The document discusses a traffic and pedestrian management study for Yeshwanthpur, Bangalore. It outlines issues in the area such as lack of pedestrian infrastructure like footpaths and crossings, congestion from irregular parking and encroachment. The study analyzed accident data and existing transport modes. Proposals are made to improve pedestrian amenities and safety through dedicated bus shelters, connecting subways on both sides of the road, continuous footpaths, designated auto stands, and improved signage and lighting.
mattuthavani bus terminal (or) MGR bus terminal - Mattuthavani Integrated Bus Terminus is a mofussil bus terminus in Mattuthavani, Madurai in Tamil Nadu, India. The bus stand is one of the largest bus terminus
Interstate bus terminal - Library Study & Case Study, by 4th-year students of bachelors of architecture, Indo Global college of architecture affiliated with I.K.GUJRAL PUNJAB TECHNICAL UNIVERSITY.
TRANSIT TERMINAL DESIGN - INTRODUCTION, Terminal Characteristics, Functional Attributes, CIRCULATION, DESIGN, SERVICES.
CASE STUDY - ISBT-Sector 43 Chandigarh
Urban Design-Literature study St. Marks Road, BangaloreAnsh Agarwal
Urban Planning
Literature study of St. Marks Road, Bangalore.
Includes:
1. Road Details
2. Survey Details & Analysis
3. Action Needed
4. Proposals
5. Action Made
6. Before & After Scenerio
7. Anatomy of Changes
CHANDNI CHOWK REDEVELOPMENT
HUMAN SETTLEMENT AND PLANING
AREA REDEVELPOED
ABOUT CHANDNI CHOWK
A RS 65-CRORE PROJECT
CHANDNI CHOWK SECTION SHOWING SERVICES
PLAN-1
PLAN-2
PLAN-3
PLAN-4
INTRODUCTION
COORDINATES - 23.22 ON 72.680 E ELEVATION - 265 feet (81 m)*
LOCATED 23 KM NORTH OF AHEMDABAD (FIN CAP. OF GUJARAT)
PLANNED IN 1960S BY, PRAKASH M APTE & H. K. MEWADA,
AFTER PARTITION OF BOMBAY * STATE : AHEMDABAD WAS MADE AS THE CAPTAL OFGUJARAT
AREA TOTAL 177KM2 ELEVATION : 8IM ( 266 FT)
POPULATION (2011)
TOTAL: 206,167 DENSITY : 1,200/KM2
CLIMATE*
TROPICAL WET AND DRY CLIMATE•
SUMMER MAXIMUM - 36 to 42 °C MINIMUM - 19 to 27 C
WINTER MAXIMUM - 29 C MINIMUM - 14°C
MONSOON: THE AVERAGE ANNUAL RAINFALL IS AROUND 803.4 MM
LANGUAGES
GUJARATI, HINDI, AND ENGLISH• 54% GREEN COVER ON ITS LAND AREA
• THE CITY SITS ON THE BANKS OF THE SABARMATI RIVER, IN NORTH-CENTRALEAST GUJARAT
HISTORY
IN 1960, THE INDIAN STATE OF BOMBAY WAS SPLIT INTO TWO STATES, MAHARASHTRA AND GUJARAT LEAVING GUJARAT WITHOUT A CAPITAL CITY.
AT THE TIME AHMEDABAD WAS SELECTED TO BE THE FIRST CAPITAL OF THE NEWLY CREATED STATE.
• IT WAS LATER PROPOSED THAT A NEW CAPITAL CITY BE CONSTRUCTED FOR THE STATE.
• GANDHINAGAR GOT AN IDENTITY OF ITS OWN WHEN THE STATE OF MUMBAI WAS DIVIDED INTO TWO SEPARATE STATES OF GUJARAT AND MAHARASHTRA.
• IN THE BEGINNING, AHMEDABAD - A COMMERCIAL HUB OF GUJARAT WAS CHOSEN AS THE STATE CAPITAL AND IT WAS PROPOSED THAT A NEW CAPITAL SHOULD BE CONSTRUCTED ALONG THE LINE OF OTHER NEW STATE CAPITALS, PARTICULARLY CHANDIGARH
• THEREFORE TWO WELL-KNOWN INDIAN ARCHITECTS, H.K. MEWADA AND PRAKASH M. APTE (WHO WORKED AS BEGINNER FOR THE CHANDIGARH CITY) DESIGNED THE NEW STATE CAPITAL*
NAMED AFTER MAHATMA GANDHI THE FOUNDATION STONE OF THIS CITY WAS LAID ON 1965 AND IN 1971 THE CAPITAL WAS SHIFTED FROM AHMEDABAD TO GANDHINAGAR
PLANNING
• PLANNED AND IMPLEMENTED BETWEEN 1965-1970
• DETERMINATION TO MAKE GANDHINAGAR A PURELY INDIAN ENTERPRISE, PARTLY BECAUSE GUJARAT WAS THE BIRTHPLACE OF GANDHI.
• TO ESTABLISH AND MAINTAIN A SEPARATE IDENTITY FOR THE NEW CITY THE SURROUNDING AREA OF ABOUT 39 VILLAGES WAS BROUGHT UNDER A PERIPHERY CONTROL ACT (AS IN CHANDIGARH)
• THE AREA LATER CONSTITUTED A SEPARATE ADMINISTRATIVE DISTRICT OF GANDHINAGAR.
• THE CITY WAS PLANNED FOR A POPULATION OF 150,000 BUT CAN ACCOMMODATE DOUBLE THAT POPULATION WITH INCREASE IN THE FLOOR SPACE RATIO FROM 1 TO 2 IN THE AREAS RESERVED FOR PRIVATE DEVELOPMENT.
• THE RIVER BEING THE BORDER ON THE EAST, AND THE INDUSTRIAL AREA TO THE NORTH, THE MOST LOGICAL FUTURE PHYSICAL EXPANSION OF THE CITY WAS ENVISAGED TOWARDS THE NORTH-WEST
FINAL B.ARCH THESIS PRESENTATION IIT ROORKEE:
City Centre ,Rohini ,Delhi ,Thesis project (2013)
A Mixed use development project comprises of diverse activities and functions located at the
sprawling District centre in Rohini with site area of 16 acres.With a AIM to explore the symbiotic
character of COMMERCE and CULTURE and to evolve a contemporary model of conventional
Indian market.
mattuthavani bus terminal (or) MGR bus terminal - Mattuthavani Integrated Bus Terminus is a mofussil bus terminus in Mattuthavani, Madurai in Tamil Nadu, India. The bus stand is one of the largest bus terminus
Interstate bus terminal - Library Study & Case Study, by 4th-year students of bachelors of architecture, Indo Global college of architecture affiliated with I.K.GUJRAL PUNJAB TECHNICAL UNIVERSITY.
TRANSIT TERMINAL DESIGN - INTRODUCTION, Terminal Characteristics, Functional Attributes, CIRCULATION, DESIGN, SERVICES.
CASE STUDY - ISBT-Sector 43 Chandigarh
Urban Design-Literature study St. Marks Road, BangaloreAnsh Agarwal
Urban Planning
Literature study of St. Marks Road, Bangalore.
Includes:
1. Road Details
2. Survey Details & Analysis
3. Action Needed
4. Proposals
5. Action Made
6. Before & After Scenerio
7. Anatomy of Changes
CHANDNI CHOWK REDEVELOPMENT
HUMAN SETTLEMENT AND PLANING
AREA REDEVELPOED
ABOUT CHANDNI CHOWK
A RS 65-CRORE PROJECT
CHANDNI CHOWK SECTION SHOWING SERVICES
PLAN-1
PLAN-2
PLAN-3
PLAN-4
INTRODUCTION
COORDINATES - 23.22 ON 72.680 E ELEVATION - 265 feet (81 m)*
LOCATED 23 KM NORTH OF AHEMDABAD (FIN CAP. OF GUJARAT)
PLANNED IN 1960S BY, PRAKASH M APTE & H. K. MEWADA,
AFTER PARTITION OF BOMBAY * STATE : AHEMDABAD WAS MADE AS THE CAPTAL OFGUJARAT
AREA TOTAL 177KM2 ELEVATION : 8IM ( 266 FT)
POPULATION (2011)
TOTAL: 206,167 DENSITY : 1,200/KM2
CLIMATE*
TROPICAL WET AND DRY CLIMATE•
SUMMER MAXIMUM - 36 to 42 °C MINIMUM - 19 to 27 C
WINTER MAXIMUM - 29 C MINIMUM - 14°C
MONSOON: THE AVERAGE ANNUAL RAINFALL IS AROUND 803.4 MM
LANGUAGES
GUJARATI, HINDI, AND ENGLISH• 54% GREEN COVER ON ITS LAND AREA
• THE CITY SITS ON THE BANKS OF THE SABARMATI RIVER, IN NORTH-CENTRALEAST GUJARAT
HISTORY
IN 1960, THE INDIAN STATE OF BOMBAY WAS SPLIT INTO TWO STATES, MAHARASHTRA AND GUJARAT LEAVING GUJARAT WITHOUT A CAPITAL CITY.
AT THE TIME AHMEDABAD WAS SELECTED TO BE THE FIRST CAPITAL OF THE NEWLY CREATED STATE.
• IT WAS LATER PROPOSED THAT A NEW CAPITAL CITY BE CONSTRUCTED FOR THE STATE.
• GANDHINAGAR GOT AN IDENTITY OF ITS OWN WHEN THE STATE OF MUMBAI WAS DIVIDED INTO TWO SEPARATE STATES OF GUJARAT AND MAHARASHTRA.
• IN THE BEGINNING, AHMEDABAD - A COMMERCIAL HUB OF GUJARAT WAS CHOSEN AS THE STATE CAPITAL AND IT WAS PROPOSED THAT A NEW CAPITAL SHOULD BE CONSTRUCTED ALONG THE LINE OF OTHER NEW STATE CAPITALS, PARTICULARLY CHANDIGARH
• THEREFORE TWO WELL-KNOWN INDIAN ARCHITECTS, H.K. MEWADA AND PRAKASH M. APTE (WHO WORKED AS BEGINNER FOR THE CHANDIGARH CITY) DESIGNED THE NEW STATE CAPITAL*
NAMED AFTER MAHATMA GANDHI THE FOUNDATION STONE OF THIS CITY WAS LAID ON 1965 AND IN 1971 THE CAPITAL WAS SHIFTED FROM AHMEDABAD TO GANDHINAGAR
PLANNING
• PLANNED AND IMPLEMENTED BETWEEN 1965-1970
• DETERMINATION TO MAKE GANDHINAGAR A PURELY INDIAN ENTERPRISE, PARTLY BECAUSE GUJARAT WAS THE BIRTHPLACE OF GANDHI.
• TO ESTABLISH AND MAINTAIN A SEPARATE IDENTITY FOR THE NEW CITY THE SURROUNDING AREA OF ABOUT 39 VILLAGES WAS BROUGHT UNDER A PERIPHERY CONTROL ACT (AS IN CHANDIGARH)
• THE AREA LATER CONSTITUTED A SEPARATE ADMINISTRATIVE DISTRICT OF GANDHINAGAR.
• THE CITY WAS PLANNED FOR A POPULATION OF 150,000 BUT CAN ACCOMMODATE DOUBLE THAT POPULATION WITH INCREASE IN THE FLOOR SPACE RATIO FROM 1 TO 2 IN THE AREAS RESERVED FOR PRIVATE DEVELOPMENT.
• THE RIVER BEING THE BORDER ON THE EAST, AND THE INDUSTRIAL AREA TO THE NORTH, THE MOST LOGICAL FUTURE PHYSICAL EXPANSION OF THE CITY WAS ENVISAGED TOWARDS THE NORTH-WEST
FINAL B.ARCH THESIS PRESENTATION IIT ROORKEE:
City Centre ,Rohini ,Delhi ,Thesis project (2013)
A Mixed use development project comprises of diverse activities and functions located at the
sprawling District centre in Rohini with site area of 16 acres.With a AIM to explore the symbiotic
character of COMMERCE and CULTURE and to evolve a contemporary model of conventional
Indian market.
Track & Trace System Barkode 2D : Penguatan Pengawasan Obat Berbasis Digital ...Stefanus Nofa
Solusi Digital Farmasi , sebuah konsep besar untuk masalah besar di bidang rantai pasok obat dan vaksin palsu.
Paparan ini menjadi dasar awal pengembangan & pembuatan Peraturan Badan POMNo. 33 Tahun 2018 Mengenai Penerapan 2D Barcode dalam Pengawasan Obat dan Makanan
Peraturan Badan POM No. 33 Tahun 2018 ini mengatur ketentuan dan tata laksana penerapan 2D Barcode dalam Produk Obat dan Makanan yang diedarkan di wilayah Indonesia. Peraturan dilengkapi dengan Lampiran Petunjuk teknis tentang alur kerja sistem pengawasan obat dan makanan berbasis digital (Track and Trace, Anti Counteirfeit control product System)
Track & Trace System Barkode 2D : Penguatan Pengawasan Obat Berbasis Digital oleh BPOM https://ttac.pom.go.id/
Tracxn Research — Investment Tech Landscape, October 2016Tracxn
A number of Asian companies are among top funded in the last one year - Guangzhou-based Zhiniu8 ($150M, Series C), Singapore-based M-DAQ ($95M, Series C), Beijing-based Jusfoun Big Data ($76M, Series C), and Shanghai-based Madai Licai ($65M, PE) accounted for the top investments in the last year.
Tracxn Research — Immuno-Oncology Landscape, September 2016Tracxn
In 2015/16, five startups in this space — Stemcentrx, Gritstone Oncology, Hengrui Therapeutics, and Zai Lab secured big ticket funding rounds of $100 million and above.
Tracxn Research — Big Data Infrastructure Landscape, September 2016Tracxn
Following a rather muted 2015, the year 2016 witnessed an impressive bounce back by the big data sector, with a total funding of $1.1B secured in 37 rounds.
Tracxn Research — Marketing Tech Landscape, September 2016Tracxn
The report covers companies that provide tools for marketers to create, manage and analyse their marketing campaigns across multiple channels ranging from email and social media to mobile.
Tracxn Startup Research — Life Sciences Landscape, October 2016Tracxn
There were 20+ acquisitions in this space in 2016; IBM’s $2.6B acquisition of Truven Analytics, and Affymetrix’s acquisition by Thermo Fisher Scientific for $1.6B were the largest M&A events for the sector this year.
Tracxn Research - 3D Printing Landscape, September 2016Tracxn
Healthcare, printer matching services, and marketplaces for 3D printed objects are some of the large business models emerging out of the 3D printing landscape, which has witnessed three of the largest years by funding from 2014 to 2016.
Transport planning is a science that study the problems that arise in proving transportation facilities in an urban, regional or national setting and to prepare a systematic basis for planning.
The principles of urban transport planning can be applied to regional or national transport planning as well with due changes.
Urban transport networks are no longer capable of accommodating the movement of road users and vehicles.
Levels of traffic overloading vary in time.
In city centres, motorised movements difficult and long-term car parking almost impossible because of narrow streets often accessible only to non-motorised traffic.
At present, there are many problems being faced by road users in urban area with limitation of land space and traffic congestion, pedestrian are one of the most vulnerable entities of the transportation system It is observed that there is an increase in number of conflicts between pedestrian and the vehicles in the city. In order to mitigate the conflicts between vehicular traffic and pedestrian traffic an attempt is made to provide a Skywalk. The present study involves the Opinion survey of pedestrians, Mid-block traffic count, pedestrian count were carried out for Ashoka road on weekdays and weekends. From the opinion survey, traffic count and pedestrian counts we can conclude that there is a need to construct Skywalk to reduce the pedestrian accidents rates on Ashoka road.
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...inventionjournals
A sidewalk as part of the road facilities to secure the pedestrian safety in Korea shall be provided when the pedestrian and vehicle traffic reach to a certain level but applying this regulation to the rural road where there are less pedestrian traffic but vehicle traffic at high speed and thus the driver's attention to the pedestrians is relatively low is not rational. Thus the installation of the sidewalk shall be determined, taking into account of the pedestrian traffic accident record and the characteristics from the viewpoint of traffic environment to the pedestrian. Installation of sidewalk is greatly dependent on economic efficiency, particularly to the rural road. For rational investment within the given budget, it's necessary to determine the priority with regard to sidewalk installation, considering the pedestrian safety, regional society's need and installation effect comprehensively. Thus this study is intended to propose the evaluation items and quantitative method with regard to the installation priority in consideration of the function of the road to be installed, regional social and cultural characteristics and overall road and traffic conditions such as pedestrian traffic pattern and school.
Analysis of the Pedestrian System In Jayapura City (A Case Study of Pedestria...ijceronline
Pedestrian line on Percetakan Street in Jayapura city still need to get handling to pedestrian performance. This study aims to analyze the characteristics of pedestrian traffic, to know the condition of pedestrian infrastructure and analyzing the pedestrian performance. This study uses qualitative descriptive method, Customer Satisfaction Index (CSI), Importance Performance Analysis (IPA) and service quality. The results showed that pedestrian traffic characteristic in segment 1 was average of 52 people/ hour, Segment 2 was on average 70 people/hour, and segment 3 was on average 82 people/hour. The condition of pedestrian facilities and equipment has not met the standard. Performance of pedestrian line according to CSI Customer Satisfaction Index at segment 1 CSI = 73.54%, segment 2 CSI = 68.44%. And segment 3 CSI = 59.35%. In the Importance Performance Analysis (IPA) diagram of the worst segment 3 indicator. Priority of handling of pedestrian performance indicated by service quality with lowest indicator value must be completed soon.
design of saperate lane for ambulance at high intensity traffic zone ElbichAkhtarkhan
data analysis, traffic volume studies, parking studies, separate lane for ambulance, data collection, geometric design, lane design using auto cad, traffic safety and public coordination, advantages and disadvantages
KAJANG LOCAL PLAN PROPOSAL/RESHMINDER KAURReshmi Kaur
Final Project under Sustainable Urban Design Course,4th Year Civil Engineering at UKM.Comprimising of sustainable development principles that can implemented or improved in Kajang for a better quality of life in Kajang.
TRAFFIC AND PEDESTRIAN MANAGEMENT FOR YESHWANTHPUR
1. TRAFFIC AND PEDESTRIAN MANAGEMENT FOR
YESHWANTHPUR
Project Interns : Pramod and Yashaswini
Guided by: N. Ramesh BabuTraffic and Pedestrian management
CiSTUP(Centre for Infrastructure, Sustainable Transport and Urban Planning),IISc,
Bangalore.
2. OUTLINEOUTLINETRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian assessment study
Objective and Scope of the Study
Introduction to the study area
Study area and its issues
Analysis and Proposals
1
2
Pedestrian Amenities
Public Transport Amenities
Pedestrian safety
Traffic Management at Congestion
points
OUTLINEOUTLINE
Traffic and Pedestrian management
3. OUTLINEOUTLINETRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian assessment study
OBJECTIVE & METHODOLOGYOBJECTIVE & METHODOLOGY
The objective of the study is
Traffic management and solving the pedestrian problems by suitable strategies
and measures for systematic functioning of the area
Traffic and Pedestrian management
PRESENTATION AND REPORT
FINAL PROPOSAL OF DESIGN
ANALYSING THE PROBLEMS AND TRAFFIC MANAGEMENT SOLUTIONS
IDENTIFYING THE ISSUES AND POTENTIALS
PRIMARY DATA COLLECTION
LITERATURE REVIEW AND SECONDARY DATA COLLECTION
PROBLEM IDENTIFICATION
4. SITE STUDYSITE STUDY
•Yeshwanthpur is a sub locality
in the north western part of
Bangalore City.
• It is located to the north of
Malleshwaram and west of
Hebbal.
•The biggest wholesale market
of agricultural produce, the
Yeshwanthpur APMC Yard, is
situated in Yeshwanthpur.
•Yeshwanthpur is 6km from
Bangalore City Railway
Station.
Yeshwanthpur
railway station
Govardhan Theatre
Maruthi Suzuki
Yeshwanthpur
santhe
Total gas
station
TRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian management
5. ACCIDENT STATSACCIDENT STATSTRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian management
INDIAN JOURNAL OF APPLIED RESEARCH
Volume : 3 | Issue : 9 | Sept 2013 | ISSN - 2249-555X
• A review on the road crash
analysis world over implies
that the human factor
attributes to the majority of
accidents.
• A similar instance has been
observed in India as well as
in Bangalore.
•A CRRI study says, In
Bangalore about 47% of
road users killed are
pedestrians & 40% are two-
wheeler users
6. MODES OF TRANSPORTMODES OF TRANSPORTTRAFFICANDPEDESTRIANMANAGEMENT
TRANSPORT
Bus - Bangalore Metropolitan Transport Corporation(BMTC) connects Yeshwanthpur
with various parts of the city. It has a Traffic Transit Management Center.
Rail- Yeshwanthpur railway station is a major railway terminal of South Western
Railway connecting to major rail heads in the country.
Bangalore Metro – Yeshwanthpur metro operates through Green line.
IPT there are autos, cabs.
CONNECTIVITY
Yeshwanthpur is well connected from all parts of Bangalore.
Traffic and Pedestrian management
11. EXISTING SCENARIOEXISTING SCENARIOTRAFFICANDPEDESTRIANMANAGEMENT
5
•The subway is towards only one side of the
road.
•Due to the lack of visibility the commuters
take the entrance which is facing the road
to reach the railway station.
•The existing subway being encroached by
street hawkers.
•Subway is being used as a parking space
for vehicles
•The choking of drainage pipes has
resulted in the burst and spillover, stinking
•No proper drainage , lighting and security
14. EXISTING CROSS SECTIONEXISTING CROSS SECTION
Waiting area has no covered shelter, or
seating, nor adequate lighting.
No zebra crossing or table tops for
crossing the road.
TRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian management
15. EXISTING CROSS SECTIONEXISTING CROSS SECTION
• Improper site design has lead to slower speeds, longer trip times and increased
vehicular queuing which results in traffic congestion.
Traffic and Pedestrian management
TRAFFICANDPEDESTRIANMANAGEMENT
16. PROVISIONSPROVISIONS
Designated bus shelters for private and government buses.
Connecting the subway from the either sides of the road.
Making continuous pedestrian pathways.
Environmental Sensitive landscaping.
Designated Auto stands.
Road Markings and Signage.
TRAFFICANDPEDESTRIANMANAGEMENT
21. PROPOSALS
By addressing issues such as:
•Natural storm water
management
•Ground water infiltration
•Excessive heat reflection
With the help for provision of:
•Increased plantation
•Use of heat absorbent material for paving
Green belt
Filtration bed
Anti reflective
paving material
use of trees to minimize
solar gain
PROPOSALS
Traffic and Pedestrian management
TRAFFICANDPEDESTRIANMANAGEMENT
Filtration bed
27. THINGS HAVE BEEN AVOIDTHINGS HAVE BEEN AVOIDED
Provision of zebra crossing/table tops
Pelican signals
Foot over bridge
Multiple entry points to railway station
TRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian management
28. REFERENCESREFERENCESTRAFFICANDPEDESTRIANMANAGEMENT
Traffic and Pedestrian management
•Enhancing the Performance of Public Transportation
•System by Effective Re-design, by Anuja Shukla
•Pedestrian and Bicycle Infrastructure in Indian cities, by Geetam Tiwari
•UTTIPEC, Delhi Development Authority, New Delhi, November 2009
•Sacramento Transportation and Air Quality Collaborative.
•IRC
•http://cistup.iisc.ernet.in
•Guidelines and low cost traffic management techniques for Urban areas(IRC)
29. “Some roads are born to be admired and born to be travelled!”
― Mehmet Murati ldan
THANK YOUCiSTUP, IISc, Bangalore.