SlideShare a Scribd company logo
1 of 12
Download to read offline
Page 1
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Persons at Risk (Groups) Risk Assessor Appointment Tel. No. Description of Task or Activity
A – SALCO employees Ahmad Ali Khan H&S Manager 0506219441 SALCO Operatives accessing roof
areas in order to carry out surveys,
inspections or carry out maintenance
activities
B – Contractors/Sub contractors
C – Tenants
D – Members of the public
Work Type Review Date
Routine Nov 2023
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
1) Falls from
height
Serious injury
A,B,C,D Cr O H 1) Only persons trained and
competent to do so must access
roof areas
2) Roof areas should be
appropriately secured in order to
prevent unauthorised access
3) Avoid accessing roof areas where
practicably possible
4) Use work equipment or other
measures to prevent falls where
work at height cannot be avoided
M 3) Consider viewing roof area by
other means such as google
maps, drone footage or remote
camera/cctv or other safe
elevated view point
4) Use area with existing 950mm
minimum height parapet wall,
erecting edge protection, using
MEWP or work restraint system
5) Using nets, air or bean bags or
fall arrest harness system
L
Page 2
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
5) Where they cannot eliminate
the risk of fall, use work
equipment or other measures
to minimise the distance and
consequences of a fall should
one occur
2) No or
limited edge
protection
A,B,C,D Cr O H 1) Where fully compliant collective
edge protection does not
exist access should be further
controlled by the following; a
safe system of work should be
implemented which sets out
the precautions to be taken
L
3) Roof anchors
and man safe
systems
A,B Cr O H 1) All anchor devices and man
safe systems should be
inspected by a competent
person and tagged to indicate
they have been tested and are
within date.
2) Only use harnesses and
lanyards which are compatible
with the equipment
M 1) Do not use any equipment that
has not been tested and is
within its expiry date
2) Harnesses and lanyards should
be specifically fitted to an
individual user and maintained
in line with an appropriate
testing schedule
L
Page 3
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
4) Getting on
and off the
roof
A,B Cr O H 1) Means of entry and exit to a
roof should always be secure
and should consists of either
a general access scaffold or
mobile tower Roof hatch with a
secure ladder, staircase or an
appropriately secured ladder
with safe step on step off area
M 1) All ladders used should be
subject to an appropriate
inspection schedule
L
5) Roof access
hatches
A,B Cr O H 1) Roof access hatches pose
openings that must be
protected
M 1) Close the hatch once on the
roof to prevent falls through
opening
2) Ensure that the cover will not
latch in a way that prevents exit
3) If the hatch must be left open
for any reason ensure it is
protected by either a guard
rail or personal fall arrest
equipment
L
6) Falling
objects
A,B,C,D Cr O H 1) Use edge protection when
appropriate to prevent objects
falling such as toe boards on
scaffold
2) Where tools and equipment are
being used close to the roof
M 1,2,3) Where this level of protection
cannot be provided, consider
using debris netting, fans, covered
walkways or similar safeguards to
stop falling material from causing
injury
L
Page 4
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
edge and there is risk of items
falling and causing injury,
ensure they are attached to a
safety lanyard
3) Where possible prevent access
to the ground area below or
adjacent to roof work
4) Beware of the sail effect for
sheet or light materials
5) Maintain good standards of
housekeeping and prevent
waste from accumulating
5) Never throw waste on or off
of roof area, either securely
lower waste to the ground or
use a rubbish chute to a secure
container
7) Fixed vertical
ladders
(Jacobs
ladders)
A,B S O M 1) Inspect ladders prior to use to
ensure they secure and safe to
use
2) Always maintain the maximum
number of contacts with the
ladder
3) Do not use vertical ladders as a
work platform
L 1) If ladder is found to be unsafe
don’t not use, use hazard tape
or signage to indicate that the
ladder is out of use and report
any defects
2) Exercise caution if the ladder is
slippery or wet or is not fitted
with hoop protection
L
Page 5
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
8) Slippery
surfaces
A,B S P H 1) Appropriate footwear should
be worn when accessing roof
areas, extra care should be
taken in areas that are wet, icy
or covered in moss or similar
L
9) Adverse
weather
conditions
A,B S P H 1) Work should not be carried
out in conditions that could
endanger the health and safety
of workers; such as high winds
heavy rain, snow or ice
L
10) Insufficient
lighting
A,B S P H 1) Do not attempt to access roofs
or carry out work in poorly lit
areas
1) Provide additional lighting such
as torches or fixed temporary
lighting or carry out work during
daylight hours
11) Unprotected
walkways
A,B S O M 1) Extra care should be taken
when walking in unprotected
walkways, pay particular
attention to slip or trip hazards
that may be present
M 2) Avoid walking in valley gutters
where possible as they can be
very slippery and damage to
lead flashing is likely
L
Page 6
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
12) Lone Working A,B S O M 1) Lone working on roofs is not
permitted unless without
express permission of
supervisor/manager and
confirmation that all potential
risks are adequately controlled
L
13) Fragile roofs,
sky lights
A,B Cr O H 1) The fragility of a roof should
be confirmed by a competent
person prior to accessing the
roof
2) Where possible work off of an
alternative platform such as a
MEWP
3) Access to fragile areas of the
roof should be communicated
to all workers and signed or
blocked off where ever possible
1) If there is any doubt then a roof
should be treated as fragile
until it is confirmed it is not
3) Working off a fragile roof or
roofs containing unprotected
fragile areas should be carefully
planned and subjected to
a safe system of work which
should be communicated to all
workers
14) Overloading
roof
A,B,C,D Cr O H 1) Where heavy equipment of
equipment are required to be
placed on a roof consideration
should be given to the safe
working load of the roof
M 1) If in doubt competent advise
should be sought
L
Page 7
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
15) Asbestos A,B,C,D S O M 1) Consult the asbestos
information for the property
prior to accessing the roof area
and follow asbestos procedures
prior to commencing work
L
16) Hot works A,B,C,D Cr O H 1) All hot works undertaken on a
roof must be done under a hot
works permit system
M 1) Permits must be supervised
and signed off by a competent
supervisor
L
17) Electrical
hazards
(including
High Voltage)
A,B Cr O H 1) Workers should be aware of any
potential electrical hazards.
2) Particular attention should
be paid to electrical services/
cables that may be suspended
above the roof area. Contact
with or arcing to a material that
conducts electricity, such as
scaffold poles or metal sheeting
will cause serious injury or
death
M 1) If in any doubt advice should
be sought from a competent
electrician
2) Where possible electrical
services should be isolated
prior to work starting or access
to these areas should be
restricted
3) Any electrical hazards should
be communicated to all workers
that access the roof area
L
Page 8
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
18) Manual
handling
A,B S O M 1) Operatives are trained and
competent to carry out manual
handling
M 1) See SRA0024 Manual Handling
2) Consideration should be given
to handling tools, material and
equipment safely onto the
roof area, mechanical lifting
aids should be used where
appropriate
L
19) Trip hazards A,B S O M 1) Particular care should be taken
of any potential trip hazards on
the roof such as the presence
of services, plant, gantries, roof
finishes, drains, gulley’s, man
safe systems and vents
2) Good housekeeping should be
applied at all times to prevent
hazards from tools, equipment,
material and waste
M 1) Purpose made walk ways should
be provided where possible
L
20) Electroma-
gnetic/radio
waves
A,B S O M 1) The presence of all transmitters
should be noted and where
appropriate competent advice
should be sought from the
device owners
M 1) where potential risks are
identified work should be
undertaken in line with a safe
system of work
L
Page 9
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
21) UV Exposure/
heat
A,B M O L 1) Workers who are exposed to
UV rays should use adequate
protection/PPE to cover
exposed areas of skin and eyes.
2) Keep well hydrated with
drinking water
L 1) Avoid working in direct sunlight
for extended periods of time or
during the hottest part of the
day where possible
L
22) Hazardous
substances
A,B S O M 1) All hazardous substances
should be used in line with
the appropriate COSHH control
measures
L
23) Head height
obstructions
A,B S O M 1) Head height obstructions
should be signed and also
locally protected where
possible
2) Hard hats should be worn
where identified
L
Page 10
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Hazard/Risk Groups at
Risk
Severity Probability Risk Level
before
Controls
Existing Controls Risk Level
with
Controls
Additional Controls Required Risk Level
with added
Controls
Actioned by
24) Hazardous
emissions
from fume
stacks
A,B S O M 1) Fume stacks should be
identified prior to the
commencement of works
2) If stacks are not venting to a
safe height above roof level
and are affecting the work area,
then the plant producing the
fumes should be isolated prior
to the commencement of any
works.
L 2) If isolation is not possible
and works cannot be carried
out safely then work should
not commence. Contact your
supervisor for advice
L
25) Automatic
opening
vents (AOV)
and windows
A,B S O M 1) AOV’s and automatic opening
windows should be identified
prior to the commencement of
any works
2) The presence of AOV’s
and windows should be
appropriately communicated to
all workers and barrier of where
necessary particularly if they
present a fragile roof hazard
L
Page 11
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Personal Protective Equipment required (PPE): Icon Glossary
HARD HAT
YES
SAFETY VISOR
NO
DUST MASK
NO
SAFETY FOOTWEAR
YES
EYE PROTECTION
NO
EAR PROTECTION
NO
HAND PROTECTION
NO
HIGH VIZ
YES
Page 12
SRA 0029
SAUDI SALCO
Safety Risk Assessment
Roofing Works/Surveying/Inspections
Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable,
Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable
Contingency Plan
Item
No
Hazard/Risk Occurrence Contingency/Action
1 Unauthorised entry to working area.
Violence and aggression/public access
to restricted work area
1) Aggressive behaviour/damage to access equipment 1) Work would cease. Unauthorised visitors asked to leave One
Direct supervisor informed. Emergency services called if
required.
2) Lone working procedure in place.
2 Electricity failure/flood/pipe leak/
striking cable/pipework/suspected
asbestos containing material
Lighting failure/water in premises/
electrocution/gas leak/exposure to
asbestos
1) Severance of services/lighting failure.
2) Detection of suspected asbestos containing materials
1) Work would cease and client would be informed by One
Direct Supervisor so remedial work can be carried out in
order for the work to re-start.
2) Work would cease and client would be informed by One
Direct Supervisor so remedial work can be carried out in
order for the work to re-start. One Direct asbestos policy
and procedures as agreed with individual clients.
3 Poor communication/lack of contact
between direct labour and sub-
contractors
Poor standards/work being carried out
in an inappropriate manner
1) Poor standard of work/low customer
satisfaction/violent and aggressive behaviour from
customer
1) One Direct supervisor to keep all parties informed of work
procedures and standards

More Related Content

Similar to sra0029_roof_works_-_surveying_-_inspections.pdf

FARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxFARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxssuser10f6ca
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJESUSBASILIOANTONIO
 
International Journal of Computational Engineering Research (IJCER)
International Journal of Computational Engineering Research (IJCER) International Journal of Computational Engineering Research (IJCER)
International Journal of Computational Engineering Research (IJCER) ijceronline
 
Street of risk assessment
Street of risk assessmentStreet of risk assessment
Street of risk assessmentBruna Martins
 
Street of risk assessment
Street of risk assessmentStreet of risk assessment
Street of risk assessmentErica Da Silva
 
Defense against Drones- Understand Challenges and Solutions.pdf
Defense against Drones- Understand Challenges and Solutions.pdfDefense against Drones- Understand Challenges and Solutions.pdf
Defense against Drones- Understand Challenges and Solutions.pdfNovoQuad
 

Similar to sra0029_roof_works_-_surveying_-_inspections.pdf (10)

FARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docxFARC nº 21 – 4G1. TD01B - AAA.docx
FARC nº 21 – 4G1. TD01B - AAA.docx
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
sana
sanasana
sana
 
International Journal of Computational Engineering Research (IJCER)
International Journal of Computational Engineering Research (IJCER) International Journal of Computational Engineering Research (IJCER)
International Journal of Computational Engineering Research (IJCER)
 
Street of risk assessment
Street of risk assessmentStreet of risk assessment
Street of risk assessment
 
Street of risk assessment
Street of risk assessmentStreet of risk assessment
Street of risk assessment
 
Defense against Drones- Understand Challenges and Solutions.pdf
Defense against Drones- Understand Challenges and Solutions.pdfDefense against Drones- Understand Challenges and Solutions.pdf
Defense against Drones- Understand Challenges and Solutions.pdf
 
Construction safety
Construction safetyConstruction safety
Construction safety
 
Safety topics
Safety topicsSafety topics
Safety topics
 

More from AhmedAliKhan38

PP FOR Food Safety Campaign -Nov-18-2023.pptx
PP FOR Food Safety Campaign -Nov-18-2023.pptxPP FOR Food Safety Campaign -Nov-18-2023.pptx
PP FOR Food Safety Campaign -Nov-18-2023.pptxAhmedAliKhan38
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...AhmedAliKhan38
 
Traffic management PPT To enhance awareness.pptx
Traffic management PPT To enhance awareness.pptxTraffic management PPT To enhance awareness.pptx
Traffic management PPT To enhance awareness.pptxAhmedAliKhan38
 
iso-14001-2015-checklist lead auditor .pdf
iso-14001-2015-checklist lead auditor .pdfiso-14001-2015-checklist lead auditor .pdf
iso-14001-2015-checklist lead auditor .pdfAhmedAliKhan38
 
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptx
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptxHEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptx
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptxAhmedAliKhan38
 
safety gloves . power point presentation
safety gloves . power point presentationsafety gloves . power point presentation
safety gloves . power point presentationAhmedAliKhan38
 

More from AhmedAliKhan38 (6)

PP FOR Food Safety Campaign -Nov-18-2023.pptx
PP FOR Food Safety Campaign -Nov-18-2023.pptxPP FOR Food Safety Campaign -Nov-18-2023.pptx
PP FOR Food Safety Campaign -Nov-18-2023.pptx
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...
 
Traffic management PPT To enhance awareness.pptx
Traffic management PPT To enhance awareness.pptxTraffic management PPT To enhance awareness.pptx
Traffic management PPT To enhance awareness.pptx
 
iso-14001-2015-checklist lead auditor .pdf
iso-14001-2015-checklist lead auditor .pdfiso-14001-2015-checklist lead auditor .pdf
iso-14001-2015-checklist lead auditor .pdf
 
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptx
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptxHEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptx
HEALTY LIFE IS A HAPPY LIFE StaffWellnessinECE-Nationalversion-YouMatter.pptx
 
safety gloves . power point presentation
safety gloves . power point presentationsafety gloves . power point presentation
safety gloves . power point presentation
 

Recently uploaded

Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 

Recently uploaded (20)

Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 

sra0029_roof_works_-_surveying_-_inspections.pdf

  • 1. Page 1 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Persons at Risk (Groups) Risk Assessor Appointment Tel. No. Description of Task or Activity A – SALCO employees Ahmad Ali Khan H&S Manager 0506219441 SALCO Operatives accessing roof areas in order to carry out surveys, inspections or carry out maintenance activities B – Contractors/Sub contractors C – Tenants D – Members of the public Work Type Review Date Routine Nov 2023 Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 1) Falls from height Serious injury A,B,C,D Cr O H 1) Only persons trained and competent to do so must access roof areas 2) Roof areas should be appropriately secured in order to prevent unauthorised access 3) Avoid accessing roof areas where practicably possible 4) Use work equipment or other measures to prevent falls where work at height cannot be avoided M 3) Consider viewing roof area by other means such as google maps, drone footage or remote camera/cctv or other safe elevated view point 4) Use area with existing 950mm minimum height parapet wall, erecting edge protection, using MEWP or work restraint system 5) Using nets, air or bean bags or fall arrest harness system L
  • 2. Page 2 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 5) Where they cannot eliminate the risk of fall, use work equipment or other measures to minimise the distance and consequences of a fall should one occur 2) No or limited edge protection A,B,C,D Cr O H 1) Where fully compliant collective edge protection does not exist access should be further controlled by the following; a safe system of work should be implemented which sets out the precautions to be taken L 3) Roof anchors and man safe systems A,B Cr O H 1) All anchor devices and man safe systems should be inspected by a competent person and tagged to indicate they have been tested and are within date. 2) Only use harnesses and lanyards which are compatible with the equipment M 1) Do not use any equipment that has not been tested and is within its expiry date 2) Harnesses and lanyards should be specifically fitted to an individual user and maintained in line with an appropriate testing schedule L
  • 3. Page 3 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 4) Getting on and off the roof A,B Cr O H 1) Means of entry and exit to a roof should always be secure and should consists of either a general access scaffold or mobile tower Roof hatch with a secure ladder, staircase or an appropriately secured ladder with safe step on step off area M 1) All ladders used should be subject to an appropriate inspection schedule L 5) Roof access hatches A,B Cr O H 1) Roof access hatches pose openings that must be protected M 1) Close the hatch once on the roof to prevent falls through opening 2) Ensure that the cover will not latch in a way that prevents exit 3) If the hatch must be left open for any reason ensure it is protected by either a guard rail or personal fall arrest equipment L 6) Falling objects A,B,C,D Cr O H 1) Use edge protection when appropriate to prevent objects falling such as toe boards on scaffold 2) Where tools and equipment are being used close to the roof M 1,2,3) Where this level of protection cannot be provided, consider using debris netting, fans, covered walkways or similar safeguards to stop falling material from causing injury L
  • 4. Page 4 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by edge and there is risk of items falling and causing injury, ensure they are attached to a safety lanyard 3) Where possible prevent access to the ground area below or adjacent to roof work 4) Beware of the sail effect for sheet or light materials 5) Maintain good standards of housekeeping and prevent waste from accumulating 5) Never throw waste on or off of roof area, either securely lower waste to the ground or use a rubbish chute to a secure container 7) Fixed vertical ladders (Jacobs ladders) A,B S O M 1) Inspect ladders prior to use to ensure they secure and safe to use 2) Always maintain the maximum number of contacts with the ladder 3) Do not use vertical ladders as a work platform L 1) If ladder is found to be unsafe don’t not use, use hazard tape or signage to indicate that the ladder is out of use and report any defects 2) Exercise caution if the ladder is slippery or wet or is not fitted with hoop protection L
  • 5. Page 5 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 8) Slippery surfaces A,B S P H 1) Appropriate footwear should be worn when accessing roof areas, extra care should be taken in areas that are wet, icy or covered in moss or similar L 9) Adverse weather conditions A,B S P H 1) Work should not be carried out in conditions that could endanger the health and safety of workers; such as high winds heavy rain, snow or ice L 10) Insufficient lighting A,B S P H 1) Do not attempt to access roofs or carry out work in poorly lit areas 1) Provide additional lighting such as torches or fixed temporary lighting or carry out work during daylight hours 11) Unprotected walkways A,B S O M 1) Extra care should be taken when walking in unprotected walkways, pay particular attention to slip or trip hazards that may be present M 2) Avoid walking in valley gutters where possible as they can be very slippery and damage to lead flashing is likely L
  • 6. Page 6 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 12) Lone Working A,B S O M 1) Lone working on roofs is not permitted unless without express permission of supervisor/manager and confirmation that all potential risks are adequately controlled L 13) Fragile roofs, sky lights A,B Cr O H 1) The fragility of a roof should be confirmed by a competent person prior to accessing the roof 2) Where possible work off of an alternative platform such as a MEWP 3) Access to fragile areas of the roof should be communicated to all workers and signed or blocked off where ever possible 1) If there is any doubt then a roof should be treated as fragile until it is confirmed it is not 3) Working off a fragile roof or roofs containing unprotected fragile areas should be carefully planned and subjected to a safe system of work which should be communicated to all workers 14) Overloading roof A,B,C,D Cr O H 1) Where heavy equipment of equipment are required to be placed on a roof consideration should be given to the safe working load of the roof M 1) If in doubt competent advise should be sought L
  • 7. Page 7 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 15) Asbestos A,B,C,D S O M 1) Consult the asbestos information for the property prior to accessing the roof area and follow asbestos procedures prior to commencing work L 16) Hot works A,B,C,D Cr O H 1) All hot works undertaken on a roof must be done under a hot works permit system M 1) Permits must be supervised and signed off by a competent supervisor L 17) Electrical hazards (including High Voltage) A,B Cr O H 1) Workers should be aware of any potential electrical hazards. 2) Particular attention should be paid to electrical services/ cables that may be suspended above the roof area. Contact with or arcing to a material that conducts electricity, such as scaffold poles or metal sheeting will cause serious injury or death M 1) If in any doubt advice should be sought from a competent electrician 2) Where possible electrical services should be isolated prior to work starting or access to these areas should be restricted 3) Any electrical hazards should be communicated to all workers that access the roof area L
  • 8. Page 8 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 18) Manual handling A,B S O M 1) Operatives are trained and competent to carry out manual handling M 1) See SRA0024 Manual Handling 2) Consideration should be given to handling tools, material and equipment safely onto the roof area, mechanical lifting aids should be used where appropriate L 19) Trip hazards A,B S O M 1) Particular care should be taken of any potential trip hazards on the roof such as the presence of services, plant, gantries, roof finishes, drains, gulley’s, man safe systems and vents 2) Good housekeeping should be applied at all times to prevent hazards from tools, equipment, material and waste M 1) Purpose made walk ways should be provided where possible L 20) Electroma- gnetic/radio waves A,B S O M 1) The presence of all transmitters should be noted and where appropriate competent advice should be sought from the device owners M 1) where potential risks are identified work should be undertaken in line with a safe system of work L
  • 9. Page 9 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 21) UV Exposure/ heat A,B M O L 1) Workers who are exposed to UV rays should use adequate protection/PPE to cover exposed areas of skin and eyes. 2) Keep well hydrated with drinking water L 1) Avoid working in direct sunlight for extended periods of time or during the hottest part of the day where possible L 22) Hazardous substances A,B S O M 1) All hazardous substances should be used in line with the appropriate COSHH control measures L 23) Head height obstructions A,B S O M 1) Head height obstructions should be signed and also locally protected where possible 2) Hard hats should be worn where identified L
  • 10. Page 10 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Hazard/Risk Groups at Risk Severity Probability Risk Level before Controls Existing Controls Risk Level with Controls Additional Controls Required Risk Level with added Controls Actioned by 24) Hazardous emissions from fume stacks A,B S O M 1) Fume stacks should be identified prior to the commencement of works 2) If stacks are not venting to a safe height above roof level and are affecting the work area, then the plant producing the fumes should be isolated prior to the commencement of any works. L 2) If isolation is not possible and works cannot be carried out safely then work should not commence. Contact your supervisor for advice L 25) Automatic opening vents (AOV) and windows A,B S O M 1) AOV’s and automatic opening windows should be identified prior to the commencement of any works 2) The presence of AOV’s and windows should be appropriately communicated to all workers and barrier of where necessary particularly if they present a fragile roof hazard L
  • 11. Page 11 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Personal Protective Equipment required (PPE): Icon Glossary HARD HAT YES SAFETY VISOR NO DUST MASK NO SAFETY FOOTWEAR YES EYE PROTECTION NO EAR PROTECTION NO HAND PROTECTION NO HIGH VIZ YES
  • 12. Page 12 SRA 0029 SAUDI SALCO Safety Risk Assessment Roofing Works/Surveying/Inspections Severity C=Catastrophic, Cr=Critical, S=Serious, M=Minor, Probability N=Negligible, F=Frequent, P=Probable, O=Occasional, R=Remote, I=Improbable, Risk T=Tolerable, L=Low, M=Medium, H=High, N=Intolerable Contingency Plan Item No Hazard/Risk Occurrence Contingency/Action 1 Unauthorised entry to working area. Violence and aggression/public access to restricted work area 1) Aggressive behaviour/damage to access equipment 1) Work would cease. Unauthorised visitors asked to leave One Direct supervisor informed. Emergency services called if required. 2) Lone working procedure in place. 2 Electricity failure/flood/pipe leak/ striking cable/pipework/suspected asbestos containing material Lighting failure/water in premises/ electrocution/gas leak/exposure to asbestos 1) Severance of services/lighting failure. 2) Detection of suspected asbestos containing materials 1) Work would cease and client would be informed by One Direct Supervisor so remedial work can be carried out in order for the work to re-start. 2) Work would cease and client would be informed by One Direct Supervisor so remedial work can be carried out in order for the work to re-start. One Direct asbestos policy and procedures as agreed with individual clients. 3 Poor communication/lack of contact between direct labour and sub- contractors Poor standards/work being carried out in an inappropriate manner 1) Poor standard of work/low customer satisfaction/violent and aggressive behaviour from customer 1) One Direct supervisor to keep all parties informed of work procedures and standards