WHAT IT TAKES TO HARNESS THE SUN
IVANPAH SOLAR TOWER DESIGN
Kristin M. Santamont P.E.
Senior Civil Engineer, Bechtel Corporation
© Bechtel 2012 | 1
IVANPAH SOLAR ELECTRIC GENERATING FACILITY
Location
San Bernardino County, California, USA
45 miles South West of Las Vegas
Customer
Solar Partners
Scope of Service
Engineering
Procurement
Construction
Startup
Project Completion
2013
Units and Megawatts
3 separate power plants totaling 392MW
© Bechtel 2012 | 2
“GREEN” POWER GENERATING FACILITY
363,000 tonnes of CO2 emissions
avoided each year. Equivalent to
70,000 cars
140,000 homes powered by the
Ivanpah facility
Low impact construction
techniques © Bechtel 2012 | 3
TYPICAL UNIT
SRS
G
Air Cooled
Condense
r
Tower
Mirror
Field
Steam Turbine
Generator
© Bechtel 2012 | 4
PROJECT SITE
1
2
3
Project Size 3,600 Acres
Project Capacity Unit 1 = 126 MW
Units 2 & 3 = 133 MW
Solar Field Size Unit 1 = 895 acres
Unit 2 = 1078 acres
Unit 3 = 1209 acres
Number of
Heliostats
Total = ~173,500
Unit 1 = 53,500
Units 2 & 3 = 60,000
© Bechtel 2012 | 5
173,500 HELIOSTATS
Enough reflective area to cover
approximately 600 football fields
Enough mirrors to replace all the
windows in the Empire State
Building…54 times
© Bechtel 2012 | 6
3,600 ACRE SITE
Manhattan
Island
1
2
3
 ~ 6 square miles
 Roughly 25% the
size of Manhattan
© Bechtel 2012 | 7
© Bechtel 2012 | 8
SOLAR TOWER STRUCTURE
 120’ tall Solar Receiver Steam Generator
(SRSG)
 54’ x 54’ footprint
 Each SRSG receives solar flux from mirror field
 Conventional steel braced frame
 339’ tall Tower
 70’ x 70’ footprint at base
 45’ x 45’ main tower footprint
 Column splices located for modular erection
 Concrete Foundation
 120’ x 120’ in plan
 9’ thick mat © Bechtel 2012 | 9
SOLAR TOWER
 1,800 tons of structural steel
 9 Tiers ~40’ tall
 Lowest 4 Tiers are “stick built”
 5 Tiers Ground Assembled as Modules
 Columns are 36” f pipe sections
 API 5L X56 material
 1 ½” or 2” wall thickness
 2” f A354 Grade BD bolts in splices
 HSS16 square vertical braces
 Traditional floor framing
© Bechtel 2012 | 10
TOWER STEEL ERECTION
© Bechtel 2012 | 11
TOWER COLUMN SPLICES
 Each column splice utilizes an identical circular
pattern of 16 2”f A354 Grade BD bolts
 Extra 4 bolts for shear loads at discrete locations
only © Bechtel 2012 | 12
SRSG CONFIGURATION
Superheater Panel
Reheater Panel
Steam Generator
Panel
Protection Panel
Protection Panel
 3 Stage Steam Generator
 700 tons of structural steel
for internal framing
 Total weight including piping
& equipment ~2,000 tons
 Traditional framing
geometry and member sizes
© Bechtel 2012 | 13
SRSG CONFIGURATION
 Highly congested
volume
 External water walls
with piping, headers
and associated
valves
 Contains steam
drum, silencers,
access platforms,
etc.
© Bechtel 2012 | 14
SOLAR RECOVERY STEAM
GENERATOR (SRSG)
 “Modularized” in 5 Tiers
 Ground Assembled and transported
to Tower
 Lifted in thirds due to weight limits
© Bechtel 2012 | 15
STRUCTURAL DESIGN
 2007 California Building Code
 Seismic Design Category C
 Design Wind Speed 85 mph
 Operating wind speed of 30 mph
 Flexible Structure Governed by
Wind
 Flexible Structure
 Fundamental Period 3.3 seconds
© Bechtel 2012 | 16
VORTEX SHEDDING
© Bechtel 2012 | 17
WIND TUNNEL TESTING
 Boundary Layer Wind Tunnel Laboratory at
University of Western Ontario
 Performed a Rigid Model Test
 The measured cross-wind loads ~3 times
calculated along-wind code prescribed load
© Bechtel 2012 | 18
TUNED MASS DAMPER
 Changing foundation and stiffening
structure deemed not practical
 Opted for Tuned Mass Damper
Solution
 Required minimum 5% of critical
damping to mitigate cross-wind
response to an acceptable level
 Other TMD requirements:
 30 year design life
 Operating temperature range 10oF –
o
Idealized TMD with
Suspended Mass &
Dashpots
© Bechtel 2012 | 19
TUNED MASS DAMPER
 Limited space in SRSG for
addition of TMD.
 11’-4” X 11’-4” X 20’-6” volume
© Bechtel 2012 | 20
TUNED MASS DAMPER FINAL DESIGN
© Bechtel 2012 | 21
TUNED MASS DAMPER INSTALLATION
© Bechtel 2012 | 22
© Bechtel 2012 | 23
HELIOSTAT ASSEMBLY AREA
2 Pad Bonding
Buildings
Heliostat Storage
& Pit Lane
Material
Laydown
Assembly Building
© Bechtel 2012 | 24
HELIOSTAT TRANSPORTATION
© Bechtel 2012 | 25
Record Number of
Pylons Inserted in One
Day =
711
PYLON INSTALLATION
© Bechtel 2012 | 26
Record Number of
Heliostats
Installed in One
Day =
512
HELIOSTAT INSTALLATION
© Bechtel 2012 | 27
CURRENT CONSTRUCTION
STATUS
© Bechtel 2012 | 28
© Bechtel 2012 | 29
CURRENT
CONSTRUCTION STATUS
ACKNOWLEDGEMENTS
 Boundary Layer Wind Tunnel Laboratory
 GERB Vibration Control Systems
www.ivanpahsolar.com
© Bechtel 2012 | 30

What it Takes to Harness the Sun

  • 1.
    WHAT IT TAKESTO HARNESS THE SUN IVANPAH SOLAR TOWER DESIGN Kristin M. Santamont P.E. Senior Civil Engineer, Bechtel Corporation © Bechtel 2012 | 1
  • 2.
    IVANPAH SOLAR ELECTRICGENERATING FACILITY Location San Bernardino County, California, USA 45 miles South West of Las Vegas Customer Solar Partners Scope of Service Engineering Procurement Construction Startup Project Completion 2013 Units and Megawatts 3 separate power plants totaling 392MW © Bechtel 2012 | 2
  • 3.
    “GREEN” POWER GENERATINGFACILITY 363,000 tonnes of CO2 emissions avoided each year. Equivalent to 70,000 cars 140,000 homes powered by the Ivanpah facility Low impact construction techniques © Bechtel 2012 | 3
  • 4.
  • 5.
    PROJECT SITE 1 2 3 Project Size3,600 Acres Project Capacity Unit 1 = 126 MW Units 2 & 3 = 133 MW Solar Field Size Unit 1 = 895 acres Unit 2 = 1078 acres Unit 3 = 1209 acres Number of Heliostats Total = ~173,500 Unit 1 = 53,500 Units 2 & 3 = 60,000 © Bechtel 2012 | 5
  • 6.
    173,500 HELIOSTATS Enough reflectivearea to cover approximately 600 football fields Enough mirrors to replace all the windows in the Empire State Building…54 times © Bechtel 2012 | 6
  • 7.
    3,600 ACRE SITE Manhattan Island 1 2 3 ~ 6 square miles  Roughly 25% the size of Manhattan © Bechtel 2012 | 7
  • 8.
  • 9.
    SOLAR TOWER STRUCTURE 120’ tall Solar Receiver Steam Generator (SRSG)  54’ x 54’ footprint  Each SRSG receives solar flux from mirror field  Conventional steel braced frame  339’ tall Tower  70’ x 70’ footprint at base  45’ x 45’ main tower footprint  Column splices located for modular erection  Concrete Foundation  120’ x 120’ in plan  9’ thick mat © Bechtel 2012 | 9
  • 10.
    SOLAR TOWER  1,800tons of structural steel  9 Tiers ~40’ tall  Lowest 4 Tiers are “stick built”  5 Tiers Ground Assembled as Modules  Columns are 36” f pipe sections  API 5L X56 material  1 ½” or 2” wall thickness  2” f A354 Grade BD bolts in splices  HSS16 square vertical braces  Traditional floor framing © Bechtel 2012 | 10
  • 11.
    TOWER STEEL ERECTION ©Bechtel 2012 | 11
  • 12.
    TOWER COLUMN SPLICES Each column splice utilizes an identical circular pattern of 16 2”f A354 Grade BD bolts  Extra 4 bolts for shear loads at discrete locations only © Bechtel 2012 | 12
  • 13.
    SRSG CONFIGURATION Superheater Panel ReheaterPanel Steam Generator Panel Protection Panel Protection Panel  3 Stage Steam Generator  700 tons of structural steel for internal framing  Total weight including piping & equipment ~2,000 tons  Traditional framing geometry and member sizes © Bechtel 2012 | 13
  • 14.
    SRSG CONFIGURATION  Highlycongested volume  External water walls with piping, headers and associated valves  Contains steam drum, silencers, access platforms, etc. © Bechtel 2012 | 14
  • 15.
    SOLAR RECOVERY STEAM GENERATOR(SRSG)  “Modularized” in 5 Tiers  Ground Assembled and transported to Tower  Lifted in thirds due to weight limits © Bechtel 2012 | 15
  • 16.
    STRUCTURAL DESIGN  2007California Building Code  Seismic Design Category C  Design Wind Speed 85 mph  Operating wind speed of 30 mph  Flexible Structure Governed by Wind  Flexible Structure  Fundamental Period 3.3 seconds © Bechtel 2012 | 16
  • 17.
  • 18.
    WIND TUNNEL TESTING Boundary Layer Wind Tunnel Laboratory at University of Western Ontario  Performed a Rigid Model Test  The measured cross-wind loads ~3 times calculated along-wind code prescribed load © Bechtel 2012 | 18
  • 19.
    TUNED MASS DAMPER Changing foundation and stiffening structure deemed not practical  Opted for Tuned Mass Damper Solution  Required minimum 5% of critical damping to mitigate cross-wind response to an acceptable level  Other TMD requirements:  30 year design life  Operating temperature range 10oF – o Idealized TMD with Suspended Mass & Dashpots © Bechtel 2012 | 19
  • 20.
    TUNED MASS DAMPER Limited space in SRSG for addition of TMD.  11’-4” X 11’-4” X 20’-6” volume © Bechtel 2012 | 20
  • 21.
    TUNED MASS DAMPERFINAL DESIGN © Bechtel 2012 | 21
  • 22.
    TUNED MASS DAMPERINSTALLATION © Bechtel 2012 | 22
  • 23.
  • 24.
    HELIOSTAT ASSEMBLY AREA 2Pad Bonding Buildings Heliostat Storage & Pit Lane Material Laydown Assembly Building © Bechtel 2012 | 24
  • 25.
  • 26.
    Record Number of PylonsInserted in One Day = 711 PYLON INSTALLATION © Bechtel 2012 | 26
  • 27.
    Record Number of Heliostats Installedin One Day = 512 HELIOSTAT INSTALLATION © Bechtel 2012 | 27
  • 28.
  • 29.
    © Bechtel 2012| 29 CURRENT CONSTRUCTION STATUS
  • 30.
    ACKNOWLEDGEMENTS  Boundary LayerWind Tunnel Laboratory  GERB Vibration Control Systems www.ivanpahsolar.com © Bechtel 2012 | 30