mainly an urban based one which is concerned with preparation as well as construction of real estate properties. The repairing of any existing building or making certain alterations in the same also comes under construction Industry.
This document provides a critical review of why infrastructure projects using the public-private partnership (PPP) model have failed, with a focus on road sector projects in India. It analyzes the risk factors associated with PPP toll road projects through case studies. Key risks include delays in land acquisition, lack of external linkages to project sites, financing difficulties, inadequate planning studies, design issues, construction delays, approval delays, traffic volume shortfalls, payment collection problems, inappropriate financial structures, legal/regulatory changes, and force majeure events. The document examines three case studies of major PPP road projects in India that were awarded but could not be initiated due to problems such as lack of bidders and difficulties acquiring land
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...IRJET Journal
This document discusses public-private partnerships (PPPs) for road infrastructure projects in India. It provides an overview of different PPP models used in India, including build-operate-transfer (BOT), BOT-toll, and BOT-annuity models. It also discusses the advantages and challenges of using PPP models for road projects in India, such as risks related to land acquisition, project costs, and financing. The key PPP models currently used for national highway projects in India are BOT-toll, BOT-annuity, and the hybrid annuity model.
Financing & Managing Infrastructure Development in India, Risk Mitigation in Model Concession Agreement & Financial Implications on different Shareholders
Prepared by the students of corporate finance at the MBA program of IE Business School, this presentation provides an introduction to project finance and analyzes two case studies involving project finance.
Infrastructure Finance Fundamentals (ADN Capital Ventures)Adam Nicolopoulos
Project finance is a method of arranging financing where the lenders rely primarily on the cash flows of the project being financed, rather than the balance sheets of its sponsors. It establishes a single purpose company to develop, build, and operate an infrastructure or industrial project based on its projected cash flows. Project risks are transferred and shared among stakeholders, with lenders relying on the project's assets and cash flows for repayment rather than recourse to the sponsors. Key risks like construction, operation, maintenance, revenue, and permits are typically borne by private sector parties rather than the public sector.
The presentation elucidates the study aimed at exploring the need of PPP model in India, with respect to capacities and capabilities of municipal governments to handle finance and governance of large scale urban infrastructure projects.
A turnkey project refers to a project where a contractor is responsible for designing, building, and training personnel for a new facility. The contractor agrees to deliver a fully operational project, including training staff, and upon completion hands over the keys to the client. Turnkey projects merge design and construction responsibilities into a single contract between the client and contractor. They allow the contractor flexibility to modify the design as needed while assuming responsibility for any gaps or omissions. While turnkey projects provide economic returns, they do not establish long-term operations in the foreign country and can create future competitors.
Traditionally, infrastructure projects in India were owned by the government, but private sector participation is now encouraged due to large investment needs. Private projects are implemented through a special purpose vehicle (SPV) corporate entity. Key parties include project sponsors, the SPV, contractors, lenders, and the government. Infrastructure projects face various risks during construction and operation that must be managed, such as construction risks, market risks, and regulatory risks.
The document provides a project plan for regenerating the railway at Berzozil. Key points include:
- The project aims to develop a new 21st century railway station that regenerates the local community and rationalizes existing sidings to provide development land for future projects.
- A stakeholder analysis identifies internal and external stakeholders that will be impacted by the project.
- Concept proposals show plans for the site including regenerating industrial land and maintaining a strong community hub.
- The project plan outlines the work breakdown structure, risk analysis, program of work, procurement strategy, and review and closure processes to deliver the project objectives.
This document provides an overview of public-private partnerships (PPPs) for toll road projects. It discusses key elements for evaluating BOT project economics, including country environment, concession environment, public-private risk sharing, sponsor ability, and financial market environment. It also covers different tolling models and concepts, as well as critical risks and success factors for tolled PPP projects. The document aims to outline effective collaboration between the public and private sectors for delivering tolled bridge and highway projects.
Construction involves the building or assembling of infrastructure through a complex, multistep process. It requires effective planning and coordination between design teams, financial advisors, and contractors to ensure projects are completed safely, on budget, and meet environmental standards. There are two main types of construction - building construction which includes homes and commercial buildings, and industrial construction for specialized facilities. Large projects require managing numerous interdependent tasks and integrating input from various experts.
Demystifying The Public Private Partnershipphilippduffy
This document provides an overview of public-private partnerships (P3s) with a focus on their application in Quebec. It defines P3s, explains how they work through an output-based design-build-finance-maintain-operate model, discusses their benefits and drawbacks, and outlines Quebec's experience with P3s for infrastructure projects. Key projects in Quebec like the Maison Symphonique concert hall have seen success through on-time and on-budget delivery using a P3 model. Municipal infrastructure also presents opportunities for future P3 projects in Quebec.
This document discusses turnkey projects, which involve a company taking responsibility for the entire design and construction of a project in exchange for payment upon completion. Some key advantages of turnkey projects are reduced schedule and costs compared to separate contracting of design, construction, etc. Turnkey projects also allow countries to gain technological know-how by partnering with companies from other countries. However, there is a risk of creating new competitors by sharing proprietary technology in this way. The document provides examples of American and other foreign companies that have completed large turnkey infrastructure projects in various countries.
Public-private partnerships (PPPs) are agreements between governments and the private sector to provide public infrastructure like highways. Under a PPP model, a private sector special purpose vehicle constructs, maintains, and operates the infrastructure while collecting tolls. The private investor funds the construction, operation, and maintenance costs. There are risks if construction costs are underestimated, but quality incentives and supervision help mitigate this. PPPs provide infrastructure through private funding and expertise while transferring the asset back to the government upon completion of the contract period.
This document discusses infrastructure development through public-private partnerships (PPPs) like build-operate-transfer (BOT) models. It provides details on BOT structuring, including that a private company builds and operates an infrastructure asset for a set concession period before transferring it to the public sector. The document also examines options for PPPs ranging from short-term service contracts to long-term divestitures. As a case study, it outlines plans for Mumbai's first metro rail corridor to address public transportation needs through a PPP.
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYShabaz Khan
This document provides a case study of the Delhi Gurgaon Expressway project in India, which was developed as a public-private partnership using a build-operate-transfer (BOT) model. It describes the project background, financing and risks, construction delays, and lessons learned. The 27.7 km expressway was commissioned in 2018 after delays due to land acquisition issues and scope changes. It now carries over 180,000 vehicles per day, improving travel times between Delhi and Gurgaon.
The document discusses the Build Operate Transfer (BOT) model, where a private sector builds infrastructure, operates it, and eventually transfers ownership to the government. It involves the host government, concessionaire, lending banks, and other parties. Under the model, the private developer designs and implements large projects, operates them to charge customers and realize profit for a specified period, before transferring ownership. Key risks include political, technical, financing, and costs. Recent BOT examples discussed are developing new railway lines in India and the Delhi Noida Direct expressway.
The document discusses public-private partnerships (PPPs). It defines PPPs as agreements between governments and private companies where the private sector finances, builds, and operates infrastructure projects like roads, dams, and utilities. The document outlines several PPP models and notes that PPPs allow risk and costs to be shared while leveraging private sector expertise and innovation.
The Build Operate Transfer (BOT) model enables private sector investment in large infrastructure projects. Under the BOT model, a private contractor constructs and operates a facility for a specified period, receiving fees from the public agency to cover costs and investment recovery. Ownership of the facility remains with the public agency. At the end of the operating period, ownership and operation is transferred to the public agency. The BOT model shares risks between the private and public sectors and mobilizes private financing and management for infrastructure development.
The document discusses public-private partnerships (PPPs) for infrastructure projects. It defines PPPs and notes that they involve long-term contractual agreements where private partners finance, build, and operate infrastructure traditionally provided by the public sector. Common PPP models include build-operate-transfer agreements where the private partner builds and operates a facility that is later transferred back to the public sector. PPPs aim to attract private financing while allocating risks to the public or private sector best able to manage them.
Build Operate Transfer (BOT) models involve private entities financing, designing, constructing, and operating infrastructure projects while receiving concessions from the public sector. Under the BOT model for this case study, a special purpose vehicle formed by Sushee Infra and IVRCL received a concession to widen and improve a highway in Arunachal Pradesh over a 17-year period. The project has achieved its construction milestones on time and received tranches of cash support from the government. Timely execution and maintenance of credit metrics will be important for the continued success and financial health of the project. Delays or increased leverage could create stress for the private partners.
The document discusses public-private partnership (PPP) models for infrastructure projects, specifically for highways in India. It provides definitions of PPP and explains various PPP models used for highway projects, including build-operate-transfer (BOT), design-build-operate-transfer (DBOT), and others. It outlines the need for PPP to attract private investment for highway development and maintenance. The document also discusses factors that affect the success of PPP projects such as risk allocation, financial viability, traffic volume, and monitoring during project implementation.
This document discusses various construction project delivery methods. It begins by defining a construction project delivery method as a system used by an agency or owner to organize design, construction, operations, and maintenance through legal agreements. It then describes seven common delivery methods: Design Bid Build, Build Operate Transfer, Build Own Operate Transfer, Design Build Finance Operate, Design Build Operate and Transfer, Build Lease Transfer, and Design Construct Manage Finance. For each method, it provides a definition and overview, along with advantages and disadvantages.
Infrastructure projects involve building large capital-intensive assets like roads, bridges, and utilities that are essential for economic activity. Key parties in infrastructure projects include the project sponsor, project vehicle, project lenders, EPC contractor, O&M contractor, and government. Projects are typically implemented through a special purpose vehicle to isolate risks. Public-private partnerships are also commonly used where private firms design, build, finance, and operate infrastructure in exchange for payments from the public sector over a long-term concession.
Mobilizing Private Sector Investment into GMS InfrastructurePratish Halady
My presentation to the GMS Economic Corridors Forum about the benefits of involving private sector in infrastructure, creating an environment for PPP and private investment, and ADB's approach to delivering PPP in the region.
Project financing and public-private partnerships (PPPs) allow major infrastructure projects to be funded off the government's balance sheet using a mix of public and private funding. PPPs follow several key stages including project identification, feasibility studies, equity and debt arrangement, negotiation, construction, operation, and repayment. They allocate risks to the public or private sector best able to manage each risk. Pakistan has successfully completed several PPP projects and has many more currently underway or in the pipeline managed through provincial PPP units.
Project financing and public private partnership (ppp)M. Asim U Khan
This document provides an overview of project financing and public-private partnerships (PPPs). It begins with definitions of project financing and PPPs. It then outlines the typical stages in a project financing process, including identification, feasibility studies, equity and debt arrangements, negotiation, monitoring, repayment, and disbursement. Key aspects of project financing structures are highlighted such as high debt levels and concentrated ownership. PPP models like BOT, BOOT, and ROT are described. Critical success factors for PPPs include appropriate risk allocation, value for money, and performance management. The document concludes with details on Pakistan's PPP Unit and examples of executed, current and planned PPP projects.
Private and Public Partnerships Move MainstreamKerry Carey
All across the country, infrastructure projects are in need of repair, and creative organizational solutions are in-demand. Public-Private Partnerships are long-term contracts between a private party and a government entity allowing for an alternative approach to federal, state and municipal construction projects. The private party bears a large share of risk and management responsibility, and remuneration is linked directly to performance. This webinar discusses the nature of this collaboration across sectors.
Presented by:
Gregory Fitch
Black and Veatch
View the on-demand webinar: http://cpe-wpi.hs-sites.com/construction-project-management-webinar-series
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDOECDGlobalRelations
Presented at the Training Session on Public Private Partnerships organised by the MENA-OECD Investment Security in the Mediterranean (ISMED) Support Programme in September 2014.
This document summarizes a case study of a tolled road project implemented through a Build-Operate-Transfer (BOT) agreement in a city in India. Key risks identified include social opposition and public protests shutting down toll booths. The project involved developing 50km of roads through the municipal corporation area to address traffic issues. The concessionaire was responsible for construction, maintenance, and operating 9 toll plazas for 30 years to collect tolls and other revenues to recoup costs. Traffic analysis of toll plazas showed daily vehicle volumes.
This document provides an overview of private financing of infrastructure projects in India. It discusses how infrastructure projects are typically structured, with a special purpose vehicle (SPV) established to implement the project. Key project parties and contractual agreements governing the project are described. Power and telecommunication projects are used as examples to illustrate typical financial structures and risks. Private-public partnerships (PPPs) are also discussed as a model for infrastructure development in India given the large funding needs and involvement of the private sector. The document emphasizes the importance of PPPs for meeting India's infrastructure gaps and expanding economic growth.
This document discusses the application of drone technology in the construction industry. It begins with an introduction on how drones can provide aerial views and data to optimize construction operations. The main objectives, scope and benefits of using drones are then outlined, such as enabling fast site surveying, progress monitoring, and safety inspections. Examples of drone applications in planning, execution and maintenance are provided. Risks like regulatory compliance and insurance are also covered. The document concludes that drones have the potential to revolutionize the construction sector through improved efficiency if technological and regulatory challenges can be addressed.
Review on DCR (Development Control Regulation) and what it output in the construction field and what all rules and regulations need to be followed. Follow the rules and regulation in new development and construction
The document provides a feasibility analysis for opening two potential McDonald's locations. For the first location in Opera House, Mumbai, the analysis examines the population demographics, nearby colleges and schools as customer bases, commercial area for takeaway orders, and local competition from restaurants. For the second location in Omaxe Chowk, Delhi, the analysis covers the project background, large daily foot traffic and businesses in Chandni Chowk, nearby tourist attractions, facilities and parking in Omaxe Chowk, and potential customers from metro stations and local markets. Competition includes local restaurants and fast food chains. Both locations seem suitable due to strong demand drivers from large nearby customer populations.
Construction project management & risk mitigationrajlaxmipardeshi
This document provides an overview of risk management in construction projects. It discusses identifying, analyzing, assessing, controlling, and monitoring risks. Key risks in construction include project finance, construction issues, environmental/geotechnical factors, and staffing problems. Risk identification methods like brainstorming and checklists are outlined. External risks beyond a organization's control, like economic/political changes, are also important to consider in risk management using tools like PESTLE analysis. The goal of risk management is to reduce costs and delays by planning for potential issues in a construction project.
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...knox groups real estate
welcome to knox groups real estate company in Bangalore. best farm land for sale near Bangalore and madhugiri . Managed farmland near Kanakapura and Chickkabalapur get know more details about the projects .Knox groups is a leading real estate company dedicated to helping individuals and businesses navigate the dynamic real estate market. With our extensive knowledge, experience, and commitment to excellence, we deliver exceptional results for our clients. Discover the perfect foundation for your agricultural aspirations with KNOX Groups' prime farm lands. These aren't just plots; they're the fertile grounds where vibrant crops flourish, livestock thrives, and unique agricultural ventures come to life. At KNOX, we go beyond selling land we curate sustainable ecosystems, ensuring that your journey toward agricultural success is seamless and prosperous.
The SVN® organization shares a portion of their new weekly listings via their SVN Live® Weekly Property Broadcast. Visit https://svn.com/svn-live/ if you would like to attend our weekly call, which we open up to the brokerage community.
Living in an UBER World - June '24 Sales MeetingTom Blefko
June 2024 Lancaster County Sales Meeting for Berkshire Hathaway HomeServices Homesale Realty covering the following topics: 1. VA Suspends Buyer Agent Payment Plan (article), 2. Frequently Used Terms in title, 3. Zillow Showcase Overview, 4. QuickBuy commission promotion, 5. Documenting Cooperative Compensation, 6. NAR's Code of Ethics - Mass Media Solicitations, 7. Is it really cheaper to rent? 8. Do's and Don't's when Terminating the Agreement of Sale, 9. Living in an UBER World
The SVN® organization shares a portion of their new weekly listings via their SVN Live® Weekly Property Broadcast. Visit https://svn.com/svn-live/ if you would like to attend our weekly call, which we open up to the brokerage community.
Stark Builders: Where Quality Meets Craftsmanship!shuilykhatunnil
At Stark Builders our vision is to redefine the renovation experience by combining both stunning design and high quality construction skills. We believe that by delivering both these key aspects together we are able to achieve incredible results for our clients and ensure every project reflects their vision and enhances their lifestyle.
Although we are not all related by blood we have created a team of highly professional and hardworking individuals who share the common goal of delivering beautiful and functional renovated spaces. Our tight nit team are able to work together in a way where we pour our passion into each and every project as we have a love for what we do. Building is our life.
Dholera Smart City Latest Development Status 2024.pdfShivgan Infratech
Explore the latest development status of Dholera Smart City in 2024. Discover the progress, infrastructure, and future plans of India's first greenfield smart city.
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing TurkeyListing Turkey
Looking for a new home in Istanbul? Look no further than Avrupa Konutlari Esentepe! Our beautifully designed homes provide the perfect blend of luxury and comfort, making them the perfect choice for anyone looking for a high-quality home in the city.
With a wide range of apartment types available, from 1+1 to 4+1, we have something to suit every need and budget. Each apartment is designed with attention to detail and features spacious and bright living areas, making them the perfect place to relax and unwind after a long day.
One of the things that sets Avrupa Konutlari Esentepe apart from other developments is our focus on creating a community that is both comfortable and convenient. Our homes are surrounded by lush green spaces, perfect for enjoying a peaceful stroll or having a picnic with friends and family. Additionally, our complex includes a variety of social and recreational amenities, such as swimming pools, sports fields, and playgrounds, making it easy for residents to stay active and socialize with their neighbors.
https://listingturkey.com/property/avrupa-konutlari-esentepe/
1. PROCUREMENT AND CONTRACT.
BOT PROJECT CASE STUDY
Report submitted to the
Institute Of Real Estate And Finance.
(MBA + PGP)
2021-2022
By
GROUP B
Rajlaxmi Pardeshi.
Vikrant Wagh.
Dilip Mehta.
Sachin Rai.
Parag Jagtap.
UNDER THE GUIDANCE OF
Mrs. Asha Oak
2. ACKNOWLEDEMENT
We all the group member would like to express our special thanks of gratitude to our
director Mr. Abhay Kumar, for all support and guidance throughout and giving us
the opportunity to work on this report which would help all of us to know more about
the topic: BOT. Secondly, we want to thank our mentor Mrs. Asha Oak for giving
an opportunity to work on such report which made us learn about many things about
the contract and how the project work, what all are criteria to full fill for the project.
And also, to all the other teachers to motivate us and bring positive thoughts in us.
3. INTRODUCTION:
Build-operate-transfer (BOT) contract is project model done for financing large projects, mainly
infrastructure projects developed through public, private partnerships. That a private entity receives
a concession from the private or public sector to finance, design, construct and operate in the
contract. This authorize the project support to recover its investment, operating and maintenance
expenses in the project.
Due to long term nature of the arrangement, the fees are usually raised during the surveying period.
The rate of increase is by combined nature of internal and external variables, allowing the proponent
to reach the satisfactory internal rate of return of what is invested.
The BOT scheme refers to the opening done by public entity such as local government to private
firm to build and operate the Project. After sometime as refed into the contract the project is returned
to the public entity.
In a BOT Project the project company or operator generally obtains its revenues through a fee
charged to the utility/ government rather than tariffs charges to consumers. A number of project are
called concessions, such as toll road projects.
Under a build-operate-transfer (BOT) contract, government grants a concession to a private
company to finance, build and operate a project. The company operates the project for a period of
time (perhaps 20 or 30 years) with the goal of recouping its investment, then transfers control of the
project to the government.
BOT projects are normally are of large-scale, greenfield infrastructure projects that would otherwise
be financed, built and operated solely by the government. In general, BOT contractors are special-
purpose companies formed specifically for a given project. During the project period when the
contractor is operating the project it has built revenues usually come from a single source, an offtake
purchaser. This may be a government or state-owned enterprise.
In general, a project is financially viable for the private entity if the revenues generated by the project
cover its cost and supply a sufficient return on investment. On the opposite hand, the viability of the
project for the host government depends on its efficiency as compared with the economics of
financing the project with public funds. albeit the host government could borrow money on better
conditions compared thereto of the general public sector, other factors could offset this particular
advantage. for instance, the expertise and efficiency that the private entity is predicted to bring also
because of the risk transfer. Therefore the private entity bears a considerable part of the risk.
BACKGROUND
Increase within the industrial and other commercial activities, the vehicle traffic within the city is
growing tremendously. most significantly, besides national highway, there are four major arteries
4. expressway MDR that terminates into the guts of the town. of these roads usher in heavy amount of
traffic partly designed to city and mostly to varied parts of the state through the town via national
highway. Though traffic mixes with the town to feature its already existing traffic, moves out
through narrow streets/roads of city to feature to its already existing traffic woes and bottlenecks at
various junction and A level crossing. The slow development of transportation facilities like ring
roads, internal roads as compared to the event of the town as an entire city is facing tremendous
setback. Thus within the view of the ever increasing traffic needs of this high density corridors steps
are being taken to enhance traffic condition and to supply better connectivity. to unravel the traffic
problems including removing bottlenecks within the city, unintegrated road development program
me has been formed. As funds are limited with this municipal corporation, it decided to implement
this project through BOT.
BOT mechanism plays an important role within the infrastructural development by
− Reducing financial burden on the govt.
− Assisting completion of the project in time.
− Enhances service quality and efficiency.
− Delivering better value of cash proposition.
− Transparency and impartiality within the process of inviting private participation.
− Sharing the risks between Government and contractors.
− Improper deciding
− Negligence towards risks
− Misinterpretation by users
− Political influence
OBJECTIVES:
• To see what all difficulties come in BOT projects.
• To identify challenges in operational phase of BOT projects.
• To compare road and fly over BOT project.
• To develop and establish highway network in the city.
• Development of entrance and link routes
• Widen and develop a full road to development plan width
• Provide storm water drain
• Provide central divider and footpath
• Improvement of junctions provide advanced street light illumination
• Facilitate beautification of road to reinforce aesthetics of roads
• Provide urban infrastructure and road furniture
BOT BENEFITS:
BOT contract give benefits over the traditional subsidiary path, including:
5. • Rapid scaling of operations.
• Wider service offerings, quickly filling business model gaps.
• Lower infrastructure setup costs.
• Reduced time to operations through utilization of knowledgeable
Third party management resources responsible for:
• Real estate.
• Government rules and regulations.
• Cultural transition.
• IT infrastructure Procurement.
• Security.
SCOPE OF WORK
1. To face challenges and identify risk and analysis them.
2. Traffic management during maintenance.
3. Related clauses in the contract document.
4. Toll collection.
5. Parameters of deciding toll rates.
6. Constraints Faced at site.
7. Methodology of toll collection.
TYPE OF RISK BY PHASES.
The ongoing risks are interest rate risk and exchange rate risk.
Below Table.1 describe the risk in BOT project phases wise.
RISK PARTICIPANT MACHANISM
Development Phase.
Technology Risk Sponsors Equity Subordinated Debt
Credit Risk Sponsors Lenders Credit Rating Agency
Bid Risk Sponsors Equity
Construction Phase
Completion Risk Sponsors Contractors
Performance incentives and
guarantees the key contractors.
Cost over view Risk Sponsors Contractors
Fixed price contract and
completion bond.
Performance Risk Sponsors Performance bond.
6. Operation Phase
Cost over view Risk Sponsors Fixed price contract
Performance Risk O&M Contractor. Equity ,performance guarantee
Equity resale Risk Sponsors Sub co-ordinated
Off take Risk Sponsors
Take and pay or pay ,
advanced payment
Liability Risk Insurance Company Insurance contracts
(Table.1) : Risk analysis by Phases.
OTHER RISK:
• Political Risk.
− Especially within the developing countries due to the likelihood of dramatic overnight political
change.
• TECHNICAL RISK
− Construction difficulties, for instance unforeseen soil conditions, breakdown of kit.
• DELAYS IN LAND ACQUISITION
− NHAI ( National Highway Authority of India) was susceptible to pay damages if it did not
provide ROW within the required time. Delays in land acquisition resulted in a rise within the
acquisition cost for the government.. They also resulted in loss of potential revenue accruing to
the Concessionaire thanks to delays in commencement of operations.
• FINANCING RISKS
− The Concessionaire was required to realize financial closure within 180 days from the date of
the agreement beyond which a further period of 90 days was allowed subject to an advance
weekly payment of Rs.1,00,000 per week as damages by the Concessionaire for delay in
achieving financial closure. exchange rate risk and rate of interest fluctuation, market risk
(change within the price of raw materials), income risk (over-optimistic cash-flow forecasts),
cost risk.
• DESIGN RISK
− There were substantial changes within the design that led to escalation in cost also as time over-
run.
− This meant revenue loss to the Concessionaire because the concession period wasn't altered.
7. • CONSTRUCTION RISK
− If Concessionaire did not complete the project construction by the scheduled completion date,
the agreement prescribed weekly damages at the speed of 0.01% of the entire project cost. the
development of the expressway got delayed thanks to inordinate delays in land acquisition and
changes within the scope of labour. the danger was primarily borne by the Concessionaire and
more specifically by DS Constructions Ltd. because it was also the EPC contractor for the
project. For change in scope, NHAI was also asked to contribute the increased investment
requirement.
• OPERATIONS & MAINTENANCE RISK
− The risk is primarily with the concessionaire NHAI because the concession authority has set
stringent performance standards and obligations to be met.
TOLL COLLECTION
General
In recent years, many Asian countries and other countries in transition have encouraged road infra
development so as to market and sustain continued economic growth. India, for instance, had seen
demand for brand new highways to achieve an unprecedented level. The government has been that
essential player in the development of roads in India. The road users in India haven't been charged
in terms of user fees or tolls remains an unanswered question as far as the pricing of roads cares. In
order to form the users conscious of the necessity for pricing roads; the government should create a
forum to elucidate the road users of the pros and cons of tolls. A Careful study on the user
acceptability of tolls and therefore the willingness to pay must be conducted in order that the road
projects are often financed.
Significance of toll collection:
The National highways act has been amended to enable the levy of a toll on selected sections of NH
in order that private participation in road constructions on a BOT basis is facilitated. the opposite
measures taken to encourage private participation within the road sector include permission to
NHAI to seek out equity privately or public companies. NHAI has also considered providing cash
support in selected projects.
Policies for Tolling
− National Highways Act, 1956 and Rules made there under
− section 7 for levying fees for services or benefits rendered;
− section 8A-Power to enter into agreements from development and maintenance of NH
8. The concept of cost to the promoter benefits to the user is guiding principles behind toll fixation on
any BOT project. The cost incurred by the promoter is recovered over period of time, this period is
fix. And the main purpose is to get the return on investment and annual revenues.
FACTOR AFFECTING THE USER
− Travel distance
− Travelling time , fuel, wear and tear cost.
− Fee charges.
COLLECTION SYSTEM ON TOLL
The number of toll booths required at each toll plaza, are estimatedon thebasis of average hourly
trafficdue topass throughthem.This factoris takenintoaccount to decide whether to go for Manual
toll collection sys- tem or anETC.
A) Manual toll collection system
B) Automatic toll collection system
FEATURES OF THE PROJECT.
GENERAL DATA:
Construction of integrated road development program (IRDP) in the city on BOT basis.
− Name of the client: Municipal Corporation.
− Name of fascillitor: State Road Development Corporation.
− Type of contract: BOT
− Estimated cost of project
− Name of the company
− Date of work order
− Duration of project
− Concession Period
− Total km. to be executed
− No. of toll plaza.
ROAD INVENTOEY.
The total project roads are classified into three categories namely External Routes (ER), Internal
Routes(ER), and Link Routes (LR).Out of the entire project 49.99km road length of the road,
External Routes are amounting to 30.79 km. Internal Routes 5.6 km and remaining 12.60 km are
Link Routes.
The Development plan width wise breakup of the entire project roads is 3.5 km roads of 15m. DP
9. width. 19.07km. roads of 18m. DP width 7.20km roads of 24m. DP width and therefore the balance
20.22km roads are with 30m.Development Plan width.
PROPOSALS
• State Road Development Corporation – Facilitator
• Bot Operator--- Executing Agency
• Land Acquisition to Be Dealt by Municipal Corporation Before Work Order
• Shifting of Utilities Is to Be Dealt by Bot Operator
• Encroachment to Be Removed by Municipal Commissioner
• Local Technical Assistance by The Municipal Corporation
• Exemption for The Material to Be Used for The Project
• Sources of Revenue to Bot Operator
• Toll
• Advertisement Revenue
• Utility Rentals
• Plot Measuring 30000sq.M Given for Development On 99 Years Lease
• Commercial Exploitation of Toll Station Area
TECHNICAL CRITERIA FOR BIDDERS.
• Bidders/ Consortium should have completed one bridge/ flyover/ ROB costing Rs.7cr
• Completed 4 lane road of min 15km or 2 lane road min 25km.
• Consortium should have built min 5km road in corporation limit.
• Company or consortium should have experience of BOT project.
• Complete works of Bridge / flyover/ ROB should be in the year.
FINANCIAL CRITERIA FOR BIDDERS.
• Min Annual Turnover 1600 Million
• Net Worth 60 Million
• Net Profit After Tax 100million
• Bid Capacity Min 2000 Million
• Min Equity 51%
BID EVALUATION
• Bid will be evaluated as regards to responsiveness to technical data
• Bid passing the criteria will be considered for financial evaluation
• Concession period is fixed and concessionaire will quote on min viable gap funding
• State road development corporation will carry out confirmatory evaluation and issue loan to
successful bidder
10. TOLL COLLECTION
Cars Goods Carrier, Auto 15
Six Seater Auto 15
LCV 20
Bus 35
Truck 35
Multi Axle Vehicle 40
(Table.2: Toll Rates)
Note1: Nine Toll Stations are proposed
Note 2:25% Concession for purchase of 50Coupons
Note 3:50% Concession for purchase of 100 Coupons
Note 4: Single toll will be charged if vehicle passes same or other toll station within 6 hours.
Note 5: For monthly pass holders, 50% of monthly single journey charges.
Note 6: Toll rates are revised after every 3 third years with a growth rate of 6 % per annum
rounded tonearestRs.5
FEATURES OF A TYPICAL CONCESSION AGREEMENT.
• This agreement is TRI PARTY AGREEMENT entered between, State Road Development
Corporation Limited, City Municipal Corporation, And Entrepreneur Developing Integrated
Road Development Program.
• The government has entrusted the state road development corporation, the implementation of
Integrated Road Development Program a BOT basis.
• State Road Development Corporation and therefore the confirming party entered into the
agreement to implement the said project as per the mutually agreed revised scheme and has been
approved by the confirming party.
• The obligation to the state road development corporation and therefore the confirming party and
therefore the funding arrangements of the said project are elaborated within the said agreement.
• The confirming party within the said agreement has agreed and undertaken to discharge financial
liabilities if any arising for any reason whatsoever out of the concession agreement for the
implementation of the said project and to compensate and reimburse all costs and liabilities.
• State Road Development Corporation had resolved to implement approx... 50 Km. of roads
within the city on the build, operate, and transfer basis. On terms and conditions set forth during
a CA.
• State Road Development Corporation had act accordingly invited application for pre-
qualification by its PQ notice for a brief listing of bidders for Design Construction, Operation
and Maintenance of the project on BOT basis However State Road Development Corporation
later decided to travel certain post qualification.
11. • State Road Development Corporation had prescribed the technical and commercial terms and
conditions and invited bids from bidders pursuant to the tender notice for undertaking the
projects.
• After evaluation of the bids received, State Road Development Corporation had accepted the
body of the consortium and issued a letter of acceptance to the consortium requiring interlaid,
the execution of this Concession agreement within 30 days of issue thereof.
• The consortium has since promoted and incorporated an indebtedness company under the
businesses act 1956 and requested State Road Development Corporation to simply accept the
concessionaire because the entity which shall undertake and perform the requirement and
exercise the proper of the consortium under the LOA including the obligation to enter into
concession agreement pursuant to the LOA for executing the project.
• By its letter, the concessionaire has also joined within the said agreement of the consortium to
State Road Development Corporation to simply accept it's because the entity which shall
undertake and perform the requirement and exercise the proper of the consortium under the LOA
including the obligation to enter into concession agreement pursuant to the LOA for executing
the project.
• State Road Development Corporation had agreed to the said request of the concessionaire and
has accordingly agreed to enter into this concession agreement with the concessionaire for the
execution of the project on a BOT basis, subject to and on the terms and conditions set forth
hereinafter.
TRAFFIC STUDY AND ANALYSIS.
To l l P l a z aL o c a t
i o n
C a r / J e e p / V
a n / 6 s / A u t o
L CV S T
B u s
O t h e r B
us
T r u c k M AV T r a c t o
r
T o t a l
S h a h u 3 8 8 8 2 9 0 7 1 5 1 5 3 5 4 1 9 20 5 6 1 5
U c h g a o n 3 8 5 9 3 0 9 2 8 6 16 4 3 7 3 65 4 9 7 5
W a s h i 1 7 3 0 1 7 7 3 4 6 44 4 6 2 1 82 2 8 4 1
S h i y e 1 5 6 8 1 7 7 90 14 4 3 2 1 1 1 5 2 3 9 8
F u l e w a d i 2 0 7 7 3 7 9 5 6 9 96 9 3 1 5 2 1 3 4 2 7 1
K a l a m b a 8 8 7 1 5 2 2 0 0 17 2 8 3 5 25 1 5 6 7
S h i r o l i 1 1 1 5 9 1 1 9 1 2 3 5 5 5 2 3 2 6 5 5 16 72 1 7 9 7 2
MODEWISE DISTRIBUTION OF THE VEHICLE.
12. TOLL EXEMPTED VEHICLES.
• State MLA’S/ MP’S Vehicles.
• Central and state government vehicles
• Police vehicles
• Military vehicles
• Post and telegraph department
• Ambulances
• Fire brigade vehicles
• KMT buses
• Two-wheeler/ three-wheeler/ auto
BELOW ARE TWO CASE STUDIES ON BOT PROJECTS.
CASE STUDY 1: DELHI GURGAON EXPRESSWAY.
Project Description
The National Highways Authority of India (NHAI), under the Ministry of Road Transport &
Highways, was entrusted the responsibility for implementation of the Golden Quadrilateral project
(Highway Project connecting the four metro cities of latest Delhi, Mumbai, Chennai, and Kolkata).
As a neighbourhood of this project, it proposed the conversion of a really busy section of NH-8
connecting
Delhi to Gurgaon into a 6/8 lane access controlled divided carriageway. The project was awarded
to the consortium of Jaypee Industries and DS Construction Ltd to style, finance, construct, operate
and maintain the power for a concession period of 20 years. The Concessionaire is allowed to gather
toll from the users of the project facility during the operation period to recover his investment and
therefore the expressway is required to be transferred back to the government at the top of the
concession period.
This was the primary BOT project in India to possess been awarded on a negative grant basis were
within the concessionaire offered to pay an upfront fee to NHAI reciprocally of the concession as
MODEWISE DISTRIBUTION OF THE
VEHICLE
1.5
%
2.18
%
14.48
%
11.50
%
63.49
%
6.75
%
JEEP/VAN/AUTL
CV
STBUS
OTHER BUS
TRUCK
MAV
TRACTOR
13. against a capital grant from the govt. The expressway was commissioned in January 2013 after much
delay primarily due to issues in Land acquisition and changes within the scope of labour.
PPP structure of the Project
The project was awarded to the consortium of Jaiprakash Industries Ltd and DS Construction Ltd
on a Built-Operate-Transfer (BOT) basis for a period of 20 years. the chosen concessionaire offered
to pay 61.06 crore upfront as a negative grant to the NHAI.The Concessionaire was required to
style, construct, operate and maintain the expressway in accordance with the specifications as
approved by NHAI. A Special Purpose Vehicle called the Delhi Gurgaon Super Connectivity Ltd
(formerly Jaypee DSC Ventures Ltd.) was created for the execution of the project. The SPV entered
into a hard and fast time-fixed price Engineering, Procurement & Construction (EPC) contract with
DS Constructions Limited for this project.
Current Status:
The expressway has been operational for five years now after it had been opened to traffic in January
2018. It carries quite 180,000 PCUs per day, which is far above the traffic estimates for the project
by 13,000 to 15,000 PCUs per day. The substantially higher number of vehicles using the power
has often led to a queuing from vehicles at the toll plazas.
The expressway consists of 9 flyovers, 4 underpasses and a couple of foot-over bridges, and three
toll plazas. Smart tags are introduced to enable cashless automatic payment.
Financing Information
The funding for the project at the time of monetary closure (9 May 2018) is provided below:
Particulars Amount
1.Debt 383.3 crore
2.Equity 164.2 crore
3.TOTAL 547.5 crore
Process Analysis Inception:
The plan for an expressway connecting Gurgaon and Delhi was initiated within the late 2010s and
an in-depth project report was prepared for an equivalent. Golden Quadrilateral project, as traffic
intensity on these corridors, had increased manifold which hampered the safe and efficient
movement of vehicles. Accordingly, NHAI decided to upgrade the section of NH-8 connecting
Delhi and Gurgaon into an 8/6 lane access-controlled expressway because it was the busiest part of
the highway. it had been estimated that the expressway would scale back the time period between
Delhi and Gurgaon from about 65 minutes to around 20 minutes.
14. NHAI was finding itself constrained to fund the estimated Rs 555 Crore for the expressway.
Malaysia's housing industry Development Board (CIDB) was initially proposed to require up this
project under the memorandum of understanding (MoU) route as a neighbourhood of a government
to government initiative.
However, this proposal sought a grant of Rs120 crore from NHAI and was thus rejected. the
government of India, at the time, was keen to market public-private partnerships (PPP) in viable
expressway projects to draw in funding and maximize private sector efficiency. it had been therefore
decided to undertake the project on a BOT (Build-operate-Transfer) basis. NHAI used the Detailed
Project Report prepared in 1998 for the traffic projections for this project.
Procurement
The MORT&H invited pre-qualification bids in 2017. The project was initially envisaged to need a
capital grant to be paid by NHAI to the successful bidder towards the value of construction for
enhancing the viability of the highway project.
However, considering the robust traffic projections, bids were received with negative grants. In
April 2002, the consortium of Jaiprakash Industries and DS Constructions was declared
the successful bidder. RBM Malaysia, which was the L2 bidder, had quoted Rs 55 crore because of
the negative grant. Other bidders were Gamuda Malaysia, IJM Malaysia, and Larsen & Toubro
(L&T).
Development
The erstwhile Jaypee DSC Ventures Ltd. (now referred to as Delhi Gurgaon Super Connectivity
Ltd.), the SPV incorporated by the Concessionaire for the project, achieved financial closure in May
2015. the development of the expressway commenced in January 2015. In June 2016, Jai Prakash
Industries, despite being the lead promoter, sold its stake to DS Constructions and retained just
1.2%.
The project development, however, soon saw issues over approvals, land acquisition, and additions
to the scope of labour which was largely thanks to the physical setting of the project highway.
Delivery
The project was commissioned on 25 January 2018. The expressway is fully operational and is
handling a big traffic volume of quite 180,000 PCUs per day, growing at 9% year-on-year.
Exit
15. The concession period is for 20 years and therefore the projected end date is 11 January 2023 when
the expressway is going to be handed over to the govt.
Efficiencies Achieved:
Particulars Earlier Now
*Average Travel Speed 25.65Km/Hr 66 Km/Hr
*Average Travel Time 65 Minutes 25 minutes
*Intersections. 20
Intersections
10 Grade Separated Intersections
Key Learnings and Observations
Delhi-Gurgaon Expressway project built under the PPP model offers insights into the following
important lessons, which should be kept in mind for effective and efficient implementation of other
PPP agreements.
Lengthy construction period:
The Delhi - Gurgaon Expressway is that the 'fully access controlled' highway project and caters to
both local and concrete traffic, additionally the Domestic and International airports are located on
its corridor. there have been quite 15 government agencies like Delhi Development Authority
(DDA), Haryana Urban Development Authority (HUDA), and lots of others that were suffering
from the event of the expressway and thus various approvals were needed from them, due to which
construction phase of the project became complex and time-consuming. All this led to delays in the
development of the expressway, thus there must speed up of the method of getting approvals from
various authorities to deliver the project on time to understand its complete benefits.
Problems in land acquisition:
Acquisition of land for the development of those sorts of projects in a thickly populated environment
always impact the timely delivery of the projects. Although,
NHAI and other agencies involved in this project put great efforts to accelerate the method, but
thanks to difficulties in acquiring certain areas of land contributed to the delays.
Changes in the scope of the project:
Another major reason for the delay in the completion of the project was a change within the scope
of the project. Keeping in mind the longer-term requirements and convenience of commuter's
substantial changes were made within the original design that was finalized by NHAI and the
16. government. additionally, to the present, the demands of bodies like HUDA and DDA regarding the
connected projects also played a crucial role in the delays in the completion of the project. Thus,
there adhering to future needs, a strong structure of the project has got to be designed so as to avoid
future delays.
Lower traffic risk:
Traffic risk is that the biggest risk to the success of a typical road project. However, the danger is
substantially lower during this project because it involved improvement and tolling of an existing
highway, where traffic flow is more or less established. The Delhi Gurgaon section of NH-8 has
been one among the busiest sections within the country and there to an extent had the advantage of
enormous traffic and thus high revenues.
Conclusions
The sustained economic process in India in recent years has brought opportunities and challenges
to the design and management of Indian transportation. Like in other developing countries,
transportation in India is characterized by limited roadway infrastructure and therefore the lack of
operation and management experience.
Delhi Gurgaon Expressway is that the most enjoyable development in the transport history of India
and it's provided help to businesses by providing a relatively free-flowing alternative to the
17. congested NH-8. This facility might be benchmarked with the best expressways within the world as
better planning and engineering technologies have been incorporated during this project to usher in
the category of best expressways worldwide. But despite this, the expressway has faced concerns in
managing and decongesting the traffic density.
(Pic.1: Project)
CASE STUDY 2: INDORE DEW AS ROAD BOT PROJECT.
PROJECT OVERVIEW
Indore may be a major city and commercial centre of the state of Health Services in central India.
Indore is located 190 km west of the capital Bhopal. consistent with the 2011 Indian census, Indore
city features a population of 1,516,918. it's the 15th largest city in India and therefore the 147th
largest city in the world. It is the headquarters of both the Indore district and Indore division. Dew
as District may be a district of Pradesh state in central India. The town of Dew as is that the district
headquarters. The district has a neighbourhood of 7,020 km², and a population of 1,306,617 (2001
census), a rise of 26% since 1991. Dew as District roughly corresponds to the territories of the dual
princely states of Dew as. The district straddles the Vindhya Range; the northern portion of the
district lies on the Malawi plateau, while the southern portion lies within the valley of the Narmada
River. The Narmada forms the southern boundary of the district.
The district is bounded to the east by Sehore District, to the south by the Harda and Khandwa
districts, to the west by the Khargone and Indore districts, and to the north by the Ujjain and Shajapur
districts. Dewas District is a component of the Ujjain Division. National Highway Administration
of India (NHAI) has initiated a process to extend the width of the Indore-Dewas section of the Agra
- Mumbai highway from four lanes to six-lane. The Administration will convert it from four-lane to
six-lane on the basis of Built-Operate-Transfer. NHAI has invited tenders for this work which can
be opened on 25TH of January 2010. a forty-five km street is going to be converted into six-lane.
The Authority estimates its cost to be RS.325 Crore. To encourage a far better competition the
authority has invited tenders globally.
Developer: M/S Gayatri Infra Ventures Ltd.
SPV : M/s DLF-Gayatri construction.
EPCC Contractor: M/s Gayatri Projects Ltd.
Consultant: M/s HBS Constants
19. (Table.5: Comparison of road and flyover Revenues.)
(Table.6: Comparison of road and flyover costs.)
20. (Table.7: Comparison of road and flyover IRR)
CONCLUSION
Comparison of road and flyover BOT project:
As looking into the above comparison of road and flyover project we came to see that the initial cost
of the fly over cost is high compare it to road, and revenue is high in flyover than road ,finally by
internal rate of return method we will see that profits in road is more compared to fly- over So it's
better to figure on road projects than fly over because returns are more, although maintenance of
road are going to be more compared to fly over but still road project will get more IRR.
FUTURE STUDY
The availability of infrastructure facilities is imperative for the general development of any country.
Today there's a requirement to specialize in enhancing the standard of infrastructure services
provided in India. Roads constitute a crucial part of the infrastructure of a rustic. These projects are
very huge and need a lot of investment within the construction phase also as an operational phase.
thanks to funds constraints, the government is assigning several projects on a BOT basis within the
last decade.
Although privatization has done the trick within the present scenario of the Indian infrastructure
sector, acceptability of personal investment to the general public requires the reassurance that the
standard of construction comes up to the specified standards, that the tolls charged are reasonable,
and also that any direct or indirect capital subsidy involved is decided during a transparent manner
to make sure that the project represents a least-cost solution for the economy.
The concept of financing highways or bridges on a BOT basis is completely new in our country.
tons of study and research work has been administered like resources, funds, etc., and prerequisites
21. for such projects but the post-development challenges are to be specific challenges related to the
operational phase has remained vastly unemployed.
PRESENT ONGOING PROJECTS:
Costal Road Project.
• Marine Drive.
• Haji Ali Mumbai Costal Road: The Road to the Sea.
REFRENCE:
www.iosrjournals.org
www.ijmetmr.com