SlideShare a Scribd company logo
RENA CUMMINGS, MS
Seattle, WA
rcummings43@gmail.com
www.linkedin.com/in/projectmanager3/
Cell (360)-550-8216
HIGHLIGHTS OF QUALIFICATIONS
• MS in Project Manager and Technology Management
• Improved SharePoint documentation process predicted cost savings of $75,000
• Achieved cost savings of $800,000 using six sigma and lean applications process
• Chaired multiple data review and change management “solution meetings”
• Secured a supplier within 30 days despite varying deliverable schedule
• Scrum Project Manager co-manage 28 teams to update websites.
• Veteran, 20 years of service, specialty in Flight Operations
• Research Security impact on Wireless Sensor Cloud Architect
KEY KNOWLEDGE AND SKILLS
Work-Flow  Project Scheduling  Waterfall
Business Process Modeling  Change Management  SDLC
 Risk Analysis  Risk Management  Agile Application
NoImImprovementImproveme
nts
 Lean Application

 Resource Planning  Data Analysis

Education
● Masters of Science in Technology Management, City University 2014
● Masters of Science in Project Management, City University 2011
● BS in Mechanical Engineering, University of Memphis 1998
● BS in Manufacturing Engineering, University of Memphis 1998
● IT Security Networking Certificate, Edmonds Community College 2016
● Scrum Master, CSM, Nityo Infotech expected completion 2016
● Project Management Professional, PMP, Nittyo Infotech 2016
PROFESSIONAL EXPERIENCE
Seattle Give Camp: Microsoft Commons, Bellevue, WA October 2013 – 2015
Scrum Project Manager; volunteer
Co-managed 28 teams of Software Developers, Web Developers, Database Administrators to update or create webpages for 28
nonprofit organizations using Agile and Sprint application. As Scrum Master, my responsibility included staying within each project
scope, creating requirement analysis, and keeping tasks moving throughout the production pipeline. Engaging with the site -owners
providing continuous feedback to the team.
Bu s in e s s Pro c e s s Sy s t e m A n a ly s t November 2013 - August 2014
J TS Manag e S e r vi c e s ;Seattle, Washington
JTS needed to update its document control operations to meet increased production demands. They want to replace their legacy
software system to meet needs of their clients
• Applied Business Architect Enterprise methodology to identify inefficient process operations.
• Implemented process change management procedures with predicted cost savings of$75,000.00.
• Applied Visio and Workflow process modeling diagrams to increase operation effectively by 25 percent.
• Project lead and coached team of five on how to improve operation effectiveness
• Prepare Data flow to migrate into Share-Point
Daimler North America, Portland, Oregon January 2011 - January 2012
Senior Electronic Development Engineer
New Product Design Project: Linde Gas Gate-lift project required a specially designed battery to accommodate their new design lift-
gate to retrofit 300 trucks. As PM, I led a cross-functional team, which included Linde Gas, sales manager, plant manager and
liaisons to create a project plan to retrofit 300 trucks. My tasks included planning phrase lift-gate for pre-production builds and
program transition into production phrase Linde Gas Gate-lift deliverable using DFMA methodology to reduce inventory cost.
● Coordinated and verified expectations and design requirements within Linde Gas Company and Daimler North America.
● Managed and monitored the Linde Gas-lift new product line from production to delivery.
● Exceeded the project delivery schedule deadline by 6 months
● Improved resource and inventory scheduling,with cost saving $500,000 in labor.
● Facilitate “solution focus” meeting between plant managers and engineers.
● Analysis production data flow to identify repeated pattern of failures.
Boeing, Seattle, Washington July 2008 - June 2010
Project Manager, Manufacturing Flight Test Operations & Validation Engineer
Led a cross-functional team of ground engineers, design engineers and production engineers to manufacture 747, 777 and 737 parts in
support flight test operations. As a liaison, I created test plans to be implemented by aircraft maintenance crews for operational
readiness of the plane.
● Implemented a change management meeting between engineers,and suppliers to secure new part specification.
● Secured a supplier within 30 days despite varying deliverable schedule
IMC - Infinite Minde Concept, Seattle WA January 2005- September 2015
CEO/Project Manager Consultant
Project lead team of three on modification of El Ranchito’s tamale machine. Project lead of “The Great African Cook-In”
● Implemented project impact analysis on production of tamales with predicted sales
● and cost increased of 46.7 percent
● Submitted bid of $478,000 to install solar panels and windmill in Central Seattle.
● Project team of five on The Great African Cook-In event,with 300 attendants.
Siemens Westinghouse,Fort Payne, AL March 2002-March 2004
Project Manager, Product DesignEngineer
As project manager, assignments included:
● Chaired multiple data review and change management “solution meetings”
● Implemented change management solution among suppliers resulting in 47% reduction of rework.
● Achieved cost savings of $800,000 using six sigma and lean applications process
• Improved operational workflow efficiency by 25 percent in 12 mos.
• Analysis production data flow to identify repeated pattern of tube failures.
Graduate Dissertation:
City University October 2011
MS in Project Management
Project Lead - Cloud Web: Based – Hospital Patient Billing System
● Managed two global teams; project scope to created a patient web based health care billing-system
● Collaborated on the planning and execution phrase of the cloud base application
● Used Microsoft Azure: Cloud Base Database to create the web based system
MS in Technology Management October 2014
Daimler North America: Technology Pilot Infrastructure Proposal
Mercedes Benz parent global company of Daimler North America was conducting an extensive global infrastructure upgrade using
cloud-based technology to synchronize their business around the globe.
● Created a cloud technology SQL Azure application proposal that would implement SQL database technology and provide a
seamless cloud integration that synchronizes and connects all employees and instances globally
● Identified core issues identified throughout Daimler’s global work force that impedes IT infrastructure production
● Created Service and Technical Enterprise Architecture solutions on IT infrastructure cloud-based upgrade proposal
● Research security impact on Wireless Sensor Cloud Architecture.

More Related Content

What's hot

RT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based EngineeringRT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based Engineering
AVEVA Group plc
 
Brian Simoes Resume
Brian Simoes ResumeBrian Simoes Resume
Brian Simoes Resume
Brian Simoes
 
SENEGER_Thomas_CV-15
SENEGER_Thomas_CV-15SENEGER_Thomas_CV-15
SENEGER_Thomas_CV-15
Thomas Seneger
 
AVEVA World Conference NA - Keith Parker, Eastman Chemicals
AVEVA World Conference NA - Keith Parker, Eastman ChemicalsAVEVA World Conference NA - Keith Parker, Eastman Chemicals
AVEVA World Conference NA - Keith Parker, Eastman Chemicals
AVEVA-Americas
 
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
Paladino and Company
 
Engineering and Program Management Services
Engineering and Program Management ServicesEngineering and Program Management Services
Engineering and Program Management Services
Jaka Legawa
 
AVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsonsAVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA-Americas
 
Overview of SAFe
Overview of SAFeOverview of SAFe
Overview of SAFe
Sandeep Yadav
 
Global Trends in Delivery Projects
Global Trends in Delivery ProjectsGlobal Trends in Delivery Projects
Global Trends in Delivery Projects
Aconex
 
Jessica_Cabral_Resume1i
Jessica_Cabral_Resume1iJessica_Cabral_Resume1i
Jessica_Cabral_Resume1i
Jessica Cabral
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_Presentation
Bert Bruijn
 
Shellman Tracey - Resume
Shellman Tracey - ResumeShellman Tracey - Resume
Shellman Tracey - Resume
Tracey Shellman
 
ToddClapp
ToddClappToddClapp
ToddClapp
Todd Clapp
 
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAVWhat is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
NETRONIC Software GmbH
 
Perdziola Resume Final
Perdziola Resume FinalPerdziola Resume Final
Perdziola Resume Final
Roman Perdziola
 
De Wilkins Resume
De Wilkins ResumeDe Wilkins Resume
De Wilkins Resume
dewilkin
 
jbieda summary res0416
jbieda summary res0416jbieda summary res0416
jbieda summary res0416
Jim Bieda, PE
 
AVEVA World Conference NA - Rashaad Sader, SNC Lavalin
AVEVA World Conference NA - Rashaad Sader, SNC LavalinAVEVA World Conference NA - Rashaad Sader, SNC Lavalin
AVEVA World Conference NA - Rashaad Sader, SNC Lavalin
AVEVA-Americas
 
Software Advice BuyerView: Construction Software Report 2014
Software Advice BuyerView: Construction Software Report 2014Software Advice BuyerView: Construction Software Report 2014
Software Advice BuyerView: Construction Software Report 2014
Software Advice
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Aconex
 

What's hot (20)

RT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based EngineeringRT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based Engineering
 
Brian Simoes Resume
Brian Simoes ResumeBrian Simoes Resume
Brian Simoes Resume
 
SENEGER_Thomas_CV-15
SENEGER_Thomas_CV-15SENEGER_Thomas_CV-15
SENEGER_Thomas_CV-15
 
AVEVA World Conference NA - Keith Parker, Eastman Chemicals
AVEVA World Conference NA - Keith Parker, Eastman ChemicalsAVEVA World Conference NA - Keith Parker, Eastman Chemicals
AVEVA World Conference NA - Keith Parker, Eastman Chemicals
 
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
Using Retro-Commissioning to Improve Operations and Energy Use through Climat...
 
Engineering and Program Management Services
Engineering and Program Management ServicesEngineering and Program Management Services
Engineering and Program Management Services
 
AVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsonsAVEVA World Conference NA - Jim Purvis, WorleyParsons
AVEVA World Conference NA - Jim Purvis, WorleyParsons
 
Overview of SAFe
Overview of SAFeOverview of SAFe
Overview of SAFe
 
Global Trends in Delivery Projects
Global Trends in Delivery ProjectsGlobal Trends in Delivery Projects
Global Trends in Delivery Projects
 
Jessica_Cabral_Resume1i
Jessica_Cabral_Resume1iJessica_Cabral_Resume1i
Jessica_Cabral_Resume1i
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_Presentation
 
Shellman Tracey - Resume
Shellman Tracey - ResumeShellman Tracey - Resume
Shellman Tracey - Resume
 
ToddClapp
ToddClappToddClapp
ToddClapp
 
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAVWhat is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
What is new in Visual Jobs Scheduler for Microsoft Dynamics NAV
 
Perdziola Resume Final
Perdziola Resume FinalPerdziola Resume Final
Perdziola Resume Final
 
De Wilkins Resume
De Wilkins ResumeDe Wilkins Resume
De Wilkins Resume
 
jbieda summary res0416
jbieda summary res0416jbieda summary res0416
jbieda summary res0416
 
AVEVA World Conference NA - Rashaad Sader, SNC Lavalin
AVEVA World Conference NA - Rashaad Sader, SNC LavalinAVEVA World Conference NA - Rashaad Sader, SNC Lavalin
AVEVA World Conference NA - Rashaad Sader, SNC Lavalin
 
Software Advice BuyerView: Construction Software Report 2014
Software Advice BuyerView: Construction Software Report 2014Software Advice BuyerView: Construction Software Report 2014
Software Advice BuyerView: Construction Software Report 2014
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 

Viewers also liked

Julia Clark Resume' 2
Julia Clark Resume' 2Julia Clark Resume' 2
Julia Clark Resume' 2
Julie Clark
 
New Resume Amol Joshi Delivery Management
New Resume Amol Joshi Delivery ManagementNew Resume Amol Joshi Delivery Management
New Resume Amol Joshi Delivery Management
Amol Joshi
 
Final Resume Syed.compressed
Final Resume Syed.compressedFinal Resume Syed.compressed
Final Resume Syed.compressed
Syed Sirajuddin
 
Resume - Masood Ahmad
Resume - Masood AhmadResume - Masood Ahmad
Resume - Masood Ahmad
Masood Ahmad
 
Nicole L Klein, Resume
Nicole L  Klein, ResumeNicole L  Klein, Resume
Nicole L Klein, Resume
Nicole Klein
 
Rob Gagne Resume
Rob Gagne Resume Rob Gagne Resume
Rob Gagne Resume
Rob Gagne
 
Timothy_Pace_Resume_2016
Timothy_Pace_Resume_2016Timothy_Pace_Resume_2016
Timothy_Pace_Resume_2016
Timothy Pace
 
Kekst ALL 10-21-16
Kekst ALL 10-21-16Kekst ALL 10-21-16
Kekst ALL 10-21-16
Audrey Kekst
 
DeepakTaneja_SE
DeepakTaneja_SEDeepakTaneja_SE
DeepakTaneja_SE
Deepak Taneja
 
Malia Bruhn Resume
Malia Bruhn ResumeMalia Bruhn Resume
Malia Bruhn Resume
Malia Bruhn
 
RAM_resume
RAM_resumeRAM_resume
RAM_resume
Robert A. Menafee
 
Designer - graphics and web
Designer - graphics and webDesigner - graphics and web
Designer - graphics and web
marichter
 
ChrisKorczykResume_December2016
ChrisKorczykResume_December2016ChrisKorczykResume_December2016
ChrisKorczykResume_December2016
Chris Korczyk
 
TB416
TB416TB416
CS_Resume
CS_ResumeCS_Resume
CV-Jayusman
CV-JayusmanCV-Jayusman
CV-Jayusman
Jayusman .
 
JSHolman2016
JSHolman2016JSHolman2016
JSHolman2016
Jeffrey Holman
 

Viewers also liked (17)

Julia Clark Resume' 2
Julia Clark Resume' 2Julia Clark Resume' 2
Julia Clark Resume' 2
 
New Resume Amol Joshi Delivery Management
New Resume Amol Joshi Delivery ManagementNew Resume Amol Joshi Delivery Management
New Resume Amol Joshi Delivery Management
 
Final Resume Syed.compressed
Final Resume Syed.compressedFinal Resume Syed.compressed
Final Resume Syed.compressed
 
Resume - Masood Ahmad
Resume - Masood AhmadResume - Masood Ahmad
Resume - Masood Ahmad
 
Nicole L Klein, Resume
Nicole L  Klein, ResumeNicole L  Klein, Resume
Nicole L Klein, Resume
 
Rob Gagne Resume
Rob Gagne Resume Rob Gagne Resume
Rob Gagne Resume
 
Timothy_Pace_Resume_2016
Timothy_Pace_Resume_2016Timothy_Pace_Resume_2016
Timothy_Pace_Resume_2016
 
Kekst ALL 10-21-16
Kekst ALL 10-21-16Kekst ALL 10-21-16
Kekst ALL 10-21-16
 
DeepakTaneja_SE
DeepakTaneja_SEDeepakTaneja_SE
DeepakTaneja_SE
 
Malia Bruhn Resume
Malia Bruhn ResumeMalia Bruhn Resume
Malia Bruhn Resume
 
RAM_resume
RAM_resumeRAM_resume
RAM_resume
 
Designer - graphics and web
Designer - graphics and webDesigner - graphics and web
Designer - graphics and web
 
ChrisKorczykResume_December2016
ChrisKorczykResume_December2016ChrisKorczykResume_December2016
ChrisKorczykResume_December2016
 
TB416
TB416TB416
TB416
 
CS_Resume
CS_ResumeCS_Resume
CS_Resume
 
CV-Jayusman
CV-JayusmanCV-Jayusman
CV-Jayusman
 
JSHolman2016
JSHolman2016JSHolman2016
JSHolman2016
 

Similar to Technology project manager

Cloud Technology Manager1a
Cloud Technology Manager1aCloud Technology Manager1a
Cloud Technology Manager1a
Rena Cummings MSPM, MSTM
 
Seanresume3-15.docx-2
Seanresume3-15.docx-2Seanresume3-15.docx-2
Seanresume3-15.docx-2
Sean Hedden
 
ESantavicca Resume March-2016
ESantavicca Resume March-2016ESantavicca Resume March-2016
ESantavicca Resume March-2016
Ed Santavicca
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
Kevin Fox, PMP, MBA
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
Kevin Fox, PMP, MBA
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
Kevin Fox, PMP, MBA
 
Jack Holcombe
Jack HolcombeJack Holcombe
Jack Holcombe
jack0352
 
Michael_L_Jones_resume_1_27_15New
Michael_L_Jones_resume_1_27_15NewMichael_L_Jones_resume_1_27_15New
Michael_L_Jones_resume_1_27_15New
Michael Jones
 
Resume_Lehigh_Bruce
Resume_Lehigh_BruceResume_Lehigh_Bruce
Resume_Lehigh_Bruce
Bruce Lehigh
 
Sandra.Schneider(PM) Resume 11-15
Sandra.Schneider(PM) Resume 11-15Sandra.Schneider(PM) Resume 11-15
Sandra.Schneider(PM) Resume 11-15
Sandy Schneider
 
Sheldon cousino resume
Sheldon cousino resumeSheldon cousino resume
Sheldon cousino resume
Sheldon Cousino
 
Profile_Dhananjay_Bhave
Profile_Dhananjay_BhaveProfile_Dhananjay_Bhave
Profile_Dhananjay_Bhave
Dhananjay Bhave
 
Glenn J Melton Resume
Glenn J Melton ResumeGlenn J Melton Resume
Glenn J Melton Resume
gjmelton
 
Blaine Wolff Resume
Blaine Wolff ResumeBlaine Wolff Resume
Blaine Wolff Resume
bwolff52
 
JubrilOgunbunmiC2017WF
JubrilOgunbunmiC2017WFJubrilOgunbunmiC2017WF
JubrilOgunbunmiC2017WF
Jus September
 
Resume G Bisanz Presentation Format
Resume G Bisanz Presentation FormatResume G Bisanz Presentation Format
Resume G Bisanz Presentation Format
Gregory Bisanz
 
Resume_Dhananjay_Bhave
Resume_Dhananjay_BhaveResume_Dhananjay_Bhave
Resume_Dhananjay_Bhave
Dhananjay Bhave
 
Mike_Kuenkel_Complete Resume_20150422
Mike_Kuenkel_Complete Resume_20150422Mike_Kuenkel_Complete Resume_20150422
Mike_Kuenkel_Complete Resume_20150422
Mike Kuenkel
 
Marc Cadden IT PM 3
Marc Cadden IT PM 3Marc Cadden IT PM 3
Marc Cadden IT PM 3
Marc Cadden
 
Nick Edmunds Resume PM
Nick Edmunds Resume PMNick Edmunds Resume PM
Nick Edmunds Resume PM
Nick Edmunds
 

Similar to Technology project manager (20)

Cloud Technology Manager1a
Cloud Technology Manager1aCloud Technology Manager1a
Cloud Technology Manager1a
 
Seanresume3-15.docx-2
Seanresume3-15.docx-2Seanresume3-15.docx-2
Seanresume3-15.docx-2
 
ESantavicca Resume March-2016
ESantavicca Resume March-2016ESantavicca Resume March-2016
ESantavicca Resume March-2016
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
 
Jack Holcombe
Jack HolcombeJack Holcombe
Jack Holcombe
 
Michael_L_Jones_resume_1_27_15New
Michael_L_Jones_resume_1_27_15NewMichael_L_Jones_resume_1_27_15New
Michael_L_Jones_resume_1_27_15New
 
Resume_Lehigh_Bruce
Resume_Lehigh_BruceResume_Lehigh_Bruce
Resume_Lehigh_Bruce
 
Sandra.Schneider(PM) Resume 11-15
Sandra.Schneider(PM) Resume 11-15Sandra.Schneider(PM) Resume 11-15
Sandra.Schneider(PM) Resume 11-15
 
Sheldon cousino resume
Sheldon cousino resumeSheldon cousino resume
Sheldon cousino resume
 
Profile_Dhananjay_Bhave
Profile_Dhananjay_BhaveProfile_Dhananjay_Bhave
Profile_Dhananjay_Bhave
 
Glenn J Melton Resume
Glenn J Melton ResumeGlenn J Melton Resume
Glenn J Melton Resume
 
Blaine Wolff Resume
Blaine Wolff ResumeBlaine Wolff Resume
Blaine Wolff Resume
 
JubrilOgunbunmiC2017WF
JubrilOgunbunmiC2017WFJubrilOgunbunmiC2017WF
JubrilOgunbunmiC2017WF
 
Resume G Bisanz Presentation Format
Resume G Bisanz Presentation FormatResume G Bisanz Presentation Format
Resume G Bisanz Presentation Format
 
Resume_Dhananjay_Bhave
Resume_Dhananjay_BhaveResume_Dhananjay_Bhave
Resume_Dhananjay_Bhave
 
Mike_Kuenkel_Complete Resume_20150422
Mike_Kuenkel_Complete Resume_20150422Mike_Kuenkel_Complete Resume_20150422
Mike_Kuenkel_Complete Resume_20150422
 
Marc Cadden IT PM 3
Marc Cadden IT PM 3Marc Cadden IT PM 3
Marc Cadden IT PM 3
 
Nick Edmunds Resume PM
Nick Edmunds Resume PMNick Edmunds Resume PM
Nick Edmunds Resume PM
 

Recently uploaded

GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
panagenda
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
Kari Kakkonen
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
Neo4j
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
Mariano Tinti
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
Tomaz Bratanic
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
Zilliz
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
IndexBug
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
Aftab Hussain
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
SOFTTECHHUB
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
Neo4j
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 

Recently uploaded (20)

GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 

Technology project manager

  • 1. RENA CUMMINGS, MS Seattle, WA rcummings43@gmail.com www.linkedin.com/in/projectmanager3/ Cell (360)-550-8216 HIGHLIGHTS OF QUALIFICATIONS • MS in Project Manager and Technology Management • Improved SharePoint documentation process predicted cost savings of $75,000 • Achieved cost savings of $800,000 using six sigma and lean applications process • Chaired multiple data review and change management “solution meetings” • Secured a supplier within 30 days despite varying deliverable schedule • Scrum Project Manager co-manage 28 teams to update websites. • Veteran, 20 years of service, specialty in Flight Operations • Research Security impact on Wireless Sensor Cloud Architect KEY KNOWLEDGE AND SKILLS Work-Flow  Project Scheduling  Waterfall Business Process Modeling  Change Management  SDLC  Risk Analysis  Risk Management  Agile Application NoImImprovementImproveme nts  Lean Application   Resource Planning  Data Analysis  Education ● Masters of Science in Technology Management, City University 2014 ● Masters of Science in Project Management, City University 2011 ● BS in Mechanical Engineering, University of Memphis 1998 ● BS in Manufacturing Engineering, University of Memphis 1998 ● IT Security Networking Certificate, Edmonds Community College 2016 ● Scrum Master, CSM, Nityo Infotech expected completion 2016 ● Project Management Professional, PMP, Nittyo Infotech 2016 PROFESSIONAL EXPERIENCE Seattle Give Camp: Microsoft Commons, Bellevue, WA October 2013 – 2015 Scrum Project Manager; volunteer Co-managed 28 teams of Software Developers, Web Developers, Database Administrators to update or create webpages for 28 nonprofit organizations using Agile and Sprint application. As Scrum Master, my responsibility included staying within each project scope, creating requirement analysis, and keeping tasks moving throughout the production pipeline. Engaging with the site -owners providing continuous feedback to the team. Bu s in e s s Pro c e s s Sy s t e m A n a ly s t November 2013 - August 2014 J TS Manag e S e r vi c e s ;Seattle, Washington JTS needed to update its document control operations to meet increased production demands. They want to replace their legacy software system to meet needs of their clients • Applied Business Architect Enterprise methodology to identify inefficient process operations. • Implemented process change management procedures with predicted cost savings of$75,000.00. • Applied Visio and Workflow process modeling diagrams to increase operation effectively by 25 percent. • Project lead and coached team of five on how to improve operation effectiveness • Prepare Data flow to migrate into Share-Point
  • 2. Daimler North America, Portland, Oregon January 2011 - January 2012 Senior Electronic Development Engineer New Product Design Project: Linde Gas Gate-lift project required a specially designed battery to accommodate their new design lift- gate to retrofit 300 trucks. As PM, I led a cross-functional team, which included Linde Gas, sales manager, plant manager and liaisons to create a project plan to retrofit 300 trucks. My tasks included planning phrase lift-gate for pre-production builds and program transition into production phrase Linde Gas Gate-lift deliverable using DFMA methodology to reduce inventory cost. ● Coordinated and verified expectations and design requirements within Linde Gas Company and Daimler North America. ● Managed and monitored the Linde Gas-lift new product line from production to delivery. ● Exceeded the project delivery schedule deadline by 6 months ● Improved resource and inventory scheduling,with cost saving $500,000 in labor. ● Facilitate “solution focus” meeting between plant managers and engineers. ● Analysis production data flow to identify repeated pattern of failures. Boeing, Seattle, Washington July 2008 - June 2010 Project Manager, Manufacturing Flight Test Operations & Validation Engineer Led a cross-functional team of ground engineers, design engineers and production engineers to manufacture 747, 777 and 737 parts in support flight test operations. As a liaison, I created test plans to be implemented by aircraft maintenance crews for operational readiness of the plane. ● Implemented a change management meeting between engineers,and suppliers to secure new part specification. ● Secured a supplier within 30 days despite varying deliverable schedule IMC - Infinite Minde Concept, Seattle WA January 2005- September 2015 CEO/Project Manager Consultant Project lead team of three on modification of El Ranchito’s tamale machine. Project lead of “The Great African Cook-In” ● Implemented project impact analysis on production of tamales with predicted sales ● and cost increased of 46.7 percent ● Submitted bid of $478,000 to install solar panels and windmill in Central Seattle. ● Project team of five on The Great African Cook-In event,with 300 attendants. Siemens Westinghouse,Fort Payne, AL March 2002-March 2004 Project Manager, Product DesignEngineer As project manager, assignments included: ● Chaired multiple data review and change management “solution meetings” ● Implemented change management solution among suppliers resulting in 47% reduction of rework. ● Achieved cost savings of $800,000 using six sigma and lean applications process • Improved operational workflow efficiency by 25 percent in 12 mos. • Analysis production data flow to identify repeated pattern of tube failures. Graduate Dissertation: City University October 2011 MS in Project Management Project Lead - Cloud Web: Based – Hospital Patient Billing System ● Managed two global teams; project scope to created a patient web based health care billing-system ● Collaborated on the planning and execution phrase of the cloud base application ● Used Microsoft Azure: Cloud Base Database to create the web based system MS in Technology Management October 2014 Daimler North America: Technology Pilot Infrastructure Proposal Mercedes Benz parent global company of Daimler North America was conducting an extensive global infrastructure upgrade using cloud-based technology to synchronize their business around the globe. ● Created a cloud technology SQL Azure application proposal that would implement SQL database technology and provide a seamless cloud integration that synchronizes and connects all employees and instances globally ● Identified core issues identified throughout Daimler’s global work force that impedes IT infrastructure production ● Created Service and Technical Enterprise Architecture solutions on IT infrastructure cloud-based upgrade proposal ● Research security impact on Wireless Sensor Cloud Architecture.