SlideShare a Scribd company logo
Upgrading CO2
removal systems
A
cid gas removal is an impor-
tant step in petrochemi-
cal plants, refineries and
syngas production. This article
describes experience in cost effec-
tively upgrading CO2
removal sys-
tems in three ammonia plants with
an attractive payback of just a few
months. One of the plants uses a
MDEA system and the other two
use Benfield systems. A similar
approach can be used in acid gas
removal systems in petrochemicals
plants and refineries.
MDEA based CO2
removal system
The existing single stage MDEA
CO2
removal system scheme is
shown in Figure 1. This conver-
sion of an old MEA based system
was implemented as a part of the
overall ammonia plant capacity
revamp from the original name-
plate capacity of 600 t/d to about
1100 t/d. The original absorber and
stripper columns were used, with
trays replaced with packings and
other internals. The current oper-
ating capacity is 1140 t/d to 1170
t/d, depending on seasonal varia-
tion. This plant was stretched to its
design limits and beyond.
A holistic review of the reference
CO2
removal system was carried
out by KPI to identify all the poten-
tial bottlenecks contributing to a
shortfall in performance. To sup-
port this, the following steps were
taken:
•	Gamma scan of the columns to
determine any maldistribution
•	Representative operating data
corresponding to maximum operat-
ing capacity
•	Reconciliation of the operating
data
Simple modifications to three carbon dioxide removal systems raised their
efficiencies with short payback periods
V K ARORA
Kinetics Process Improvements
•	Simulation of the existing scheme
to match the reconciled operating
data
•	Evaluation of potential bottlenecks
at the current operating conditions:
	 ■	Mass transfer limits of the
existing packing type and height
	 ■	 Adequacy/limitations of liquid
distributor
	 ■	Adequacy/limitations of feed
vapour distributor
	 ■	Hydraulic adequacy/limita-
tions of the solvent circulation loop
	 ■	Solvent and activator concen-
tration for optimal performance.
Figures 2-5 represent the base
operating performance at 1140 t/d
as modelled and reconciled with
actual operating performance. A
gamma scan of the absorber indi-
cates the liquid density variation
profile in Figure 2, with a variation
between 8 and 15 units indicating
maldistribution. The absorber is
operating at about 85% flood while
the stripper has enough hydrau-
lic capacity available (see Figure 5).
The absorber temperature profile in
www.eptq.com PTQ Q2 2017 67
Water
Raw
syngas
Absorber
Stripper
LC
CO2 product
Treated
syngas
Figure 1 MDEA-piperazine CO2
removal scheme
Drydensity:15lb/ft3
Base
operation
20 15 10 5 0
Figure 2 Absorber liquid density profile
68 PTQ Q2 2017 	 www.eptq.com
fall in performance. The potential
causes identified in the absorber
system were:
•	Liquid maldistribution deter-
mined through gamma scan
•	Under-sized liquid distribu-
tor in the absorber, leading to
maldistribution
•	High momentum through the
vapour distributor in the absorber,
leading to maldistribution
•	Mass transfer limitations due to
short packing height and incorrect
loading
•	Hydraulics and mass transfer lim-
itations of the existing packing.
The stripper column did not indi-
cate any hydraulic or mass trans-
fer limitations or any performance
issues.
Options to reduce CO2
slip
As the next step, several options
were evaluated with relevant inputs
gathered from vendors. The fol-
lowing options were further simu-
lated and reviewed for improved
performance, including cost-benefit
analysis:
•	New efficient packing configura-
tions with improved mass transfer
and hydraulics
•	Increase in packing height, as
noted later for different options
•	New liquid distributor
•	New feed vapour distributor
•	Increase in circulation rate
•	Optimise solution concentration.
New liquid distributor
The existing trough type V-notch
liquid distributors were inadequate
and considered less efficient for
the service conditions. They were
replaced with new efficient ori-
fice deck distributors rated with
sufficient design margin over the
new service conditions for current
and future operating cases. Most
importantly, the new distributors
were designed for installation and
removal through the existing 17in
manways to facilitate correct load-
ing of packing.
New feed vapour distributor
The existing feed vapour distributor
was also found to be inadequate,
with a much higher momentum
than recommended and also insuf-
ficient coverage of the cross section.
Figure 3 seems reasonable while the
CO2
concentration profile in Figure
4 indicates about 2600 ppmv of CO2
slip.
Potential causes of high CO2
slip
Based on an initial evaluation, the
absorber column indicated major
limitations, resulting in a short-
16
8
10
4
6
2
0
12
14
18
20
22
24
26
Packingheight,ft(topdown)
28
100 115 130 145 160 175
Temperature, ºF
Base operation
0 500 1000 1500 2000 2500 3000 3500 4000
CO2 concentration, ppmv
15
5
0
10
20
25
Packingheight,ft(topdown)
30
Base operation
Figure 3 Absorber temperature profile
Figure 4 Absorber vapour CO2
concentration profile
30 40 50 60 70 80 90
Flood, %
5
0
10
15
20
25
30
35
Packingheight,ft(topdown)
Absorber
Stripper
Base operation
Figure 5 % flood: absorber and stripper
It was replaced with a T-type lat-
eral distributor rated with sufficient
design margin over the new ser-
vice conditions for both the current
and future operating cases. Most
importantly, the new distributors
were designed for installation and
removal through the existing 17in
manways.
Increase in circulation and
hydraulics adequacy
Increasing the solvent circulation
rate was reviewed along with a
complete hydraulics evaluation of
the lean circuit and the lean MDEA
pumps, with a clear premise not to
replace any of the existing pumps
and drivers. Interestingly, a mar-
ginal increase in circulation rate
was possible with replacement of
the existing impellers at the maxi-
mum possible size, well within the
maximum design rating of the exist-
ing drivers. Further, the impact of
the higher circulation rate was also
evaluated for both absorber and
stripper columns with new pack-
ing type, size and different bed
configurations.
New efficient packing
To improve the limitations of both
mass transfer and hydraulics in the
absorber, new and efficient packings
from two suppliers were evaluated
with extensive in-house modelling
for their quantitative impact on per-
formance. The improved hydrau-
lics with the selected new efficient
packing with increased packing
height (127% of the existing height)
is shown in Figure 6 and compared
with the hydraulics of the existing
packing for both base and future
capacities (1140 t/d and 1250 t/d,
respectively). The hydraulic capac-
ity of the absorber indicates a sub-
stantial improvement with the new
efficient packing.
New packing configurations
The latest and most efficient proven
packings from two suppliers were
reviewed and modelled to evalu-
ate their impact on CO2
slip and
hydraulics. A combination of split
bed with two different packing
sizes – with and without liquid
redistributors – was also reviewed.
Based on the detailed evaluation
www.eptq.com PTQ Q2 2017 69
and modelled performance, it was
decided to go ahead with only one
deeper bed for the most value.
Incremental packing height and
practical constraints
The existing packing height was
determined to be a limiting fac-
tor to achieve the target CO2
slip
despite changes with the most effi-
cient packing and the vapour-liquid
distributors along with optimised
solution concentration. Therefore,
several options to maximise the
packing bed height were investi-
gated (see Table 1) with all the prac-
tical constraints for this old column.
Based on a thorough review of
all the options with the owner’s
operations and engineering groups,
together with the inspection his-
tory and construction group, it was
decided to pursue the maximum
height option #3 with some hot
work within the absorber column.
Estimated performance
improvements
The new performance of CO2
removal is estimated using the
Option#	 Packing height	 CO2
slip target	 Bed configuration	 Tower modifications
Base	 100% of base	 Way below target	 Single	 Wall clips
1	 112% 	 Below target	 Single	 Wall clips
2	 123%	 Closer to target	 Split bed	 Wall clips, complex supports
3	 127%	 Meets target	 Single bed	 Wall clips and ring
Options to maximise packing bed height
Table 1
55 65 75 85
Flood, %
10
0
5
15
20
25
30
35
40
Packingheight,ft(topdown)
Base capacity with new packing
Future capacity with new packing
Base capacity with existing packing
Figure 6 % flood: absorber with new and old packing
1140 1250
Plant capacity, stpd
1500
2000
1000
500
CO2slip,ppmv
0
Modified height (h × 127%)
Existing packing height (h)
Figure 7 Performance estimation with modifications
70 PTQ Q2 2017 	 www.eptq.com
new efficient packing, new efficient
vapour and liquid distributors and
an optimised solution concentra-
tion. The performance with new
internals/packing with optimised
solvent is further compared for two
capacity cases using the modified
packing height (127% of the exist-
ing packing height) in the existing
absorber to provide the most value
with the least cost. The two capacity
cases compared are:
•	Base capacity (1140 t/d)
•	Future capacity (1250 t/d).
The additional packing height
provides a significant reduction in
CO2
slip to achieve a figure well
below 300 ppmv for the base capac-
ity and <500 ppmv for future capac-
ity (see Figure 7).
Incremental ammonia production
Reducing CO2
slip benefits ammo-
nia plant efficiency with a propor-
tionate increase in production for
the same amount of feed gas used
with high CO2
slip.
Incremental ammonia produc-
tion with improved performance
of the CO2
removal system for the
base operating capacity (1140 t/d)
and the future operating capacity
(1250 t/d) are estimated and shown
in Figure 8. This indicates a capac-
ity and efficiency improvement of
about 2.4% for the base case and
about 3.6% for the future case.
Economics of CO2
removal system
upgrade
Based on the modifications being
carried out and the expected perfor-
mance improvements, the payback
period for the base case is estimated
to be less than eight months and the
payback for the future capacity case
would be less than four months (see
Figure 9). The basis of this estimate
is the incremental ammonia produc-
tion relative to the base case ammo-
nia production corresponding to
a high CO2
slip for the two capac-
ity cases and median netback on
ammonia.
Additional CO2
removal schemes
under review
Another MDEA based two stage
CO2
removal system is under
review for high CO2
slip and corro-
sion related issues (see Figure 10).
60
40
20
Incrementalammonia,stpd
0
100 200 300 400 500
CO2 slip, ppmv
1250 stpd
1140 stpd
Figure 8 Incremental ammonia production with reduced CO2
slip
6
8
7
5
4
3
2
1
Simplepayback,months
0
100 200 300 400 500
CO2 slip, ppmv
1250 stpd
1140 stpd Base capacity payback <8 months
Future capacity payback <4 months
Figure 9 Estimated payback of modifications
Water
Absorber
LP flash
HP flash
Raw
syngas
Treated
syngas
Flash /
fuel gas
LC
PC
CO2
product
Stripper
Figure 10 MDEA-piperazine scheme: two stage
72 PTQ Q2 2017 	 www.eptq.com
ment space in the absorbers and
syngas knockout drums could
lead to channelling with inefficient
vapour-liquid separation.
•	Make-up water quality with
carry-over of any undissolved sol-
ids could eventually deposit in the
downstream methanator feed/efflu-
ent exchangers.
•	Excessive foaming could poten-
tially result in carry-over.
•	Lower velocities with carry-over
coupled with higher localised tem-
perature in the downstream meth-
anator feed/effluent exchanger
could promote fouling rates.
Findings and recommendations
Based on an adequacy check and
further analysis of the absorber
overhead system, the following rec-
ommendations were made based on
the findings:
•	The vapour-liquid disengagement
space in the syngas knockout drum
was found to be inadequate. This
was considered to be a significant
cause of uneven flow distribution
and channelling, resulting in poor
separation efficiency and potential
carry-over.
•	The existing slotted pipe feed dis-
tributor was recommended to be
replaced with an even flow distrib-
utor to overcome this limitation.
•	Recently replaced demister pads
in the absorbers and syngas knock-
out drums of both plants were also
found to be inadequate to efficiently
capture the smaller liquid droplets,
potentially resulting in carry-over.
•	It was recommended that the
demister pads be replaced with a
new design using a combination of
co-knit polymer with metal.
•	Syngas velocities in the shell
side of the feed/effluent exchang-
ers were initially concerning but
no modification was warranted
as the intent was to simply min-
imise or eliminate carry-over as
opposed to pushing the carry-over
through higher exchanger veloc-
ities into the downstream cata-
lyst beds. Therefore, no change in
the downstream exchanger was
recommended.
•	A phase 2 recommendation was
made for an in situ spray system for
the syngas knockout drums, should
the recommended modifications
in carry-over, KPI was engaged
to study and review the poten-
tial deficiencies and recommend
suitable cost effective improve-
ments to minimise or eliminate the
carry-over.
The following potential causes of
carry-over were identified:
•	A significant fraction of smaller
droplets (<10 microns) in the
carry-over: recently replaced sep-
aration devices were considered
inadequate to efficiently capture the
smaller droplets.
•	Insufficient vapour disengage-
Benfield CO2
removal system
The existing Benfield process
scheme for CO2
removal in ammo-
nia plants 2 and 3 is shown in Figure
11. Both plants operated at about
108% of their name plate capacity
of about 2000 t/d and consistently
experienced a significant carry-over
from the absorber, resulting in
pressure drop build-up across the
downstream methanator feed/
effluent exchanger. Based on plant
historical data, the system segment
pressure drop increased from 20
psi to 30 psi in about three months,
resulting in a gradual reduction in
ammonia production and in the
plants’ efficiencies. This situation
forced the operators to undertake
a short plant shutdown every three
months to clean up the exchanger,
which also resulted in additional
loss of ammonia production for
nearly 10 hours with reduced plant
reliability. This problem contin-
ued despite replacement with new
efficient liquid distributors and
demisters in both the absorbers and
syngas knockout drums.
Following replacement with new
liquid distributors and demisters
with only marginal improvement
Absorber
Semi-lean
pump
Lean
pump
Syngas
KO drum
Eductor flash
system
Feed
Treated syngas to
methanator feed /
effluent exchanger
Stripper
CO2
LP
steam
Figure 11 Benfield process schematic for ammonia plants 2 and 3
Reducing CO2
slip
benefits ammonia
plant efficiency with
a proportionate
increase in production
for the same amount
of feed gas used with
high CO2
slip
www.eptq.com 	 PTQ Q2 2017 73
Conclusions
High CO2
slippage is a common
problem in ammonia plants as well
as acid gas removal systems in pet-
rochemical plants and refineries. It
mainly occurs when plant capaci-
ties are stretched with the following
common limiting factors:
•	Limited mass transfer due to:
	 ■	Inadequate vapour/liquid
distribution
	 ■	 Inefficient packing
	 ■	 Packing height limitations
•	Heat transfer limitations due to:
	 ■	Cooling
	 ■	Reboiling
•	Insufficient circulation due to lim-
iting pump capacities:
•	Non-optimal solution concentration.
KPI implemented simple and cost
effective solutions with a MDEA-
piperazine based system in an
ammonia plant with a payback
period of four to eight months.
Carry-over in a Benfield CO2
removal system is experienced in
several plants. Plant operators have
adopted different measures to miti-
gate this problem. KPI successfully
implemented simple and cost effec-
tive systems in two large ammonia
plants with a payback of less than
three months.
V K Arora is Director of Process & Operations
with KPI through its Houston & Bahrain
offices and is the company’s founder. He has
led and directed development of two major
petrochemicals projects in Saudi Arabia and
several revamps. Prior to joining KPI, he was
with CBI/Lummus in various positions. A
licensed professional engineer in the state of
Texas, he holds a chemical engineering degree
from IIT, Delhi.
Email:vka@kpieng.com
in phase 1 not yield the expected
performance.
Modifications
Based on the above findings and
recommendations, the following
modifications were engineered
and supplied through KPI for both
plants:
•	Special co-knit polymer demisters
for the absorbers and syngas knock-
out drums in both ammonia plants
•	Even flow distributors engineered
to be supported within the existing
vessels without any hot work on
the vessel shell.
	
Performance improvements
A performance chart of the ∆P
trend over more than 450 days,
before and after the modifications,
clearly indicates a fairly steady
pressure drop (see Figure 12). No
plant shutdown or any loss of
ammonia production was experi-
enced for the next four years before
a turnaround for the lingering car-
ry-over problem in both ammonia
plants. The simple modifications
were successful and were carried
out within a day.
Further, the phase 2 recommen-
dation to include a spray sys-
tem was not required during this
period.
Economics of a CO2
removal
system upgrade
The modifications implemented
were very simple and engineered
and supplied within a month. They
were installed quickly within a day
shift by the operator. Based on a
reclaim of production lost following
the modifications, the real payback
time was less than three months.
0
60
120
180
240
300
360
420
480
30
90
150
210
270
330
390
450
Elapsed time, days
22
30
34
26
18
14
Pressuredrop,
lb/ft3
10
After modifications
Just before modifications
Figure 12 ∆P trend before and after modifications

More Related Content

What's hot

PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
Vijay Sarathy
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project Presentation
Gazi Mahade Hasan
 
Practical Aspects of Using and Making High RAP and RAS HMA
Practical Aspects of Using and Making High RAP and RAS HMAPractical Aspects of Using and Making High RAP and RAS HMA
Practical Aspects of Using and Making High RAP and RAS HMA
California Asphalt Pavement Association
 
Chemical process debottlenecking
Chemical process debottleneckingChemical process debottlenecking
Chemical process debottlenecking
Stephen (Steve) Galante
 
Model-based Optimization of a CompactCooking G2 Digesting Process Stage
Model-based Optimization of a CompactCooking G2 Digesting Process StageModel-based Optimization of a CompactCooking G2 Digesting Process Stage
Model-based Optimization of a CompactCooking G2 Digesting Process Stage
Igor Saavedra Salas
 
Pipeline Design Project
Pipeline Design ProjectPipeline Design Project
Pipeline Design Project
Daniel Kerkhoff
 
Ion exchange plant design
Ion exchange plant designIon exchange plant design
Ion exchange plant design
Vikas Janu
 
Asphalt Binders Used in Mongolia in the view of Superpave Specification,jul...
Asphalt Binders Used  in Mongolia in the view of  Superpave Specification,jul...Asphalt Binders Used  in Mongolia in the view of  Superpave Specification,jul...
Asphalt Binders Used in Mongolia in the view of Superpave Specification,jul...
Bayar Tsend
 
Development of an innovative 3 stage steady bed gasifier slides
Development of an innovative 3 stage steady bed gasifier slidesDevelopment of an innovative 3 stage steady bed gasifier slides
Development of an innovative 3 stage steady bed gasifier slides
ravi8492
 
Recommendations for Mix Design Using RAP/RAS
Recommendations for Mix Design Using RAP/RASRecommendations for Mix Design Using RAP/RAS
Recommendations for Mix Design Using RAP/RAS
California Asphalt Pavement Association
 
Design of sensible and latent heat thermal energy storage systems for concent...
Design of sensible and latent heat thermal energy storage systems for concent...Design of sensible and latent heat thermal energy storage systems for concent...
Design of sensible and latent heat thermal energy storage systems for concent...
Himanshu Bora
 
Pipeline b
Pipeline bPipeline b
Pipeline b
Kinosraj Kumaran
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
UK Carbon Capture and Storage Research Centre
 
WMA & Admixtures
WMA & AdmixturesWMA & Admixtures
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
KBC (A Yokogawa Company)
 
pgpager_Wolfson Heat treat-UK
pgpager_Wolfson Heat treat-UKpgpager_Wolfson Heat treat-UK
pgpager_Wolfson Heat treat-UK
Pratap Ghorpade
 
Warm Mix Asphalt research and performance
Warm Mix Asphalt research and performanceWarm Mix Asphalt research and performance
Warm Mix Asphalt research and performance
California Asphalt Pavement Association
 
Chemical eor
Chemical eorChemical eor
Chemical eor
Kumar
 

What's hot (18)

PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
PVTSim - Beginners Guide & Tutorial (Multi-Phase Calculations)
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project Presentation
 
Practical Aspects of Using and Making High RAP and RAS HMA
Practical Aspects of Using and Making High RAP and RAS HMAPractical Aspects of Using and Making High RAP and RAS HMA
Practical Aspects of Using and Making High RAP and RAS HMA
 
Chemical process debottlenecking
Chemical process debottleneckingChemical process debottlenecking
Chemical process debottlenecking
 
Model-based Optimization of a CompactCooking G2 Digesting Process Stage
Model-based Optimization of a CompactCooking G2 Digesting Process StageModel-based Optimization of a CompactCooking G2 Digesting Process Stage
Model-based Optimization of a CompactCooking G2 Digesting Process Stage
 
Pipeline Design Project
Pipeline Design ProjectPipeline Design Project
Pipeline Design Project
 
Ion exchange plant design
Ion exchange plant designIon exchange plant design
Ion exchange plant design
 
Asphalt Binders Used in Mongolia in the view of Superpave Specification,jul...
Asphalt Binders Used  in Mongolia in the view of  Superpave Specification,jul...Asphalt Binders Used  in Mongolia in the view of  Superpave Specification,jul...
Asphalt Binders Used in Mongolia in the view of Superpave Specification,jul...
 
Development of an innovative 3 stage steady bed gasifier slides
Development of an innovative 3 stage steady bed gasifier slidesDevelopment of an innovative 3 stage steady bed gasifier slides
Development of an innovative 3 stage steady bed gasifier slides
 
Recommendations for Mix Design Using RAP/RAS
Recommendations for Mix Design Using RAP/RASRecommendations for Mix Design Using RAP/RAS
Recommendations for Mix Design Using RAP/RAS
 
Design of sensible and latent heat thermal energy storage systems for concent...
Design of sensible and latent heat thermal energy storage systems for concent...Design of sensible and latent heat thermal energy storage systems for concent...
Design of sensible and latent heat thermal energy storage systems for concent...
 
Pipeline b
Pipeline bPipeline b
Pipeline b
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
WMA & Admixtures
WMA & AdmixturesWMA & Admixtures
WMA & Admixtures
 
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
Europe User Conference: thermodynamic behaviour of HPHT reservoir fluids and ...
 
pgpager_Wolfson Heat treat-UK
pgpager_Wolfson Heat treat-UKpgpager_Wolfson Heat treat-UK
pgpager_Wolfson Heat treat-UK
 
Warm Mix Asphalt research and performance
Warm Mix Asphalt research and performanceWarm Mix Asphalt research and performance
Warm Mix Asphalt research and performance
 
Chemical eor
Chemical eorChemical eor
Chemical eor
 

Similar to Upgrading co2 removal systems

Senior Design Final Report (2)
Senior Design Final Report (2)Senior Design Final Report (2)
Senior Design Final Report (2)
AN TRAN
 
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu Chen
 
HEP_Feb2013_EPA
HEP_Feb2013_EPAHEP_Feb2013_EPA
HEP_Feb2013_EPA
Sheri Vanhooser
 
Ge remove oxygen
Ge   remove oxygenGe   remove oxygen
Ge remove oxygen
AMAZONWATERLamTrn
 
78201906
7820190678201906
78201906
IJRAT
 
78201906
7820190678201906
78201906
IJRAT
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
Ureaplantenergysavingbyselectionoflinermaterialandinernals
Prem Baboo
 
ChE184B - FinalDesign
ChE184B - FinalDesignChE184B - FinalDesign
ChE184B - FinalDesign
Russell Wong
 
4 modeling and control of distillation column in a petroleum process
4 modeling and control of distillation column in a petroleum process4 modeling and control of distillation column in a petroleum process
4 modeling and control of distillation column in a petroleum process
nazir1988
 
EnergyEfficientHydraulicshd2015_KERydberg (1).pdf
EnergyEfficientHydraulicshd2015_KERydberg (1).pdfEnergyEfficientHydraulicshd2015_KERydberg (1).pdf
EnergyEfficientHydraulicshd2015_KERydberg (1).pdf
morteza shakerien
 
Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008
tasander
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
simachem
 
articleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdfarticleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdf
Roy Niekerk
 
errico2013.pdf
errico2013.pdferrico2013.pdf
errico2013.pdf
karitoIsa2
 
Anaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of SewageAnaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of Sewage
Amit Christian
 
1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main
Heri Faisandra
 
Dynamic future flare_design2020
Dynamic future flare_design2020Dynamic future flare_design2020
Dynamic future flare_design2020
Armin Mn
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
williampatricklaw
 
Minimising emissions, maximising alternative fuels
Minimising emissions, maximising alternative fuelsMinimising emissions, maximising alternative fuels
Minimising emissions, maximising alternative fuels
A TEC Group
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reforming
Tanay_Bobde
 

Similar to Upgrading co2 removal systems (20)

Senior Design Final Report (2)
Senior Design Final Report (2)Senior Design Final Report (2)
Senior Design Final Report (2)
 
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
Guofu_Chen_Optimize Design and Operation of Renewable Energy Cycle through As...
 
HEP_Feb2013_EPA
HEP_Feb2013_EPAHEP_Feb2013_EPA
HEP_Feb2013_EPA
 
Ge remove oxygen
Ge   remove oxygenGe   remove oxygen
Ge remove oxygen
 
78201906
7820190678201906
78201906
 
78201906
7820190678201906
78201906
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
Ureaplantenergysavingbyselectionoflinermaterialandinernals
 
ChE184B - FinalDesign
ChE184B - FinalDesignChE184B - FinalDesign
ChE184B - FinalDesign
 
4 modeling and control of distillation column in a petroleum process
4 modeling and control of distillation column in a petroleum process4 modeling and control of distillation column in a petroleum process
4 modeling and control of distillation column in a petroleum process
 
EnergyEfficientHydraulicshd2015_KERydberg (1).pdf
EnergyEfficientHydraulicshd2015_KERydberg (1).pdfEnergyEfficientHydraulicshd2015_KERydberg (1).pdf
EnergyEfficientHydraulicshd2015_KERydberg (1).pdf
 
Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
articleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdfarticleHydrocarbonEngineeringSeptember2019.pdf
articleHydrocarbonEngineeringSeptember2019.pdf
 
errico2013.pdf
errico2013.pdferrico2013.pdf
errico2013.pdf
 
Anaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of SewageAnaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of Sewage
 
1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main
 
Dynamic future flare_design2020
Dynamic future flare_design2020Dynamic future flare_design2020
Dynamic future flare_design2020
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
 
Minimising emissions, maximising alternative fuels
Minimising emissions, maximising alternative fuelsMinimising emissions, maximising alternative fuels
Minimising emissions, maximising alternative fuels
 
Hydrogen Production steam reforming
Hydrogen Production steam reformingHydrogen Production steam reforming
Hydrogen Production steam reforming
 

Recently uploaded

一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
21uul8se
 
Heuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdfHeuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdf
Jaime Brown
 
Design Thinking: Madhu Prabakaran 17th July 2024
Design Thinking: Madhu Prabakaran 17th July 2024Design Thinking: Madhu Prabakaran 17th July 2024
Design Thinking: Madhu Prabakaran 17th July 2024
Madhu Prabakaran
 
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
qa8dk1wm
 
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
oabn3692
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NishantRathi18
 
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
k7nm6tk
 
Getting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by NeontribeGetting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by Neontribe
Harry Harrold
 
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
p74xokfq
 
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
etls06p8
 
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
kohd1ci2
 
一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样
tobbk6s8
 
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
wkip62b
 
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
mfria419
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
340qn0m1
 
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
zv943dhb
 
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptxTOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
BAWAALEX1
 
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
k4krdgxx
 
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
02tygie
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
ellemjani
 

Recently uploaded (20)

一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
 
Heuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdfHeuristics Evaluation - How to Guide.pdf
Heuristics Evaluation - How to Guide.pdf
 
Design Thinking: Madhu Prabakaran 17th July 2024
Design Thinking: Madhu Prabakaran 17th July 2024Design Thinking: Madhu Prabakaran 17th July 2024
Design Thinking: Madhu Prabakaran 17th July 2024
 
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
一比一原版澳洲查理斯特大学毕业证(CSU学位证)如何办理
 
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
一比一原版(Rice毕业证)美国莱斯大学毕业证如何办理
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
 
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
一比一原版(LSBU毕业证书)伦敦南岸大学毕业证如何办理
 
Getting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by NeontribeGetting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by Neontribe
 
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
一比一原版(USQ毕业证书)南昆士兰大学毕业证如何办理
 
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
一比一原版(UWE毕业证书)西英格兰大学毕业证如何办理
 
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证)澳洲埃迪斯科文大学毕业证如何办理
 
一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样
 
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
 
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
一比一原版(Teesside毕业证)英国提赛德大学毕业证如何办理
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证如何办理
 
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
一比一原版(UCB毕业证)英国伯明翰大学学院毕业证如何办理
 
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptxTOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
TOWER DESIGN PROCEDURE TOWER DESIGN BASIS .pptx
 
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
一比一原版(Deakin毕业证书)澳洲迪肯大学毕业证文凭如何办理
 
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
一比一原版美国加州大学欧文分校毕业证(UCI学位证)如何办理
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
 

Upgrading co2 removal systems

  • 1. Upgrading CO2 removal systems A cid gas removal is an impor- tant step in petrochemi- cal plants, refineries and syngas production. This article describes experience in cost effec- tively upgrading CO2 removal sys- tems in three ammonia plants with an attractive payback of just a few months. One of the plants uses a MDEA system and the other two use Benfield systems. A similar approach can be used in acid gas removal systems in petrochemicals plants and refineries. MDEA based CO2 removal system The existing single stage MDEA CO2 removal system scheme is shown in Figure 1. This conver- sion of an old MEA based system was implemented as a part of the overall ammonia plant capacity revamp from the original name- plate capacity of 600 t/d to about 1100 t/d. The original absorber and stripper columns were used, with trays replaced with packings and other internals. The current oper- ating capacity is 1140 t/d to 1170 t/d, depending on seasonal varia- tion. This plant was stretched to its design limits and beyond. A holistic review of the reference CO2 removal system was carried out by KPI to identify all the poten- tial bottlenecks contributing to a shortfall in performance. To sup- port this, the following steps were taken: • Gamma scan of the columns to determine any maldistribution • Representative operating data corresponding to maximum operat- ing capacity • Reconciliation of the operating data Simple modifications to three carbon dioxide removal systems raised their efficiencies with short payback periods V K ARORA Kinetics Process Improvements • Simulation of the existing scheme to match the reconciled operating data • Evaluation of potential bottlenecks at the current operating conditions: ■ Mass transfer limits of the existing packing type and height ■ Adequacy/limitations of liquid distributor ■ Adequacy/limitations of feed vapour distributor ■ Hydraulic adequacy/limita- tions of the solvent circulation loop ■ Solvent and activator concen- tration for optimal performance. Figures 2-5 represent the base operating performance at 1140 t/d as modelled and reconciled with actual operating performance. A gamma scan of the absorber indi- cates the liquid density variation profile in Figure 2, with a variation between 8 and 15 units indicating maldistribution. The absorber is operating at about 85% flood while the stripper has enough hydrau- lic capacity available (see Figure 5). The absorber temperature profile in www.eptq.com PTQ Q2 2017 67 Water Raw syngas Absorber Stripper LC CO2 product Treated syngas Figure 1 MDEA-piperazine CO2 removal scheme Drydensity:15lb/ft3 Base operation 20 15 10 5 0 Figure 2 Absorber liquid density profile
  • 2. 68 PTQ Q2 2017 www.eptq.com fall in performance. The potential causes identified in the absorber system were: • Liquid maldistribution deter- mined through gamma scan • Under-sized liquid distribu- tor in the absorber, leading to maldistribution • High momentum through the vapour distributor in the absorber, leading to maldistribution • Mass transfer limitations due to short packing height and incorrect loading • Hydraulics and mass transfer lim- itations of the existing packing. The stripper column did not indi- cate any hydraulic or mass trans- fer limitations or any performance issues. Options to reduce CO2 slip As the next step, several options were evaluated with relevant inputs gathered from vendors. The fol- lowing options were further simu- lated and reviewed for improved performance, including cost-benefit analysis: • New efficient packing configura- tions with improved mass transfer and hydraulics • Increase in packing height, as noted later for different options • New liquid distributor • New feed vapour distributor • Increase in circulation rate • Optimise solution concentration. New liquid distributor The existing trough type V-notch liquid distributors were inadequate and considered less efficient for the service conditions. They were replaced with new efficient ori- fice deck distributors rated with sufficient design margin over the new service conditions for current and future operating cases. Most importantly, the new distributors were designed for installation and removal through the existing 17in manways to facilitate correct load- ing of packing. New feed vapour distributor The existing feed vapour distributor was also found to be inadequate, with a much higher momentum than recommended and also insuf- ficient coverage of the cross section. Figure 3 seems reasonable while the CO2 concentration profile in Figure 4 indicates about 2600 ppmv of CO2 slip. Potential causes of high CO2 slip Based on an initial evaluation, the absorber column indicated major limitations, resulting in a short- 16 8 10 4 6 2 0 12 14 18 20 22 24 26 Packingheight,ft(topdown) 28 100 115 130 145 160 175 Temperature, ºF Base operation 0 500 1000 1500 2000 2500 3000 3500 4000 CO2 concentration, ppmv 15 5 0 10 20 25 Packingheight,ft(topdown) 30 Base operation Figure 3 Absorber temperature profile Figure 4 Absorber vapour CO2 concentration profile 30 40 50 60 70 80 90 Flood, % 5 0 10 15 20 25 30 35 Packingheight,ft(topdown) Absorber Stripper Base operation Figure 5 % flood: absorber and stripper
  • 3. It was replaced with a T-type lat- eral distributor rated with sufficient design margin over the new ser- vice conditions for both the current and future operating cases. Most importantly, the new distributors were designed for installation and removal through the existing 17in manways. Increase in circulation and hydraulics adequacy Increasing the solvent circulation rate was reviewed along with a complete hydraulics evaluation of the lean circuit and the lean MDEA pumps, with a clear premise not to replace any of the existing pumps and drivers. Interestingly, a mar- ginal increase in circulation rate was possible with replacement of the existing impellers at the maxi- mum possible size, well within the maximum design rating of the exist- ing drivers. Further, the impact of the higher circulation rate was also evaluated for both absorber and stripper columns with new pack- ing type, size and different bed configurations. New efficient packing To improve the limitations of both mass transfer and hydraulics in the absorber, new and efficient packings from two suppliers were evaluated with extensive in-house modelling for their quantitative impact on per- formance. The improved hydrau- lics with the selected new efficient packing with increased packing height (127% of the existing height) is shown in Figure 6 and compared with the hydraulics of the existing packing for both base and future capacities (1140 t/d and 1250 t/d, respectively). The hydraulic capac- ity of the absorber indicates a sub- stantial improvement with the new efficient packing. New packing configurations The latest and most efficient proven packings from two suppliers were reviewed and modelled to evalu- ate their impact on CO2 slip and hydraulics. A combination of split bed with two different packing sizes – with and without liquid redistributors – was also reviewed. Based on the detailed evaluation www.eptq.com PTQ Q2 2017 69 and modelled performance, it was decided to go ahead with only one deeper bed for the most value. Incremental packing height and practical constraints The existing packing height was determined to be a limiting fac- tor to achieve the target CO2 slip despite changes with the most effi- cient packing and the vapour-liquid distributors along with optimised solution concentration. Therefore, several options to maximise the packing bed height were investi- gated (see Table 1) with all the prac- tical constraints for this old column. Based on a thorough review of all the options with the owner’s operations and engineering groups, together with the inspection his- tory and construction group, it was decided to pursue the maximum height option #3 with some hot work within the absorber column. Estimated performance improvements The new performance of CO2 removal is estimated using the Option# Packing height CO2 slip target Bed configuration Tower modifications Base 100% of base Way below target Single Wall clips 1 112% Below target Single Wall clips 2 123% Closer to target Split bed Wall clips, complex supports 3 127% Meets target Single bed Wall clips and ring Options to maximise packing bed height Table 1 55 65 75 85 Flood, % 10 0 5 15 20 25 30 35 40 Packingheight,ft(topdown) Base capacity with new packing Future capacity with new packing Base capacity with existing packing Figure 6 % flood: absorber with new and old packing 1140 1250 Plant capacity, stpd 1500 2000 1000 500 CO2slip,ppmv 0 Modified height (h × 127%) Existing packing height (h) Figure 7 Performance estimation with modifications
  • 4. 70 PTQ Q2 2017 www.eptq.com new efficient packing, new efficient vapour and liquid distributors and an optimised solution concentra- tion. The performance with new internals/packing with optimised solvent is further compared for two capacity cases using the modified packing height (127% of the exist- ing packing height) in the existing absorber to provide the most value with the least cost. The two capacity cases compared are: • Base capacity (1140 t/d) • Future capacity (1250 t/d). The additional packing height provides a significant reduction in CO2 slip to achieve a figure well below 300 ppmv for the base capac- ity and <500 ppmv for future capac- ity (see Figure 7). Incremental ammonia production Reducing CO2 slip benefits ammo- nia plant efficiency with a propor- tionate increase in production for the same amount of feed gas used with high CO2 slip. Incremental ammonia produc- tion with improved performance of the CO2 removal system for the base operating capacity (1140 t/d) and the future operating capacity (1250 t/d) are estimated and shown in Figure 8. This indicates a capac- ity and efficiency improvement of about 2.4% for the base case and about 3.6% for the future case. Economics of CO2 removal system upgrade Based on the modifications being carried out and the expected perfor- mance improvements, the payback period for the base case is estimated to be less than eight months and the payback for the future capacity case would be less than four months (see Figure 9). The basis of this estimate is the incremental ammonia produc- tion relative to the base case ammo- nia production corresponding to a high CO2 slip for the two capac- ity cases and median netback on ammonia. Additional CO2 removal schemes under review Another MDEA based two stage CO2 removal system is under review for high CO2 slip and corro- sion related issues (see Figure 10). 60 40 20 Incrementalammonia,stpd 0 100 200 300 400 500 CO2 slip, ppmv 1250 stpd 1140 stpd Figure 8 Incremental ammonia production with reduced CO2 slip 6 8 7 5 4 3 2 1 Simplepayback,months 0 100 200 300 400 500 CO2 slip, ppmv 1250 stpd 1140 stpd Base capacity payback <8 months Future capacity payback <4 months Figure 9 Estimated payback of modifications Water Absorber LP flash HP flash Raw syngas Treated syngas Flash / fuel gas LC PC CO2 product Stripper Figure 10 MDEA-piperazine scheme: two stage
  • 5. 72 PTQ Q2 2017 www.eptq.com ment space in the absorbers and syngas knockout drums could lead to channelling with inefficient vapour-liquid separation. • Make-up water quality with carry-over of any undissolved sol- ids could eventually deposit in the downstream methanator feed/efflu- ent exchangers. • Excessive foaming could poten- tially result in carry-over. • Lower velocities with carry-over coupled with higher localised tem- perature in the downstream meth- anator feed/effluent exchanger could promote fouling rates. Findings and recommendations Based on an adequacy check and further analysis of the absorber overhead system, the following rec- ommendations were made based on the findings: • The vapour-liquid disengagement space in the syngas knockout drum was found to be inadequate. This was considered to be a significant cause of uneven flow distribution and channelling, resulting in poor separation efficiency and potential carry-over. • The existing slotted pipe feed dis- tributor was recommended to be replaced with an even flow distrib- utor to overcome this limitation. • Recently replaced demister pads in the absorbers and syngas knock- out drums of both plants were also found to be inadequate to efficiently capture the smaller liquid droplets, potentially resulting in carry-over. • It was recommended that the demister pads be replaced with a new design using a combination of co-knit polymer with metal. • Syngas velocities in the shell side of the feed/effluent exchang- ers were initially concerning but no modification was warranted as the intent was to simply min- imise or eliminate carry-over as opposed to pushing the carry-over through higher exchanger veloc- ities into the downstream cata- lyst beds. Therefore, no change in the downstream exchanger was recommended. • A phase 2 recommendation was made for an in situ spray system for the syngas knockout drums, should the recommended modifications in carry-over, KPI was engaged to study and review the poten- tial deficiencies and recommend suitable cost effective improve- ments to minimise or eliminate the carry-over. The following potential causes of carry-over were identified: • A significant fraction of smaller droplets (<10 microns) in the carry-over: recently replaced sep- aration devices were considered inadequate to efficiently capture the smaller droplets. • Insufficient vapour disengage- Benfield CO2 removal system The existing Benfield process scheme for CO2 removal in ammo- nia plants 2 and 3 is shown in Figure 11. Both plants operated at about 108% of their name plate capacity of about 2000 t/d and consistently experienced a significant carry-over from the absorber, resulting in pressure drop build-up across the downstream methanator feed/ effluent exchanger. Based on plant historical data, the system segment pressure drop increased from 20 psi to 30 psi in about three months, resulting in a gradual reduction in ammonia production and in the plants’ efficiencies. This situation forced the operators to undertake a short plant shutdown every three months to clean up the exchanger, which also resulted in additional loss of ammonia production for nearly 10 hours with reduced plant reliability. This problem contin- ued despite replacement with new efficient liquid distributors and demisters in both the absorbers and syngas knockout drums. Following replacement with new liquid distributors and demisters with only marginal improvement Absorber Semi-lean pump Lean pump Syngas KO drum Eductor flash system Feed Treated syngas to methanator feed / effluent exchanger Stripper CO2 LP steam Figure 11 Benfield process schematic for ammonia plants 2 and 3 Reducing CO2 slip benefits ammonia plant efficiency with a proportionate increase in production for the same amount of feed gas used with high CO2 slip
  • 6. www.eptq.com PTQ Q2 2017 73 Conclusions High CO2 slippage is a common problem in ammonia plants as well as acid gas removal systems in pet- rochemical plants and refineries. It mainly occurs when plant capaci- ties are stretched with the following common limiting factors: • Limited mass transfer due to: ■ Inadequate vapour/liquid distribution ■ Inefficient packing ■ Packing height limitations • Heat transfer limitations due to: ■ Cooling ■ Reboiling • Insufficient circulation due to lim- iting pump capacities: • Non-optimal solution concentration. KPI implemented simple and cost effective solutions with a MDEA- piperazine based system in an ammonia plant with a payback period of four to eight months. Carry-over in a Benfield CO2 removal system is experienced in several plants. Plant operators have adopted different measures to miti- gate this problem. KPI successfully implemented simple and cost effec- tive systems in two large ammonia plants with a payback of less than three months. V K Arora is Director of Process & Operations with KPI through its Houston & Bahrain offices and is the company’s founder. He has led and directed development of two major petrochemicals projects in Saudi Arabia and several revamps. Prior to joining KPI, he was with CBI/Lummus in various positions. A licensed professional engineer in the state of Texas, he holds a chemical engineering degree from IIT, Delhi. Email:vka@kpieng.com in phase 1 not yield the expected performance. Modifications Based on the above findings and recommendations, the following modifications were engineered and supplied through KPI for both plants: • Special co-knit polymer demisters for the absorbers and syngas knock- out drums in both ammonia plants • Even flow distributors engineered to be supported within the existing vessels without any hot work on the vessel shell. Performance improvements A performance chart of the ∆P trend over more than 450 days, before and after the modifications, clearly indicates a fairly steady pressure drop (see Figure 12). No plant shutdown or any loss of ammonia production was experi- enced for the next four years before a turnaround for the lingering car- ry-over problem in both ammonia plants. The simple modifications were successful and were carried out within a day. Further, the phase 2 recommen- dation to include a spray sys- tem was not required during this period. Economics of a CO2 removal system upgrade The modifications implemented were very simple and engineered and supplied within a month. They were installed quickly within a day shift by the operator. Based on a reclaim of production lost following the modifications, the real payback time was less than three months. 0 60 120 180 240 300 360 420 480 30 90 150 210 270 330 390 450 Elapsed time, days 22 30 34 26 18 14 Pressuredrop, lb/ft3 10 After modifications Just before modifications Figure 12 ∆P trend before and after modifications