SlideShare a Scribd company logo
Tary B. Burritt
919 Kentbury Court Katy Texas 77450
Message Phone: (321) 432-8992 Home: 281 676-4942
E-mail: waveslider53@yahoo.com
EXPERIENCE: Worked in the construction industry since 1970.
Conam
BPXA Prudhoe Bay Alaska
E&I Quality Control (QC) Supervisor-Jan.2016 to present
FS3-EOA:
Supervisor the E&I QC Field Technicians. Coordinate with client (BP) QA, Project engineers, project
managers, superintendents, general foreman, doc control, commissioning, FCO and the BP turnover coordinator to
complete MC1 systems and turn them over as scheduled to the client. These duties include all the E&I documents,
redlines and required instruments/tubing & associated materials to complete the project. These duties include the
demolition of existing systems and installation of new Modules, equipment, instruments/tubing and materials.
Bergaila Engineering Group (BEG)
HESS Oil Company
Minot North Dakota
E&I Supervisor-March 2013 to October 2015
Bakken Shale-Keene Area South of the River
Responsible for the oversight of the installation Contractors involved in the HESS well site builds, to include
civil, structural, piping/mechanical and E&I installations. Requesting and overseeing the temporary power
generation for these remote sites and coordination of the permanent power installations with the local utility.
Preform receiving inspections, daily reports and plan site walk downs and turnover inspections.
Alaska Frontier Constructors Inc.
ExxonMobil/Worley Parsons-Flour
Electrical Superintendent/Field Engineer/QA-QC-Feb.2012 to Feb 2013
Field Installation Manager-March 2013-to present.
Pt. Thomson Project:
Project pre-planning for the Pt. Thomson Project including interface meeting with Worley Parsons, Exxon Mobil
and sub-contractors. QA/QC ITP & ITF development- building and submittal for Client approval. Installation &
oversight of the project Temp. Helipad, Permanent 350 men camp, Permanent Runway/Airstrip &
FAA support Systems, Installation of several project support buildings and modules.
Office bldg.., warehouse, incinerator, hazmat bldg., cold storage bldg., and other life safety systems. Plan and
oversee installation of the above listed project phases. This is to include design review, material review,
DFO and turn over docs for commissioning team. We are currently in the field for installation phase.
Udelhoven Oilfield Systems Services
Conoco Phillips
Electrical Estimator/Field Engineer/QC-Sept.2009 to Jan. 2012
Beluga Compressor upgrades project.
Alpine CD3 Pipe Rack Extension project
Alpine AWH Water Handling project
Kuparuk Projects
Pre-Project estimating and pre-planning in Anchorage
Some of my pre-project duties were E&I estimating using the WIN EST version 12.1 estimating software and JD
Edwards software. The on the job portion of my position, E&I field engineer was to review drawings, prepare work
packages, and submit a proposal package along with the Project Management team and the two Conoco Phillips
Construction Group for approval. I was also responsible for E&I field modification to existing designs to include
installation & writing of electrical/instrument, and mech. /arch. RFI/PCR’s for any changes to the drawings or scope
of work. An additional duty is to keep all the records for the electrical installations work and work with QA/QC on
any electrical installation issues. Attended daily tool-box meeting with the Electrical team and filled in as alternate
Electrical Superintendent. Near the end of the project I will work as the electrical turn-over coordinator if needed,
and have attended the daily turn-over meeting and set-up system walk downs for turn over to Operations/Conoco
Phillips.
Tary B. Burritt Resume’ Page 2
Udelhoven Oilfield Systems Services
Conoco Phillips
Electrical Estimator/Field Engineer/QC-May 2008 to Aug.2009
Alpine CD2/CD4 Pipe Rack Extension
Alpine Water Handling Project
Pre-Project: estimating and project set-up in Anchorage. The Qannik/CD2 expansion. I worked as E&I QC.
The CD4 Pipe Rack Extension portion of the job was estimated with our own excel data base /spread sheet. The
second portion; Water Handling portion of the project (AWH) was estimated using the WIN EST version 11.9
estimating software and JD Edwards software. The on the job portion of my position, electrical field engineering
was to review drawings, prepare work packages, work with the field foreman/superintendent, correspond with the
CH2MHILL engineering group, Conoco Phillips TA’s and the O&M electrical group for corrections needed (red
line drawings) to complete the installations of each system per the scope of work. I also wrote all the
electrical/instrument RFI/PCR’s for any changes to the drawings or scope of work, attended daily and weekly
progress meetings with Conoco Phillips. I created lists for SS cable tags, conductor wire tags, and Phenolic tags to
be made for cables, j-boxes, heat trace, and Instrument Panels. Kept all the records for the electrical installations
work and worked with QA/QC on any electrical installation issues. Attended daily tool-box meeting with the
Electrical team and filled in as alternate Electrical Superintendent. Near the end of the project, I was the electrical
turn-over coordinator and helped build the FCO folders, attended the daily turn-over meeting and set-up system
walk downs for turn over to FCO/Conoco Phillips.
VECO/CH2MHill
E/I Quality Control Supervisor – May 2006 to 2008
Alpine CD3/CD4 Project
Conoco Phillips
Built and QC inspected the 13 kV power and fiber lines to two different drill sites for a total of 16 miles,
crossing several rivers and rough terrain, in adverse weather. These were mounted below the pipeline on
Messenger cable. Involved in all inspections, splicing, cable high pot testing, TDR testing of fiber. Prepared
Documentation for turnover to client. Involved in final turn over package building and implementation of these
Packages and meetings with client.
Oougarook Project/PIONEER OILFIELD RESOURCES
Over saw construction of modules in Anchorage at the Fab shop before shipment to Prudhoe Bay. Worked with field
engineers to identify issues, wrote estimates and work orders. Addressed code issues, researched materials, attended
meetings with client to ready modules for both an offshore drill site (6 miles out in the frozen ocean) and an onshore
site for metering, power generation and distribution (25 kV subsea feeders). Attended client meetings at the North
Slope job site. Set up all record keeping and forms for project inspections concerning electrical and instrumentation
work.
Strategic Reconfiguration Project (SR) ALYESKA PIPELINE
Responsible for all project documentation and inspections concerning electrical/instrumentation,
medium voltage cabling, Siemens dual fuel generators, back-up diesel generation and UPS backup
systems. Control modules, fuel gas skids, mainline pumps and booster pumps, control modules,
communication modules, VFD drives and all testing of cables and torques for documentation for
turnover to client.
CONAM
Conoco Phillips
Journeyman Electrician – February 2006 to May 2006
Alpine CD3/CD4 Project
Supervisor: Tim Jones
Project Start-up, CD3 Electrical Reim, IWL, Scope work
Terminated conductors entering the Remote Electrical /Inst. Module.
Tary B. Burritt Resume’ Page 3
INDUSTRIAL ELECTRIC, INC.
Electrician Foreman/ Superintendent – May 2004 to May 2005
Fairbanks, Alaska – First National Bank of Alaska and Fairbanks Fire Station/Headquarters
Commercial and industrial type of electrical installation involving rigid metallic conduit and installation and
Termination of power and lighting circuits. Installation of motor control centers, programmable logic
Controllers and uninterruptible power supply systems. Use of low voltage testing equipment, such as fluke
multimeters, and meggers.
ALLSTAR ELECTRICAL SERVICES
Melbourne Beach, Florida – Electrical Service Company
Partner/Electrician – October 2002 to April 2004
Electrical Service Contractor – July 1999 to February 2000
Commercial and residential service work.
CONAM
BRITISH PETROLEUM
Journeyman Electrician -S.P.O.C. June 2002 through September 2002
Journeyman Electrician –S.P.O.C- August 1990 through January 1991
Milne Point Project
Worked as a Single Point of Contact (S.P.O.C.) at the S-Pad, Milne Point Project. Worked on MCC cabinets,
PLC cabinets, fire and gas systems, motor control systems, heat trace, cable tray systems, UPS systems and HVAC
systems for Class I Division I and II locations. IWL/QC.
ALASKA PETROLEUM CONTRACTORS
Conoco Phillips-Kuparuk, Alaska
Journeyman Electrician – October 2001 to June 2002
Journeyman Electrician/Instrument Technician – February 1991 to July 1991
Maintenance Contract
Responsible for maintenance, troubleshooting, repair, installation and construction of industrial electrical
Equipment and systems through the proper use of standard wire, conduit, fittings and hardware commonly found in
petrochemical facilities. Read and understand drawings, schematics and specifications. Bend, cut, thread and installed
conduit; installed and terminated wiring; checked and troubleshoot electric circuits, electrical devises and machinery.
Responsible for use and care of my tools and equipment, such as hydraulic/electric benders, knockout punch sets,
cable puller, meggers, high-pot equipment, volt meters multi-testers and ammeters. Test, troubleshoot, set and
calibrate power distribution systems, work with protective relaying and motor control circuits. Worked to set and
coordinate over current protective devices, size feeder circuits and work on systems up to and including 13.8 KV.
Routinely performed safety and productivity observations; shop, field, and vehicle inspections; and have attended
various technical, developmental safety training. Working knowledge of the National Electrical Code and have an
understanding of electrical circuits including the operation and function of typical electrical devices and machinery,
such as; solenoids, relays, motors, transformers, switches, motor control centers, generators, batteries and lighting
systems. Experienced working in Class One Division I and II areas and understand Lock-out/Tag-out procedures.
INDUSTRIAL ELECTRIC, INC.
Fairbanks, Alaska – University of Alaska, Fairbanks – Auditorium/Dormitory Project, Museum Project
Journeyman Electrician/Foreman – August 2001 to October 2001
Journeyman Electrician/Foreman – May 1997 to July 1999
Primary duties included the repair, maintenance and installation of industrial process equipment including
motors, generators, controls, high and low voltage gear, HVAC equipment, power distribution panels, emergency
generators, multiphase motors, variable speed controllers, analog and digital computer interface devices,
programmable controls and associated wiring, as well as all calibration associated with instrumentation. Performed
both installation and wiring of associated equipment. Installation panels, conduit, wiring for industrial boilers,
including control circuit wiring
Tary B. Burritt Resume’ Page 4
Additional work history and experience available upon request.
SPECIAL TRAINING/EDUCATION:
State of Alaska: Journeyman Electrician License #115988
State of North Dakota: Electrician J-Man License
NSTC Card holder since 1990
NFPA 70E Awareness Cert.
Documents for Operations (DFO) Supervisor
TMCX2 Cert., 2016
3M Cert., 2016
State of California: General Contractor’s License #642085
COMPUTER SKILLS:
Share Point, EDDI,
MS Word, Excel, Power Point, and Outlook
Journeyman Electrician License #115988
State of North Dakota Electrician J-Man License
Data Entry, Spreadsheets
WIN-EST Estimating Software
JD Edwards’s software systems
Southern California Regional Occupation Center
Computer Operations Certificate, spring of 1992

More Related Content

What's hot

Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons
 
Senior Controls System Designer
Senior Controls System DesignerSenior Controls System Designer
Senior Controls System DesignerRoger Pelletier
 
Ahart resume
Ahart resumeAhart resume
Ahart resume
Andy Hart
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers
 
CV - Wright, James R
CV - Wright, James RCV - Wright, James R
CV - Wright, James RJames Wright
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland
 
James Nimmo CV -2015-E&I-
James Nimmo CV -2015-E&I-James Nimmo CV -2015-E&I-
James Nimmo CV -2015-E&I-Stevie Nimmo
 
MOHAMMED AKBAR Sr MEP Mech_Engr
MOHAMMED AKBAR Sr MEP Mech_EngrMOHAMMED AKBAR Sr MEP Mech_Engr
MOHAMMED AKBAR Sr MEP Mech_EngrMohammed Akbar
 
Sandher Updated Resume15
Sandher Updated Resume15Sandher Updated Resume15
Sandher Updated Resume15Sandher Subayno
 
Zaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed
 
Instrument and Control Engineer
Instrument and Control EngineerInstrument and Control Engineer
Instrument and Control Engineer
VICTORIA NGOZI U.
 

What's hot (20)

KEVIN DAVID MORTON cv
KEVIN DAVID MORTON cvKEVIN DAVID MORTON cv
KEVIN DAVID MORTON cv
 
Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_
 
Merrit CV
Merrit CVMerrit CV
Merrit CV
 
RA CV Current
RA CV CurrentRA CV Current
RA CV Current
 
rod wimberly
rod wimberlyrod wimberly
rod wimberly
 
Senior Controls System Designer
Senior Controls System DesignerSenior Controls System Designer
Senior Controls System Designer
 
Irfan-Mohammad
Irfan-MohammadIrfan-Mohammad
Irfan-Mohammad
 
Ahart resume
Ahart resumeAhart resume
Ahart resume
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
 
CV - Wright, James R
CV - Wright, James RCV - Wright, James R
CV - Wright, James R
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum Vitae
 
CV2014
CV2014CV2014
CV2014
 
nestor
nestornestor
nestor
 
James Nimmo CV -2015-E&I-
James Nimmo CV -2015-E&I-James Nimmo CV -2015-E&I-
James Nimmo CV -2015-E&I-
 
Sathish Kumar-Resume.
Sathish Kumar-Resume.Sathish Kumar-Resume.
Sathish Kumar-Resume.
 
RESUME 2015
RESUME 2015RESUME 2015
RESUME 2015
 
MOHAMMED AKBAR Sr MEP Mech_Engr
MOHAMMED AKBAR Sr MEP Mech_EngrMOHAMMED AKBAR Sr MEP Mech_Engr
MOHAMMED AKBAR Sr MEP Mech_Engr
 
Sandher Updated Resume15
Sandher Updated Resume15Sandher Updated Resume15
Sandher Updated Resume15
 
Zaheer Ahmed E&I Professional
Zaheer Ahmed E&I ProfessionalZaheer Ahmed E&I Professional
Zaheer Ahmed E&I Professional
 
Instrument and Control Engineer
Instrument and Control EngineerInstrument and Control Engineer
Instrument and Control Engineer
 

Viewers also liked

Resume Emily Fodor UF
Resume Emily Fodor UFResume Emily Fodor UF
Resume Emily Fodor UF
Emily Fodor
 
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANO
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANOLorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANO
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANOdanypastrano
 
Metia_B2B_Marketers_Guide_Social_Media_Advertising
Metia_B2B_Marketers_Guide_Social_Media_AdvertisingMetia_B2B_Marketers_Guide_Social_Media_Advertising
Metia_B2B_Marketers_Guide_Social_Media_AdvertisingAlan Miller
 
Sri porque glosa
Sri porque glosaSri porque glosa
Sri porque glosa
Jorge Ceron
 
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum EfficiencyDeploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
Amazon Web Services
 
3 клас. Корнієнко. Урок 3,4. Носії повідомлень
3 клас. Корнієнко. Урок 3,4. Носії повідомлень3 клас. Корнієнко. Урок 3,4. Носії повідомлень
3 клас. Корнієнко. Урок 3,4. Носії повідомлень
Дмитро Загура
 
1 การพัฒนาที่ยั่งยืน
1 การพัฒนาที่ยั่งยืน1 การพัฒนาที่ยั่งยืน
1 การพัฒนาที่ยั่งยืน
Watcharin Chongkonsatit
 
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
HxRefactored
 
Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)
Gautham Sankaraselvam
 
Regression lineaire simple
Regression lineaire simpleRegression lineaire simple
Regression lineaire simple
Mehdi Rajawi
 

Viewers also liked (12)

Resume Emily Fodor UF
Resume Emily Fodor UFResume Emily Fodor UF
Resume Emily Fodor UF
 
RESUME-2017
RESUME-2017RESUME-2017
RESUME-2017
 
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANO
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANOLorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANO
Lorti (LEY ORGÁNICA DE TRIBUTARIA INTERNA) POR DANIEL PASTRANO
 
Metia_B2B_Marketers_Guide_Social_Media_Advertising
Metia_B2B_Marketers_Guide_Social_Media_AdvertisingMetia_B2B_Marketers_Guide_Social_Media_Advertising
Metia_B2B_Marketers_Guide_Social_Media_Advertising
 
SUBLIMACÍON
SUBLIMACÍONSUBLIMACÍON
SUBLIMACÍON
 
Sri porque glosa
Sri porque glosaSri porque glosa
Sri porque glosa
 
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum EfficiencyDeploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
Deploying a Disaster Recovery Site on AWS: Minimal Cost with Maximum Efficiency
 
3 клас. Корнієнко. Урок 3,4. Носії повідомлень
3 клас. Корнієнко. Урок 3,4. Носії повідомлень3 клас. Корнієнко. Урок 3,4. Носії повідомлень
3 клас. Корнієнко. Урок 3,4. Носії повідомлень
 
1 การพัฒนาที่ยั่งยืน
1 การพัฒนาที่ยั่งยืน1 การพัฒนาที่ยั่งยืน
1 การพัฒนาที่ยั่งยืน
 
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
HXR 2016: Content Strategy: How Do we Talk About Healthcare - Marli Mesibov &...
 
Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)
 
Regression lineaire simple
Regression lineaire simpleRegression lineaire simple
Regression lineaire simple
 

Similar to TBResume 2016 update

Josh Resume 11_18_2016
Josh Resume 11_18_2016Josh Resume 11_18_2016
Josh Resume 11_18_2016Smith Joshua
 
Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015Devin Howell
 
Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea
 
Alwin CV 032016_neW.
Alwin CV 032016_neW.Alwin CV 032016_neW.
Alwin CV 032016_neW.Alwin Jose
 
Ww CV 2016
Ww CV 2016Ww CV 2016
Ww CV 2016
Walt Williams
 
Ww cv 2016
Ww cv 2016Ww cv 2016
Ww cv 2016
Walt Williams
 
Tom van wyk c.v.
Tom van wyk c.v.Tom van wyk c.v.
Tom van wyk c.v.
TOM VAN WYK
 
Cameron dipple resume
Cameron dipple resumeCameron dipple resume
Cameron dipple resume
Cameron Dipple
 
Bidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan Dey
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
shaik karimulla
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
shaik karimulla
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
shaik karimulla
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATRommel Siasat
 

Similar to TBResume 2016 update (20)

ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
Josh Resume 11_18_2016
Josh Resume 11_18_2016Josh Resume 11_18_2016
Josh Resume 11_18_2016
 
Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015
 
PathakA Resume
PathakA ResumePathakA Resume
PathakA Resume
 
RES-Philip.Harper
RES-Philip.HarperRES-Philip.Harper
RES-Philip.Harper
 
Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea. CV October 2016
Richard Kildea. CV October 2016
 
Alwin CV 032016_neW.
Alwin CV 032016_neW.Alwin CV 032016_neW.
Alwin CV 032016_neW.
 
EJP CV_January2016
EJP CV_January2016EJP CV_January2016
EJP CV_January2016
 
Ww CV 2016
Ww CV 2016Ww CV 2016
Ww CV 2016
 
Ww cv 2016
Ww cv 2016Ww cv 2016
Ww cv 2016
 
Tom van wyk c.v.
Tom van wyk c.v.Tom van wyk c.v.
Tom van wyk c.v.
 
RichmondApande PM
RichmondApande PMRichmondApande PM
RichmondApande PM
 
Cameron dipple resume
Cameron dipple resumeCameron dipple resume
Cameron dipple resume
 
MAraziR-1 (1)
MAraziR-1 (1)MAraziR-1 (1)
MAraziR-1 (1)
 
Bidhan R DEY-Resume
Bidhan R DEY-ResumeBidhan R DEY-Resume
Bidhan R DEY-Resume
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
 
Kareem cv updated
Kareem cv  updatedKareem cv  updated
Kareem cv updated
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
 
Michael%20Weir-3
Michael%20Weir-3Michael%20Weir-3
Michael%20Weir-3
 

TBResume 2016 update

  • 1. Tary B. Burritt 919 Kentbury Court Katy Texas 77450 Message Phone: (321) 432-8992 Home: 281 676-4942 E-mail: waveslider53@yahoo.com EXPERIENCE: Worked in the construction industry since 1970. Conam BPXA Prudhoe Bay Alaska E&I Quality Control (QC) Supervisor-Jan.2016 to present FS3-EOA: Supervisor the E&I QC Field Technicians. Coordinate with client (BP) QA, Project engineers, project managers, superintendents, general foreman, doc control, commissioning, FCO and the BP turnover coordinator to complete MC1 systems and turn them over as scheduled to the client. These duties include all the E&I documents, redlines and required instruments/tubing & associated materials to complete the project. These duties include the demolition of existing systems and installation of new Modules, equipment, instruments/tubing and materials. Bergaila Engineering Group (BEG) HESS Oil Company Minot North Dakota E&I Supervisor-March 2013 to October 2015 Bakken Shale-Keene Area South of the River Responsible for the oversight of the installation Contractors involved in the HESS well site builds, to include civil, structural, piping/mechanical and E&I installations. Requesting and overseeing the temporary power generation for these remote sites and coordination of the permanent power installations with the local utility. Preform receiving inspections, daily reports and plan site walk downs and turnover inspections. Alaska Frontier Constructors Inc. ExxonMobil/Worley Parsons-Flour Electrical Superintendent/Field Engineer/QA-QC-Feb.2012 to Feb 2013 Field Installation Manager-March 2013-to present. Pt. Thomson Project: Project pre-planning for the Pt. Thomson Project including interface meeting with Worley Parsons, Exxon Mobil and sub-contractors. QA/QC ITP & ITF development- building and submittal for Client approval. Installation & oversight of the project Temp. Helipad, Permanent 350 men camp, Permanent Runway/Airstrip & FAA support Systems, Installation of several project support buildings and modules. Office bldg.., warehouse, incinerator, hazmat bldg., cold storage bldg., and other life safety systems. Plan and oversee installation of the above listed project phases. This is to include design review, material review, DFO and turn over docs for commissioning team. We are currently in the field for installation phase. Udelhoven Oilfield Systems Services Conoco Phillips Electrical Estimator/Field Engineer/QC-Sept.2009 to Jan. 2012 Beluga Compressor upgrades project. Alpine CD3 Pipe Rack Extension project Alpine AWH Water Handling project Kuparuk Projects Pre-Project estimating and pre-planning in Anchorage Some of my pre-project duties were E&I estimating using the WIN EST version 12.1 estimating software and JD Edwards software. The on the job portion of my position, E&I field engineer was to review drawings, prepare work packages, and submit a proposal package along with the Project Management team and the two Conoco Phillips Construction Group for approval. I was also responsible for E&I field modification to existing designs to include installation & writing of electrical/instrument, and mech. /arch. RFI/PCR’s for any changes to the drawings or scope of work. An additional duty is to keep all the records for the electrical installations work and work with QA/QC on any electrical installation issues. Attended daily tool-box meeting with the Electrical team and filled in as alternate Electrical Superintendent. Near the end of the project I will work as the electrical turn-over coordinator if needed, and have attended the daily turn-over meeting and set-up system walk downs for turn over to Operations/Conoco Phillips.
  • 2. Tary B. Burritt Resume’ Page 2 Udelhoven Oilfield Systems Services Conoco Phillips Electrical Estimator/Field Engineer/QC-May 2008 to Aug.2009 Alpine CD2/CD4 Pipe Rack Extension Alpine Water Handling Project Pre-Project: estimating and project set-up in Anchorage. The Qannik/CD2 expansion. I worked as E&I QC. The CD4 Pipe Rack Extension portion of the job was estimated with our own excel data base /spread sheet. The second portion; Water Handling portion of the project (AWH) was estimated using the WIN EST version 11.9 estimating software and JD Edwards software. The on the job portion of my position, electrical field engineering was to review drawings, prepare work packages, work with the field foreman/superintendent, correspond with the CH2MHILL engineering group, Conoco Phillips TA’s and the O&M electrical group for corrections needed (red line drawings) to complete the installations of each system per the scope of work. I also wrote all the electrical/instrument RFI/PCR’s for any changes to the drawings or scope of work, attended daily and weekly progress meetings with Conoco Phillips. I created lists for SS cable tags, conductor wire tags, and Phenolic tags to be made for cables, j-boxes, heat trace, and Instrument Panels. Kept all the records for the electrical installations work and worked with QA/QC on any electrical installation issues. Attended daily tool-box meeting with the Electrical team and filled in as alternate Electrical Superintendent. Near the end of the project, I was the electrical turn-over coordinator and helped build the FCO folders, attended the daily turn-over meeting and set-up system walk downs for turn over to FCO/Conoco Phillips. VECO/CH2MHill E/I Quality Control Supervisor – May 2006 to 2008 Alpine CD3/CD4 Project Conoco Phillips Built and QC inspected the 13 kV power and fiber lines to two different drill sites for a total of 16 miles, crossing several rivers and rough terrain, in adverse weather. These were mounted below the pipeline on Messenger cable. Involved in all inspections, splicing, cable high pot testing, TDR testing of fiber. Prepared Documentation for turnover to client. Involved in final turn over package building and implementation of these Packages and meetings with client. Oougarook Project/PIONEER OILFIELD RESOURCES Over saw construction of modules in Anchorage at the Fab shop before shipment to Prudhoe Bay. Worked with field engineers to identify issues, wrote estimates and work orders. Addressed code issues, researched materials, attended meetings with client to ready modules for both an offshore drill site (6 miles out in the frozen ocean) and an onshore site for metering, power generation and distribution (25 kV subsea feeders). Attended client meetings at the North Slope job site. Set up all record keeping and forms for project inspections concerning electrical and instrumentation work. Strategic Reconfiguration Project (SR) ALYESKA PIPELINE Responsible for all project documentation and inspections concerning electrical/instrumentation, medium voltage cabling, Siemens dual fuel generators, back-up diesel generation and UPS backup systems. Control modules, fuel gas skids, mainline pumps and booster pumps, control modules, communication modules, VFD drives and all testing of cables and torques for documentation for turnover to client. CONAM Conoco Phillips Journeyman Electrician – February 2006 to May 2006 Alpine CD3/CD4 Project Supervisor: Tim Jones Project Start-up, CD3 Electrical Reim, IWL, Scope work Terminated conductors entering the Remote Electrical /Inst. Module.
  • 3. Tary B. Burritt Resume’ Page 3 INDUSTRIAL ELECTRIC, INC. Electrician Foreman/ Superintendent – May 2004 to May 2005 Fairbanks, Alaska – First National Bank of Alaska and Fairbanks Fire Station/Headquarters Commercial and industrial type of electrical installation involving rigid metallic conduit and installation and Termination of power and lighting circuits. Installation of motor control centers, programmable logic Controllers and uninterruptible power supply systems. Use of low voltage testing equipment, such as fluke multimeters, and meggers. ALLSTAR ELECTRICAL SERVICES Melbourne Beach, Florida – Electrical Service Company Partner/Electrician – October 2002 to April 2004 Electrical Service Contractor – July 1999 to February 2000 Commercial and residential service work. CONAM BRITISH PETROLEUM Journeyman Electrician -S.P.O.C. June 2002 through September 2002 Journeyman Electrician –S.P.O.C- August 1990 through January 1991 Milne Point Project Worked as a Single Point of Contact (S.P.O.C.) at the S-Pad, Milne Point Project. Worked on MCC cabinets, PLC cabinets, fire and gas systems, motor control systems, heat trace, cable tray systems, UPS systems and HVAC systems for Class I Division I and II locations. IWL/QC. ALASKA PETROLEUM CONTRACTORS Conoco Phillips-Kuparuk, Alaska Journeyman Electrician – October 2001 to June 2002 Journeyman Electrician/Instrument Technician – February 1991 to July 1991 Maintenance Contract Responsible for maintenance, troubleshooting, repair, installation and construction of industrial electrical Equipment and systems through the proper use of standard wire, conduit, fittings and hardware commonly found in petrochemical facilities. Read and understand drawings, schematics and specifications. Bend, cut, thread and installed conduit; installed and terminated wiring; checked and troubleshoot electric circuits, electrical devises and machinery. Responsible for use and care of my tools and equipment, such as hydraulic/electric benders, knockout punch sets, cable puller, meggers, high-pot equipment, volt meters multi-testers and ammeters. Test, troubleshoot, set and calibrate power distribution systems, work with protective relaying and motor control circuits. Worked to set and coordinate over current protective devices, size feeder circuits and work on systems up to and including 13.8 KV. Routinely performed safety and productivity observations; shop, field, and vehicle inspections; and have attended various technical, developmental safety training. Working knowledge of the National Electrical Code and have an understanding of electrical circuits including the operation and function of typical electrical devices and machinery, such as; solenoids, relays, motors, transformers, switches, motor control centers, generators, batteries and lighting systems. Experienced working in Class One Division I and II areas and understand Lock-out/Tag-out procedures. INDUSTRIAL ELECTRIC, INC. Fairbanks, Alaska – University of Alaska, Fairbanks – Auditorium/Dormitory Project, Museum Project Journeyman Electrician/Foreman – August 2001 to October 2001 Journeyman Electrician/Foreman – May 1997 to July 1999 Primary duties included the repair, maintenance and installation of industrial process equipment including motors, generators, controls, high and low voltage gear, HVAC equipment, power distribution panels, emergency generators, multiphase motors, variable speed controllers, analog and digital computer interface devices, programmable controls and associated wiring, as well as all calibration associated with instrumentation. Performed both installation and wiring of associated equipment. Installation panels, conduit, wiring for industrial boilers, including control circuit wiring
  • 4. Tary B. Burritt Resume’ Page 4 Additional work history and experience available upon request. SPECIAL TRAINING/EDUCATION: State of Alaska: Journeyman Electrician License #115988 State of North Dakota: Electrician J-Man License NSTC Card holder since 1990 NFPA 70E Awareness Cert. Documents for Operations (DFO) Supervisor TMCX2 Cert., 2016 3M Cert., 2016 State of California: General Contractor’s License #642085 COMPUTER SKILLS: Share Point, EDDI, MS Word, Excel, Power Point, and Outlook Journeyman Electrician License #115988 State of North Dakota Electrician J-Man License Data Entry, Spreadsheets WIN-EST Estimating Software JD Edwards’s software systems Southern California Regional Occupation Center Computer Operations Certificate, spring of 1992