Shaft Construction
Brian Doyle | Jacob Groezinger | Lillian Kravitz | John Rosser
Team 5
ISE 311 A51 – Enterprise Systems
Monday, April 11, 2016
2
Agenda
Introduction
Background
Assumptions
Analysis
Conclusions
Recommendations
Ideas for Future Research
3
Framework Analysis Conclusions Recommendations
Introduction
Shaft Construction Company
(SCC)
• Key Stakeholders:
• John Shaft – President & CEO
• Bumpy Jonas – Lead Designer
• Ellie Moore – Director of Personnel
• Objective:
• 15,000 seat stadium on college
campus
• Net Income: $450,000
• Client Details:
• Jamestown, PA
• Jamestown Community College
http://cdn0.wideopencountry.com/wp-content/uploads/2015/08/high-school-football-793x526.jpg
4
Framework Analysis Conclusions Recommendations
Background
Background
• Constraints:
• August 26th, 2017 deadline
• Resource allocation
• Penalties
• Potential Risks:
• Approximately 10-week strike
• Harsh winter:
• Charge for pouring concrete
5
Framework Analysis Conclusions Recommendations
Assumptions
Project:
• Project start date: June 6th, 2016
• No work on weekends
• No overtime
• Equipment and materials are out of scope
• Winter months: December, January & February
6
Framework Analysis Conclusions Recommendations
Assumptions (con’t)
Construction:
• Footings require three weeks to cure
• Work that follows footings cannot begin until curing is complete
• Site preparation and foundation includes staging areas and traffic flow
redirection
• “Filling of the field” is assumed to be activity C, build field
• Tasks can pause midway through duration and resume at a later time
7
Framework Analysis Conclusions Recommendations
Assumptions (con’t)
Employees:
• 67% of employees laid off during winter
• 15 employees during December, January and February, 30 for other months
• 5 employees utilized for management
• SCC hires unionized employees
• Strike begins when contract expires
Costs
• Projected net income of project: $450,000
• Indirect cost applied to alternate scenarios based off of do nothing benchmark
• Federal Holidays are insignificant
8
Framework Analysis Conclusions Recommendations
Work Breakdown Structure
9
Framework Analysis Conclusions Recommendations
Network Information
Item Structure or Field Task Duration Predecessor
A Both Site Preparation & foundation 8 weeks -
B Field Subsurface drainage 4 weeks A
C Field Build field 4 weeks B
D Field Installation of artificial surface 7 weeks C
E Structure Footing & Curing 4 weeks & 3 weeks A
F Structure Concrete Pillars 4 weeks E
G Structure Steel structure 6 weeks E
H Structure Seat Galleries Concrete Pour 10 weeks F
I Structure Pre-cast Galleries 11 weeks H
J Structure Roof 8 weeks G
K Structure Seat Installations 4 weeks I
L Structure Office & Dressing rooms 4 weeks J
M Structure Seat Painting 3 weeks K
N Structure Painting Other & Interior & Lights 5 weeks L
O Structure Scoreboard and other elctronics 4 weeks L
10
Framework Analysis Conclusions Recommendations
Risk Assessment
Colder Temperatures:
• $1,640 per week to pour concrete
Strike:
• 50 percent likelihood
Penalty Clause
• Construction extends past August 26th deadline
• Cost: $18,000 per week
11
Framework Analysis Conclusions Recommendations
Given Alternatives
Do Nothing Expedite H**
Expedite H**
& Double
Shift C*
*Task C : Build Field
**Task H : Pouring of the seat gallery supports
12
Framework Analysis Conclusions Recommendations
PERT – Do Nothing
8 B 12 12 C 16 16 D 23
24 24 24
32 4 36 36 4 40 40 7 47
0 A 8
0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 47 - 47
0 8 8 0 0 0 0 0
15 4 19 19 10 29 29 11 40 40 4 44 44 3 47 47 0 47
8 E 15
0 33 N 38
8 7 15 15 G 21 21 J 29 29 L 33 9
9 9 9 42 5 47
24 6 30 30 8 38 38 4 42
ES ID EF 33 O 37
SL Descrip. 10
LS DUR LF 43 4 47
Sub. Drain Surface
Seat Galleries
Steel
Pillars
Build field
Site Prep
Electric
Office Dress
Paint
OccupancySeat PaintSeatsPre-Cast
Roof
Footings
13
Framework Analysis Conclusions Recommendations
Gantt Chart – Do Nothing
Shaft
Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th
PLAN PLAN ACTUAL ACTUAL
October 3rd January 9th March 13th
ACTIVITY START DURATION START DURATIONWEEK
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
A: Site/Foundation
Prep 1 7 1 7
B: Subsurface
Drainage Install 8 4 8 4
C: Field Build 12 4 12 4
D: Artificial Surface
Install 16 7 16 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure
Build 15 6 15 6
H: Seat Galleries
Concrete Pour 19 10 19 10
I: Galleries Install 29 11 29 11
J: Roof Build 21 8 21 8
K: Seat Install 40 4 40 4
L: Office/Dressing
Room Build 29 4 29 4
M: Seat Painting 44 3 44 3
N: Interior
Paint/Electrical Install 33 5 33 5
O: Concrete Pillar
Pour 33 4 33 4
17
Framework Analysis Conclusions Recommendations
Resource PERT – Do Nothing
8 B 12 12 C 39 40 D 47
24 24 0
32 4 36 36 4 40 40 7 47
0 A 8
0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 53 - 53
0 8 8 6 6 6 6 6
21 4 25 25 10 35 35 11 46 46 4 50 50 3 53 53 0 53
8 E 15
0 48 N 53
8 7 15 15 G 21 21 J 44 44 L 48 0
0 0 0 48 5 53
15 6 21 21 8 44 44 4 48
ES ID EF 48 O 52
SL Descrip. 1
LS DUR LF 49 4 53
Site Prep
Pillars Seat Galleries Seat Paint Occupancy
Footings
Paint
Sub. Drain Build field Surface
Steel Roof Office Dress
Electric
Pre-Cast Seats
18
Framework Analysis Conclusions Recommendations
Resource Gantt – Do Nothing
Week duration: 53 weeks
Shaft
Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th June 12th
PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th
ACTIVITY START DURATION START DURATION WEEK
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 535455
A: Site/Foundation
Prep 1 7 1 7
B: Subsurface
Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial
Surface Install 40 7 40 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar
Pour 15 4 15 4
G: Steel Structure
Build 15 6 15 6
H: Seat Galleries
Concrete Pour 19 10 19 10
I: Galleries Install 29 11 29 11
J: Roof Build 21 22 21 22
K: Seat Install 40 4 40 4
L: Office/Dressing
Room Build 44 4 44 4
M: Seat Painting 44 3 44 3
N: Interior
Paint/Electrical
Install 48 5 48 5
O: Concrete Pillar
Pour 48 4 48 4
19
Framework Analysis Conclusions Recommendations
Gantt Chart – Expedite H
Shaft Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
StartJune 6th July 4th August 1st September 5th
November 7st December 12th February 13th April 10th May 8th
PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th
ACTIVITY START DURATION START DURATION WEEK
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial Surface Install 40 7 40 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete Pour 19 6 19 6
I: Galleries Install 25 11 25 11
J: Roof Build 21 8 21 8
K: Seat Install 36 4 36 4
L: Office/Dressing Room Build 40 4 40 4
M: Seat Painting 40 3 40 3
N: Interior Paint/Electrical
Install 44 5 44 5
O: Concrete Pillar Pour 44 4 44 4
Week duration: 49 weeks
28
Framework Analysis Conclusions Recommendations
Strike Gantt Chart
Shaft Construction
Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
Start June 6th .July 4th August 1st September 5th
November 7st December 12th
February
13th
April 10th May 8th June 12th July 3rd August 7th
PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th August 21st
ACTIVITY START DURATION START DURATION WEEK STRIKE
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
A: Site/Foundation Prep 1 7 1 7
B: Subsurface Drainage Install 8 4 8 4
C: Field Build 12 26 12 26
D: Artificial Surface Install 44 7 44 7
E: Footing Pour 8 7 8 7
F: Concrete Pillar Pour 15 4 15 4
G: Steel Structure Build 15 6 15 6
H: Seat Galleries Concrete Pour 34 10 34 10
I: Galleries Install 39 11 39 11
J: Roof Build 21 22 21 22
K: Seat Install 50 4 50 4
L: Office/Dressing Room Build 44 4 44 4
M: Seat Painting 54 3 54 3
N: Interior Paint/Electrical Install 48 5 48 5
O: Concrete Pillar Pour 48 6 48 6
Week duration: 57 weeks
41
Framework Analysis Conclusions Recommendations
Statistical Analysis
Probability Warm
Temp (>33O)
Probability Cold Temp
(<33O) Cold AND Strike Cold OR Strike
December 48.4% 51.6% 25.8% 75.8%
January 46.8% 53.2% 26.6% 76.6%
February 56.4% 43.6% - 43.6%
42
Framework Analysis Conclusions Recommendations
Net Income & Project Duration
# Scenario
Projected Net
Income ($) Project Duration (weeks)
1Expedite H $474,360 49
2Expedite H & Cold $472,720 49
3Do Nothing $450,000 53
4Do Nothing & Cold $441,800 53
5Strike $403,640 57
6Strike & Cold $397,080 57
7Expedite H & Strike $381,640 57
8Close & Expedite H $381,640 57
9Expedite H & Strike & Cold $380,000 57
10Expedite H & Double Shift $360,050 58
11Expedite H & Double Shift & Cold $358,410 58
12Close $357,280 61
44
Framework Analysis Conclusions Recommendations
Conclusions
Conclusions
• 76% chance of a strike or a harsh
winter
• Expediting H decreases duration and
increases net income
• Incur the $22,000 charge
• Cut task duration from 10 to 6 weeks
• Best alternative:
• No obstacles
• Cold winter
45
Framework Analysis Conclusions Recommendations
Recommendations
Expedite H:
Pouring of the
Seat Gallery Supports
Highest Net Income
Shortest Duration
Accounts for the Most Risk
46
Framework Analysis Conclusions Recommendations
Implementation Roadmap
Meet with
leadership
Project
start
Follow-up
47
Framework Analysis Conclusions Recommendations
Ideas for Future Research
Next Steps
• Increase employees
• Different concrete mixtures
• Reassess winter forecast in
October
48
Framework Analysis Conclusions Recommendations
References
• (2013). Business Economics – A Library of Information. What is a Reasonable Profit in Construction?
Retrieved from http://businessecon.org/2013/01/what-is-a-reasonable-profit-in-construction/
• (2016). Placing Concrete in Hot or Cold Weather. Sakrete. Retrieved from http://www.sakrete.com/media-
center/blog-detail.cfm/bp_alias/Placing-Concrete-in-hot-or-cold-weather
• (2016). U.S. Climate Change. Temperature-Precipitation-Sunshine-Snowfall. Retrieved
from<http://www.usclimatedata.com/climate/jamestown/pennsylvania/united-states/uspa0781>
• Blank, L. & Tarquin, A. (2012). Engineering Economy. New York, NY: McGraw-Hill.
• Department of Commerce. (2016). National Centers for Environmental Information (NCEI). Retrieved from
<https://www.ncdc.noaa.gov/>
• Grabianowski, E. (2006, March). How Strikes Work. Retrieved from
<http://money.howstuffworks.com/strike.htm>
• Mishra, G. (2016). The Constructor – Civil Engineering Home. Construction Project Costs. Retrieved from
http://theconstructor.org/constrution/construction-project-costs/7677/
Questions
Appendix
51
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
10
7 7 7 7
8 8 8 8 8 8
10 10 10 10 10 10 10 10 10
10 X X X X 10 10 10 10 10
X X X X 8 8 8 8
X X X X
Strike Period X X X X
18 8 8 8 18 20 20 20 20 20 25 25 25 25
25 10 10 10 25 25 25 25 25 25 25 25 25 25
H
52
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 10/31 11/7 11/14
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X X X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10 10 10
H 8 10 19 29 0 8 8 8 8
I 10 11 29 40 0
J 10 8 21 38 9 10 10
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
53
Framework Analysis Conclusions Recommendations
Strike Resource Schedule
5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31
49 50 51 52 53 54 55 56 57 58 59 60
7 7 7
10 10
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6X X 6
22 22 20 21 21 21 6 6 6 0 25 22
25 25 25 25 25 25 25 25 25 25 25 25
H
54
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10 10
H 8 10 19 29 0 8
I 10 11 29 40 0
J 10 8 21 38 9
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
55
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X
10
8 8 8 8 8 8 8 8 8
10 10 10 10 10 10 10 10
18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 18 18 18 18
25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
56
Framework Analysis Conclusions Recommendations
Close Winter Resource Schedule
4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
10
7 7 7 7 7 7 7
10 10 10 10 10 10 10 10 10 10 10
8 8 8 8
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6 6
18 18 18 18 22 22 22 22 16 20 17 15 15 15 15 13 13 6
25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
57
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17
ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
A 25 8 0 8 0 25 25 25 25 25 25 25 25 25
B 10 4 8 36 24 10 10 10 10
C 10 4 12 40 24 10 10 10X
D 7 7 16 47 24 X X X
E 12 7 8 15 0 12 12 12 12 12 12 12
F 8 4 15 19 0 8 8 8 8
G 10 6 15 30 9 10 10 10 10
H 8 10 19 29 0
I 10 11 29 40 0
J 10 8 21 38 9
K 8 4 40 44 0
L 8 4 29 42 9
M 6 3 44 47 0
N 6 5 33 47 9
O 6 4 33 47 10
Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18
Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
58
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X X
10 10
8 8 8 8 8 8
10 10 10 10
10 10 10 10 10 10 10 10
18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20
25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
59
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
X X X X
10 10
8 8 8 8 8 8
10 10 10 10
10 10 10 10 10 10 10 10
18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20
25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25
H
60
Framework Analysis Conclusions Recommendations
Close Winter Expedite H: Resource
Schedule
4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10
44 45 46 47 48 49 50 51 52 53 54 55 56 57
10
7 7 7 7 7 7
10 10 10 10 10 10 10
8 8 8 8
8 8 8 8
6 6 6
6 6 6 6 6
6 6 6 6
18 18 18 18 22 22 22 30 21 15 15 13 13 13
25 25 25 25 25 25 25 25 25 25 25 25 25 25
H
62
Framework Analysis Conclusions Recommendations
Weather Data
December Mean = 32.56o F
January Mean = 32.61 o F
February Mean = 33.88 o F
December Standard Deviation = 10.136
January Standard Deviation = 5.076
February Standard Deviation = 5.374
December Z-value = 0.043778
January Z-value = 0.077565
February Z-value = -0.16281
H
63
Framework Analysis Conclusions Recommendations
Indirect Costs
(x)*(0.09) = $450,000
$5,000,000 = x
Costs = $5,000,000 - $450,000 = $4,550,000
Project overhead = (5% + 15%)/2 = 10%
General overhead = (2% + 5%)/2 = 3.5%
Indirect costs = (0.1)*($4,550,000) + (0.035)*($4,550,000)
Indirect costs = $614,250
Weekly indirect cost = $614,250/53 = $11,589.63
H

More Related Content

Viewers also liked

Challenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of TunnellingChallenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of TunnellingIEI GSC
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Hamed Zarei
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Aerodynamic Performance Improvement of Renault Duster
Aerodynamic Performance Improvement of Renault DusterAerodynamic Performance Improvement of Renault Duster
Aerodynamic Performance Improvement of Renault DusterSelf-employed
 
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...500 Startups
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experiencegifanta
 

Viewers also liked (7)

Challenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of TunnellingChallenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Aerodynamic Performance Improvement of Renault Duster
Aerodynamic Performance Improvement of Renault DusterAerodynamic Performance Improvement of Renault Duster
Aerodynamic Performance Improvement of Renault Duster
 
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...
[500DISTRO] The Scientific Method: How to Design & Track Viral Growth Experim...
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experience
 

Similar to Shaft Construction

Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement SchedulingRonald Rhodes
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3Ahmad Basim Hamza
 
John Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry
 
Bim final documentation
Bim final documentation Bim final documentation
Bim final documentation Sheau Hui Tan
 
Nicholas Socrates' Architecture and Urban Design Portfolio 2013
Nicholas Socrates' Architecture and Urban Design Portfolio 2013Nicholas Socrates' Architecture and Urban Design Portfolio 2013
Nicholas Socrates' Architecture and Urban Design Portfolio 2013Nicholas Socrates
 
Sharon Construction Case Study
Sharon Construction Case StudySharon Construction Case Study
Sharon Construction Case Studyst0000000000
 
Final Portfolio Layout
Final Portfolio LayoutFinal Portfolio Layout
Final Portfolio LayoutMichael Mulvey
 
D Trolley 273.4.PDF
D Trolley 273.4.PDFD Trolley 273.4.PDF
D Trolley 273.4.PDFDavid Bales
 
Exercise 1 networking
Exercise 1 networkingExercise 1 networking
Exercise 1 networkingMendana Pweka
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)Nikka Lopez
 
UI Solidworks Presentation.pptx
UI Solidworks Presentation.pptxUI Solidworks Presentation.pptx
UI Solidworks Presentation.pptxSHILPIYADAV37
 
Civil course
Civil courseCivil course
Civil courseOlik3
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT Saurav Shrestha
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABsToe Myint Naing
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxHumnaTolina
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03jncgw5t6xq
 

Similar to Shaft Construction (20)

Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement Scheduling
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
 
John Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfs
 
Bim final documentation
Bim final documentation Bim final documentation
Bim final documentation
 
Nicholas Socrates' Architecture and Urban Design Portfolio 2013
Nicholas Socrates' Architecture and Urban Design Portfolio 2013Nicholas Socrates' Architecture and Urban Design Portfolio 2013
Nicholas Socrates' Architecture and Urban Design Portfolio 2013
 
Sharon Construction Case Study
Sharon Construction Case StudySharon Construction Case Study
Sharon Construction Case Study
 
Final Portfolio Layout
Final Portfolio LayoutFinal Portfolio Layout
Final Portfolio Layout
 
D Trolley 273.4.PDF
D Trolley 273.4.PDFD Trolley 273.4.PDF
D Trolley 273.4.PDF
 
Presentation-MCFA
Presentation-MCFAPresentation-MCFA
Presentation-MCFA
 
CE236_Final_2007
CE236_Final_2007CE236_Final_2007
CE236_Final_2007
 
Exercise 1 networking
Exercise 1 networkingExercise 1 networking
Exercise 1 networking
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
UI Solidworks Presentation.pptx
UI Solidworks Presentation.pptxUI Solidworks Presentation.pptx
UI Solidworks Presentation.pptx
 
D18cl124 internship_report
D18cl124 internship_reportD18cl124 internship_report
D18cl124 internship_report
 
Civil course
Civil courseCivil course
Civil course
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptx
 
Lisans portfolyo
Lisans portfolyoLisans portfolyo
Lisans portfolyo
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03
 

More from Jacob Groezinger

Mr. Albert's Harvesting Decision - Team 3
Mr. Albert's Harvesting Decision - Team 3Mr. Albert's Harvesting Decision - Team 3
Mr. Albert's Harvesting Decision - Team 3Jacob Groezinger
 
Plexus Consulting Final Presentation
Plexus Consulting Final PresentationPlexus Consulting Final Presentation
Plexus Consulting Final PresentationJacob Groezinger
 
Nostalgia Electrics Popcorn Maker
Nostalgia Electrics Popcorn MakerNostalgia Electrics Popcorn Maker
Nostalgia Electrics Popcorn MakerJacob Groezinger
 
New Directions for Wind Turbines
New Directions for Wind TurbinesNew Directions for Wind Turbines
New Directions for Wind TurbinesJacob Groezinger
 

More from Jacob Groezinger (6)

Carson Distribution Inc.
Carson Distribution Inc.Carson Distribution Inc.
Carson Distribution Inc.
 
Mr. Albert's Harvesting Decision - Team 3
Mr. Albert's Harvesting Decision - Team 3Mr. Albert's Harvesting Decision - Team 3
Mr. Albert's Harvesting Decision - Team 3
 
Plexus Consulting Final Presentation
Plexus Consulting Final PresentationPlexus Consulting Final Presentation
Plexus Consulting Final Presentation
 
Nostalgia Electrics Popcorn Maker
Nostalgia Electrics Popcorn MakerNostalgia Electrics Popcorn Maker
Nostalgia Electrics Popcorn Maker
 
New Directions for Wind Turbines
New Directions for Wind TurbinesNew Directions for Wind Turbines
New Directions for Wind Turbines
 
JEDD 24x6 led matrix
JEDD 24x6 led matrixJEDD 24x6 led matrix
JEDD 24x6 led matrix
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Shaft Construction

  • 1. 1 Shaft Construction Brian Doyle | Jacob Groezinger | Lillian Kravitz | John Rosser Team 5 ISE 311 A51 – Enterprise Systems Monday, April 11, 2016
  • 3. 3 Framework Analysis Conclusions Recommendations Introduction Shaft Construction Company (SCC) • Key Stakeholders: • John Shaft – President & CEO • Bumpy Jonas – Lead Designer • Ellie Moore – Director of Personnel • Objective: • 15,000 seat stadium on college campus • Net Income: $450,000 • Client Details: • Jamestown, PA • Jamestown Community College http://cdn0.wideopencountry.com/wp-content/uploads/2015/08/high-school-football-793x526.jpg
  • 4. 4 Framework Analysis Conclusions Recommendations Background Background • Constraints: • August 26th, 2017 deadline • Resource allocation • Penalties • Potential Risks: • Approximately 10-week strike • Harsh winter: • Charge for pouring concrete
  • 5. 5 Framework Analysis Conclusions Recommendations Assumptions Project: • Project start date: June 6th, 2016 • No work on weekends • No overtime • Equipment and materials are out of scope • Winter months: December, January & February
  • 6. 6 Framework Analysis Conclusions Recommendations Assumptions (con’t) Construction: • Footings require three weeks to cure • Work that follows footings cannot begin until curing is complete • Site preparation and foundation includes staging areas and traffic flow redirection • “Filling of the field” is assumed to be activity C, build field • Tasks can pause midway through duration and resume at a later time
  • 7. 7 Framework Analysis Conclusions Recommendations Assumptions (con’t) Employees: • 67% of employees laid off during winter • 15 employees during December, January and February, 30 for other months • 5 employees utilized for management • SCC hires unionized employees • Strike begins when contract expires Costs • Projected net income of project: $450,000 • Indirect cost applied to alternate scenarios based off of do nothing benchmark • Federal Holidays are insignificant
  • 8. 8 Framework Analysis Conclusions Recommendations Work Breakdown Structure
  • 9. 9 Framework Analysis Conclusions Recommendations Network Information Item Structure or Field Task Duration Predecessor A Both Site Preparation & foundation 8 weeks - B Field Subsurface drainage 4 weeks A C Field Build field 4 weeks B D Field Installation of artificial surface 7 weeks C E Structure Footing & Curing 4 weeks & 3 weeks A F Structure Concrete Pillars 4 weeks E G Structure Steel structure 6 weeks E H Structure Seat Galleries Concrete Pour 10 weeks F I Structure Pre-cast Galleries 11 weeks H J Structure Roof 8 weeks G K Structure Seat Installations 4 weeks I L Structure Office & Dressing rooms 4 weeks J M Structure Seat Painting 3 weeks K N Structure Painting Other & Interior & Lights 5 weeks L O Structure Scoreboard and other elctronics 4 weeks L
  • 10. 10 Framework Analysis Conclusions Recommendations Risk Assessment Colder Temperatures: • $1,640 per week to pour concrete Strike: • 50 percent likelihood Penalty Clause • Construction extends past August 26th deadline • Cost: $18,000 per week
  • 11. 11 Framework Analysis Conclusions Recommendations Given Alternatives Do Nothing Expedite H** Expedite H** & Double Shift C* *Task C : Build Field **Task H : Pouring of the seat gallery supports
  • 12. 12 Framework Analysis Conclusions Recommendations PERT – Do Nothing 8 B 12 12 C 16 16 D 23 24 24 24 32 4 36 36 4 40 40 7 47 0 A 8 0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 47 - 47 0 8 8 0 0 0 0 0 15 4 19 19 10 29 29 11 40 40 4 44 44 3 47 47 0 47 8 E 15 0 33 N 38 8 7 15 15 G 21 21 J 29 29 L 33 9 9 9 9 42 5 47 24 6 30 30 8 38 38 4 42 ES ID EF 33 O 37 SL Descrip. 10 LS DUR LF 43 4 47 Sub. Drain Surface Seat Galleries Steel Pillars Build field Site Prep Electric Office Dress Paint OccupancySeat PaintSeatsPre-Cast Roof Footings
  • 13. 13 Framework Analysis Conclusions Recommendations Gantt Chart – Do Nothing Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th ACTIVITY START DURATION START DURATIONWEEK 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 4 12 4 D: Artificial Surface Install 16 7 16 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 10 19 10 I: Galleries Install 29 11 29 11 J: Roof Build 21 8 21 8 K: Seat Install 40 4 40 4 L: Office/Dressing Room Build 29 4 29 4 M: Seat Painting 44 3 44 3 N: Interior Paint/Electrical Install 33 5 33 5 O: Concrete Pillar Pour 33 4 33 4
  • 14. 17 Framework Analysis Conclusions Recommendations Resource PERT – Do Nothing 8 B 12 12 C 39 40 D 47 24 24 0 32 4 36 36 4 40 40 7 47 0 A 8 0 15 F 19 19 H 29 29 I 40 40 K 44 44 M 47 53 - 53 0 8 8 6 6 6 6 6 21 4 25 25 10 35 35 11 46 46 4 50 50 3 53 53 0 53 8 E 15 0 48 N 53 8 7 15 15 G 21 21 J 44 44 L 48 0 0 0 0 48 5 53 15 6 21 21 8 44 44 4 48 ES ID EF 48 O 52 SL Descrip. 1 LS DUR LF 49 4 53 Site Prep Pillars Seat Galleries Seat Paint Occupancy Footings Paint Sub. Drain Build field Surface Steel Roof Office Dress Electric Pre-Cast Seats
  • 15. 18 Framework Analysis Conclusions Recommendations Resource Gantt – Do Nothing Week duration: 53 weeks Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Start June 6thJuly 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th June 12th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th ACTIVITY START DURATION START DURATION WEEK 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 535455 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 40 7 40 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 10 19 10 I: Galleries Install 29 11 29 11 J: Roof Build 21 22 21 22 K: Seat Install 40 4 40 4 L: Office/Dressing Room Build 44 4 44 4 M: Seat Painting 44 3 44 3 N: Interior Paint/Electrical Install 48 5 48 5 O: Concrete Pillar Pour 48 4 48 4
  • 16. 19 Framework Analysis Conclusions Recommendations Gantt Chart – Expedite H Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) StartJune 6th July 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th ACTIVITY START DURATION START DURATION WEEK 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 40 7 40 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 19 6 19 6 I: Galleries Install 25 11 25 11 J: Roof Build 21 8 21 8 K: Seat Install 36 4 36 4 L: Office/Dressing Room Build 40 4 40 4 M: Seat Painting 40 3 40 3 N: Interior Paint/Electrical Install 44 5 44 5 O: Concrete Pillar Pour 44 4 44 4 Week duration: 49 weeks
  • 17. 28 Framework Analysis Conclusions Recommendations Strike Gantt Chart Shaft Construction Week Select: 1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan) Start June 6th .July 4th August 1st September 5th November 7st December 12th February 13th April 10th May 8th June 12th July 3rd August 7th PLAN PLAN ACTUAL ACTUAL October 3rd January 9th March 13th August 21st ACTIVITY START DURATION START DURATION WEEK STRIKE 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 A: Site/Foundation Prep 1 7 1 7 B: Subsurface Drainage Install 8 4 8 4 C: Field Build 12 26 12 26 D: Artificial Surface Install 44 7 44 7 E: Footing Pour 8 7 8 7 F: Concrete Pillar Pour 15 4 15 4 G: Steel Structure Build 15 6 15 6 H: Seat Galleries Concrete Pour 34 10 34 10 I: Galleries Install 39 11 39 11 J: Roof Build 21 22 21 22 K: Seat Install 50 4 50 4 L: Office/Dressing Room Build 44 4 44 4 M: Seat Painting 54 3 54 3 N: Interior Paint/Electrical Install 48 5 48 5 O: Concrete Pillar Pour 48 6 48 6 Week duration: 57 weeks
  • 18. 41 Framework Analysis Conclusions Recommendations Statistical Analysis Probability Warm Temp (>33O) Probability Cold Temp (<33O) Cold AND Strike Cold OR Strike December 48.4% 51.6% 25.8% 75.8% January 46.8% 53.2% 26.6% 76.6% February 56.4% 43.6% - 43.6%
  • 19. 42 Framework Analysis Conclusions Recommendations Net Income & Project Duration # Scenario Projected Net Income ($) Project Duration (weeks) 1Expedite H $474,360 49 2Expedite H & Cold $472,720 49 3Do Nothing $450,000 53 4Do Nothing & Cold $441,800 53 5Strike $403,640 57 6Strike & Cold $397,080 57 7Expedite H & Strike $381,640 57 8Close & Expedite H $381,640 57 9Expedite H & Strike & Cold $380,000 57 10Expedite H & Double Shift $360,050 58 11Expedite H & Double Shift & Cold $358,410 58 12Close $357,280 61
  • 20. 44 Framework Analysis Conclusions Recommendations Conclusions Conclusions • 76% chance of a strike or a harsh winter • Expediting H decreases duration and increases net income • Incur the $22,000 charge • Cut task duration from 10 to 6 weeks • Best alternative: • No obstacles • Cold winter
  • 21. 45 Framework Analysis Conclusions Recommendations Recommendations Expedite H: Pouring of the Seat Gallery Supports Highest Net Income Shortest Duration Accounts for the Most Risk
  • 22. 46 Framework Analysis Conclusions Recommendations Implementation Roadmap Meet with leadership Project start Follow-up
  • 23. 47 Framework Analysis Conclusions Recommendations Ideas for Future Research Next Steps • Increase employees • Different concrete mixtures • Reassess winter forecast in October
  • 24. 48 Framework Analysis Conclusions Recommendations References • (2013). Business Economics – A Library of Information. What is a Reasonable Profit in Construction? Retrieved from http://businessecon.org/2013/01/what-is-a-reasonable-profit-in-construction/ • (2016). Placing Concrete in Hot or Cold Weather. Sakrete. Retrieved from http://www.sakrete.com/media- center/blog-detail.cfm/bp_alias/Placing-Concrete-in-hot-or-cold-weather • (2016). U.S. Climate Change. Temperature-Precipitation-Sunshine-Snowfall. Retrieved from<http://www.usclimatedata.com/climate/jamestown/pennsylvania/united-states/uspa0781> • Blank, L. & Tarquin, A. (2012). Engineering Economy. New York, NY: McGraw-Hill. • Department of Commerce. (2016). National Centers for Environmental Information (NCEI). Retrieved from <https://www.ncdc.noaa.gov/> • Grabianowski, E. (2006, March). How Strikes Work. Retrieved from <http://money.howstuffworks.com/strike.htm> • Mishra, G. (2016). The Constructor – Civil Engineering Home. Construction Project Costs. Retrieved from http://theconstructor.org/constrution/construction-project-costs/7677/
  • 27. 51 Framework Analysis Conclusions Recommendations Strike Resource Schedule 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 10 7 7 7 7 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 X X X X 10 10 10 10 10 X X X X 8 8 8 8 X X X X Strike Period X X X X 18 8 8 8 18 20 20 20 20 20 25 25 25 25 25 10 10 10 25 25 25 25 25 25 25 25 25 25 H
  • 28. 52 Framework Analysis Conclusions Recommendations Strike Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 10/31 11/7 11/14 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X X X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 10 10 H 8 10 19 29 0 8 8 8 8 I 10 11 29 40 0 J 10 8 21 38 9 10 10 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 29. 53 Framework Analysis Conclusions Recommendations Strike Resource Schedule 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 49 50 51 52 53 54 55 56 57 58 59 60 7 7 7 10 10 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6X X 6 22 22 20 21 21 21 6 6 6 0 25 22 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 30. 54 Framework Analysis Conclusions Recommendations Close Winter Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 10/24 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 10 H 8 10 19 29 0 8 I 10 11 29 40 0 J 10 8 21 38 9 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 31. 55 Framework Analysis Conclusions Recommendations Close Winter Resource Schedule 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X 10 8 8 8 8 8 8 8 8 8 10 10 10 10 10 10 10 10 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 18 18 18 18 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 32. 56 Framework Analysis Conclusions Recommendations Close Winter Resource Schedule 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 10 7 7 7 7 7 7 7 10 10 10 10 10 10 10 10 10 10 10 8 8 8 8 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 18 18 18 18 22 22 22 22 16 20 17 15 15 15 15 13 13 6 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 33. 57 Framework Analysis Conclusions Recommendations Close Winter Expedite H: Resource Schedule 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/3 10/10 10/17 ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 A 25 8 0 8 0 25 25 25 25 25 25 25 25 25 B 10 4 8 36 24 10 10 10 10 C 10 4 12 40 24 10 10 10X D 7 7 16 47 24 X X X E 12 7 8 15 0 12 12 12 12 12 12 12 F 8 4 15 19 0 8 8 8 8 G 10 6 15 30 9 10 10 10 10 H 8 10 19 29 0 I 10 11 29 40 0 J 10 8 21 38 9 K 8 4 40 44 0 L 8 4 29 42 9 M 6 3 44 47 0 N 6 5 33 47 9 O 6 4 33 47 10 Total 25 25 25 25 25 25 25 25 25 22 22 22 22 22 22 22 18 18 18 18 Max Resource 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 34. 58 Framework Analysis Conclusions Recommendations Close Winter Expedite H: Resource Schedule 10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X X 10 10 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20 25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 35. 59 Framework Analysis Conclusions Recommendations Close Winter Expedite H: Resource Schedule 10/24 10/31 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6 2/13 2/20 2/27 3/6 3/13 3/20 3/27 4/3 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 X X X X 10 10 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 18 18 18 18 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 20 20 20 20 25 25 25 25 25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 25 25 25 25 H
  • 36. 60 Framework Analysis Conclusions Recommendations Close Winter Expedite H: Resource Schedule 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 44 45 46 47 48 49 50 51 52 53 54 55 56 57 10 7 7 7 7 7 7 10 10 10 10 10 10 10 8 8 8 8 8 8 8 8 6 6 6 6 6 6 6 6 6 6 6 6 18 18 18 18 22 22 22 30 21 15 15 13 13 13 25 25 25 25 25 25 25 25 25 25 25 25 25 25 H
  • 37. 62 Framework Analysis Conclusions Recommendations Weather Data December Mean = 32.56o F January Mean = 32.61 o F February Mean = 33.88 o F December Standard Deviation = 10.136 January Standard Deviation = 5.076 February Standard Deviation = 5.374 December Z-value = 0.043778 January Z-value = 0.077565 February Z-value = -0.16281 H
  • 38. 63 Framework Analysis Conclusions Recommendations Indirect Costs (x)*(0.09) = $450,000 $5,000,000 = x Costs = $5,000,000 - $450,000 = $4,550,000 Project overhead = (5% + 15%)/2 = 10% General overhead = (2% + 5%)/2 = 3.5% Indirect costs = (0.1)*($4,550,000) + (0.035)*($4,550,000) Indirect costs = $614,250 Weekly indirect cost = $614,250/53 = $11,589.63 H

Editor's Notes

  1. Jay
  2. Jay
  3. Jay
  4. Brian
  5. Brian
  6. Brian
  7. Brian
  8. Brian
  9. Brian
  10. Jay
  11. Jay
  12. Jay
  13. Lillian
  14. Lillian
  15. Lillian
  16. Lillian
  17. Lillian
  18. Jake
  19. Jake
  20. Jake
  21. Jake
  22. Jake
  23. Jake