SlideShare a Scribd company logo
1 of 19
Download to read offline
How is my project doing
INTRODUCTION
There comes a time as a project manager that you will need
to conduct a project health check when the project is not
achieving the planned goals and objectives.
Even the best planned projects will encounter problems along
the way. These hurdles however, do not mean that your
project is doomed to failure. The key is to identify these
challenges early and take the appropriate steps to get your
project back on track.
A project health check can be conducted when you have just
taken over a project from a project manager or during a
project that is underway and you need to have an
understanding of why the project is running into trouble.
PREPARING FOR THE PROJECT HEALTH CHECK
Time
The Triple ConstraintsThe structure and process of a project will always
encompass key processes and in PMBOK we refer
to these as the triple constraints and each project
will be broken down into:
• Scope
• Cost
• Time
Quality will also be taken into the configuration as
this has to be measured for a successful delivery.
This presentation is using the standards and best practice provided by PMBOK
as a guideline for setting up the steps to conduct a project audit
PREPARING FOR THE PROJECT HEALTH CHECK
Fundamentally you must audit the three key factors that form the project however the
level of detail that you need to produce will be based on:
• The size and complexity of the project
• The requirement for the project to be implemented
• The speed to market
• The speed to meet the strategic objectives
The findings should be collated into an agreed matrix to easily identify what the high
risk areas are that are impacting on the current state of the project.
Area to cover during the audit can include:
Executive Support
Scope
Project Management
Change Management
Resource Management
Risk Management
This presentation will focus on the areas above, however the areas to be
audited could change according to your particular project.. The guidelines
presented here could be used for any project.
ACTION PLAN
Step 1
• Define The Project Health Check Charter
Step 2
• Outline The Project Health Check Plan
Step 3
• Conduct the Health Check
Step 4
• Present the report
Step 5
• Implement the approved plan
DEFINE THE PROJECT HEALTH CHECK CHARTER
A project health charter is setup to provide the project manager with the
authority to move ahead with the project audit and to ensure that there is
enough budget assigned and resources allocated for the project audit to
be conducted
Identify
stakeholders
Identify the
project team
Compile the
charter
Review charter
Update the
charter with
the feedback
Approve the
charter
Documentation
• Approved charter
OUTLINE THE PROJECT HEALTH CHECK PLAN
The project health check plan will outline what tasks/activities will need to
be carried out to perform the assessment. It is important to note that the
plan must specify the tools to gather the analysis, the allocation of the
teams and costs and align back to the agreed budget.
Identify the
audit tools
Identify the
tasks to be
performed
Assign the
resources
Assign the
durations
Align the costs
Finalise the
dependencies
Finalise the
cost and
budget
Baseline and
Obtain final
approval
Documentation
• Audit matrix to record findings
• Audit documentation and questionnaires
• Project Plan
• Resource Plan
• Communication Plan
CONDUCT THE PROJECT HEALTH CHECK
In order to ensure that the project health check is conducted correctly the
project plan and the tools to be used for the health check must be
communicated to the project team. Workshops and meetings must be
setup and the dates confirmed and where required, questionnaires to be
sent out to a selected target audience in preparation for the audit.
Conduct a kick off
meeting
Perform the
agreed activities
Record the
findings
Review the
findings
Finalise and
document
Distribute the
findings
Documentation
• Kick off presentation
• Completed questionnaires
• Completed matrix
• Minutes of meetings
PRESENT THE REPORT
The report for the project health check must be presented in a concise and
clear manner that allows for easy reading by both the stakeholders as well
as the team. The report should clearly show the findings from the health
check and provide the solutions to allow for the required decisions to be
made for the project/s undergoing a project health check
Finalise the table
of contents
Send out draft
copy of report
Update report
with feedback
Finalise the
report
Walkthrough the
report with the
full team
Otain stakeholder
approval
Documentation
• Audit report
• Implementation Plan
• Minutes of meetings
IMPLEMENT THE APPROVED PLAN
Once the health check findings have been agreed it will be necessary to
implement the approved findings. The implementation of the approved
plan must be conducted as a normal project following the agreed process
and governance. Training may be required to introduce the agreed
changes for project delivery.
Confirm the
actions to be
carried out
Setup a project
plan and timeline
Kick off the
project
Track into the
project roadmap
and programme
Move into the
agreed project
methodology
Close out the
project audit
Documentation
• Approved Health Check Report
• Revised project plan
• Revised project roadmap
• Updated release programme
• Close out document for project audit
GUIDELINES FOR QUESTION AND ANSWERS
 In order to accurately assess the findings of the questionnaires the questions posed
to the stakeholders and project teams should be clear and not confusing.
 All of the answers should be easily uploaded into a control matrix to show where the
problem areas are and what needs to be focussed on. Microsoft Excel is a great
document to use for this and can easily be adapted as required
 Provide a method for the questions to be answered and this should be done in a
quiet place away from the normal day to day work routine
 Communicate back to the responders to let them know how things are progressing
EXECUTIVE SUPPORT QUESTIONS AND RESPONSES
Project Sponsor Buy-in The project sponsor is fully committed to the project success
Business Case There is a clear, written, approved business case for the project
Project Budget The entire project has been financed and the budget approved
Accountability The project sponsor shares accountability with the project team to ensure
success
Success criteria The steering committee have adequate authority and have approved what
constitutes the success criteria for the project
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
SCOPE QUESTIONS AND RESPONSES
Objectives The objectives are the project are clear to all stakeholders and project team
Business Alignment The objectives of the project are in line with the corporate goals and standards
Documentation There is adequate documentation for the project requirements and performance
Stakeholder Input The stakeholders are given opportunity to provide inputs throughout the project
Tolerances There is an understanding of the tolerances for the scope of the project
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
PROJECT MANAGEMENT QUESTIONS AND RESPONSES
Stakeholder representation Are all the stakeholders represented by the steering committee? Is there
representation for the business the users and the vendors?
Project Plan There is a detailed plan including critical path, resource schedule, milestones for
the completion of the project to track releases?
Project Meetings There are regular minuted project meetings?
Lessons Learnt Have lessons from previous projects been identified and if necessary applied
Project Methodology There is an approved project methodology for the project
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
COMMUNICATION AND TRAINING QUESTIONS AND RESPONSES
Written Plans There is a written approved change management and communication plan
Communication Plan The communication plan clearly outlines the delivery mechanism for all lines of
communication
Training Plan There is a training plan with the agreed budget and approach for training
Documentation There is a clear understanding of where and how all documentation for the
project will be stored to provide easy access for the project team and
stakeholders
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
RESOURCE MANAGEMENT QUESTIONS AND RESPONSES
Manpower There is sufficient manpower to complete the project
Resource Plan Is there a resource management plan integrated into the project plan to show
public holiday and resource constraints including resource levelling
Roles and responsibilities There are clear and concise roles and responsibilities for the project team
Training Training for resources have been included in the project plan
Technology All project management technology to be used in the project is understood by
the project team
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
RISK MANAGEMENT QUESTIONS AND RESPONSES
Risk Management Project risks are tracked and appropriate responses are assigned and monitored
Risk Assessment Project risks have been assessed with the Impact and proximity of each risk and
the correct mitigation strategies assigned
Owner There are clear roles and responsibilities assigned to the risks
Communication The risks are being communicated both internally within the project and
externally to stakeholders as well as vendors
Risk Improvement All risks are being moved into a continuation improvement model for reducing
risks in future projects
0 Strongly disagree or don’t know
1 Disagree
2 Neutral
3 Agree
4 Strongly disagree
HOW THE RESULTS WILL BE PRESENTED
0%
25%
50%
75%
100%
Executive
Support
Scope
Project
Management
Communicatio
n and Training
Resource
Management
Risk
Management
Project healthcheck
Score Confidence
Executive Support 13% Very low
Scope 56% Medium
Project Management 63% Medium
Communication and Training 88% High
Resource Management 100% High
Risk Management 88% High
This is just an example and not an accurate depiction of results. It is used to
give you an idea of how the results can be presented using accurate
information.
PROJECT HEALTH CHECK BENEFITS
For The Project Manager
 The project manager receives immediate information in all areas of the project and can optimise
processes and project deliverables
 The project manager can zone in and very quickly put in an action plan to turn the project
around
 The project manager receives the right level of feedback from the team and stakeholders
For The Company
 Immediate option to mitigate the risk for the project failing
 Able to identify the need for action on the project a well as at organisational level
 Can look at current project practice to see how this an be improved
 Identify quality concerns and address them

More Related Content

What's hot

Project Governance Framework Powerpoint Presentation Slides
Project Governance Framework Powerpoint Presentation SlidesProject Governance Framework Powerpoint Presentation Slides
Project Governance Framework Powerpoint Presentation SlidesSlideTeam
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides SlideTeam
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training programParamjit Arora
 
Project Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesProject Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesSlideTeam
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
The Agile PMO: From Process Police to Adaptive Leadership
The Agile PMO: From Process Police to Adaptive LeadershipThe Agile PMO: From Process Police to Adaptive Leadership
The Agile PMO: From Process Police to Adaptive LeadershipLitheSpeed
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementWaleed Elnaggar
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plantigcap
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
Project management
Project managementProject management
Project managementAshok Pandey
 

What's hot (20)

Project Governance Framework Powerpoint Presentation Slides
Project Governance Framework Powerpoint Presentation SlidesProject Governance Framework Powerpoint Presentation Slides
Project Governance Framework Powerpoint Presentation Slides
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Project Health Checks
Project Health ChecksProject Health Checks
Project Health Checks
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
Project Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesProject Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation Slides
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
The Agile PMO: From Process Police to Adaptive Leadership
The Agile PMO: From Process Police to Adaptive LeadershipThe Agile PMO: From Process Police to Adaptive Leadership
The Agile PMO: From Process Police to Adaptive Leadership
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
PMO as a service
PMO as a servicePMO as a service
PMO as a service
 
The Project Management Plan in 20 steps
The Project Management Plan in 20 stepsThe Project Management Plan in 20 steps
The Project Management Plan in 20 steps
 
project management
project managementproject management
project management
 
PMP MINDMAP
PMP MINDMAPPMP MINDMAP
PMP MINDMAP
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Pc 2011 Epmo Plan
Pc 2011 Epmo PlanPc 2011 Epmo Plan
Pc 2011 Epmo Plan
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Project management
Project managementProject management
Project management
 

Viewers also liked

Got Problems? Let's Do a Health Check
Got Problems? Let's Do a Health CheckGot Problems? Let's Do a Health Check
Got Problems? Let's Do a Health CheckLuis Guirigay
 
Project Performance Dashboard
Project Performance DashboardProject Performance Dashboard
Project Performance DashboardChris Vizzuett
 
The Critical Value of Project Risk Management - Why do we have to manage Proj...
The Critical Value of Project Risk Management - Why do we have to manage Proj...The Critical Value of Project Risk Management - Why do we have to manage Proj...
The Critical Value of Project Risk Management - Why do we have to manage Proj...Torsten Koerting
 
Business Healthcheck Service By John Capper & Co
Business Healthcheck Service By John Capper & CoBusiness Healthcheck Service By John Capper & Co
Business Healthcheck Service By John Capper & CoJohn Capper & Co
 
The Real Value of Oracle Health Checks
The Real Value of Oracle Health ChecksThe Real Value of Oracle Health Checks
The Real Value of Oracle Health ChecksDatavail
 
Importance of program health checks
Importance of program health checksImportance of program health checks
Importance of program health checksMaveric Systems
 
Benefits and better business cases_Alan Brown and Stefan Sanchez
Benefits and better business cases_Alan Brown and Stefan SanchezBenefits and better business cases_Alan Brown and Stefan Sanchez
Benefits and better business cases_Alan Brown and Stefan SanchezAssociation for Project Management
 
Workshop F, A healthy respect for benefits by David Waller and Hugo Minney
Workshop F, A healthy respect for benefits by David Waller and Hugo MinneyWorkshop F, A healthy respect for benefits by David Waller and Hugo Minney
Workshop F, A healthy respect for benefits by David Waller and Hugo MinneyAssociation for Project Management
 
OpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits RealisationOpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits RealisationImprovement Skills Consulting Ltd.
 
Social Media Tools (BAW-Vorlesung Juli 2012)
Social Media Tools (BAW-Vorlesung Juli 2012)Social Media Tools (BAW-Vorlesung Juli 2012)
Social Media Tools (BAW-Vorlesung Juli 2012)Daniel Rehn
 
BPM Benefits Realisation Framework
BPM Benefits Realisation FrameworkBPM Benefits Realisation Framework
BPM Benefits Realisation FrameworkLeonardo Consulting
 
Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...Association for Project Management
 
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check Arvind Rajan
 
Benefits-led portfolio management: maximising capital investment returns, by ...
Benefits-led portfolio management: maximising capital investment returns, by ...Benefits-led portfolio management: maximising capital investment returns, by ...
Benefits-led portfolio management: maximising capital investment returns, by ...Association for Project Management
 
DevDay 2016: Peter Lehmann - Testautomatisierungsframework Xeta
DevDay 2016: Peter Lehmann - Testautomatisierungsframework XetaDevDay 2016: Peter Lehmann - Testautomatisierungsframework Xeta
DevDay 2016: Peter Lehmann - Testautomatisierungsframework XetaDevDay Dresden
 

Viewers also liked (20)

Project Health Check
Project Health CheckProject Health Check
Project Health Check
 
Got Problems? Let's Do a Health Check
Got Problems? Let's Do a Health CheckGot Problems? Let's Do a Health Check
Got Problems? Let's Do a Health Check
 
Project Performance Dashboard
Project Performance DashboardProject Performance Dashboard
Project Performance Dashboard
 
The Critical Value of Project Risk Management - Why do we have to manage Proj...
The Critical Value of Project Risk Management - Why do we have to manage Proj...The Critical Value of Project Risk Management - Why do we have to manage Proj...
The Critical Value of Project Risk Management - Why do we have to manage Proj...
 
Business Healthcheck Service By John Capper & Co
Business Healthcheck Service By John Capper & CoBusiness Healthcheck Service By John Capper & Co
Business Healthcheck Service By John Capper & Co
 
The Real Value of Oracle Health Checks
The Real Value of Oracle Health ChecksThe Real Value of Oracle Health Checks
The Real Value of Oracle Health Checks
 
Workshop D, Benefits for whom? by Ben Pinches
Workshop D, Benefits for whom? by Ben PinchesWorkshop D, Benefits for whom? by Ben Pinches
Workshop D, Benefits for whom? by Ben Pinches
 
Importance of program health checks
Importance of program health checksImportance of program health checks
Importance of program health checks
 
Benefits and better business cases_Alan Brown and Stefan Sanchez
Benefits and better business cases_Alan Brown and Stefan SanchezBenefits and better business cases_Alan Brown and Stefan Sanchez
Benefits and better business cases_Alan Brown and Stefan Sanchez
 
Workshop F, A healthy respect for benefits by David Waller and Hugo Minney
Workshop F, A healthy respect for benefits by David Waller and Hugo MinneyWorkshop F, A healthy respect for benefits by David Waller and Hugo Minney
Workshop F, A healthy respect for benefits by David Waller and Hugo Minney
 
Sonar - Software Qualitätsmanagement ohne Schmerzen
Sonar - Software Qualitätsmanagement ohne SchmerzenSonar - Software Qualitätsmanagement ohne Schmerzen
Sonar - Software Qualitätsmanagement ohne Schmerzen
 
OpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits RealisationOpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits Realisation
 
Social Media Tools (BAW-Vorlesung Juli 2012)
Social Media Tools (BAW-Vorlesung Juli 2012)Social Media Tools (BAW-Vorlesung Juli 2012)
Social Media Tools (BAW-Vorlesung Juli 2012)
 
BPM Benefits Realisation Framework
BPM Benefits Realisation FrameworkBPM Benefits Realisation Framework
BPM Benefits Realisation Framework
 
Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...
 
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check
PeopleSoft 9.2 Upgrade Readiness Assessment and Health Check
 
Benefits-led portfolio management: maximising capital investment returns, by ...
Benefits-led portfolio management: maximising capital investment returns, by ...Benefits-led portfolio management: maximising capital investment returns, by ...
Benefits-led portfolio management: maximising capital investment returns, by ...
 
Scrum im Marketing
Scrum im MarketingScrum im Marketing
Scrum im Marketing
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
DevDay 2016: Peter Lehmann - Testautomatisierungsframework Xeta
DevDay 2016: Peter Lehmann - Testautomatisierungsframework XetaDevDay 2016: Peter Lehmann - Testautomatisierungsframework Xeta
DevDay 2016: Peter Lehmann - Testautomatisierungsframework Xeta
 

Similar to Project health check updated and improved

Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackProject Management Solutions
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project StandardsUjjwal Joshi
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
PM skillz [jz]
PM skillz [jz]PM skillz [jz]
PM skillz [jz]Jo Zaarour
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021Sprintzeal
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Introduction-to-Project-Management systems
Introduction-to-Project-Management systemsIntroduction-to-Project-Management systems
Introduction-to-Project-Management systemsAbshirAhmed8
 
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...MarivicPenarubia1
 
Change Management Plan
Change Management PlanChange Management Plan
Change Management PlanDemand Metric
 
NCV 4 Project Management Hands-On Support Slide Show - Module 4
NCV 4 Project Management Hands-On Support Slide Show - Module 4NCV 4 Project Management Hands-On Support Slide Show - Module 4
NCV 4 Project Management Hands-On Support Slide Show - Module 4Future Managers
 

Similar to Project health check updated and improved (20)

Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project Standards
 
Unit 1.pptx
Unit 1.pptxUnit 1.pptx
Unit 1.pptx
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
PM skillz [jz]
PM skillz [jz]PM skillz [jz]
PM skillz [jz]
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Proect Review
Proect ReviewProect Review
Proect Review
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
MODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptxMODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptx
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Introduction-to-Project-Management systems
Introduction-to-Project-Management systemsIntroduction-to-Project-Management systems
Introduction-to-Project-Management systems
 
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
 
Change Management Plan
Change Management PlanChange Management Plan
Change Management Plan
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
NCV 4 Project Management Hands-On Support Slide Show - Module 4
NCV 4 Project Management Hands-On Support Slide Show - Module 4NCV 4 Project Management Hands-On Support Slide Show - Module 4
NCV 4 Project Management Hands-On Support Slide Show - Module 4
 

More from Project Management Solutions

A guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectA guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectProject Management Solutions
 

More from Project Management Solutions (17)

A project quick start guide
A project quick start guideA project quick start guide
A project quick start guide
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162
 
Taking a web site from concept to launch
Taking a web site from concept to launchTaking a web site from concept to launch
Taking a web site from concept to launch
 
Managing multiple projects
Managing multiple projectsManaging multiple projects
Managing multiple projects
 
A guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery projectA guide for the rolling out of a software delivery project
A guide for the rolling out of a software delivery project
 
The agile pmo v2
The agile pmo v2The agile pmo v2
The agile pmo v2
 
Business and project changing the paradigm
Business and project changing the paradigmBusiness and project changing the paradigm
Business and project changing the paradigm
 
Why not - Words to make you think
Why not - Words to make you thinkWhy not - Words to make you think
Why not - Words to make you think
 
Project management today a step ahead
Project management today   a step aheadProject management today   a step ahead
Project management today a step ahead
 
Managing your suppliers makes perfect sense
Managing your suppliers makes perfect senseManaging your suppliers makes perfect sense
Managing your suppliers makes perfect sense
 
Ready get set go your project is approved
Ready get set go your project is approvedReady get set go your project is approved
Ready get set go your project is approved
 
The digital project manager
The digital project managerThe digital project manager
The digital project manager
 
Lets get digital
Lets get digitalLets get digital
Lets get digital
 
Getting Ready for UAT
Getting Ready for UATGetting Ready for UAT
Getting Ready for UAT
 
Strategy planning for small digital companies
Strategy planning for small digital companiesStrategy planning for small digital companies
Strategy planning for small digital companies
 
Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011
 

Recently uploaded

Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607dollysharma2066
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 

Recently uploaded (20)

Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 

Project health check updated and improved

  • 1. How is my project doing
  • 2. INTRODUCTION There comes a time as a project manager that you will need to conduct a project health check when the project is not achieving the planned goals and objectives. Even the best planned projects will encounter problems along the way. These hurdles however, do not mean that your project is doomed to failure. The key is to identify these challenges early and take the appropriate steps to get your project back on track. A project health check can be conducted when you have just taken over a project from a project manager or during a project that is underway and you need to have an understanding of why the project is running into trouble.
  • 3. PREPARING FOR THE PROJECT HEALTH CHECK Time The Triple ConstraintsThe structure and process of a project will always encompass key processes and in PMBOK we refer to these as the triple constraints and each project will be broken down into: • Scope • Cost • Time Quality will also be taken into the configuration as this has to be measured for a successful delivery. This presentation is using the standards and best practice provided by PMBOK as a guideline for setting up the steps to conduct a project audit
  • 4. PREPARING FOR THE PROJECT HEALTH CHECK Fundamentally you must audit the three key factors that form the project however the level of detail that you need to produce will be based on: • The size and complexity of the project • The requirement for the project to be implemented • The speed to market • The speed to meet the strategic objectives The findings should be collated into an agreed matrix to easily identify what the high risk areas are that are impacting on the current state of the project. Area to cover during the audit can include: Executive Support Scope Project Management Change Management Resource Management Risk Management This presentation will focus on the areas above, however the areas to be audited could change according to your particular project.. The guidelines presented here could be used for any project.
  • 5. ACTION PLAN Step 1 • Define The Project Health Check Charter Step 2 • Outline The Project Health Check Plan Step 3 • Conduct the Health Check Step 4 • Present the report Step 5 • Implement the approved plan
  • 6. DEFINE THE PROJECT HEALTH CHECK CHARTER A project health charter is setup to provide the project manager with the authority to move ahead with the project audit and to ensure that there is enough budget assigned and resources allocated for the project audit to be conducted Identify stakeholders Identify the project team Compile the charter Review charter Update the charter with the feedback Approve the charter Documentation • Approved charter
  • 7. OUTLINE THE PROJECT HEALTH CHECK PLAN The project health check plan will outline what tasks/activities will need to be carried out to perform the assessment. It is important to note that the plan must specify the tools to gather the analysis, the allocation of the teams and costs and align back to the agreed budget. Identify the audit tools Identify the tasks to be performed Assign the resources Assign the durations Align the costs Finalise the dependencies Finalise the cost and budget Baseline and Obtain final approval Documentation • Audit matrix to record findings • Audit documentation and questionnaires • Project Plan • Resource Plan • Communication Plan
  • 8. CONDUCT THE PROJECT HEALTH CHECK In order to ensure that the project health check is conducted correctly the project plan and the tools to be used for the health check must be communicated to the project team. Workshops and meetings must be setup and the dates confirmed and where required, questionnaires to be sent out to a selected target audience in preparation for the audit. Conduct a kick off meeting Perform the agreed activities Record the findings Review the findings Finalise and document Distribute the findings Documentation • Kick off presentation • Completed questionnaires • Completed matrix • Minutes of meetings
  • 9. PRESENT THE REPORT The report for the project health check must be presented in a concise and clear manner that allows for easy reading by both the stakeholders as well as the team. The report should clearly show the findings from the health check and provide the solutions to allow for the required decisions to be made for the project/s undergoing a project health check Finalise the table of contents Send out draft copy of report Update report with feedback Finalise the report Walkthrough the report with the full team Otain stakeholder approval Documentation • Audit report • Implementation Plan • Minutes of meetings
  • 10. IMPLEMENT THE APPROVED PLAN Once the health check findings have been agreed it will be necessary to implement the approved findings. The implementation of the approved plan must be conducted as a normal project following the agreed process and governance. Training may be required to introduce the agreed changes for project delivery. Confirm the actions to be carried out Setup a project plan and timeline Kick off the project Track into the project roadmap and programme Move into the agreed project methodology Close out the project audit Documentation • Approved Health Check Report • Revised project plan • Revised project roadmap • Updated release programme • Close out document for project audit
  • 11. GUIDELINES FOR QUESTION AND ANSWERS  In order to accurately assess the findings of the questionnaires the questions posed to the stakeholders and project teams should be clear and not confusing.  All of the answers should be easily uploaded into a control matrix to show where the problem areas are and what needs to be focussed on. Microsoft Excel is a great document to use for this and can easily be adapted as required  Provide a method for the questions to be answered and this should be done in a quiet place away from the normal day to day work routine  Communicate back to the responders to let them know how things are progressing
  • 12. EXECUTIVE SUPPORT QUESTIONS AND RESPONSES Project Sponsor Buy-in The project sponsor is fully committed to the project success Business Case There is a clear, written, approved business case for the project Project Budget The entire project has been financed and the budget approved Accountability The project sponsor shares accountability with the project team to ensure success Success criteria The steering committee have adequate authority and have approved what constitutes the success criteria for the project 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 13. SCOPE QUESTIONS AND RESPONSES Objectives The objectives are the project are clear to all stakeholders and project team Business Alignment The objectives of the project are in line with the corporate goals and standards Documentation There is adequate documentation for the project requirements and performance Stakeholder Input The stakeholders are given opportunity to provide inputs throughout the project Tolerances There is an understanding of the tolerances for the scope of the project 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 14. PROJECT MANAGEMENT QUESTIONS AND RESPONSES Stakeholder representation Are all the stakeholders represented by the steering committee? Is there representation for the business the users and the vendors? Project Plan There is a detailed plan including critical path, resource schedule, milestones for the completion of the project to track releases? Project Meetings There are regular minuted project meetings? Lessons Learnt Have lessons from previous projects been identified and if necessary applied Project Methodology There is an approved project methodology for the project 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 15. COMMUNICATION AND TRAINING QUESTIONS AND RESPONSES Written Plans There is a written approved change management and communication plan Communication Plan The communication plan clearly outlines the delivery mechanism for all lines of communication Training Plan There is a training plan with the agreed budget and approach for training Documentation There is a clear understanding of where and how all documentation for the project will be stored to provide easy access for the project team and stakeholders 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 16. RESOURCE MANAGEMENT QUESTIONS AND RESPONSES Manpower There is sufficient manpower to complete the project Resource Plan Is there a resource management plan integrated into the project plan to show public holiday and resource constraints including resource levelling Roles and responsibilities There are clear and concise roles and responsibilities for the project team Training Training for resources have been included in the project plan Technology All project management technology to be used in the project is understood by the project team 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 17. RISK MANAGEMENT QUESTIONS AND RESPONSES Risk Management Project risks are tracked and appropriate responses are assigned and monitored Risk Assessment Project risks have been assessed with the Impact and proximity of each risk and the correct mitigation strategies assigned Owner There are clear roles and responsibilities assigned to the risks Communication The risks are being communicated both internally within the project and externally to stakeholders as well as vendors Risk Improvement All risks are being moved into a continuation improvement model for reducing risks in future projects 0 Strongly disagree or don’t know 1 Disagree 2 Neutral 3 Agree 4 Strongly disagree
  • 18. HOW THE RESULTS WILL BE PRESENTED 0% 25% 50% 75% 100% Executive Support Scope Project Management Communicatio n and Training Resource Management Risk Management Project healthcheck Score Confidence Executive Support 13% Very low Scope 56% Medium Project Management 63% Medium Communication and Training 88% High Resource Management 100% High Risk Management 88% High This is just an example and not an accurate depiction of results. It is used to give you an idea of how the results can be presented using accurate information.
  • 19. PROJECT HEALTH CHECK BENEFITS For The Project Manager  The project manager receives immediate information in all areas of the project and can optimise processes and project deliverables  The project manager can zone in and very quickly put in an action plan to turn the project around  The project manager receives the right level of feedback from the team and stakeholders For The Company  Immediate option to mitigate the risk for the project failing  Able to identify the need for action on the project a well as at organisational level  Can look at current project practice to see how this an be improved  Identify quality concerns and address them