1
Shaft Construction
Dr. Greene
Brian Doyle | Jacob Groezinger | Lillian Kravitz | John Rosser
Team 5
ISE 311 A51 – Enterprise Systems
Monday, April 11, 2016
2
Agenda
Introduction
Background
Assumptions
Analysis
Conclusions
Recommendations
Ideas for Future Research
3
Framework Analysis Conclusions Recommendations
Introduction
Shaft Construction Company
(SCC)
• Key Stakeholders:
• John Shaft – President & CEO
• Bumpy Jonas – Lead Designer
• Ellie Moore – Director of Personnel
• Objective:
• 15,000 seat stadium on college
campus
• Net Income: $450,000
• Client Details:
• Jamestown, PA
• Jamestown Community College
http://cdn0.wideopencountry.com/wp-content/uploads/2015/08/high-school-football-793x526.jpg
4
Framework Analysis Conclusions Recommendations
Background
Background
• Constraints:
• August 26th, 2017 deadline
• Resource allocation
• Penalties
• Potential Risks:
• Approximately 10-week strike
• Harsh winter:
• Charge for pouring concrete
5
Framework Analysis Conclusions Recommendations
Assumptions
Project:
• Project start date: June 6th, 2016
• No work on weekends
• No overtime
• Equipment and materials are out of scope
• Winter months: December, January & February
6
Framework Analysis Conclusions Recommendations
Assumptions (con’t)
Construction:
• Footings require three weeks to cure
• Work that follows footings cannot begin until curing is complete
• Site preparation and foundation includes staging areas and traffic flow
redirection
• When forecasted temperatures are higher than 90 degrees, workers will
utilize early mornings for heat sensitive activities
• “Filling of the field” is assumed to be activity C, build field
• Tasks can pause midway through duration and resume at a later time
7
Framework Analysis Conclusions Recommendations
Assumptions (con’t)
Employees:
• 67% of employees laid off during winter
• 15 employees during December, January and February, 30 for other months
• 5 employees utilized for management
• SCC hires unionized employees
• Strike begins when contract expires
Costs
• Projected net income of project: $450,000
• Indirect cost applied to alternate scenarios based off of do nothing benchmark
• Federal Holidays are insignificant
8
Framework Analysis Conclusions Recommendations
Work Breakdown Structure
9
Framework Analysis Conclusions Recommendations
Network Information
Item Structure or Field Task Duration Predecessor
A Both Site Preparation & foundation 8 weeks -
B Field Subsurface drainage 4 weeks A
C Field Build field 4 weeks B
D Field Installation of artificial surface 7 weeks C
E Structure Footing & Curing 4 weeks & 3 weeks A
F Structure Concrete Pillars 4 weeks E
G Structure Steel structure 6 weeks E
H Structure Seat Galleries Concrete Pour 10 weeks F
I Structure Pre-cast Galleries 11 weeks H
J Structure Roof 8 weeks G
K Structure Seat Installations 4 weeks I
L Structure Office & Dressing rooms 4 weeks J
M Structure Seat Painting 3 weeks K
N Structure Painting Other & Interior & Lights 5 weeks L
O Structure Scoreboard and other elctronics 4 weeks L
10
Framework Analysis Conclusions Recommendations
Risk Assessment
Colder Temperatures:
• $1,640 per week to pour concrete
Strike:
• 50 percent likelihood
Penalty Clause
• Construction extends past August 26th deadline
• Cost: $18,000 per week
11
Framework Analysis Conclusions Recommendations
Given Alternatives
Do Nothing Expedite H**
Expedite H**
& Double
Shift C*
*Task C : Build Field
**Task H : Pouring of the seat gallery supports
12
Framework Analysis Conclusions Recommendations
PERT – Do Nothing
8 B 12 12 C 16 16 D 23
24 24 24
32 4 36 36 4 40 40 7 47
0 A 8
0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 47 - 47
0 8 8 0 0 0 0 0
15 4 19 19 10 29 29 11 40 40 4 44 44 3 47 47 0 47
8 E 15
0 33 N 38
8 7 15 15 G 21 21 J 29 29 L 33 9
9 9 9 42 5 47
24 6 30 30 8 38 38 4 42
ES ID EF 33 O 37
SL Descrip. 10
LS DUR LF 43 4 47
Site Prep
Electric
Office Dress
Paint
OccupancySeat PaintSeatsPre-Cast
Roof
Footings
Sub. Drain Surface
Seat Gallaries
Steel
Pillars
Build field
13
Framework Analysis Conclusions Recommendations
Gantt Chart – Do Nothing
Shaft
Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th
PLAN PLAN ACTUAL ACTUAL October 3rd
January 9th
March 13th
ACTIVITY
STAR
T
DURATIO
N START DURATIONWEEK
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage
Install 8 4 8 4
C: Field Build 12 4 12 4
D: Artificial Surface Install 16 7 16 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete
Pour 19 10 19 10
I: Galleries Install 29 11 29 11
J: Roof Build 21 8 21 8
K: Seat Install 40 4 40 4
L: Office/Dressing Room
Build 29 4 29 4
M: Seat Painting 44 3 44 3
N: Interior Paint/Electrical
Install 33 5 33 5
O: Concrete Pillar Pour 33 4 33 4
17
Framework Analysis Conclusions Recommendations
Resource PERT – Do Nothing
8 B 12 12 C 39 40 D 47
24 24 0
32 4 36 36 4 40 40 7 47
0 A 8
0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 53 - 53
0 8 8 6 6 6 6 6
21 4 25 25 10 35 35 11 46 46 4 50 50 3 53 53 0 53
8 E 15
0 48 N 53
8 7 15 15 G 21 21 J 44 44 L 48 0
0 0 0 48 5 53
15 6 21 21 8 44 44 4 48
ES ID EF 48 O 52
SL Descrip. 1
LS DUR LF 49 4 53
Steel Roof Office Dress
Electric
Pre-Cast Seats
Footings
Paint
Sub. Drain Build field Surface
Site Prep
Pillars Seat Gallaries Seat Paint Occupancy
18
Framework Analysis Conclusions Recommendations
Resource Gantt – Do Nothing
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PLAN PLAN ACTUAL ACTUAL
ACTIVITY START DURATION START DURATION
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial Surface Install 40 7 40 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete Pour 19 10 19 10
I: Galleries Install 29 11 29 11
J: Roof Build 21 22 21 22
K: Seat Install 40 4 40 4
L: Office/Dressing Room Build 44 4 44 4
M: Seat Painting 44 3 44 3
N: Interior Paint/Electrical Install 48 5 48 5
O: Concrete Pillar Pour 48 4 48 4
February 13th
March 13th
April 10th May 8th June 12thSeptember 5th
October 3rd
November 7st December 12th
January 9th
Shaft Construction
WEEK
Start June 6th July 4th August 1st
19
Framework Analysis Conclusions Recommendations
Gantt Chart – Expedite H
Shaft Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Sta
rtJune 6th July 4th August 1st September 5th
November 7st December 12th February 13th April 10th May 8th
PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th
ACTIVITY START DURATION START DURATION
WE
EK
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial Surface Install 40 7 40 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete Pour 19 6 19 6
I: Galleries Install 25 11 25 11
J: Roof Build 21 8 21 8
K: Seat Install 36 4 36 4
L: Office/Dressing Room Build 40 4 40 4
M: Seat Painting 40 3 40 3
N: Interior Paint/Electrical
Install 44 5 44 5
O: Concrete Pillar Pour 44 4 44 4
28
Framework Analysis Conclusions Recommendations
Strike Gantt Chart
Shaft Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Start June 6th .July 4th August 1st September 5th
November 7st December 12th
February
13th
April 10th May 8th June 12th July 3rd August 7th
PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th August 21st
ACTIVITY START DURATION START DURATION WEEK STRIKE
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial Surface Install 44 7 44 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete Pour 34 10 34 10
I: Galleries Install 39 11 39 11
J: Roof Build 21 22 21 22
K: Seat Install 50 4 50 4
L: Office/Dressing Room Build 44 4 44 4
M: Seat Painting 54 3 54 3
N: Interior Paint/Electrical Install 48 5 48 5
O: Concrete Pillar Pour 48 6 48 6
40
Framework Analysis Conclusions Recommendations
Statistical Analysis
Probability Warm
Temp (>33O)
Probability Cold Temp
(<33O) Cold AND Strike Cold OR Strike
December 48.4% 51.6% 25.8% 75.8%
January 46.8% 53.2% 26.6% 76.6%
February 56.4% 43.6% - 43.6%
41
Framework Analysis Conclusions Recommendations
Net Income & Project Duration
# Scenario
Projected Net
Income ($) Project Duration (weeks)
1Expedite H $474,360 49
2Expedite H & Cold $472,720 49
3Do Nothing $450,000 53
4Do Nothing & Cold $441,800 53
5Strike $403,640 57
6Strike & Cold $397,080 57
7Expedite H & Strike $381,640 57
8Close & Expedite H $381,640 57
9Expedite H & Strike & Cold $380,000 57
10Expedite H & Double Shift $360,050 58
11Expedite H & Double Shift & Cold $358,410 58
12Close $357,280 61
43
Framework Analysis Conclusions Recommendations
Conclusions
Conclusions
• 76% chance of a strike or a harsh
winter
• Expediting H decreases duration and
increases net income
• Incur the $22,000 charge
• Cut task duration from 10 to 6 weeks
• Best alternative:
• No obstacles
• Cold winter
44
Framework Analysis Conclusions Recommendations
Recommendations
Expedite H:
Pouring of the
Seat Gallery Supports
Highest Net Income
Shortest Duration
Accounts for the Most Risk
45
Framework Analysis Conclusions Recommendations
Implementation Roadmap
Meet with
leadership
Project
start
Follow-up
46
Framework Analysis Conclusions Recommendations
Ideas for Future Research
Next Steps
• Increase employees
• Different concrete mixtures
• Reassess winter forecast in
October
47
Framework Analysis Conclusions Recommendations
References
• (2013). Business Economics – A Library of Information. What is a Reasonable Profit in Construction?
Retrieved from http://businessecon.org/2013/01/what-is-a-reasonable-profit-in-construction/
• (2016). Placing Concrete in Hot or Cold Weather. Sakrete. Retrieved from http://www.sakrete.com/media-
center/blog-detail.cfm/bp_alias/Placing-Concrete-in-hot-or-cold-weather
• (2016). U.S. Climate Change. Temperature-Precipitation-Sunshine-Snowfall. Retrieved
from<http://www.usclimatedata.com/climate/jamestown/pennsylvania/united-states/uspa0781>
• Blank, L. & Tarquin, A. (2012). Engineering Economy. New York, NY: McGraw-Hill.
• Department of Commerce. (2016). National Centers for Environmental Information (NCEI). Retrieved from
<https://www.ncdc.noaa.gov/>
• Grabianowski, E. (2006, March). How Strikes Work. Retrieved from
<http://money.howstuffworks.com/strike.htm>
• Mishra, G. (2016). The Constructor – Civil Engineering Home. Construction Project Costs. Retrieved from
http://theconstructor.org/constrution/construction-project-costs/7677/
Questions
Appendix
50
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
10
7 7 7 7
8 8 8 8 8 8
10 10 10 10 10 10 10 10 10
10 X X X X 10 10 10 10 10
X X X X 8 8 8 8
X X X X
Strike Period X X X X
18 8 8 8 18 20 20 20 20 20 25 25 25 25
25 10 10 10 25 25 25 25 25 25 25 25 25 25
H
51
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 10/31 11/7 11/14
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X X X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10 10 10
H 8 10 19 29 0 8 8 8 8
I 10 11 29 40 0
J 10 8 21 38 9 10 10
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
52
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31
49 50 51 52 53 54 55 56 57 58 59 60
7 7 7
10 10
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6X X 6
22 22 20 21 21 21 6 6 6 0 25 22
25 25 25 25 25 25 25 25 25 25 25 25
H
53
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10 10
H 8 10 19 29 0 8
I 10 11 29 40 0
J 10 8 21 38 9
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
54
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X
10
8 8 8 8 8 8 8 8 8
10 10 10 10 10 10 10 10
18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 18 18 18 18
25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
55
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
10
7 7 7 7 7 7 7
10 10 10 10 10 10 10 10 10 10 10
8 8 8 8
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6 6
18 18 18 18 22 22 22 22 16 20 17 15 15 15 15 13 13 6
25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
56
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10
H 8 10 19 29 0
I 10 11 29 40 0
J 10 8 21 38 9
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
57
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X X
10 10
8 8 8 8 8 8
10 10 10 10
10 10 10 10 10 10 10 10
18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20
25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
58
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X X
10 10
8 8 8 8 8 8
10 10 10 10
10 10 10 10 10 10 10 10
18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20
25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
59
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10
44 45 46 47 48 49 50 51 52 53 54 55 56 57
10
7 7 7 7 7 7
10 10 10 10 10 10 10
8 8 8 8
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6 6
18 18 18 18 22 22 22 30 21 15 15 13 13 13
25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
60
Framework Analysis Conclusions Recommendations
Weather Data
December Mean = 32.56o F
January Mean = 32.61 o F
February Mean = 33.88 o F
December Standard Deviation = 10.136
January Standard Deviation = 5.076
February Standard Deviation = 5.374
December Z-value = 0.043778
January Z-value = 0.077565
February Z-value = -0.16281
H
61
Framework Analysis Conclusions Recommendations
Indirect Costs
(x)*(0.09) = $450,000
$5,000,000 = x
Costs = $5,000,000 - $450,000 = $4,550,000
Project overhead = (5% + 15%)/2 = 10%
General overhead = (2% + 5%)/2 = 3.5%
Indirect costs = (0.1)*($4,550,000) + (0.035)*($4,550,000)
Indirect costs = $614,250
Weekly indirect cost = $614,250/53 = $11,589.63
H

Shaft Construction

  • 1.
    1 Shaft Construction Dr. Greene BrianDoyle | Jacob Groezinger | Lillian Kravitz | John Rosser Team 5 ISE 311 A51 – Enterprise Systems Monday, April 11, 2016
  • 2.
  • 3.
    3 Framework Analysis ConclusionsRecommendations Introduction Shaft Construction Company (SCC) • Key Stakeholders: • John Shaft – President & CEO • Bumpy Jonas – Lead Designer • Ellie Moore – Director of Personnel • Objective: • 15,000 seat stadium on college campus • Net Income: $450,000 • Client Details: • Jamestown, PA • Jamestown Community College http://cdn0.wideopencountry.com/wp-content/uploads/2015/08/high-school-football-793x526.jpg
  • 4.
    4 Framework Analysis ConclusionsRecommendations Background Background • Constraints: • August 26th, 2017 deadline • Resource allocation • Penalties • Potential Risks: • Approximately 10-week strike • Harsh winter: • Charge for pouring concrete
  • 5.
    5 Framework Analysis ConclusionsRecommendations Assumptions Project: • Project start date: June 6th, 2016 • No work on weekends • No overtime • Equipment and materials are out of scope • Winter months: December, January & February
  • 6.
    6 Framework Analysis ConclusionsRecommendations Assumptions (con’t) Construction: • Footings require three weeks to cure • Work that follows footings cannot begin until curing is complete • Site preparation and foundation includes staging areas and traffic flow redirection • When forecasted temperatures are higher than 90 degrees, workers will utilize early mornings for heat sensitive activities • “Filling of the field” is assumed to be activity C, build field • Tasks can pause midway through duration and resume at a later time
  • 7.
    7 Framework Analysis ConclusionsRecommendations Assumptions (con’t) Employees: • 67% of employees laid off during winter • 15 employees during December, January and February, 30 for other months • 5 employees utilized for management • SCC hires unionized employees • Strike begins when contract expires Costs • Projected net income of project: $450,000 • Indirect cost applied to alternate scenarios based off of do nothing benchmark • Federal Holidays are insignificant
  • 8.
    8 Framework Analysis ConclusionsRecommendations Work Breakdown Structure
  • 9.
    9 Framework Analysis ConclusionsRecommendations Network Information Item Structure or Field Task Duration Predecessor A Both Site Preparation & foundation 8 weeks - B Field Subsurface drainage 4 weeks A C Field Build field 4 weeks B D Field Installation of artificial surface 7 weeks C E Structure Footing & Curing 4 weeks & 3 weeks A F Structure Concrete Pillars 4 weeks E G Structure Steel structure 6 weeks E H Structure Seat Galleries Concrete Pour 10 weeks F I Structure Pre-cast Galleries 11 weeks H J Structure Roof 8 weeks G K Structure Seat Installations 4 weeks I L Structure Office & Dressing rooms 4 weeks J M Structure Seat Painting 3 weeks K N Structure Painting Other & Interior & Lights 5 weeks L O Structure Scoreboard and other elctronics 4 weeks L
  • 10.
    10 Framework Analysis ConclusionsRecommendations Risk Assessment Colder Temperatures: • $1,640 per week to pour concrete Strike: • 50 percent likelihood Penalty Clause • Construction extends past August 26th deadline • Cost: $18,000 per week
  • 11.
    11 Framework Analysis ConclusionsRecommendations Given Alternatives Do Nothing Expedite H** Expedite H** & Double Shift C* *Task C : Build Field **Task H : Pouring of the seat gallery supports
  • 12.
    12 Framework Analysis ConclusionsRecommendations PERT – Do Nothing 8 B 12 12 C 16 16 D 23 24 24 24 32 4 36 36 4 40 40 7 47 0 A 8 0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 47 - 47 0 8 8 0 0 0 0 0 15 4 19 19 10 29 29 11 40 40 4 44 44 3 47 47 0 47 8 E 15 0 33 N 38 8 7 15 15 G 21 21 J 29 29 L 33 9 9 9 9 42 5 47 24 6 30 30 8 38 38 4 42 ES ID EF 33 O 37 SL Descrip. 10 LS DUR LF 43 4 47 Site Prep Electric Office Dress Paint OccupancySeat PaintSeatsPre-Cast Roof Footings Sub. Drain Surface Seat Gallaries Steel Pillars Build field
  • 13.
    13 Framework Analysis ConclusionsRecommendations Gantt Chart – Do Nothing Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th ACTIVITY STAR T DURATIO N START DURATIONWEEK 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 4 12 4 D: Artificial Surface Install 16 7 16 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 10 19 10 I: Galleries Install 29 11 29 11 J: Roof Build 21 8 21 8 K: Seat Install 40 4 40 4 L: Office/Dressing Room Build 29 4 29 4 M: Seat Painting 44 3 44 3 N: Interior Paint/Electrical Install 33 5 33 5 O: Concrete Pillar Pour 33 4 33 4
  • 14.
    17 Framework Analysis ConclusionsRecommendations Resource PERT – Do Nothing 8 B 12 12 C 39 40 D 47 24 24 0 32 4 36 36 4 40 40 7 47 0 A 8 0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 53 - 53 0 8 8 6 6 6 6 6 21 4 25 25 10 35 35 11 46 46 4 50 50 3 53 53 0 53 8 E 15 0 48 N 53 8 7 15 15 G 21 21 J 44 44 L 48 0 0 0 0 48 5 53 15 6 21 21 8 44 44 4 48 ES ID EF 48 O 52 SL Descrip. 1 LS DUR LF 49 4 53 Steel Roof Office Dress Electric Pre-Cast Seats Footings Paint Sub. Drain Build field Surface Site Prep Pillars Seat Gallaries Seat Paint Occupancy
  • 15.
    18 Framework Analysis ConclusionsRecommendations Resource Gantt – Do Nothing Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) PLAN PLAN ACTUAL ACTUAL ACTIVITY START DURATION START DURATION 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 40 7 40 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 10 19 10 I: Galleries Install 29 11 29 11 J: Roof Build 21 22 21 22 K: Seat Install 40 4 40 4 L: Office/Dressing Room Build 44 4 44 4 M: Seat Painting 44 3 44 3 N: Interior Paint/Electrical Install 48 5 48 5 O: Concrete Pillar Pour 48 4 48 4 February 13th March 13th April 10th May 8th June 12thSeptember 5th October 3rd November 7st December 12th January 9th Shaft Construction WEEK Start June 6th July 4th August 1st
  • 16.
    19 Framework Analysis ConclusionsRecommendations Gantt Chart – Expedite H Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Sta rtJune 6th July 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th ACTIVITY START DURATION START DURATION WE EK 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 40 7 40 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 6 19 6 I: Galleries Install 25 11 25 11 J: Roof Build 21 8 21 8 K: Seat Install 36 4 36 4 L: Office/Dressing Room Build 40 4 40 4 M: Seat Painting 40 3 40 3 N: Interior Paint/Electrical Install 44 5 44 5 O: Concrete Pillar Pour 44 4 44 4
  • 17.
    28 Framework Analysis ConclusionsRecommendations Strike Gantt Chart Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Start June 6th .July 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th June 12th July 3rd August 7th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th August 21st ACTIVITY START DURATION START DURATION WEEK STRIKE 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 44 7 44 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 34 10 34 10 I: Galleries Install 39 11 39 11 J: Roof Build 21 22 21 22 K: Seat Install 50 4 50 4 L: Office/Dressing Room Build 44 4 44 4 M: Seat Painting 54 3 54 3 N: Interior Paint/Electrical Install 48 5 48 5 O: Concrete Pillar Pour 48 6 48 6
  • 18.
    40 Framework Analysis ConclusionsRecommendations Statistical Analysis Probability Warm Temp (>33O) Probability Cold Temp (<33O) Cold AND Strike Cold OR Strike December 48.4% 51.6% 25.8% 75.8% January 46.8% 53.2% 26.6% 76.6% February 56.4% 43.6% - 43.6%
  • 19.
    41 Framework Analysis ConclusionsRecommendations Net Income & Project Duration # Scenario Projected Net Income ($) Project Duration (weeks) 1Expedite H $474,360 49 2Expedite H & Cold $472,720 49 3Do Nothing $450,000 53 4Do Nothing & Cold $441,800 53 5Strike $403,640 57 6Strike & Cold $397,080 57 7Expedite H & Strike $381,640 57 8Close & Expedite H $381,640 57 9Expedite H & Strike & Cold $380,000 57 10Expedite H & Double Shift $360,050 58 11Expedite H & Double Shift & Cold $358,410 58 12Close $357,280 61
  • 20.
    43 Framework Analysis ConclusionsRecommendations Conclusions Conclusions • 76% chance of a strike or a harsh winter • Expediting H decreases duration and increases net income • Incur the $22,000 charge • Cut task duration from 10 to 6 weeks • Best alternative: • No obstacles • Cold winter
  • 21.
    44 Framework Analysis ConclusionsRecommendations Recommendations Expedite H: Pouring of the Seat Gallery Supports Highest Net Income Shortest Duration Accounts for the Most Risk
  • 22.
    45 Framework Analysis ConclusionsRecommendations Implementation Roadmap Meet with leadership Project start Follow-up
  • 23.
    46 Framework Analysis ConclusionsRecommendations Ideas for Future Research Next Steps • Increase employees • Different concrete mixtures • Reassess winter forecast in October
  • 24.
    47 Framework Analysis ConclusionsRecommendations References • (2013). Business Economics – A Library of Information. What is a Reasonable Profit in Construction? Retrieved from http://businessecon.org/2013/01/what-is-a-reasonable-profit-in-construction/ • (2016). Placing Concrete in Hot or Cold Weather. Sakrete. Retrieved from http://www.sakrete.com/media- center/blog-detail.cfm/bp_alias/Placing-Concrete-in-hot-or-cold-weather • (2016). U.S. Climate Change. Temperature-Precipitation-Sunshine-Snowfall. Retrieved from<http://www.usclimatedata.com/climate/jamestown/pennsylvania/united-states/uspa0781> • Blank, L. & Tarquin, A. (2012). Engineering Economy. New York, NY: McGraw-Hill. • Department of Commerce. (2016). National Centers for Environmental Information (NCEI). Retrieved from <https://www.ncdc.noaa.gov/> • Grabianowski, E. (2006, March). How Strikes Work. Retrieved from <http://money.howstuffworks.com/strike.htm> • Mishra, G. (2016). The Constructor – Civil Engineering Home. Construction Project Costs. Retrieved from http://theconstructor.org/constrution/construction-project-costs/7677/
  • 25.
  • 26.
  • 27.
    50 Framework Analysis ConclusionsRecommendations Strike Resource Schedule 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 10 7 7 7 7 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 X X X X 10 10 10 10 10 X X X X 8 8 8 8 X X X X Strike Period X X X X 18 8 8 8 18 20 20 20 20 20 25 25 25 25 25 10 10 10 25 25 25 25 25 25 25 25 25 25 H
  • 28.
    51 Framework Analysis ConclusionsRecommendations Strike Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 10/31 11/7 11/14 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X X X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 10 10 H 8 10 19 29 0 8 8 8 8 I 10 11 29 40 0 J 10 8 21 38 9 10 10 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 29.
    52 Framework Analysis ConclusionsRecommendations Strike Resource Schedule 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 49 50 51 52 53 54 55 56 57 58 59 60 7 7 7 10 10 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6X X 6 22 22 20 21 21 21 6 6 6 0 25 22 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 30.
    53 Framework Analysis ConclusionsRecommendations Close Winter Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 10 H 8 10 19 29 0 8 I 10 11 29 40 0 J 10 8 21 38 9 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 31.
    54 Framework Analysis ConclusionsRecommendations Close Winter Resource Schedule 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X 10 8 8 8 8 8 8 8 8 8 10 10 10 10 10 10 10 10 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 18 18 18 18 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 32.
    55 Framework Analysis ConclusionsRecommendations Close Winter Resource Schedule 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 10 7 7 7 7 7 7 7 10 10 10 10 10 10 10 10 10 10 10 8 8 8 8 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 18 18 18 18 22 22 22 22 16 20 17 15 15 15 15 13 13 6 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 33.
    56 Framework Analysis ConclusionsRecommendations Close Winter Expedite H: Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 H 8 10 19 29 0 I 10 11 29 40 0 J 10 8 21 38 9 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 34.
    57 Framework Analysis ConclusionsRecommendations Close Winter Expedite H: Resource Schedule 10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X X 10 10 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20 25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 35.
    58 Framework Analysis ConclusionsRecommendations Close Winter Expedite H: Resource Schedule 10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X X 10 10 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20 25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 36.
    59 Framework Analysis ConclusionsRecommendations Close Winter Expedite H: Resource Schedule 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 44 45 46 47 48 49 50 51 52 53 54 55 56 57 10 7 7 7 7 7 7 10 10 10 10 10 10 10 8 8 8 8 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 18 18 18 18 22 22 22 30 21 15 15 13 13 13 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 37.
    60 Framework Analysis ConclusionsRecommendations Weather Data December Mean = 32.56o F January Mean = 32.61 o F February Mean = 33.88 o F December Standard Deviation = 10.136 January Standard Deviation = 5.076 February Standard Deviation = 5.374 December Z-value = 0.043778 January Z-value = 0.077565 February Z-value = -0.16281 H
  • 38.
    61 Framework Analysis ConclusionsRecommendations Indirect Costs (x)*(0.09) = $450,000 $5,000,000 = x Costs = $5,000,000 - $450,000 = $4,550,000 Project overhead = (5% + 15%)/2 = 10% General overhead = (2% + 5%)/2 = 3.5% Indirect costs = (0.1)*($4,550,000) + (0.035)*($4,550,000) Indirect costs = $614,250 Weekly indirect cost = $614,250/53 = $11,589.63 H

Editor's Notes