INTRODUCTION
• Thrissur Railway Station – commenced on June 2, 1902
• A-1 category railway station located in Thrissur City.
• It lies on the busy Shoranur – Cochin Harbour section.
• Also connects to the temple town of Guruvayur.
• 65 pairs of trains passes through the station on an
average day.
• Have a traffic of 20,000 passengers per day.
NEED ANALYSIS
• Growth of passenger traffic.
• New trains are coming – Budget 2013.
• Ernakulam - Thrissur MEMU will start running.
• 3rd
and 4th
rails have been started using.
• Passengers have to cross the rail to reach 4th
platform.
• Passengers have to walk a lot of distance to get bus
towards North stand or Sakthan stand.
SUMMARY
• Development of Thrissur railway station.
• To supply necessary facilities for the comfort of
increasing passengers.
• To provide platform facilities for increasing number of
trains and passengers.
OBJECTIVES
• Development of 4th
platform
▫ Shops and Benches
▫ Flooring
▫ Structure
▫ Roofing
▫ Lighting
▫ Drinking Water Supply
▫ Cctv cameras
▫ Announcement System
• Foot over bridge
• Bus service
First and Second
platform, of Thrissur
Railway Station
Fourth Platform
TECHNICAL FEASIBILITY
• Foot over bridge from fourth platform can be connected
to the existing bridge.
• Buses doesn’t have a much difference in their travel
distance and time.
SOCICAL FEASIBILITY
• No need of acquiring land.
• Useful for People
FINANCIAL FEASIBILTY
• Source of income – Palghat Railway division
• Secondary source - Budget
BUDGET AND DURATION
• Estimated Cost = 2 Crore
• Estimated Time = 10 Months
5%
75%
15%
5%
Work Cost(Lakhs)
Design 10
Bus service system 10
Shops and Benches 10
Flooring Works 30
Plumbing Works for water supply 10
Foot Over bridge Construction 30
Roofing Works, Structure 80
Lighting, Announcement sys,CCtv 20
Total 200
Activity Work Time in months
A Design of Overall Plan 2
B Approval 1
C Tender 2
D Bus service system 2
E Shops and Benches 2
F Flooring Works 2
G Plumbing Works for water supply 2
H Foot Over bridge Construction 2
I Roofing Works, Structure 4
J Lighting, Announcement sys,CCtv 1
MASTER SCHEDULE
GANTT CHART
0 1 2 3 4 5 6 7 8 9 10
TIME IN MONTHS
WORK PACKAGES
Approval (B)
Plumbing Works(G)
Structure, Roofing Works(I)
Lighting, CCtv(J)
Bus service (D)
Design of Overall Plan (A)
Over bridge (H)
Tender (C)
Shops and Benches(E)
Flooring Works(F)
WORK BREAK DOWN STRUCTURE
Development
Project
Over bridge
Construction
Bus Service
Shops and
Benches
Project
Development
Platform
Construction
Data collection Waiting Shed
Flooring,
Plumbing
Structure,
Roofing
Lighting, Cctv,
Announcement sys.
Analysis
Feasibility study
Structure
Roof
Approval
Sanction
Tender
General Manager
(Southern
Railway)
Electrical
engineer
Civil engineer
Finance officer
Supervisor
Chief Administrative
Officer
Project Committee
Administrative
manager
Office staff
Assistants
supervisor
WorkersOffice staff
Workers
Ex. Engineer
PROJECT ORGANISATION STRUCTURE
Project Manager
ADVANTAGES
• A new development for the station.
• Improves comfort of passengers.
• Improves safety of passengers.
CONCLUSION
• Simple
• Executable
Thrissur railway station development 2

More Related Content

What's hot

Berlin hauptbanhof central railway
Berlin hauptbanhof central railwayBerlin hauptbanhof central railway
Berlin hauptbanhof central railway
Sneha Lata
 
10 most amazing railway stations in the world
10 most amazing railway stations in the world10 most amazing railway stations in the world
10 most amazing railway stations in the world
Md. Nural Hoque Amin
 
Designing Kong Kong: Tsim Sha Tsui terminus design illustrations
Designing Kong Kong: Tsim Sha Tsui terminus design illustrationsDesigning Kong Kong: Tsim Sha Tsui terminus design illustrations
Designing Kong Kong: Tsim Sha Tsui terminus design illustrations
DesigningHongKong
 
TANA RAILWAY BRIDGE
TANA RAILWAY BRIDGETANA RAILWAY BRIDGE
TANA RAILWAY BRIDGE
Andrew Kago
 

What's hot (20)

Railway Station Design 251115
Railway Station Design 251115Railway Station Design 251115
Railway Station Design 251115
 
Railway station
Railway stationRailway station
Railway station
 
Berlin hauptbanhof central railway
Berlin hauptbanhof central railwayBerlin hauptbanhof central railway
Berlin hauptbanhof central railway
 
Railway engineering 3-presentation
Railway engineering 3-presentationRailway engineering 3-presentation
Railway engineering 3-presentation
 
10 most amazing railway stations in the world
10 most amazing railway stations in the world10 most amazing railway stations in the world
10 most amazing railway stations in the world
 
Denver union station
Denver union stationDenver union station
Denver union station
 
Union station
Union stationUnion station
Union station
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 
Kashmere gate isbt
Kashmere gate isbtKashmere gate isbt
Kashmere gate isbt
 
Chennai mofussil bus terminal
Chennai mofussil bus terminalChennai mofussil bus terminal
Chennai mofussil bus terminal
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
Geeta mandir bus port
Geeta mandir bus portGeeta mandir bus port
Geeta mandir bus port
 
Ad bus terminal chennai
Ad bus terminal chennaiAd bus terminal chennai
Ad bus terminal chennai
 
Rail transport
Rail transportRail transport
Rail transport
 
Designing Kong Kong: Tsim Sha Tsui terminus design illustrations
Designing Kong Kong: Tsim Sha Tsui terminus design illustrationsDesigning Kong Kong: Tsim Sha Tsui terminus design illustrations
Designing Kong Kong: Tsim Sha Tsui terminus design illustrations
 
Ropeway
RopewayRopeway
Ropeway
 
Planning principles of Railways Engineering
Planning principles of Railways EngineeringPlanning principles of Railways Engineering
Planning principles of Railways Engineering
 
Indian Freight Trains
Indian Freight TrainsIndian Freight Trains
Indian Freight Trains
 
Presentation on Railway STATION LAYOUT
Presentation on  Railway STATION LAYOUTPresentation on  Railway STATION LAYOUT
Presentation on Railway STATION LAYOUT
 
TANA RAILWAY BRIDGE
TANA RAILWAY BRIDGETANA RAILWAY BRIDGE
TANA RAILWAY BRIDGE
 

Viewers also liked

Quantitative Analysis From Ftir
Quantitative Analysis From FtirQuantitative Analysis From Ftir
Quantitative Analysis From Ftir
guest824336
 
Hcm721 fms railway station in ipoh&kl awatif 300615
Hcm721 fms railway station in ipoh&kl awatif 300615Hcm721 fms railway station in ipoh&kl awatif 300615
Hcm721 fms railway station in ipoh&kl awatif 300615
Umairah Alias
 

Viewers also liked (20)

The City Connector- Kharagpur
The City Connector- KharagpurThe City Connector- Kharagpur
The City Connector- Kharagpur
 
Multitouch: FTIR
Multitouch: FTIRMultitouch: FTIR
Multitouch: FTIR
 
Presentation for Railway Kamlapur Station (Branding Scopes)
Presentation for Railway Kamlapur Station (Branding Scopes)Presentation for Railway Kamlapur Station (Branding Scopes)
Presentation for Railway Kamlapur Station (Branding Scopes)
 
TESTS TO SIMULATE AGEING OF BITUMEN
TESTS TO SIMULATE AGEING OF BITUMEN TESTS TO SIMULATE AGEING OF BITUMEN
TESTS TO SIMULATE AGEING OF BITUMEN
 
Analyzing Chemical Composition of Rigid Polyurethane (PU) Foams Using FTIR Mi...
Analyzing Chemical Composition of Rigid Polyurethane (PU) Foams Using FTIR Mi...Analyzing Chemical Composition of Rigid Polyurethane (PU) Foams Using FTIR Mi...
Analyzing Chemical Composition of Rigid Polyurethane (PU) Foams Using FTIR Mi...
 
Quantitative Analysis From Ftir
Quantitative Analysis From FtirQuantitative Analysis From Ftir
Quantitative Analysis From Ftir
 
Asian Bitumen Conference , Nov 2011 Singapore , Presentation by Benzene Inter...
Asian Bitumen Conference , Nov 2011 Singapore , Presentation by Benzene Inter...Asian Bitumen Conference , Nov 2011 Singapore , Presentation by Benzene Inter...
Asian Bitumen Conference , Nov 2011 Singapore , Presentation by Benzene Inter...
 
Bitumen and modified bitumen
Bitumen and modified bitumenBitumen and modified bitumen
Bitumen and modified bitumen
 
Aging of bitumen
Aging of bitumenAging of bitumen
Aging of bitumen
 
FTIR
FTIRFTIR
FTIR
 
Train Station: A Case Study
Train Station: A Case StudyTrain Station: A Case Study
Train Station: A Case Study
 
Dispersive & FTIR
Dispersive & FTIRDispersive & FTIR
Dispersive & FTIR
 
Aging of bitumen
Aging of bitumenAging of bitumen
Aging of bitumen
 
Stations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stationsStations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stations
 
Core shell nanostructures
Core shell nanostructuresCore shell nanostructures
Core shell nanostructures
 
Surface modification of nanomaterials
Surface modification of nanomaterialsSurface modification of nanomaterials
Surface modification of nanomaterials
 
Introduction to Railway Signalling
Introduction to Railway SignallingIntroduction to Railway Signalling
Introduction to Railway Signalling
 
Ftir
FtirFtir
Ftir
 
Region II: Cagayan Valley
Region II: Cagayan Valley Region II: Cagayan Valley
Region II: Cagayan Valley
 
Hcm721 fms railway station in ipoh&kl awatif 300615
Hcm721 fms railway station in ipoh&kl awatif 300615Hcm721 fms railway station in ipoh&kl awatif 300615
Hcm721 fms railway station in ipoh&kl awatif 300615
 

Similar to Thrissur railway station development 2

Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
Crosstown TO
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
Crosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
Crosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
Crosstown TO
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
Crosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
Crosstown TO
 

Similar to Thrissur railway station development 2 (20)

Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Integrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureIntegrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's future
 
TFL Presentation
TFL Presentation TFL Presentation
TFL Presentation
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 

Recently uploaded

Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
soniyagrag336
 
TriStar Gold- 05-13-2024 corporate presentation
TriStar Gold- 05-13-2024 corporate presentationTriStar Gold- 05-13-2024 corporate presentation
TriStar Gold- 05-13-2024 corporate presentation
Adnet Communications
 
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Klinik kandungan
 
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
soniyagrag336
 

Recently uploaded (20)

cost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptxcost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptx
 
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
 
fundamentals of corporate finance 11th canadian edition test bank.docx
fundamentals of corporate finance 11th canadian edition test bank.docxfundamentals of corporate finance 11th canadian edition test bank.docx
fundamentals of corporate finance 11th canadian edition test bank.docx
 
Retail sector trends for 2024 | European Business Review
Retail sector trends for 2024  | European Business ReviewRetail sector trends for 2024  | European Business Review
Retail sector trends for 2024 | European Business Review
 
No 1 Top Love marriage specialist baba ji amil baba kala ilam powerful vashik...
No 1 Top Love marriage specialist baba ji amil baba kala ilam powerful vashik...No 1 Top Love marriage specialist baba ji amil baba kala ilam powerful vashik...
No 1 Top Love marriage specialist baba ji amil baba kala ilam powerful vashik...
 
Webinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumWebinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech Belgium
 
Call Girl In Siliguri 💯Niamh 📲🔝6378878445🔝Call Girls No💰Advance Cash On Deliv...
Call Girl In Siliguri 💯Niamh 📲🔝6378878445🔝Call Girls No💰Advance Cash On Deliv...Call Girl In Siliguri 💯Niamh 📲🔝6378878445🔝Call Girls No💰Advance Cash On Deliv...
Call Girl In Siliguri 💯Niamh 📲🔝6378878445🔝Call Girls No💰Advance Cash On Deliv...
 
Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
Sonagachi % High Profile Call Girls in Kolkata Real photos of Female Escorts ...
 
asli amil baba bengali black magic kala jadu expert in uk usa canada france c...
asli amil baba bengali black magic kala jadu expert in uk usa canada france c...asli amil baba bengali black magic kala jadu expert in uk usa canada france c...
asli amil baba bengali black magic kala jadu expert in uk usa canada france c...
 
Black magic specialist in Saudi Arabia (Kala jadu expert in UK) Bangali Amil ...
Black magic specialist in Saudi Arabia (Kala jadu expert in UK) Bangali Amil ...Black magic specialist in Saudi Arabia (Kala jadu expert in UK) Bangali Amil ...
Black magic specialist in Saudi Arabia (Kala jadu expert in UK) Bangali Amil ...
 
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
 
Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...
 
black magic removal amil baba in pakistan karachi islamabad america canada uk...
black magic removal amil baba in pakistan karachi islamabad america canada uk...black magic removal amil baba in pakistan karachi islamabad america canada uk...
black magic removal amil baba in pakistan karachi islamabad america canada uk...
 
Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024
 
TriStar Gold- 05-13-2024 corporate presentation
TriStar Gold- 05-13-2024 corporate presentationTriStar Gold- 05-13-2024 corporate presentation
TriStar Gold- 05-13-2024 corporate presentation
 
Shrambal_Distributors_Newsletter_May-2024.pdf
Shrambal_Distributors_Newsletter_May-2024.pdfShrambal_Distributors_Newsletter_May-2024.pdf
Shrambal_Distributors_Newsletter_May-2024.pdf
 
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
Jual obat aborsi Jogja ( 085657271886 ) Cytote pil telat bulan penggugur kand...
 
DIGITAL COMMERCE SHAPE VIETNAMESE SHOPPING HABIT IN 4.0 INDUSTRY
DIGITAL COMMERCE SHAPE VIETNAMESE SHOPPING HABIT IN 4.0 INDUSTRYDIGITAL COMMERCE SHAPE VIETNAMESE SHOPPING HABIT IN 4.0 INDUSTRY
DIGITAL COMMERCE SHAPE VIETNAMESE SHOPPING HABIT IN 4.0 INDUSTRY
 
najoomi asli amil baba kala jadu expert rawalpindi bangladesh uk usa
najoomi asli amil baba kala jadu expert rawalpindi bangladesh uk usanajoomi asli amil baba kala jadu expert rawalpindi bangladesh uk usa
najoomi asli amil baba kala jadu expert rawalpindi bangladesh uk usa
 
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
Sealdah $ Cheap Call Girls In Kolkata ₹7.5k Pick Up & Drop With Cash Payment ...
 

Thrissur railway station development 2

  • 2. INTRODUCTION • Thrissur Railway Station – commenced on June 2, 1902 • A-1 category railway station located in Thrissur City. • It lies on the busy Shoranur – Cochin Harbour section. • Also connects to the temple town of Guruvayur. • 65 pairs of trains passes through the station on an average day. • Have a traffic of 20,000 passengers per day.
  • 3. NEED ANALYSIS • Growth of passenger traffic. • New trains are coming – Budget 2013. • Ernakulam - Thrissur MEMU will start running. • 3rd and 4th rails have been started using. • Passengers have to cross the rail to reach 4th platform. • Passengers have to walk a lot of distance to get bus towards North stand or Sakthan stand.
  • 4. SUMMARY • Development of Thrissur railway station. • To supply necessary facilities for the comfort of increasing passengers. • To provide platform facilities for increasing number of trains and passengers.
  • 5. OBJECTIVES • Development of 4th platform ▫ Shops and Benches ▫ Flooring ▫ Structure ▫ Roofing ▫ Lighting ▫ Drinking Water Supply ▫ Cctv cameras ▫ Announcement System • Foot over bridge • Bus service
  • 6. First and Second platform, of Thrissur Railway Station Fourth Platform
  • 7.
  • 8. TECHNICAL FEASIBILITY • Foot over bridge from fourth platform can be connected to the existing bridge. • Buses doesn’t have a much difference in their travel distance and time.
  • 9. SOCICAL FEASIBILITY • No need of acquiring land. • Useful for People
  • 10. FINANCIAL FEASIBILTY • Source of income – Palghat Railway division • Secondary source - Budget
  • 11. BUDGET AND DURATION • Estimated Cost = 2 Crore • Estimated Time = 10 Months 5% 75% 15% 5%
  • 12. Work Cost(Lakhs) Design 10 Bus service system 10 Shops and Benches 10 Flooring Works 30 Plumbing Works for water supply 10 Foot Over bridge Construction 30 Roofing Works, Structure 80 Lighting, Announcement sys,CCtv 20 Total 200
  • 13. Activity Work Time in months A Design of Overall Plan 2 B Approval 1 C Tender 2 D Bus service system 2 E Shops and Benches 2 F Flooring Works 2 G Plumbing Works for water supply 2 H Foot Over bridge Construction 2 I Roofing Works, Structure 4 J Lighting, Announcement sys,CCtv 1 MASTER SCHEDULE
  • 14. GANTT CHART 0 1 2 3 4 5 6 7 8 9 10 TIME IN MONTHS WORK PACKAGES Approval (B) Plumbing Works(G) Structure, Roofing Works(I) Lighting, CCtv(J) Bus service (D) Design of Overall Plan (A) Over bridge (H) Tender (C) Shops and Benches(E) Flooring Works(F)
  • 15. WORK BREAK DOWN STRUCTURE Development Project Over bridge Construction Bus Service Shops and Benches Project Development Platform Construction Data collection Waiting Shed Flooring, Plumbing Structure, Roofing Lighting, Cctv, Announcement sys. Analysis Feasibility study Structure Roof Approval Sanction Tender
  • 16. General Manager (Southern Railway) Electrical engineer Civil engineer Finance officer Supervisor Chief Administrative Officer Project Committee Administrative manager Office staff Assistants supervisor WorkersOffice staff Workers Ex. Engineer PROJECT ORGANISATION STRUCTURE Project Manager