SlideShare a Scribd company logo
1 of 29
Seite 1 
Support Mechanisms for RE 
Development in Viet Nam 
Hanoi, 19/09/2014 
Ingmar Stelter, Program Manager 
Werner Kossmann, Chief Technical Advisor 
GIZ Viet Nam Energy Support Program
Seite 2 
Technical Cooperation in Viet Nam
National Strategy 
PDP VII objectives on RE: Increase in electricity produced from RE sources 
2020 2030 
5.6% 9.4% 
500 MW 
1000 MW 
2000 MW 
6200 MW 
2700 MW 
Biomass Wind Biomass Wind 
5620 MW 
Other RE 
Other RE 
Planned Installed Capacity 
Other RE: Biogas, Waste-to-Energy, Solar PV/ST, SHP etc. 
Source: PDP 7 
19.09.2014 Energy Sector Development Partners Coordination Page 3
Barriers for RE Development in Viet Nam 
Lack of national 
(comprehensive) law 
for RE 
Low electricity price 
Limited data 
availability (and poor 
data quality) 
Limited capacities on 
central and provincial 
level 
Difficult access to 
information 
Limited access to 
financing (equity & 
loans) 
Complex and unclear 
procedures for RE 
investments 
19.09.2014 Energy Sector Development Partners Coordination Page 4
Existing Support Mechanisms for RE – I/II 
SHP Wind Power 
Decision 18/2008/QD-TTg (18.07.2008) 
• In 2014: 2.7 – 3.2 US-Cents/kWh (depending on 
season and daytime) 
• Avoided-Cost-Tariff, varied by year 
• Calculated annually based on 1 kWh electricity 
avoided from the most expensive power plant 
connected to the national grid 
• Duration of PPA: 20 Years 
Decision 37/2011/QD-TTg (29.06.2011) 
• Feed-in-Tariff for Wind Power 
• Tariff: 7,8 US-Cents/kWh (6.8+1) 
• Duration of PPA: 20 Years 
• GIZ-supported; currently under revision 
19.09.2014 Energy Sector Development Partners Coordination Page 5
Existing Support Mechanisms for RE – II/II 
Biomass Solid Waste 
Decision 24/2014/QD-TTg (29.06.2014) 
• FiT for electricity from CHP-Biomass 
Power: 5.8 US-Cents/kWh 
• Avoided-Cost Tariff for electricity from 
other Biomass plants 
• Annually calculated based on the avoided 
cost for 1 kWh electricity from imported 
coal 
• Duration of PPA: 20 Years 
• GIZ-supported 
Decision: 31/2014/QD-TTg (05.05.2014) 
• Feed-in-Tariff for electricity from MSW 
• Incineration: 10.05 US-Cents/kWh 
• Landfill-Gas: 7.28 US-Cents/kWh 
• Duration of PPA: 20 Years 
• GIZ-supported 
19.09.2014 Energy Sector Development Partners Coordination Page 6
Additional Incentive Mechanisms for RE 
• Corporate income tax 
• Years 1-4: tax exemption 
• Years 5-13: 50% tax reduction 
• Import tax (goods, machinery etc.) 
• Varying levels of import tax, depending on type of imported goods 
• Exemption on goods forming fixed assets, which cannot be 
produced locally 
• Waiving of land use/lease fees 
• Land is provided for free as part of the licensing agreement 
 These are substantial financial incentives for project developers. 
 However, in a situation of financial stress, tax incentives cannot 
cushion liquidity problems as there are no tax payments to be made. 
19.09.2014 Energy Sector Development Partners Coordination Page 7
Revision of the support mechanism for wind – I/III 
• Methodology: 
• Qualitative: interviews, questionnaires, assessment of exist. framework 
• Quantitative: wind data, pre-/feasibility studies, international comparison 
• General findings/recommendations (excerpt): 
• FiT payment system should be a one-stop-shop (not VNEPF+FiT) 
• Government guarantee for payments 
• Better wind speed measurements and improved standards are required 
• Enforce standard agreements for network connection and power 
purchase 
19.09.2014 Energy Sector Development Partners Coordination Page 8
Revision of the support mechanism for wind – II/III 
• Basis for analysis: 
• PDP target: 1GW wind power by 2020 (currently: ca. 50MW) 
• Assumptions for CapEx, O&M, Capacity Factor: based on P/FS, 
questionnaires, international experience 
• Required investment and assumed investor structure: 
• 1GW by 2020 = ca. US$ 2.1 billion over the next 6 years 
• At average debt level of 70% => US$ 630m equity and 1.47b debt 
• This investment level cannot (should not) be reached with public 
investment only. 
• Assumed investor types: highly-subsidized, strategic, fully commercial 
19.09.2014 Energy Sector Development Partners Coordination Page 9
Revision of the support mechanism for wind – III/III 
• FiT calculation: 
• All three investor types must be targeted with the FiT 
• Assumed IRR: 10% (international experience) 
• Basis for FiT calculation: Levelized cost of electricity (LEC) 
• Also included: additional incentives like tax breaks etc. 
• Result: 
• Proposed FiT for on-shore installations: US-cents 10.4 / kWh 
• Proposed funding scheme: Tariff-funded, i.e. through a levy on the 
electricity price: for 1GW by 2020 => less than 5VND/kWh 
19.09.2014 Energy Sector Development Partners Coordination Page 10
Bioenergy technologies applicable in Vietnam 
Biomass 
- Sugarcane bagasse 
- Rice straw/husk 
- Timber waste 
Biogas 
- Animal manure 
- Industrial wastewater 
- HDPE covered lagoon 
Municipal Solid Waste 
- Incineration 
- Landfill Gas 
19.09.2014 Energy Sector Development Partners Coordination Page 11
FiT for non-CHP biomass power (avoided cost tariff) 
Government opted for the avoided cost tariff based on imported coal as 
reference price for biomass 
Reason to apply an avoided cost tariff based on imported coal: 
• Coal thermal power plant has the highest share in power mix 
• Avoid electricity generated from these plants 
• Biomass power plants as substitution to provide base load in the system 
Problem: 
• Annually calculated and issued 
• Fluctuating coal prices 
• Inflexible in combination with 20 years PPA 
19.09.2014 Energy Sector Development Partners Coordination Page 12
Comparison of regulated prices with proposed levels for 
Bioenergy 
Technology Proposed 
purchasing price 
(US-Cents/kWh) 
Regulated level (US-Cents/ 
kWh) 
Sugarcane bagasse 5.6 5.8 
Rice husk 7.34 
Avoided cost based 
tariff 
Rice straw 10.79 
Timber waste 8.77 
SW - Landfill gas 7.28 7.28 
SW – Incineration 10.05 10.05 
19.09.2014 Energy Sector Development Partners Coordination Page 13
Thank you for your attention!! 
Werner Kossmann Ingmar Stelter 
werner.Kossmann@giz.de ingmar.stelter@giz.de 
04 39 41 26 05 - 15 04 39 34 49 51 - 114 
19.09.2014 Energy Sector Development Partners Coordination Page 14
Backup: Installed capacity of electricity sources (2013) 
Source Capacity (MW) Rate (%) 
Big hydropower 13,260 43.21 
Coal thermo-electric 7,116 23.19 
Gas thermo-electric 7,446 2.97 
Oil thermo-electric 912 0.22 
RE 
Small hydropower (≤ 30MW) 1,670 5.44 
Wind 52 0.18 
Biomass 150 0.49 
Biogas/MSW 4 0.01 
Solar PV 4 0.01 
Total 30,684 
Share of RE: 
6.13% 
Source: GDE 2014 
19.09.2014 Energy Sector Development Partners Coordination Page 15
Backup: Electricity production (2013) 
Source Output (GWh) Rate (%) 
Big hydropower 56,943 40.51 
Coal thermo-electric 26.843 20.93 
Gas thermo-electric 42,650 33.26 
Oil thermo-electric 95 0.07 
Others 249 0.19 
Exported 1,337 1.04 
Diesel 7 - 
Small hydropower 4,989 3.89 
Wind 62 est. 0,05 
Bioenergy (Biomass, -gas, 
47 est. 0,04 
MSW) 
Solar PV 
Total 128,228 
Share of RE: 
3.98% 
Source: GDE 2014 
19.09.2014 Energy Sector Development Partners Coordination Page 16
5.2 FiT calculations 
The following assumptions result from the analysis of the 
feasibility studies and questionnaires 
• Average CapEx: 2.0 USD Mio. /MW 
• Average O&M cost 35,000 USD / MW per year 
• Average capacity factor: 30% 
This is in line with international experience! 
19.09.2014 Energy Sector Development Partners Coordination Page 17
5.2 FiT calculations; international benchmark: CapEx 
19.09.2014 Energy Sector Development Partners Coordination Page 18
5.2 FiT calculations; international benchmark: OpEx 
19.09.2014 Energy Sector Development Partners Coordination Page 19
5.2 FiT calculations; international benchmark: Capacity 
Factor 
19.09.2014 Energy Sector Development Partners Coordination Page 20
5.2 FiT calculations 
• Levelized Electricity Cost (LEC) as basis of analysis 
• LEC is function of CapEx, discounted OM (OpEx) and total electricity 
production (Capacity factor) 
• LEC(푰푹푹) = 
푪풂풑푬풙+푷푽푶풑푬풙(푰푹푹) 
푷푽푬풍풆풄(푰푹푹) 
• There is a direct relationship between internal rate of return (IRR) and 
LEC 
• According to intl. experience, investors typically demand a project 
IRR of 10%, resulting in an LEC of US Cent 10.4 
19.09.2014 Energy Sector Development Partners Coordination Page 21
5.2 FiT calculations 
Sensitivities derived from feasibility studies and questionnaires 
Scenario CapEx [million USD/MW] O&M [T USD/MW*year] Capacity Factor 
Base 
2.00 35.00 30.0% 
case 
CapEx+ 2.25 35.00 30.0% 
CapEx- 1.65 35.00 30.0% 
O&M+ 2.00 45.00 30.0% 
O&M- 2.00 25.00 30.0% 
Capacity+ 2.00 35.00 35.0% 
Capacity- 2.00 35.00 25.0% 
19.09.2014 Energy Sector Development Partners Coordination Page 22
5.2 FiT calculations 
Scenario LEC 
Base Case 10.39 
CapEx+ 11.51 
CapEx- 8.83 
O&M+ 10.80 
O&M- 9.98 
Capacity+ 8.91 
Capacity- 12.47 
Min. value 8.83 
Max. value 12.47 
19.09.2014 Energy Sector Development Partners Coordination Page 23
5.3 Financing properties for developing the national 
wind power market 
a. Target installation of 1 GW till 2020 requires investment amount of 
about USD 2.1 billion over six years. 
b. At average debt level of 70% this translates into: 
• USD 630 million equity and 
• USD 1,470 million debt 
19.09.2014 Energy Sector Development Partners Coordination Page 24
5.4 Developing the national wind power market by 
targeting diverse investor types 
Market is assumed to be developed by mixture of three investor types 
i. Highly subsidized investors like ODAs: access debt funding at 
interest rates of 1%-2% and demand single digit project IRRs. These 
early movers may provide funding of one third of target capacity and 
lay foundation of wind development by boosting synergy effects 
ii. Strategic investors: like turbine manufactures, large industry 
enterprises and sovereign wealth funds: access pools of debt funding 
in the range of 6% and accept projects IRRs of about 10%. 
iii. Fully commercial investors: have to resort to local loans at interest 
rates of 10% and above and demand two digit project IRRs. They 
require additional incentives like tax breaks. 
19.09.2014 Energy Sector Development Partners Coordination Page 25
5.5 Additional regulatory incentives have been 
considered and quantified at calculated FiT-level 
Tax effects: 
a. Reduced corporate tax contributes by 0.3 US Cent/kWh to FiT 
b. Exemption from import tax e.g., 10% tax break corresponds to FiT 
surplus of 0.7-1.0 US Cent/kWh 
19.09.2014 Energy Sector Development Partners Coordination Page 26
5.6 FiT funding for 1 GW target installation 
Funding requirements for 1GW by 2020 at US 10.4Cent/kWh 
Description 2016 2020 2021 2030 
FIT 10,4 10,4 9,4 9,4 
ttl Energy Sold TWh 158 243 273 545 
Wind Energy generated GWh 0 2628 4021 16556 
Average System Cost 7,7 8,8 9,28 10 
TTL Cost demand for funding Mio USD 0 42 46 -73 
Levy per kWh in VND 0 3,7 3,5 -2,8 
19.09.2014 Energy Sector Development Partners Coordination Page 27
5.6 FiT funding for 1 GW target installation (cont.) 
Funding sources of FiT for 1 GW target installation 
Tariff funded Tax funded 
Advantage Disadvantage Advantage Disadvantage 
• Transparency 
of subsidies 
• Independent 
of budgetary 
needs 
Requires “fair” 
allocation of 
costs of 
customer 
segments 
• Independent 
of electricity 
prices for 
customers 
• More 
flexibility 
with 
adjustments 
Potential 
regular disputes 
with MoF over 
budget 
availability, and 
thus 
uncertainties for 
investors 
19.09.2014 Energy Sector Development Partners Coordination Page 28
Levelized costs for Bioenergy based power plants 
Technology Levelized costs in US-Cents/kWh 
Base (~ 10% IRR) Low (~ 8% IRR) High (~ 12% IRR) 
Biomass Power Plant 
Sugarcane bagasse 5.6 5.15 5.85 
Rice husk 7.34 6.87 7.84 
Rice straw 10.79 10.35 11.27 
Timber waste 8.77 8.35 9.22 
Biogas Power Plant 
Animal manure 7.72 7.11 8.36 
Industrial wastewater 12.29 11.20 13.31 
HDPE covered lagoon 6.12 5.69 6.57 
SW Power Plant 
Landfill gas 7.28 6.65 7.95 
Incineration 10.05 8.8 11.39 
19.09.2014 Energy Sector Development Partners Coordination Page 29

More Related Content

What's hot

A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Morocco industrial integration of csp technologies
Morocco industrial integration of csp technologiesMorocco industrial integration of csp technologies
Morocco industrial integration of csp technologiesParti Djibouti
 
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...MYO AUNG Myanmar
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Seokho Shin
 
Bhutan - Utility Scale Solar Power Assessment
Bhutan - Utility Scale Solar Power AssessmentBhutan - Utility Scale Solar Power Assessment
Bhutan - Utility Scale Solar Power AssessmentVikas Lakhani
 
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...OECD Environment
 
Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Atanas Georgiev
 
Mrs. Zohra ETTAIK - Moroccan Energy Sector
Mrs. Zohra ETTAIK - Moroccan Energy SectorMrs. Zohra ETTAIK - Moroccan Energy Sector
Mrs. Zohra ETTAIK - Moroccan Energy SectorMouhcine Benmeziane
 
Acceleration the utilization of Renewable Energy
Acceleration the utilization of Renewable Energy Acceleration the utilization of Renewable Energy
Acceleration the utilization of Renewable Energy Sampe Purba
 
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensa
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensaHandbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensa
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensashrimphead
 
Vietnam, a hidden gem in power development & investing
Vietnam, a hidden gem in power development & investingVietnam, a hidden gem in power development & investing
Vietnam, a hidden gem in power development & investingPhat Nguyen
 
Feed-in tariffs: The legislative challenges for promoting sustainable inves...
Feed-in tariffs: The legislative challenges for promoting sustainable inves...Feed-in tariffs: The legislative challenges for promoting sustainable inves...
Feed-in tariffs: The legislative challenges for promoting sustainable inves...Atanas Georgiev
 
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLN
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLNExperience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLN
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLNOECD Environment
 
UK, nuclear and renewables' struggle
UK, nuclear and renewables' struggleUK, nuclear and renewables' struggle
UK, nuclear and renewables' struggleLeonardo ENERGY
 
Janez Kopac, Director of the Energy Community Secretariat
Janez Kopac, Director of the Energy Community SecretariatJanez Kopac, Director of the Energy Community Secretariat
Janez Kopac, Director of the Energy Community SecretariatWEC Italia
 
Environment Friendly Technology
Environment Friendly TechnologyEnvironment Friendly Technology
Environment Friendly TechnologyProbodh Mallick
 
Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20Mayank Munjal
 
Vietnam Power Sector
Vietnam Power SectorVietnam Power Sector
Vietnam Power SectorHuy Nguyen
 

What's hot (20)

Task 24 The Swiss Energy Story
Task 24 The Swiss Energy StoryTask 24 The Swiss Energy Story
Task 24 The Swiss Energy Story
 
Myanmar energy-sector-assessment
Myanmar energy-sector-assessmentMyanmar energy-sector-assessment
Myanmar energy-sector-assessment
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
Morocco industrial integration of csp technologies
Morocco industrial integration of csp technologiesMorocco industrial integration of csp technologies
Morocco industrial integration of csp technologies
 
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13
 
Bhutan - Utility Scale Solar Power Assessment
Bhutan - Utility Scale Solar Power AssessmentBhutan - Utility Scale Solar Power Assessment
Bhutan - Utility Scale Solar Power Assessment
 
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...
Lowering-Clean-Energy-Risk-Through-Government-Regulation-presentation-Chrisna...
 
Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?
 
Mrs. Zohra ETTAIK - Moroccan Energy Sector
Mrs. Zohra ETTAIK - Moroccan Energy SectorMrs. Zohra ETTAIK - Moroccan Energy Sector
Mrs. Zohra ETTAIK - Moroccan Energy Sector
 
Acceleration the utilization of Renewable Energy
Acceleration the utilization of Renewable Energy Acceleration the utilization of Renewable Energy
Acceleration the utilization of Renewable Energy
 
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensa
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensaHandbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensa
Handbook - Malaysia Solar FiT feed-in-tariff - renewable energy - EcoSensa
 
Vietnam, a hidden gem in power development & investing
Vietnam, a hidden gem in power development & investingVietnam, a hidden gem in power development & investing
Vietnam, a hidden gem in power development & investing
 
Feed-in tariffs: The legislative challenges for promoting sustainable inves...
Feed-in tariffs: The legislative challenges for promoting sustainable inves...Feed-in tariffs: The legislative challenges for promoting sustainable inves...
Feed-in tariffs: The legislative challenges for promoting sustainable inves...
 
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLN
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLNExperience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLN
Experience from the Emission Trading System (ETS) Trials - Syovfi Roekman, PLN
 
UK, nuclear and renewables' struggle
UK, nuclear and renewables' struggleUK, nuclear and renewables' struggle
UK, nuclear and renewables' struggle
 
Janez Kopac, Director of the Energy Community Secretariat
Janez Kopac, Director of the Energy Community SecretariatJanez Kopac, Director of the Energy Community Secretariat
Janez Kopac, Director of the Energy Community Secretariat
 
Environment Friendly Technology
Environment Friendly TechnologyEnvironment Friendly Technology
Environment Friendly Technology
 
Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20
 
Vietnam Power Sector
Vietnam Power SectorVietnam Power Sector
Vietnam Power Sector
 

Viewers also liked

2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)
2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)
2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)Tuong Do
 
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)Tuong Do
 
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)Tuong Do
 
SMX Social Media eBay
SMX Social Media eBaySMX Social Media eBay
SMX Social Media eBayjtkoene
 
ebay social measurement by Sudha Jamthe at Social data panel at Adobe
ebay social measurement by Sudha Jamthe at Social data panel at Adobe   ebay social measurement by Sudha Jamthe at Social data panel at Adobe
ebay social measurement by Sudha Jamthe at Social data panel at Adobe Sudha Jamthe
 
Converting rice residues into energy - opportunities and challenges
Converting rice residues into energy - opportunities and challengesConverting rice residues into energy - opportunities and challenges
Converting rice residues into energy - opportunities and challengesTuong Do
 
Renewable energy models for rice residues - SNV Vietnam
Renewable energy models for rice residues - SNV VietnamRenewable energy models for rice residues - SNV Vietnam
Renewable energy models for rice residues - SNV VietnamTuong Do
 
Social business for corp social summit sf 2012
Social business for corp social summit sf 2012Social business for corp social summit sf 2012
Social business for corp social summit sf 2012Sudha Jamthe
 
Expand Your Business With Social Media - ColderICE at eBay On Location
Expand Your Business With Social Media - ColderICE at eBay On LocationExpand Your Business With Social Media - ColderICE at eBay On Location
Expand Your Business With Social Media - ColderICE at eBay On LocationJohn Lawson
 
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...Heather Drake
 
eBay Business Efficiency Optimization: Tools, Tips & Tricks
eBay Business Efficiency Optimization: Tools, Tips & TrickseBay Business Efficiency Optimization: Tools, Tips & Tricks
eBay Business Efficiency Optimization: Tools, Tips & TricksSandi Garcia
 
Leads United aka LEWIS pr brings an eBay.be case at #SMF10
Leads United aka LEWIS pr brings an eBay.be case at #SMF10Leads United aka LEWIS pr brings an eBay.be case at #SMF10
Leads United aka LEWIS pr brings an eBay.be case at #SMF10Pieter De Wit
 
2006-11-16 RFID and OSS for Agriculture
2006-11-16 RFID and OSS for Agriculture2006-11-16 RFID and OSS for Agriculture
2006-11-16 RFID and OSS for AgricultureJazz Yao-Tsung Wang
 
Hadoop World 2011 Keynote: Ebay - Hugh Williams
Hadoop World 2011 Keynote: Ebay - Hugh WilliamsHadoop World 2011 Keynote: Ebay - Hugh Williams
Hadoop World 2011 Keynote: Ebay - Hugh WilliamsCloudera, Inc.
 
Serverless & Event-driven Architecture
Serverless & Event-driven ArchitectureServerless & Event-driven Architecture
Serverless & Event-driven ArchitectureJosué Neis
 
Beyond Post-Editing: The Work of the eBay MTLS
Beyond Post-Editing: The Work of the eBay MTLSBeyond Post-Editing: The Work of the eBay MTLS
Beyond Post-Editing: The Work of the eBay MTLSJose Luis Bonilla Sánchez
 

Viewers also liked (17)

2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)
2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)
2013 EVN Smart Grid Plan, Nguyen Hai Ha (EN)
 
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)
2013 The Way Forward for Smart Grid in Vietnam, Nguyen Vu Quang (EN)
 
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)
2013 Smart Grid Potential in Thailand & Vietnam, Anand Menon (EN)
 
SMX Social Media eBay
SMX Social Media eBaySMX Social Media eBay
SMX Social Media eBay
 
ebay social measurement by Sudha Jamthe at Social data panel at Adobe
ebay social measurement by Sudha Jamthe at Social data panel at Adobe   ebay social measurement by Sudha Jamthe at Social data panel at Adobe
ebay social measurement by Sudha Jamthe at Social data panel at Adobe
 
Converting rice residues into energy - opportunities and challenges
Converting rice residues into energy - opportunities and challengesConverting rice residues into energy - opportunities and challenges
Converting rice residues into energy - opportunities and challenges
 
Renewable energy models for rice residues - SNV Vietnam
Renewable energy models for rice residues - SNV VietnamRenewable energy models for rice residues - SNV Vietnam
Renewable energy models for rice residues - SNV Vietnam
 
Social business for corp social summit sf 2012
Social business for corp social summit sf 2012Social business for corp social summit sf 2012
Social business for corp social summit sf 2012
 
Expand Your Business With Social Media - ColderICE at eBay On Location
Expand Your Business With Social Media - ColderICE at eBay On LocationExpand Your Business With Social Media - ColderICE at eBay On Location
Expand Your Business With Social Media - ColderICE at eBay On Location
 
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...
Social Commerce and Local: The New Retail Environment: Jody Ford, VP Marketin...
 
eBay Business Efficiency Optimization: Tools, Tips & Tricks
eBay Business Efficiency Optimization: Tools, Tips & TrickseBay Business Efficiency Optimization: Tools, Tips & Tricks
eBay Business Efficiency Optimization: Tools, Tips & Tricks
 
Leads United aka LEWIS pr brings an eBay.be case at #SMF10
Leads United aka LEWIS pr brings an eBay.be case at #SMF10Leads United aka LEWIS pr brings an eBay.be case at #SMF10
Leads United aka LEWIS pr brings an eBay.be case at #SMF10
 
2006-11-16 RFID and OSS for Agriculture
2006-11-16 RFID and OSS for Agriculture2006-11-16 RFID and OSS for Agriculture
2006-11-16 RFID and OSS for Agriculture
 
Hadoop World 2011 Keynote: Ebay - Hugh Williams
Hadoop World 2011 Keynote: Ebay - Hugh WilliamsHadoop World 2011 Keynote: Ebay - Hugh Williams
Hadoop World 2011 Keynote: Ebay - Hugh Williams
 
Serverless & Event-driven Architecture
Serverless & Event-driven ArchitectureServerless & Event-driven Architecture
Serverless & Event-driven Architecture
 
Hype driven development
Hype driven developmentHype driven development
Hype driven development
 
Beyond Post-Editing: The Work of the eBay MTLS
Beyond Post-Editing: The Work of the eBay MTLSBeyond Post-Editing: The Work of the eBay MTLS
Beyond Post-Editing: The Work of the eBay MTLS
 

Similar to GIZ support mechanism for RE development in Vietnam

SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy
 
Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...SustainableEnergyAut
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables DirectiveLeonardo ENERGY
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directivefernando nuño
 
Policy feedback FGD (power) Indonesian 2019
Policy feedback FGD (power) Indonesian 2019Policy feedback FGD (power) Indonesian 2019
Policy feedback FGD (power) Indonesian 2019Danang Yogisworo
 
U.S. Department of State, Office of International Information Programs Confer...
U.S. Department of State, Office of International Information Programs Confer...U.S. Department of State, Office of International Information Programs Confer...
U.S. Department of State, Office of International Information Programs Confer...Alliance To Save Energy
 
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...IEA-ETSAP
 
Green Finance: Business Opportunities and Role of Financial Institutions
Green Finance: Business Opportunities and Role of Financial InstitutionsGreen Finance: Business Opportunities and Role of Financial Institutions
Green Finance: Business Opportunities and Role of Financial InstitutionsADFIAP
 
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...Marko Lehtovaara
 
Remida fedarene - gorizia 13.5.2015
Remida   fedarene - gorizia 13.5.2015Remida   fedarene - gorizia 13.5.2015
Remida fedarene - gorizia 13.5.2015Informest
 
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...OECD Environment
 
2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable Energy2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable EnergyHoang Le Hang
 
Solar Power Development Vietnam
Solar Power Development VietnamSolar Power Development Vietnam
Solar Power Development VietnamJAIDEEP MANN
 

Similar to GIZ support mechanism for RE development in Vietnam (20)

Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015SmartestEnergy: The transition to new renewable subsidy schemes June 2015
SmartestEnergy: The transition to new renewable subsidy schemes June 2015
 
Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...Implementing Agreement for Co-operation in the Research, Development and Depl...
Implementing Agreement for Co-operation in the Research, Development and Depl...
 
Major_Proj_Ramya
Major_Proj_RamyaMajor_Proj_Ramya
Major_Proj_Ramya
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables Directive
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directive
 
Policy feedback FGD (power) Indonesian 2019
Policy feedback FGD (power) Indonesian 2019Policy feedback FGD (power) Indonesian 2019
Policy feedback FGD (power) Indonesian 2019
 
U.S. Department of State, Office of International Information Programs Confer...
U.S. Department of State, Office of International Information Programs Confer...U.S. Department of State, Office of International Information Programs Confer...
U.S. Department of State, Office of International Information Programs Confer...
 
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
 
Green Finance: Business Opportunities and Role of Financial Institutions
Green Finance: Business Opportunities and Role of Financial InstitutionsGreen Finance: Business Opportunities and Role of Financial Institutions
Green Finance: Business Opportunities and Role of Financial Institutions
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...
Energy Certification - an Efficient Tool to Achieve Ambitious RES Targets - C...
 
Remida fedarene - gorizia 13.5.2015
Remida   fedarene - gorizia 13.5.2015Remida   fedarene - gorizia 13.5.2015
Remida fedarene - gorizia 13.5.2015
 
Vietnam _Green Growth
Vietnam _Green GrowthVietnam _Green Growth
Vietnam _Green Growth
 
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
 
2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable Energy2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable Energy
 
Solar Power Development Vietnam
Solar Power Development VietnamSolar Power Development Vietnam
Solar Power Development Vietnam
 
2025 Minnesota Energy Action Plan
2025 Minnesota Energy Action Plan2025 Minnesota Energy Action Plan
2025 Minnesota Energy Action Plan
 

More from Tuong Do

Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt Nam
Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt NamTiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt Nam
Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt NamTuong Do
 
Tổng quan Công nghệ Khí sinh học
Tổng quan Công nghệ Khí sinh họcTổng quan Công nghệ Khí sinh học
Tổng quan Công nghệ Khí sinh họcTuong Do
 
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại Thailand
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại ThailandĐiện mặt trời và cơ chế thanh toán bù trừ net-metering tại Thailand
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại ThailandTuong Do
 
Solar PV development in singapore and SERIS introduction
Solar PV development in singapore and SERIS introductionSolar PV development in singapore and SERIS introduction
Solar PV development in singapore and SERIS introductionTuong Do
 
Vietnam the new powerhouse for cell manufacturing in Southeast Asia
Vietnam the new powerhouse for cell manufacturing in Southeast AsiaVietnam the new powerhouse for cell manufacturing in Southeast Asia
Vietnam the new powerhouse for cell manufacturing in Southeast AsiaTuong Do
 
Solar technology and market trend 2017 - Tuong Do
Solar technology and market trend 2017 - Tuong DoSolar technology and market trend 2017 - Tuong Do
Solar technology and market trend 2017 - Tuong DoTuong Do
 
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gió
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gióXu hướng công nghệ thị trường - Điện mặt trời và Điện gió
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gióTuong Do
 
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016Tuong Do
 
Module 1: Technical options and international best practices for on-grid powe...
Module 1: Technical options and international best practices for on-grid powe...Module 1: Technical options and international best practices for on-grid powe...
Module 1: Technical options and international best practices for on-grid powe...Tuong Do
 
Module 2: Assessment of international good practices in the fields of biomass...
Module 2: Assessment of international good practices in the fields of biomass...Module 2: Assessment of international good practices in the fields of biomass...
Module 2: Assessment of international good practices in the fields of biomass...Tuong Do
 
Module 3: Criteria for the siting and systems integration
Module 3: Criteria for the siting and systems integrationModule 3: Criteria for the siting and systems integration
Module 3: Criteria for the siting and systems integrationTuong Do
 
Module 7: Assessment of framework conditions and necessary adaptations
Module 7: Assessment of framework conditions and necessary adaptationsModule 7: Assessment of framework conditions and necessary adaptations
Module 7: Assessment of framework conditions and necessary adaptationsTuong Do
 
Module 4: Basic design parameters (technical and economic) for commercially v...
Module 4: Basic design parameters (technical and economic) for commercially v...Module 4: Basic design parameters (technical and economic) for commercially v...
Module 4: Basic design parameters (technical and economic) for commercially v...Tuong Do
 
04 giz doris_beck_presentation_vietnam_september_2013
04 giz doris_beck_presentation_vietnam_september_201304 giz doris_beck_presentation_vietnam_september_2013
04 giz doris_beck_presentation_vietnam_september_2013Tuong Do
 
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...Module 6 Basic design parameters for commercially viable on-grid biomass gasi...
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...Tuong Do
 
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến Long
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến LongTổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến Long
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến LongTuong Do
 
Peter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaPeter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaTuong Do
 
Bio w properties & production techniques z wallage
Bio w properties & production techniques z wallageBio w properties & production techniques z wallage
Bio w properties & production techniques z wallageTuong Do
 
Usth master of-re-b-18-jui1
Usth master of-re-b-18-jui1Usth master of-re-b-18-jui1
Usth master of-re-b-18-jui1Tuong Do
 
SELCO - Webinar - Financing for Solar Offgrid Businesses
SELCO - Webinar - Financing for Solar Offgrid BusinessesSELCO - Webinar - Financing for Solar Offgrid Businesses
SELCO - Webinar - Financing for Solar Offgrid BusinessesTuong Do
 

More from Tuong Do (20)

Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt Nam
Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt NamTiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt Nam
Tiềm năng và xu hướng công nghệ phát triển điện mặt trời ở Việt Nam
 
Tổng quan Công nghệ Khí sinh học
Tổng quan Công nghệ Khí sinh họcTổng quan Công nghệ Khí sinh học
Tổng quan Công nghệ Khí sinh học
 
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại Thailand
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại ThailandĐiện mặt trời và cơ chế thanh toán bù trừ net-metering tại Thailand
Điện mặt trời và cơ chế thanh toán bù trừ net-metering tại Thailand
 
Solar PV development in singapore and SERIS introduction
Solar PV development in singapore and SERIS introductionSolar PV development in singapore and SERIS introduction
Solar PV development in singapore and SERIS introduction
 
Vietnam the new powerhouse for cell manufacturing in Southeast Asia
Vietnam the new powerhouse for cell manufacturing in Southeast AsiaVietnam the new powerhouse for cell manufacturing in Southeast Asia
Vietnam the new powerhouse for cell manufacturing in Southeast Asia
 
Solar technology and market trend 2017 - Tuong Do
Solar technology and market trend 2017 - Tuong DoSolar technology and market trend 2017 - Tuong Do
Solar technology and market trend 2017 - Tuong Do
 
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gió
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gióXu hướng công nghệ thị trường - Điện mặt trời và Điện gió
Xu hướng công nghệ thị trường - Điện mặt trời và Điện gió
 
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016
STATE OF THE INDUSTRY KEYNOTE BNEF SUMMIT 2016
 
Module 1: Technical options and international best practices for on-grid powe...
Module 1: Technical options and international best practices for on-grid powe...Module 1: Technical options and international best practices for on-grid powe...
Module 1: Technical options and international best practices for on-grid powe...
 
Module 2: Assessment of international good practices in the fields of biomass...
Module 2: Assessment of international good practices in the fields of biomass...Module 2: Assessment of international good practices in the fields of biomass...
Module 2: Assessment of international good practices in the fields of biomass...
 
Module 3: Criteria for the siting and systems integration
Module 3: Criteria for the siting and systems integrationModule 3: Criteria for the siting and systems integration
Module 3: Criteria for the siting and systems integration
 
Module 7: Assessment of framework conditions and necessary adaptations
Module 7: Assessment of framework conditions and necessary adaptationsModule 7: Assessment of framework conditions and necessary adaptations
Module 7: Assessment of framework conditions and necessary adaptations
 
Module 4: Basic design parameters (technical and economic) for commercially v...
Module 4: Basic design parameters (technical and economic) for commercially v...Module 4: Basic design parameters (technical and economic) for commercially v...
Module 4: Basic design parameters (technical and economic) for commercially v...
 
04 giz doris_beck_presentation_vietnam_september_2013
04 giz doris_beck_presentation_vietnam_september_201304 giz doris_beck_presentation_vietnam_september_2013
04 giz doris_beck_presentation_vietnam_september_2013
 
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...Module 6 Basic design parameters for commercially viable on-grid biomass gasi...
Module 6 Basic design parameters for commercially viable on-grid biomass gasi...
 
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến Long
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến LongTổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến Long
Tổng quan Năng lượng tái tạo Việt Nam - Nguyễn Tiến Long
 
Peter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and SrilankaPeter Meier Feed-in-tariff for Vietnam and Srilanka
Peter Meier Feed-in-tariff for Vietnam and Srilanka
 
Bio w properties & production techniques z wallage
Bio w properties & production techniques z wallageBio w properties & production techniques z wallage
Bio w properties & production techniques z wallage
 
Usth master of-re-b-18-jui1
Usth master of-re-b-18-jui1Usth master of-re-b-18-jui1
Usth master of-re-b-18-jui1
 
SELCO - Webinar - Financing for Solar Offgrid Businesses
SELCO - Webinar - Financing for Solar Offgrid BusinessesSELCO - Webinar - Financing for Solar Offgrid Businesses
SELCO - Webinar - Financing for Solar Offgrid Businesses
 

Recently uploaded

VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证mbetknu
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.Christina Parmionova
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书mbetknu
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxHenryBriggs2
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersCongressional Budget Office
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.pptsilvialandin2
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...narwatsonia7
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...narwatsonia7
 

Recently uploaded (20)

VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptx
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists Lawmakers
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
 

GIZ support mechanism for RE development in Vietnam

  • 1. Seite 1 Support Mechanisms for RE Development in Viet Nam Hanoi, 19/09/2014 Ingmar Stelter, Program Manager Werner Kossmann, Chief Technical Advisor GIZ Viet Nam Energy Support Program
  • 2. Seite 2 Technical Cooperation in Viet Nam
  • 3. National Strategy PDP VII objectives on RE: Increase in electricity produced from RE sources 2020 2030 5.6% 9.4% 500 MW 1000 MW 2000 MW 6200 MW 2700 MW Biomass Wind Biomass Wind 5620 MW Other RE Other RE Planned Installed Capacity Other RE: Biogas, Waste-to-Energy, Solar PV/ST, SHP etc. Source: PDP 7 19.09.2014 Energy Sector Development Partners Coordination Page 3
  • 4. Barriers for RE Development in Viet Nam Lack of national (comprehensive) law for RE Low electricity price Limited data availability (and poor data quality) Limited capacities on central and provincial level Difficult access to information Limited access to financing (equity & loans) Complex and unclear procedures for RE investments 19.09.2014 Energy Sector Development Partners Coordination Page 4
  • 5. Existing Support Mechanisms for RE – I/II SHP Wind Power Decision 18/2008/QD-TTg (18.07.2008) • In 2014: 2.7 – 3.2 US-Cents/kWh (depending on season and daytime) • Avoided-Cost-Tariff, varied by year • Calculated annually based on 1 kWh electricity avoided from the most expensive power plant connected to the national grid • Duration of PPA: 20 Years Decision 37/2011/QD-TTg (29.06.2011) • Feed-in-Tariff for Wind Power • Tariff: 7,8 US-Cents/kWh (6.8+1) • Duration of PPA: 20 Years • GIZ-supported; currently under revision 19.09.2014 Energy Sector Development Partners Coordination Page 5
  • 6. Existing Support Mechanisms for RE – II/II Biomass Solid Waste Decision 24/2014/QD-TTg (29.06.2014) • FiT for electricity from CHP-Biomass Power: 5.8 US-Cents/kWh • Avoided-Cost Tariff for electricity from other Biomass plants • Annually calculated based on the avoided cost for 1 kWh electricity from imported coal • Duration of PPA: 20 Years • GIZ-supported Decision: 31/2014/QD-TTg (05.05.2014) • Feed-in-Tariff for electricity from MSW • Incineration: 10.05 US-Cents/kWh • Landfill-Gas: 7.28 US-Cents/kWh • Duration of PPA: 20 Years • GIZ-supported 19.09.2014 Energy Sector Development Partners Coordination Page 6
  • 7. Additional Incentive Mechanisms for RE • Corporate income tax • Years 1-4: tax exemption • Years 5-13: 50% tax reduction • Import tax (goods, machinery etc.) • Varying levels of import tax, depending on type of imported goods • Exemption on goods forming fixed assets, which cannot be produced locally • Waiving of land use/lease fees • Land is provided for free as part of the licensing agreement  These are substantial financial incentives for project developers.  However, in a situation of financial stress, tax incentives cannot cushion liquidity problems as there are no tax payments to be made. 19.09.2014 Energy Sector Development Partners Coordination Page 7
  • 8. Revision of the support mechanism for wind – I/III • Methodology: • Qualitative: interviews, questionnaires, assessment of exist. framework • Quantitative: wind data, pre-/feasibility studies, international comparison • General findings/recommendations (excerpt): • FiT payment system should be a one-stop-shop (not VNEPF+FiT) • Government guarantee for payments • Better wind speed measurements and improved standards are required • Enforce standard agreements for network connection and power purchase 19.09.2014 Energy Sector Development Partners Coordination Page 8
  • 9. Revision of the support mechanism for wind – II/III • Basis for analysis: • PDP target: 1GW wind power by 2020 (currently: ca. 50MW) • Assumptions for CapEx, O&M, Capacity Factor: based on P/FS, questionnaires, international experience • Required investment and assumed investor structure: • 1GW by 2020 = ca. US$ 2.1 billion over the next 6 years • At average debt level of 70% => US$ 630m equity and 1.47b debt • This investment level cannot (should not) be reached with public investment only. • Assumed investor types: highly-subsidized, strategic, fully commercial 19.09.2014 Energy Sector Development Partners Coordination Page 9
  • 10. Revision of the support mechanism for wind – III/III • FiT calculation: • All three investor types must be targeted with the FiT • Assumed IRR: 10% (international experience) • Basis for FiT calculation: Levelized cost of electricity (LEC) • Also included: additional incentives like tax breaks etc. • Result: • Proposed FiT for on-shore installations: US-cents 10.4 / kWh • Proposed funding scheme: Tariff-funded, i.e. through a levy on the electricity price: for 1GW by 2020 => less than 5VND/kWh 19.09.2014 Energy Sector Development Partners Coordination Page 10
  • 11. Bioenergy technologies applicable in Vietnam Biomass - Sugarcane bagasse - Rice straw/husk - Timber waste Biogas - Animal manure - Industrial wastewater - HDPE covered lagoon Municipal Solid Waste - Incineration - Landfill Gas 19.09.2014 Energy Sector Development Partners Coordination Page 11
  • 12. FiT for non-CHP biomass power (avoided cost tariff) Government opted for the avoided cost tariff based on imported coal as reference price for biomass Reason to apply an avoided cost tariff based on imported coal: • Coal thermal power plant has the highest share in power mix • Avoid electricity generated from these plants • Biomass power plants as substitution to provide base load in the system Problem: • Annually calculated and issued • Fluctuating coal prices • Inflexible in combination with 20 years PPA 19.09.2014 Energy Sector Development Partners Coordination Page 12
  • 13. Comparison of regulated prices with proposed levels for Bioenergy Technology Proposed purchasing price (US-Cents/kWh) Regulated level (US-Cents/ kWh) Sugarcane bagasse 5.6 5.8 Rice husk 7.34 Avoided cost based tariff Rice straw 10.79 Timber waste 8.77 SW - Landfill gas 7.28 7.28 SW – Incineration 10.05 10.05 19.09.2014 Energy Sector Development Partners Coordination Page 13
  • 14. Thank you for your attention!! Werner Kossmann Ingmar Stelter werner.Kossmann@giz.de ingmar.stelter@giz.de 04 39 41 26 05 - 15 04 39 34 49 51 - 114 19.09.2014 Energy Sector Development Partners Coordination Page 14
  • 15. Backup: Installed capacity of electricity sources (2013) Source Capacity (MW) Rate (%) Big hydropower 13,260 43.21 Coal thermo-electric 7,116 23.19 Gas thermo-electric 7,446 2.97 Oil thermo-electric 912 0.22 RE Small hydropower (≤ 30MW) 1,670 5.44 Wind 52 0.18 Biomass 150 0.49 Biogas/MSW 4 0.01 Solar PV 4 0.01 Total 30,684 Share of RE: 6.13% Source: GDE 2014 19.09.2014 Energy Sector Development Partners Coordination Page 15
  • 16. Backup: Electricity production (2013) Source Output (GWh) Rate (%) Big hydropower 56,943 40.51 Coal thermo-electric 26.843 20.93 Gas thermo-electric 42,650 33.26 Oil thermo-electric 95 0.07 Others 249 0.19 Exported 1,337 1.04 Diesel 7 - Small hydropower 4,989 3.89 Wind 62 est. 0,05 Bioenergy (Biomass, -gas, 47 est. 0,04 MSW) Solar PV Total 128,228 Share of RE: 3.98% Source: GDE 2014 19.09.2014 Energy Sector Development Partners Coordination Page 16
  • 17. 5.2 FiT calculations The following assumptions result from the analysis of the feasibility studies and questionnaires • Average CapEx: 2.0 USD Mio. /MW • Average O&M cost 35,000 USD / MW per year • Average capacity factor: 30% This is in line with international experience! 19.09.2014 Energy Sector Development Partners Coordination Page 17
  • 18. 5.2 FiT calculations; international benchmark: CapEx 19.09.2014 Energy Sector Development Partners Coordination Page 18
  • 19. 5.2 FiT calculations; international benchmark: OpEx 19.09.2014 Energy Sector Development Partners Coordination Page 19
  • 20. 5.2 FiT calculations; international benchmark: Capacity Factor 19.09.2014 Energy Sector Development Partners Coordination Page 20
  • 21. 5.2 FiT calculations • Levelized Electricity Cost (LEC) as basis of analysis • LEC is function of CapEx, discounted OM (OpEx) and total electricity production (Capacity factor) • LEC(푰푹푹) = 푪풂풑푬풙+푷푽푶풑푬풙(푰푹푹) 푷푽푬풍풆풄(푰푹푹) • There is a direct relationship between internal rate of return (IRR) and LEC • According to intl. experience, investors typically demand a project IRR of 10%, resulting in an LEC of US Cent 10.4 19.09.2014 Energy Sector Development Partners Coordination Page 21
  • 22. 5.2 FiT calculations Sensitivities derived from feasibility studies and questionnaires Scenario CapEx [million USD/MW] O&M [T USD/MW*year] Capacity Factor Base 2.00 35.00 30.0% case CapEx+ 2.25 35.00 30.0% CapEx- 1.65 35.00 30.0% O&M+ 2.00 45.00 30.0% O&M- 2.00 25.00 30.0% Capacity+ 2.00 35.00 35.0% Capacity- 2.00 35.00 25.0% 19.09.2014 Energy Sector Development Partners Coordination Page 22
  • 23. 5.2 FiT calculations Scenario LEC Base Case 10.39 CapEx+ 11.51 CapEx- 8.83 O&M+ 10.80 O&M- 9.98 Capacity+ 8.91 Capacity- 12.47 Min. value 8.83 Max. value 12.47 19.09.2014 Energy Sector Development Partners Coordination Page 23
  • 24. 5.3 Financing properties for developing the national wind power market a. Target installation of 1 GW till 2020 requires investment amount of about USD 2.1 billion over six years. b. At average debt level of 70% this translates into: • USD 630 million equity and • USD 1,470 million debt 19.09.2014 Energy Sector Development Partners Coordination Page 24
  • 25. 5.4 Developing the national wind power market by targeting diverse investor types Market is assumed to be developed by mixture of three investor types i. Highly subsidized investors like ODAs: access debt funding at interest rates of 1%-2% and demand single digit project IRRs. These early movers may provide funding of one third of target capacity and lay foundation of wind development by boosting synergy effects ii. Strategic investors: like turbine manufactures, large industry enterprises and sovereign wealth funds: access pools of debt funding in the range of 6% and accept projects IRRs of about 10%. iii. Fully commercial investors: have to resort to local loans at interest rates of 10% and above and demand two digit project IRRs. They require additional incentives like tax breaks. 19.09.2014 Energy Sector Development Partners Coordination Page 25
  • 26. 5.5 Additional regulatory incentives have been considered and quantified at calculated FiT-level Tax effects: a. Reduced corporate tax contributes by 0.3 US Cent/kWh to FiT b. Exemption from import tax e.g., 10% tax break corresponds to FiT surplus of 0.7-1.0 US Cent/kWh 19.09.2014 Energy Sector Development Partners Coordination Page 26
  • 27. 5.6 FiT funding for 1 GW target installation Funding requirements for 1GW by 2020 at US 10.4Cent/kWh Description 2016 2020 2021 2030 FIT 10,4 10,4 9,4 9,4 ttl Energy Sold TWh 158 243 273 545 Wind Energy generated GWh 0 2628 4021 16556 Average System Cost 7,7 8,8 9,28 10 TTL Cost demand for funding Mio USD 0 42 46 -73 Levy per kWh in VND 0 3,7 3,5 -2,8 19.09.2014 Energy Sector Development Partners Coordination Page 27
  • 28. 5.6 FiT funding for 1 GW target installation (cont.) Funding sources of FiT for 1 GW target installation Tariff funded Tax funded Advantage Disadvantage Advantage Disadvantage • Transparency of subsidies • Independent of budgetary needs Requires “fair” allocation of costs of customer segments • Independent of electricity prices for customers • More flexibility with adjustments Potential regular disputes with MoF over budget availability, and thus uncertainties for investors 19.09.2014 Energy Sector Development Partners Coordination Page 28
  • 29. Levelized costs for Bioenergy based power plants Technology Levelized costs in US-Cents/kWh Base (~ 10% IRR) Low (~ 8% IRR) High (~ 12% IRR) Biomass Power Plant Sugarcane bagasse 5.6 5.15 5.85 Rice husk 7.34 6.87 7.84 Rice straw 10.79 10.35 11.27 Timber waste 8.77 8.35 9.22 Biogas Power Plant Animal manure 7.72 7.11 8.36 Industrial wastewater 12.29 11.20 13.31 HDPE covered lagoon 6.12 5.69 6.57 SW Power Plant Landfill gas 7.28 6.65 7.95 Incineration 10.05 8.8 11.39 19.09.2014 Energy Sector Development Partners Coordination Page 29

Editor's Notes

  1. DD
  2. Base: after tax IRR 10.05% - 10.5% Low: after tax IRR 8.2% - 8.6% High: after tax IRR 12% - 12.5%