SlideShare a Scribd company logo
1 of 27
Vico Office Demo Videos




Watch 5D BIM for Dummies or download




                                 Watch BIM-based Estimating or download
Clash,
                      Quantity               Cost
Constructability
                      Takeoff              Planning
     RFI




                                   DEMO
                     Location              Flowline
     Cost
                    Breakdown             Planning &
   Exploring
                     Structure              Control



                      2D Docs              2D Takeoff
  Integrated
                     Site Layout          Cost Control
  Reporting
                   3D Model Comp           Enterprise
Integrated Process Overview

                                                              LBS
                         Rebar
                                                  Equipment



                         Formwork

                                                  Labor


                         Concrete



   Column
    ‘Type 1’             Cladding;
                         Surface                  Materials
                         Finish


     TOIs              TOQs                   Resources
  Takeoff Items   Takeoff Quantities
                                                $/Qty
     $/Qty             $/Qty


    Design                             Cost                   Time
Vico Office - Workflow
My Projects Dashboard
Combine 3D Models
Activate and Manage Model Versions
Clash Detection
Constructability Analysis + Tracking
Take Off Quantities
'Construction Caliber'
Take Off Quantities (TOQs)
Visual Cost Planning
Cost Planner – Spreadsheet + Formula Editor
Cost Planning (n-tiered 'Evolutionary')
          Database power   Spreadsheet flexibility
Evolutionary Estimating




                                 $/       $/
Target $   $ / SF   $ / SYS                        $ / Unit
                              Element   Activity
Explore and Compare Versions
Define Locations to virtually split elements
Flowline Intro

                             Calendar


Locations


                  Tasks
Flowline Optimization

                      Take these three tasks…
                      1. Show in Flowline
                      2. Optimize production rates
                      3. Compress project duration


                      -10 to 20% without increasing risk




      Duration B


         Duration A
Location Based Management System
  Task durations calculated with explicit assumptions recorded
  Highlight planned work locations and wasted opportunities
  Identify bottle necks, inefficiencies, stops and starts
                                                           2010
    Building   Floor       January             February    Calendar
                                                                 March                           April
                       4   11   18   25   1     8     15   22   1      8   15       22    29     5   12   19

                3rd


       B        2nd
                                                                                         Waste
       Locationsst
                1


                3rd                                                 Start & Stops


       A        2nd
                                              Waste

                1st
Flowline Schedule Planning
  Optimized for continuous labor flow
  Optimal resources + starts ensure continuous workflow
  Buffers protect against uncertainty in the field
                                                         2010
    Building   Floor       January            February            March                  April
                       4   11   18   25   1    8   15    22   1   8   15   22   29   5     12    19

                3rd


       B        2nd


                1st


                3rd


       A        2nd


                1st
Flowline Schedule Planning
  Optimized for continuous labor flow
  Optimal resources + starts ensure continuous workflow
  Buffers protect against uncertainty in the field
                                                         2010
    Building   Floor       January            February            March                  April
                       4   11   18   25   1    8   15    22   1   8   15   22   29   5     12    19

                3rd


       B        2nd


                1st


                3rd


       A        2nd


                1st
Production Control

         3rd


   B     2nd                                                   Late start

                45%
         1st     or
                                                                Behind
               323m2

         3rd
                                                              On-time


               
                         23%
   A     2nd              or
                        Behind
                        53No.                                  Complete

         1st
                                     Late




                                                Prime & Seal
                         Dry Walling
                Frame




                                       Tiling
Forecasting
 Weekly Subcontractor Meetings
 Review Forecasts
 Adjust to Maintain Planned Schedule
                                          Report Date
                                                           2010
    Building   Floor       January              February            March                     April
                       4   11   18   25   1      8   15    22   1   8   15   22    29     5      12   19

                3rd                                                                           Delay

       B        2nd


                1st

                                                                             Task: Dry Walling
                3rd
                                                                             Location      Resource        Number
                                                                                    3rd    Crew 1             1
       A        2nd                                                           B     2nd    Crew 1             1
                                      Behind                                        1st    Crew 1             1
                                                                                    3rd    Crew 1             1
                1st                                                           A     2nd    Crew 1             1
                                              Late                                  1st    Crew 1             1
Forecasting
 Weekly Subcontractor Meetings
 Review Forecasts
 Adjust to Maintain Planned Schedule
                                          Report Date
                                                         2010
    Building   Floor       January            February            March                     April
                       4   11   18   25   1    8   15    22   1   8   15   22    29     5      12   19

                3rd


       B        2nd


                1st

                                                                           Task: Dry Walling
                3rd
                                                                           Location      Resource        Number
                                                                                  3rd    Crew 1            1 2
       A        2nd                                                         B     2nd    Crew 1            1 2
                                                                                  1st    Crew 1            1 2
                                                                                  3rd    Crew 1            1 2
                1st                                                         A     2nd    Crew 1            1 2
                                                                                  1st    Crew 1             1
Custom Reports
Create + distribute reports for submission

More Related Content

What's hot

BIM for Construction
BIM for Construction BIM for Construction
BIM for Construction Marc Goldman
 
Design and Development of BIM on GIS Interoperability Open Platform
Design and Development of BIM on GIS Interoperability Open PlatformDesign and Development of BIM on GIS Interoperability Open Platform
Design and Development of BIM on GIS Interoperability Open Platformslhead1
 
Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectMANNU KUMAR
 
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...Dalbir Dugal
 
BIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and ProcedureBIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and Procedureanhc5l77 actp84nya
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation Omar Selim
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
BIM project execution
BIM project executionBIM project execution
BIM project executionStephen Au
 
02- Coordination (Clash Detection).pptx
02- Coordination (Clash Detection).pptx02- Coordination (Clash Detection).pptx
02- Coordination (Clash Detection).pptxMustafa Ahmed
 
Difference between cad and bim
Difference between cad and bimDifference between cad and bim
Difference between cad and bimmariem badr
 
3D Models for Construction Estimating
3D Models for Construction Estimating3D Models for Construction Estimating
3D Models for Construction EstimatingIan McGaw
 
Intro to BIM and Revit Structure
Intro to BIM and Revit StructureIntro to BIM and Revit Structure
Intro to BIM and Revit StructureMostafa El-Ashmawy
 
How BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectHow BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectJacob Ostwald
 

What's hot (20)

BIM for Construction
BIM for Construction BIM for Construction
BIM for Construction
 
Design and Development of BIM on GIS Interoperability Open Platform
Design and Development of BIM on GIS Interoperability Open PlatformDesign and Development of BIM on GIS Interoperability Open Platform
Design and Development of BIM on GIS Interoperability Open Platform
 
Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real project
 
BIM Execution plan
BIM  Execution  planBIM  Execution  plan
BIM Execution plan
 
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
 
Virtual Design and Construction
Virtual Design and ConstructionVirtual Design and Construction
Virtual Design and Construction
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
BIM
BIMBIM
BIM
 
what is BIM
what is BIMwhat is BIM
what is BIM
 
BIM: an overview
BIM: an overviewBIM: an overview
BIM: an overview
 
BIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and ProcedureBIM Execution Plan - Bim Process Model Rview and Procedure
BIM Execution Plan - Bim Process Model Rview and Procedure
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
BIM project execution
BIM project executionBIM project execution
BIM project execution
 
02- Coordination (Clash Detection).pptx
02- Coordination (Clash Detection).pptx02- Coordination (Clash Detection).pptx
02- Coordination (Clash Detection).pptx
 
Difference between cad and bim
Difference between cad and bimDifference between cad and bim
Difference between cad and bim
 
3D Models for Construction Estimating
3D Models for Construction Estimating3D Models for Construction Estimating
3D Models for Construction Estimating
 
Bim overview
Bim overviewBim overview
Bim overview
 
Intro to BIM and Revit Structure
Intro to BIM and Revit StructureIntro to BIM and Revit Structure
Intro to BIM and Revit Structure
 
How BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectHow BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction project
 

Vico Office - 5D BIM

  • 1. Vico Office Demo Videos Watch 5D BIM for Dummies or download Watch BIM-based Estimating or download
  • 2. Clash, Quantity Cost Constructability Takeoff Planning RFI DEMO Location Flowline Cost Breakdown Planning & Exploring Structure Control 2D Docs 2D Takeoff Integrated Site Layout Cost Control Reporting 3D Model Comp Enterprise
  • 3. Integrated Process Overview LBS Rebar Equipment Formwork Labor Concrete Column ‘Type 1’ Cladding; Surface Materials Finish TOIs TOQs Resources Takeoff Items Takeoff Quantities $/Qty $/Qty $/Qty Design Cost Time
  • 4. Vico Office - Workflow
  • 7. Activate and Manage Model Versions
  • 11. 'Construction Caliber' Take Off Quantities (TOQs)
  • 13. Cost Planner – Spreadsheet + Formula Editor
  • 14. Cost Planning (n-tiered 'Evolutionary') Database power Spreadsheet flexibility
  • 15. Evolutionary Estimating $/ $/ Target $ $ / SF $ / SYS $ / Unit Element Activity
  • 17. Define Locations to virtually split elements
  • 18. Flowline Intro Calendar Locations Tasks
  • 19. Flowline Optimization Take these three tasks… 1. Show in Flowline 2. Optimize production rates 3. Compress project duration -10 to 20% without increasing risk Duration B Duration A
  • 20. Location Based Management System  Task durations calculated with explicit assumptions recorded  Highlight planned work locations and wasted opportunities  Identify bottle necks, inefficiencies, stops and starts 2010 Building Floor January February Calendar March April 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 3rd B 2nd Waste Locationsst 1 3rd Start & Stops A 2nd Waste 1st
  • 21. Flowline Schedule Planning  Optimized for continuous labor flow  Optimal resources + starts ensure continuous workflow  Buffers protect against uncertainty in the field 2010 Building Floor January February March April 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 3rd B 2nd 1st 3rd A 2nd 1st
  • 22. Flowline Schedule Planning  Optimized for continuous labor flow  Optimal resources + starts ensure continuous workflow  Buffers protect against uncertainty in the field 2010 Building Floor January February March April 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 3rd B 2nd 1st 3rd A 2nd 1st
  • 23. Production Control 3rd B 2nd Late start 45% 1st or Behind 323m2 3rd  On-time  23% A 2nd or Behind 53No. Complete 1st   Late Prime & Seal Dry Walling Frame Tiling
  • 24. Forecasting  Weekly Subcontractor Meetings  Review Forecasts  Adjust to Maintain Planned Schedule Report Date 2010 Building Floor January February March April 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 3rd Delay B 2nd 1st Task: Dry Walling 3rd Location Resource Number 3rd Crew 1 1 A 2nd B 2nd Crew 1 1 Behind 1st Crew 1 1 3rd Crew 1 1 1st A 2nd Crew 1 1 Late 1st Crew 1 1
  • 25. Forecasting  Weekly Subcontractor Meetings  Review Forecasts  Adjust to Maintain Planned Schedule Report Date 2010 Building Floor January February March April 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 3rd B 2nd 1st Task: Dry Walling 3rd Location Resource Number 3rd Crew 1 1 2 A 2nd B 2nd Crew 1 1 2 1st Crew 1 1 2 3rd Crew 1 1 2 1st A 2nd Crew 1 1 2 1st Crew 1 1
  • 27. Create + distribute reports for submission

Editor's Notes

  1. After the bid is wonComplete the model for use in project control and managementUpdate the estimate with more accurate subs pricesCompare against your bid ‘budget’
  2. SLIDE: 13   5D: Schedule (CONCEPT SLIDE):  (Tim)
  3. SLIDE: 13   5D: Schedule (CONCEPT SLIDE):  (Tim)
  4. SLIDE: 13   5D: Schedule (CONCEPT SLIDE):  (Tim)
  5. SLIDE: 15   5D: Schedule (DETAIL SLIDE  MSM MODEL):  (Clay)MSM Model Example (Toggle Over) The result is that on the fly we are able to provide the team with specific SCHEDULE data that can be manipulated at a working team meeting to help inform critical project decisions. No need to wait for a monthly or weekly reportNo live document – a truly live 5 dimensional model that allows all parties the ability to:
  6. SLIDE: 15   5D: Schedule (DETAIL SLIDE  MSM MODEL):  (Clay)MSM Model Example (Toggle Over) The result is that on the fly we are able to provide the team with specific SCHEDULE data that can be manipulated at a working team meeting to help inform critical project decisions. No need to wait for a monthly or weekly reportNo live document – a truly live 5 dimensional model that allows all parties the ability to: