SlideShare a Scribd company logo
JAIPUR ENGINEERING COLLEGE AND RESEARCH CENTRE
• A
Presentation
• On
• Cement Road Construction
• SUBMITTED TO:- SUBMITTED BY:-
Mr. YOGESH AGARWAL VIJAYPAL BAGARIYA
• (ASSISTANT PROFESSOR VIJENDRA SAINI
• OF CIVIL DEPARTMENT )
Using mix Concrete, there Some
Point to Construct the road-
• 1. preparation of Subgrade
• 2. Preparation of base
• 3. Watering of base
4. Formwork
• 5. Joints
• 6. Material mix & placing
• 7. Compaction
8. Finishing of Surface
9. Curing
• 10. Joint filling & Edging
• 11. Open to traffic
1.Preparation of Subgrade
• 1. Rolling on sub grade by roller.
• 2. Filling the granular soil in the weak part
and pot holes.
• 3. Correct the soil coat , Camber , longitudinal
slope.
• When concrete direct laid on subgrade, For
preventing the water-seepaging into the soil ,
used water proof paper on entire length.
2.Preparation of Base
W.B.M. base :-
As base material of W.B.M. Road; stone ballast &
concrete 10-15cm layer are used With Water.
 For bonding between concrete slab & W.B.M.
used 1:2 cement wash on W.B.M.
•
3.Watering of Base
• If base is dry then using the sprinkling process
on it properly after that placing the concrete.
4. Formwork
• Material for formwork:-
• Wooden sheets, battens, plywood, fibre hard
board, steel plates, angles, rope, minerals.
1. before using form work, it should free from
all type material like as dust ,cement.
2. To placing the concrete in appropriate depth
used 2.5-5cm thick and 3mtr long wooden
sheeting.
3. After 24hrs form work displaced next length
of road.
5. Joints
 Where it is necessary to provide transverse,
Longitudinal joints; there wedge of woods,
metals fix on level of concrete.
 After setting of concrete it should be pull out.
Types of joints:-
• 1. Logitudinal Joints
• 2. Transverse Joints
6. Material Mix & Placing
• Mixer is equipment that mix the concrete
using cement, concrete, sand and water.
7. Compaction
• Purpose of compaction is that to pull out air
from void and make concrete harden.
• Compaction done by:-
• 1.mechanically surface vibrator
2. manually hand tempers
8. Finishing of Surface
For levelling the surface use floating,
screeding , power trowel. So that there is no
acceptable more than 3mm variation in
concrete level surface.
9. Curing
• Curing is the name of increasing the hydration
process of cement. After setting the concrete ,
curing process done till 14-28days.
• Some method of curing are:-
• 1. Covering with gunny bags
• 2. Sprinkling of water
• 3.By ponding
• 4. Membrane curing
• 5. Steam curing
10. Filling Joint & Edging
 After drying road, clean the joints and fill the
shelling compound or hot bitumen .
 Also bitumen fill road bank.
To protect damaging the sides of concrete
pavements used over burnt brick work.
 In place of brick, provided kerb of pre mix
concrete.
11. Open to Traffic
Generally after a month, road should be open
to traffic.
 If used rapid hardening cement it take 7 days
to open traffic.
Summer training ppt on cc road construction
Summer training ppt on cc road construction

More Related Content

What's hot

PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
Imrul Quesh
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
arslan000
 
Summer training report on cement Road Construction
 Summer training report on cement Road Construction Summer training report on cement Road Construction
Summer training report on cement Road Construction
Vijaypal Bagariya
 
Construction of roads presentations
Construction of roads presentationsConstruction of roads presentations
Construction of roads presentationsIjaz Hassan Khan
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
Anil Gupta
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
UTU Dehradun
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
deepak athwal
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
Pradeep Yadav
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
Pawan Kumar
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
Shoaib Wani
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavements
Shaik Asif Ahmed
 
Road Construction
Road ConstructionRoad Construction
Road Construction
Danish Mohd
 
Grouting
GroutingGrouting
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
rakeshchoudhary129
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
Ratnesh Kushwaha
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
Meet Shah
 
road construction
road constructionroad construction
road construction
Rebwar Anwar
 

What's hot (20)

PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
 
Summer training report on cement Road Construction
 Summer training report on cement Road Construction Summer training report on cement Road Construction
Summer training report on cement Road Construction
 
Construction of roads presentations
Construction of roads presentationsConstruction of roads presentations
Construction of roads presentations
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavements
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
Grouting
GroutingGrouting
Grouting
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
 
road construction
road constructionroad construction
road construction
 

Similar to Summer training ppt on cc road construction

Naresh kumar ppt
Naresh kumar  pptNaresh kumar  ppt
Naresh kumar ppt
Naresh Ambesh
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
Anshul Shakya
 
Presentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,deptPresentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,dept
Lovely Professional University
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water Concreting
Sanjan Banerjee
 
CONCRETE PPT SA JBP
CONCRETE PPT SA JBPCONCRETE PPT SA JBP
CONCRETE PPT SA JBP
Suyash Awasthi
 
Construction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roadsConstruction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roads
ssuserdcb186
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
JOMIN JOSE
 
Building construction
Building constructionBuilding construction
Building construction
nhmurad
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
Himanshu Gupta
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
BalpreetSingh47890
 
Making of concrete
Making of concreteMaking of concrete
Making of concrete
builtify
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam cores
Ujwal Ujwal
 
Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
KumarS250747
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
reemajadwani
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
Adib Ramli
 
Buildingmaterials 131128125947-phpapp01
Buildingmaterials 131128125947-phpapp01Buildingmaterials 131128125947-phpapp01
Buildingmaterials 131128125947-phpapp01
Udit Jain
 
Summer internship at patel infrastructure
Summer internship at patel infrastructureSummer internship at patel infrastructure
Summer internship at patel infrastructure
parth ghoghari
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
Janki Patel
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
AMITYADAV960525
 

Similar to Summer training ppt on cc road construction (20)

Naresh kumar ppt
Naresh kumar  pptNaresh kumar  ppt
Naresh kumar ppt
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 
Presentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,deptPresentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,dept
 
A Seminar on Under Water Concreting
A Seminar on Under Water ConcretingA Seminar on Under Water Concreting
A Seminar on Under Water Concreting
 
CONCRETE PPT SA JBP
CONCRETE PPT SA JBPCONCRETE PPT SA JBP
CONCRETE PPT SA JBP
 
Construction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roadsConstruction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roads
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Building construction
Building constructionBuilding construction
Building construction
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
 
Making of concrete
Making of concreteMaking of concrete
Making of concrete
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam cores
 
Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Buildingmaterials 131128125947-phpapp01
Buildingmaterials 131128125947-phpapp01Buildingmaterials 131128125947-phpapp01
Buildingmaterials 131128125947-phpapp01
 
Summer internship at patel infrastructure
Summer internship at patel infrastructureSummer internship at patel infrastructure
Summer internship at patel infrastructure
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 

Recently uploaded

一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 

Recently uploaded (20)

一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 

Summer training ppt on cc road construction

  • 1. JAIPUR ENGINEERING COLLEGE AND RESEARCH CENTRE • A Presentation • On • Cement Road Construction • SUBMITTED TO:- SUBMITTED BY:- Mr. YOGESH AGARWAL VIJAYPAL BAGARIYA • (ASSISTANT PROFESSOR VIJENDRA SAINI • OF CIVIL DEPARTMENT )
  • 2. Using mix Concrete, there Some Point to Construct the road- • 1. preparation of Subgrade • 2. Preparation of base • 3. Watering of base 4. Formwork • 5. Joints • 6. Material mix & placing • 7. Compaction
  • 3. 8. Finishing of Surface 9. Curing • 10. Joint filling & Edging • 11. Open to traffic
  • 4. 1.Preparation of Subgrade • 1. Rolling on sub grade by roller. • 2. Filling the granular soil in the weak part and pot holes. • 3. Correct the soil coat , Camber , longitudinal slope. • When concrete direct laid on subgrade, For preventing the water-seepaging into the soil , used water proof paper on entire length.
  • 5.
  • 6. 2.Preparation of Base W.B.M. base :- As base material of W.B.M. Road; stone ballast & concrete 10-15cm layer are used With Water.  For bonding between concrete slab & W.B.M. used 1:2 cement wash on W.B.M. •
  • 7. 3.Watering of Base • If base is dry then using the sprinkling process on it properly after that placing the concrete.
  • 8. 4. Formwork • Material for formwork:- • Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope, minerals. 1. before using form work, it should free from all type material like as dust ,cement. 2. To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting. 3. After 24hrs form work displaced next length of road.
  • 9. 5. Joints  Where it is necessary to provide transverse, Longitudinal joints; there wedge of woods, metals fix on level of concrete.  After setting of concrete it should be pull out. Types of joints:- • 1. Logitudinal Joints • 2. Transverse Joints
  • 10. 6. Material Mix & Placing • Mixer is equipment that mix the concrete using cement, concrete, sand and water.
  • 11. 7. Compaction • Purpose of compaction is that to pull out air from void and make concrete harden. • Compaction done by:- • 1.mechanically surface vibrator 2. manually hand tempers
  • 12. 8. Finishing of Surface For levelling the surface use floating, screeding , power trowel. So that there is no acceptable more than 3mm variation in concrete level surface.
  • 13. 9. Curing • Curing is the name of increasing the hydration process of cement. After setting the concrete , curing process done till 14-28days. • Some method of curing are:- • 1. Covering with gunny bags • 2. Sprinkling of water • 3.By ponding • 4. Membrane curing • 5. Steam curing
  • 14.
  • 15. 10. Filling Joint & Edging  After drying road, clean the joints and fill the shelling compound or hot bitumen .  Also bitumen fill road bank. To protect damaging the sides of concrete pavements used over burnt brick work.  In place of brick, provided kerb of pre mix concrete.
  • 16. 11. Open to Traffic Generally after a month, road should be open to traffic.  If used rapid hardening cement it take 7 days to open traffic.