SlideShare a Scribd company logo
SUSOL
AIR CIRCUIT BREAKER
BASIC FUNCTION
■ ACB prevents a fire, a property damage, the breakage of an electrical
equipment on load side by protecting a circuit from the fault currents.
1. Circuit Closing
The closing operation of mechanism applies the current to the load. When
energized, some loads makes inrush current much greater than rated current (In)
(e.g. Motor takes in 7~8times of In for a few seconds). To prevent these over current
which causes the dangerous phenomena for contacts (Erosion by arcs), closing
operation should be prompt. If a circuit breaker is in accordance with all standard
cases, it should be able to endure 15~20 times of the rated current and be opened
promptly for the faults occurred during closing operation or after it has closed.
2. Current Conducting
A circuit breaker must not be exceeding an acceptable temperature rise
under normal current conducting and there must be safe current conducting within
specified breaking time under over current. Furthermore, if a circuit breaker is of the
discriminated type, it must has the structure which can withstand the high
electrodynamics to accept the short-circuit current while a circuit breaker in
downstream is operating to break it.
BASIC FUNCTION
3. Circuit Opening, Current Breaking
1) Current can be broken manually or remotely by voluntary operation on
mechanism.
2) A circuit breaker opens a circuit automatically under condition of current which
may has any values at this time by an auxiliary trip unit (Under voltage, Ground fault,
etc.)
3) A circuit breaker opens a circuit automatically against the over current because it
is operated by OCR (the trip unit) even if it is in the closed position.
4. Isolation
When a circuit breaker is open, a certain isolation level is required between
charging and non-charging parts. The Isolation Level is decided by following tests.
1) A maximum leakage current test under rated using voltage (Max. Ue)
2) An impulse voltage
BASIC FUNCTION
■ There are following breaking principles regarding over current.
1. Instantaneous trip
When short-circuit current flows in, ACB trips instantly to minimize side
effect due to the accident on load side. It is called instantaneous trip.
2. Time delay breaking
When abnormal current flows in such as inrush current of transformer or
condenser, and starting current of motor, ACB keeps the conducting condition for a
regular time and break the current if it is continuously remained. In case of short-
circuit, ACB minimizes the damage from accident by keeping the circuit for the time
previously set concerning the operating time of branch breakers under selective
discrimination. However, it breaks the circuit after the delayed time in case
abnormal current continuously flows in due to the breaking failure of branch
breakers. It is called as Time delayed breaking.
BASIC FUNCTION
3. Overload trip
If the current which exceeds the rated current flows in continuously, the
cable is getting hotter and it causes the big fire. Therefore, ACB breaks the
current before the temperature of cable reaches the dangerous level. It is called
overload trip.
4. Ground-fault trip
Ground fault defines as current flows into the ground from circuit or charging
part of load due to breakdown. If ground fault current flows, it is inducted to other
cables nearby owing to electronic induction, voltage level is risen and it finally cause
severe effects or damage on other device. Furthermore, in case personnel hands are
touched, it may result in electrical shock. Ground fault breaking is to prevent any
possible accident occurred from ground fault.
BASIC FUNCTION
• lcu=lcs=150kA/500Vac
• W=785(3P),1015(4P)mm
50
63
4000AF
5000AF
6300AF
40
• lcu=lcs=100kA/500Vac
• W=412(3P),527(4P)mm
25
32
40
2000AF
2500AF
3200AF
4000AF
20
• lcu=lcs=85kA/500Vac
• W=334(3P),419(4P)mm
08
10
13
16
630AF
800AF
1000AF
1250AF
1600AF
06
W=334mm
H=430mm
W=412mm W=785mm
AH-06~20D/W AH-20~40E/X AH-40~63G/Z
D=375mm
FULL LINE-UP
H=460mm
RATING PLATE
Main nameplate
Secondary
nameplate
MAIN NAMEPLATE
TYPE
AH 630AF~6300AF
Phase Array
D Standard RST(N) For
630AF~2000AF
W Reverse NRST
For 630AF~2000AF
E Standard RST(N) For
2000AF~4000AF
X Reverse NRST
For 2000AF~4000AF
G Standard RST(N) For
4000AF~6300AF
Z Reverse NRST
For 4000AF~6300AF
AH – 10 D 3 – 10 A
1 2 3 5 6
4
1 3
Ampere frame
06 630AF
08 800AF
10 1000AF
13 1250AF
~ ~
32 3200AF
40 4000AF
50 5000AF
63 6300AF
2
No. of pole
3 3 pole
4 4 pole
4
Reted current (CT Spect.)
02 200A
~ ~
63 6300A
5
Connections
J Manual [Draw-out type]
A Automatic [Draw-out type]
H Horizontal [Fix type]
V Vertical [ Fix type]
M Line : Horizontal, Load :
Vertical [Fix type]
N Line : Vertical, Load :
Horizontal [Fix type]
6
Cradle nameplate
AL – H16D 3 – A H F S
1 2 3 5 6
4 7
1
2
3
5
6
4
7
LS ACB
CRADLE
Rated Current & frame
H06~16D AH-06~16D
H20D AH-20D
H20~32E AH-20~32E
H40E AH-40E
H40~50G AH-40~50G
H63G AH-63G
No. of pole
3 3 pole
4 4 pole
Terminal
connections
J Manual
connection
A Automatic
connection
Connections
H Horizontal type
(H20D inapplicable)
V Vertical type
M Mixed type
Line : Horizontal
Load : Vertical
(H20D inapplicable)
N Mixed type
Line : Vertical
Load : Horizontal
(H20D inapplicable)
P Front type
(40E, 50FG, 63G
inapplicable)
Safety
Shutter
E Without
safety
shutter
F With
safety
shutter
Arc cover
N Without
Arc cover
S With
Arc cover
SECONDARY NAMEPLATE
Motor rated voltage
MA Without
motor
M1 AC/DC
100V~130V
M2 AC/DC
200V~250V
M2 D2 D2 BX AC6 U2 A4
1 2 3 4 5 6 7
1
Closing coil rated
voltage
D0 Without
Closing coil
D1 AC/DC
100V~130V
D2 AC/DC
200V~250V
2
Aux.contact &
charging types
AX Standard OFF-
Charge 3a3b
AC Standard ON-
Charge 3a3b
BX Standard OFF-
Charge 5a5b
BC Standard ON-
Charge 5a5b
4
Shunt coil rated
voltage
D0 Without
Shunt coil
D1 AC/DC
100V~130V
D2 AC/DC
200V~250V
3 Trip relay
AG6 L/S/I/G Protection, without Comm.,
AC/DC100V~250V, 50Hz
AC6 L/S/I/G Protection, with Comm.,
AC/DC100V~250V, 50Hz
5
UVT coil rated
voltage
U0 Without
UVT coil
U1 AC/DC
100V~130V
U2 AC/DC
200V~250V
6 Option
C Counter
A4 AL1+MRB+RES
(AC200~250V)
7
CHARGING THE CIRCUIT BREAKER
 Manual charging
1. Pull the handle down 7~8 times until you hear a "clack".
2. When the closing spring is completely charged, the charging indicator shows
“CHARGED”.
The springs in the circuit breaker operating mechanism must be charged to store
the energy required to close the main contacts. The springs may be charged
manually using the charging handle or the optional motorize.
CHARGING THE CIRCUIT BREAKER
 Electrical charging
1. Energize terminal U1~U2 for automatic charging
2. When the closing spring is completely charged, the geared motor is stop
automatically and the charging indicator shows “CHARGED”.
U1
U2
Power supply
for motor
MANUAL OPERATION
■ Manual closing
1. Push ON button.
2. The breaker will be closed.
3. The ON/OFF indicator
shows “ON” and the charging
indicator shows
“DISCHARGED”.
■ Manual opening
1. Push the OFF button and
breaker will be tripped.
2. The ON/OFF indicator
shows “OFF”.
ELECTRICAL OPERATION
■ Electrical opening
1. Remote opening can be made by energizing the shunt trip device or under
voltage trip device.
2. In the case of SHT, apply the rated voltage to the terminal C1 and C2.
3. In the case of UVT, remote opening is also possible by applying a short -
circuit across terminals D1 and D2 of the UVT controller.
■ Electrical closing
Remote closing can be made by energizing the closing coil
(CC). Apply
the rated voltage to the control terminals A1 and A2 and close the
breaker.
ACCESSORIES CONFIGURATIONS
OCR
UVT CC
SHT
AUX
Motor
Accessories Configurations
􀓋When a circuit breaker is tripped by OCR which
operates against the faulty current
(Over Current Relay), Trip Alarm switch provides the
information regarding the trip of circuit
breaker by sending the electrical signal from the
mechanical indicator on main cover of main
circuit breaker or internal auxiliary switch. (Installed
at the inside of circuit breaker)
Trip Alarm Contact [AL]
Accessories Configurations
Manual Reset Button [MRB]
􀓋It is a function which resets a circuit
breaker manually when a circuit breaker is tripped by OCR.
Accessories Configurations
􀓋Following tripping, this function resets the "fault trip" alarm contacts(AL) and
the mechanical
indicator(MRB) and enables circuit breaker closing.
Push button swich : AC 125V 10A, AC 250V 6A, DC 110V 2.2A, DC 220V 1.1A
Registive load
Remote Reset Switch [RES]
Wiring diagram of Control circuit
Connection terminals
Connection terminals
Connection terminals
Jack Control terminal
Example connection crimp contact
A B B
A
Female crimp contact
Draw-in operation
1. Pull the extension
rails of cradle forward
2. Put the breaker on the rail by
using lifting device. Please
check if the circuit breaker fits
well to the cradle.
3. Slowly push the circuit
breaker by moving the rail
handle until it stops.
Draw-in operation
4. Keep pushing the OFF button when the circuit breaker in a trip condition, and insert a
handle to the body of the circuit breaker.
5. Check the draw-out handle properly inserted and then push the lock plate and turn
the draw-out handle clockwise in order to insert the breaker.
6. When the breaker reaches the TEST position, the lock plate automatically projects
and the draw-out handle is locked.
7. Push in the lock plate and turn the draw-out handle again clockwise until the lock
plate projects, the inserting operation is finished. At this time, the draw-out position
indicator shows CONNECTED position.
Operating handle of cradle only can be inserted when
pushing OFF button.
If locking device for draw in/out protrudes, stop handle
operation and move to next procedure as it indicates the
complete operation of ongoing process.
Draw-in operation
Draw-out operation
■ Draw-out operation procedure
1. Keep pushing the OFF button when the circuit breaker in a trip condition, and
insert a handle to the body of the circuit breaker.
2. Check the draw-out handle properly inserted and then push the lock plate and
turn the draw-out handle counterclockwise in order to insert the breaker.
3. When the breaker reaches the TEST position, the lock plate automatically projects
and the draw-out handle is locked.
4. Push in the lock plate and turn the draw-out handle again counterclockwise until
the lock plate projects, At this time, the draw-out operation is finished with indicator
which shows DISCONNECTED position.
Draw-out operation
Draw-out operation
Draw-out operation
5. The circuit breaker indicated with ‘DISCONNECTED’ can be separated safely from
the cradle by removing a draw in/out handle and releasing right and left locks.
6. Use a lifting hook to separate a circuit breaker from a cradle.
Phase Array
R S T N N R S T
Standard type RST(N)  Reverse phase type NRST
Installation Recommendation
1. Cables connections
Make sure that no excessive mechanical force put
on the rear terminals for cable connection.
Installation Recommendation
2. Bus-bar connections
For busbar connection, connect access parts with a provided torque and
fix with parallel installing the support not to apply terminal weight to circuit
breaker.
Digital Trip Relay
 L/S/I/G  L/S/I/G  L/S/I/G  L/S/I/G
 Self Power  Current (R/S/T/N)  Current, Power,
Energy, Frequency
Current, Power,
Energy, Frequency
 Self Power
 AC/DC 100~250V
 AC/DC 24~60V
 Self Power
 AC/DC 100~250V
 AC/DC 24~60V
 Self Power
 AC/DC 100~250V
 AC/DC 24~60V
 10 Records
(Fault/Current/Date and
Time)
 256 Records
(Fault/Current/Date
and Time)
 256 Records
(Fault/Current/Date and
Time)
256 Records
(Fault/Current/Date
and Time)
256 Records
(Fault/Current/Date and
Time)
Digital Trip Relay
① Graphic LCD: Indication of measurement and information
② LED: Indication of trip info. and overload state
Comm: LED indicating comm. state (Blink when running)
Ig: LED indicating ground-fault
Isd/Ii: LED indicating short-time or instantaneous tripping
Ir: LED indicating long-time delay
SP: Self-protection LED and battery test LED
Alarm: LED indicating an overload
(Turn on above 90%, Blink above 105%)
③ Key: Move to menu or reset
Reset/ESC: Fault reset or ESC from menu
Enter: Enter into secondary menu or setting input
Up/Down: Move the cursor up/down on screen or
increase/decrease a setting value
Right/Left: Move the cursor or setting right/left on screen
(Rotation)
Menu: Menu display ↔ Measurement display
④ Ir: Long-time current setting, tr: Long-time tripping delay
setting
⑤ Isd: Short-time current setting, tsd: Short-time tripping
delay setting
⑥ Ii: Instantaneous current setting
⑦ Ig: Ground fault current setting, tg: Ground fault tripping
delay setting
⑧ Test terminal: OCR test terminal (Connected with OCR
tester)
Digital Trip Relay
Voltage module
For P and S type Trip relay, separate voltage module is provided to measure other
element besides current
- Voltage input range: AC 60~690V
Operation of S type Trip Relay
Menu Tree
Operation of S type Trip Relay
1. Measurement element display
Operation of S type Trip Relay
Operation of S type Trip Relay
2.1. Device H/W Setting – Wiring Setting
Operation of S type Trip Relay
2.2. Device H/W Setting – Communication Setting
Operation of S type Trip Relay
2.3. Device H/W Setting – Password Setting
Operation of S type Trip Relay
2.4. Device H/W Setting – Time Setting
Operation of S type Trip Relay
2.5. Device H/W Setting – Demand Setting
Operation of S type Trip Relay
2.6. Device H/W Setting – Data Reset
Operation of S type Trip Relay
2.7. Device H/W Setting – DO Setting
Operation of S type Trip Relay
2.8. Device H/W Setting – DO Setting
Operation of S type Trip Relay
3.1. Relay Set – Fine Adjustment OCR Setting
Operation of S type Trip Relay
3.2. Relay Set – Fine Adjustment OCR Setting
Operation of S type Trip Relay
3.3. Relay Set – Fine Adjustment OCGR Setting
Operation of S type Trip Relay
Relay Set – Fine Adjustment OCGR Setting
Operation of S type Trip Relay
3.4. Relay Set – OVR/UVR Setting
Operation of S type Trip Relay
Relay Set – OVR/UVR Setting
Operation of S type Trip Relay
Relay Set – OVR/UVR Setting
Operation of S type Trip Relay
3.5. Relay Set – Voltage/Current Unbalance Setting
Operation of S type Trip Relay
Relay Set – Voltage/Current Unbalance Setting
Operation of S type Trip Relay
Relay Set – Voltage/Current Unbalance Setting
Operation of S type Trip Relay
3.6. Relay Set – Reverse Power
Operation of S type Trip Relay
Relay Set – Reverse Power
Operation of S type Trip Relay
3.7. Relay Set – Over/Under Frequency Setting
Operation of S type Trip Relay
Relay Set – Over/Under Frequency Setting
Operation of S type Trip Relay
4.1. Event Information Display
Operation of S type Trip Relay
4.2. Fault Information Display
Operation of S type Trip Relay
4.3. Event/Fault Information Deletion
Operation of S type Trip Relay
5. System Information Display
Operation of S type Trip Relay
6. Local/Remote Setting
Operating Characteristic
The function for overload protection which has time delayed
characteristic in inverse ratio to fault current.
1. Standard current setting knob: Ir
1) Setting range in P type and S type: (0.4-0.5-0.6-0.7-0.8-0.9-
1.0)×In
2) Setting range in N type and A type: (0.4 ~1.0)×In
- Iu: (0.5-0.6-0.7-0.8-0.9-1.0)×In
- Ir: (0.8-0.83-0.85-0.88-0.9-0.93-0.95-0.98-1.0)×Iu
2. Time delay setting knob: tr
- Standard operating time is based on the time of 6×Ir
- Setting range: 0.5-1-2-4-8-12-16-20-Off sec (9 modes)
3. Relay pick-up current
- When current over (1.15)×Ir flows in, relay is picked up.
4. Relay operates basing on the largest load current among
R/S/T/N phase.
Long-time delay (L)
Operating Characteristic
Short-time delay (S)
The function for fault current (over current) protection which has
definite
time characteristic and time delayed in inverse ratio to fault
current.
1. Standard current setting knob: Isd
- Setting range: (1.5-2-3-4-5-6-8-10-Off)×Ir
2. Time delay setting knob: tsd
- Standard operating time is based on the time of 10×Ir.
- Inverse time (I2t On ): 0.1-0.2-0.3-0.4 sec
- Definite time (I2t Off): 0.05-0.1-0.2-0.3-0.4 sec
3. Relay operates basing on the largest load current among R/S/T/N
phase.
4. Relay can operate at instantaneous current through ZSI.
Operating Characteristic
Instantaneous (I)
The function for breaking fault current above the setting value
within
the shortest time to protect the circuit from short-circuit.
1. Standard current setting knob: Ii
- Setting range: (2-3-4-6-8-10-12-15-Off)×In
2. Relay operates basing on the largest load current among
R/S/T/N phase.
3. Total breaking time is below 50ms.
Operating Characteristic
Ground Fault (G)
The function for breaking ground fault current above
setting value
after time-delay to protect the circuit from ground fault.
1. Standard setting current knob: Ig
- Setting range: (0.2-0.3-0.4-0.5-0.6-0.7-0.8-1.0-Off)×In
2. Time delay setting knob: tg
- Inverse time (I2t On): 0.1-0.2-0.3-0.4 sec
- Definite time (I2t Off): 0.05-0.1-0.2-0.3-0.4 sec
3. Ground fault current =R+S+T+N(Vector Sum)
4. Relay can operate at instantaneous current through ZSI.
5. The protection for ground fault is a basic function of Trip
relay (Internal CT type)
THANK YOU

More Related Content

What's hot

Eplan simbologia - simbolos eléctricos
Eplan   simbologia - simbolos eléctricosEplan   simbologia - simbolos eléctricos
Eplan simbologia - simbolos eléctricosJoaquín Briz
 
Guia montaje de tablero electrico domiciliario con circuito basico
Guia montaje de tablero electrico domiciliario con circuito basicoGuia montaje de tablero electrico domiciliario con circuito basico
Guia montaje de tablero electrico domiciliario con circuito basico
Nialito
 
Circuitos Eléctricos de Control y Diagramas Fuerza
Circuitos Eléctricos de Control y Diagramas FuerzaCircuitos Eléctricos de Control y Diagramas Fuerza
Circuitos Eléctricos de Control y Diagramas Fuerza
Bernardo Jesús Sahagún Martín del Campo
 
Fusibles
FusiblesFusibles
Generator protection
Generator protectionGenerator protection
Generator protection
Parimal Bhagat
 
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
jksjmdmd
 
Placa de características generador
Placa de características generadorPlaca de características generador
Placa de características generador
Juan Pablo Martínez Lorrio
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Sheikh Nazmul Islam
 
Abb transformer handbook abb
Abb transformer handbook abbAbb transformer handbook abb
Abb transformer handbook abb
Alex Carmo
 
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...Otorongosabroso
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
Himmelstern
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
TanvirkabirShishir
 
Transformer
TransformerTransformer
Transformer
Sandeep Kumar
 
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
SANTIAGO PABLO ALBERTO
 
Presentacion lvsim-ems - resumen rev.0
Presentacion   lvsim-ems - resumen rev.0Presentacion   lvsim-ems - resumen rev.0
Presentacion lvsim-ems - resumen rev.0
Nestor A
 
Lecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptxLecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptx
AniruddhaRay11
 
Copper Cable Lugs and Terminals Catalogue
Copper Cable Lugs and Terminals CatalogueCopper Cable Lugs and Terminals Catalogue
Copper Cable Lugs and Terminals Catalogue
Grey Hawk Electricals
 
Motores DC & Variadores de Velocidad
Motores DC  & Variadores de VelocidadMotores DC  & Variadores de Velocidad
Motores DC & Variadores de Velocidad
Angel Castillo
 

What's hot (20)

Eplan simbologia - simbolos eléctricos
Eplan   simbologia - simbolos eléctricosEplan   simbologia - simbolos eléctricos
Eplan simbologia - simbolos eléctricos
 
Guia montaje de tablero electrico domiciliario con circuito basico
Guia montaje de tablero electrico domiciliario con circuito basicoGuia montaje de tablero electrico domiciliario con circuito basico
Guia montaje de tablero electrico domiciliario con circuito basico
 
Circuitos Eléctricos de Control y Diagramas Fuerza
Circuitos Eléctricos de Control y Diagramas FuerzaCircuitos Eléctricos de Control y Diagramas Fuerza
Circuitos Eléctricos de Control y Diagramas Fuerza
 
Fusibles
FusiblesFusibles
Fusibles
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
Caterpillar cat gc15 k forklift lift trucks service repair manual snat81d 000...
 
Placa de características generador
Placa de características generadorPlaca de características generador
Placa de características generador
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Abb transformer handbook abb
Abb transformer handbook abbAbb transformer handbook abb
Abb transformer handbook abb
 
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...
Dimensionamiento de los motores y generadores en aplicaciones de energía eléc...
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Transformer
TransformerTransformer
Transformer
 
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
Electrónica digital: Electrónica digital microprogramable por Fernando Blanco...
 
Presentacion lvsim-ems - resumen rev.0
Presentacion   lvsim-ems - resumen rev.0Presentacion   lvsim-ems - resumen rev.0
Presentacion lvsim-ems - resumen rev.0
 
Lecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptxLecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptx
 
Semaforo, deposito de agua y bombas alternadas ..plc
Semaforo, deposito de agua y bombas alternadas ..plcSemaforo, deposito de agua y bombas alternadas ..plc
Semaforo, deposito de agua y bombas alternadas ..plc
 
Copper Cable Lugs and Terminals Catalogue
Copper Cable Lugs and Terminals CatalogueCopper Cable Lugs and Terminals Catalogue
Copper Cable Lugs and Terminals Catalogue
 
Motores DC & Variadores de Velocidad
Motores DC  & Variadores de VelocidadMotores DC  & Variadores de Velocidad
Motores DC & Variadores de Velocidad
 

Similar to Susol ACB Cyber Training.ppt

Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
Satish Pydimarla
 
161122 lbs ass_e
161122 lbs ass_e161122 lbs ass_e
161122 lbs ass_e
sibarak
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
vikas kumar
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
Ashwani Kumar
 
LV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptxLV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptx
shivendra68
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
DigantaSinha1
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
Md Hasan
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
Aman Rajput
 
Hướng dẫn sử dụng biến tần
Hướng dẫn sử dụng biến tầnHướng dẫn sử dụng biến tần
Hướng dẫn sử dụng biến tần
Hồng Trọng
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
srijan tripathi
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Rahul Prajapati
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
pk130992
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
Wipro
 
L.v tech presentation 2
L.v tech presentation 2L.v tech presentation 2
power house training seminar
power house training seminarpower house training seminar
power house training seminar
Paras kumar
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
Himansu Pradhan
 

Similar to Susol ACB Cyber Training.ppt (20)

Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
161122 lbs ass_e
161122 lbs ass_e161122 lbs ass_e
161122 lbs ass_e
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
LV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptxLV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptx
 
bhuwnesh
bhuwneshbhuwnesh
bhuwnesh
 
Lm555
Lm555Lm555
Lm555
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
Hướng dẫn sử dụng biến tần
Hướng dẫn sử dụng biến tầnHướng dẫn sử dụng biến tần
Hướng dẫn sử dụng biến tần
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Wp series manual
Wp series manualWp series manual
Wp series manual
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
L.v tech presentation 2
L.v tech presentation 2L.v tech presentation 2
L.v tech presentation 2
 
power house training seminar
power house training seminarpower house training seminar
power house training seminar
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 

Susol ACB Cyber Training.ppt

  • 2. BASIC FUNCTION ■ ACB prevents a fire, a property damage, the breakage of an electrical equipment on load side by protecting a circuit from the fault currents. 1. Circuit Closing The closing operation of mechanism applies the current to the load. When energized, some loads makes inrush current much greater than rated current (In) (e.g. Motor takes in 7~8times of In for a few seconds). To prevent these over current which causes the dangerous phenomena for contacts (Erosion by arcs), closing operation should be prompt. If a circuit breaker is in accordance with all standard cases, it should be able to endure 15~20 times of the rated current and be opened promptly for the faults occurred during closing operation or after it has closed. 2. Current Conducting A circuit breaker must not be exceeding an acceptable temperature rise under normal current conducting and there must be safe current conducting within specified breaking time under over current. Furthermore, if a circuit breaker is of the discriminated type, it must has the structure which can withstand the high electrodynamics to accept the short-circuit current while a circuit breaker in downstream is operating to break it.
  • 3. BASIC FUNCTION 3. Circuit Opening, Current Breaking 1) Current can be broken manually or remotely by voluntary operation on mechanism. 2) A circuit breaker opens a circuit automatically under condition of current which may has any values at this time by an auxiliary trip unit (Under voltage, Ground fault, etc.) 3) A circuit breaker opens a circuit automatically against the over current because it is operated by OCR (the trip unit) even if it is in the closed position. 4. Isolation When a circuit breaker is open, a certain isolation level is required between charging and non-charging parts. The Isolation Level is decided by following tests. 1) A maximum leakage current test under rated using voltage (Max. Ue) 2) An impulse voltage
  • 4. BASIC FUNCTION ■ There are following breaking principles regarding over current. 1. Instantaneous trip When short-circuit current flows in, ACB trips instantly to minimize side effect due to the accident on load side. It is called instantaneous trip. 2. Time delay breaking When abnormal current flows in such as inrush current of transformer or condenser, and starting current of motor, ACB keeps the conducting condition for a regular time and break the current if it is continuously remained. In case of short- circuit, ACB minimizes the damage from accident by keeping the circuit for the time previously set concerning the operating time of branch breakers under selective discrimination. However, it breaks the circuit after the delayed time in case abnormal current continuously flows in due to the breaking failure of branch breakers. It is called as Time delayed breaking.
  • 5. BASIC FUNCTION 3. Overload trip If the current which exceeds the rated current flows in continuously, the cable is getting hotter and it causes the big fire. Therefore, ACB breaks the current before the temperature of cable reaches the dangerous level. It is called overload trip. 4. Ground-fault trip Ground fault defines as current flows into the ground from circuit or charging part of load due to breakdown. If ground fault current flows, it is inducted to other cables nearby owing to electronic induction, voltage level is risen and it finally cause severe effects or damage on other device. Furthermore, in case personnel hands are touched, it may result in electrical shock. Ground fault breaking is to prevent any possible accident occurred from ground fault.
  • 7. • lcu=lcs=150kA/500Vac • W=785(3P),1015(4P)mm 50 63 4000AF 5000AF 6300AF 40 • lcu=lcs=100kA/500Vac • W=412(3P),527(4P)mm 25 32 40 2000AF 2500AF 3200AF 4000AF 20 • lcu=lcs=85kA/500Vac • W=334(3P),419(4P)mm 08 10 13 16 630AF 800AF 1000AF 1250AF 1600AF 06 W=334mm H=430mm W=412mm W=785mm AH-06~20D/W AH-20~40E/X AH-40~63G/Z D=375mm FULL LINE-UP H=460mm
  • 9. MAIN NAMEPLATE TYPE AH 630AF~6300AF Phase Array D Standard RST(N) For 630AF~2000AF W Reverse NRST For 630AF~2000AF E Standard RST(N) For 2000AF~4000AF X Reverse NRST For 2000AF~4000AF G Standard RST(N) For 4000AF~6300AF Z Reverse NRST For 4000AF~6300AF AH – 10 D 3 – 10 A 1 2 3 5 6 4 1 3 Ampere frame 06 630AF 08 800AF 10 1000AF 13 1250AF ~ ~ 32 3200AF 40 4000AF 50 5000AF 63 6300AF 2 No. of pole 3 3 pole 4 4 pole 4 Reted current (CT Spect.) 02 200A ~ ~ 63 6300A 5 Connections J Manual [Draw-out type] A Automatic [Draw-out type] H Horizontal [Fix type] V Vertical [ Fix type] M Line : Horizontal, Load : Vertical [Fix type] N Line : Vertical, Load : Horizontal [Fix type] 6
  • 10. Cradle nameplate AL – H16D 3 – A H F S 1 2 3 5 6 4 7 1 2 3 5 6 4 7 LS ACB CRADLE Rated Current & frame H06~16D AH-06~16D H20D AH-20D H20~32E AH-20~32E H40E AH-40E H40~50G AH-40~50G H63G AH-63G No. of pole 3 3 pole 4 4 pole Terminal connections J Manual connection A Automatic connection Connections H Horizontal type (H20D inapplicable) V Vertical type M Mixed type Line : Horizontal Load : Vertical (H20D inapplicable) N Mixed type Line : Vertical Load : Horizontal (H20D inapplicable) P Front type (40E, 50FG, 63G inapplicable) Safety Shutter E Without safety shutter F With safety shutter Arc cover N Without Arc cover S With Arc cover
  • 11. SECONDARY NAMEPLATE Motor rated voltage MA Without motor M1 AC/DC 100V~130V M2 AC/DC 200V~250V M2 D2 D2 BX AC6 U2 A4 1 2 3 4 5 6 7 1 Closing coil rated voltage D0 Without Closing coil D1 AC/DC 100V~130V D2 AC/DC 200V~250V 2 Aux.contact & charging types AX Standard OFF- Charge 3a3b AC Standard ON- Charge 3a3b BX Standard OFF- Charge 5a5b BC Standard ON- Charge 5a5b 4 Shunt coil rated voltage D0 Without Shunt coil D1 AC/DC 100V~130V D2 AC/DC 200V~250V 3 Trip relay AG6 L/S/I/G Protection, without Comm., AC/DC100V~250V, 50Hz AC6 L/S/I/G Protection, with Comm., AC/DC100V~250V, 50Hz 5 UVT coil rated voltage U0 Without UVT coil U1 AC/DC 100V~130V U2 AC/DC 200V~250V 6 Option C Counter A4 AL1+MRB+RES (AC200~250V) 7
  • 12. CHARGING THE CIRCUIT BREAKER  Manual charging 1. Pull the handle down 7~8 times until you hear a "clack". 2. When the closing spring is completely charged, the charging indicator shows “CHARGED”. The springs in the circuit breaker operating mechanism must be charged to store the energy required to close the main contacts. The springs may be charged manually using the charging handle or the optional motorize.
  • 13. CHARGING THE CIRCUIT BREAKER  Electrical charging 1. Energize terminal U1~U2 for automatic charging 2. When the closing spring is completely charged, the geared motor is stop automatically and the charging indicator shows “CHARGED”. U1 U2 Power supply for motor
  • 14. MANUAL OPERATION ■ Manual closing 1. Push ON button. 2. The breaker will be closed. 3. The ON/OFF indicator shows “ON” and the charging indicator shows “DISCHARGED”. ■ Manual opening 1. Push the OFF button and breaker will be tripped. 2. The ON/OFF indicator shows “OFF”.
  • 15. ELECTRICAL OPERATION ■ Electrical opening 1. Remote opening can be made by energizing the shunt trip device or under voltage trip device. 2. In the case of SHT, apply the rated voltage to the terminal C1 and C2. 3. In the case of UVT, remote opening is also possible by applying a short - circuit across terminals D1 and D2 of the UVT controller. ■ Electrical closing Remote closing can be made by energizing the closing coil (CC). Apply the rated voltage to the control terminals A1 and A2 and close the breaker.
  • 17. Accessories Configurations 􀓋When a circuit breaker is tripped by OCR which operates against the faulty current (Over Current Relay), Trip Alarm switch provides the information regarding the trip of circuit breaker by sending the electrical signal from the mechanical indicator on main cover of main circuit breaker or internal auxiliary switch. (Installed at the inside of circuit breaker) Trip Alarm Contact [AL]
  • 18. Accessories Configurations Manual Reset Button [MRB] 􀓋It is a function which resets a circuit breaker manually when a circuit breaker is tripped by OCR.
  • 19. Accessories Configurations 􀓋Following tripping, this function resets the "fault trip" alarm contacts(AL) and the mechanical indicator(MRB) and enables circuit breaker closing. Push button swich : AC 125V 10A, AC 250V 6A, DC 110V 2.2A, DC 220V 1.1A Registive load Remote Reset Switch [RES]
  • 20. Wiring diagram of Control circuit
  • 24. Jack Control terminal Example connection crimp contact A B B A Female crimp contact
  • 25. Draw-in operation 1. Pull the extension rails of cradle forward 2. Put the breaker on the rail by using lifting device. Please check if the circuit breaker fits well to the cradle. 3. Slowly push the circuit breaker by moving the rail handle until it stops.
  • 26. Draw-in operation 4. Keep pushing the OFF button when the circuit breaker in a trip condition, and insert a handle to the body of the circuit breaker. 5. Check the draw-out handle properly inserted and then push the lock plate and turn the draw-out handle clockwise in order to insert the breaker. 6. When the breaker reaches the TEST position, the lock plate automatically projects and the draw-out handle is locked. 7. Push in the lock plate and turn the draw-out handle again clockwise until the lock plate projects, the inserting operation is finished. At this time, the draw-out position indicator shows CONNECTED position. Operating handle of cradle only can be inserted when pushing OFF button. If locking device for draw in/out protrudes, stop handle operation and move to next procedure as it indicates the complete operation of ongoing process.
  • 28. Draw-out operation ■ Draw-out operation procedure 1. Keep pushing the OFF button when the circuit breaker in a trip condition, and insert a handle to the body of the circuit breaker. 2. Check the draw-out handle properly inserted and then push the lock plate and turn the draw-out handle counterclockwise in order to insert the breaker. 3. When the breaker reaches the TEST position, the lock plate automatically projects and the draw-out handle is locked. 4. Push in the lock plate and turn the draw-out handle again counterclockwise until the lock plate projects, At this time, the draw-out operation is finished with indicator which shows DISCONNECTED position.
  • 31. Draw-out operation 5. The circuit breaker indicated with ‘DISCONNECTED’ can be separated safely from the cradle by removing a draw in/out handle and releasing right and left locks. 6. Use a lifting hook to separate a circuit breaker from a cradle.
  • 32. Phase Array R S T N N R S T Standard type RST(N)  Reverse phase type NRST
  • 33. Installation Recommendation 1. Cables connections Make sure that no excessive mechanical force put on the rear terminals for cable connection.
  • 34. Installation Recommendation 2. Bus-bar connections For busbar connection, connect access parts with a provided torque and fix with parallel installing the support not to apply terminal weight to circuit breaker.
  • 35. Digital Trip Relay  L/S/I/G  L/S/I/G  L/S/I/G  L/S/I/G  Self Power  Current (R/S/T/N)  Current, Power, Energy, Frequency Current, Power, Energy, Frequency  Self Power  AC/DC 100~250V  AC/DC 24~60V  Self Power  AC/DC 100~250V  AC/DC 24~60V  Self Power  AC/DC 100~250V  AC/DC 24~60V  10 Records (Fault/Current/Date and Time)  256 Records (Fault/Current/Date and Time)  256 Records (Fault/Current/Date and Time) 256 Records (Fault/Current/Date and Time) 256 Records (Fault/Current/Date and Time)
  • 36. Digital Trip Relay ① Graphic LCD: Indication of measurement and information ② LED: Indication of trip info. and overload state Comm: LED indicating comm. state (Blink when running) Ig: LED indicating ground-fault Isd/Ii: LED indicating short-time or instantaneous tripping Ir: LED indicating long-time delay SP: Self-protection LED and battery test LED Alarm: LED indicating an overload (Turn on above 90%, Blink above 105%) ③ Key: Move to menu or reset Reset/ESC: Fault reset or ESC from menu Enter: Enter into secondary menu or setting input Up/Down: Move the cursor up/down on screen or increase/decrease a setting value Right/Left: Move the cursor or setting right/left on screen (Rotation) Menu: Menu display ↔ Measurement display ④ Ir: Long-time current setting, tr: Long-time tripping delay setting ⑤ Isd: Short-time current setting, tsd: Short-time tripping delay setting ⑥ Ii: Instantaneous current setting ⑦ Ig: Ground fault current setting, tg: Ground fault tripping delay setting ⑧ Test terminal: OCR test terminal (Connected with OCR tester)
  • 37. Digital Trip Relay Voltage module For P and S type Trip relay, separate voltage module is provided to measure other element besides current - Voltage input range: AC 60~690V
  • 38. Operation of S type Trip Relay Menu Tree
  • 39. Operation of S type Trip Relay 1. Measurement element display
  • 40. Operation of S type Trip Relay
  • 41. Operation of S type Trip Relay 2.1. Device H/W Setting – Wiring Setting
  • 42. Operation of S type Trip Relay 2.2. Device H/W Setting – Communication Setting
  • 43. Operation of S type Trip Relay 2.3. Device H/W Setting – Password Setting
  • 44. Operation of S type Trip Relay 2.4. Device H/W Setting – Time Setting
  • 45. Operation of S type Trip Relay 2.5. Device H/W Setting – Demand Setting
  • 46. Operation of S type Trip Relay 2.6. Device H/W Setting – Data Reset
  • 47. Operation of S type Trip Relay 2.7. Device H/W Setting – DO Setting
  • 48. Operation of S type Trip Relay 2.8. Device H/W Setting – DO Setting
  • 49. Operation of S type Trip Relay 3.1. Relay Set – Fine Adjustment OCR Setting
  • 50. Operation of S type Trip Relay 3.2. Relay Set – Fine Adjustment OCR Setting
  • 51. Operation of S type Trip Relay 3.3. Relay Set – Fine Adjustment OCGR Setting
  • 52. Operation of S type Trip Relay Relay Set – Fine Adjustment OCGR Setting
  • 53. Operation of S type Trip Relay 3.4. Relay Set – OVR/UVR Setting
  • 54. Operation of S type Trip Relay Relay Set – OVR/UVR Setting
  • 55. Operation of S type Trip Relay Relay Set – OVR/UVR Setting
  • 56. Operation of S type Trip Relay 3.5. Relay Set – Voltage/Current Unbalance Setting
  • 57. Operation of S type Trip Relay Relay Set – Voltage/Current Unbalance Setting
  • 58. Operation of S type Trip Relay Relay Set – Voltage/Current Unbalance Setting
  • 59. Operation of S type Trip Relay 3.6. Relay Set – Reverse Power
  • 60. Operation of S type Trip Relay Relay Set – Reverse Power
  • 61. Operation of S type Trip Relay 3.7. Relay Set – Over/Under Frequency Setting
  • 62. Operation of S type Trip Relay Relay Set – Over/Under Frequency Setting
  • 63. Operation of S type Trip Relay 4.1. Event Information Display
  • 64. Operation of S type Trip Relay 4.2. Fault Information Display
  • 65. Operation of S type Trip Relay 4.3. Event/Fault Information Deletion
  • 66. Operation of S type Trip Relay 5. System Information Display
  • 67. Operation of S type Trip Relay 6. Local/Remote Setting
  • 68. Operating Characteristic The function for overload protection which has time delayed characteristic in inverse ratio to fault current. 1. Standard current setting knob: Ir 1) Setting range in P type and S type: (0.4-0.5-0.6-0.7-0.8-0.9- 1.0)×In 2) Setting range in N type and A type: (0.4 ~1.0)×In - Iu: (0.5-0.6-0.7-0.8-0.9-1.0)×In - Ir: (0.8-0.83-0.85-0.88-0.9-0.93-0.95-0.98-1.0)×Iu 2. Time delay setting knob: tr - Standard operating time is based on the time of 6×Ir - Setting range: 0.5-1-2-4-8-12-16-20-Off sec (9 modes) 3. Relay pick-up current - When current over (1.15)×Ir flows in, relay is picked up. 4. Relay operates basing on the largest load current among R/S/T/N phase. Long-time delay (L)
  • 69. Operating Characteristic Short-time delay (S) The function for fault current (over current) protection which has definite time characteristic and time delayed in inverse ratio to fault current. 1. Standard current setting knob: Isd - Setting range: (1.5-2-3-4-5-6-8-10-Off)×Ir 2. Time delay setting knob: tsd - Standard operating time is based on the time of 10×Ir. - Inverse time (I2t On ): 0.1-0.2-0.3-0.4 sec - Definite time (I2t Off): 0.05-0.1-0.2-0.3-0.4 sec 3. Relay operates basing on the largest load current among R/S/T/N phase. 4. Relay can operate at instantaneous current through ZSI.
  • 70. Operating Characteristic Instantaneous (I) The function for breaking fault current above the setting value within the shortest time to protect the circuit from short-circuit. 1. Standard current setting knob: Ii - Setting range: (2-3-4-6-8-10-12-15-Off)×In 2. Relay operates basing on the largest load current among R/S/T/N phase. 3. Total breaking time is below 50ms.
  • 71. Operating Characteristic Ground Fault (G) The function for breaking ground fault current above setting value after time-delay to protect the circuit from ground fault. 1. Standard setting current knob: Ig - Setting range: (0.2-0.3-0.4-0.5-0.6-0.7-0.8-1.0-Off)×In 2. Time delay setting knob: tg - Inverse time (I2t On): 0.1-0.2-0.3-0.4 sec - Definite time (I2t Off): 0.05-0.1-0.2-0.3-0.4 sec 3. Ground fault current =R+S+T+N(Vector Sum) 4. Relay can operate at instantaneous current through ZSI. 5. The protection for ground fault is a basic function of Trip relay (Internal CT type)