The document discusses risk management and preventive maintenance strategies for industrial assets. It covers:
- Risk-based inspection approaches to identify critical assets and prioritize maintenance. This can include failure analysis, fitness-for-service assessments, and quantitative life assessments.
- Case studies of applying these methods to evaluate issues like creep damage, corrosion rates, microstructural changes, and develop inspection schedules or replacement guidelines.
- The TOLKKU toolbox, a customizable solution from VTT for condition monitoring, data analysis, diagnostics and prognostics to support preventive maintenance and decision making. It integrates data from multiple sources to assess risks and remaining useful life.
The document outlines the requirements and expectations for a chemical plant design project. It includes sections on the project scope, required deliverables, evaluation criteria, and technical considerations. Students will work in groups of up to 4 people to develop a complete design package for a chemical process. The project is due on December 1st and must include items such as a technology review, heat and material balances, process flow diagrams, equipment specifications, and a cost analysis. Updates on progress must be submitted every two weeks.
The document provides an overview of the Process Equipment Reliability Database (PERD) Project. It discusses PERD's mission to operate an equipment reliability database and help companies improve their reliability and maintenance data collection processes. It also describes how PERD participants can benefit from PERD's methods for addressing common deficiencies in enterprise resource planning and computerized maintenance management systems. The document outlines PERD's bottom-line approach to optimizing equipment reliability through identifying, analyzing, and resolving high-consequence failure events and issues with "bad actor" equipment.
Ankur Sood has over 9 years of experience as an instrumentation and control engineer. He is seeking a position as a project engineer, commissioning engineer, instrumentation maintenance engineer, planner, or instrument supervisor. He has experience working for Reliance Industries Limited on projects including large petrochemical plants, power plants, air separation plants, and product transfer systems. He has expertise in commissioning, maintenance, and project management of instrumentation and control systems.
Episode 7 : iCON Basic Training
Outline
Introduction to Process Simulation
iCON Software
Thermodynamic Property Package
Modeling Approach
Hands On Training
Episode 34 : Project Execution Part (5)
•Large components – used suitable cranes, usually are leased/rent
– electronically controllable by remote control
•Medium/Smaller components
hoists or fork‐lifts are used
are ordered to the building site at an early stage and intermediately stored there.
‐If possible, at the same time, during the assembly of main components, the assembly of medium/smaller components will begin.
‐Subcontractor is required to provide suitable packaging or tarpaulin cover
(cover for vessel opening such as nozzle, by means of plastic caps)
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Sam Najmi has over 25 years of experience in mechanical engineering, including patented designs. He has worked in various roles such as project management, product engineering, commissioning, and sales across industries like data centers, transportation, and refrigeration. Najmi's skills include designing, testing, and commissioning complex mechanical systems for mission critical facilities. He currently works as a Senior Mechanical Commissioning Engineer, leading acceptance testing and reporting.
110921 commissioning of offshore installationslaithu2908
This document discusses the commissioning process for offshore installations built in yards. It covers the total commissioning activity and defines the key phases of mechanical completion, pre-commissioning and commissioning. Mechanical completion involves verifying construction work is complete according to design. Pre-commissioning verifies functionality and system integration. Commissioning verifies systems are ready for operation. The document provides details on planning, organization and activities for each phase. Estimates suggest 95-105 systems for an FPSO requiring around 135,000-145,000 hours for commissioning, taking around 6 months with a team of 90 people. Addressing issues can help improve estimates over time.
Enabling Corporate Failure Metrics at Nexen Energy with ISO 14224Tony Ciliberti PE
The document discusses Nexen Energy's implementation of ISO 14224 standards for asset reliability data collection and analysis using SAP software. It describes how Nexen redesigned its technical hierarchy to align with ISO 14224, defining clear equipment boundaries and relationships. This improved data quality and enabled aggregated reliability metrics at the equipment level. The redesign process and lessons learned are discussed. Standard methods like the Industry Standard Plant Maintenance (ISPM) approach are presented for simplifying and automating failure analysis to identify high-risk equipment and prioritize corrective actions.
The document outlines the requirements and expectations for a chemical plant design project. It includes sections on the project scope, required deliverables, evaluation criteria, and technical considerations. Students will work in groups of up to 4 people to develop a complete design package for a chemical process. The project is due on December 1st and must include items such as a technology review, heat and material balances, process flow diagrams, equipment specifications, and a cost analysis. Updates on progress must be submitted every two weeks.
The document provides an overview of the Process Equipment Reliability Database (PERD) Project. It discusses PERD's mission to operate an equipment reliability database and help companies improve their reliability and maintenance data collection processes. It also describes how PERD participants can benefit from PERD's methods for addressing common deficiencies in enterprise resource planning and computerized maintenance management systems. The document outlines PERD's bottom-line approach to optimizing equipment reliability through identifying, analyzing, and resolving high-consequence failure events and issues with "bad actor" equipment.
Ankur Sood has over 9 years of experience as an instrumentation and control engineer. He is seeking a position as a project engineer, commissioning engineer, instrumentation maintenance engineer, planner, or instrument supervisor. He has experience working for Reliance Industries Limited on projects including large petrochemical plants, power plants, air separation plants, and product transfer systems. He has expertise in commissioning, maintenance, and project management of instrumentation and control systems.
Episode 7 : iCON Basic Training
Outline
Introduction to Process Simulation
iCON Software
Thermodynamic Property Package
Modeling Approach
Hands On Training
Episode 34 : Project Execution Part (5)
•Large components – used suitable cranes, usually are leased/rent
– electronically controllable by remote control
•Medium/Smaller components
hoists or fork‐lifts are used
are ordered to the building site at an early stage and intermediately stored there.
‐If possible, at the same time, during the assembly of main components, the assembly of medium/smaller components will begin.
‐Subcontractor is required to provide suitable packaging or tarpaulin cover
(cover for vessel opening such as nozzle, by means of plastic caps)
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Sam Najmi has over 25 years of experience in mechanical engineering, including patented designs. He has worked in various roles such as project management, product engineering, commissioning, and sales across industries like data centers, transportation, and refrigeration. Najmi's skills include designing, testing, and commissioning complex mechanical systems for mission critical facilities. He currently works as a Senior Mechanical Commissioning Engineer, leading acceptance testing and reporting.
110921 commissioning of offshore installationslaithu2908
This document discusses the commissioning process for offshore installations built in yards. It covers the total commissioning activity and defines the key phases of mechanical completion, pre-commissioning and commissioning. Mechanical completion involves verifying construction work is complete according to design. Pre-commissioning verifies functionality and system integration. Commissioning verifies systems are ready for operation. The document provides details on planning, organization and activities for each phase. Estimates suggest 95-105 systems for an FPSO requiring around 135,000-145,000 hours for commissioning, taking around 6 months with a team of 90 people. Addressing issues can help improve estimates over time.
Enabling Corporate Failure Metrics at Nexen Energy with ISO 14224Tony Ciliberti PE
The document discusses Nexen Energy's implementation of ISO 14224 standards for asset reliability data collection and analysis using SAP software. It describes how Nexen redesigned its technical hierarchy to align with ISO 14224, defining clear equipment boundaries and relationships. This improved data quality and enabled aggregated reliability metrics at the equipment level. The redesign process and lessons learned are discussed. Standard methods like the Industry Standard Plant Maintenance (ISPM) approach are presented for simplifying and automating failure analysis to identify high-risk equipment and prioritize corrective actions.
Episode 33 : Project Execution Part (4)
complete quotations for spare and wear parts
instructions for maintenance and repair of the whole plant
lists of lubricants in consideration of the selected lubricant suppliers
coding of the operating resources and equipments
establishment of special single data sheets for the entire equipment
establishment of a complete plant index resp. plant database (plant registration system)
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Piping and instrumentation diagrams (P&IDs) are complex diagrams that show the piping, instrumentation, and process flow in chemical plants. The presentation discusses P&IDs in detail, including:
1. The purpose of P&IDs in understanding chemical processes, operations, and maintenance.
2. The various standards and symbols used to represent equipment, piping, instruments, and their interconnectivity.
3. How P&IDs are developed through various stages and used by different engineering departments and industries for design and operations.
4. Examples of software that can be used to create detailed P&IDs.
The document discusses commissioning of offshore installations in building yards. It covers the total commissioning activity and defines the key phases of mechanical completion, pre-commissioning, and commissioning. Mechanical completion involves verifying construction meets design requirements through testing. Pre-commissioning focuses on verifying system functionality and instrument calibration. Commissioning execution involves final checks before handover to operations. Effective planning is critical to the success of each phase.
This document provides an overview of aging management experience and the status of the IVMR Project. It discusses:
1) The importance of proper scoping and screening as the basic step for aging management and long-term operation (LTO) of nuclear power plants.
2) The results of aging management reviews (AMR), including the identification of new degradation mechanisms and validation of time-limited aging analyses.
3) Updates on experimental work being done as part of the IVMR Project to study core melt progression and heat flux in a reactor pressure vessel, including results from small-scale and plans for large-scale testing facilities.
The document outlines requirements and procedures for mechanical completion and handover of projects from construction to commissioning. It discusses establishing inspection and test records, punch lists, certificates, and documentation like as-built drawings and manuals. Responsibilities include contractors performing mechanical completion and pre-commissioning activities with oversight from the client. Systems are handed over in phases from contractors to the client and eventually to the operator once pre-commissioning and commissioning are complete.
Mind map the_9_key_elements_video_05_pre-commissioningsakol kai
Pre-commissioning activities refer to tasks completed after construction but before commissioning to prepare systems for operation. They include cleaning, catalyst loading, dry runs, and checks of systems. Records of pre-commissioning tests and checklists are made to verify systems are ready for commissioning. Common pre-commissioning tasks involve flushing, blowing, drying, leak testing, lubrication, equipment run-ins, and filter/catalyst installation. The goal is to achieve a "Ready for Commissioning" milestone where systems are prepared to begin the commissioning process.
This document summarizes the Nuclear Directorate's assessment of the control and instrumentation (C&I) systems for the proposed UK EPR nuclear reactor design. The assessment concluded that the C&I safety case was generally adequate but identified some issues requiring resolution. These issues related to diversifying safety systems, justifying network communications, and providing more detailed information on system reliability and displays. The Requesting Party addressed the issues to the regulator's satisfaction by providing additional safety case documentation and proposing design changes and future qualification plans. While some topics require further information, the C&I systems were found to be suitable subject to future assessment as more design details become available.
This presentation shows how to use SAP for end-to-end warranty management, including warranty master set-up, warranty event data collection using ISO 14224 methods, RMA options and processes, and cost recovery.
The document provides maintenance norms and logbooks for water quality laboratories established under the Hydrology Project in India. It outlines the necessary upkeep and annual operation and maintenance costs for three levels of laboratories - Level I, Level II, and Level II+. Level I laboratories require about Rs. 23,500 annually for chemicals, equipment maintenance, and building upkeep. Level II laboratories have higher annual costs of approximately Rs. 65,500 to maintain chemicals, glassware, equipment, and the building. The document also includes several annexes that list required chemicals, glassware, other laboratory items, and logbook templates to track laboratory equipment and inventory.
This document discusses the key aspects of electrical, measurement, and control (E/MC) engineering as they relate to project execution. It outlines the major tasks and considerations for each discipline. Electrical engineering involves designing the energy supply, control cabinets, and cabling. Measurement engineering includes selecting measuring instruments and connecting them to the control system. Control engineering develops the control program to analyze sensor data, determine necessary actions, and connect everything to the control room and local control panels. Close cooperation is needed between process and control engineers to properly define requirements and design the integrated automation system.
Allen Bailey is seeking a position as a heavy equipment/machinery/vehicle engineer. He has over 15 years of experience in reliability engineering, root cause analysis, testing, and technical project management. His background includes analyzing failures, developing and performing product tests, and initiating engineering projects. He has expertise in diesel engines, hydraulic and electronic systems, vehicle dynamics, and commercial driver operation.
A large part of the Norwegian gas and oil production facilities has reached their initial design life, but the respective fields are still producing substantial levels of hydrocarbons. In order to ensure technical and operational integrity of these ageing facilities the Norwegian oil industry Association (OLF) has initiated a project to establish the necessary standards and guidelines for assessing and ensuring safe life extensions. This paper presents this project and the headlines of these standards and guidelines.
The document discusses mechanical completion, which involves checking and testing equipment, piping, instrumentation, and other components to confirm they are installed correctly and ready for commissioning. It describes the documentation involved, including mechanical completion certificates, check records, and punch lists. Various activities involved in mechanical completion are also outlined for disciplines like mechanical, electrical, instrumentation, and piping.
Practical application of ISO 14224 methods in corporate softwareTony Ciliberti PE
Tony Ciliberti PE Principal Engineer, Reliability Dynamics
4th ISO seminar on international standardization in the reliability technology and cost area Statoil, Houston, USA
May 4, 2018
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
The document provides an overview of plant commissioning and start-up procedures. It discusses the commissioning process which includes preparation and planning, mechanical completion and integrity checking, pre-commissioning and operational testing, start-up and initial operation, performance and acceptance testing, and post-commissioning. It then goes into more detail on specific aspects of the commissioning process such as developing start-up procedures, commissioning utilities, pressure testing, cleaning and flushing, and pre-commissioning operational testing.
introduction to chemical process technology,process flow diagram and block fl...saeed memon
This document discusses flow sheets used to describe chemical processes. It defines three types of flow sheets: flowcharts, process flow sheets, and piping and instrumentation diagrams. Flowcharts use simple symbols to represent logic or processes, while process flow sheets (PFDs) show relationships between major components and include process design values. PFDs provide the plant design basis, identify the process scope, and show equipment configuration and required utilities. The document provides examples of operations and equipment in chemical processes and details what information PFDs should include.
Pip arc01015(architechtural & building utilities design criteria)Muhammad Hassan
This document provides design criteria for architectural and building utility systems in process industry facilities. It establishes minimum requirements for building design, construction materials, and mechanical, electrical, communication, fire protection, and plumbing systems. The criteria reference applicable industry codes and standards to harmonize technical requirements and reduce costs for owners and manufacturers.
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...GSE Systems, Inc.
This presentation highlights a project in which a high-fidelity operator training simulator was implemented in a North American combined cycle power plant prior to commissioning.
For more information, go to GSES.com, email info@gses, and follow us on Twitter @GSESystems and at Facebook.com/GSESystems. Thanks for viewing!
This document provides information on the Chassis II course which focuses on electric power steering. The course aims to teach students how to setup a scan tool, perform electric power steering diagnosis using the scan tool, and replace electric power steering components. The course contains 3 competency units - setup scan tool, operate scan tool for electric power steering diagnosis, and replace the electric power steering motor and control module. It outlines the learning standards, assessment criteria, and references for each competency unit.
This document discusses electronic component management plans (ECMP) and obsolescence management in the avionics supply chain. It notes that 57% of reported counterfeit parts involve obsolete or end-of-life parts. The document outlines the 11 step ECMP process defined in IEC/TS 62239-1, including component selection, qualification, and obsolescence management. It provides an example where monitoring of manufacturer product change notices through the ECMP process allowed alternatives to be found for 40% of last-time buys. The document also discusses related standards like IEC/TS 62239-2 for COTS assemblies and third-party audit schemes through organizations like IECQ.
Incorporating an asset integrity program into the design stage of projects supports the lifecycle reliability and operability of equipment. Key elements of an asset integrity program include risk assessments, material selection, condition monitoring location selection, inspection, mitigation, monitoring, and data management. Implementing asset integrity activities at each stage of a project from front-end engineering to construction can improve project execution, optimize costs, and enhance operational reliability over the long-term lifecycle of the asset. Deliverables at each stage provide documentation of integrity-related decisions to support effective long-term management and operation of the facility.
Episode 33 : Project Execution Part (4)
complete quotations for spare and wear parts
instructions for maintenance and repair of the whole plant
lists of lubricants in consideration of the selected lubricant suppliers
coding of the operating resources and equipments
establishment of special single data sheets for the entire equipment
establishment of a complete plant index resp. plant database (plant registration system)
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Piping and instrumentation diagrams (P&IDs) are complex diagrams that show the piping, instrumentation, and process flow in chemical plants. The presentation discusses P&IDs in detail, including:
1. The purpose of P&IDs in understanding chemical processes, operations, and maintenance.
2. The various standards and symbols used to represent equipment, piping, instruments, and their interconnectivity.
3. How P&IDs are developed through various stages and used by different engineering departments and industries for design and operations.
4. Examples of software that can be used to create detailed P&IDs.
The document discusses commissioning of offshore installations in building yards. It covers the total commissioning activity and defines the key phases of mechanical completion, pre-commissioning, and commissioning. Mechanical completion involves verifying construction meets design requirements through testing. Pre-commissioning focuses on verifying system functionality and instrument calibration. Commissioning execution involves final checks before handover to operations. Effective planning is critical to the success of each phase.
This document provides an overview of aging management experience and the status of the IVMR Project. It discusses:
1) The importance of proper scoping and screening as the basic step for aging management and long-term operation (LTO) of nuclear power plants.
2) The results of aging management reviews (AMR), including the identification of new degradation mechanisms and validation of time-limited aging analyses.
3) Updates on experimental work being done as part of the IVMR Project to study core melt progression and heat flux in a reactor pressure vessel, including results from small-scale and plans for large-scale testing facilities.
The document outlines requirements and procedures for mechanical completion and handover of projects from construction to commissioning. It discusses establishing inspection and test records, punch lists, certificates, and documentation like as-built drawings and manuals. Responsibilities include contractors performing mechanical completion and pre-commissioning activities with oversight from the client. Systems are handed over in phases from contractors to the client and eventually to the operator once pre-commissioning and commissioning are complete.
Mind map the_9_key_elements_video_05_pre-commissioningsakol kai
Pre-commissioning activities refer to tasks completed after construction but before commissioning to prepare systems for operation. They include cleaning, catalyst loading, dry runs, and checks of systems. Records of pre-commissioning tests and checklists are made to verify systems are ready for commissioning. Common pre-commissioning tasks involve flushing, blowing, drying, leak testing, lubrication, equipment run-ins, and filter/catalyst installation. The goal is to achieve a "Ready for Commissioning" milestone where systems are prepared to begin the commissioning process.
This document summarizes the Nuclear Directorate's assessment of the control and instrumentation (C&I) systems for the proposed UK EPR nuclear reactor design. The assessment concluded that the C&I safety case was generally adequate but identified some issues requiring resolution. These issues related to diversifying safety systems, justifying network communications, and providing more detailed information on system reliability and displays. The Requesting Party addressed the issues to the regulator's satisfaction by providing additional safety case documentation and proposing design changes and future qualification plans. While some topics require further information, the C&I systems were found to be suitable subject to future assessment as more design details become available.
This presentation shows how to use SAP for end-to-end warranty management, including warranty master set-up, warranty event data collection using ISO 14224 methods, RMA options and processes, and cost recovery.
The document provides maintenance norms and logbooks for water quality laboratories established under the Hydrology Project in India. It outlines the necessary upkeep and annual operation and maintenance costs for three levels of laboratories - Level I, Level II, and Level II+. Level I laboratories require about Rs. 23,500 annually for chemicals, equipment maintenance, and building upkeep. Level II laboratories have higher annual costs of approximately Rs. 65,500 to maintain chemicals, glassware, equipment, and the building. The document also includes several annexes that list required chemicals, glassware, other laboratory items, and logbook templates to track laboratory equipment and inventory.
This document discusses the key aspects of electrical, measurement, and control (E/MC) engineering as they relate to project execution. It outlines the major tasks and considerations for each discipline. Electrical engineering involves designing the energy supply, control cabinets, and cabling. Measurement engineering includes selecting measuring instruments and connecting them to the control system. Control engineering develops the control program to analyze sensor data, determine necessary actions, and connect everything to the control room and local control panels. Close cooperation is needed between process and control engineers to properly define requirements and design the integrated automation system.
Allen Bailey is seeking a position as a heavy equipment/machinery/vehicle engineer. He has over 15 years of experience in reliability engineering, root cause analysis, testing, and technical project management. His background includes analyzing failures, developing and performing product tests, and initiating engineering projects. He has expertise in diesel engines, hydraulic and electronic systems, vehicle dynamics, and commercial driver operation.
A large part of the Norwegian gas and oil production facilities has reached their initial design life, but the respective fields are still producing substantial levels of hydrocarbons. In order to ensure technical and operational integrity of these ageing facilities the Norwegian oil industry Association (OLF) has initiated a project to establish the necessary standards and guidelines for assessing and ensuring safe life extensions. This paper presents this project and the headlines of these standards and guidelines.
The document discusses mechanical completion, which involves checking and testing equipment, piping, instrumentation, and other components to confirm they are installed correctly and ready for commissioning. It describes the documentation involved, including mechanical completion certificates, check records, and punch lists. Various activities involved in mechanical completion are also outlined for disciplines like mechanical, electrical, instrumentation, and piping.
Practical application of ISO 14224 methods in corporate softwareTony Ciliberti PE
Tony Ciliberti PE Principal Engineer, Reliability Dynamics
4th ISO seminar on international standardization in the reliability technology and cost area Statoil, Houston, USA
May 4, 2018
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
The document provides an overview of plant commissioning and start-up procedures. It discusses the commissioning process which includes preparation and planning, mechanical completion and integrity checking, pre-commissioning and operational testing, start-up and initial operation, performance and acceptance testing, and post-commissioning. It then goes into more detail on specific aspects of the commissioning process such as developing start-up procedures, commissioning utilities, pressure testing, cleaning and flushing, and pre-commissioning operational testing.
introduction to chemical process technology,process flow diagram and block fl...saeed memon
This document discusses flow sheets used to describe chemical processes. It defines three types of flow sheets: flowcharts, process flow sheets, and piping and instrumentation diagrams. Flowcharts use simple symbols to represent logic or processes, while process flow sheets (PFDs) show relationships between major components and include process design values. PFDs provide the plant design basis, identify the process scope, and show equipment configuration and required utilities. The document provides examples of operations and equipment in chemical processes and details what information PFDs should include.
Pip arc01015(architechtural & building utilities design criteria)Muhammad Hassan
This document provides design criteria for architectural and building utility systems in process industry facilities. It establishes minimum requirements for building design, construction materials, and mechanical, electrical, communication, fire protection, and plumbing systems. The criteria reference applicable industry codes and standards to harmonize technical requirements and reduce costs for owners and manufacturers.
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...GSE Systems, Inc.
This presentation highlights a project in which a high-fidelity operator training simulator was implemented in a North American combined cycle power plant prior to commissioning.
For more information, go to GSES.com, email info@gses, and follow us on Twitter @GSESystems and at Facebook.com/GSESystems. Thanks for viewing!
This document provides information on the Chassis II course which focuses on electric power steering. The course aims to teach students how to setup a scan tool, perform electric power steering diagnosis using the scan tool, and replace electric power steering components. The course contains 3 competency units - setup scan tool, operate scan tool for electric power steering diagnosis, and replace the electric power steering motor and control module. It outlines the learning standards, assessment criteria, and references for each competency unit.
This document discusses electronic component management plans (ECMP) and obsolescence management in the avionics supply chain. It notes that 57% of reported counterfeit parts involve obsolete or end-of-life parts. The document outlines the 11 step ECMP process defined in IEC/TS 62239-1, including component selection, qualification, and obsolescence management. It provides an example where monitoring of manufacturer product change notices through the ECMP process allowed alternatives to be found for 40% of last-time buys. The document also discusses related standards like IEC/TS 62239-2 for COTS assemblies and third-party audit schemes through organizations like IECQ.
Incorporating an asset integrity program into the design stage of projects supports the lifecycle reliability and operability of equipment. Key elements of an asset integrity program include risk assessments, material selection, condition monitoring location selection, inspection, mitigation, monitoring, and data management. Implementing asset integrity activities at each stage of a project from front-end engineering to construction can improve project execution, optimize costs, and enhance operational reliability over the long-term lifecycle of the asset. Deliverables at each stage provide documentation of integrity-related decisions to support effective long-term management and operation of the facility.
IMPROVEMENT OF PRODUCTIVITY AND QUALITY IN THE WIND ENERGY INDUSTRY THROUGH THE USE OF AN ADVANCED SENSOR SYSTEM , presented at SAMPE-Europe Conference 2017,
Stuttgart, November 15th 2017
Interested to learn how Inspecta can help you? We invited customers and partners to a presentation of Certification. Topics in the attached Slideshare is:
- Inspecta Overview
- Integrity Engineering
- Definition and lifecycle perspective
- Design verification and optimization
- Revisions, Fitness-for-service evaluation, Inspection planning
- Non-Intrusive Inspection (NII)
- Examples of Assignments and Projects
Development of a_standard_for_the_use_of_composites_in_a_high_temperature_rea...Mark Mitchell
Presented to SYMPOSIUM 13: International Symposium on Advanced Ceramics and Composites for Sustainable Nuclear Energy and Fusion Energy
Several high-temperature reactors have been designed, built and operated successfully using conventional materials. This application invariably pushed the materials to the edge of their envelope. Over the last 20 years it has become clear that unlocking the use of advanced materials – such as ceramic matrix composites and carbon-carbon composites – will enable significant improvements in the performance of high-temperature reactors.
This presentation provided an overview of some of the work completed to enable the use of these materials in various reactor development programmes, and explained the current work that is being completed in the ASME Boiler and Pressure Vessel Code committees to establish codes and standards for this application.
Mangalamoorthi E is a senior instrumentation and control engineer with over 12 years of experience. He is currently working as a senior lead engineer at Enmas GB power systems projects limited in Chennai, India. In this role, he is responsible for instrumentation engineering tasks like preparing wiring diagrams, datasheets, and overseeing field installation and commissioning activities. Previously, he has worked on several coal and gas power plant projects handling instrumentation for boilers, turbines, and other equipment. He is proficient in various instrumentation standards and software tools. Mangalamoorthi holds a B.E. in Instrumentation and Control Engineering and is willing to relocate for new opportunities.
The ILP is all about high-quality CPD and, if we want our members to have access to CPD and technical services as a core membership benefit, then we need to make that available to all our members, especially those up-and-coming within our industry.
by Haydn Yeo CEng MILP FIHIE, ILP VP Technical, Peter Harrison MBA CEng FILP, ILP Technical Services Manager & Allan Howard BEng(Hons) CEng FILP FSLL, WSP
Extensive experience executing large complex Capital Projects (grass-root or expansion/upgrading the existing facilities), related with different sectors of Energy and Oil/Gas Industry such as Upstream Oil & Gas Handling Facilities/Oil field Processing; Midstream (Gas Processing Plants; Pipelines, Marine Terminal/ Tank Farm, marine installations, and related infrastructure, etc), Downstream (Oil Refinery-Supply, Atm. & Vacuum Crude Oil Distillation systems, Distribution, Utilities & Auxiliaries); Fuel Aviation system and Power Plant Combined Heat & Power Steam Turbine unit (CTG & HRSG).
Ability to supporting & sustaining ongoing Operations of Production, performed by Continuous Process Optimization (monitoring the unit operations are running efficiently, increase production capacity, improve operating reliability, reduce manufacturing costs, reduce energy usage, conserve raw materials, improve product yields and improve product quality); oversight & compliance all aspect of Safety & Environmental ( controlling emissions to Air/Water, fire, etc.), identify new capital projects to enhance the process and reduce the cost of production, extend life of equipment, etc.
This a compilation of the overall process in conducting energy audit based on my personal experiences, training that I attended in Malaysia, India and Japan and information sharing between fellow EE practitioners.Not to forget references from books and internet.
I believe this would benefit to those who wants to understand what is energy audit all about for beginners to become an energy auditor and to facilities owners to assess the need to conduct energy audit and energy audit proposals submitted by consultants
Chanchalerm Watcharapasakhon has over 15 years of experience in instrumentation, control, and automation engineering. He has worked on projects in various industries including chemical, petrochemical, pharmaceutical, and offshore platforms. Some of his responsibilities have included engineering design, project management, commissioning, procurement, and ensuring safety and cost-effective designs. He has extensive experience working with international standards and codes.
Chanchalerm Watcharapasakhon has over 15 years of experience in instrumentation, control, and automation engineering. He has worked on projects in various industries including chemical, petrochemical, pharmaceutical, and offshore platforms. Some of his responsibilities have included engineering design, project management, commissioning, procurement, and ensuring safety and cost-effective designs. He has extensive experience working with international standards and codes.
Chanchalerm Watcharapasakhon has over 15 years of experience in instrumentation, control, and automation engineering. He has worked on projects in various industries including chemical, petrochemical, pharmaceutical, and offshore platforms. Some of his responsibilities have included engineering design, project management, commissioning, procurement, and ensuring safety and cost-effective designs. He has extensive experience working with international standards and codes.
Study of Microstructure Degradation of Boiler Tubes Due To Creep for Remainin...IJERA Editor
This document discusses the methodology for analyzing the microstructural degradation of boiler tubes due to creep in order to assess their remaining life. It outlines a three-level approach where level 1 uses design data and minimum material properties, level 2 includes measurements and stress calculations, and level 3 performs in-depth inspections and generates actual material data from samples. Key aspects of the methodology include examining changes in hardness, microstructure, and oxide scale thickness to estimate operating temperatures, and comparing the resulting stresses and temperatures to creep rupture data to evaluate failure criteria like crack initiation. Micrographs of samples from boiler tubes that operated for different durations show increasing carbide phases, coagulation, and sizes over time.
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET Journal
This document discusses preventive maintenance and root cause analysis of a sealed quench furnace used in an axle heat treatment line. The furnace was experiencing frequent breakdowns related to the heating and quenching units, including damage to the loading track, failures of the quench oil pump coupling and air cylinder seals, and delays in reaching the required temperature. Root cause analysis using why-why analysis and fishbone diagrams identified issues like a lack of rigid track support, improper burner design, pump misalignment, and components being too close to high heat. Countermeasures were implemented such as adding rigid track supports, modifying the burner design, changing couplings, and increasing cylinder height. After implementation, availability increased from 96.07
Syed K. Rizvi is a chemical engineer with over 30 years of experience in petroleum testing, laboratory management, process engineering, and project management. He currently works as a Lab Technical Team Lead/Manager at Suncor Energy, where he is responsible for new technology introductions, equipment reliability, and methodology development. Previously he has held roles such as Lab Manager, Scientific Specialist, and Quality Assurance Manager. He has a strong technical background and proven skills in developing testing methods, authoring standard operating procedures, and training technicians.
The document provides comprehensive guidelines for steam turbine-generator inspections and maintenance overhauls, including detailed procedures, templates, industry experience, and technical guidance across 7 volumes and 4 CDs. It addresses all aspects of planning and conducting turbine maintenance outages, from assessing unit condition to repairing specific components like diaphragms and generators. Utilities can use the guidelines and accompanying tools and data to effectively plan and execute outage work that incorporates industry best practices.
Khalid Mohammed Ismail El-Mowafy is a mechanical engineer with over 10 years of experience, currently working as a Static Equipment Engineer for UNION FENOSA GAS in Spain. He has experience working in Egypt, Saudi Arabia, and Kuwait, specializing in maintenance and construction of static equipment and piping systems in oil, gas, and petrochemical plants. Some of his responsibilities include preparing work packages for maintenance projects, developing shutdown plans, and supervising the execution of maintenance and turnaround activities. He has a bachelor's degree in mechanical engineering and is proficient in English, Arabic, and Microsoft Office.
This curriculum vitae summarizes the qualifications and experience of Kalpesh R. Chauhan. He has over 10 years of experience in instrumentation maintenance, installation, commissioning and project work in refinery, petrochemical and oil & gas industries. He held various roles such as manager, lead engineer and deputy manager at companies including Reliance Industries, Pearl Shell Gas to Liquid, Cairn India Limited and Essar Oil Ltd. He has extensive experience in commissioning and maintenance of instrumentation systems, executing projects, and ensuring safety standards. He holds a Bachelor's degree in Instrumentation and Control from SVIT, Vasad.
1. VTT TECHNICAL RESEARCH CENTRE OF FINLAND LTD
Risk management based on
proper material selection,
advanced monitoring and
remote maintenance
Jouko Suokas, Executive Vice President
VTT
2. 226/06/2015 2
Outline
Drivers and needs
Background
Risk based inspection (RBI)
FFS assessment
Lifing concepts and case examples
Preventive maintenance – VTT solution (Tolkku toolbox)
Remote maintenance
RAMS analysis
Gas turbine air filter performance evaluation
Concluding remarks
3. 326/06/2015 3
Drivers and needs
Drivers
Productivity, efficiency
Ageing assets, availability and reliability
HSE targets
Increased need for
Critical asset evaluation, risk analysis
Predicting and managing safe life
Correct targeting and timing of
maintenance
Deferring investments
4. 426/06/2015 4
Life Cycle Management
New facility Operation Ageing and
retrofitting
Conceptualization
Design phases
Manufacturing
Construction and
installation
Commissioning and
start-up
Operation and maintenance
Technical and operational
changes
Ageing management
Modernization
Retrofits
Investment decisions
Presentation focus
5. 526/06/2015 5
Risk based inspection (RBI)
In refineries/petrochemical industry often aligned to API RP 581
‘Risk-based Inspection Technology’:
To develop inspection plans for pressurized fixed equipment
Sections on inspection planning, determining probability of failure (PoF), and
consequence (CoF) modelling
Focus on impact and benefit from inspections, assumes time-independent
consequences
When critical items have been identified by RBI, VTT can e.g.
Analyse the criticality, condition and FFS in detail
Provide quantitative life assessment to support inspection/investment plans
Provide analysis and guidance on inspections, repairs and material issues
6. 626/06/2015 6
Fitness-for-service (FFS)
Assessment of ageing equipment for continued service
Why - Equipment in operation is no longer covered by design codes
Need - Economic run/repair/replace decisions require information on
damage mechanisms and their likelihood
Challenge - There are many possible damage or degradation
mechanisms which must be considered and identified
Brittle and ductile fracture, fatigue, corrosion, environmental assisted
cracking and creep at higher temperatures.
Various FFS assessment codes exist like API, BS, ASME and ANSI
API RP 579-1/ASME FFS-1 Fitness-For-Service
7. 726/06/2015 7
API RP 579-1/ASME FFS-1 Fitness-For-Service
Assessment levels
Level 1
Minimum amount of inspection or component information
Conservative screening - general concurrence with NBIC rules,
Plant inspection or engineering personnel
Level 2
More detailed, less conservative with more accurate results based on local stresses and material
properties
Quantitative damage characterization – size, shape, location, orientation
Qualified engineering personnel
Level 3
Most detailed evaluation – requires very detailed inspection and component information
Analysis procedures are based on material testing and/or numerical analysis techniques such as the
finite element method
Personnel with expertise in complex FFS assessments
8. 826/06/2015 8
Assessment of time/cycle to next
inspection/investment
When approaching design life or for life extension
purposes
After process disturbance (overheating, -loading or
chemical environment)
When changing process parameters or type of service
Flexible modules depending on needs
Life estimation based on microstructural changes,
deterministic life assessment
Probabilistic life assessment, RBI, simulations
Lifetime assessment concepts
AnalysisInspection TestingInitial data Recommendations Documentation
€
€ €
€
Owner benefits from FFS –
at least 10% reduction in
maintenance costs
(Bennet & Mixon 2011)
9. 926/06/2015 9
Lifetime assessment
Input information
Design, fabrication and maintenance history, QA documentation
Operational history (T, p, other loads, operating environments, process chemistry)
Materials (incl. welding, heat treatments etc.) and operating damage mechanisms
(e.g. creep, fatigue, corrosion, wear/erosion, combined mechanisms)
Methods
Condition assessment by inspection and testing
Predictive life modelling from combined initial info, measured/modelled material
and component properties, loads, damage progression and critical limits
Validation based on experimental data
After a year in service
Creep cracks on
7CrMoVTiB10-10 weld
SCC
10. 1026/06/2015 10
Case examples
Illustrating
Assessment of damage mechanisms
New lifing concepts
Benefits of selected technology
…
…
Different application areas
Heat exchangers and reformers
Reheater
Welded components
(Gas turbines)
…
…
11. 111126/06/2015
Remaining life
estimates
Thinning rate
• erosion and
corrosion
Creep life
• strain
• rupture
Scale growth rate
• impact on T
Inspection timing
Remaining life at
spec. locations
Operational data compilation
(temp + pressure history, maintenance)
Understanding ageing that results
to damage
• characteristics, mechanisms
• initial and end state
• for stress history
Temperature(°C)
Time (h)
Microstructural state
f(T) predict temp
Hardness
g(T) predict temp
Oxide thickness
h(T) predict temp
Data bases and in-house
models for microstructural
aging, oxidation and
hardness - functions of time
and temperature
Representative
stress and temp
Service
environment
Life management of high temperature components
12. 1226/06/2015 12
Evaluation of microstructural change, defects and local
composition (HT equipment)
Performance assessment: creep, impact, hardness…
Comparison to acceptance limits according to experience
Case: Ageing of heat exchangers and
reformers
Benefits
• Evaluated scope and extent for further operation
• Established needs and timing for repairs or
replacement
13. 1326/06/2015 13
Case - X20 header inspections + modelling + guidelines
Creep damage in X20 header after 135 000 h at 530°C
→ not common → rules for timing of inspections not as
as well established as in case of low alloy steels
• Cavitation evolving to crack growth at saddle
point: 4-year follow-up, extracted for detailed
evaluation
FEA of the branch: predicted damage confirmed
Benefits
• Guidelines for condition-based maintenance
• Material-specific behaviour established
14. 1426/06/2015 14
Ts
Tox
t1 t2 t3 ta
Temperature(°C)
tr
Ts
Tox
t3 ta
Time (h)
Temperature(°C)
tr
Teff
t0
As-new 16Mo3
Predicted +35 000 h
and verified in plantConversion from unknown to manageable equivalent history.
After 185000 h / (465) - 520°C
Unknown details of thermal history after multiple cycles of operation
+ internal cleaning
Solution: converted to equivalent history with single cleaning and
prediction from current condition → predicted minimum residual life
of 35 000 hours
Case: Reheater life extension
15. 1526/06/2015 15
Ni-based superalloy Rene N4 coated with platinum
aluminide coating
In-service material temperature evaluation based on
microstructural changes
Figure 1: Predicted temperature distribution of the overheated blade.
Case - Degradation in single-crystal gas
turbine blade
Benefits
• New method to evaluate the local metal
temperatures
• Assist to focus maintenance efforts ...
16. 1626/06/2015 16
Miniature testing – ease and improved
reliability for lifetime evaluation
Minature testing → small samples
Sampling easier, no need to cut tubes ,
no need to extensive weld repairs and heat
treatments → Time and cost savings
Miniature testing is cheaper that traditional
uniaxial creep testing
Results are obtained faster
Small punch (SP) test: one sample →
many tests
Yield and tensile strength
Impact energy (Charpy-V)
Fracture toughness (KIC , JIC)
Creep test
Pneumatic loading
system (push / pull)
based on bellows
technology
Examples of different
sample sizes ; miniature
on the right
18. 1826/06/2015 18
Preventive maintenance – VTT solution:
TOLKKU toolbox
Decision-making requires information. TOLKKU provides tools
for extracting useful information from vast amounts of data
collected from different sources.
T☺lkku
19. 1926/06/2015 19
TOLKKU toolbox - custom solutions
Varying situations and needs require versatile analysis tools. TOLKKU toolbox
provides building blocks to match current needs, allowing more flexibility than a
software with a fixed set of features.
Company-wide product development, machine operation, maintenance, and
management decision-making each have specific needs for information. TOLKKU
toolbox provides functionality to cover the whole life times of machines.
TOLKKU toolbox is a part of VTT's offering for lifetime management facilitating
solutions customized to company needs, such as early detection of faults,
optimizing maintenance plans, monitoring the use profiles of a machine fleet.
Design data
Fault statistics
Measurements
Etc.
Input / Data
Failure risk level
Remaining useful life
How to operate until
next planned service
Etc.
Output / Information
R&D
Machine operator
Control
Service and
maintenance
Utilization
20. 2026/06/2015 20
TOLKKU toolbox: Building blocks for O&M
Measurement
methods
Data acquisition
and transmission
Signal
processing
Diagnostics
methods
0 0.1 0.2 0.3
3
2.4
1.8
1.2
0.6
0
0.6
1.2
1.8
2.4
3
Aika [s]
Värähtelykiihtyvyys[m/s2]
0 50 100 150 200 250 300 350 400 450 500
0
0.004
0.008
0.012
0.016
Taajuus [Hz]
Värähtelykiihtyvyys[m/s2]
Now Time
Interaction of
components
Prognostics
Increased efficiency
Time
Cutting Lifting Moving
PotholeBegining End
Meas.
data Rainflow (tB..tE)
Time at level (tB..tE)
…
Use and load profiles
Spectrometry (SOAP)
Wear particles, etc
Acoustic emission (80 -120 kHz)
Temperature
Vibrations (0 - 10 kHz)
TOLKKU toolbox includes modules for
Data import
Data preparation
Feature extraction
State recognition
Load profiles
Anomaly detection
Analysis of causality
Time-frequency analysis
Analysis of bearings
and gearboxes
Decision support
Big data analytics
21. 2126/06/2015 21
TOLKKU toolbox: Continuous improvement
Data from
the whole
fleet
Feature extraction
State identification
Prognostics
Continuous
refining of
computational
models
Maintenance
plan
optimization
Exploratory
data analysis to
gain new insight
Service
data
22. 2226/06/2015 22
TOLKKU toolbox: Industrial perspective
The TOLKKU project gave us tools for collecting, organising, and
analysing huge amounts of data in a very short time. TOLKKU
tools are a powerful package for finding out the real cause of
failure (root cause). The analyses result in the repair being
carried out exactly on the right part of the machine. Machine
down time and service visits are minimised.
Bronto Skylift Oy Abj
The TOLKKU project has created a practical and applicable
data analysis toolkit that has already shown some promising
results in use. We are very pleased with the way a project that
is essentially research-oriented has been so well focused on
the industrial needs.
Konecranes Oy
25. 2526/06/2015 25
Manual maintenance work support with virtual
and Augmented Reality creates safe, reliable
and effective maintenance tasks
Courtesy of Delta Cygni Labs Ltd, Finland
26. 2626/06/2015 26
Assembly work assisted with Augmented
Reality: measurable improvements
Image courtesy of supakitmod at FreeDigitalPhotos.net
29. 2926/06/2015 29
The design phase lays the foundation for
RAMS performance - Case Total Train-Life
Management
Alstom was challenged to develop a full life cycle service offering to a new line of
the London subway network.
Subway trains are planned for 30 years service time and the construction time is two
years
The value of life cycle services across 30 years of service is 3 - 4 times the
aquisition cost of the trains
The development of the Total Train-Life Management offering lead the
manufacturing company to think about the impacts of system reliability, availability
and maintainability to the life cycle cost and performance
The machinery manufacturer made over 250 design
changes and modifications in order to make the trains
easier to operate and maintain
Source: Davies A.(2004). Industrial and Corporate Change. Vol 13, Nr. 5, pp. 727-756
30. 303026/06/2015
Transferring customer needs to RAMS
requirements - Case Pesmel Oy
Setting up a challenge
Pesmel Oy needed support to fulfil the RAMS process
requirements set by an international steel company
Solution
VTT helped Pesmel to understand the meaning and
implications of final customer´s RAMS requirements
as design criteria and manufacturing cost items.
Benefit
The final customer in steel industry received a
warehouse system that met their requirements
and had a profound documentation of
RAMS aspects.
32. 3226/06/2015 32
Gas turbine inlet air filter performance
evaluation
Filter performance evaluation on site
In land, on shore and off-shore
Tailored laboratory tests
Special expertise on wet condition evaluation
Chemical analysis of penetrated particles
Filter material and filter development
Mechanical fiber filters
Electrical filtration systems
References
GE Energy Products France SNC • Solar Turbines Inc • Donaldson • AAF •
Camfil • W.L.GORE & Associates GmbH • Northern Technical L.L.C. •
Eagle Filters • Ahlström Oy
Supply duct
(to be connected to the
ventilation system)
Material samples
High speed fan
Flow measurement
& control
34. 3426/06/2015 34
Concluding remarks 1/2
Accidents can be prevented - risk-based inspection and
maintenance provide ways for safe and economically
viable operation
Lifetime assessment help owners maintain the integrity
of assets and ensure the continued reliability of plant operation
Key issue in predicting and managing safe life is the
identification of critical assets, active damage mechanisms
and their likelihood
Novel remaining lifetime assessment techniques adapt
to a range of operating conditions, materials and
damage mechanisms and provide safe but not unduly
conservative predictions.
Maintenance on-demand is more cost efficient than fixed
intervals. Correct focussing and timing reduce costs, save
time and minimise impacts on HSE.
35. 3526/06/2015 35
Concluding remarks 2/2
Decision making requires information - Extracting useful
information from data for accurate and timely decision
making is a growing challenge.
Newest condition monitoring systems utilising software
toolboxes and data processing enable e.g. to detect
overloads and wear of the machine/process parts prior
failure, thus open new possibilities for O&M.
Role of simulation is increasing. Personnel can be trained
and production process optimized based on online
measurements and the respective simulators, both of which
increase safety and productivity.
Proper design, remote operation, monitoring and
maintenance with implementing new advanced information
technology is an emerging field and has proved its
applicability in various hazardous applications