SlideShare a Scribd company logo
VTT TECHNICAL RESEARCH CENTRE OF FINLAND LTD
Risk management based on
proper material selection,
advanced monitoring and
remote maintenance
Jouko Suokas, Executive Vice President
VTT
226/06/2015 2
Outline
Drivers and needs
Background
Risk based inspection (RBI)
FFS assessment
Lifing concepts and case examples
Preventive maintenance – VTT solution (Tolkku toolbox)
Remote maintenance
RAMS analysis
Gas turbine air filter performance evaluation
Concluding remarks
326/06/2015 3
Drivers and needs
 Drivers
 Productivity, efficiency
 Ageing assets, availability and reliability
 HSE targets
 Increased need for
 Critical asset evaluation, risk analysis
 Predicting and managing safe life
 Correct targeting and timing of
maintenance
 Deferring investments
426/06/2015 4
Life Cycle Management
New facility Operation Ageing and
retrofitting
 Conceptualization
 Design phases
 Manufacturing
 Construction and
installation
 Commissioning and
start-up
 Operation and maintenance
 Technical and operational
changes
 Ageing management
 Modernization
 Retrofits
 Investment decisions
Presentation focus
526/06/2015 5
Risk based inspection (RBI)
In refineries/petrochemical industry often aligned to API RP 581
‘Risk-based Inspection Technology’:
 To develop inspection plans for pressurized fixed equipment
 Sections on inspection planning, determining probability of failure (PoF), and
consequence (CoF) modelling
 Focus on impact and benefit from inspections, assumes time-independent
consequences
When critical items have been identified by RBI, VTT can e.g.
 Analyse the criticality, condition and FFS in detail
 Provide quantitative life assessment to support inspection/investment plans
 Provide analysis and guidance on inspections, repairs and material issues
626/06/2015 6
Fitness-for-service (FFS)
Assessment of ageing equipment for continued service
 Why - Equipment in operation is no longer covered by design codes
 Need - Economic run/repair/replace decisions require information on
damage mechanisms and their likelihood
 Challenge - There are many possible damage or degradation
mechanisms which must be considered and identified
 Brittle and ductile fracture, fatigue, corrosion, environmental assisted
cracking and creep at higher temperatures.
 Various FFS assessment codes exist like API, BS, ASME and ANSI
 API RP 579-1/ASME FFS-1 Fitness-For-Service
726/06/2015 7
API RP 579-1/ASME FFS-1 Fitness-For-Service
Assessment levels
Level 1
 Minimum amount of inspection or component information
 Conservative screening - general concurrence with NBIC rules,
 Plant inspection or engineering personnel
Level 2
 More detailed, less conservative with more accurate results based on local stresses and material
properties
 Quantitative damage characterization – size, shape, location, orientation
 Qualified engineering personnel
Level 3
 Most detailed evaluation – requires very detailed inspection and component information
 Analysis procedures are based on material testing and/or numerical analysis techniques such as the
finite element method
 Personnel with expertise in complex FFS assessments
826/06/2015 8
Assessment of time/cycle to next
inspection/investment
 When approaching design life or for life extension
purposes
 After process disturbance (overheating, -loading or
chemical environment)
 When changing process parameters or type of service
Flexible modules depending on needs
 Life estimation based on microstructural changes,
deterministic life assessment
 Probabilistic life assessment, RBI, simulations
Lifetime assessment concepts
AnalysisInspection TestingInitial data Recommendations Documentation
€
€ €
€
Owner benefits from FFS –
at least 10% reduction in
maintenance costs
(Bennet & Mixon 2011)
926/06/2015 9
Lifetime assessment
Input information
 Design, fabrication and maintenance history, QA documentation
 Operational history (T, p, other loads, operating environments, process chemistry)
 Materials (incl. welding, heat treatments etc.) and operating damage mechanisms
(e.g. creep, fatigue, corrosion, wear/erosion, combined mechanisms)
Methods
 Condition assessment by inspection and testing
 Predictive life modelling from combined initial info, measured/modelled material
and component properties, loads, damage progression and critical limits
 Validation based on experimental data
After a year in service
Creep cracks on
7CrMoVTiB10-10 weld
SCC
1026/06/2015 10
Case examples
Illustrating
 Assessment of damage mechanisms
 New lifing concepts
 Benefits of selected technology
 …
 …
Different application areas
 Heat exchangers and reformers
 Reheater
 Welded components
 (Gas turbines)
 …
 …
111126/06/2015
Remaining life
estimates
Thinning rate
• erosion and
corrosion
Creep life
• strain
• rupture
Scale growth rate
• impact on T
Inspection timing
Remaining life at
spec. locations
Operational data compilation
(temp + pressure history, maintenance)
Understanding ageing that results
to damage
• characteristics, mechanisms
• initial and end state
• for stress history
Temperature(°C)
Time (h)
Microstructural state
f(T)  predict temp
Hardness
g(T)  predict temp
Oxide thickness
h(T)  predict temp
Data bases and in-house
models for microstructural
aging, oxidation and
hardness - functions of time
and temperature
Representative
stress and temp
Service
environment
Life management of high temperature components
1226/06/2015 12
 Evaluation of microstructural change, defects and local
composition (HT equipment)
 Performance assessment: creep, impact, hardness…
 Comparison to acceptance limits according to experience
Case: Ageing of heat exchangers and
reformers
Benefits
• Evaluated scope and extent for further operation
• Established needs and timing for repairs or
replacement
1326/06/2015 13
Case - X20 header inspections + modelling + guidelines
Creep damage in X20 header after 135 000 h at 530°C
→ not common → rules for timing of inspections not as
as well established as in case of low alloy steels
• Cavitation evolving to crack growth at saddle
point: 4-year follow-up, extracted for detailed
evaluation
FEA of the branch: predicted damage confirmed
Benefits
• Guidelines for condition-based maintenance
• Material-specific behaviour established
1426/06/2015 14
Ts
Tox
t1 t2 t3 ta
Temperature(°C)
tr
Ts
Tox
t3 ta
Time (h)
Temperature(°C)
tr
Teff
t0
As-new 16Mo3
Predicted +35 000 h
and verified in plantConversion from unknown to manageable equivalent history.
After 185000 h / (465) - 520°C
 Unknown details of thermal history after multiple cycles of operation
+ internal cleaning
 Solution: converted to equivalent history with single cleaning and
prediction from current condition → predicted minimum residual life
of 35 000 hours
Case: Reheater life extension
1526/06/2015 15
 Ni-based superalloy Rene N4 coated with platinum
aluminide coating
 In-service material temperature evaluation based on
microstructural changes
Figure 1: Predicted temperature distribution of the overheated blade.
Case - Degradation in single-crystal gas
turbine blade
Benefits
• New method to evaluate the local metal
temperatures
• Assist to focus maintenance efforts ...
1626/06/2015 16
Miniature testing – ease and improved
reliability for lifetime evaluation
Minature testing → small samples
 Sampling easier, no need to cut tubes ,
no need to extensive weld repairs and heat
treatments → Time and cost savings
 Miniature testing is cheaper that traditional
uniaxial creep testing
 Results are obtained faster
Small punch (SP) test: one sample →
many tests
 Yield and tensile strength
 Impact energy (Charpy-V)
 Fracture toughness (KIC , JIC)
 Creep test
Pneumatic loading
system (push / pull)
based on bellows
technology
Examples of different
sample sizes ; miniature
on the right
17
Preventive maintenance
– VTT solution
1826/06/2015 18
Preventive maintenance – VTT solution:
TOLKKU toolbox
Decision-making requires information. TOLKKU provides tools
for extracting useful information from vast amounts of data
collected from different sources.
T☺lkku
1926/06/2015 19
TOLKKU toolbox - custom solutions
 Varying situations and needs require versatile analysis tools. TOLKKU toolbox
provides building blocks to match current needs, allowing more flexibility than a
software with a fixed set of features.
 Company-wide product development, machine operation, maintenance, and
management decision-making each have specific needs for information. TOLKKU
toolbox provides functionality to cover the whole life times of machines.
 TOLKKU toolbox is a part of VTT's offering for lifetime management facilitating
solutions customized to company needs, such as early detection of faults,
optimizing maintenance plans, monitoring the use profiles of a machine fleet.
Design data
Fault statistics
Measurements
Etc.
Input / Data
Failure risk level
Remaining useful life
How to operate until
next planned service
Etc.
Output / Information
R&D
Machine operator
Control
Service and
maintenance
Utilization
2026/06/2015 20
TOLKKU toolbox: Building blocks for O&M
Measurement
methods
Data acquisition
and transmission
Signal
processing
Diagnostics
methods
0 0.1 0.2 0.3
3
2.4
1.8
1.2
0.6
0
0.6
1.2
1.8
2.4
3
Aika [s]
Värähtelykiihtyvyys[m/s2]
0 50 100 150 200 250 300 350 400 450 500
0
0.004
0.008
0.012
0.016
Taajuus [Hz]
Värähtelykiihtyvyys[m/s2]
Now Time
Interaction of
components
Prognostics
Increased efficiency
Time
Cutting Lifting Moving
PotholeBegining End
Meas.
data Rainflow (tB..tE)
Time at level (tB..tE)
…
Use and load profiles
Spectrometry (SOAP)
Wear particles, etc
Acoustic emission (80 -120 kHz)
Temperature
Vibrations (0 - 10 kHz)
TOLKKU toolbox includes modules for
 Data import
 Data preparation
 Feature extraction
 State recognition
 Load profiles
 Anomaly detection
 Analysis of causality
 Time-frequency analysis
 Analysis of bearings
and gearboxes
 Decision support
 Big data analytics
2126/06/2015 21
TOLKKU toolbox: Continuous improvement
Data from
the whole
fleet
Feature extraction
State identification
Prognostics
Continuous
refining of
computational
models
Maintenance
plan
optimization
Exploratory
data analysis to
gain new insight
Service
data
2226/06/2015 22
TOLKKU toolbox: Industrial perspective
The TOLKKU project gave us tools for collecting, organising, and
analysing huge amounts of data in a very short time. TOLKKU
tools are a powerful package for finding out the real cause of
failure (root cause). The analyses result in the repair being
carried out exactly on the right part of the machine. Machine
down time and service visits are minimised.
Bronto Skylift Oy Abj
The TOLKKU project has created a practical and applicable
data analysis toolkit that has already shown some promising
results in use. We are very pleased with the way a project that
is essentially research-oriented has been so well focused on
the industrial needs.
Konecranes Oy
23
Remote maintenance with
virtual and Augmented
Reality
2426/06/2015 24
Remote operation of maintenance
implementing virtual and augmented
technology
2526/06/2015 25
Manual maintenance work support with virtual
and Augmented Reality creates safe, reliable
and effective maintenance tasks
Courtesy of Delta Cygni Labs Ltd, Finland
2626/06/2015 26
Assembly work assisted with Augmented
Reality: measurable improvements
Image courtesy of supakitmod at FreeDigitalPhotos.net
2726/06/2015 27
Assembly work assisted with Augmented
Reality (AR): measurable improvements
28
Setting RAMS requirements
for suppliers
2926/06/2015 29
The design phase lays the foundation for
RAMS performance - Case Total Train-Life
Management
 Alstom was challenged to develop a full life cycle service offering to a new line of
the London subway network.
 Subway trains are planned for 30 years service time and the construction time is two
years
 The value of life cycle services across 30 years of service is 3 - 4 times the
aquisition cost of the trains
 The development of the Total Train-Life Management offering lead the
manufacturing company to think about the impacts of system reliability, availability
and maintainability to the life cycle cost and performance
The machinery manufacturer made over 250 design
changes and modifications in order to make the trains
easier to operate and maintain
Source: Davies A.(2004). Industrial and Corporate Change. Vol 13, Nr. 5, pp. 727-756
303026/06/2015
Transferring customer needs to RAMS
requirements - Case Pesmel Oy
Setting up a challenge
 Pesmel Oy needed support to fulfil the RAMS process
requirements set by an international steel company
Solution
 VTT helped Pesmel to understand the meaning and
implications of final customer´s RAMS requirements
as design criteria and manufacturing cost items.
Benefit
 The final customer in steel industry received a
warehouse system that met their requirements
and had a profound documentation of
RAMS aspects.
31
Gas turbine inlet air filter
performance evaluation
3226/06/2015 32
Gas turbine inlet air filter performance
evaluation
Filter performance evaluation on site
 In land, on shore and off-shore
Tailored laboratory tests
 Special expertise on wet condition evaluation
 Chemical analysis of penetrated particles
Filter material and filter development
 Mechanical fiber filters
 Electrical filtration systems
References
GE Energy Products France SNC • Solar Turbines Inc • Donaldson • AAF •
Camfil • W.L.GORE & Associates GmbH • Northern Technical L.L.C. •
Eagle Filters • Ahlström Oy
Supply duct
(to be connected to the
ventilation system)
Material samples
High speed fan
Flow measurement
& control
33
Concluding remarks
3426/06/2015 34
Concluding remarks 1/2
 Accidents can be prevented - risk-based inspection and
maintenance provide ways for safe and economically
viable operation
 Lifetime assessment help owners maintain the integrity
of assets and ensure the continued reliability of plant operation
 Key issue in predicting and managing safe life is the
identification of critical assets, active damage mechanisms
and their likelihood
 Novel remaining lifetime assessment techniques adapt
to a range of operating conditions, materials and
damage mechanisms and provide safe but not unduly
conservative predictions.
 Maintenance on-demand is more cost efficient than fixed
intervals. Correct focussing and timing reduce costs, save
time and minimise impacts on HSE.
3526/06/2015 35
Concluding remarks 2/2
 Decision making requires information - Extracting useful
information from data for accurate and timely decision
making is a growing challenge.
 Newest condition monitoring systems utilising software
toolboxes and data processing enable e.g. to detect
overloads and wear of the machine/process parts prior
failure, thus open new possibilities for O&M.
 Role of simulation is increasing. Personnel can be trained
and production process optimized based on online
measurements and the respective simulators, both of which
increase safety and productivity.
 Proper design, remote operation, monitoring and
maintenance with implementing new advanced information
technology is an emerging field and has proved its
applicability in various hazardous applications
36
TECHNOLOGY FOR BUSINESS

More Related Content

What's hot

Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
SAJJAD KHUDHUR ABBAS
 
Piping and Insruementaion Diagrams
Piping and Insruementaion DiagramsPiping and Insruementaion Diagrams
Piping and Insruementaion Diagrams
Tejas Deshpande
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
wan saiful arini
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
НАЕК «Енергоатом»
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
Ukrainian Nuclear Society
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
Andy Lang
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioning
sakol kai
 
gi-ukepr-ci-01-close-out
gi-ukepr-ci-01-close-outgi-ukepr-ci-01-close-out
gi-ukepr-ci-01-close-out
Dijesh Das
 
ISPM Equipment Warranty Solution for SAP
ISPM Equipment Warranty Solution for SAPISPM Equipment Warranty Solution for SAP
ISPM Equipment Warranty Solution for SAP
Tony Ciliberti PE
 
Maintenance norms for wq labs
Maintenance norms for wq labsMaintenance norms for wq labs
Maintenance norms for wq labs
hydrologyproject0
 
Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)
SAJJAD KHUDHUR ABBAS
 
2016 Resume
2016  Resume2016  Resume
2016 Resume
Allen Bailey
 
Paper: Life Extension of Aging Petroleum Production Facilities Offshore
Paper: Life Extension of Aging Petroleum Production Facilities Offshore Paper: Life Extension of Aging Petroleum Production Facilities Offshore
Paper: Life Extension of Aging Petroleum Production Facilities Offshore
E.ON Exploration & Production
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
Ronie Chu
 
Practical application of ISO 14224 methods in corporate software
Practical application of ISO 14224 methods in corporate softwarePractical application of ISO 14224 methods in corporate software
Practical application of ISO 14224 methods in corporate software
Tony Ciliberti PE
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
HIMADRI BANERJI
 
introduction to chemical process technology,process flow diagram and block fl...
introduction to chemical process technology,process flow diagram and block fl...introduction to chemical process technology,process flow diagram and block fl...
introduction to chemical process technology,process flow diagram and block fl...
saeed memon
 
Pip arc01015(architechtural & building utilities design criteria)
Pip arc01015(architechtural & building utilities design criteria)Pip arc01015(architechtural & building utilities design criteria)
Pip arc01015(architechtural & building utilities design criteria)
Muhammad Hassan
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
GSE Systems, Inc.
 

What's hot (19)

Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
 
Piping and Insruementaion Diagrams
Piping and Insruementaion DiagramsPiping and Insruementaion Diagrams
Piping and Insruementaion Diagrams
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
 
Aging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR ProjectAging Management Experience. Status of the IVMR Project
Aging Management Experience. Status of the IVMR Project
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioning
 
gi-ukepr-ci-01-close-out
gi-ukepr-ci-01-close-outgi-ukepr-ci-01-close-out
gi-ukepr-ci-01-close-out
 
ISPM Equipment Warranty Solution for SAP
ISPM Equipment Warranty Solution for SAPISPM Equipment Warranty Solution for SAP
ISPM Equipment Warranty Solution for SAP
 
Maintenance norms for wq labs
Maintenance norms for wq labsMaintenance norms for wq labs
Maintenance norms for wq labs
 
Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)
 
2016 Resume
2016  Resume2016  Resume
2016 Resume
 
Paper: Life Extension of Aging Petroleum Production Facilities Offshore
Paper: Life Extension of Aging Petroleum Production Facilities Offshore Paper: Life Extension of Aging Petroleum Production Facilities Offshore
Paper: Life Extension of Aging Petroleum Production Facilities Offshore
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Practical application of ISO 14224 methods in corporate software
Practical application of ISO 14224 methods in corporate softwarePractical application of ISO 14224 methods in corporate software
Practical application of ISO 14224 methods in corporate software
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
introduction to chemical process technology,process flow diagram and block fl...
introduction to chemical process technology,process flow diagram and block fl...introduction to chemical process technology,process flow diagram and block fl...
introduction to chemical process technology,process flow diagram and block fl...
 
Pip arc01015(architechtural & building utilities design criteria)
Pip arc01015(architechtural & building utilities design criteria)Pip arc01015(architechtural & building utilities design criteria)
Pip arc01015(architechtural & building utilities design criteria)
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
 

Similar to SUOKAS Kuwait s-2015 slides_FINAL

2. ELECTRIC POWER STEERING.doc.docx
2. ELECTRIC POWER STEERING.doc.docx2. ELECTRIC POWER STEERING.doc.docx
2. ELECTRIC POWER STEERING.doc.docx
AUTVPDPPA1022Muhamma
 
Converge Short ECMP Sept 2015
Converge Short ECMP Sept 2015Converge Short ECMP Sept 2015
Converge Short ECMP Sept 2015
Jo_Vann
 
Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
AnonymoushdXKzBhoN
 
2017 11-13 sampe synthesites-carbon rotec
2017 11-13 sampe synthesites-carbon rotec2017 11-13 sampe synthesites-carbon rotec
2017 11-13 sampe synthesites-carbon rotec
Nikos Pantelelis
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation
inacatrine
 
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Mark Mitchell
 
Sr Lead Engineer - Instrumentation & control
Sr Lead Engineer - Instrumentation & controlSr Lead Engineer - Instrumentation & control
Sr Lead Engineer - Instrumentation & control
Bathrinath mangalamoorthi
 
PLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee UpdatePLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee Update
Institution of Lighting Professionals
 
Oam mechanical eng
Oam mechanical engOam mechanical eng
Oam mechanical eng
Odoardo Merida
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2
ZAINI ABDUL WAHAB
 
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
IJERA Editor
 
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET Journal
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)
ravindradatar
 
Resume - Suncor
Resume - SuncorResume - Suncor
Resume - Suncor
Syed Rizvi
 
steam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdfsteam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdf
chintanraval24
 
khalid mowafy CV
khalid mowafy CVkhalid mowafy CV
khalid mowafy CV
khalid elmowafy
 
Instrument engineer CV
Instrument engineer CVInstrument engineer CV
Instrument engineer CV
kalpesh chauhan
 

Similar to SUOKAS Kuwait s-2015 slides_FINAL (20)

2. ELECTRIC POWER STEERING.doc.docx
2. ELECTRIC POWER STEERING.doc.docx2. ELECTRIC POWER STEERING.doc.docx
2. ELECTRIC POWER STEERING.doc.docx
 
Converge Short ECMP Sept 2015
Converge Short ECMP Sept 2015Converge Short ECMP Sept 2015
Converge Short ECMP Sept 2015
 
Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
 
2017 11-13 sampe synthesites-carbon rotec
2017 11-13 sampe synthesites-carbon rotec2017 11-13 sampe synthesites-carbon rotec
2017 11-13 sampe synthesites-carbon rotec
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation
 
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...
 
Sr Lead Engineer - Instrumentation & control
Sr Lead Engineer - Instrumentation & controlSr Lead Engineer - Instrumentation & control
Sr Lead Engineer - Instrumentation & control
 
PLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee UpdatePLS 2018: ILP Technical Committee Update
PLS 2018: ILP Technical Committee Update
 
Oam mechanical eng
Oam mechanical engOam mechanical eng
Oam mechanical eng
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2
 
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
CV_Chanchalerm
 
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
CV_Chanchalerm
 
CV_Chanchalerm
CV_ChanchalermCV_Chanchalerm
CV_Chanchalerm
 
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...
 
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)
 
Resume - Suncor
Resume - SuncorResume - Suncor
Resume - Suncor
 
steam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdfsteam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdf
 
khalid mowafy CV
khalid mowafy CVkhalid mowafy CV
khalid mowafy CV
 
Instrument engineer CV
Instrument engineer CVInstrument engineer CV
Instrument engineer CV
 

SUOKAS Kuwait s-2015 slides_FINAL

  • 1. VTT TECHNICAL RESEARCH CENTRE OF FINLAND LTD Risk management based on proper material selection, advanced monitoring and remote maintenance Jouko Suokas, Executive Vice President VTT
  • 2. 226/06/2015 2 Outline Drivers and needs Background Risk based inspection (RBI) FFS assessment Lifing concepts and case examples Preventive maintenance – VTT solution (Tolkku toolbox) Remote maintenance RAMS analysis Gas turbine air filter performance evaluation Concluding remarks
  • 3. 326/06/2015 3 Drivers and needs  Drivers  Productivity, efficiency  Ageing assets, availability and reliability  HSE targets  Increased need for  Critical asset evaluation, risk analysis  Predicting and managing safe life  Correct targeting and timing of maintenance  Deferring investments
  • 4. 426/06/2015 4 Life Cycle Management New facility Operation Ageing and retrofitting  Conceptualization  Design phases  Manufacturing  Construction and installation  Commissioning and start-up  Operation and maintenance  Technical and operational changes  Ageing management  Modernization  Retrofits  Investment decisions Presentation focus
  • 5. 526/06/2015 5 Risk based inspection (RBI) In refineries/petrochemical industry often aligned to API RP 581 ‘Risk-based Inspection Technology’:  To develop inspection plans for pressurized fixed equipment  Sections on inspection planning, determining probability of failure (PoF), and consequence (CoF) modelling  Focus on impact and benefit from inspections, assumes time-independent consequences When critical items have been identified by RBI, VTT can e.g.  Analyse the criticality, condition and FFS in detail  Provide quantitative life assessment to support inspection/investment plans  Provide analysis and guidance on inspections, repairs and material issues
  • 6. 626/06/2015 6 Fitness-for-service (FFS) Assessment of ageing equipment for continued service  Why - Equipment in operation is no longer covered by design codes  Need - Economic run/repair/replace decisions require information on damage mechanisms and their likelihood  Challenge - There are many possible damage or degradation mechanisms which must be considered and identified  Brittle and ductile fracture, fatigue, corrosion, environmental assisted cracking and creep at higher temperatures.  Various FFS assessment codes exist like API, BS, ASME and ANSI  API RP 579-1/ASME FFS-1 Fitness-For-Service
  • 7. 726/06/2015 7 API RP 579-1/ASME FFS-1 Fitness-For-Service Assessment levels Level 1  Minimum amount of inspection or component information  Conservative screening - general concurrence with NBIC rules,  Plant inspection or engineering personnel Level 2  More detailed, less conservative with more accurate results based on local stresses and material properties  Quantitative damage characterization – size, shape, location, orientation  Qualified engineering personnel Level 3  Most detailed evaluation – requires very detailed inspection and component information  Analysis procedures are based on material testing and/or numerical analysis techniques such as the finite element method  Personnel with expertise in complex FFS assessments
  • 8. 826/06/2015 8 Assessment of time/cycle to next inspection/investment  When approaching design life or for life extension purposes  After process disturbance (overheating, -loading or chemical environment)  When changing process parameters or type of service Flexible modules depending on needs  Life estimation based on microstructural changes, deterministic life assessment  Probabilistic life assessment, RBI, simulations Lifetime assessment concepts AnalysisInspection TestingInitial data Recommendations Documentation € € € € Owner benefits from FFS – at least 10% reduction in maintenance costs (Bennet & Mixon 2011)
  • 9. 926/06/2015 9 Lifetime assessment Input information  Design, fabrication and maintenance history, QA documentation  Operational history (T, p, other loads, operating environments, process chemistry)  Materials (incl. welding, heat treatments etc.) and operating damage mechanisms (e.g. creep, fatigue, corrosion, wear/erosion, combined mechanisms) Methods  Condition assessment by inspection and testing  Predictive life modelling from combined initial info, measured/modelled material and component properties, loads, damage progression and critical limits  Validation based on experimental data After a year in service Creep cracks on 7CrMoVTiB10-10 weld SCC
  • 10. 1026/06/2015 10 Case examples Illustrating  Assessment of damage mechanisms  New lifing concepts  Benefits of selected technology  …  … Different application areas  Heat exchangers and reformers  Reheater  Welded components  (Gas turbines)  …  …
  • 11. 111126/06/2015 Remaining life estimates Thinning rate • erosion and corrosion Creep life • strain • rupture Scale growth rate • impact on T Inspection timing Remaining life at spec. locations Operational data compilation (temp + pressure history, maintenance) Understanding ageing that results to damage • characteristics, mechanisms • initial and end state • for stress history Temperature(°C) Time (h) Microstructural state f(T)  predict temp Hardness g(T)  predict temp Oxide thickness h(T)  predict temp Data bases and in-house models for microstructural aging, oxidation and hardness - functions of time and temperature Representative stress and temp Service environment Life management of high temperature components
  • 12. 1226/06/2015 12  Evaluation of microstructural change, defects and local composition (HT equipment)  Performance assessment: creep, impact, hardness…  Comparison to acceptance limits according to experience Case: Ageing of heat exchangers and reformers Benefits • Evaluated scope and extent for further operation • Established needs and timing for repairs or replacement
  • 13. 1326/06/2015 13 Case - X20 header inspections + modelling + guidelines Creep damage in X20 header after 135 000 h at 530°C → not common → rules for timing of inspections not as as well established as in case of low alloy steels • Cavitation evolving to crack growth at saddle point: 4-year follow-up, extracted for detailed evaluation FEA of the branch: predicted damage confirmed Benefits • Guidelines for condition-based maintenance • Material-specific behaviour established
  • 14. 1426/06/2015 14 Ts Tox t1 t2 t3 ta Temperature(°C) tr Ts Tox t3 ta Time (h) Temperature(°C) tr Teff t0 As-new 16Mo3 Predicted +35 000 h and verified in plantConversion from unknown to manageable equivalent history. After 185000 h / (465) - 520°C  Unknown details of thermal history after multiple cycles of operation + internal cleaning  Solution: converted to equivalent history with single cleaning and prediction from current condition → predicted minimum residual life of 35 000 hours Case: Reheater life extension
  • 15. 1526/06/2015 15  Ni-based superalloy Rene N4 coated with platinum aluminide coating  In-service material temperature evaluation based on microstructural changes Figure 1: Predicted temperature distribution of the overheated blade. Case - Degradation in single-crystal gas turbine blade Benefits • New method to evaluate the local metal temperatures • Assist to focus maintenance efforts ...
  • 16. 1626/06/2015 16 Miniature testing – ease and improved reliability for lifetime evaluation Minature testing → small samples  Sampling easier, no need to cut tubes , no need to extensive weld repairs and heat treatments → Time and cost savings  Miniature testing is cheaper that traditional uniaxial creep testing  Results are obtained faster Small punch (SP) test: one sample → many tests  Yield and tensile strength  Impact energy (Charpy-V)  Fracture toughness (KIC , JIC)  Creep test Pneumatic loading system (push / pull) based on bellows technology Examples of different sample sizes ; miniature on the right
  • 18. 1826/06/2015 18 Preventive maintenance – VTT solution: TOLKKU toolbox Decision-making requires information. TOLKKU provides tools for extracting useful information from vast amounts of data collected from different sources. T☺lkku
  • 19. 1926/06/2015 19 TOLKKU toolbox - custom solutions  Varying situations and needs require versatile analysis tools. TOLKKU toolbox provides building blocks to match current needs, allowing more flexibility than a software with a fixed set of features.  Company-wide product development, machine operation, maintenance, and management decision-making each have specific needs for information. TOLKKU toolbox provides functionality to cover the whole life times of machines.  TOLKKU toolbox is a part of VTT's offering for lifetime management facilitating solutions customized to company needs, such as early detection of faults, optimizing maintenance plans, monitoring the use profiles of a machine fleet. Design data Fault statistics Measurements Etc. Input / Data Failure risk level Remaining useful life How to operate until next planned service Etc. Output / Information R&D Machine operator Control Service and maintenance Utilization
  • 20. 2026/06/2015 20 TOLKKU toolbox: Building blocks for O&M Measurement methods Data acquisition and transmission Signal processing Diagnostics methods 0 0.1 0.2 0.3 3 2.4 1.8 1.2 0.6 0 0.6 1.2 1.8 2.4 3 Aika [s] Värähtelykiihtyvyys[m/s2] 0 50 100 150 200 250 300 350 400 450 500 0 0.004 0.008 0.012 0.016 Taajuus [Hz] Värähtelykiihtyvyys[m/s2] Now Time Interaction of components Prognostics Increased efficiency Time Cutting Lifting Moving PotholeBegining End Meas. data Rainflow (tB..tE) Time at level (tB..tE) … Use and load profiles Spectrometry (SOAP) Wear particles, etc Acoustic emission (80 -120 kHz) Temperature Vibrations (0 - 10 kHz) TOLKKU toolbox includes modules for  Data import  Data preparation  Feature extraction  State recognition  Load profiles  Anomaly detection  Analysis of causality  Time-frequency analysis  Analysis of bearings and gearboxes  Decision support  Big data analytics
  • 21. 2126/06/2015 21 TOLKKU toolbox: Continuous improvement Data from the whole fleet Feature extraction State identification Prognostics Continuous refining of computational models Maintenance plan optimization Exploratory data analysis to gain new insight Service data
  • 22. 2226/06/2015 22 TOLKKU toolbox: Industrial perspective The TOLKKU project gave us tools for collecting, organising, and analysing huge amounts of data in a very short time. TOLKKU tools are a powerful package for finding out the real cause of failure (root cause). The analyses result in the repair being carried out exactly on the right part of the machine. Machine down time and service visits are minimised. Bronto Skylift Oy Abj The TOLKKU project has created a practical and applicable data analysis toolkit that has already shown some promising results in use. We are very pleased with the way a project that is essentially research-oriented has been so well focused on the industrial needs. Konecranes Oy
  • 23. 23 Remote maintenance with virtual and Augmented Reality
  • 24. 2426/06/2015 24 Remote operation of maintenance implementing virtual and augmented technology
  • 25. 2526/06/2015 25 Manual maintenance work support with virtual and Augmented Reality creates safe, reliable and effective maintenance tasks Courtesy of Delta Cygni Labs Ltd, Finland
  • 26. 2626/06/2015 26 Assembly work assisted with Augmented Reality: measurable improvements Image courtesy of supakitmod at FreeDigitalPhotos.net
  • 27. 2726/06/2015 27 Assembly work assisted with Augmented Reality (AR): measurable improvements
  • 29. 2926/06/2015 29 The design phase lays the foundation for RAMS performance - Case Total Train-Life Management  Alstom was challenged to develop a full life cycle service offering to a new line of the London subway network.  Subway trains are planned for 30 years service time and the construction time is two years  The value of life cycle services across 30 years of service is 3 - 4 times the aquisition cost of the trains  The development of the Total Train-Life Management offering lead the manufacturing company to think about the impacts of system reliability, availability and maintainability to the life cycle cost and performance The machinery manufacturer made over 250 design changes and modifications in order to make the trains easier to operate and maintain Source: Davies A.(2004). Industrial and Corporate Change. Vol 13, Nr. 5, pp. 727-756
  • 30. 303026/06/2015 Transferring customer needs to RAMS requirements - Case Pesmel Oy Setting up a challenge  Pesmel Oy needed support to fulfil the RAMS process requirements set by an international steel company Solution  VTT helped Pesmel to understand the meaning and implications of final customer´s RAMS requirements as design criteria and manufacturing cost items. Benefit  The final customer in steel industry received a warehouse system that met their requirements and had a profound documentation of RAMS aspects.
  • 31. 31 Gas turbine inlet air filter performance evaluation
  • 32. 3226/06/2015 32 Gas turbine inlet air filter performance evaluation Filter performance evaluation on site  In land, on shore and off-shore Tailored laboratory tests  Special expertise on wet condition evaluation  Chemical analysis of penetrated particles Filter material and filter development  Mechanical fiber filters  Electrical filtration systems References GE Energy Products France SNC • Solar Turbines Inc • Donaldson • AAF • Camfil • W.L.GORE & Associates GmbH • Northern Technical L.L.C. • Eagle Filters • Ahlström Oy Supply duct (to be connected to the ventilation system) Material samples High speed fan Flow measurement & control
  • 34. 3426/06/2015 34 Concluding remarks 1/2  Accidents can be prevented - risk-based inspection and maintenance provide ways for safe and economically viable operation  Lifetime assessment help owners maintain the integrity of assets and ensure the continued reliability of plant operation  Key issue in predicting and managing safe life is the identification of critical assets, active damage mechanisms and their likelihood  Novel remaining lifetime assessment techniques adapt to a range of operating conditions, materials and damage mechanisms and provide safe but not unduly conservative predictions.  Maintenance on-demand is more cost efficient than fixed intervals. Correct focussing and timing reduce costs, save time and minimise impacts on HSE.
  • 35. 3526/06/2015 35 Concluding remarks 2/2  Decision making requires information - Extracting useful information from data for accurate and timely decision making is a growing challenge.  Newest condition monitoring systems utilising software toolboxes and data processing enable e.g. to detect overloads and wear of the machine/process parts prior failure, thus open new possibilities for O&M.  Role of simulation is increasing. Personnel can be trained and production process optimized based on online measurements and the respective simulators, both of which increase safety and productivity.  Proper design, remote operation, monitoring and maintenance with implementing new advanced information technology is an emerging field and has proved its applicability in various hazardous applications