SlideShare a Scribd company logo
WindBarriers
Administrative and grid access barriers to wind power
July 2010
Grant agreement number: IEE/07/513/SI2.499556
Duration: December 2008 – November 2010
Co-ordinator: European Wind Energy Association asbl/vzw (EWEA)
Cover picture: © Ecotecnia

Project partners:
Asociación Empresarial Eólica (AEE)
DONG Energy A/S
Austrian Wind Power GmbH
Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer)
Iberdrola Renovables S.A.
Magyar Szélenergia Társaság (HWEA)
Polskie Stowarzyszenie Energetyki Wiatrowej (PWEA)
Vindmølleindustrien (DWIA)

Supported by:




The sole responsibility for the content of this document lies with the authors. It does not necessarily reflect the
opinion of the European Communities. The European Commission is not responsible for any use that may be
made of the information contained herein.
WindBarriers
Administrative and grid access barriers to wind power




July 2010
Photo: RES




             2   July 2010
Contents


Executive summary................................................................................................................................... 6


Chapter 2: Project methodology. ............................................................................................................. 14
                              .


Chapter 3: Analysis of barriers in administrative procedures..................................................................... 20
                                                            .
    3.1 Generic model of the permitting process........................................................................................ 21
                                               .
    3.2 Barriers to administrative procedures............................................................................................. 24
    3.3 A quick look at offshore. ............................................................................................................... 32
                                .
    3.4 Recommendations........................................................................................................................ 34


Chapter 4: Analysis of barriers to grid connection. ................................................................................... 38
                                                  .
    4.1 Generic model of the grid connection process................................................................................. 39
    4.2 Barriers to grid connection. ........................................................................................................... 42
                                   .
     4.3 A quick look at offshore. ............................................................................................................... 50
                                 .
     4.4 Recommendations........................................................................................................................ 51


Chapter 5: Market-based analysis............................................................................................................ 56
     5.1 Types of market............................................................................................................................ 57
     5.2 Analysis per type of market. .......................................................................................................... 59
                                    .
     5.3 Regional analysis.......................................................................................................................... 68


Chapter 6: Country factsheets................................................................................................................. 74
     6.1 Reader’s guide to the country factsheets........................................................................................ 75
     6.2 Factsheets................................................................................................................................... 76


Appendix. ............................................................................................................................................. 145
        .
     Windbarriers project partners. ........................................................................................................... 145
                                  .


Bibliography.......................................................................................................................................... 146




WindBarriers - Administrative and grid access barriers to wind power                                                                                     3
PRINCIPAL AUTHORS:
Alberto Ceña, Asociación Empresarial Eólica (AEE)
Dorina Iuga, European Wind Energy Association (EWEA)
Emilien Simonot, Asociación Empresarial Eólica (AEE)
Nicolas Fichaux, European Wind Energy Association (EWEA)
Sharon Wokke, European Wind Energy Association (EWEA)
Sune Strøm, Vindmølleindustrien (DWIA)



ACKNOWLEDGEMENTS:
The authors wish to thank everyone who contributed to drafting and producing this report.
In particular we would like to gratefully acknowledge the following persons:
Contributors:
Benjamin Pfluger, Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer)
Wendelin Macht, Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer)
Revisers:
Julian Scola, European Wind Energy Association (EWEA)
Editing:
Sarah Azau, European Wind Energy Association (EWEA)
Zoe Casey, European Wind Energy Association (EWEA)
Special thanks to:
EWEA’s national wind energy member associations for their important contribution to the project.
The developers who replied to the WindBarriers survey.
Glória Rodrigues (EWEA) and Jacopo Moccia (EWEA) for their very useful remarks.

Design and production by: Megaluna
Design coordinator: Raffaella Bianchin, European Wind Energy Association (EWEA)
Published in July 2010
Printed on FSC certified paper


    Disclaimer: The analysis, conclusions and recommendations provided in this publication are based on the answers received on
    onshore and offshore wind projects from developers in 23 EU countries in the framework of the WindBarriers project. Some of the
    samples are too small to be representative and therefore the corresponding recommendations would need to be confirmed on a
    larger scale.




4                                                                                                                           July 2010
Foreword
I am delighted to introduce this first publication from                The WindBarriers project, which is supported by the
the WindBarriers project. The Directive on the pro-                    Intelligent Energy Europe programme, is expected to
motion of the use of energy from renewable sources                     significantly reduce the lead times for the develop-
(2009/28/EC) is a pillar of European sustainable                       ment of new wind projects, and it also has the po-
energy policy, and its implementation will require sig-                tential to accelerate the development of projects in-
nificant efforts from EU member states to reduce ad-                   volving other renewable energy sources. It will engage
ministrative and grid access barriers. The WindBarri-                  with decision makers and help them to benchmark
ers project is important because it supports member                    their performance using an agreed monitoring meth-
states in this implementation process by providing                     odology.
a clear and detailed picture of the challenges being
faced across the EU, as well as indicating some of the                 WindBarriers has the potential to make an important
ways these challenges can be overcome.                                 contribution to accelerating the growth of renewable
                                                                       energy markets across the EU, and to implementing
WindBarriers analyses both the administrative and                      our common European vision of a more sustainable
grid access processes in the different member states                   future.
and regions, and compares them using transparent
and objective criteria. This will help to highlight best
practices, as well as to identify potential bottlenecks.




William Gillett
Head of Unit Renewable Energy
European Commission
Executive Agency for Competiveness and Innovation (EACI)




WindBarriers - Administrative and grid access barriers to wind power                                                       5
xxx




                                          Photo: Gehring




          Executive summary




      6                       July 2010
Introduction                                                           Questions were asked on a set of potential barriers –
                                                                       referred to as “indicators” - allowing information to be
On 30 June 2009, the European Commission adopted                       gathered on the administrative and grid obstacles in
a template setting out the minimum requirements for                    23 countries of the EU. The results from the indicators
the National Renewable Energy Action Plans (NREAPs),                   can be compared from country to country, giving an in-
as required by Directive 2009/28/EC of the European                    dication of the implementation of the 2001 and 2009
Parliament and of the Council of 23 April 2009 (2009                   EU directives. The results are accompanied by a set
Renewable Energy Directive).                                           of recommendations on how to improve administrative
                                                                       and grid access procedures in the EU-27 in order to
The NREAPs, which are to be provided to the European                   help each EU member state reach its binding target, as
Commission by June 2010, are national roadmaps of                      described in Table 1.1.
each country’s expected path to its binding renewable
energy target for 2020. Each NREAP is to set out the
country’s expected renewable energy contribution, both
                                                                       Administrative procedures and
in terms of capacity to be installed (MW) and of energy
production (MWh), for each of the renewable energy                     corresponding barriers
technologies mentioned in the directive from 2010 to
2020. Moreover, each member state (MS) has to pro-                     Project developers need to obtain a building permit in
vide an estimate of its gross final energy consumption                 order to install a wind farm. This goes for the grid con-
from all types of energy (both renewable and non-renew-                nection as well. The total time taken to get the building
able), for each year between 2010 and 2020, for three                  consent and grid connection permits is called the to-
sectors: heating/cooling, electricity and transport. The               tal “lead time” of a wind farm. Based on the WindBar-
NREAPs will also include information on all policies and               riers survey, the average total lead time in the EU is
support schemes to promote renewable energy in that                    54.8 months for onshore and 32 months for offshore.
country.                                                               Reasons for the long lead times vary from country
                                                                       to country, but they are often related to Environmen-
The WindBarriers project seeks to build a reliable meth-               tal Impact Assessment (EIA) restrictions and/or grid
odology to obtain concise information on the adminis-                  connection constraints.
trative and grid connection barriers that obstruct the
development of wind energy. This methodology is to be                  The EU average for the administrative lead time of an
used by member states and the European Commission                      onshore wind energy project is 42 months. Compared
to monitor the implementation of Articles 6 (adminis-                  to this, offshore wind energy projects seem to be much
trative schemes) and 7 (grid connection) of directive                  quicker, with an average of 18 months according to
2001/77/EC on the promotion of electricity produced                    the surveys submitted to the WindBarriers project. The
from renewable energy sources, which correspond to                     administrative lead time differs significantly for each
the new Articles 13 and 16 of the 2009 Renewable                       country and each project: from 2 to 154 months. Some
Energy Directive.                                                      developers in Greece, Portugal and Spain have experi-
                                                                       enced lead times of 100 months or longer for their build-
Building on a large stakeholder consultation, the Wind-                ing permit applications. As regards offshore, a possible
Barriers consortium put together an extensive data-                    explanation for the shorter building consent time is that
base with precise information on administrative and                    the six countries in the survey seem to have developed
grid barriers. More than 200 wind energy projects in-                  efficient and streamlined decision-making processes,
stalled during 2007 and 2008, both onshore and off-                    including Maritime Spatial Planning (MSP).
shore across the EU-27, were analysed.




WindBarriers - Administrative and grid access barriers to wind power                                                          7
Executive summary




             On average nine authorities have to be contacted di-         Once a project developer has secured the basic tech-
             rectly and an additional nine indirectly for onshore         nical requirements (e.g. project location, sufficient
             wind projects in the EU, while offshore developers           wind resource, access to the site of the future farm),
             have to liaise with seven authorities directly and 16        a grid connection application can be sent to the
             indirectly. This is, however, many more than would           system operator.
             be involved in the recommended ‘one-stop-shop’
             approach, whereby the applicant would have to contact        A basic technical project is submitted to the Distribu-
             a single entity which would be in charge of coordinat-       tion System Operator (DSO), but can be transferred to
             ing the whole application process. The ‘one-stop-shop’       the Transmission System Operator (TSO) if it requires a
             should be an EU objective for both onshore and off-          higher grid capacity (usually over 132 kV).
             shore projects.
                                                                          According to the WindBarriers survey, the EU aver-
             The barriers faced by developers during this proc-           age for grid connection lead time is 25.8 months for
             ess are often related to the approval and scope              onshore projects and 14 months for offshore; for on-
             of the Environmental Impact Assessment, compli-              shore, the grid access lead time is significantly lower
             ance with spatial planning, the number of parties/           than the administrative one (42 months).
             authorities involved and to barriers related to other
             stakeholders involved in the process (e.g. social            The average number of TSOs involved in the grid
             acceptance issues).                                          connection process is 0.85 onshore and 0.92 off-
                                                                          shore, whereas for the DSOs, it is 0.77 onshore and
             For offshore, the main barriers are likely to be the ad-     0.47 offshore. In terms of third parties involved dur-
             ministrative bodies’ lack of experience, an unclear EIA      ing the grid connection process, the EU average is
             process, and difficult interaction with other users of the   24 onshore and 4.4 offshore. The ideal situa-
             sea, according to the survey.                                tion remains the ‘one-stop-shop’ approach, as
                                                                          described above.
             Costs, the approach of the authorities, the transparen-
             cy of the decision-making process and the use of dead-       The barriers faced by developers during this process
             lines are also analysed in the survey - and depending        are mostly related to an absence of clear information
             on the country, they can constitute an obstacle to wind      on the available grid connection capacity, a lack of plan-
             power development.                                           ning for future grid extension and reinforcements on
                                                                          behalf of system operators, insufficient grid capacity,
                                                                          and other aspects such as land ownership and the EIA.

             Grid connection procedure and
             corresponding barriers
             Some of the main barriers to grid connection pro-
             cedures were evaluated against the requirements
             of Article 13 of the Renewable Energy Directive
             2009/28/EC.




             8                                                                                                             July 2010
Table 1.1: Overview of the main results of the survey on administrative and grid procedures

                                          Administrative procedure                                Grid access procedure

                           Total lead    Administra-    Authorities:   Authorities:      Grid      TSOs          DSOs         Other
                              time           tive          direct        indirect      access                                parties:
                                          lead time       contact        contact      lead time                                grid

                            Average        Average       Average        Average       Average     Average       Average      Average

 Country                    Months         Months        Number         Number        Months      Number        Number       Number

 Austria**                   31.65          18.93          10.38          13.90         17.56        0.84         1.00          3.42

 Belgium                     22.61          20.33           4.08          10.28          7.08        0.91         1.00          3.18

 Bulgaria**                  31.65          18.93          10.38          13.90         17.56        0.84         1.00          3.42

 Czech Republic              39.44          31.56          11.23          11.44         24.76        1.25         0.77          6.91

 Denmark                     34.46          31.81           4.25           0.90          2.01        0.78         0.92          0.13

 Estonia*                    37.80          28.30          10.54          16.03         22.33        1.72         1.38          5.46

 Finland*                    37.80          28.30          10.54          16.03         22.33        1.72         1.38          5.46

 France                      34.02          29.58          22.06          14.22          6.36        1.00         1.65         14.39

 Germany                     55.15          30.12           6.16          20.41          6.59        0.76         0.64          8.60

 Greece                      54.60          50.09          18.63          22.38         20.20        0.84         1.00         11.80

 Hungary**                   31.65          18.93          10.38          13.90         17.56        0.84         1.00          3.42

 Ireland                     55.59          33.49           5.74           8.77         31.42        0.82         1.00          5.01

 Italy                       32.24          18.06          12.73           2.84         18.96        0.45         0.51         32.25

 Latvia*                     37.80          28.30          10.54          16.03         22.33        1.72         1.38          5.46

 Lithuania*                  37.80          28.30          10.54          16.03         22.33        1.72         1.38          5.46

 Netherlands                 45.74          38.85           4.34           1.93         12.93        0.75         0.66          1.11

 Poland                      48.76          43.09           7.78          12.57         15.46        0.89         0.88         32.13

 Portugal                    71.11          58.03           7.58           6.61         46.61        0.79         0.38         47.25

 Romania**                   31.65          18.93          10.38          13.90         17.56        0.84         1.00          3.42

 Spain                       76.08          57.74           5.53           4.28         33.50        0.94         0.80         27.85

 Sweden*                     37.80          28.30          10.54          16.03         22.33        1.72         1.38          5.46

 United Kingdom              25.88          26.87           3.47          11.74          8.36        0.55         0.94          2.62

 Offshore EU                 32.00          18.52           6.88          15.92         14.06        0.92         0.47          4.44

 Onshore EU-27               54.80          42.32           9.03           9.13         25.83        0.85         0.77         23.89

 Offshore EU-6               31.67          28.67          12.10          11.63          7.68        1.00         1.25          7.87

                                                                                                  Source: EWEA 2010, WindBarriers survey




* grouped as ‘Baltic and nordic countries with less than four projects’
** grouped as ‘Central and eastern European countries with under four projects’




WindBarriers - Administrative and grid access barriers to wind power                                                                    9
Executive summary




             Recommendations to EU-27 member states

             Administrative procedures: Article 13 of the EU 2009 Renewable Energy Directive

             Total lead times          •	 Reduce the average total lead time in the EU to 24 months;
                                       •	 Make clear requirements on Environmental Impact Assessments (EIAs) (fixed dead-
                                          lines, how many EIAs need to be carried out depending on the size of the park, its
                                          location) and reduce the number of irrelevant documents;
                                       •	 Develop spatial planning by defining the most appropriate locations and wind
                                          development areas, lowering investment risks and streamlining project application
                                          procedures;
                                       •	 Train and allocate enough civil servants to handle the expected applications;

             Number of authori-        •	 Develop and implement the ‘one-stop-shop’ approach in all member states;
             ties to be contacted      •	 The authorities should disseminate clear information to developers on the adminis-
             directly and indirectly      trative procedures and decision-making processes;

             Administrative            •	 Lower the average administrative lead time to a maximum of 20 months, to ensure
             lead times                   that the total lead time in the EU stays below 24 months;
                                       •	 Perform onshore and offshore spatial planning and define the most suitable wind
                                          development areas, with streamlined administrative procedures in these areas;
                                       •	 Provide clear definitions of the administrative requirements, in terms of procedures,
                                          deadlines and EIA content;
                                       •	 Set deadlines for the administrative process. If the authority is not able to meet the
                                          deadline, the project automatically goes to the next stage;
                                       •	 Train and allocate the necessary civil servants to handle the expected applications;

             Administrative costs      •	 Lower the average administrative costs in the EU to 1.5% of the total project costs;
                                       •	 Perform a preliminary environmental assessment;
                                       •	 Give incentives to competent authorities to gather data and studies collected under
                                          the EIA process and make them public;
                                       •	 Limit the administrative requirements to the key relevant elements, in particular the
                                          ones identified through past projects. Update procedures regularly;
                                       •	 Learn from past projects, and avoid requiring similar information from other
                                          projects with the same conditions;
                                       •	 For offshore, maritime spatial planning should give special importance to cross-
                                          border cooperation and to developing synergies with other sea users;




             10                                                                                                            July 2010
Transparency of               •	 Improve the transparency of administrative procedures across the EU to an average
the administrative               of 4 out of 5 1;
procedure                     •	 Inform both the developers and the local authorities of the applicable rules
                                 and regulations;
                              •	 Set deadlines for the administrative process. If the authority is not able to meet the
                                 deadline, the project automatically goes to the next stage;

Authority’s attitude          •	 Improve the attitude of local authorities across the EU to an average of 4 out of 5 2;
                              •	 National authorities should make sure local and regional authorities are aware of
                                 the targets set out in their NREAP and of the necessity for their country to
                                                                   ,
                                 meet them;
                              •	 Disseminate transparent and unbiased information to the authorities at all levels
                                 on wind energy technology and developments, addressing the myths associated
                                 with wind energy.




1
 	According to the WindBarriers survey, the transparency of administrative procedures is rated 3.21 on average, on a range from 1 to
  5 where 1 means non-transparent and 5 means maximum transparency.
2
 	The attitude of local authorities is rated 3.36 on average across the EU, on a range from 1 to 5, where 1 means ‘negative attitude’
  and 5 means ‘maximum positive attitude’




WindBarriers - Administrative and grid access barriers to wind power                                                               11
Executive summary




             Grid connection procedures: Article 16 of the 2009 EU Renewable Energy Directive

             Grid connection         •	 Reduce the average grid connection lead time in the EU to six months;
             lead time               •	 Set deadlines for the administrative process. If the authority is not able to meet the
                                        deadline, the project automatically goes to the next stage;
                                     •	 Train and allocate the necessary civil servants to handle the expected applications;
                                     •	 Develop the grid infrastructure:
                                        -	 Provide clear definitions of the grid connection requirements. In particular, de-
                                           velop and implement standardised grid codes across the EU;
                                        -	 Plan and build transnational offshore grid infrastructure to connect the antici-
                                           pated offshore wind power, and guarantee connection to the grid for offshore
                                           wind projects;
                                        -	 Reinforce the onshore and offshore transmission system (through cooperation
                                           between different EU member states);
                                        -	 Finding and occupying the land for interconnection infrastructure for wind farms
                                           should be made easier, with adequate economic compensation for the land owners;
                                     •	 On the developer’s side:
                                        -	 Avoid an excess of requests on the same grid point; the projects should be
                                           realistic and based on measured wind data. The use of the land should also be
                                           guaranteed for the entire length of the project;
                                        -	 Close collaboration with grid operators is required;

             Grid connection costs   •	 Lower the average grid connection costs in the EU to 2.5% of project costs;
                                     •	 System operators should cover and contribute to the grid connection costs in the
                                        countries where this is not yet the case, and adapt these costs to the project size;
                                     •	 Upgrade the public grid infrastructure within reasonable costs;
                                     •	 Limit the technical grid connection requirements to a reasonable level (remain
                                        within the scope of the project);
                                     •	 Provide clear definitions of the grid connection requirements. In particular, develop
                                        and implement standardised grid codes across the EU. Grid codes have to be real-
                                        istic and compatible with the latest technology. Harmonisation of grid codes at EU
                                        level is important;
                                     •	 The voltage range should be the minimum required according to the short circuit ca-
                                        pacity of the grid and the load flows in the common coupling point (PCC). Feasibility
                                        studies should identify the voltage range for the connection. This will affect the final
                                        line tracing and the costs and time schedule;
                                     •	 Clear information about grid costs should be provided to developers at an early at
                                        an early stage of project development, in order to reduce investment risks;




             12                                                                                                            July 2010
Transparency of               •	 Improve the transparency of the grid connection process at EU level to an average
the grid connection              of 4 out of 5 1;
                              •	 Provide a clear, streamlined procedure and decision-making process for
process
                                 grid connection;
                              •	 Unbundling of vertically integrated power companies would make grid access fairer.
                                 Plans for the construction and reinforcement of new grid lines should be realistic
                                 and effective. It is fundamental to have better coordination between distribution
                                 and transmission companies when building new infrastructure and for connection
                                 requests. This coordination should also be extended during the wind
                                 farm’s operation;
                              •	 Widely publicise information on the characteristics of the grid. Developers can carry
                                 out access capacity studies and propose technical and management solutions.
                                 These proposals will allow grid capacity to be increased and a realistic calendar to
                                 be set for grid connection;
                              •	 Set deadlines for the grid connection process. If the authority is not able to meet
                                 the deadline, the project should automatically go to the next stage of the authorisa-
                                 tion process.




	According to the WindBarriers survey, the transparency of administrative procedures is rated 3.21 on average, on a range from 1 to
1

 5 where 1 means non-transparent and 5 means maximum transparency.




WindBarriers - Administrative and grid access barriers to wind power                                                             13
xxx




                                         Photo: Jan Oelker




       Project methodology




      14                     July 2010
The aim of the project methodology was to find criteria                     Targeting recent projects:
that could be used to measure administrative and grid
barriers to wind energy projects for years to come.
                                                                            2008 and 2007

Before beginning to collect the data, the consortium                        The objective of the project was to collect recent data
set up a working group made up of experts from the                          from both large and small projects, in all EU-27 coun-
consortium partners, 27 national wind energy asso-                          tries, via a questionnaire. In order to have the most
ciations, and representatives of the Executive Agency                       up-to-date information on barriers to wind energy devel-
for Competiveness and Innovation (EACI). The working                        opment, it was decided to focus on projects installed
group agreed on a specific methodology, based around                        in 2008 (when the project started). In order to obtain
the following criteria.                                                     statistically reliable datasets, representative of the dif-
                                                                            ferent rates of development across the EU, the consor-
                                                                            tium decided to monitor a minimum of 10 projects per
                                                                            country, and to cover from 20% to 50% of new capacity
                                                                            installed in 2008 in each country, as described below.
                                                                            Since some countries installed low amounts of wind en-
                                                                            ergy in 2008, projects from 2007 were also sometimes
                                                                            taken into account, provided they were relevant.




Figure 2.1: Map of the cumulative capacity in MW at the end of 2008


                                                                                                              Finland
                                                                                                                143
                                                                                 Norway
                                                                                  428
  Faroe Islands                                                                                                  Estonia          Russia
        4                                                                                   Sweden                 78              11
                                                                                             1,021
                                                                                Denmark                          Latvia
                                        Rep. of Ireland                          3,180                            27
                                            1,002                                                         Lithuania
                                                           UK                                                 54
                                                          3,241
                                                                  Netherlands
 European Union: 64,935 MW                                           2,225                      Poland
                                                               Belgium          Germany           472
 Candidate Countries: 452 MW                                     384            23,903
 EFTA: 442 MW                                                       Luxembourg        Czech Republic                    Ukraine
 Total Europe: 65,933 MW                                                 35                150                            90
                                                                                                   Slovakia
                                                            France                                    3
                                                                      Switzerland       Austria
                                                            3,404                         995    Hungary
                                                                          14
                                                                                                    127
                                                                                             Croatia             Romania
                                                                                               18                  10
                        Portugal
                         2,862
                                        Spain                                                                       Bulgaria
                                       16,740                                       Italy
                                                                                                                      158
                                                                                   3,736

                                                                                                                                  Turkey
                                                                                                                                   433
                                                                                                         Greece
                                                                                                          985




                                                                                                                                  Source: EWEA




WindBarriers - Administrative and grid access barriers to wind power                                                                       15
Project methodology




              Building a representative                                      Getting a minimum
              sample: adaptation to                                          number of projects
              market dynamism
                                                                             In addition to covering the minimum percentages men-
              The goal was to build a data sample that represented           tioned above, the sample was expected to include at
              the different types of market in Europe. Considering the       least 10 projects per country. However, this was not
              wide variability of annual installed capacity in the differ-   possible in Cyprus, Latvia, Luxembourg, Malta and
              ent countries, the sample size for each country had to         Slovenia, as there were not enough new projects in
              be adapted to the market size. This was done in order          2008. In such cases, the project collected other rel-
              to avoid collecting the vast majority of data from large       evant data to indicate the barriers.
              developed markets, and losing focus of the newer wind
              energy players, where the barriers may be higher.

                                                                             Analysing regional variations:
              Generally, market analysts determine the maturity of
              the market (regulatory environment, public authorities’        regional distribution
              expertise, developers’ skills, and so on) using four mar-
              ket categories based on the new installed capacity. Ex-        In order to ensure that all types of regional develop-
              perience shows that a high annual installation of wind         ment were considered, the samples targeted regions
              power is a good indicator of the level of barriers for         where wind power was less developed.
              countries with similar wind resources.
                                                                             The Nomenclature of Territorial Units for Statistics
              For the WindBarriers project, the consortium used the          (NUTS) classification of the Committee of the Regions
              capacity installed in 2008 as per statistics published         was used to define regions; but not all regions in each
              by the European Wind Energy Association (EWEA: see             country were to be covered by WindBarriers.
              Figure 3.1). More information on these statistics is
              available on EWEA’s annual statistics web page on              A substantial number of the projects to be consid-
              www.ewea.org.                                                  ered per country were to come from regions that
                                                                             performed at or below the European average. The
              •	 For countries where less than 150 MW came online            remaining projects were to come from the best
                 in 2008, the sample had to cover at least 50% of the        performing regions.
                 new installed capacity.
              •	 For countries where between 150 MW and 1,000                Balancing the regional distribution was one of the most
                 MW came online in 2008, the sample had to cover             complex tasks in this project and only a few countries
                 at least 30% of the new installed capacity.                 managed to take it into account in the definition of their
              •	 For countries where more than 1,000 MW came on-             country sample.
                 line in 2008, the sample had to cover at least 20%
                 of the new installed capacity.




              16                                                                                                              July 2010
Looking for showstoppers:                                              Definition of the indicators
analysis of non-finalised projects
                                                                       The main aim of the questionnaire was to obtain a
While obtaining a balanced overview of recently imple-                 comprehensive description of existing administra-
mented projects in the EU was relatively straightfor-                  tive and grid access barriers, primarily in a quantita-
ward, projects that are planned but whose implementa-                  tive manner, by means of particular criteria or “indi-
tion has been delayed represent a significant capacity                 cators”. In order to evaluate the results, and make
that is not registered in any database and can be at                   recommendations, it was necessary to make the bar-
various stages of development.                                         riers in the individual member states measureable
                                                                       and comparable.
However, it is necessary to differentiate between
projects delayed specifically due to administrative barri-             A summary of the indicators is given in Table 2.1. They
ers, and projects delayed because of the lack of experi-               fall into three categories depending on whether they
ence of the developer, an inadequate project proposal,                 measure administrative or grid access barriers, or pro-
or an overly speculative approach.                                     vide overall information on the project and the devel-
                                                                       oper’s success rate.
The WindBarriers consortium decided to address
this issue by adding a specific section on delayed/                    In most cases, direct quantification of the barriers was
blocked projects to the questionnaire. Since the ques-                 possible. The questions relate to numerical values with
tionnaire was filled in by developers with a proven                    pre-defined units. Lead times are measured in months,
track record, the consortium avoided considering                       costs as a percentage of the overall project costs,
unrealistic projects.                                                  and the number of involved authorities, operators or
                                                                       other persons/parties involved in the project in ab-
                                                                       solute values.

Sample and survey
                                                                       The indicators measuring administrative and grid ac-
                                                                       cess transparency are derived from several ques-
On the basis of these criteria, each national wind                     tions. The respective answers are ranked on a
energy association compiled a sample of repre-                         five-point scale.
sentative projects, and identified the developers to
be contacted.

A copy of the WindBarriers online based questionnaire
was sent to those developers. Almost all member
states were covered, with the exception of the coun-
tries where no capacity was installed at all in 2008.




WindBarriers - Administrative and grid access barriers to wind power                                                        17
Project methodology




              Table 2.1: Selected indicators

                                                                                                                                                              Number of
                                                                      Indicator                                                   Unit
                                                                                                                                                              questions


                                          Total lead time                                                     Months                                              1
               Overall




                                          Number of projects on hold in same region                           Numerical value                                     1



                                          Number of authorities that developer must contact directly          Numerical value                                     1



                                          Number of authorities developer does not have to contact directly   Numerical value                                     1
               Administrative barriers




                                          Administrative lead time                                            Months                                              1



                                          Administrative costs                                                As share (%) of total project costs                 1



                                          Authority’s attitude                                                [1-5]                                               1



                                          Transparency of administrative procedure                            [1-5]                                               4



                                          Number of Transmission System Operators (TSOs) involved             Numerical value                                     1



                                          Number of Distribution System Operators (DSOs) involved             Numerical value                                     1
               Grid connection barriers




                                          Number of other parties involved in obtaining grid connection       Numerical value                                     1



                                          Grid connection lead time                                           Months                                              1



                                          Grid connection costs                                               As share (%) of total project costs                 1



                                          Transparency of grid connection process                             [1-5]                                               3


                                                                                                                              Source: Fraunhofer ISI 2009, for WindBarriers




              18                                                                                                                                                 July 2010
Confidentiality and                                                                                                                                    the project partners and that only aggregated figures
                                                                                                                                                       would be published. Despite these measures, for some
representativeness                                                                                                                                     countries the number of replies was relatively low and
                                                                                                                                                       the results would therefore have to be considered cau-
Before the data gathering process began, the consor-                                                                                                   tiously and tested on a larger sample.
tium decided to cover the whole questionnaire with a
confidentiality agreement. It stipulated that the data                                                                                                 The target amount of replies for each country, and the
from the questionnaire would only be visible to two of                                                                                                 actual number received, can be seen below:




Figure 2.2: Rate of replies
                    900
                    900   31
                    800
                    800
                    700
                    700                         23
                    600
                                                             15
  Answers in MWMW




                    600
                    500
     Answers in




                    500
                                                                                 10
                    400
                    400
                    300                                                                         13
                    300                                                                                                   10
                    200                                                                                                                 10                     11                   12                           9                          13
                    200                                                                                                                                                                                                                                      6
                    100                                                                                                                                                                                                                                                    12
                                                                                                                                                                                                                                                                                      12                     6
                    100
                    0
                             Spain


                                                  Portugal


                                                               Poland


                                                                                       Italy


                                                                                                   Greece


                                                                                                                              France


                                                                                                                                           Ireland


                                                                                                                                                               Baltic & Nordic


                                                                                                                                                                                  Netherlands


                                                                                                                                                                                                                 Central & southeastern


                                                                                                                                                                                                                                                   Germany


                                                                                                                                                                                                                                                                Belgium


                                                                                                                                                                                                                                                                            Denmark


                                                                                                                                                                                                                                                                                      United Kingdom


                                                                                                                                                                                                                                                                                                       Czech Republic
                    0
                          Spain

                                     Portugal

                                                Poland

                                                             Italy

                                                                        Greece

                                                                                 France

                                                                                               Ireland

                                                                                                            Netherlands

                                                                                                                          Germany

                                                                                                                                       Hungary

                                                                                                                                                     Belgium

                                                                                                                                                                 Denmark

                                                                                                                                                                                   Estonia

                                                                                                                                                                                                United Kingdom

                                                                                                                                                                                                                              Latvia

                                                                                                                                                                                                                                                Sweden

                                                                                                                                                                                                                                          Czech Republic

                                                                                                                                                                                                                                                             Bulgaria

                                                                                                                                                                                                                                                                          Finland

                                                                                                                                                                                                                                                                          Austria

                                                                                                                                                                                                                                                                                         Lithuania

                                                                                                                                                                                                                                                                                                         Romania




  Baltic and nordic countries:
  Estonia, Finland, Latvia, Lithuania, Sweden
  Central and southeastern European countries:
  Austria, Bulgaria, Hungary, Romania                                                                                                                                                ■ Actual ■ Target (based on installed capacity 2008)
                                                                                                                                                                                 ■ Actual ■ Target (based on installed capacity 2008)

                                                                                                                                                                                                                             Source: Fraunhofer ISI, 2010, for WindBarriers




WindBarriers - Administrative and grid access barriers to wind power                                                                                                                                                                                                                                                19
xxx




                                                                Photo: Shutterstock




       Analysis of barriers
       in administrative procedures
      3.1 Generic model of the permitting process
      3.2 Barriers to administrative procedures
      3.3 A quick look at offshore
      3.4 Recommendations


      20                                            July 2010
In the following sections, the main barriers to the ad-                3.1 Generic model of
ministrative procedures are evaluated against the
requirements of Article 13 on “Administrative proce-                   the permitting process
dures, regulations and codes” of the 2009 Renewable
Energy Directive.                                                      Throughout the EU-27, project developers need to ob-
                                                                       tain a building permit in order to install a wind farm. This
This article is included at the end of this chapter                    goes for the grid connection as well: developers cannot
(page 36) its first paragraph reads: “All member states                link up to a network without a grid permit. Developers
[must] apply all proportionate and necessary rules con-                often need more than one permit, and barriers can be
cerning the authorisation, certification and licensing                 related both to other stakeholders involved in the proc-
procedures for the production of electricity, heating or               ess (such as NGOs, local community opposition, and
cooling from renewable energy.”                                        other sea users in the case of offshore) and/or the final
                                                                       building consent and grid connection.
The rest of the article defines the responsibility of the
member states to take the necessary steps in order                     Based on the information WindBarriers gathered on the
to ensure:                                                             perceived barriers to wind energy projects, a simplified
•	 Clear administrative structures and rules for certifi-              process can be drawn for the permit process, as shown
   cation and licensing at all administrative levels: lo-              in Figure 3.1.1 below.
   cal, regional and national.
•	 All the actors involved in the authorisation, certifica-            This simplified process is primarily based on onshore
   tion and licensing application for renewable energy                 wind farm procedures, as at this stage there are few
   installations have clear and concise information on                 descriptions of the procedures for offshore wind farms.
   what is required.                                                   The time needed to obtain these permits - the “lead
•	 Administrative procedures are simplified and stream-                time” - is calculated from the moment when the project
   lined at all levels for all stakeholders involved in the            developer submits his first application (both for the
   authorisation and permitting processes.                             building permit and for the grid connection permit) to
                                                                       the point in time when a wind farm is online.

                                                                       As the application processes for building and connect-
                                                                       ing a wind farm to the grid can run in parallel, the overall
                                                                       lead time cannot be calculated as the sum of the build-
                                                                       ing permit procedure and the grid connection procedure.
                                                                       Figure 3.1.1 summarises this process.

Figure 3.1.1: The process of getting the permit to build and connect a wind turbine



                                        2. Building                          3.  onstruction of
                                                                                C
                                        	 permit                                the wind farm

     1. Investment                                                                                          6. Productive
     	 decision                                                                                             	 wind farm
                                        4. Grid acces                        5. Physical grid
                                        	 permit                             	 access


                                                                 Lead time

                                                                                                Source: DWIA 2009, Windbarriers survey




WindBarriers - Administrative and grid access barriers to wind power                                                              21
Analysis of barriers in administrative procedures




               Phase 1: Investment decision/project planning:               •	 Lack of regulation and/or uncertainty about regula-
               The project developer first has to decide when to start         tion related to wind farms and electricity production.
               the application process for the necessary permits. If        •	 Overly strict rules on noise requirements and dis-
               the initial application is rejected, the lead time is con-      tance of wind farms from habitations.
               sidered to be zero.                                          •	 Negative/lack of support from local authorities and/
                                                                               or the neighbouring community.
               The most common barriers during this phase are mar-
               ket barriers, for example insufficient support schemes,      Phase 2: Early development and maturation:
               rejection of the project based on an informal dialogue       The real process of getting a permit starts when the
               with the public authority, or risks that are perceived by    project developer submits an application to get a build-
               developer as too high compared to the expected rate of       ing permit. Now a ‘sub-process’ begins and this proc-
               return. High risk can be caused by administrative barri-     ess differs from country to country.
               ers in the form of:
               •	 Lack of access to information concerning the mate-        The five sub-processes described in Figure 3.1.2 sum
                  rial needed for the permits.                              up the complete building permit procedure.



               Figure 3.1.2: Process for getting the building consent




                                                                                                        3.5. The building
                                                                  3.1. Approval of
                                                                                                        	    consent is
                                                                  	    the EIA
                                                                                                        	    approved



                          3.2. Public                             3.3. The planning                     3.4. Appeal
                          	    hearing                            	    act is decided                   	    process



                                                                                                     Source: DWIA, 2009, for WindBarriers




               22                                                                                                              July 2010
3.1 EIA approval process:                                              3.4 Complaint procedures / appeal process:
The public authorities prepare to take a decision to ap-               Much time can be wasted waiting for the outcome of
prove or reject the building permit. The process gener-                a complaint/appeal process. From the perspective of
ally begins at local level and it can run in parallel with             the project developer, these processes often lack clear,
other phases of the administrative processes.                          fixed deadlines, causing great uncertainty for the devel-
                                                                       oper as to the exact date/time when the building permit
The project developer can encounter barriers such as:                  will finally be obtained. There is also the possibility that
•	 Lack of official information about the decision-mak-                the authorities will reject the wind farm based on the
   ing process.                                                        complaint procedures.
•	 Delays in the administrative process. For example,
   even when the authority has a fixed deadline to give                The project is then stopped or started again with a new
   an answer to the EIA, it can postpone this deadline                 EIA process (box 2.1, Figure 3.2.1). Some developers
   by asking for more materials or studies from the                    also face legal proceedings against the project during
   project developer.                                                  or after the construction of the wind farm, which is a
•	 Negative attitude and inexperience of the authori-                  great financial burden.
   ties.
•	 Disagreement regarding the scope of the EIA and                     3.5. Building permit approved:
   the spatial planning.                                               At this stage, all the necessary permits are approved
•	 Having to contact several authorities to obtain the                 and the final building permit has been obtained.
   necessary permits.                                                  The project developer can now start building the
                                                                       wind farm.
3.2 Public hearing:
Approval of the EIA is often followed by a public hear-                Construction of the wind farm:
ing, where the local community can express their views                 Barriers related to the construction process are not
on the project. The typical barriers encountered at this               targeted in the WindBarriers project; therefore delays
stage are social acceptance barriers, such as the “not                 during construction were not counted in the overall lead
in my backyard” attitude (NIMBY), answering questions                  time.
from environmental NGOs, and a negative attitude from
the local authorities. Developers can face a lawsuit
against the project at this stage, but this happens more
often after the building consent has been given.

3.3 The planning act:
If the planning act is adapted to the wind farm project,
the developers will continue with an appeal process or
another legal proceeding (box 2.4, Figure 3.1.2) or they
will directly obtain the building permit (box 5, Figure
3.1.2). If the planning act is not adapted to the wind
farm, it can either be rejected outright, or developers
can be asked to start again with a new EIA process
(box 2.1, Figure 3.1.2). This delay occurs in almost all
EU countries.




WindBarriers - Administrative and grid access barriers to wind power                                                           23
Analysis of barriers in administrative procedures




               3.2. Barriers to administrative procedures

               Table 3.2.1: Barriers to administrative procedures and corresponding indicators


                                    Total           Number of        Number of         Administra-      Administra-       Transparency     Authority
                                    lead            authorities to   authorities       tive lead time   tive costs (of    of the           attitude (1-5)
                                    time            be contacted     with indirect     (months)         overall project   administrative
                                    (months)        directly         contact                            costs)            procedure
                                                                                                                          (1-5)
                Austria                  +                +                 -                +                 -                +                 -

                Belgium                  +                +                 -                +                 +                +                 0

                Bulgaria                 +                 -                +                +                 +                -                 -

                Czech Republic           +                 -                -                +                 -                0                 -

                Denmark                  +                +                 +                +                 +                 -                +

                Estonia                  +                 -                -                +                 +                +                 -

                Finland                  +                0                 -                +                 +                0                 -

                France                   +                 -                -                +                 +                0                 -

                Germany                  0                +                 -                +                 -                0                 0

                Greece                   0                 -                -                 -                -                 -                -

                Hungary                   -                -                -                +                 +                0                 -

                Ireland                  0                +                 0                +                 +                +                 +

                Italy                    +                 -                +                +                 +                0                 0

                Latvia                   +                +                 +                +                 +                0                 -

                Lithuania                +                 -                -                +                 -                 -                -

                Netherlands              +                +                 +                0                 -                 -                -

                Poland                   +                +                 -                0                 0                0                 0

                Portugal                  -               +                 +                 -                +                +                 +

                Romania                  +                0                 +                +                 +                0                 -

                Spain                     -               +                 +                 -                -                0                 0

                Sweden                   +                +                 -                0                 -                +                 +

                United Kingdom           +                +                 -                +                 0                0                 0

                Offshore EU              +                +                 -                +                 -                0                 0

                                                                                                             Source: EWEA 2010, based on WindBarriers




               Relative country performance:                                         Country colour codes:
               • “+” performs 10% or more better than the EU aver-                   ■ : Noticeable deviation from the EU average in negative
                  age.                                                               	 direction (worst cases).
               • “-” performs 10% or more below the EU average.                      ■ : Noticeable deviation from the EU average in positive
               • “0” performs at EU average, within a 10% range.                     	 direction (best cases).
                                                                                     ■ : Emerging markets.
               Offshore: comparison onshore / offshore practices                     ■ : Growth market.
                                                                                     ■ : Developed market.




               24                                                                                                                                July 2010
Total lead time                                                           The countries that have a lead time of longer than the
                                                                          EU average are Hungary, Portugal and Spain.
The length of the total lead time for obtaining all the
needed permits for wind projects across the EU-27 is                      Urgent action is needed to reduce these lead times,
on average 54.8 months for onshore and 32 months                          despite the fact that Portugal and Spain are considered
for offshore.                                                             extremely dynamic markets, falling in the categories of
                                                                          “developed” and “growth” markets.
As indicated in Figure 3.2.2, the total lead time is based
on both the administrative and grid connection proce-                     Reasons for long lead times vary from country to coun-
dures. For onshore, the best performing countries are                     try, but are often related to EIA restrictions and/or grid
Austria, Romania, and Finland with a total lead time of                   connection constraints due to a high number of re-
less than 20 months each. However, the very small sam-                    quests for connection to the power network.
ple size from these countries, due to a low level of MW
installed in 2008 (less than 10 projects), means that the                 We recommend an average lead time of 24 months at
results are not representative enough to be the basis of                  EU level for both onshore and offshore. EU member
a recommendation.                                                         states should take measures to reach this target by
                                                                          improving their EIA procedure3: reducing the number of
According to the survey, Belgium, the UK, Italy, France,                  authorities to be contacted when carrying out the EIA,
and Denmark each have a total lead time of between                        and putting concise EIA procedures in place.
25 and 35 months.




Figure 3.2.2: Definition of total lead time, administrative procedure, and grid connection procedures


                                  First application                                                         All main permits
        Administrative           made to an authority                                                           obtained
          procedure

                                                 First application made                                               Access to the grid
         Grid access                                to a grid operator                                                    secured
          procedure

                                    First application to an                                                       All main permits and
                                   authority or grid operator                                                     grid access obtained
         Overall process


                                                                                            Source: Fraunhofer ISI, based on WindBarriers




3
    The EIA should be carried out at member state level, based on European recommendations.




WindBarriers - Administrative and grid access barriers to wind power                                                                  25
Analysis of barriers in administrative procedures




               Administrative lead time                                                                     The three countries that are performing far below the
                                                                                                            average are Greece, Spain and Portugal, with more than
               The EU average administrative lead time for an onshore                                       50 months on average. For Spain and Portugal, this is
               wind energy project is 42 months. Compared to that,                                          related to the long total lead time. The Spanish case
               offshore wind energy is much quicker, with an average                                        is a paradox with a very long lead time for the admin-
               of 18 months. Figure 3.2.3 below shows clearly how                                           istrative process, but a small number of authorities to
               much the administrative lead time differs from country                                       be contacted (nine). This could indicate that there is
               to country.                                                                                  a surcharge on the administrative side due to a high
                                                                                                            number of applications in comparison to the allocated
               The total range of the administrative lead time varies                                       staff resources.
               from two to 154 months. Some developers in Den-
               mark, Greece, Portugal and Spain have experienced                                            However, taking into account the earlier recommen-
               lead times of 100 months or longer for their applica-                                        dations, and in order to achieve a total lead time of
               tions. For onshore, the five best performing countries                                       24 months, the EU average administrative lead time
               are: Finland, Austria, Romania, Italy and Belgium, with                                      should be reduced to a maximum of 20 months, pro-
               an administrative lead time of less than 20 months.                                          vided that the administrative and grid connection proce-
               Considering the small sample size for Finland, Austria                                       dures run in parallel.
               and Romania, with very little wind power capacity in-
               stalled in 2008 and 2007, the recommendations we
               make in the factsheets (Chapter 6) need to be tested
               on a larger sample.




               Figure 3.2.3: Administrative lead time for obtaining the building consent per EU country
                Month

                160

                140

                120

                 100

                 80

                 60

                 40

                 20

                  0
                         Belgium


                                   Czech Republic


                                                    Denmark


                                                              France


                                                                       Germany


                                                                                 Greece


                                                                                          Ireland


                                                                                                    Italy


                                                                                                            Netherlands


                                                                                                                          Poland


                                                                                                                                   Portugal


                                                                                                                                              Spain


                                                                                                                                                      United Kingdom


                                                                                                                                                                           CSE  4 proj.


                                                                                                                                                                                            BN  4 proj.


                                                                                                                                                                                                            Onshore EU


                                                                                                                                                                                                                            Offshore EU-27




                                                                                                                                                                       Source: 2009 WindBarriers survey


               Note 1: C and SE: Central and southeastern European countries: Austria, Bulgaria, Hungary and Romania; B and N: Baltic and Nordic
               countries: Estonia, Finland, Latvia, Lithuania and Sweden
               Note 2: The top of the box plot represents the maximum lead time, the middle bar the mean lead time and the bottom of the box plot
               the minimum lead time according to the survey answers received.




               26                                                                                                                                                                                                        July 2010
Number of authorities to be                                                                  EU countries, as already indicated in the 2001 Copen-
                                                                                             hagen strategy on offshore wind power deployment5.
contacted directly and indirectly4
                                                                                             Five countries are performing significantly below av-
On average, nine authorities have to be contacted di-                                        erage, namely Austria, Hungary, Finland, France and
rectly and an additional nine indirectly for onshore wind                                    Greece, with over 30 direct and indirect contacts to
projects in the EU, while offshore developers have to                                        make. In these countries, urgent action is needed to
liaise with seven authorities directly and 16 indirectly.                                    streamline the administrative processes.
These averages are relatively high compared to the
best performing countries on this indicator.

                                                                                             Administrative costs6
Taking into account both direct and indirect contacts,
the best performing countries in this study are Den-                                         On average, administrative costs in the EU represent
mark, the Netherlands and Spain, with fewer than ten                                         2.9% of the overall project costs for onshore and 14%
contacts in total. This is however much higher than the                                      for offshore. For offshore, this particularly large share
‘one-stop-shop’ approach, where the applicant would                                          is related to the high costs of the EIA studies required
have to contact a single entity in charge of coordinating                                    for the application procedure. For onshore, ten EU coun-
the application process for them. This should be the ob-                                     tries have administrative costs below 2%.
jective both for onshore and offshore wind energy in all



Figure 3.2.4: Administrative cost as a percentage of total project costs

    14

    12

    10

    8

    6

    5

    4

    2

    0
          Belgium


                    Czech Republic


                                     Denmark


                                               France


                                                        Germany


                                                                  Greece


                                                                           Ireland


                                                                                     Italy


                                                                                             Netherlands


                                                                                                           Poland


                                                                                                                      Portugal


                                                                                                                                 Spain


                                                                                                                                         United Kingdom


                                                                                                                                                          CSE  4 projects


                                                                                                                                                                              BN  4 projects


                                                                                                                                                                                                 Onshore EU-27


                                                                                                                                                                                                                 Offshore EU




                                                                                                                    Source: DWIA and Fraunhofer ISI 2010, for WindBarriers


Note 1: C and SE: Central and southeastern European countries: Austria, Bulgaria, Hungary and Romania, B and N: Baltic and Nordic
countries: Estonia, Finland, Latvia, Lithuania and Sweden

4
  Authorities to be contacted directly are the ones that a developer has to negotiate with personally or in correspondence, e.g.
  through applications or other documents. In some cases these documents are automatically forwarded to other authorities for
  processing, without action from the developer.
5
  Copenhagen Strategy on Offshore Wind Power Deployment, European Policy Seminar on Offshore Wind Power, Copenhagen,
  27 October 2005.
6
  The costs of the administrative procedures include all expenses needed for the building consent (NOT the grid connection proce-
  dures): a) staff costs for the administrative procedures, b) fees, c) costs for the preparation of necessary studies such as environ-
  mental impact assessments. “Overall cost” in this context means all the money spent in order to build the wind park, but not later
  operation and maintenance costs.
WindBarriers - Administrative and grid access barriers to wind power                                                                                                                                                     27
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power
Wind Barriers - Administrative and grid access barriers to wind power

More Related Content

What's hot

Myanmar energy-sector-assessment
Myanmar energy-sector-assessmentMyanmar energy-sector-assessment
Myanmar energy-sector-assessment
Next Gen Group of Company
 
Pv industry status report 2009
Pv industry status report 2009Pv industry status report 2009
Pv industry status report 2009
pvcoworker
 
The effect of wind on chp
The effect of wind on chpThe effect of wind on chp
The effect of wind on chpEamon Keane
 
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
Leonardo ENERGY
 
Solar PV Rural Electrification and Energy-Poverty
Solar PV Rural Electrification and Energy-PovertySolar PV Rural Electrification and Energy-Poverty
Solar PV Rural Electrification and Energy-Poverty
Hans-Dieter Evers
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
vijcons
 
An Overview of the Electricity Industry in Myanmar
An Overview of the Electricity Industry in MyanmarAn Overview of the Electricity Industry in Myanmar
An Overview of the Electricity Industry in Myanmar
Vikas Sharma
 
Myanmar’s Hydropower Strategy and Its Impact on Industry Players
Myanmar’s  Hydropower Strategy  and  Its  Impact on Industry  PlayersMyanmar’s  Hydropower Strategy  and  Its  Impact on Industry  Players
Myanmar’s Hydropower Strategy and Its Impact on Industry Players
Dr. Oliver Massmann
 
Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...
Private Consultants
 
Consultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERCConsultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERCSpark Network
 
SETT seminar presentation, RU2
SETT seminar presentation, RU2SETT seminar presentation, RU2
SETT seminar presentation, RU2
artursskroderis
 
The Future Perspective of the Electricity Market – Unbundling and Market Inte...
The Future Perspective of the Electricity Market – Unbundling and Market Inte...The Future Perspective of the Electricity Market – Unbundling and Market Inte...
The Future Perspective of the Electricity Market – Unbundling and Market Inte...
Oeko-Institut
 
Ser for 2020
Ser for 2020Ser for 2020
Ser for 2020ProjetoBr
 
Utah's Energy Landscape
Utah's Energy LandscapeUtah's Energy Landscape
Utah's Energy Landscape
State of Utah, Salt Lake City
 

What's hot (15)

Ukraine
UkraineUkraine
Ukraine
 
Myanmar energy-sector-assessment
Myanmar energy-sector-assessmentMyanmar energy-sector-assessment
Myanmar energy-sector-assessment
 
Pv industry status report 2009
Pv industry status report 2009Pv industry status report 2009
Pv industry status report 2009
 
The effect of wind on chp
The effect of wind on chpThe effect of wind on chp
The effect of wind on chp
 
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
Article 14 of Directive 2012/27/EU: “Promotion of efficiency in heating and c...
 
Solar PV Rural Electrification and Energy-Poverty
Solar PV Rural Electrification and Energy-PovertySolar PV Rural Electrification and Energy-Poverty
Solar PV Rural Electrification and Energy-Poverty
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
 
An Overview of the Electricity Industry in Myanmar
An Overview of the Electricity Industry in MyanmarAn Overview of the Electricity Industry in Myanmar
An Overview of the Electricity Industry in Myanmar
 
Myanmar’s Hydropower Strategy and Its Impact on Industry Players
Myanmar’s  Hydropower Strategy  and  Its  Impact on Industry  PlayersMyanmar’s  Hydropower Strategy  and  Its  Impact on Industry  Players
Myanmar’s Hydropower Strategy and Its Impact on Industry Players
 
Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...Report of the committee appointed to investigate the Electricity Supply Inter...
Report of the committee appointed to investigate the Electricity Supply Inter...
 
Consultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERCConsultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERC
 
SETT seminar presentation, RU2
SETT seminar presentation, RU2SETT seminar presentation, RU2
SETT seminar presentation, RU2
 
The Future Perspective of the Electricity Market – Unbundling and Market Inte...
The Future Perspective of the Electricity Market – Unbundling and Market Inte...The Future Perspective of the Electricity Market – Unbundling and Market Inte...
The Future Perspective of the Electricity Market – Unbundling and Market Inte...
 
Ser for 2020
Ser for 2020Ser for 2020
Ser for 2020
 
Utah's Energy Landscape
Utah's Energy LandscapeUtah's Energy Landscape
Utah's Energy Landscape
 

Viewers also liked

EWEA Annual Offshore Statistics 2013
EWEA Annual Offshore Statistics 2013EWEA Annual Offshore Statistics 2013
EWEA Annual Offshore Statistics 2013
EWEA - European Wind Energy Association
 
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
EWEA - European Wind Energy Association
 
EWEA wind energy annual statistics 2013
EWEA wind energy annual statistics 2013EWEA wind energy annual statistics 2013
EWEA wind energy annual statistics 2013
EWEA - European Wind Energy Association
 
Lettre nationale décembre 2016
Lettre nationale décembre 2016Lettre nationale décembre 2016
Lettre nationale décembre 2016
Empruntis
 
2030: The next steps for EU climate and energy policy
2030: The next steps for EU climate and energy policy2030: The next steps for EU climate and energy policy
2030: The next steps for EU climate and energy policy
EWEA - European Wind Energy Association
 
2030: the next steps for EU climate and energy policy
2030: the next steps for EU climate and energy policy2030: the next steps for EU climate and energy policy
2030: the next steps for EU climate and energy policy
EWEA - European Wind Energy Association
 

Viewers also liked (6)

EWEA Annual Offshore Statistics 2013
EWEA Annual Offshore Statistics 2013EWEA Annual Offshore Statistics 2013
EWEA Annual Offshore Statistics 2013
 
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
European Offshore Wind Industry - Key Trends and Statistics, first half 2013 ...
 
EWEA wind energy annual statistics 2013
EWEA wind energy annual statistics 2013EWEA wind energy annual statistics 2013
EWEA wind energy annual statistics 2013
 
Lettre nationale décembre 2016
Lettre nationale décembre 2016Lettre nationale décembre 2016
Lettre nationale décembre 2016
 
2030: The next steps for EU climate and energy policy
2030: The next steps for EU climate and energy policy2030: The next steps for EU climate and energy policy
2030: The next steps for EU climate and energy policy
 
2030: the next steps for EU climate and energy policy
2030: the next steps for EU climate and energy policy2030: the next steps for EU climate and energy policy
2030: the next steps for EU climate and energy policy
 

Similar to Wind Barriers - Administrative and grid access barriers to wind power

Accelerated replacement of electric motors
Accelerated replacement of electric motorsAccelerated replacement of electric motors
Accelerated replacement of electric motors
Leonardo ENERGY
 
European research on concentrated solar thermal energi
European research on concentrated solar thermal energiEuropean research on concentrated solar thermal energi
European research on concentrated solar thermal energiSaif Azhar
 
Wind Power Regulatory Framework Survey 2016
Wind Power Regulatory Framework  Survey 2016Wind Power Regulatory Framework  Survey 2016
Wind Power Regulatory Framework Survey 2016
Stavros Thomas
 
The European Renewable Electricity Sector 2009/20
The European Renewable Electricity Sector 2009/20The European Renewable Electricity Sector 2009/20
The European Renewable Electricity Sector 2009/20
ReportLinker.com
 
Jrc115923 stationary fuel_cells_16042019_final_pubsy_online
Jrc115923 stationary fuel_cells_16042019_final_pubsy_onlineJrc115923 stationary fuel_cells_16042019_final_pubsy_online
Jrc115923 stationary fuel_cells_16042019_final_pubsy_online
Enzo Ochoa Montes
 
Consulta pública sobre la directiva de eficiencia energética en edificios
Consulta pública sobre la directiva de eficiencia energética en edificiosConsulta pública sobre la directiva de eficiencia energética en edificios
Consulta pública sobre la directiva de eficiencia energética en edificios
MARATUM Marketing A Tu Medida
 
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05Grupa PTWP S.A.
 
Energy efficiency technologies
Energy efficiency technologiesEnergy efficiency technologies
Energy efficiency technologies
Teale Asia
 
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
Leonardo ENERGY
 
How to develop an adaptation city plan jrc3
How to develop an adaptation city plan jrc3How to develop an adaptation city plan jrc3
How to develop an adaptation city plan jrc3
PatrickTanz
 
Glass
GlassGlass
Energy waste in buildings
Energy waste in buildingsEnergy waste in buildings
Energy waste in buildings
World Office Forum
 
7-libre.pdf
7-libre.pdf7-libre.pdf
7-libre.pdf
prabu kumar
 
Solar Plan Report 2010
Solar Plan Report 2010Solar Plan Report 2010
Solar Plan Report 2010
PARIS
 
Draft report on the implementation and impact of the energy efficiency measur...
Draft report on the implementation and impact of the energy efficiency measur...Draft report on the implementation and impact of the energy efficiency measur...
Draft report on the implementation and impact of the energy efficiency measur...
MARIE Project
 
Minigrid policy toolkit 2014 REN21
Minigrid policy toolkit 2014 REN21Minigrid policy toolkit 2014 REN21
Minigrid policy toolkit 2014 REN21
PatrickTanz
 
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
Leonardo ENERGY
 
2016 Eurelectric ActivityReport
2016 Eurelectric ActivityReport2016 Eurelectric ActivityReport
2016 Eurelectric ActivityReportAnamaria Olaru
 
Ec8 seismic design_of_buildings-worked_examples
Ec8 seismic design_of_buildings-worked_examplesEc8 seismic design_of_buildings-worked_examples
Ec8 seismic design_of_buildings-worked_examples
jfernando22
 
How to develop an adaptation city plan jrc1
How to develop an adaptation city plan jrc1How to develop an adaptation city plan jrc1
How to develop an adaptation city plan jrc1
PatrickTanz
 

Similar to Wind Barriers - Administrative and grid access barriers to wind power (20)

Accelerated replacement of electric motors
Accelerated replacement of electric motorsAccelerated replacement of electric motors
Accelerated replacement of electric motors
 
European research on concentrated solar thermal energi
European research on concentrated solar thermal energiEuropean research on concentrated solar thermal energi
European research on concentrated solar thermal energi
 
Wind Power Regulatory Framework Survey 2016
Wind Power Regulatory Framework  Survey 2016Wind Power Regulatory Framework  Survey 2016
Wind Power Regulatory Framework Survey 2016
 
The European Renewable Electricity Sector 2009/20
The European Renewable Electricity Sector 2009/20The European Renewable Electricity Sector 2009/20
The European Renewable Electricity Sector 2009/20
 
Jrc115923 stationary fuel_cells_16042019_final_pubsy_online
Jrc115923 stationary fuel_cells_16042019_final_pubsy_onlineJrc115923 stationary fuel_cells_16042019_final_pubsy_online
Jrc115923 stationary fuel_cells_16042019_final_pubsy_online
 
Consulta pública sobre la directiva de eficiencia energética en edificios
Consulta pública sobre la directiva de eficiencia energética en edificiosConsulta pública sobre la directiva de eficiencia energética en edificios
Consulta pública sobre la directiva de eficiencia energética en edificios
 
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05
Ey ecf macro-economic-impacts-of-the-low-carbon-transition_report_2014-06-05
 
Energy efficiency technologies
Energy efficiency technologiesEnergy efficiency technologies
Energy efficiency technologies
 
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
The Scope for Energy Saving in the EU through the Use of Energy-Efficient Dis...
 
How to develop an adaptation city plan jrc3
How to develop an adaptation city plan jrc3How to develop an adaptation city plan jrc3
How to develop an adaptation city plan jrc3
 
Glass
GlassGlass
Glass
 
Energy waste in buildings
Energy waste in buildingsEnergy waste in buildings
Energy waste in buildings
 
7-libre.pdf
7-libre.pdf7-libre.pdf
7-libre.pdf
 
Solar Plan Report 2010
Solar Plan Report 2010Solar Plan Report 2010
Solar Plan Report 2010
 
Draft report on the implementation and impact of the energy efficiency measur...
Draft report on the implementation and impact of the energy efficiency measur...Draft report on the implementation and impact of the energy efficiency measur...
Draft report on the implementation and impact of the energy efficiency measur...
 
Minigrid policy toolkit 2014 REN21
Minigrid policy toolkit 2014 REN21Minigrid policy toolkit 2014 REN21
Minigrid policy toolkit 2014 REN21
 
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
Replicable NAMA Concept - Promoting the Use of Energy Efficient Motors in Ind...
 
2016 Eurelectric ActivityReport
2016 Eurelectric ActivityReport2016 Eurelectric ActivityReport
2016 Eurelectric ActivityReport
 
Ec8 seismic design_of_buildings-worked_examples
Ec8 seismic design_of_buildings-worked_examplesEc8 seismic design_of_buildings-worked_examples
Ec8 seismic design_of_buildings-worked_examples
 
How to develop an adaptation city plan jrc1
How to develop an adaptation city plan jrc1How to develop an adaptation city plan jrc1
How to develop an adaptation city plan jrc1
 

More from EWEA - European Wind Energy Association

EWEA Annual Report 2012: United in tough times
EWEA Annual Report 2012: United in tough timesEWEA Annual Report 2012: United in tough times
EWEA Annual Report 2012: United in tough times
EWEA - European Wind Energy Association
 
Fix the Emissions Trading System infographic
Fix the Emissions Trading System infographicFix the Emissions Trading System infographic
Fix the Emissions Trading System infographic
EWEA - European Wind Energy Association
 
Emerging wind energy markets europe
Emerging wind energy markets europeEmerging wind energy markets europe
Emerging wind energy markets europe
EWEA - European Wind Energy Association
 
Wind energy: a pocketful of facts
Wind energy: a pocketful of factsWind energy: a pocketful of facts
Wind energy: a pocketful of facts
EWEA - European Wind Energy Association
 
European offshore statistics 2012
European offshore statistics 2012European offshore statistics 2012
European offshore statistics 2012
EWEA - European Wind Energy Association
 
Wind in Power: European wind energy statistics 2012
Wind in Power: European wind energy statistics 2012Wind in Power: European wind energy statistics 2012
Wind in Power: European wind energy statistics 2012
EWEA - European Wind Energy Association
 
Creating the Internal Energy Market in Europe
Creating the Internal Energy Market in EuropeCreating the Internal Energy Market in Europe
Creating the Internal Energy Market in Europe
EWEA - European Wind Energy Association
 
Energy and the EU budget 2014-2020
Energy and the EU budget 2014-2020Energy and the EU budget 2014-2020
Energy and the EU budget 2014-2020
EWEA - European Wind Energy Association
 
EWEA Annual Report 2011
EWEA Annual Report 2011EWEA Annual Report 2011
Green Growth - the impact of wind energy on jobs and the economy
Green Growth - the impact of wind energy on jobs and the economyGreen Growth - the impact of wind energy on jobs and the economy
Green Growth - the impact of wind energy on jobs and the economy
EWEA - European Wind Energy Association
 
Wind in our Sails - The coming of Europe's offshore wind energy industry
Wind in our Sails - The coming of Europe's offshore wind energy industryWind in our Sails - The coming of Europe's offshore wind energy industry
Wind in our Sails - The coming of Europe's offshore wind energy industry
EWEA - European Wind Energy Association
 
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
EWEA - European Wind Energy Association
 
OffshoreGrid: Offshore Electricity Infrastructure in Europe
OffshoreGrid: Offshore Electricity Infrastructure in EuropeOffshoreGrid: Offshore Electricity Infrastructure in Europe
OffshoreGrid: Offshore Electricity Infrastructure in Europe
EWEA - European Wind Energy Association
 
EU energy policy after 2020 - Mind the gap
EU energy policy after 2020 - Mind the gapEU energy policy after 2020 - Mind the gap
EU energy policy after 2020 - Mind the gap
EWEA - European Wind Energy Association
 
Pure Power - Wind Energy Targets from 2020 and 2030
Pure Power - Wind Energy Targets from 2020 and 2030Pure Power - Wind Energy Targets from 2020 and 2030
Pure Power - Wind Energy Targets from 2020 and 2030
EWEA - European Wind Energy Association
 
EWEA Annual Report 2010 - Powering the Energy Debate
EWEA Annual Report 2010 - Powering the Energy DebateEWEA Annual Report 2010 - Powering the Energy Debate
EWEA Annual Report 2010 - Powering the Energy Debate
EWEA - European Wind Energy Association
 
Single market - The most powerful freedom
Single market - The most powerful freedomSingle market - The most powerful freedom
Single market - The most powerful freedom
EWEA - European Wind Energy Association
 
Upwind - Design limits and solutions for very large wind turbines
Upwind - Design limits and solutions for very large wind turbinesUpwind - Design limits and solutions for very large wind turbines
Upwind - Design limits and solutions for very large wind turbines
EWEA - European Wind Energy Association
 
EU Energy Policy to 2050 - Achieving 80-95% emissions reductions
EU Energy Policy to 2050 - Achieving 80-95% emissions reductionsEU Energy Policy to 2050 - Achieving 80-95% emissions reductions
EU Energy Policy to 2050 - Achieving 80-95% emissions reductions
EWEA - European Wind Energy Association
 
Powering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity gridPowering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity grid
EWEA - European Wind Energy Association
 

More from EWEA - European Wind Energy Association (20)

EWEA Annual Report 2012: United in tough times
EWEA Annual Report 2012: United in tough timesEWEA Annual Report 2012: United in tough times
EWEA Annual Report 2012: United in tough times
 
Fix the Emissions Trading System infographic
Fix the Emissions Trading System infographicFix the Emissions Trading System infographic
Fix the Emissions Trading System infographic
 
Emerging wind energy markets europe
Emerging wind energy markets europeEmerging wind energy markets europe
Emerging wind energy markets europe
 
Wind energy: a pocketful of facts
Wind energy: a pocketful of factsWind energy: a pocketful of facts
Wind energy: a pocketful of facts
 
European offshore statistics 2012
European offshore statistics 2012European offshore statistics 2012
European offshore statistics 2012
 
Wind in Power: European wind energy statistics 2012
Wind in Power: European wind energy statistics 2012Wind in Power: European wind energy statistics 2012
Wind in Power: European wind energy statistics 2012
 
Creating the Internal Energy Market in Europe
Creating the Internal Energy Market in EuropeCreating the Internal Energy Market in Europe
Creating the Internal Energy Market in Europe
 
Energy and the EU budget 2014-2020
Energy and the EU budget 2014-2020Energy and the EU budget 2014-2020
Energy and the EU budget 2014-2020
 
EWEA Annual Report 2011
EWEA Annual Report 2011EWEA Annual Report 2011
EWEA Annual Report 2011
 
Green Growth - the impact of wind energy on jobs and the economy
Green Growth - the impact of wind energy on jobs and the economyGreen Growth - the impact of wind energy on jobs and the economy
Green Growth - the impact of wind energy on jobs and the economy
 
Wind in our Sails - The coming of Europe's offshore wind energy industry
Wind in our Sails - The coming of Europe's offshore wind energy industryWind in our Sails - The coming of Europe's offshore wind energy industry
Wind in our Sails - The coming of Europe's offshore wind energy industry
 
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
Wind Energy and EU climate policy: Achieving 30% lower emissions by 2020
 
OffshoreGrid: Offshore Electricity Infrastructure in Europe
OffshoreGrid: Offshore Electricity Infrastructure in EuropeOffshoreGrid: Offshore Electricity Infrastructure in Europe
OffshoreGrid: Offshore Electricity Infrastructure in Europe
 
EU energy policy after 2020 - Mind the gap
EU energy policy after 2020 - Mind the gapEU energy policy after 2020 - Mind the gap
EU energy policy after 2020 - Mind the gap
 
Pure Power - Wind Energy Targets from 2020 and 2030
Pure Power - Wind Energy Targets from 2020 and 2030Pure Power - Wind Energy Targets from 2020 and 2030
Pure Power - Wind Energy Targets from 2020 and 2030
 
EWEA Annual Report 2010 - Powering the Energy Debate
EWEA Annual Report 2010 - Powering the Energy DebateEWEA Annual Report 2010 - Powering the Energy Debate
EWEA Annual Report 2010 - Powering the Energy Debate
 
Single market - The most powerful freedom
Single market - The most powerful freedomSingle market - The most powerful freedom
Single market - The most powerful freedom
 
Upwind - Design limits and solutions for very large wind turbines
Upwind - Design limits and solutions for very large wind turbinesUpwind - Design limits and solutions for very large wind turbines
Upwind - Design limits and solutions for very large wind turbines
 
EU Energy Policy to 2050 - Achieving 80-95% emissions reductions
EU Energy Policy to 2050 - Achieving 80-95% emissions reductionsEU Energy Policy to 2050 - Achieving 80-95% emissions reductions
EU Energy Policy to 2050 - Achieving 80-95% emissions reductions
 
Powering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity gridPowering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity grid
 

Recently uploaded

Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
Product School
 

Recently uploaded (20)

Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 

Wind Barriers - Administrative and grid access barriers to wind power

  • 1. WindBarriers Administrative and grid access barriers to wind power July 2010
  • 2. Grant agreement number: IEE/07/513/SI2.499556 Duration: December 2008 – November 2010 Co-ordinator: European Wind Energy Association asbl/vzw (EWEA) Cover picture: © Ecotecnia Project partners: Asociación Empresarial Eólica (AEE) DONG Energy A/S Austrian Wind Power GmbH Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer) Iberdrola Renovables S.A. Magyar Szélenergia Társaság (HWEA) Polskie Stowarzyszenie Energetyki Wiatrowej (PWEA) Vindmølleindustrien (DWIA) Supported by: The sole responsibility for the content of this document lies with the authors. It does not necessarily reflect the opinion of the European Communities. The European Commission is not responsible for any use that may be made of the information contained herein.
  • 3. WindBarriers Administrative and grid access barriers to wind power July 2010
  • 4. Photo: RES 2 July 2010
  • 5. Contents Executive summary................................................................................................................................... 6 Chapter 2: Project methodology. ............................................................................................................. 14 . Chapter 3: Analysis of barriers in administrative procedures..................................................................... 20 . 3.1 Generic model of the permitting process........................................................................................ 21 . 3.2 Barriers to administrative procedures............................................................................................. 24 3.3 A quick look at offshore. ............................................................................................................... 32 . 3.4 Recommendations........................................................................................................................ 34 Chapter 4: Analysis of barriers to grid connection. ................................................................................... 38 . 4.1 Generic model of the grid connection process................................................................................. 39 4.2 Barriers to grid connection. ........................................................................................................... 42 . 4.3 A quick look at offshore. ............................................................................................................... 50 . 4.4 Recommendations........................................................................................................................ 51 Chapter 5: Market-based analysis............................................................................................................ 56 5.1 Types of market............................................................................................................................ 57 5.2 Analysis per type of market. .......................................................................................................... 59 . 5.3 Regional analysis.......................................................................................................................... 68 Chapter 6: Country factsheets................................................................................................................. 74 6.1 Reader’s guide to the country factsheets........................................................................................ 75 6.2 Factsheets................................................................................................................................... 76 Appendix. ............................................................................................................................................. 145 . Windbarriers project partners. ........................................................................................................... 145 . Bibliography.......................................................................................................................................... 146 WindBarriers - Administrative and grid access barriers to wind power 3
  • 6. PRINCIPAL AUTHORS: Alberto Ceña, Asociación Empresarial Eólica (AEE) Dorina Iuga, European Wind Energy Association (EWEA) Emilien Simonot, Asociación Empresarial Eólica (AEE) Nicolas Fichaux, European Wind Energy Association (EWEA) Sharon Wokke, European Wind Energy Association (EWEA) Sune Strøm, Vindmølleindustrien (DWIA) ACKNOWLEDGEMENTS: The authors wish to thank everyone who contributed to drafting and producing this report. In particular we would like to gratefully acknowledge the following persons: Contributors: Benjamin Pfluger, Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer) Wendelin Macht, Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. (Fraunhofer) Revisers: Julian Scola, European Wind Energy Association (EWEA) Editing: Sarah Azau, European Wind Energy Association (EWEA) Zoe Casey, European Wind Energy Association (EWEA) Special thanks to: EWEA’s national wind energy member associations for their important contribution to the project. The developers who replied to the WindBarriers survey. Glória Rodrigues (EWEA) and Jacopo Moccia (EWEA) for their very useful remarks. Design and production by: Megaluna Design coordinator: Raffaella Bianchin, European Wind Energy Association (EWEA) Published in July 2010 Printed on FSC certified paper Disclaimer: The analysis, conclusions and recommendations provided in this publication are based on the answers received on onshore and offshore wind projects from developers in 23 EU countries in the framework of the WindBarriers project. Some of the samples are too small to be representative and therefore the corresponding recommendations would need to be confirmed on a larger scale. 4 July 2010
  • 7. Foreword I am delighted to introduce this first publication from The WindBarriers project, which is supported by the the WindBarriers project. The Directive on the pro- Intelligent Energy Europe programme, is expected to motion of the use of energy from renewable sources significantly reduce the lead times for the develop- (2009/28/EC) is a pillar of European sustainable ment of new wind projects, and it also has the po- energy policy, and its implementation will require sig- tential to accelerate the development of projects in- nificant efforts from EU member states to reduce ad- volving other renewable energy sources. It will engage ministrative and grid access barriers. The WindBarri- with decision makers and help them to benchmark ers project is important because it supports member their performance using an agreed monitoring meth- states in this implementation process by providing odology. a clear and detailed picture of the challenges being faced across the EU, as well as indicating some of the WindBarriers has the potential to make an important ways these challenges can be overcome. contribution to accelerating the growth of renewable energy markets across the EU, and to implementing WindBarriers analyses both the administrative and our common European vision of a more sustainable grid access processes in the different member states future. and regions, and compares them using transparent and objective criteria. This will help to highlight best practices, as well as to identify potential bottlenecks. William Gillett Head of Unit Renewable Energy European Commission Executive Agency for Competiveness and Innovation (EACI) WindBarriers - Administrative and grid access barriers to wind power 5
  • 8. xxx Photo: Gehring Executive summary 6 July 2010
  • 9. Introduction Questions were asked on a set of potential barriers – referred to as “indicators” - allowing information to be On 30 June 2009, the European Commission adopted gathered on the administrative and grid obstacles in a template setting out the minimum requirements for 23 countries of the EU. The results from the indicators the National Renewable Energy Action Plans (NREAPs), can be compared from country to country, giving an in- as required by Directive 2009/28/EC of the European dication of the implementation of the 2001 and 2009 Parliament and of the Council of 23 April 2009 (2009 EU directives. The results are accompanied by a set Renewable Energy Directive). of recommendations on how to improve administrative and grid access procedures in the EU-27 in order to The NREAPs, which are to be provided to the European help each EU member state reach its binding target, as Commission by June 2010, are national roadmaps of described in Table 1.1. each country’s expected path to its binding renewable energy target for 2020. Each NREAP is to set out the country’s expected renewable energy contribution, both Administrative procedures and in terms of capacity to be installed (MW) and of energy production (MWh), for each of the renewable energy corresponding barriers technologies mentioned in the directive from 2010 to 2020. Moreover, each member state (MS) has to pro- Project developers need to obtain a building permit in vide an estimate of its gross final energy consumption order to install a wind farm. This goes for the grid con- from all types of energy (both renewable and non-renew- nection as well. The total time taken to get the building able), for each year between 2010 and 2020, for three consent and grid connection permits is called the to- sectors: heating/cooling, electricity and transport. The tal “lead time” of a wind farm. Based on the WindBar- NREAPs will also include information on all policies and riers survey, the average total lead time in the EU is support schemes to promote renewable energy in that 54.8 months for onshore and 32 months for offshore. country. Reasons for the long lead times vary from country to country, but they are often related to Environmen- The WindBarriers project seeks to build a reliable meth- tal Impact Assessment (EIA) restrictions and/or grid odology to obtain concise information on the adminis- connection constraints. trative and grid connection barriers that obstruct the development of wind energy. This methodology is to be The EU average for the administrative lead time of an used by member states and the European Commission onshore wind energy project is 42 months. Compared to monitor the implementation of Articles 6 (adminis- to this, offshore wind energy projects seem to be much trative schemes) and 7 (grid connection) of directive quicker, with an average of 18 months according to 2001/77/EC on the promotion of electricity produced the surveys submitted to the WindBarriers project. The from renewable energy sources, which correspond to administrative lead time differs significantly for each the new Articles 13 and 16 of the 2009 Renewable country and each project: from 2 to 154 months. Some Energy Directive. developers in Greece, Portugal and Spain have experi- enced lead times of 100 months or longer for their build- Building on a large stakeholder consultation, the Wind- ing permit applications. As regards offshore, a possible Barriers consortium put together an extensive data- explanation for the shorter building consent time is that base with precise information on administrative and the six countries in the survey seem to have developed grid barriers. More than 200 wind energy projects in- efficient and streamlined decision-making processes, stalled during 2007 and 2008, both onshore and off- including Maritime Spatial Planning (MSP). shore across the EU-27, were analysed. WindBarriers - Administrative and grid access barriers to wind power 7
  • 10. Executive summary On average nine authorities have to be contacted di- Once a project developer has secured the basic tech- rectly and an additional nine indirectly for onshore nical requirements (e.g. project location, sufficient wind projects in the EU, while offshore developers wind resource, access to the site of the future farm), have to liaise with seven authorities directly and 16 a grid connection application can be sent to the indirectly. This is, however, many more than would system operator. be involved in the recommended ‘one-stop-shop’ approach, whereby the applicant would have to contact A basic technical project is submitted to the Distribu- a single entity which would be in charge of coordinat- tion System Operator (DSO), but can be transferred to ing the whole application process. The ‘one-stop-shop’ the Transmission System Operator (TSO) if it requires a should be an EU objective for both onshore and off- higher grid capacity (usually over 132 kV). shore projects. According to the WindBarriers survey, the EU aver- The barriers faced by developers during this proc- age for grid connection lead time is 25.8 months for ess are often related to the approval and scope onshore projects and 14 months for offshore; for on- of the Environmental Impact Assessment, compli- shore, the grid access lead time is significantly lower ance with spatial planning, the number of parties/ than the administrative one (42 months). authorities involved and to barriers related to other stakeholders involved in the process (e.g. social The average number of TSOs involved in the grid acceptance issues). connection process is 0.85 onshore and 0.92 off- shore, whereas for the DSOs, it is 0.77 onshore and For offshore, the main barriers are likely to be the ad- 0.47 offshore. In terms of third parties involved dur- ministrative bodies’ lack of experience, an unclear EIA ing the grid connection process, the EU average is process, and difficult interaction with other users of the 24 onshore and 4.4 offshore. The ideal situa- sea, according to the survey. tion remains the ‘one-stop-shop’ approach, as described above. Costs, the approach of the authorities, the transparen- cy of the decision-making process and the use of dead- The barriers faced by developers during this process lines are also analysed in the survey - and depending are mostly related to an absence of clear information on the country, they can constitute an obstacle to wind on the available grid connection capacity, a lack of plan- power development. ning for future grid extension and reinforcements on behalf of system operators, insufficient grid capacity, and other aspects such as land ownership and the EIA. Grid connection procedure and corresponding barriers Some of the main barriers to grid connection pro- cedures were evaluated against the requirements of Article 13 of the Renewable Energy Directive 2009/28/EC. 8 July 2010
  • 11. Table 1.1: Overview of the main results of the survey on administrative and grid procedures Administrative procedure Grid access procedure Total lead Administra- Authorities: Authorities: Grid TSOs DSOs Other time tive direct indirect access parties: lead time contact contact lead time grid Average Average Average Average Average Average Average Average Country Months Months Number Number Months Number Number Number Austria** 31.65 18.93 10.38 13.90 17.56 0.84 1.00 3.42 Belgium 22.61 20.33 4.08 10.28 7.08 0.91 1.00 3.18 Bulgaria** 31.65 18.93 10.38 13.90 17.56 0.84 1.00 3.42 Czech Republic 39.44 31.56 11.23 11.44 24.76 1.25 0.77 6.91 Denmark 34.46 31.81 4.25 0.90 2.01 0.78 0.92 0.13 Estonia* 37.80 28.30 10.54 16.03 22.33 1.72 1.38 5.46 Finland* 37.80 28.30 10.54 16.03 22.33 1.72 1.38 5.46 France 34.02 29.58 22.06 14.22 6.36 1.00 1.65 14.39 Germany 55.15 30.12 6.16 20.41 6.59 0.76 0.64 8.60 Greece 54.60 50.09 18.63 22.38 20.20 0.84 1.00 11.80 Hungary** 31.65 18.93 10.38 13.90 17.56 0.84 1.00 3.42 Ireland 55.59 33.49 5.74 8.77 31.42 0.82 1.00 5.01 Italy 32.24 18.06 12.73 2.84 18.96 0.45 0.51 32.25 Latvia* 37.80 28.30 10.54 16.03 22.33 1.72 1.38 5.46 Lithuania* 37.80 28.30 10.54 16.03 22.33 1.72 1.38 5.46 Netherlands 45.74 38.85 4.34 1.93 12.93 0.75 0.66 1.11 Poland 48.76 43.09 7.78 12.57 15.46 0.89 0.88 32.13 Portugal 71.11 58.03 7.58 6.61 46.61 0.79 0.38 47.25 Romania** 31.65 18.93 10.38 13.90 17.56 0.84 1.00 3.42 Spain 76.08 57.74 5.53 4.28 33.50 0.94 0.80 27.85 Sweden* 37.80 28.30 10.54 16.03 22.33 1.72 1.38 5.46 United Kingdom 25.88 26.87 3.47 11.74 8.36 0.55 0.94 2.62 Offshore EU 32.00 18.52 6.88 15.92 14.06 0.92 0.47 4.44 Onshore EU-27 54.80 42.32 9.03 9.13 25.83 0.85 0.77 23.89 Offshore EU-6 31.67 28.67 12.10 11.63 7.68 1.00 1.25 7.87 Source: EWEA 2010, WindBarriers survey * grouped as ‘Baltic and nordic countries with less than four projects’ ** grouped as ‘Central and eastern European countries with under four projects’ WindBarriers - Administrative and grid access barriers to wind power 9
  • 12. Executive summary Recommendations to EU-27 member states Administrative procedures: Article 13 of the EU 2009 Renewable Energy Directive Total lead times • Reduce the average total lead time in the EU to 24 months; • Make clear requirements on Environmental Impact Assessments (EIAs) (fixed dead- lines, how many EIAs need to be carried out depending on the size of the park, its location) and reduce the number of irrelevant documents; • Develop spatial planning by defining the most appropriate locations and wind development areas, lowering investment risks and streamlining project application procedures; • Train and allocate enough civil servants to handle the expected applications; Number of authori- • Develop and implement the ‘one-stop-shop’ approach in all member states; ties to be contacted • The authorities should disseminate clear information to developers on the adminis- directly and indirectly trative procedures and decision-making processes; Administrative • Lower the average administrative lead time to a maximum of 20 months, to ensure lead times that the total lead time in the EU stays below 24 months; • Perform onshore and offshore spatial planning and define the most suitable wind development areas, with streamlined administrative procedures in these areas; • Provide clear definitions of the administrative requirements, in terms of procedures, deadlines and EIA content; • Set deadlines for the administrative process. If the authority is not able to meet the deadline, the project automatically goes to the next stage; • Train and allocate the necessary civil servants to handle the expected applications; Administrative costs • Lower the average administrative costs in the EU to 1.5% of the total project costs; • Perform a preliminary environmental assessment; • Give incentives to competent authorities to gather data and studies collected under the EIA process and make them public; • Limit the administrative requirements to the key relevant elements, in particular the ones identified through past projects. Update procedures regularly; • Learn from past projects, and avoid requiring similar information from other projects with the same conditions; • For offshore, maritime spatial planning should give special importance to cross- border cooperation and to developing synergies with other sea users; 10 July 2010
  • 13. Transparency of • Improve the transparency of administrative procedures across the EU to an average the administrative of 4 out of 5 1; procedure • Inform both the developers and the local authorities of the applicable rules and regulations; • Set deadlines for the administrative process. If the authority is not able to meet the deadline, the project automatically goes to the next stage; Authority’s attitude • Improve the attitude of local authorities across the EU to an average of 4 out of 5 2; • National authorities should make sure local and regional authorities are aware of the targets set out in their NREAP and of the necessity for their country to , meet them; • Disseminate transparent and unbiased information to the authorities at all levels on wind energy technology and developments, addressing the myths associated with wind energy. 1 According to the WindBarriers survey, the transparency of administrative procedures is rated 3.21 on average, on a range from 1 to 5 where 1 means non-transparent and 5 means maximum transparency. 2 The attitude of local authorities is rated 3.36 on average across the EU, on a range from 1 to 5, where 1 means ‘negative attitude’ and 5 means ‘maximum positive attitude’ WindBarriers - Administrative and grid access barriers to wind power 11
  • 14. Executive summary Grid connection procedures: Article 16 of the 2009 EU Renewable Energy Directive Grid connection • Reduce the average grid connection lead time in the EU to six months; lead time • Set deadlines for the administrative process. If the authority is not able to meet the deadline, the project automatically goes to the next stage; • Train and allocate the necessary civil servants to handle the expected applications; • Develop the grid infrastructure: - Provide clear definitions of the grid connection requirements. In particular, de- velop and implement standardised grid codes across the EU; - Plan and build transnational offshore grid infrastructure to connect the antici- pated offshore wind power, and guarantee connection to the grid for offshore wind projects; - Reinforce the onshore and offshore transmission system (through cooperation between different EU member states); - Finding and occupying the land for interconnection infrastructure for wind farms should be made easier, with adequate economic compensation for the land owners; • On the developer’s side: - Avoid an excess of requests on the same grid point; the projects should be realistic and based on measured wind data. The use of the land should also be guaranteed for the entire length of the project; - Close collaboration with grid operators is required; Grid connection costs • Lower the average grid connection costs in the EU to 2.5% of project costs; • System operators should cover and contribute to the grid connection costs in the countries where this is not yet the case, and adapt these costs to the project size; • Upgrade the public grid infrastructure within reasonable costs; • Limit the technical grid connection requirements to a reasonable level (remain within the scope of the project); • Provide clear definitions of the grid connection requirements. In particular, develop and implement standardised grid codes across the EU. Grid codes have to be real- istic and compatible with the latest technology. Harmonisation of grid codes at EU level is important; • The voltage range should be the minimum required according to the short circuit ca- pacity of the grid and the load flows in the common coupling point (PCC). Feasibility studies should identify the voltage range for the connection. This will affect the final line tracing and the costs and time schedule; • Clear information about grid costs should be provided to developers at an early at an early stage of project development, in order to reduce investment risks; 12 July 2010
  • 15. Transparency of • Improve the transparency of the grid connection process at EU level to an average the grid connection of 4 out of 5 1; • Provide a clear, streamlined procedure and decision-making process for process grid connection; • Unbundling of vertically integrated power companies would make grid access fairer. Plans for the construction and reinforcement of new grid lines should be realistic and effective. It is fundamental to have better coordination between distribution and transmission companies when building new infrastructure and for connection requests. This coordination should also be extended during the wind farm’s operation; • Widely publicise information on the characteristics of the grid. Developers can carry out access capacity studies and propose technical and management solutions. These proposals will allow grid capacity to be increased and a realistic calendar to be set for grid connection; • Set deadlines for the grid connection process. If the authority is not able to meet the deadline, the project should automatically go to the next stage of the authorisa- tion process. According to the WindBarriers survey, the transparency of administrative procedures is rated 3.21 on average, on a range from 1 to 1 5 where 1 means non-transparent and 5 means maximum transparency. WindBarriers - Administrative and grid access barriers to wind power 13
  • 16. xxx Photo: Jan Oelker Project methodology 14 July 2010
  • 17. The aim of the project methodology was to find criteria Targeting recent projects: that could be used to measure administrative and grid barriers to wind energy projects for years to come. 2008 and 2007 Before beginning to collect the data, the consortium The objective of the project was to collect recent data set up a working group made up of experts from the from both large and small projects, in all EU-27 coun- consortium partners, 27 national wind energy asso- tries, via a questionnaire. In order to have the most ciations, and representatives of the Executive Agency up-to-date information on barriers to wind energy devel- for Competiveness and Innovation (EACI). The working opment, it was decided to focus on projects installed group agreed on a specific methodology, based around in 2008 (when the project started). In order to obtain the following criteria. statistically reliable datasets, representative of the dif- ferent rates of development across the EU, the consor- tium decided to monitor a minimum of 10 projects per country, and to cover from 20% to 50% of new capacity installed in 2008 in each country, as described below. Since some countries installed low amounts of wind en- ergy in 2008, projects from 2007 were also sometimes taken into account, provided they were relevant. Figure 2.1: Map of the cumulative capacity in MW at the end of 2008 Finland 143 Norway 428 Faroe Islands Estonia Russia 4 Sweden 78 11 1,021 Denmark Latvia Rep. of Ireland 3,180 27 1,002 Lithuania UK 54 3,241 Netherlands European Union: 64,935 MW 2,225 Poland Belgium Germany 472 Candidate Countries: 452 MW 384 23,903 EFTA: 442 MW Luxembourg Czech Republic Ukraine Total Europe: 65,933 MW 35 150 90 Slovakia France 3 Switzerland Austria 3,404 995 Hungary 14 127 Croatia Romania 18 10 Portugal 2,862 Spain Bulgaria 16,740 Italy 158 3,736 Turkey 433 Greece 985 Source: EWEA WindBarriers - Administrative and grid access barriers to wind power 15
  • 18. Project methodology Building a representative Getting a minimum sample: adaptation to number of projects market dynamism In addition to covering the minimum percentages men- The goal was to build a data sample that represented tioned above, the sample was expected to include at the different types of market in Europe. Considering the least 10 projects per country. However, this was not wide variability of annual installed capacity in the differ- possible in Cyprus, Latvia, Luxembourg, Malta and ent countries, the sample size for each country had to Slovenia, as there were not enough new projects in be adapted to the market size. This was done in order 2008. In such cases, the project collected other rel- to avoid collecting the vast majority of data from large evant data to indicate the barriers. developed markets, and losing focus of the newer wind energy players, where the barriers may be higher. Analysing regional variations: Generally, market analysts determine the maturity of the market (regulatory environment, public authorities’ regional distribution expertise, developers’ skills, and so on) using four mar- ket categories based on the new installed capacity. Ex- In order to ensure that all types of regional develop- perience shows that a high annual installation of wind ment were considered, the samples targeted regions power is a good indicator of the level of barriers for where wind power was less developed. countries with similar wind resources. The Nomenclature of Territorial Units for Statistics For the WindBarriers project, the consortium used the (NUTS) classification of the Committee of the Regions capacity installed in 2008 as per statistics published was used to define regions; but not all regions in each by the European Wind Energy Association (EWEA: see country were to be covered by WindBarriers. Figure 3.1). More information on these statistics is available on EWEA’s annual statistics web page on A substantial number of the projects to be consid- www.ewea.org. ered per country were to come from regions that performed at or below the European average. The • For countries where less than 150 MW came online remaining projects were to come from the best in 2008, the sample had to cover at least 50% of the performing regions. new installed capacity. • For countries where between 150 MW and 1,000 Balancing the regional distribution was one of the most MW came online in 2008, the sample had to cover complex tasks in this project and only a few countries at least 30% of the new installed capacity. managed to take it into account in the definition of their • For countries where more than 1,000 MW came on- country sample. line in 2008, the sample had to cover at least 20% of the new installed capacity. 16 July 2010
  • 19. Looking for showstoppers: Definition of the indicators analysis of non-finalised projects The main aim of the questionnaire was to obtain a While obtaining a balanced overview of recently imple- comprehensive description of existing administra- mented projects in the EU was relatively straightfor- tive and grid access barriers, primarily in a quantita- ward, projects that are planned but whose implementa- tive manner, by means of particular criteria or “indi- tion has been delayed represent a significant capacity cators”. In order to evaluate the results, and make that is not registered in any database and can be at recommendations, it was necessary to make the bar- various stages of development. riers in the individual member states measureable and comparable. However, it is necessary to differentiate between projects delayed specifically due to administrative barri- A summary of the indicators is given in Table 2.1. They ers, and projects delayed because of the lack of experi- fall into three categories depending on whether they ence of the developer, an inadequate project proposal, measure administrative or grid access barriers, or pro- or an overly speculative approach. vide overall information on the project and the devel- oper’s success rate. The WindBarriers consortium decided to address this issue by adding a specific section on delayed/ In most cases, direct quantification of the barriers was blocked projects to the questionnaire. Since the ques- possible. The questions relate to numerical values with tionnaire was filled in by developers with a proven pre-defined units. Lead times are measured in months, track record, the consortium avoided considering costs as a percentage of the overall project costs, unrealistic projects. and the number of involved authorities, operators or other persons/parties involved in the project in ab- solute values. Sample and survey The indicators measuring administrative and grid ac- cess transparency are derived from several ques- On the basis of these criteria, each national wind tions. The respective answers are ranked on a energy association compiled a sample of repre- five-point scale. sentative projects, and identified the developers to be contacted. A copy of the WindBarriers online based questionnaire was sent to those developers. Almost all member states were covered, with the exception of the coun- tries where no capacity was installed at all in 2008. WindBarriers - Administrative and grid access barriers to wind power 17
  • 20. Project methodology Table 2.1: Selected indicators Number of Indicator Unit questions Total lead time Months 1 Overall Number of projects on hold in same region Numerical value 1 Number of authorities that developer must contact directly Numerical value 1 Number of authorities developer does not have to contact directly Numerical value 1 Administrative barriers Administrative lead time Months 1 Administrative costs As share (%) of total project costs 1 Authority’s attitude [1-5] 1 Transparency of administrative procedure [1-5] 4 Number of Transmission System Operators (TSOs) involved Numerical value 1 Number of Distribution System Operators (DSOs) involved Numerical value 1 Grid connection barriers Number of other parties involved in obtaining grid connection Numerical value 1 Grid connection lead time Months 1 Grid connection costs As share (%) of total project costs 1 Transparency of grid connection process [1-5] 3 Source: Fraunhofer ISI 2009, for WindBarriers 18 July 2010
  • 21. Confidentiality and the project partners and that only aggregated figures would be published. Despite these measures, for some representativeness countries the number of replies was relatively low and the results would therefore have to be considered cau- Before the data gathering process began, the consor- tiously and tested on a larger sample. tium decided to cover the whole questionnaire with a confidentiality agreement. It stipulated that the data The target amount of replies for each country, and the from the questionnaire would only be visible to two of actual number received, can be seen below: Figure 2.2: Rate of replies 900 900 31 800 800 700 700 23 600 15 Answers in MWMW 600 500 Answers in 500 10 400 400 300 13 300 10 200 10 11 12 9 13 200 6 100 12 12 6 100 0 Spain Portugal Poland Italy Greece France Ireland Baltic & Nordic Netherlands Central & southeastern Germany Belgium Denmark United Kingdom Czech Republic 0 Spain Portugal Poland Italy Greece France Ireland Netherlands Germany Hungary Belgium Denmark Estonia United Kingdom Latvia Sweden Czech Republic Bulgaria Finland Austria Lithuania Romania Baltic and nordic countries: Estonia, Finland, Latvia, Lithuania, Sweden Central and southeastern European countries: Austria, Bulgaria, Hungary, Romania ■ Actual ■ Target (based on installed capacity 2008) ■ Actual ■ Target (based on installed capacity 2008) Source: Fraunhofer ISI, 2010, for WindBarriers WindBarriers - Administrative and grid access barriers to wind power 19
  • 22. xxx Photo: Shutterstock Analysis of barriers in administrative procedures 3.1 Generic model of the permitting process 3.2 Barriers to administrative procedures 3.3 A quick look at offshore 3.4 Recommendations 20 July 2010
  • 23. In the following sections, the main barriers to the ad- 3.1 Generic model of ministrative procedures are evaluated against the requirements of Article 13 on “Administrative proce- the permitting process dures, regulations and codes” of the 2009 Renewable Energy Directive. Throughout the EU-27, project developers need to ob- tain a building permit in order to install a wind farm. This This article is included at the end of this chapter goes for the grid connection as well: developers cannot (page 36) its first paragraph reads: “All member states link up to a network without a grid permit. Developers [must] apply all proportionate and necessary rules con- often need more than one permit, and barriers can be cerning the authorisation, certification and licensing related both to other stakeholders involved in the proc- procedures for the production of electricity, heating or ess (such as NGOs, local community opposition, and cooling from renewable energy.” other sea users in the case of offshore) and/or the final building consent and grid connection. The rest of the article defines the responsibility of the member states to take the necessary steps in order Based on the information WindBarriers gathered on the to ensure: perceived barriers to wind energy projects, a simplified • Clear administrative structures and rules for certifi- process can be drawn for the permit process, as shown cation and licensing at all administrative levels: lo- in Figure 3.1.1 below. cal, regional and national. • All the actors involved in the authorisation, certifica- This simplified process is primarily based on onshore tion and licensing application for renewable energy wind farm procedures, as at this stage there are few installations have clear and concise information on descriptions of the procedures for offshore wind farms. what is required. The time needed to obtain these permits - the “lead • Administrative procedures are simplified and stream- time” - is calculated from the moment when the project lined at all levels for all stakeholders involved in the developer submits his first application (both for the authorisation and permitting processes. building permit and for the grid connection permit) to the point in time when a wind farm is online. As the application processes for building and connect- ing a wind farm to the grid can run in parallel, the overall lead time cannot be calculated as the sum of the build- ing permit procedure and the grid connection procedure. Figure 3.1.1 summarises this process. Figure 3.1.1: The process of getting the permit to build and connect a wind turbine 2. Building 3. onstruction of C permit the wind farm 1. Investment 6. Productive decision wind farm 4. Grid acces 5. Physical grid permit access Lead time Source: DWIA 2009, Windbarriers survey WindBarriers - Administrative and grid access barriers to wind power 21
  • 24. Analysis of barriers in administrative procedures Phase 1: Investment decision/project planning: • Lack of regulation and/or uncertainty about regula- The project developer first has to decide when to start tion related to wind farms and electricity production. the application process for the necessary permits. If • Overly strict rules on noise requirements and dis- the initial application is rejected, the lead time is con- tance of wind farms from habitations. sidered to be zero. • Negative/lack of support from local authorities and/ or the neighbouring community. The most common barriers during this phase are mar- ket barriers, for example insufficient support schemes, Phase 2: Early development and maturation: rejection of the project based on an informal dialogue The real process of getting a permit starts when the with the public authority, or risks that are perceived by project developer submits an application to get a build- developer as too high compared to the expected rate of ing permit. Now a ‘sub-process’ begins and this proc- return. High risk can be caused by administrative barri- ess differs from country to country. ers in the form of: • Lack of access to information concerning the mate- The five sub-processes described in Figure 3.1.2 sum rial needed for the permits. up the complete building permit procedure. Figure 3.1.2: Process for getting the building consent 3.5. The building 3.1. Approval of consent is the EIA approved 3.2. Public 3.3. The planning 3.4. Appeal hearing act is decided process Source: DWIA, 2009, for WindBarriers 22 July 2010
  • 25. 3.1 EIA approval process: 3.4 Complaint procedures / appeal process: The public authorities prepare to take a decision to ap- Much time can be wasted waiting for the outcome of prove or reject the building permit. The process gener- a complaint/appeal process. From the perspective of ally begins at local level and it can run in parallel with the project developer, these processes often lack clear, other phases of the administrative processes. fixed deadlines, causing great uncertainty for the devel- oper as to the exact date/time when the building permit The project developer can encounter barriers such as: will finally be obtained. There is also the possibility that • Lack of official information about the decision-mak- the authorities will reject the wind farm based on the ing process. complaint procedures. • Delays in the administrative process. For example, even when the authority has a fixed deadline to give The project is then stopped or started again with a new an answer to the EIA, it can postpone this deadline EIA process (box 2.1, Figure 3.2.1). Some developers by asking for more materials or studies from the also face legal proceedings against the project during project developer. or after the construction of the wind farm, which is a • Negative attitude and inexperience of the authori- great financial burden. ties. • Disagreement regarding the scope of the EIA and 3.5. Building permit approved: the spatial planning. At this stage, all the necessary permits are approved • Having to contact several authorities to obtain the and the final building permit has been obtained. necessary permits. The project developer can now start building the wind farm. 3.2 Public hearing: Approval of the EIA is often followed by a public hear- Construction of the wind farm: ing, where the local community can express their views Barriers related to the construction process are not on the project. The typical barriers encountered at this targeted in the WindBarriers project; therefore delays stage are social acceptance barriers, such as the “not during construction were not counted in the overall lead in my backyard” attitude (NIMBY), answering questions time. from environmental NGOs, and a negative attitude from the local authorities. Developers can face a lawsuit against the project at this stage, but this happens more often after the building consent has been given. 3.3 The planning act: If the planning act is adapted to the wind farm project, the developers will continue with an appeal process or another legal proceeding (box 2.4, Figure 3.1.2) or they will directly obtain the building permit (box 5, Figure 3.1.2). If the planning act is not adapted to the wind farm, it can either be rejected outright, or developers can be asked to start again with a new EIA process (box 2.1, Figure 3.1.2). This delay occurs in almost all EU countries. WindBarriers - Administrative and grid access barriers to wind power 23
  • 26. Analysis of barriers in administrative procedures 3.2. Barriers to administrative procedures Table 3.2.1: Barriers to administrative procedures and corresponding indicators Total Number of Number of Administra- Administra- Transparency Authority lead authorities to authorities tive lead time tive costs (of of the attitude (1-5) time be contacted with indirect (months) overall project administrative (months) directly contact costs) procedure (1-5) Austria + + - + - + - Belgium + + - + + + 0 Bulgaria + - + + + - - Czech Republic + - - + - 0 - Denmark + + + + + - + Estonia + - - + + + - Finland + 0 - + + 0 - France + - - + + 0 - Germany 0 + - + - 0 0 Greece 0 - - - - - - Hungary - - - + + 0 - Ireland 0 + 0 + + + + Italy + - + + + 0 0 Latvia + + + + + 0 - Lithuania + - - + - - - Netherlands + + + 0 - - - Poland + + - 0 0 0 0 Portugal - + + - + + + Romania + 0 + + + 0 - Spain - + + - - 0 0 Sweden + + - 0 - + + United Kingdom + + - + 0 0 0 Offshore EU + + - + - 0 0 Source: EWEA 2010, based on WindBarriers Relative country performance: Country colour codes: • “+” performs 10% or more better than the EU aver- ■ : Noticeable deviation from the EU average in negative age. direction (worst cases). • “-” performs 10% or more below the EU average. ■ : Noticeable deviation from the EU average in positive • “0” performs at EU average, within a 10% range. direction (best cases). ■ : Emerging markets. Offshore: comparison onshore / offshore practices ■ : Growth market. ■ : Developed market. 24 July 2010
  • 27. Total lead time The countries that have a lead time of longer than the EU average are Hungary, Portugal and Spain. The length of the total lead time for obtaining all the needed permits for wind projects across the EU-27 is Urgent action is needed to reduce these lead times, on average 54.8 months for onshore and 32 months despite the fact that Portugal and Spain are considered for offshore. extremely dynamic markets, falling in the categories of “developed” and “growth” markets. As indicated in Figure 3.2.2, the total lead time is based on both the administrative and grid connection proce- Reasons for long lead times vary from country to coun- dures. For onshore, the best performing countries are try, but are often related to EIA restrictions and/or grid Austria, Romania, and Finland with a total lead time of connection constraints due to a high number of re- less than 20 months each. However, the very small sam- quests for connection to the power network. ple size from these countries, due to a low level of MW installed in 2008 (less than 10 projects), means that the We recommend an average lead time of 24 months at results are not representative enough to be the basis of EU level for both onshore and offshore. EU member a recommendation. states should take measures to reach this target by improving their EIA procedure3: reducing the number of According to the survey, Belgium, the UK, Italy, France, authorities to be contacted when carrying out the EIA, and Denmark each have a total lead time of between and putting concise EIA procedures in place. 25 and 35 months. Figure 3.2.2: Definition of total lead time, administrative procedure, and grid connection procedures First application All main permits Administrative made to an authority obtained procedure First application made Access to the grid Grid access to a grid operator secured procedure First application to an All main permits and authority or grid operator grid access obtained Overall process Source: Fraunhofer ISI, based on WindBarriers 3 The EIA should be carried out at member state level, based on European recommendations. WindBarriers - Administrative and grid access barriers to wind power 25
  • 28. Analysis of barriers in administrative procedures Administrative lead time The three countries that are performing far below the average are Greece, Spain and Portugal, with more than The EU average administrative lead time for an onshore 50 months on average. For Spain and Portugal, this is wind energy project is 42 months. Compared to that, related to the long total lead time. The Spanish case offshore wind energy is much quicker, with an average is a paradox with a very long lead time for the admin- of 18 months. Figure 3.2.3 below shows clearly how istrative process, but a small number of authorities to much the administrative lead time differs from country be contacted (nine). This could indicate that there is to country. a surcharge on the administrative side due to a high number of applications in comparison to the allocated The total range of the administrative lead time varies staff resources. from two to 154 months. Some developers in Den- mark, Greece, Portugal and Spain have experienced However, taking into account the earlier recommen- lead times of 100 months or longer for their applica- dations, and in order to achieve a total lead time of tions. For onshore, the five best performing countries 24 months, the EU average administrative lead time are: Finland, Austria, Romania, Italy and Belgium, with should be reduced to a maximum of 20 months, pro- an administrative lead time of less than 20 months. vided that the administrative and grid connection proce- Considering the small sample size for Finland, Austria dures run in parallel. and Romania, with very little wind power capacity in- stalled in 2008 and 2007, the recommendations we make in the factsheets (Chapter 6) need to be tested on a larger sample. Figure 3.2.3: Administrative lead time for obtaining the building consent per EU country Month 160 140 120 100 80 60 40 20 0 Belgium Czech Republic Denmark France Germany Greece Ireland Italy Netherlands Poland Portugal Spain United Kingdom CSE 4 proj. BN 4 proj. Onshore EU Offshore EU-27 Source: 2009 WindBarriers survey Note 1: C and SE: Central and southeastern European countries: Austria, Bulgaria, Hungary and Romania; B and N: Baltic and Nordic countries: Estonia, Finland, Latvia, Lithuania and Sweden Note 2: The top of the box plot represents the maximum lead time, the middle bar the mean lead time and the bottom of the box plot the minimum lead time according to the survey answers received. 26 July 2010
  • 29. Number of authorities to be EU countries, as already indicated in the 2001 Copen- hagen strategy on offshore wind power deployment5. contacted directly and indirectly4 Five countries are performing significantly below av- On average, nine authorities have to be contacted di- erage, namely Austria, Hungary, Finland, France and rectly and an additional nine indirectly for onshore wind Greece, with over 30 direct and indirect contacts to projects in the EU, while offshore developers have to make. In these countries, urgent action is needed to liaise with seven authorities directly and 16 indirectly. streamline the administrative processes. These averages are relatively high compared to the best performing countries on this indicator. Administrative costs6 Taking into account both direct and indirect contacts, the best performing countries in this study are Den- On average, administrative costs in the EU represent mark, the Netherlands and Spain, with fewer than ten 2.9% of the overall project costs for onshore and 14% contacts in total. This is however much higher than the for offshore. For offshore, this particularly large share ‘one-stop-shop’ approach, where the applicant would is related to the high costs of the EIA studies required have to contact a single entity in charge of coordinating for the application procedure. For onshore, ten EU coun- the application process for them. This should be the ob- tries have administrative costs below 2%. jective both for onshore and offshore wind energy in all Figure 3.2.4: Administrative cost as a percentage of total project costs 14 12 10 8 6 5 4 2 0 Belgium Czech Republic Denmark France Germany Greece Ireland Italy Netherlands Poland Portugal Spain United Kingdom CSE 4 projects BN 4 projects Onshore EU-27 Offshore EU Source: DWIA and Fraunhofer ISI 2010, for WindBarriers Note 1: C and SE: Central and southeastern European countries: Austria, Bulgaria, Hungary and Romania, B and N: Baltic and Nordic countries: Estonia, Finland, Latvia, Lithuania and Sweden 4 Authorities to be contacted directly are the ones that a developer has to negotiate with personally or in correspondence, e.g. through applications or other documents. In some cases these documents are automatically forwarded to other authorities for processing, without action from the developer. 5 Copenhagen Strategy on Offshore Wind Power Deployment, European Policy Seminar on Offshore Wind Power, Copenhagen, 27 October 2005. 6 The costs of the administrative procedures include all expenses needed for the building consent (NOT the grid connection proce- dures): a) staff costs for the administrative procedures, b) fees, c) costs for the preparation of necessary studies such as environ- mental impact assessments. “Overall cost” in this context means all the money spent in order to build the wind park, but not later operation and maintenance costs. WindBarriers - Administrative and grid access barriers to wind power 27