TONGUE POINT BASIN CONSIDERATIONS
Roch Steinbach 6-27-16
After being knocked out by some recent research discussing the possibilities for reviving the PNW RR to Tongue Point,
with the assumed objective being, that a commercial port at Tongue Point Basin (TPB) is viable and more desirable than
reviving and upgrading the original Smith Point Terminal facility, as I have suggested, I’m here offering these overview
considerations, relative to the feasibility of a commercial cargo facility at TPB.
On the Tongue Point Basin berths, there are approximately six berths it looks like. Specs, such as they are, are here,
scroll down: http://www.portofastoria.com/Tongue_Point_General_Information.aspx Counting berths not piers or
docks, it looks like six with possibly a smaller one on the North end -- and another potential on the south, if someone
gets really busy with a dredge. In length and breadth they are comparable to the Smith Point Terminal berths I’ve
emphasized: approx. 1200 feet long and maybe 500-600 ft, wide – so fully adequate in dimension to handle the largest
container carrier. The picture below documents this, with a full-size (probably HANJIN) container vessel in the main
shipping channel, or probably anchored off it, near Tongue Point
One concern is the dimensions of the existing piers, as opposed to the berths: the piers are wooden tie-up piers, docks,
really, for mooring only. And of course as they stand, they are not serviceable as container piers. I’m presuming they
were constructed for the NAS usage during the WWII,; but in my reading, I know I’ve never found that the TPB ever
served to host commercial piers. One might ask, why not? I believe the mariners and engineers who situated Port of
Astoria facilities at Smith Point, had the advantage of a working knowledge of the harbor, when they selected and
developed this site. The fact that the Port of Astoria boomed for 20-30 years after the Smith Point Terminal piers were
constructed is a factor of economic history that has to be taken into consideration, I think.
One thing to consider, for instance, is that the TPB is oriented on the river like a “catchment” pointed upriver, and so it
is going to receive an unending delivery of silt from upriver, with no “clean-out” outlet, so it will require pretty regular
maintenance dredging. Dredging will be not just an initial cost, but an ongoing one, at any Tongue Point facility….
TO GET INTO COMERCIAL PRODCUTION, THREE OF THESE FILL BERTHS will need to be completely constructed to create
the square footage area for the erection and operation of container cranes, presumably automated ones, since 9/10ths
of being competitive is having the latest gear. These piers will have to be at least of the dimensions of the existing piers
at Smith Point. By my view, this leaves three, maybe four, ship berths remaining. I would suggest that the three piers
to be constructed, should definitely be laid out on a diagonal plan, opening much more to the NE, than as the existing
moorage piers are positioned, running a little north of due East. That way, vessels can “angle in” and “angle out” and
not be forced to cut a hairpin 180 to moor. So the layout should look like this:    , instead of as is : || || || as in
the picture above. This would streamline docking, and increase efficiency.
I see that the area behind (and west of) the TPB buildings (near the bottom of this aerial photo) is served by a PNW
siding: it appears the tracks may be up, and grade only remains. EITHER WAY one question is: can secondary sidings or
spurs be run out towards the piers off this existing siding? Here my question centers around the angle at which a spur
would have to veer, to run off the existing siding/grade in order to properly serve whatever pier would be constructed….
(There is of course a lower limit to the turn radius of a string of rail cars, although single cars can often manage tight
turns, I believe.) If we are contemplating rail-shipment to Portland with a terminal at Tongue Point, the spurs
referenced above, can better serve the three newly filled piers, if the entire development is angled NE:   . This is
a question concerning ultimate economic viability of the TPB proposal, if railcars might be obliged to move at only a
reduced speed, in order to accommodate tight turn radii on these spurs: capacity in terms of the number of
railcars/containers per day could be affected. Can they move fast enough? The question arises whether TPB would be
a 19th
C. facility trying to compete in the 21st
C.
This picture may help to illustrate the considerations mentioned. The two container vessels shown at upper left, are
anchored in Coast Guard designated anchorages, off the main shipping channel. Tongue Point obviously is near the
center of the photo and the TPB with its six piers opening ENE are toward the right. The piers in this image are outlined
with a red perimeter drawn along the waterfront by Google – so they look far more substantial than they should at this
altitude. IN fact one of them is not outlined, and is nearly invisible at this altitude. The large container cargo vessels do
not turn easily, and so will have to be maneuvered upriver and then back, or turned very slowly, in order to bring them
around Tongue Point and back down into the TPB. With this in mind, we can further see the desirability – actually, the
necessity -- of angling new solid-state piers much more to the NE, so that their angle more approximates the angle of
the back of Tongue Point itself, and the new shipping channel runs more or less parallel to it. This will streamline the
maneuvers that container vessels must make to get into TPB.
We can also see plainly the real concerns referenced regarding the infiltration and catchment of silt in this area. For
instance, MOTT ISLAND immediately upriver from the TPB, is a product of such siltation, and in fact lies in the TPB itself.
It will have to be largely removed, certainly if new piers are not re-oriented as suggested. Elsewhere upriver in this area
(called the Cathlamet Basin on many old maps), the effects of siltng are manifest in various marshy islands, much of it
wildfowl habitat. While I believe this TPB area is appropriate for future development of the Port of Astoria, is it really
the place to start? And after these three piers are constructed, where will the facility expand, if it is successful? The
physical, hydrological and logistical limitations suggest that TPB may be a quick approach to a dead-end port facility.
COMPARE HOWEVER, the location and orientation of the existing piers at Smith Point, not only directly on the shipping
channel, but also perfectly, even ideally oriented almost as extension of the Tansy Point “Reach” of river navigation…
BY CONTRAST, the existing original Astoria waterfront reclamation through the construction of these three still
monstrous piers, demonstrates the results of working – not speculative -- insights that appeared to be self-evident to
mariners a century ago: the shipping channel runs directly along the Astoria waterfront, and to realize the greatest
economic efficiencies, one need only create an accommodation for vessels that are ALEADY THERE. At Smith Point.
Every vessel of any commercial consequence, that enter the Columbia River, passes this point, no matter where else
they are headed. This, and not overpaid management and a controlled municipal media, and a wastrel federal dredging
project, 100 miles long, caused Astoria to boom. See, ASTORIA ONLY PART I .
Compare, for instance, the likely cost of dredging the downriver (left) side of Pier 3, at Smith Point, above, to bring all
three pies into full operation, with the cost of building three entirely new piers at TPB, and dredging anywhere and
everywhere around there, partially removing Mott island, etc., in order to reach the same starting point.
Also consider, that after three piers are built at TPB, there is no place to expand to without construction of another
completely new facility. Meanwhile, at Smith Point, the three existing piers are large enough to accommodate
automated container cranes, have shown to be viably linked by rail, and served by sidings, and furthermore there is
around Smith Point, room for expansion for another four piers, bringing the total of working piers with historically
proven economic potential, to seven. See ASTORIA ONLY PART II
Those are a few points to consider, in evaluating the proposal that TPB might be a real alternative to Smith Point.

More Related Content

Viewers also liked

Viewers also liked (11)

Partes del navegador google chrome
Partes del navegador google chromePartes del navegador google chrome
Partes del navegador google chrome
 
Document Management, SaaS, Cloud Computing
Document Management, SaaS, Cloud ComputingDocument Management, SaaS, Cloud Computing
Document Management, SaaS, Cloud Computing
 
Derechos de autor_TIC
Derechos de autor_TICDerechos de autor_TIC
Derechos de autor_TIC
 
Gestão material dos stocks
Gestão material dos stocksGestão material dos stocks
Gestão material dos stocks
 
RSS Reader: Complete integration within IBM Lotus Notes client
RSS Reader: Complete integration within IBM Lotus Notes clientRSS Reader: Complete integration within IBM Lotus Notes client
RSS Reader: Complete integration within IBM Lotus Notes client
 
Ejercicio computación en la nube
Ejercicio computación en la nubeEjercicio computación en la nube
Ejercicio computación en la nube
 
Tactics for Implementing Test Automation for Legacy Code
Tactics for Implementing Test Automation for Legacy CodeTactics for Implementing Test Automation for Legacy Code
Tactics for Implementing Test Automation for Legacy Code
 
Manual tic parte1
Manual tic parte1Manual tic parte1
Manual tic parte1
 
Prevenção de Acidentes de Trabalho
Prevenção de Acidentes de TrabalhoPrevenção de Acidentes de Trabalho
Prevenção de Acidentes de Trabalho
 
Live Testing A Legacy App
Live Testing A Legacy AppLive Testing A Legacy App
Live Testing A Legacy App
 
Prevenção de acidentes pjf3
Prevenção de acidentes pjf3Prevenção de acidentes pjf3
Prevenção de acidentes pjf3
 

Similar to TONGUE POINT BASIN CONSIDERATIONS

KNOW YOUR ASTORIA
KNOW YOUR ASTORIAKNOW YOUR ASTORIA
KNOW YOUR ASTORIA
Roch Steinbach
 
Willamette Falls Locks (WFL) reasoning
Willamette Falls Locks (WFL) reasoningWillamette Falls Locks (WFL) reasoning
Willamette Falls Locks (WFL) reasoning
Scott Schlatter
 
A Mulligan for Capesize Owners ?
A Mulligan for Capesize Owners ?A Mulligan for Capesize Owners ?
A Mulligan for Capesize Owners ?
GE 94
 

Similar to TONGUE POINT BASIN CONSIDERATIONS (9)

KNOW YOUR ASTORIA
KNOW YOUR ASTORIAKNOW YOUR ASTORIA
KNOW YOUR ASTORIA
 
6565165455566666665161-PORT-OPERATIONS.ppt
6565165455566666665161-PORT-OPERATIONS.ppt6565165455566666665161-PORT-OPERATIONS.ppt
6565165455566666665161-PORT-OPERATIONS.ppt
 
Willamette Falls Locks (WFL) reasoning
Willamette Falls Locks (WFL) reasoningWillamette Falls Locks (WFL) reasoning
Willamette Falls Locks (WFL) reasoning
 
ports cautious investment
ports cautious investmentports cautious investment
ports cautious investment
 
Port arrastre, logistics and traffic management
Port arrastre, logistics and traffic managementPort arrastre, logistics and traffic management
Port arrastre, logistics and traffic management
 
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design reportRoyal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
 
A Mulligan for Capesize Owners ?
A Mulligan for Capesize Owners ?A Mulligan for Capesize Owners ?
A Mulligan for Capesize Owners ?
 
Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...
 
PowerLogistics Asia 2014 - Combining Experience, Know - How & Equipment - Jon...
PowerLogistics Asia 2014 - Combining Experience, Know - How & Equipment - Jon...PowerLogistics Asia 2014 - Combining Experience, Know - How & Equipment - Jon...
PowerLogistics Asia 2014 - Combining Experience, Know - How & Equipment - Jon...
 

More from Roch Steinbach

PYM PUZZLER -- MISSING PERSONS !!
PYM PUZZLER -- MISSING PERSONS !! PYM PUZZLER -- MISSING PERSONS !!
PYM PUZZLER -- MISSING PERSONS !!
Roch Steinbach
 
TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
 TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
Roch Steinbach
 
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
Roch Steinbach
 
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPTDRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
Roch Steinbach
 
PYM PUZZLER -- CAUGHT ON TYPE !!
PYM PUZZLER -- CAUGHT ON TYPE !!PYM PUZZLER -- CAUGHT ON TYPE !!
PYM PUZZLER -- CAUGHT ON TYPE !!
Roch Steinbach
 
YANKEE SCOUT -- MINE RUN !!
YANKEE SCOUT -- MINE RUN !! YANKEE SCOUT -- MINE RUN !!
YANKEE SCOUT -- MINE RUN !!
Roch Steinbach
 
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOKMcNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
Roch Steinbach
 

More from Roch Steinbach (20)

PYM PUZZLER -- MISSING PERSONS !!
PYM PUZZLER -- MISSING PERSONS !! PYM PUZZLER -- MISSING PERSONS !!
PYM PUZZLER -- MISSING PERSONS !!
 
DESCRIPTION OF THE MOUTH OF THE COLUMBIA RIVER -- Capt. Wm. Black (1813)
DESCRIPTION OF THE MOUTH OF THE COLUMBIA RIVER -- Capt. Wm. Black  (1813) DESCRIPTION OF THE MOUTH OF THE COLUMBIA RIVER -- Capt. Wm. Black  (1813)
DESCRIPTION OF THE MOUTH OF THE COLUMBIA RIVER -- Capt. Wm. Black (1813)
 
IT'S ALL IN THE MINES !! -- RE-OPEN THE BUREAU OF MINES
IT'S ALL IN THE MINES !! -- RE-OPEN THE BUREAU OF MINESIT'S ALL IN THE MINES !! -- RE-OPEN THE BUREAU OF MINES
IT'S ALL IN THE MINES !! -- RE-OPEN THE BUREAU OF MINES
 
HOOVER'S BUILDING CODE COMMITTEE REPORT -- 1925
HOOVER'S BUILDING CODE COMMITTEE REPORT -- 1925HOOVER'S BUILDING CODE COMMITTEE REPORT -- 1925
HOOVER'S BUILDING CODE COMMITTEE REPORT -- 1925
 
SYM-ZONIA -- TRUE LOCK !!!
SYM-ZONIA -- TRUE LOCK !!!SYM-ZONIA -- TRUE LOCK !!!
SYM-ZONIA -- TRUE LOCK !!!
 
TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
 TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
TONY CHAITKIN: THE COUP -- KENNEDY & TRUMP: THEN & NOW
 
CAPT. GEO FLAVEL -- WRECK & PERIL OF THE GEN'L WARREN -- LONG FORM
CAPT. GEO FLAVEL -- WRECK & PERIL OF THE GEN'L WARREN -- LONG FORMCAPT. GEO FLAVEL -- WRECK & PERIL OF THE GEN'L WARREN -- LONG FORM
CAPT. GEO FLAVEL -- WRECK & PERIL OF THE GEN'L WARREN -- LONG FORM
 
PYM PUZZLER --BY POPULAR DEMAND !!
PYM PUZZLER --BY POPULAR DEMAND !!PYM PUZZLER --BY POPULAR DEMAND !!
PYM PUZZLER --BY POPULAR DEMAND !!
 
THE ALBATROSS IFFIGY -- PART III
THE ALBATROSS IFFIGY -- PART IIITHE ALBATROSS IFFIGY -- PART III
THE ALBATROSS IFFIGY -- PART III
 
YANKEE SCOUT -- FUGITIVE SLAVE !!
YANKEE SCOUT -- FUGITIVE SLAVE !! YANKEE SCOUT -- FUGITIVE SLAVE !!
YANKEE SCOUT -- FUGITIVE SLAVE !!
 
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
YANKEE SCOUT -- CONFEDERATE CHRISTMAS !!
 
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPTDRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
DRAFT ONLY -- PROPOSAL FOR A RE-ORGANIZED COMMERCE DEPT
 
PYM PUZZLER -- CAUGHT ON TYPE !!
PYM PUZZLER -- CAUGHT ON TYPE !!PYM PUZZLER -- CAUGHT ON TYPE !!
PYM PUZZLER -- CAUGHT ON TYPE !!
 
SYM-ZONIA -- WATERSHED MOMENT !!
SYM-ZONIA -- WATERSHED MOMENT !!SYM-ZONIA -- WATERSHED MOMENT !!
SYM-ZONIA -- WATERSHED MOMENT !!
 
SYM-ZONIA -- PARADIDDLE !!
SYM-ZONIA -- PARADIDDLE !!SYM-ZONIA -- PARADIDDLE !!
SYM-ZONIA -- PARADIDDLE !!
 
SYM-ZONIA -- DRAIN !!
SYM-ZONIA -- DRAIN !! SYM-ZONIA -- DRAIN !!
SYM-ZONIA -- DRAIN !!
 
YANKEE SCOUT -- MINE RUN !!
YANKEE SCOUT -- MINE RUN !! YANKEE SCOUT -- MINE RUN !!
YANKEE SCOUT -- MINE RUN !!
 
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOKMcNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
McNARY-HAUGEN -- 1927 HIGH SCHOOL DEBATE HANDBOOK
 
SYM-ZONIA -- SPELLCHECK
SYM-ZONIA -- SPELLCHECKSYM-ZONIA -- SPELLCHECK
SYM-ZONIA -- SPELLCHECK
 
YANKEE SCOUT -- THE CONFISCATED GOOSE !
YANKEE SCOUT -- THE CONFISCATED GOOSE !YANKEE SCOUT -- THE CONFISCATED GOOSE !
YANKEE SCOUT -- THE CONFISCATED GOOSE !
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
Kamal Acharya
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
Atif Razi
 

Recently uploaded (20)

İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 

TONGUE POINT BASIN CONSIDERATIONS

  • 1. TONGUE POINT BASIN CONSIDERATIONS Roch Steinbach 6-27-16 After being knocked out by some recent research discussing the possibilities for reviving the PNW RR to Tongue Point, with the assumed objective being, that a commercial port at Tongue Point Basin (TPB) is viable and more desirable than reviving and upgrading the original Smith Point Terminal facility, as I have suggested, I’m here offering these overview considerations, relative to the feasibility of a commercial cargo facility at TPB. On the Tongue Point Basin berths, there are approximately six berths it looks like. Specs, such as they are, are here, scroll down: http://www.portofastoria.com/Tongue_Point_General_Information.aspx Counting berths not piers or docks, it looks like six with possibly a smaller one on the North end -- and another potential on the south, if someone gets really busy with a dredge. In length and breadth they are comparable to the Smith Point Terminal berths I’ve emphasized: approx. 1200 feet long and maybe 500-600 ft, wide – so fully adequate in dimension to handle the largest container carrier. The picture below documents this, with a full-size (probably HANJIN) container vessel in the main shipping channel, or probably anchored off it, near Tongue Point One concern is the dimensions of the existing piers, as opposed to the berths: the piers are wooden tie-up piers, docks, really, for mooring only. And of course as they stand, they are not serviceable as container piers. I’m presuming they were constructed for the NAS usage during the WWII,; but in my reading, I know I’ve never found that the TPB ever served to host commercial piers. One might ask, why not? I believe the mariners and engineers who situated Port of Astoria facilities at Smith Point, had the advantage of a working knowledge of the harbor, when they selected and developed this site. The fact that the Port of Astoria boomed for 20-30 years after the Smith Point Terminal piers were constructed is a factor of economic history that has to be taken into consideration, I think. One thing to consider, for instance, is that the TPB is oriented on the river like a “catchment” pointed upriver, and so it is going to receive an unending delivery of silt from upriver, with no “clean-out” outlet, so it will require pretty regular maintenance dredging. Dredging will be not just an initial cost, but an ongoing one, at any Tongue Point facility….
  • 2. TO GET INTO COMERCIAL PRODCUTION, THREE OF THESE FILL BERTHS will need to be completely constructed to create the square footage area for the erection and operation of container cranes, presumably automated ones, since 9/10ths of being competitive is having the latest gear. These piers will have to be at least of the dimensions of the existing piers at Smith Point. By my view, this leaves three, maybe four, ship berths remaining. I would suggest that the three piers to be constructed, should definitely be laid out on a diagonal plan, opening much more to the NE, than as the existing moorage piers are positioned, running a little north of due East. That way, vessels can “angle in” and “angle out” and not be forced to cut a hairpin 180 to moor. So the layout should look like this: , instead of as is : || || || as in the picture above. This would streamline docking, and increase efficiency. I see that the area behind (and west of) the TPB buildings (near the bottom of this aerial photo) is served by a PNW siding: it appears the tracks may be up, and grade only remains. EITHER WAY one question is: can secondary sidings or spurs be run out towards the piers off this existing siding? Here my question centers around the angle at which a spur would have to veer, to run off the existing siding/grade in order to properly serve whatever pier would be constructed…. (There is of course a lower limit to the turn radius of a string of rail cars, although single cars can often manage tight turns, I believe.) If we are contemplating rail-shipment to Portland with a terminal at Tongue Point, the spurs referenced above, can better serve the three newly filled piers, if the entire development is angled NE: . This is a question concerning ultimate economic viability of the TPB proposal, if railcars might be obliged to move at only a reduced speed, in order to accommodate tight turn radii on these spurs: capacity in terms of the number of railcars/containers per day could be affected. Can they move fast enough? The question arises whether TPB would be a 19th C. facility trying to compete in the 21st C.
  • 3. This picture may help to illustrate the considerations mentioned. The two container vessels shown at upper left, are anchored in Coast Guard designated anchorages, off the main shipping channel. Tongue Point obviously is near the center of the photo and the TPB with its six piers opening ENE are toward the right. The piers in this image are outlined with a red perimeter drawn along the waterfront by Google – so they look far more substantial than they should at this altitude. IN fact one of them is not outlined, and is nearly invisible at this altitude. The large container cargo vessels do not turn easily, and so will have to be maneuvered upriver and then back, or turned very slowly, in order to bring them around Tongue Point and back down into the TPB. With this in mind, we can further see the desirability – actually, the necessity -- of angling new solid-state piers much more to the NE, so that their angle more approximates the angle of the back of Tongue Point itself, and the new shipping channel runs more or less parallel to it. This will streamline the maneuvers that container vessels must make to get into TPB. We can also see plainly the real concerns referenced regarding the infiltration and catchment of silt in this area. For instance, MOTT ISLAND immediately upriver from the TPB, is a product of such siltation, and in fact lies in the TPB itself. It will have to be largely removed, certainly if new piers are not re-oriented as suggested. Elsewhere upriver in this area (called the Cathlamet Basin on many old maps), the effects of siltng are manifest in various marshy islands, much of it wildfowl habitat. While I believe this TPB area is appropriate for future development of the Port of Astoria, is it really the place to start? And after these three piers are constructed, where will the facility expand, if it is successful? The physical, hydrological and logistical limitations suggest that TPB may be a quick approach to a dead-end port facility. COMPARE HOWEVER, the location and orientation of the existing piers at Smith Point, not only directly on the shipping channel, but also perfectly, even ideally oriented almost as extension of the Tansy Point “Reach” of river navigation…
  • 4. BY CONTRAST, the existing original Astoria waterfront reclamation through the construction of these three still monstrous piers, demonstrates the results of working – not speculative -- insights that appeared to be self-evident to mariners a century ago: the shipping channel runs directly along the Astoria waterfront, and to realize the greatest economic efficiencies, one need only create an accommodation for vessels that are ALEADY THERE. At Smith Point. Every vessel of any commercial consequence, that enter the Columbia River, passes this point, no matter where else they are headed. This, and not overpaid management and a controlled municipal media, and a wastrel federal dredging project, 100 miles long, caused Astoria to boom. See, ASTORIA ONLY PART I . Compare, for instance, the likely cost of dredging the downriver (left) side of Pier 3, at Smith Point, above, to bring all three pies into full operation, with the cost of building three entirely new piers at TPB, and dredging anywhere and everywhere around there, partially removing Mott island, etc., in order to reach the same starting point. Also consider, that after three piers are built at TPB, there is no place to expand to without construction of another completely new facility. Meanwhile, at Smith Point, the three existing piers are large enough to accommodate automated container cranes, have shown to be viably linked by rail, and served by sidings, and furthermore there is around Smith Point, room for expansion for another four piers, bringing the total of working piers with historically proven economic potential, to seven. See ASTORIA ONLY PART II Those are a few points to consider, in evaluating the proposal that TPB might be a real alternative to Smith Point.