SlideShare a Scribd company logo
www.systra.com
SEPARATING UNDERGROUND
METRO LINES UNDER OPERATION
IN BAKU
SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK,
Self-employed prof.: Elena CHIRIOTTI
SEPARATING UNDERGROUND
METRO LINES
UNDER OPERATION IN BAKU
SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK,
Self-employed prof.: Elena CHIRIOTTI
SUMMARY
The “28 May Station” is the only transfer station between the
existing Green and Red metro lines in Baku. As part of the huge
development strategy of the metro network, the complete
separation of the existing underground lines has been planned
at this location, in order to simplify the operation of the future
metro system.
The extreme challenge of the project is represented by the
need of achieve the separation of such lines over a breakdown
of the operation of just five weeks. The lack of direct access
from the surface, a complex geology with artesian water
layers, a congested underground space and sensible buildings
represent additional constraints.
The chosen design solution consists in creating a complex
steel pipe jacking frame around the operating tunnels and then
excavating under such frame two large caverns where the
separation of the existing lines and the construction of the
new metro tunnels will be achieved. Soil treatments have been
conceived to mitigate the geotechnical risks and to reduce
possible impacts on the existing structures.
The paper illustrate the challenges of this extraordinary project,
one of the most complex underground structures under study,
the design solutions and the risk management approach used
to manage the complexity and to design the mitigations
measures.
2
4
The Project
Prior to the extension of the southern part
of the existing Red Line and Green Line, and
in order to improve the current transport
capacity, a key activity is the removal of
the “Y” operation at the 28 May Station and
the separation of the Red and Green Lines’
tunnels. The 28 May Station in fact, connects
today the arrivals on the Red Line in the
direction Icharishahar (Old Town) and the Green
Line in the direction Darnagul. Passengers
wishing to continue along the Green Line,
must first go through a complex system of
galleries to transfer at Cefer Cabbarli station
where the trains are dispatched to the Khatai
Station (Figure. 1).
The new project aims to simplify the operation
of the May 28 Station and to completely
separate the tunnels of the two lines. Figure 2
presents the existing and the future layout
of the tunnels and station’s platforms at the
28 May and Cefer Cabbarli Stations.
The Separation of the Red and Green lines at
the 28 May Station consists of the construction
of two tunnels of 190meters in total as shown
in Figure 3. They are created by partially
demolishing the existing garage and storage
terminals of the “Xatai shuttle” and making
available the connection to Nizami station
trough the Green Line.
INTRODUCTION
The metro network in the capital of
Azerbaijan is rapidly growing together with
its metropolitan area. The beginnings of
the existing metro system started in Baku
in 1967 in Soviet times. To date, only
two lines (Green and Red) are in operation
with a total length of 34km, including
23 stations. The future network will be
much wider: besides the construction
of three completely new lines and the
extension of two existing lines, the whole
metro project includes the development
and modernization of the existing
metro sections.
A consortium formed by SYSTRA (leader),
Mott MacDonald (Praha) and Saman (Korea)
awarded the contract for the preliminary
and detailed design of infrastructures for
the extension of Baku Metro Network.
This extension consists in 83km of new
lines and extension of existing lines.
As part of this modernization project,
the connection of the Green Line at the
28 May/Cefer Cabbarli Stations, focus of
this paper, represent also it’s “Achilles’
heel” given that the already very congested
system have only one transfer station.
Figure 1. Existing Baku metro network and location of the 28 May Station
5
of clays, sands, and some banks of limestone
and sandstone.
Based on the geological data made available
from previous project in the area at the
feasibility stage, the entire geological profile
was considered a huge layer of relatively
stiff clay.
A first investigation campaign composed by
9 core recovery borehole and 8 SPT vertical
logs was launched in 2012 in order to confirm
these assumptions. The very first boreholes of
the campaign detected loose soils and artesian
water under the stiff clays starting 25-30m BGS.
After performing laboratory analysis (more than
200 identification tests, 30 shear tests and
16 compressibility tests) the local contractor
was not able to satisfactorily characterize
the lower layer whose characteristics appeared
contradictory and inconsistent with the
description of the borehole logs.
The designer requested additional geological
surveys, which were supposed to satisfactorily
identify and characterize the lower strata.
For this purpose, 13 cone penetration tests
THE INPUT DATA
AND CONSTRAINTS
To get accurate and reliable data for planning
infrastructure and underground works in post-
Soviet countries is quite complex because
for secrecy, confidentiality, topographical
information was deliberately distorted or shifted
by tens of meters, mostly unavailable as built
documents for existing structures. In addition,
the local suppliers for exploratory work do
not follow international standard methods and
their output can be unclear.
The Geological Investigations
and their Uncertainties
Baku urban area lays in the middle of a large
syncline responsible for the amphitheatre
morphology of the city and the differences
between the formations. The folded
geological formations present in Baku subsoil
are sediments from the Quaternary, and
Neogene. These sediments are mainly made
Figure 2. Existing (left) and future (right) metro network at 28 May station.
Figure 3. 3D model – 28 May station after separation
6
Based on the above characterization,
the distribution of the geotechnical units
has been studied and a geotechnical 3D
model of the studied zone was produced.
The study has been developed using the
GDM software of BRGM that allows to build
an interpretative 3D model of the geology,
the existing and the future structures,
and to represent such interpretation along
oriented sections.
The Geotechnical
Characterization
It must be mentioned that geotechnical
campaigns (both in situ and laboratory tests),
performed in Baku by local companies,
did not comply with international standards
in terms of methodology, equipment
implementation and calibration, recovery,
testing, and interpretation. Specifically,
the sampling method (simple core barrel)
led to significant sample disturbance and
affected the reliability of mechanical test.
For such reasons many parameters were
derived more from CPTUs results or from
designer’s experience on Baku’s soils than
from Lab tests results. Also taking in to
account the intrinsic variability of the Units,
a set of worst credible values for each Unit
has been defined further to the reference
values (see Table 1), in order to develop
the design by scenarios.
CPTu (the firsts ever conducted in the country)
and 2 pumping tests were recommended and
carried out. Based on the results, the bottom
layer was characterized and classified as a
sandy silt.
During the implementation of the additional
geological survey, the presence of artesian
groundwater was confirmed, which increased
the concerns about the underground works
being executed in the layer of sandy silt.
The pump tests also confirmed a continuous
water horizon under a confined pressure of
about 3 bars.
The Geological Model
Based on the results of the CPTu it was
possible to clearly identify and distinguish
the following Geotechnical Units:
•	Unit 1 (0 to 4m depth): man-made ground
unit
•	Unit 2 (4 to 26-30m depth): stiff Silty Clay
unit. The unit is composed mainly by silty
clay, with subunits of sand and sandy
silt. These sand lenses are almost always
recognized trough the CPTUs. The connection
between such lenses, although not surely
established based on the actual data, was
considered in the implementation of risk
analysis.
•	Unit 3 (26-30 to 60m depth): Silty Sand unit,
consisting of silty fine sands laminated with
thin to very thin interbedded silty clay and
sandy silts.
Table 1. Geotechnical characterization for the geotechnical Units
7
•	The existing running metro tunnels: circular
shaped, lined by cast iron segments of
5.1m internal diameter with pressure gate
chambers with a cast iron segmental lining
of 6.2m diameter;
•	an underground shopping passage consisting
of a reinforced concrete box which extend
foundations to about 5m below the surface;
•	utilities such as a water pipeline (D 500mm),
a medium pressure gas pipeline, 0,4 kV
electric cables and multiple unspecified
manholes, which need to be diverted before
any works may take place;
•	the Azerbaijan State Oil Academy: a five
storey masonry structure, with 4,5m deep
strip foundations considered a sensitive
structure due to its public use.
The Existing Structures
One of the biggest constraints of such project
is represented by the surrounding existing
structures. The presence and the sensitivity
of such structures limits the jobsite access
and space at the surface, potentially interferes
with the designed temporary and permanent
structures, and requires particular attention
to the effects of induced settlement. Figure
4 present a 3D view of the main existing
structures at the location of the future works.
The main existing structures considered as
design constants and for risk analysis are:
•	the 28 May Station: a deep mined station
consisting of a central tunnel, two side
tunnels and transversal galleries for the
connection with the Cefer Cabbarly station;
•	the Cefer Cabbarli Station for the shuttle line
to Xataï: a deep mined station consisting
of two twin tunnels, two dead-end galleries
and a network of adits for ventilation
and drainage connected at the end;
Figure 4. Existing surrounding structures at project location
8
collisions with the network of existing tunnels,
and the possible effects of the artesian
waters. This was done in close collaboration
with the contractor selected by the Client.
The completed design was submitted
for comments to the Azerbaijani ‘state expert
analysis’ and the Independent Checker selected
by the Client.
The Basic Design
The challenge consisting of excavating two
relatively short tunnels (about 100m long)
which encountered a section of an existing
tunnel made of cast iron segments and
performing this work as quickly as possible to
minimize interruptions to the metro operation.
The work also has to be done in proximity
to a network of existing tunnels without easy
access from the surface.
The whole design was developed in considering
the following key-issues, with taking into
consideration the project’s risks and constraints:
1.	To develop a design based on a systematic
risk analysis process shared with the Employer
and his representative: the design choices were
driven by risk assessment and this process has
been traceable and explicit.
2.	To develop the design by scenarios:
	 •	a reference scenario based on a
deterministic set of parameters (most likely
soil and groundwater characteristics and
behaviour, volume loss, deconfinement
ratio, works performance, geometry, etc.);
	 •	a scenario based on “worst credible
parameters” quantitatively considering the
impact of a certain number of geotechnical
DESIGN PROCESS
AND SOLUTIONS
As stated at the previous chapter, the seemingly
simple task that involved the construction
of two 100m long track tunnels is further
complicated by the results of the investigations
and by the time constraints imposed by
the Client. Those constrains mainly consist of:
•	Topography – there is no direct surface
access; access located immediately below
university building precluded the use
of a large excavated open pit, and in
proximity to a complex system of existing
underground structures;
•	Geology - the risk of encountering saturated
sand lenses, soft clays, artesian aquifers;
•	Time - the client requested the work be
completed in an extremely short period
(during shutdown of the Green Line –
5 weeks).
During the Feasibility Phase, three different
options were analysed, including the direct
re-excavation of the existing tunnels (Fig. 5a),
the excavation of a cavern preceded by simple
side adits (Fig. 5b) or by adits combined with
diaphragm walls (Fig. 5c).
The client selected the third variant, despite
to the longer period of construction and higher
costs, because it resulted in the shortest
shutdown period.
The selected option was subsequently
developed to the preliminary design level
and then further modified to account for the
topographical and geological surveys that
allowed to better estimate the possible
Figure 5. The three options from the Feasibility Study
9
The access shafts are excavated to the level
of an intermediate slab. From there, the upper
level adits are excavated. At the same time,
the shafts are completed to the bottom level.
If necessary, ground treatment (e.g. jet grouting,
ground freezing) from the upper level adits
is performed to support the excavation phase
of the lower adits.
Between the lateral adits, vertical and horizontal
pipe jacks are installed. These pipes are then
filled with concrete and reinforced at their ends
(corner connections), within the adits, to ensure
a stiff frame around the caverns excavated at
a later time.
Longitudinal adits will be kept close to the
future and existing Green Line tunnel to form
a square cavern shape which has 3 adits in
3 corners of the rectangle. The distribution of
the longitudinal adits and pipe jacking frame
can be seen in Figure 7.
The access to the cavern excavation is opened
from the shaft with an approximately 6.0x6.5m
window to facilitate the excavation progress.
From there, the first level of the cavern
(5.5m under pipe jacking roof) is excavated as
well as the head walls. The drainage system
is also installed.
After this phase, the operation of the green
line needs to be interrupted. Then, the caverns’
excavation is completed and the existing
running tunnel demolished. The invert and
construction elements for the new running
tunnel are installed in sequence. Once
the connecting structures are built, the caverns
are filled and traffic operation is resumed.
uncertainties and their variability to test
the robustness of the proposed technical
solution, and to incorporate the necessary
corrective measures in the design.
3.	To define mitigation and contingency
measures to control the effects induced by
the installation, excavation, and completion
of the underground work, for both the
reference (mitigation measures) and the worst
(contingency measures) scenarios.
4.	To define a set of driving parameters with
their respective operational ranges (when
applicable), and attention and alert thresholds
to be used during construction to monitor
the work and assist in decision making.
5.	To predefine the sequence of actions when
attention or alert thresholds are reached.
6.	Given the multiple excavations and mutual
interferences, the correct design method is
a 3D approach. In particular, numerical, coupled
analyses have been considered (combining
mechanical and hydraulic challenges).
7.	To select in a traceable way the most
adequate construction methods and ground
treatment, taking into consideration the soil
and groundwater conditions and required space
for jobsite logistics.
8.	To cope with time and environmental
constraints.
The Basic Design’s Solution
The separation of the red and green lines is
to be performed mainly the under protection
of two underground caverns, both constructed
below the Oil Academy Building. The depth
of the new tunnel alignment is approximately
18 – 22m below the surface. The overburden
of the upper lateral adits is around 12 – 15m.
The caverns themselves are planned to have
a maximum width of approximately 17m and a
height of approx. 10m.
The ground bearing structure of the caverns
are to be built before the excavation of the
caverns. The 3D model of Figure 6 gives an
overview of the project at the 28 May station.
The magenta show the new separation tunnels,
while the objects in green, yellow and pink
represent all the preliminary works needed to
install the new separation tunnels in the cavern.
Figure 6. 3D model of the basic design’s solution
10
of the excavation and the application of
soil support.
The geotechnical hazards above mentioned
have been thoroughly considered in the
Risk Register Matrix. The process of minimizing
of such risks has been an integrated part
of the design phase and will be completed
and implemented in the future stages of this
project, together with:
•	Non deterministic approach in design
(most likely and worst credible conditions)
•	Identification of mitigation measures,
where and when needed
•	Definition of predefined countermeasures
(to be fully shared with the Contractor)
•	Observational method during construction
(role of monitoring)
A preliminary Risk Register has been drafted
in accordance with ISO: 3100 and other
relevant standards [1-4] by the designer
in the basic design phase of the 28 May
Station Upgrade project. This has allowed to
properly communicate and share the risks
among the project’s actors, establish shared
geotechnical baselines to access the impact
of geotechnical uncertainties, and to define
the provisions for risk.
The risk related to the uncertainty of certain
geotechnical parameters and to the response
of the soil to excavation and soil treatment,
has pushed the designer and the Owner
to propose that the access shafts be used
as the location for the field trial tests for
the soil treatment work and to confirm/
update as much as possible the geotechnical
characterization by means of additional vertical
and inclined boreholes and in situ tests.
Consequently, the contractor has the
responsibility of updating the design based
on the results of such tests and on the surveys
carried out through excavation of the shafts.
This has led the project’s actor to select
a design -build form of contract in which
the steps of the design update are formalized,
together with the procedure in which such
results are used to update the project.
This solution allows reducing the traffic
interruption on the green line for a period
not to exceed 5 weeks.
RISK MANAGEMENT
The main geotechnical hazards identified for
the construction phases are:
•	The presence of the artesian groundwater
during excavation of the lower adits and the
connection between the pipejackings tubes
may result in the instability of the excavation
and unsafe conditions for the workers.
•	Although the low permeability values
registered during the tests, the presence
of artesian groundwater in the Silty Sand Unit
may result in water inflows and in stability
problems at the base of the caverns.
•	The presence of sand lenses interbedded
in the Silty Clay Unit may contain water
or, if thick enough and continuous, may
be connected to the artesian aquifer,
results in possible water inflows and
instability during the excavations phases.
•	The uncertainties due to poor recovery of
the samples and questionable reliability
of lab results oblige to carry out the design
through parametric studies, analyzing
the influence of key input parameters in
the engineering solutions.
The identified hazards have also to been
considered in the context of a densely
urbanized environment and heavily utilized
underground space, which strongly limit
the investigations distribution and that present
a significant constraints for the geometry
Figure 7. The section type for basic design’s solution
11
•	two huge caverns supported by rigid closed
water resistant pipe jacked frame completely
jacked from small underground access
galleries,
•	the massive ground treatment measures
(in alternatives, also installed from the
underground) and taking in to account
existing and operating tunnels and buildings
in the close proximity,
•	replacement of old by new metro tunnels
including rail and MEP in extremely short
time.
Where the contractor’s experience has been
involved as early as possible in the study of
the construction method. This was combined
to a systematic risk management approach and
to the definition of the most adequate form
of contract considering the project constraints
and characteristics.
The project which consists in separating the
running tunnels of the Red and Green Metro
Lines in Baku is particularly challenging for
many reasons: the Client’s requirement of
interrupting the metro traffic for no longer
than 5 weeks; the complexity of the existing
underground structures; the sensitivity of the
buildings above the future work; the limited
access space on the surface and the limitations
in placing and dimensioning access shafts to
support the excavation of the underground
work; the existing condition of the subsoil and
the pressurized aquifer; the uncertainties related
to the ground characterization.
This has led to develop a very challenging
design involving innovative technical solutions
requiring high accuracy and latest technologies
for the first time used not only in Azerbaijan
such as:
REFERENCES
[1] The Code of Practice for Risk Management of Tunnel Works (2006). International Tunnelling
Insurance Group (ITIG), presented at the ITA World Congress, Seoul, April 2006.
[2] Guidelines for Tunnelling Risk Management: International Tunnelling Association, Working
Group n°2 (2004). Tunnelling and Underground Space Technology, N.19, 2004, pp. 217-237.
[3] The Joint Code of Practice for Risk Management of Tunnel Works in the UK (2003).
Published by the British Tunnelling Society (BTS), prepared jointly by BTS and the
Association of British Insurers.
[4] A Guide to the Systematic Management of Risk from Construction (1996), CIRIA,
Special Publication 125.
CONCLUSIONS
© SYSTRA2016,© M.Kadri/CAPAPictures
72 rue Henry Farman
CS 41594
75513 Paris Cedex 15
+ 33 1 40 16 61 00

More Related Content

What's hot

Lógica formal e Dialética e a Organização dos Argumentos (1).ppt
Lógica formal e Dialética e a Organização dos Argumentos (1).pptLógica formal e Dialética e a Organização dos Argumentos (1).ppt
Lógica formal e Dialética e a Organização dos Argumentos (1).ppt
Antonio Gilberto De Aquino e Silva
 
Relatorio de fisica construao de um termmetro
Relatorio de fisica   construao de um termmetroRelatorio de fisica   construao de um termmetro
Relatorio de fisica construao de um termmetroGabriela Mendes
 
Ficha Informativa - Experiência de Niremberg e Khorana
Ficha Informativa - Experiência de Niremberg e KhoranaFicha Informativa - Experiência de Niremberg e Khorana
Ficha Informativa - Experiência de Niremberg e KhoranaIsaura Mourão
 
Campo magnético produzido por corrente site
Campo magnético produzido por corrente siteCampo magnético produzido por corrente site
Campo magnético produzido por corrente sitefisicaatual
 
Platão
PlatãoPlatão
Modulo a6 alunos
Modulo a6 alunosModulo a6 alunos
Modulo a6 alunos
profernando
 
Visita ao Museu Tecnológico da PUCRS
Visita ao Museu Tecnológico da PUCRSVisita ao Museu Tecnológico da PUCRS
Visita ao Museu Tecnológico da PUCRS
FabianeM
 
Teorema de pitagoras
Teorema de pitagorasTeorema de pitagoras
Teorema de pitagorasAna Rodrigues
 
Eletromagnetismo - Resumo
Eletromagnetismo - ResumoEletromagnetismo - Resumo
Eletromagnetismo - Resumo
Mayara Daniel
 
oficina de programa de ação.pptx
oficina de programa de ação.pptxoficina de programa de ação.pptx
oficina de programa de ação.pptx
VitorFilho3
 
Biologia ensino profissional - módulo a1
Biologia   ensino profissional - módulo a1Biologia   ensino profissional - módulo a1
Biologia ensino profissional - módulo a1Rita_Brito
 
Eletrização por Atrito
Eletrização por AtritoEletrização por Atrito
Eletrização por AtritoAndré Aleixo
 
Slides da aula de Filosofia (João Luís) sobre Atitude Filosófica
Slides da aula de Filosofia (João Luís) sobre Atitude FilosóficaSlides da aula de Filosofia (João Luís) sobre Atitude Filosófica
Slides da aula de Filosofia (João Luís) sobre Atitude Filosófica
Turma Olímpica
 
TESTES INTERMÉDIOS 11ºANO
TESTES INTERMÉDIOS 11ºANOTESTES INTERMÉDIOS 11ºANO
TESTES INTERMÉDIOS 11ºANOsandranascimento
 
Trigonometria Seno e Cosseno
Trigonometria Seno e CossenoTrigonometria Seno e Cosseno
Trigonometria Seno e Cosseno
gustavocosta77
 
Pedagogia do oprimido
Pedagogia do oprimidoPedagogia do oprimido
Pedagogia do oprimidoSunia Regina
 
Relatório 2ª lei de newton turma t5
Relatório 2ª lei de newton   turma t5Relatório 2ª lei de newton   turma t5
Relatório 2ª lei de newton turma t5Roberto Leao
 
Juízo de fato e Juízo de valor
Juízo de fato e Juízo de valorJuízo de fato e Juízo de valor
Juízo de fato e Juízo de valor
Danilo Pires
 

What's hot (20)

Lógica formal e Dialética e a Organização dos Argumentos (1).ppt
Lógica formal e Dialética e a Organização dos Argumentos (1).pptLógica formal e Dialética e a Organização dos Argumentos (1).ppt
Lógica formal e Dialética e a Organização dos Argumentos (1).ppt
 
Relatorio de fisica construao de um termmetro
Relatorio de fisica   construao de um termmetroRelatorio de fisica   construao de um termmetro
Relatorio de fisica construao de um termmetro
 
Ficha Informativa - Experiência de Niremberg e Khorana
Ficha Informativa - Experiência de Niremberg e KhoranaFicha Informativa - Experiência de Niremberg e Khorana
Ficha Informativa - Experiência de Niremberg e Khorana
 
Campo magnético produzido por corrente site
Campo magnético produzido por corrente siteCampo magnético produzido por corrente site
Campo magnético produzido por corrente site
 
Platão
PlatãoPlatão
Platão
 
Sócrates
SócratesSócrates
Sócrates
 
Modulo a6 alunos
Modulo a6 alunosModulo a6 alunos
Modulo a6 alunos
 
Visita ao Museu Tecnológico da PUCRS
Visita ao Museu Tecnológico da PUCRSVisita ao Museu Tecnológico da PUCRS
Visita ao Museu Tecnológico da PUCRS
 
Teorema de pitagoras
Teorema de pitagorasTeorema de pitagoras
Teorema de pitagoras
 
Lei de coulomb
Lei de coulombLei de coulomb
Lei de coulomb
 
Eletromagnetismo - Resumo
Eletromagnetismo - ResumoEletromagnetismo - Resumo
Eletromagnetismo - Resumo
 
oficina de programa de ação.pptx
oficina de programa de ação.pptxoficina de programa de ação.pptx
oficina de programa de ação.pptx
 
Biologia ensino profissional - módulo a1
Biologia   ensino profissional - módulo a1Biologia   ensino profissional - módulo a1
Biologia ensino profissional - módulo a1
 
Eletrização por Atrito
Eletrização por AtritoEletrização por Atrito
Eletrização por Atrito
 
Slides da aula de Filosofia (João Luís) sobre Atitude Filosófica
Slides da aula de Filosofia (João Luís) sobre Atitude FilosóficaSlides da aula de Filosofia (João Luís) sobre Atitude Filosófica
Slides da aula de Filosofia (João Luís) sobre Atitude Filosófica
 
TESTES INTERMÉDIOS 11ºANO
TESTES INTERMÉDIOS 11ºANOTESTES INTERMÉDIOS 11ºANO
TESTES INTERMÉDIOS 11ºANO
 
Trigonometria Seno e Cosseno
Trigonometria Seno e CossenoTrigonometria Seno e Cosseno
Trigonometria Seno e Cosseno
 
Pedagogia do oprimido
Pedagogia do oprimidoPedagogia do oprimido
Pedagogia do oprimido
 
Relatório 2ª lei de newton turma t5
Relatório 2ª lei de newton   turma t5Relatório 2ª lei de newton   turma t5
Relatório 2ª lei de newton turma t5
 
Juízo de fato e Juízo de valor
Juízo de fato e Juízo de valorJuízo de fato e Juízo de valor
Juízo de fato e Juízo de valor
 

Similar to Separating underground metro lines under operation in Baku

Easy chair preprint-2809 (1)
Easy chair preprint-2809 (1)Easy chair preprint-2809 (1)
Easy chair preprint-2809 (1)
Jandi11
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
IRJET Journal
 
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
IJERA Editor
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET Journal
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
Applications of BDJ - EN.pptx
Applications of BDJ - EN.pptxApplications of BDJ - EN.pptx
Applications of BDJ - EN.pptx
NgcPhong3
 
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptxWidening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
SantoshMajagi
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)Pablo Miguel Jurado
 
Safety problem of Boguchansk rockfill dam with asphalt concrete core
Safety problem of Boguchansk rockfill dam with asphalt concrete coreSafety problem of Boguchansk rockfill dam with asphalt concrete core
Safety problem of Boguchansk rockfill dam with asphalt concrete core
Yury Lyapichev
 
Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...
l’Institut français des sciences et technologies des transports, de l’aménagement et des réseaux
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
Rajesh Prasad
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011ILIAS MICHALIS
 
Mohr-Coulomb and Harding soil model comparison
Mohr-Coulomb and Harding soil model comparisonMohr-Coulomb and Harding soil model comparison
Mohr-Coulomb and Harding soil model comparison
KhaoulaAmraoui2
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Dr. Amarjeet Singh
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
ijceronline
 
Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...
Multan Prajapat
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09Hans De Wit
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
CrimsonPublishersAMMS
 

Similar to Separating underground metro lines under operation in Baku (20)

Paper
PaperPaper
Paper
 
Easy chair preprint-2809 (1)
Easy chair preprint-2809 (1)Easy chair preprint-2809 (1)
Easy chair preprint-2809 (1)
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
 
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Applications of BDJ - EN.pptx
Applications of BDJ - EN.pptxApplications of BDJ - EN.pptx
Applications of BDJ - EN.pptx
 
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptxWidening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
Widening of existing Ghataprabha Bridge from 2 to 3 lane(oneway).pptx
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
Safety problem of Boguchansk rockfill dam with asphalt concrete core
Safety problem of Boguchansk rockfill dam with asphalt concrete coreSafety problem of Boguchansk rockfill dam with asphalt concrete core
Safety problem of Boguchansk rockfill dam with asphalt concrete core
 
Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011
 
Mohr-Coulomb and Harding soil model comparison
Mohr-Coulomb and Harding soil model comparisonMohr-Coulomb and Harding soil model comparison
Mohr-Coulomb and Harding soil model comparison
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
 

More from SYSTRA

INGENIE QUOI ? Ecologue chez SYSTRA
INGENIE QUOI ? Ecologue chez SYSTRAINGENIE QUOI ? Ecologue chez SYSTRA
INGENIE QUOI ? Ecologue chez SYSTRA
SYSTRA
 
Need for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro linesNeed for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro lines
SYSTRA
 
CBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehiclesCBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehicles
SYSTRA
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marls
SYSTRA
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
SYSTRA
 
Nos réalisations
Nos réalisationsNos réalisations
Nos réalisations
SYSTRA
 

More from SYSTRA (6)

INGENIE QUOI ? Ecologue chez SYSTRA
INGENIE QUOI ? Ecologue chez SYSTRAINGENIE QUOI ? Ecologue chez SYSTRA
INGENIE QUOI ? Ecologue chez SYSTRA
 
Need for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro linesNeed for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro lines
 
CBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehiclesCBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehicles
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marls
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
 
Nos réalisations
Nos réalisationsNos réalisations
Nos réalisations
 

Recently uploaded

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 

Recently uploaded (20)

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 

Separating underground metro lines under operation in Baku

  • 1. www.systra.com SEPARATING UNDERGROUND METRO LINES UNDER OPERATION IN BAKU SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK, Self-employed prof.: Elena CHIRIOTTI
  • 2.
  • 3. SEPARATING UNDERGROUND METRO LINES UNDER OPERATION IN BAKU SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK, Self-employed prof.: Elena CHIRIOTTI SUMMARY The “28 May Station” is the only transfer station between the existing Green and Red metro lines in Baku. As part of the huge development strategy of the metro network, the complete separation of the existing underground lines has been planned at this location, in order to simplify the operation of the future metro system. The extreme challenge of the project is represented by the need of achieve the separation of such lines over a breakdown of the operation of just five weeks. The lack of direct access from the surface, a complex geology with artesian water layers, a congested underground space and sensible buildings represent additional constraints. The chosen design solution consists in creating a complex steel pipe jacking frame around the operating tunnels and then excavating under such frame two large caverns where the separation of the existing lines and the construction of the new metro tunnels will be achieved. Soil treatments have been conceived to mitigate the geotechnical risks and to reduce possible impacts on the existing structures. The paper illustrate the challenges of this extraordinary project, one of the most complex underground structures under study, the design solutions and the risk management approach used to manage the complexity and to design the mitigations measures. 2
  • 4. 4 The Project Prior to the extension of the southern part of the existing Red Line and Green Line, and in order to improve the current transport capacity, a key activity is the removal of the “Y” operation at the 28 May Station and the separation of the Red and Green Lines’ tunnels. The 28 May Station in fact, connects today the arrivals on the Red Line in the direction Icharishahar (Old Town) and the Green Line in the direction Darnagul. Passengers wishing to continue along the Green Line, must first go through a complex system of galleries to transfer at Cefer Cabbarli station where the trains are dispatched to the Khatai Station (Figure. 1). The new project aims to simplify the operation of the May 28 Station and to completely separate the tunnels of the two lines. Figure 2 presents the existing and the future layout of the tunnels and station’s platforms at the 28 May and Cefer Cabbarli Stations. The Separation of the Red and Green lines at the 28 May Station consists of the construction of two tunnels of 190meters in total as shown in Figure 3. They are created by partially demolishing the existing garage and storage terminals of the “Xatai shuttle” and making available the connection to Nizami station trough the Green Line. INTRODUCTION The metro network in the capital of Azerbaijan is rapidly growing together with its metropolitan area. The beginnings of the existing metro system started in Baku in 1967 in Soviet times. To date, only two lines (Green and Red) are in operation with a total length of 34km, including 23 stations. The future network will be much wider: besides the construction of three completely new lines and the extension of two existing lines, the whole metro project includes the development and modernization of the existing metro sections. A consortium formed by SYSTRA (leader), Mott MacDonald (Praha) and Saman (Korea) awarded the contract for the preliminary and detailed design of infrastructures for the extension of Baku Metro Network. This extension consists in 83km of new lines and extension of existing lines. As part of this modernization project, the connection of the Green Line at the 28 May/Cefer Cabbarli Stations, focus of this paper, represent also it’s “Achilles’ heel” given that the already very congested system have only one transfer station. Figure 1. Existing Baku metro network and location of the 28 May Station
  • 5. 5 of clays, sands, and some banks of limestone and sandstone. Based on the geological data made available from previous project in the area at the feasibility stage, the entire geological profile was considered a huge layer of relatively stiff clay. A first investigation campaign composed by 9 core recovery borehole and 8 SPT vertical logs was launched in 2012 in order to confirm these assumptions. The very first boreholes of the campaign detected loose soils and artesian water under the stiff clays starting 25-30m BGS. After performing laboratory analysis (more than 200 identification tests, 30 shear tests and 16 compressibility tests) the local contractor was not able to satisfactorily characterize the lower layer whose characteristics appeared contradictory and inconsistent with the description of the borehole logs. The designer requested additional geological surveys, which were supposed to satisfactorily identify and characterize the lower strata. For this purpose, 13 cone penetration tests THE INPUT DATA AND CONSTRAINTS To get accurate and reliable data for planning infrastructure and underground works in post- Soviet countries is quite complex because for secrecy, confidentiality, topographical information was deliberately distorted or shifted by tens of meters, mostly unavailable as built documents for existing structures. In addition, the local suppliers for exploratory work do not follow international standard methods and their output can be unclear. The Geological Investigations and their Uncertainties Baku urban area lays in the middle of a large syncline responsible for the amphitheatre morphology of the city and the differences between the formations. The folded geological formations present in Baku subsoil are sediments from the Quaternary, and Neogene. These sediments are mainly made Figure 2. Existing (left) and future (right) metro network at 28 May station. Figure 3. 3D model – 28 May station after separation
  • 6. 6 Based on the above characterization, the distribution of the geotechnical units has been studied and a geotechnical 3D model of the studied zone was produced. The study has been developed using the GDM software of BRGM that allows to build an interpretative 3D model of the geology, the existing and the future structures, and to represent such interpretation along oriented sections. The Geotechnical Characterization It must be mentioned that geotechnical campaigns (both in situ and laboratory tests), performed in Baku by local companies, did not comply with international standards in terms of methodology, equipment implementation and calibration, recovery, testing, and interpretation. Specifically, the sampling method (simple core barrel) led to significant sample disturbance and affected the reliability of mechanical test. For such reasons many parameters were derived more from CPTUs results or from designer’s experience on Baku’s soils than from Lab tests results. Also taking in to account the intrinsic variability of the Units, a set of worst credible values for each Unit has been defined further to the reference values (see Table 1), in order to develop the design by scenarios. CPTu (the firsts ever conducted in the country) and 2 pumping tests were recommended and carried out. Based on the results, the bottom layer was characterized and classified as a sandy silt. During the implementation of the additional geological survey, the presence of artesian groundwater was confirmed, which increased the concerns about the underground works being executed in the layer of sandy silt. The pump tests also confirmed a continuous water horizon under a confined pressure of about 3 bars. The Geological Model Based on the results of the CPTu it was possible to clearly identify and distinguish the following Geotechnical Units: • Unit 1 (0 to 4m depth): man-made ground unit • Unit 2 (4 to 26-30m depth): stiff Silty Clay unit. The unit is composed mainly by silty clay, with subunits of sand and sandy silt. These sand lenses are almost always recognized trough the CPTUs. The connection between such lenses, although not surely established based on the actual data, was considered in the implementation of risk analysis. • Unit 3 (26-30 to 60m depth): Silty Sand unit, consisting of silty fine sands laminated with thin to very thin interbedded silty clay and sandy silts. Table 1. Geotechnical characterization for the geotechnical Units
  • 7. 7 • The existing running metro tunnels: circular shaped, lined by cast iron segments of 5.1m internal diameter with pressure gate chambers with a cast iron segmental lining of 6.2m diameter; • an underground shopping passage consisting of a reinforced concrete box which extend foundations to about 5m below the surface; • utilities such as a water pipeline (D 500mm), a medium pressure gas pipeline, 0,4 kV electric cables and multiple unspecified manholes, which need to be diverted before any works may take place; • the Azerbaijan State Oil Academy: a five storey masonry structure, with 4,5m deep strip foundations considered a sensitive structure due to its public use. The Existing Structures One of the biggest constraints of such project is represented by the surrounding existing structures. The presence and the sensitivity of such structures limits the jobsite access and space at the surface, potentially interferes with the designed temporary and permanent structures, and requires particular attention to the effects of induced settlement. Figure 4 present a 3D view of the main existing structures at the location of the future works. The main existing structures considered as design constants and for risk analysis are: • the 28 May Station: a deep mined station consisting of a central tunnel, two side tunnels and transversal galleries for the connection with the Cefer Cabbarly station; • the Cefer Cabbarli Station for the shuttle line to Xataï: a deep mined station consisting of two twin tunnels, two dead-end galleries and a network of adits for ventilation and drainage connected at the end; Figure 4. Existing surrounding structures at project location
  • 8. 8 collisions with the network of existing tunnels, and the possible effects of the artesian waters. This was done in close collaboration with the contractor selected by the Client. The completed design was submitted for comments to the Azerbaijani ‘state expert analysis’ and the Independent Checker selected by the Client. The Basic Design The challenge consisting of excavating two relatively short tunnels (about 100m long) which encountered a section of an existing tunnel made of cast iron segments and performing this work as quickly as possible to minimize interruptions to the metro operation. The work also has to be done in proximity to a network of existing tunnels without easy access from the surface. The whole design was developed in considering the following key-issues, with taking into consideration the project’s risks and constraints: 1. To develop a design based on a systematic risk analysis process shared with the Employer and his representative: the design choices were driven by risk assessment and this process has been traceable and explicit. 2. To develop the design by scenarios: • a reference scenario based on a deterministic set of parameters (most likely soil and groundwater characteristics and behaviour, volume loss, deconfinement ratio, works performance, geometry, etc.); • a scenario based on “worst credible parameters” quantitatively considering the impact of a certain number of geotechnical DESIGN PROCESS AND SOLUTIONS As stated at the previous chapter, the seemingly simple task that involved the construction of two 100m long track tunnels is further complicated by the results of the investigations and by the time constraints imposed by the Client. Those constrains mainly consist of: • Topography – there is no direct surface access; access located immediately below university building precluded the use of a large excavated open pit, and in proximity to a complex system of existing underground structures; • Geology - the risk of encountering saturated sand lenses, soft clays, artesian aquifers; • Time - the client requested the work be completed in an extremely short period (during shutdown of the Green Line – 5 weeks). During the Feasibility Phase, three different options were analysed, including the direct re-excavation of the existing tunnels (Fig. 5a), the excavation of a cavern preceded by simple side adits (Fig. 5b) or by adits combined with diaphragm walls (Fig. 5c). The client selected the third variant, despite to the longer period of construction and higher costs, because it resulted in the shortest shutdown period. The selected option was subsequently developed to the preliminary design level and then further modified to account for the topographical and geological surveys that allowed to better estimate the possible Figure 5. The three options from the Feasibility Study
  • 9. 9 The access shafts are excavated to the level of an intermediate slab. From there, the upper level adits are excavated. At the same time, the shafts are completed to the bottom level. If necessary, ground treatment (e.g. jet grouting, ground freezing) from the upper level adits is performed to support the excavation phase of the lower adits. Between the lateral adits, vertical and horizontal pipe jacks are installed. These pipes are then filled with concrete and reinforced at their ends (corner connections), within the adits, to ensure a stiff frame around the caverns excavated at a later time. Longitudinal adits will be kept close to the future and existing Green Line tunnel to form a square cavern shape which has 3 adits in 3 corners of the rectangle. The distribution of the longitudinal adits and pipe jacking frame can be seen in Figure 7. The access to the cavern excavation is opened from the shaft with an approximately 6.0x6.5m window to facilitate the excavation progress. From there, the first level of the cavern (5.5m under pipe jacking roof) is excavated as well as the head walls. The drainage system is also installed. After this phase, the operation of the green line needs to be interrupted. Then, the caverns’ excavation is completed and the existing running tunnel demolished. The invert and construction elements for the new running tunnel are installed in sequence. Once the connecting structures are built, the caverns are filled and traffic operation is resumed. uncertainties and their variability to test the robustness of the proposed technical solution, and to incorporate the necessary corrective measures in the design. 3. To define mitigation and contingency measures to control the effects induced by the installation, excavation, and completion of the underground work, for both the reference (mitigation measures) and the worst (contingency measures) scenarios. 4. To define a set of driving parameters with their respective operational ranges (when applicable), and attention and alert thresholds to be used during construction to monitor the work and assist in decision making. 5. To predefine the sequence of actions when attention or alert thresholds are reached. 6. Given the multiple excavations and mutual interferences, the correct design method is a 3D approach. In particular, numerical, coupled analyses have been considered (combining mechanical and hydraulic challenges). 7. To select in a traceable way the most adequate construction methods and ground treatment, taking into consideration the soil and groundwater conditions and required space for jobsite logistics. 8. To cope with time and environmental constraints. The Basic Design’s Solution The separation of the red and green lines is to be performed mainly the under protection of two underground caverns, both constructed below the Oil Academy Building. The depth of the new tunnel alignment is approximately 18 – 22m below the surface. The overburden of the upper lateral adits is around 12 – 15m. The caverns themselves are planned to have a maximum width of approximately 17m and a height of approx. 10m. The ground bearing structure of the caverns are to be built before the excavation of the caverns. The 3D model of Figure 6 gives an overview of the project at the 28 May station. The magenta show the new separation tunnels, while the objects in green, yellow and pink represent all the preliminary works needed to install the new separation tunnels in the cavern. Figure 6. 3D model of the basic design’s solution
  • 10. 10 of the excavation and the application of soil support. The geotechnical hazards above mentioned have been thoroughly considered in the Risk Register Matrix. The process of minimizing of such risks has been an integrated part of the design phase and will be completed and implemented in the future stages of this project, together with: • Non deterministic approach in design (most likely and worst credible conditions) • Identification of mitigation measures, where and when needed • Definition of predefined countermeasures (to be fully shared with the Contractor) • Observational method during construction (role of monitoring) A preliminary Risk Register has been drafted in accordance with ISO: 3100 and other relevant standards [1-4] by the designer in the basic design phase of the 28 May Station Upgrade project. This has allowed to properly communicate and share the risks among the project’s actors, establish shared geotechnical baselines to access the impact of geotechnical uncertainties, and to define the provisions for risk. The risk related to the uncertainty of certain geotechnical parameters and to the response of the soil to excavation and soil treatment, has pushed the designer and the Owner to propose that the access shafts be used as the location for the field trial tests for the soil treatment work and to confirm/ update as much as possible the geotechnical characterization by means of additional vertical and inclined boreholes and in situ tests. Consequently, the contractor has the responsibility of updating the design based on the results of such tests and on the surveys carried out through excavation of the shafts. This has led the project’s actor to select a design -build form of contract in which the steps of the design update are formalized, together with the procedure in which such results are used to update the project. This solution allows reducing the traffic interruption on the green line for a period not to exceed 5 weeks. RISK MANAGEMENT The main geotechnical hazards identified for the construction phases are: • The presence of the artesian groundwater during excavation of the lower adits and the connection between the pipejackings tubes may result in the instability of the excavation and unsafe conditions for the workers. • Although the low permeability values registered during the tests, the presence of artesian groundwater in the Silty Sand Unit may result in water inflows and in stability problems at the base of the caverns. • The presence of sand lenses interbedded in the Silty Clay Unit may contain water or, if thick enough and continuous, may be connected to the artesian aquifer, results in possible water inflows and instability during the excavations phases. • The uncertainties due to poor recovery of the samples and questionable reliability of lab results oblige to carry out the design through parametric studies, analyzing the influence of key input parameters in the engineering solutions. The identified hazards have also to been considered in the context of a densely urbanized environment and heavily utilized underground space, which strongly limit the investigations distribution and that present a significant constraints for the geometry Figure 7. The section type for basic design’s solution
  • 11. 11 • two huge caverns supported by rigid closed water resistant pipe jacked frame completely jacked from small underground access galleries, • the massive ground treatment measures (in alternatives, also installed from the underground) and taking in to account existing and operating tunnels and buildings in the close proximity, • replacement of old by new metro tunnels including rail and MEP in extremely short time. Where the contractor’s experience has been involved as early as possible in the study of the construction method. This was combined to a systematic risk management approach and to the definition of the most adequate form of contract considering the project constraints and characteristics. The project which consists in separating the running tunnels of the Red and Green Metro Lines in Baku is particularly challenging for many reasons: the Client’s requirement of interrupting the metro traffic for no longer than 5 weeks; the complexity of the existing underground structures; the sensitivity of the buildings above the future work; the limited access space on the surface and the limitations in placing and dimensioning access shafts to support the excavation of the underground work; the existing condition of the subsoil and the pressurized aquifer; the uncertainties related to the ground characterization. This has led to develop a very challenging design involving innovative technical solutions requiring high accuracy and latest technologies for the first time used not only in Azerbaijan such as: REFERENCES [1] The Code of Practice for Risk Management of Tunnel Works (2006). International Tunnelling Insurance Group (ITIG), presented at the ITA World Congress, Seoul, April 2006. [2] Guidelines for Tunnelling Risk Management: International Tunnelling Association, Working Group n°2 (2004). Tunnelling and Underground Space Technology, N.19, 2004, pp. 217-237. [3] The Joint Code of Practice for Risk Management of Tunnel Works in the UK (2003). Published by the British Tunnelling Society (BTS), prepared jointly by BTS and the Association of British Insurers. [4] A Guide to the Systematic Management of Risk from Construction (1996), CIRIA, Special Publication 125. CONCLUSIONS
  • 12. © SYSTRA2016,© M.Kadri/CAPAPictures 72 rue Henry Farman CS 41594 75513 Paris Cedex 15 + 33 1 40 16 61 00