PRE
PRE
PRE
PRE-
-
-
-LAUNCH BRIEFING
LAUNCH BRIEFING
LAUNCH BRIEFING
LAUNCH BRIEFING
21 December 2010
21 December 2010
21 December 2010
21 December 2010
Cyberview Lodge Resort & Spa
Cyberview Lodge Resort & Spa
Cyberview Lodge Resort & Spa
Cyberview Lodge Resort & Spa
THE MALAYSIAN
GRID & DISTRIBUTION
CODES
The Overview
The Overview
The Overview
The Overview
A Background
A Background
A Background
A Background
Development of the Grid System
Birth year
of
Peninsular
Grid
System
1st 275 kV
circuit
commissioned
Birth year
of TNB
Emergence
of 1st IPP
1st
Malaysian
Grid Code
introduced
1st 500 kV
circuit
commissioned
MAS – THA
300 MW
HVDC LINK
1953 1970 1990 1992 1994 1996 1998 2010
Launch of
new
Malaysian
Grid &
Distribution
Codes
Chronology of Code Development
1st
Malaysian
Grid Code
introduced
Submission
of 1st draft
of
Malaysian
Distribution
Code
Call for
Revision of
MGC & MDC
TNB
submitted
revised
MGC &
MDC
1st
Revision
by TERI
2nd
Revision
by APS
Crossing
the T’s &
dotting the
I’s
1994 1997 2004 2006 2007 2008 2009 2010
Launch of
new
Malaysian
Grid &
Distribution
Codes
Basic Premise of a Grid Code
• Technical document containing
requirement, procedures and relationships
among transmission network users
• Liberalization within the ESI necessitates a
clearly established rules and guidelines
• Centralized around a Grid Owner & a Grid
Operator with agreements of other users
General Forms of a Grid Code
• Established & maintained by Grid
Owner/Grid Operator and endorsed by the
Regulator
or
• Established by the Regulator and imposed
on the Users including Grid Owner/Grid
Operator
Framework of a Grid Code
• Permit development, maintenance &
operation of a coordinated and economical
transmission system
• Facilitate competition in the generation &
supply of electricity
• Devoted to planning: system & operational
Regulatory
Regulatory
Regulatory
Regulatory
Arrangements
Arrangements
Arrangements
Arrangements
Regulations & Acts
• Electricity Supply Act 1990 (Act 447)
• Licensee Supply Regulations 1990
• Electricity Regulations 1994
• Energy Commission Act 2001 (Act 610)
Overlying Intent
• Regulate all matters related to the ESI
• Promote competition in the generation and
supply of electricity
• Promote interests of the Consumers
Provisions within License Conditions
• Grid Code
• GSO to maintain & implement Grid Code
• Users of Grid System & GSO required to
comply
• Distribution Code
• Distributors to establish & maintain a
Distribution Code
• Users of Distribution System & Distributors
required to comply
The Needs
The Needs
The Needs
The Needs
The Need for a Revised Grid Code
• Current Malaysian Grid Code not in line
with industry structure and practices
• Clearer separation of roles and authority
• To ensure continuity for an efficient and
secure development and operation
The Need for a Distribution Code
• No Distribution Code currently exist
• To set out principles governing the relationship
between GSO, EC & all users of the distribution
system
• The advent of Distributed Generation
• Designation of franchise Distributors
The Distribution System
• Operates below 66 kV
• Purchase of power from the Grid System
• Provision and operation of Medium & Low
Voltage Distribution Networks
• Provision of service lines for retail sales
What’s New
Current Industry Structure
TNB
Generators
Grid
Owner GSO
TNB
Distribution
Consumers
Other
Distributors
IPPs
Parties in the New Codes
Interactions within the System
Redefined Roles
• TNB
• Registered incorporated company comprising of
Generation, Transmission & Distribution
• Grid Owner, planner, operator and off-taker (Single
Buyer)
• Grid Owner
• The party that owns the HV backbone Transmission
System
• Responsible for maintaining adequate Grid Capacity
• Carry out transmission functions via TNB
Transmission
Redefined Roles (cont.)
• Grid System Operator (GSO)
• A part of TNB responsible for operational
planning, real-time rescheduling, dispatch and
control of the Grid System
• Single Buyer
• A part of TNB responsible for day-ahead
scheduling and managing PPAs, SLAs &
settlement process
Redefined Roles (cont.)
Redefined Roles (cont.)
• Distributed Generation
• Small generation connected to a Distribution
System or an Embedded Distributor and not
connected to a Transmission System
• Embedded Distributor
• Licensee connected to a Distributor’s
Distribution System and not connected to a
Transmission System
Grid Code Committee
 Chairman: Energy Commission
• Members:
• 9 from TNB
• 6 from IPP
• 1 independent technical expert
• 1 from Minor Distributor
• 2 observers from Energy Commission
Independent External Audit
• Appointed by GCC
• Review operations  performance of GSO 
SB especially relating to scheduling
• Evaluate significant grid events
• Identify difficulties in MGC and make
recommendations
• Rules, procedures  functions formulated
by GCC and approved by EC
Distribution Code Committee
 Chairman: Energy Commission
• Members:
• 1 from Energy Commission
• 5 from TNB
• 4 from other Distributors
• 2 from Distributed Generators
• 1 from Consumer
• 2 observers from TNB
• Additional members if required by DCC
Moving Forward
Looking to the Future
2012
2014
2015
2011
*New MGC 
MDC in operation
1 Jan 2011
TERIMA KASIH
THANK YOU
Ahmad Johari Jaffar
Suruhanjaya Tenaga

The malaysian grid distribution codes

  • 1.
    PRE PRE PRE PRE- - - -LAUNCH BRIEFING LAUNCH BRIEFING LAUNCHBRIEFING LAUNCH BRIEFING 21 December 2010 21 December 2010 21 December 2010 21 December 2010 Cyberview Lodge Resort & Spa Cyberview Lodge Resort & Spa Cyberview Lodge Resort & Spa Cyberview Lodge Resort & Spa THE MALAYSIAN GRID & DISTRIBUTION CODES The Overview The Overview The Overview The Overview
  • 2.
    A Background A Background ABackground A Background
  • 3.
    Development of theGrid System Birth year of Peninsular Grid System 1st 275 kV circuit commissioned Birth year of TNB Emergence of 1st IPP 1st Malaysian Grid Code introduced 1st 500 kV circuit commissioned MAS – THA 300 MW HVDC LINK 1953 1970 1990 1992 1994 1996 1998 2010 Launch of new Malaysian Grid & Distribution Codes
  • 4.
    Chronology of CodeDevelopment 1st Malaysian Grid Code introduced Submission of 1st draft of Malaysian Distribution Code Call for Revision of MGC & MDC TNB submitted revised MGC & MDC 1st Revision by TERI 2nd Revision by APS Crossing the T’s & dotting the I’s 1994 1997 2004 2006 2007 2008 2009 2010 Launch of new Malaysian Grid & Distribution Codes
  • 5.
    Basic Premise ofa Grid Code • Technical document containing requirement, procedures and relationships among transmission network users • Liberalization within the ESI necessitates a clearly established rules and guidelines • Centralized around a Grid Owner & a Grid Operator with agreements of other users
  • 6.
    General Forms ofa Grid Code • Established & maintained by Grid Owner/Grid Operator and endorsed by the Regulator or • Established by the Regulator and imposed on the Users including Grid Owner/Grid Operator
  • 7.
    Framework of aGrid Code • Permit development, maintenance & operation of a coordinated and economical transmission system • Facilitate competition in the generation & supply of electricity • Devoted to planning: system & operational
  • 8.
  • 9.
    Regulations & Acts •Electricity Supply Act 1990 (Act 447) • Licensee Supply Regulations 1990 • Electricity Regulations 1994 • Energy Commission Act 2001 (Act 610)
  • 10.
    Overlying Intent • Regulateall matters related to the ESI • Promote competition in the generation and supply of electricity • Promote interests of the Consumers
  • 11.
    Provisions within LicenseConditions • Grid Code • GSO to maintain & implement Grid Code • Users of Grid System & GSO required to comply • Distribution Code • Distributors to establish & maintain a Distribution Code • Users of Distribution System & Distributors required to comply
  • 12.
    The Needs The Needs TheNeeds The Needs
  • 13.
    The Need fora Revised Grid Code • Current Malaysian Grid Code not in line with industry structure and practices • Clearer separation of roles and authority • To ensure continuity for an efficient and secure development and operation
  • 14.
    The Need fora Distribution Code • No Distribution Code currently exist • To set out principles governing the relationship between GSO, EC & all users of the distribution system • The advent of Distributed Generation • Designation of franchise Distributors
  • 15.
    The Distribution System •Operates below 66 kV • Purchase of power from the Grid System • Provision and operation of Medium & Low Voltage Distribution Networks • Provision of service lines for retail sales
  • 16.
  • 17.
    Current Industry Structure TNB Generators Grid OwnerGSO TNB Distribution Consumers Other Distributors IPPs
  • 18.
    Parties in theNew Codes
  • 19.
  • 20.
    Redefined Roles • TNB •Registered incorporated company comprising of Generation, Transmission & Distribution • Grid Owner, planner, operator and off-taker (Single Buyer) • Grid Owner • The party that owns the HV backbone Transmission System • Responsible for maintaining adequate Grid Capacity • Carry out transmission functions via TNB Transmission
  • 21.
    Redefined Roles (cont.) •Grid System Operator (GSO) • A part of TNB responsible for operational planning, real-time rescheduling, dispatch and control of the Grid System • Single Buyer • A part of TNB responsible for day-ahead scheduling and managing PPAs, SLAs & settlement process
  • 22.
  • 23.
    Redefined Roles (cont.) •Distributed Generation • Small generation connected to a Distribution System or an Embedded Distributor and not connected to a Transmission System • Embedded Distributor • Licensee connected to a Distributor’s Distribution System and not connected to a Transmission System
  • 24.
    Grid Code Committee Chairman: Energy Commission • Members: • 9 from TNB • 6 from IPP • 1 independent technical expert • 1 from Minor Distributor • 2 observers from Energy Commission
  • 25.
    Independent External Audit •Appointed by GCC • Review operations performance of GSO SB especially relating to scheduling • Evaluate significant grid events • Identify difficulties in MGC and make recommendations • Rules, procedures functions formulated by GCC and approved by EC
  • 26.
    Distribution Code Committee Chairman: Energy Commission • Members: • 1 from Energy Commission • 5 from TNB • 4 from other Distributors • 2 from Distributed Generators • 1 from Consumer • 2 observers from TNB • Additional members if required by DCC
  • 27.
  • 28.
    Looking to theFuture 2012 2014 2015 2011 *New MGC MDC in operation 1 Jan 2011
  • 29.
    TERIMA KASIH THANK YOU AhmadJohari Jaffar Suruhanjaya Tenaga