This document discusses tunnelling projects and experiences gained in Greece over the last 20 years. Significant projects include the Egnatia Motorway, Attiki Odos motorway, Athens and Thessaloniki metro systems, and various railway lines. These projects involved constructing over 347.5km of tunnels. Through these projects, Greece has gained experience with tunnel design and construction in varied geological conditions. Key experiences and methodologies developed include the Geological Strength Index (GSI) system for characterizing weak and heterogeneous rock masses, and the Tunnel Stability Factor (TSF) for assessing tunnel stability as a function of rock strength and stress conditions. Future tunnelling projects in Greece are also discussed.
Major issues to be considered for the successful application of unreinforced and steel fiber reinforced concrete (SFRC) tunnel final linings concepts include:
1) Application limits related to the geotechnical environment, seismic regime, and topography that must be determined based on safety and serviceability requirements.
2) Existing design codes and recommendations provide frameworks for evaluating the safety and serviceability of these lining concepts.
3) Case studies demonstrate that unreinforced and SFRC tunnel linings have been successfully used in tunnels up to 8km and 4.8km respectively, in various ground conditions.
1. The document examines the use of Tunnel Stability Factor (TSF) to estimate convergence and face stability in weak rock tunnels. TSF considers rock mass strength, overburden height, and tunnel size.
2. Parametric numerical analyses were conducted on 74 tunnels varying in size, depth, and rock mass quality. Dimensionless plots of plastic zone radius and convergence vs TSF showed good correlation despite varying conditions.
3. Guidelines for criticality of stability were developed based on convergence-to-radius ratio ranges associated with TSF levels, indicating severe squeezing for TSF < 0.2 and increased risk of collapse below 0.3 without support.
Separating underground metro lines under operation in BakuSYSTRA
The document discusses a project to separate the existing Green and Red underground metro lines in Baku, Azerbaijan. This is a complex project due to constraints like limited surface access, unstable soil conditions with artesian water, and the need to complete the work within a 5 week shutdown period to minimize metro disruptions. The chosen design solution involves installing a steel pipe jacking frame to excavate two large caverns and separate the existing lines while constructing new tunnels, with soil treatment to control geotechnical risks and impacts on existing structures.
Back analysis of high tunnel convergences in clayey marlsSYSTRA
Ganntas Tunnel is part of the modernization project of the
railway between Alger and Oran, in Algeria. In order to double
and rectify the existing line between El Affroun and Khémis
Miliana, the alignment foresees the excavation of a 7km-long
twin tunnel. The excavation works started in June 2011 with
the contractor CCECC, under the supervision of SYSTRA.
Excavation is driven in conventional method by hydraulic
hammer simultaneously on 8 different faces since excavation
was started also from a junction window towards the middle
of the tunnel. The minimum longitudinal distance to be
respected between two contiguous tunnel faces has been set
to 30m. The tunnel cross-section is a 70m² oval shaped profile,
temporary support consists of shotcrete, bolts and steel ribs.
A 30 to 50cm thick cast in situ concrete final lining is provided
as well.
When the tunnel reached a fault zone in soft clayey marls,
extreme squeezing occurred, works were stopped, and reprofiling
operations were carried out along more than 100m
tunnel length. To date, works proceed at slow rate since high
convergences are still monitored and completion of works is
not expected before December 2016.
Written by SYSTRA tunnel experts : MISANO Edoardo, COUBRAY Jean-Louis,
ESPINOZA CARMONA Fabiola
Assessing the interaction between the excavation of a large cavern and existi...SYSTRA
The Laboratoire Souterrain de Modane (LSM)
is an underground research laboratory located
in the Western Alps on the French – Italian
border. It is located in the middle of the
13km long Fréjus highway tunnel that links
Modane (France) to Bardonecchia (Italy) in
correspondence of the highest overburden
of 1800m. The LSM current activity is
mainly based on the investigations about
the dark matter and requires very sensitive
instrumentation which shall be protected from
cosmic rays. To comply with the new legislation
about safety in tunnels, the highway tunnels
2 owners agreed in 2007 the construction of
a parallel safety tunnel, at an average distance
of 50m from the existing tunnel and the
laboratory owner CNRS (Centre National de
recherche scientifique) also decided to extend
the existing laboratory with the construction of
a new 17000m3 cavern allowing the installation
of wider and more powerful instruments that
could increase chances of success of research.
Written by SYSTRA tunnel experts : SEMERARO Martino, MISANO Edoardo, SCHIVRE Magali, BOCHON Alain
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Dr. Amarjeet Singh
In the Ankeng Light Rail MRT system (ALRMS) project, the U7 box girder passes crossing the Erbads creek and needs a temporary supporting system for the construction work. In this study, three temporary shoring system options were proposed to be the construction method. The D-B Contractor, New Asia construction and Development Corporation, evaluated and selected the optimal choice, The Steel truss frame with supporting beams, to serve as the temporary supporting system. Compare the deflection of Δmax and Δactual, which are 1.609 cm and 1.59 cm, respectively. This result presented that the shoring system composed of the H912*302*18*37 supporting beams and steel truss frame had achieved outstanding performance and work to construct the U7 box girder. This paper presents how the three options are evaluated and the detailed construction processes along with the survey verification for the method.
Innovative solutions for complex geotechnical and tunnelling projects, april ...Dr Mazin Alhamrany
Dr Mazin Alhamrany has experience of more than 25 years in the field of Geotechnical and Tunneling Engineering. Dr Mazin is specialist in the field of applications of Finite Element Method for tackling soil-structure interaction problems. He is a highly experienced in 2D and 3D Finite Element Modelling, using advanced soil models, to simulate construction staging and soil-structure interaction to produce buildable economic designs and to assess the impact of carrying out engineering activities such as deep excavations on existing adjacent structures. We have a solid reputation in finding innovative solutions for complex geotechnical and tunneling projects.
Major issues to be considered for the successful application of unreinforced and steel fiber reinforced concrete (SFRC) tunnel final linings concepts include:
1) Application limits related to the geotechnical environment, seismic regime, and topography that must be determined based on safety and serviceability requirements.
2) Existing design codes and recommendations provide frameworks for evaluating the safety and serviceability of these lining concepts.
3) Case studies demonstrate that unreinforced and SFRC tunnel linings have been successfully used in tunnels up to 8km and 4.8km respectively, in various ground conditions.
1. The document examines the use of Tunnel Stability Factor (TSF) to estimate convergence and face stability in weak rock tunnels. TSF considers rock mass strength, overburden height, and tunnel size.
2. Parametric numerical analyses were conducted on 74 tunnels varying in size, depth, and rock mass quality. Dimensionless plots of plastic zone radius and convergence vs TSF showed good correlation despite varying conditions.
3. Guidelines for criticality of stability were developed based on convergence-to-radius ratio ranges associated with TSF levels, indicating severe squeezing for TSF < 0.2 and increased risk of collapse below 0.3 without support.
Separating underground metro lines under operation in BakuSYSTRA
The document discusses a project to separate the existing Green and Red underground metro lines in Baku, Azerbaijan. This is a complex project due to constraints like limited surface access, unstable soil conditions with artesian water, and the need to complete the work within a 5 week shutdown period to minimize metro disruptions. The chosen design solution involves installing a steel pipe jacking frame to excavate two large caverns and separate the existing lines while constructing new tunnels, with soil treatment to control geotechnical risks and impacts on existing structures.
Back analysis of high tunnel convergences in clayey marlsSYSTRA
Ganntas Tunnel is part of the modernization project of the
railway between Alger and Oran, in Algeria. In order to double
and rectify the existing line between El Affroun and Khémis
Miliana, the alignment foresees the excavation of a 7km-long
twin tunnel. The excavation works started in June 2011 with
the contractor CCECC, under the supervision of SYSTRA.
Excavation is driven in conventional method by hydraulic
hammer simultaneously on 8 different faces since excavation
was started also from a junction window towards the middle
of the tunnel. The minimum longitudinal distance to be
respected between two contiguous tunnel faces has been set
to 30m. The tunnel cross-section is a 70m² oval shaped profile,
temporary support consists of shotcrete, bolts and steel ribs.
A 30 to 50cm thick cast in situ concrete final lining is provided
as well.
When the tunnel reached a fault zone in soft clayey marls,
extreme squeezing occurred, works were stopped, and reprofiling
operations were carried out along more than 100m
tunnel length. To date, works proceed at slow rate since high
convergences are still monitored and completion of works is
not expected before December 2016.
Written by SYSTRA tunnel experts : MISANO Edoardo, COUBRAY Jean-Louis,
ESPINOZA CARMONA Fabiola
Assessing the interaction between the excavation of a large cavern and existi...SYSTRA
The Laboratoire Souterrain de Modane (LSM)
is an underground research laboratory located
in the Western Alps on the French – Italian
border. It is located in the middle of the
13km long Fréjus highway tunnel that links
Modane (France) to Bardonecchia (Italy) in
correspondence of the highest overburden
of 1800m. The LSM current activity is
mainly based on the investigations about
the dark matter and requires very sensitive
instrumentation which shall be protected from
cosmic rays. To comply with the new legislation
about safety in tunnels, the highway tunnels
2 owners agreed in 2007 the construction of
a parallel safety tunnel, at an average distance
of 50m from the existing tunnel and the
laboratory owner CNRS (Centre National de
recherche scientifique) also decided to extend
the existing laboratory with the construction of
a new 17000m3 cavern allowing the installation
of wider and more powerful instruments that
could increase chances of success of research.
Written by SYSTRA tunnel experts : SEMERARO Martino, MISANO Edoardo, SCHIVRE Magali, BOCHON Alain
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Dr. Amarjeet Singh
In the Ankeng Light Rail MRT system (ALRMS) project, the U7 box girder passes crossing the Erbads creek and needs a temporary supporting system for the construction work. In this study, three temporary shoring system options were proposed to be the construction method. The D-B Contractor, New Asia construction and Development Corporation, evaluated and selected the optimal choice, The Steel truss frame with supporting beams, to serve as the temporary supporting system. Compare the deflection of Δmax and Δactual, which are 1.609 cm and 1.59 cm, respectively. This result presented that the shoring system composed of the H912*302*18*37 supporting beams and steel truss frame had achieved outstanding performance and work to construct the U7 box girder. This paper presents how the three options are evaluated and the detailed construction processes along with the survey verification for the method.
Innovative solutions for complex geotechnical and tunnelling projects, april ...Dr Mazin Alhamrany
Dr Mazin Alhamrany has experience of more than 25 years in the field of Geotechnical and Tunneling Engineering. Dr Mazin is specialist in the field of applications of Finite Element Method for tackling soil-structure interaction problems. He is a highly experienced in 2D and 3D Finite Element Modelling, using advanced soil models, to simulate construction staging and soil-structure interaction to produce buildable economic designs and to assess the impact of carrying out engineering activities such as deep excavations on existing adjacent structures. We have a solid reputation in finding innovative solutions for complex geotechnical and tunneling projects.
Analysis of Shear Live Load Girder Distribution Factors in Integral bridges u...IJCMESJOURNAL
This paper studies the accuracy of AASHTO Standard Specifications and AASHTO LRFD design specifications girder distribution factors (GDFs) equations and their applicability to integral abutment bridges (IABs). A three-dimensional (3D) finite element (FE) model of the Scotch Road integral abutment bridge was developed using the finite element software ABAQUS/Cae. The bridge was subjected to vehicular live loading in single and multiple lanes in the FE model(s). The FE model was calibrated using load-displacement data obtained from field testing due to static truck loading. A comparison between the GDFs obtained from the FE models to those computed using both design codes was performed to evaluate their accuracy. A limited parametric study was conducted to evaluate crucial design parameters such as bridge deck thickness, span length, and piles lengths. The results showed that AASHTO LRFD GDFs equations are more conservative compared to those of AASHTO LFD equations in all cases. However, GDFs from the FE models compared more favorably to those calculated based on both design codes for the case single lane loading.
A Study on Application of Passive Control Techniques to RC Bridges through No...IRJET Journal
This document discusses a study on applying passive control techniques like tuned mass dampers (TMDs) to reduce vibrations in reinforced concrete (RC) bridges through nonlinear dynamic analysis. 3D models of box girder bridges with different spans were analyzed with and without TMDs using SAP2000 software. TMDs with mass ratios of 2%, 3%, and 4% were considered. Dynamic responses like natural period, base shear, displacements, and forces were compared for bridges with and without TMDs when subjected to ground motion records. Results showed that addition of TMDs decreased the natural frequency of bridges the most for the highest mass ratio of 2%, with decreases of up to 41.23% observed for different bridge
This document discusses geomechanical and geophysical investigations that can be conducted during the reconstruction of underground railway structures. It notes that many existing railway tunnels need repair due to defects like water leakage and structural deformation. During reconstruction, investigations allow assessing the interaction between the existing structure and surrounding rock mass, as well as the condition of the existing lining that will be dismantled. The document also discusses how the stress-strain state of underground structures changes over their long-term operation, and how a new equilibrium state is formed during reconstruction work. It proposes that additional geomechanical and geophysical data could allow reducing the standard 30% increase in assumed rock pressure load that is typically applied during tunnel reconstruction designs.
We apply state-of-the-art technology to obtain the most efficient design for geotechnical and tunnelling projects. We are specialist in the field of applications of 2D and 3D Finite Element Method for tackling complex soil-structure interaction problems.
We have experience of more than 35 years in the field of geotechnical and tunnel engineering, leading design teams for major challenging projects in The UK, Europe and Middle East.
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET Journal
The document discusses cracks in reinforced concrete bridge piers and abutments. It first provides background on the causes of cracking, including applied loads, restraint from volume changes, and drying shrinkage. It then presents a case study of a bridge exhibiting cracks in the abutments and approaches. The cracks are thought to be caused by movement of the abutments due to issues with surrounding soils. The document outlines various remedial measures that could address abutment movement and cracking, such as soil grouting, concrete jacketing, and epoxy injection. It concludes that abutment movement must be addressed to prevent further deterioration of the bridge structure.
The document discusses materials, construction methods, and sustainability aspects of a proposed flyover on the A406 road. Concrete will be used as the primary material due to its cost-effectiveness, durability, and faster construction using incremental launching. Measures will be taken to minimize waste, embodied energy, and carbon emissions from the project. These include using recycled aggregates, preventing deterioration through maintenance, and optimizing the design and procurement process. The total estimated budget for constructing the flyover is £35-40 million.
Heavy duty pavements are pavements subjected to the extremely heavy wheel loads associated with freight handling vehicles in industrial facilities, such as container terminals and warehouses. Heavy duty pavement need to handle many types of freight handling vehicles, such as forklifts, straddle carriers, gantry cranes and side loaders. Heavy duty pavement often deals with slow moving or even static traffic load with ultra high load magnitude. Furthermore, the load wandering for heavy duty pavement such as contain port or warehouse is more significant than normal highway or urban road pavement. The goal of pavement design is to determine the number, material composition and thickness of the different layers within a pavement structure required to accommodate a given loading regime.
This presentation summarizes research on using shape memory alloys (SMAs) for seismic retrofitting of reinforced concrete bridge columns. SMAs such as nickel-titanium can recover their original shape after deformation through heating. The presentation includes:
1) An overview of SMA properties and phase transformations between martensite and austenite phases.
2) A literature review of previous SMA confinement research.
3) Details of an experimental study comparing SMA spiral confinement to fiber reinforced polymer wrapping on concrete columns.
4) Test results found SMA confinement significantly improved ductility and drift capacity over FRP or unconfined columns.
5) Plans to further study SMA behavior
This document discusses the seismic design of foundations for the Rion Antirion Bridge in Greece. It describes the challenging soil and seismic conditions at the site, which required innovative foundation design. The foundations consist of large diameter caissons resting on top of reinforced natural ground, with steel tubular inclusions driven into the soil to increase its strength. Three of the four bridge piers use this reinforced foundation solution, while the fourth pier's caisson rests directly on a thick gravel layer without inclusions. The document outlines the design process and considerations, which aimed to ensure the foundations could adequately resist the large earthquake and ship impact loads expected at the seismically active site with poor soil conditions.
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
Implementation of 4 lane cable stayed road over bridge is nearing completion. It is felt that it could be a future fast track model for construction of ROB over busy railway yard in India
This document discusses pavement thickness design according to the New York State Department of Transportation guidelines. It provides an overview of flexible and rigid pavement design, including the factors considered such as traffic loading, material properties, and design methods. The key design methods covered are the ESAL-based method for projects over 1.5km in length, and the conventional method using thickness tables for shorter projects. An example calculation is provided to illustrate the ESAL method for determining equivalent single axle loads and selecting pavement thicknesses.
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
This paper titled Innovative solution for crossing larger spaces like railway yard has been presented in a seminar organised by CEAI at Kolkata on 03.06.2016
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
The document analyzes the effects of different national and international standard loadings on reinforced concrete bridge decks using finite element modeling. 36 bridge deck models of slab bridges and T-beam bridges were analyzed under loadings from IRC, AASHTO, and Eurocode standards. The results show maximum differences of 5-15% in deflection and bending moment between IRC loadings, and 5-17% difference for AASHTO loading compared to IRC. Eurocode loading causes increases of 1.7-1.8 times for slab bridges and 1.3-2.2 times for T-beam bridges over IRC due to higher load magnitudes. Transverse and torsional responses also vary significantly between standards.
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Pranamesh Chakraborty
This document provides an overview of the Ohio Department of Transportation's (ODOT) pavement design method. It discusses the basic factors considered in design, including serviceability, subgrade characterization, traffic loading, reliability, and drainage. The ODOT method is based on the American Association of State Highway and Transportation Officials (AASHTO) Guide, using a regression relationship between load cycles, pavement structural capacity, and performance. It considers traffic loads in terms of equivalent single axle loads and uses reliability levels depending on road importance. Rigid and flexible pavement designs are outlined, including parameters considered and thickness design processes. Limitations of the current ODOT method are also discussed.
Finite element analysis of innovative solutions of precast concrete beamcolum...Franco Bontempi
Especially to precast concrete structure connections are one of the most essential parts. Connections transfer forces between precast members, so the interaction between precast units is obtained. They are generally the
weakest link in the structure. An acceptable performance of precast concrete structure depends especially on the
appropriate kind of connections choice, adequate detailing of components and design of the connections is fundamental. It is interesting to study the behavior of connecting elements and to compare different solutions of ductile connections for precast concrete structures in case of horizontal applied force and vertical imposed displacement, as well as those produced by hazards situation, like that earthquake and explosion, whereby topics of structure robustness are carried out. The case of study is an innovative dissipative system of connection between precast concrete elements, usable for buildings and bridges, the investigation of these topics is carried out by F.E.A. by program DIANA with comparison with results obtained independently with ASTER.
Pavement materials and design in western australia by geoffrey cocksEngineers Australia
This document provides an overview of pavement design methods and considerations for different types of pavements including airports, container terminals, mines, public roads, and temporary haul roads. It discusses design approaches such as empirical and mechanistic methods. It also covers topics like vehicle loads, materials selection, and comparisons of different design standards. The key points are that pavement design must account for unique factors like wheel loads, tire pressures, and traffic patterns for different facility types, and that design methods have evolved over time but still have limitations.
Design And Analysis Of Precast Load Bearing Walls For Multi Storey Building ...IJMER
In the present scenario of construction industry, time of construction is very crucial factor.
Pre-cast construction is gaining significance in general and urban areas in particular. The precast
technology is a viable and alternative technique to reduce the construction time. G+11 storey live
project is taken for analysis and design with load bearing walls. Design of precast wall panels and
design of precast slabs is carried using Indian codes subjected to gravity and lateral loads (seismic and
wind). Connections of wall to wall, wall to slab and foundation beam to wall is designed. The structural
system consists of load bearing walls and one-way slabs for gravity and lateral loads have been taken
for analysis using ETABS. Various wall forces, displacements and moments have been worked out for
different load combinations. Data base is presented for the worst load combination
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...IAEME Publication
A country can achieve sustainable and rapid growth in all fields by improving its connectivity and transit systems. Connectivity of people to resources by improved transit mechanism results in improved living standards. Apart from other means, the major part of connectivity of any country is through road systems. Well designed and maintained pavements provide better and long lasting service. In India, all the major road systems are designed as flexible pavements only, because of their ease of construction and less time it takes to be opened to traffic operations. The major problem with flexible pavements is their design life and high maintenance costs. Also, globally reducing petrol reserves, which are used for bitumen and asphalt production are also increasing the need for alternatives. To tackle these problems, rigid pavements can be constructed. Although the cost of construction of rigid pavements is high, its long life, high load carrying capabilities and low maintenance cost will balance the initial cost aspect. Recently, many studies are being conducted on different pozzolanic admixtures which can be used as partial replacement of cement in rigid pavements, thereby reducing its cost and enhancing properties of the mix. Here, an attempt is made to reduce the construction cost of rigid pavements by incorporating Vitrified Polish Waste (VPW) as partial cement replacement in proportions of 5% for M40 grade concrete. Further, to enhance flexural properties of pavement, Recron fibre is added to optimum VPW in increments of 0.1%, then after C.C pavement is designed for two lane two way national highway and cost benefit analysis is performed.
The Velveteen Playboys are an internationally diverse band known for their high energy live performances blending rock, pop and swing. They feature highly talented individual musicians including Paul Souza, a throwback showman with powerful vocals; Robert Douglas Gay, a virtuosic sax player who can conjure emotions with a single note; bassist Lenny Bradford, a master bluesman who provides the band's pulse; guitarist Mike Null, a bluesman whose intricate licks enhance each song; and drummer Anthony Steele, an acrobatic drummer with international renown.
El documento critica la situación de la educación en el país, señalando que no es necesario destinar el 4% del PIB a educación mientras los niños toman clases en malas condiciones e incluso se intoxican por el desayuno escolar. También critica la corrupción de funcionarios que se roban el dinero público y cómo esto ha llevado al país a ser un desastre, a pesar del crecimiento económico reportado.
Analysis of Shear Live Load Girder Distribution Factors in Integral bridges u...IJCMESJOURNAL
This paper studies the accuracy of AASHTO Standard Specifications and AASHTO LRFD design specifications girder distribution factors (GDFs) equations and their applicability to integral abutment bridges (IABs). A three-dimensional (3D) finite element (FE) model of the Scotch Road integral abutment bridge was developed using the finite element software ABAQUS/Cae. The bridge was subjected to vehicular live loading in single and multiple lanes in the FE model(s). The FE model was calibrated using load-displacement data obtained from field testing due to static truck loading. A comparison between the GDFs obtained from the FE models to those computed using both design codes was performed to evaluate their accuracy. A limited parametric study was conducted to evaluate crucial design parameters such as bridge deck thickness, span length, and piles lengths. The results showed that AASHTO LRFD GDFs equations are more conservative compared to those of AASHTO LFD equations in all cases. However, GDFs from the FE models compared more favorably to those calculated based on both design codes for the case single lane loading.
A Study on Application of Passive Control Techniques to RC Bridges through No...IRJET Journal
This document discusses a study on applying passive control techniques like tuned mass dampers (TMDs) to reduce vibrations in reinforced concrete (RC) bridges through nonlinear dynamic analysis. 3D models of box girder bridges with different spans were analyzed with and without TMDs using SAP2000 software. TMDs with mass ratios of 2%, 3%, and 4% were considered. Dynamic responses like natural period, base shear, displacements, and forces were compared for bridges with and without TMDs when subjected to ground motion records. Results showed that addition of TMDs decreased the natural frequency of bridges the most for the highest mass ratio of 2%, with decreases of up to 41.23% observed for different bridge
This document discusses geomechanical and geophysical investigations that can be conducted during the reconstruction of underground railway structures. It notes that many existing railway tunnels need repair due to defects like water leakage and structural deformation. During reconstruction, investigations allow assessing the interaction between the existing structure and surrounding rock mass, as well as the condition of the existing lining that will be dismantled. The document also discusses how the stress-strain state of underground structures changes over their long-term operation, and how a new equilibrium state is formed during reconstruction work. It proposes that additional geomechanical and geophysical data could allow reducing the standard 30% increase in assumed rock pressure load that is typically applied during tunnel reconstruction designs.
We apply state-of-the-art technology to obtain the most efficient design for geotechnical and tunnelling projects. We are specialist in the field of applications of 2D and 3D Finite Element Method for tackling complex soil-structure interaction problems.
We have experience of more than 35 years in the field of geotechnical and tunnel engineering, leading design teams for major challenging projects in The UK, Europe and Middle East.
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET Journal
The document discusses cracks in reinforced concrete bridge piers and abutments. It first provides background on the causes of cracking, including applied loads, restraint from volume changes, and drying shrinkage. It then presents a case study of a bridge exhibiting cracks in the abutments and approaches. The cracks are thought to be caused by movement of the abutments due to issues with surrounding soils. The document outlines various remedial measures that could address abutment movement and cracking, such as soil grouting, concrete jacketing, and epoxy injection. It concludes that abutment movement must be addressed to prevent further deterioration of the bridge structure.
The document discusses materials, construction methods, and sustainability aspects of a proposed flyover on the A406 road. Concrete will be used as the primary material due to its cost-effectiveness, durability, and faster construction using incremental launching. Measures will be taken to minimize waste, embodied energy, and carbon emissions from the project. These include using recycled aggregates, preventing deterioration through maintenance, and optimizing the design and procurement process. The total estimated budget for constructing the flyover is £35-40 million.
Heavy duty pavements are pavements subjected to the extremely heavy wheel loads associated with freight handling vehicles in industrial facilities, such as container terminals and warehouses. Heavy duty pavement need to handle many types of freight handling vehicles, such as forklifts, straddle carriers, gantry cranes and side loaders. Heavy duty pavement often deals with slow moving or even static traffic load with ultra high load magnitude. Furthermore, the load wandering for heavy duty pavement such as contain port or warehouse is more significant than normal highway or urban road pavement. The goal of pavement design is to determine the number, material composition and thickness of the different layers within a pavement structure required to accommodate a given loading regime.
This presentation summarizes research on using shape memory alloys (SMAs) for seismic retrofitting of reinforced concrete bridge columns. SMAs such as nickel-titanium can recover their original shape after deformation through heating. The presentation includes:
1) An overview of SMA properties and phase transformations between martensite and austenite phases.
2) A literature review of previous SMA confinement research.
3) Details of an experimental study comparing SMA spiral confinement to fiber reinforced polymer wrapping on concrete columns.
4) Test results found SMA confinement significantly improved ductility and drift capacity over FRP or unconfined columns.
5) Plans to further study SMA behavior
This document discusses the seismic design of foundations for the Rion Antirion Bridge in Greece. It describes the challenging soil and seismic conditions at the site, which required innovative foundation design. The foundations consist of large diameter caissons resting on top of reinforced natural ground, with steel tubular inclusions driven into the soil to increase its strength. Three of the four bridge piers use this reinforced foundation solution, while the fourth pier's caisson rests directly on a thick gravel layer without inclusions. The document outlines the design process and considerations, which aimed to ensure the foundations could adequately resist the large earthquake and ship impact loads expected at the seismically active site with poor soil conditions.
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
Implementation of 4 lane cable stayed road over bridge is nearing completion. It is felt that it could be a future fast track model for construction of ROB over busy railway yard in India
This document discusses pavement thickness design according to the New York State Department of Transportation guidelines. It provides an overview of flexible and rigid pavement design, including the factors considered such as traffic loading, material properties, and design methods. The key design methods covered are the ESAL-based method for projects over 1.5km in length, and the conventional method using thickness tables for shorter projects. An example calculation is provided to illustrate the ESAL method for determining equivalent single axle loads and selecting pavement thicknesses.
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
This paper titled Innovative solution for crossing larger spaces like railway yard has been presented in a seminar organised by CEAI at Kolkata on 03.06.2016
Analysis of rc bridge decks for selected national a nd internationalstandard ...eSAT Journals
The document analyzes the effects of different national and international standard loadings on reinforced concrete bridge decks using finite element modeling. 36 bridge deck models of slab bridges and T-beam bridges were analyzed under loadings from IRC, AASHTO, and Eurocode standards. The results show maximum differences of 5-15% in deflection and bending moment between IRC loadings, and 5-17% difference for AASHTO loading compared to IRC. Eurocode loading causes increases of 1.7-1.8 times for slab bridges and 1.3-2.2 times for T-beam bridges over IRC due to higher load magnitudes. Transverse and torsional responses also vary significantly between standards.
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Pranamesh Chakraborty
This document provides an overview of the Ohio Department of Transportation's (ODOT) pavement design method. It discusses the basic factors considered in design, including serviceability, subgrade characterization, traffic loading, reliability, and drainage. The ODOT method is based on the American Association of State Highway and Transportation Officials (AASHTO) Guide, using a regression relationship between load cycles, pavement structural capacity, and performance. It considers traffic loads in terms of equivalent single axle loads and uses reliability levels depending on road importance. Rigid and flexible pavement designs are outlined, including parameters considered and thickness design processes. Limitations of the current ODOT method are also discussed.
Finite element analysis of innovative solutions of precast concrete beamcolum...Franco Bontempi
Especially to precast concrete structure connections are one of the most essential parts. Connections transfer forces between precast members, so the interaction between precast units is obtained. They are generally the
weakest link in the structure. An acceptable performance of precast concrete structure depends especially on the
appropriate kind of connections choice, adequate detailing of components and design of the connections is fundamental. It is interesting to study the behavior of connecting elements and to compare different solutions of ductile connections for precast concrete structures in case of horizontal applied force and vertical imposed displacement, as well as those produced by hazards situation, like that earthquake and explosion, whereby topics of structure robustness are carried out. The case of study is an innovative dissipative system of connection between precast concrete elements, usable for buildings and bridges, the investigation of these topics is carried out by F.E.A. by program DIANA with comparison with results obtained independently with ASTER.
Pavement materials and design in western australia by geoffrey cocksEngineers Australia
This document provides an overview of pavement design methods and considerations for different types of pavements including airports, container terminals, mines, public roads, and temporary haul roads. It discusses design approaches such as empirical and mechanistic methods. It also covers topics like vehicle loads, materials selection, and comparisons of different design standards. The key points are that pavement design must account for unique factors like wheel loads, tire pressures, and traffic patterns for different facility types, and that design methods have evolved over time but still have limitations.
Design And Analysis Of Precast Load Bearing Walls For Multi Storey Building ...IJMER
In the present scenario of construction industry, time of construction is very crucial factor.
Pre-cast construction is gaining significance in general and urban areas in particular. The precast
technology is a viable and alternative technique to reduce the construction time. G+11 storey live
project is taken for analysis and design with load bearing walls. Design of precast wall panels and
design of precast slabs is carried using Indian codes subjected to gravity and lateral loads (seismic and
wind). Connections of wall to wall, wall to slab and foundation beam to wall is designed. The structural
system consists of load bearing walls and one-way slabs for gravity and lateral loads have been taken
for analysis using ETABS. Various wall forces, displacements and moments have been worked out for
different load combinations. Data base is presented for the worst load combination
DESIGN OF RIGID PAVEMENT AND ITS COST-BENEFIT ANALYSIS BY USAGE OF VITRIFIED ...IAEME Publication
A country can achieve sustainable and rapid growth in all fields by improving its connectivity and transit systems. Connectivity of people to resources by improved transit mechanism results in improved living standards. Apart from other means, the major part of connectivity of any country is through road systems. Well designed and maintained pavements provide better and long lasting service. In India, all the major road systems are designed as flexible pavements only, because of their ease of construction and less time it takes to be opened to traffic operations. The major problem with flexible pavements is their design life and high maintenance costs. Also, globally reducing petrol reserves, which are used for bitumen and asphalt production are also increasing the need for alternatives. To tackle these problems, rigid pavements can be constructed. Although the cost of construction of rigid pavements is high, its long life, high load carrying capabilities and low maintenance cost will balance the initial cost aspect. Recently, many studies are being conducted on different pozzolanic admixtures which can be used as partial replacement of cement in rigid pavements, thereby reducing its cost and enhancing properties of the mix. Here, an attempt is made to reduce the construction cost of rigid pavements by incorporating Vitrified Polish Waste (VPW) as partial cement replacement in proportions of 5% for M40 grade concrete. Further, to enhance flexural properties of pavement, Recron fibre is added to optimum VPW in increments of 0.1%, then after C.C pavement is designed for two lane two way national highway and cost benefit analysis is performed.
The Velveteen Playboys are an internationally diverse band known for their high energy live performances blending rock, pop and swing. They feature highly talented individual musicians including Paul Souza, a throwback showman with powerful vocals; Robert Douglas Gay, a virtuosic sax player who can conjure emotions with a single note; bassist Lenny Bradford, a master bluesman who provides the band's pulse; guitarist Mike Null, a bluesman whose intricate licks enhance each song; and drummer Anthony Steele, an acrobatic drummer with international renown.
El documento critica la situación de la educación en el país, señalando que no es necesario destinar el 4% del PIB a educación mientras los niños toman clases en malas condiciones e incluso se intoxican por el desayuno escolar. También critica la corrupción de funcionarios que se roban el dinero público y cómo esto ha llevado al país a ser un desastre, a pesar del crecimiento económico reportado.
This document lists the names and blog URLs of two students, Diego Alejandro Rodríguez González and Daniel Rodríguez Maya, as well as the name and blog URL of their professor John Caraballo. It provides contact information for the students and teacher in relation to a class.
Incorporating Life-cycle Price Modelling into Pharmaceutical Cost-effectivene...Office of Health Economics
In this presentation, OHE's Pistollato explains why it is important to consider price changes after marketing in CEA analysis and presents an approach for doing so.
The document outlines different types of ambush drills that a military section may use when encountering the enemy in close jungle country. It describes immediate ambush drills when contact is made with the enemy, encounter drills for when engaged from the front, and counter ambush drills for if a section falls into an enemy ambush. Key factors for success in these drills are listed as aggressiveness, speed, discipline and common sense. The document provides details on the execution of each type of drill and subsequent actions after contact with the enemy.
The India Gaming Opportunity | Rohith BhatJessica Tams
Delivered at Casual Connect Asia 2016
Smartphones and India have become synonymous in the recent past. India is one of the fastest growing smartphone markets in the world. Early indicators suggest that India’s mobile games market will triple in the next few years, reaching $1.2 billion by the end of 2018. This session will give the audience an insight into the current state of affairs and the immediate opportunities in the mobile gaming space.
The document discusses the games industry and the major players within it, including console manufacturers Nintendo, Sony, and Microsoft, as well as publishers and developers. It covers Nintendo's focus on innovation and accessibility with the Wii, Sony and Microsoft's focus on graphical power and online experiences with the PlayStation 3 and Xbox 360, and the strategies of maintaining existing markets while expanding to new audiences.
The University of Iowa prohibits discrimination in employment, educational programs, and activities on various bases. The John Pappajohn Entrepreneurial Center (JPEC) is a collaboration among various colleges at the University of Iowa that offers three hands-on programs to students: the Entrepreneurial Management Institute (EMI), Iowa Innovation Associates (IIA), and Institute for International Business (IIB). These programs allow students to apply classroom knowledge, make professional connections, and research solutions to Iowa business challenges.
El documento critica la situación de la educación en el país, señalando que no es necesario destinar el 4% del PIB a educación mientras los niños toman clases en malas condiciones e incluso se intoxican por el desayuno escolar. También denuncia actos de corrupción por parte de funcionarios públicos como Melanio Paredes y Reinaldo Pared, y critica que el gobernador Valdez Albizu afirme que hubo un crecimiento económico del 7.8% cuando en realidad hay problemas como el aumento de la delincuencia y
The document provides an analysis of the 7th generation game console industry, focusing on the major players Xbox 360, PlayStation 3, and Nintendo Wii between 2005-2013. It summarizes that:
1) Nintendo succeeded through a differentiated strategy targeting casual gamers with its low-cost and motion-sensing Wii console, outselling rivals.
2) Both Microsoft and Sony focused on hardcore gamers but struggled with high production costs, though built strong brands and game libraries.
3) The industry now faces challenges from mobile/social gaming, but console gaming remains lucrative with new revenue models and popular franchises.
This document summarizes tunnelling projects and experiences in Greece from the early 1990s to present. It discusses the Athens Metro and use of microtunnelling and jet grouting to construct underground stations. It also describes the Egnatia Motorway project and challenges with Tunnel S3. Specifically, it examined over 100km of railway tunnels and nearly 350km of motorway and railway tunnels constructed. Lessons included using a Geological Strength Index and Tunnel Stability Factor to assess tunnel conditions. Jet grouting was used to improve weak rock and prevent face collapses during the Athens Metro project.
Monte Carlo simulation for seismic analysis of a long span suspension bridgeFranco Bontempi
This document discusses using Monte Carlo simulation to conduct seismic analysis of a long span suspension bridge that considers uncertainties. It describes generating artificial accelerograms compatible with a design response spectrum to represent seismic inputs for the probabilistic analysis. The bridge structure analyzed is based on the 1992 design for the Messina Strait Bridge in Italy, with key dimensions and material properties provided. The document outlines challenges in deterministic seismic analysis for such complex structures and the need for probabilistic methods to account for uncertainties.
Monte Carlo simulation for seismic analysis of a long span suspension bridgeStroNGER2012
This document discusses using Monte Carlo simulation to conduct seismic analysis of a long span suspension bridge that considers uncertainties. It describes generating artificial accelerograms compatible with a design response spectrum to define seismic scenarios for the probabilistic analysis. The bridge structure analyzed has a main span of 3300 meters and is based on a proposed design for the Messina Strait Bridge in Italy. The analysis is performed using a 3D finite element model developed in ADINA software along with a custom FORTRAN program for the Monte Carlo simulations. Results are presented as average displacements and stresses along with their variances to account for uncertainties.
This document discusses the effects of different concrete classes on the cost of transportation structures. It analyzes three types of reinforced concrete structures: retaining walls, culverts, and bridges. Calculations are made for each structure using concrete classes ranging from C20 to C45 to determine the impact of concrete strength on costs. Quantities of concrete are calculated for each structure and costs are compared across different classes. The goal is to reveal the real cost variations that occur when each structure is built using different concrete strengths.
This document presents the results of a parametric study to optimize the design of post-tensioned concrete box-girder pedestrian bridges with main spans ranging from 30 to 60 meters. An optimization algorithm called SAMO2 was used to minimize the cost by varying 33 design variables related to geometry, materials, and construction. The optimal solutions showed that depth and number of prestressing strands correlated with main span length, while slab thicknesses generally took minimum allowed values. Increasing the main span by 1 meter on average increased total cost by 6.38 euros per square meter. Concrete strength varied between 35 to 55 MPa but tended to increase with longer spans.
The purpose of this paper is to present from the scientific point of view the main ideas and the consequent logic which form the basis of the design and of the definition of the performances levels for the Messina Strait Bridge. With the general philosophy of design, one canalizes all the design activities toward specific goals. With the explicit definition of the performances one must reach a delicate balance between the demand for the construction of an appropriate, possibly outstandingly, structure, and the feasibility, both from the engineering and from the economic point of view. Together with the strategy necessary to originate the design of this exceptional bridge, the essential role of the structural analysis supporting the decisional process is enlightened.
Paper-11th ACUUS International ConferenceMeliti Pappa
This document compares two common methods for constructing underground car parks - the "cut-and-cover" method and the "room-and-pillar" method from mining. It analyzes the construction costs of three underground car parks built using the cut-and-cover method. Concrete works accounted for about 30% of costs, while electrical/mechanical works were 20% of costs. Location factors like proximity to buildings and geological conditions strongly influence costs. Excavating in hard rock or supporting surrounding structures increased expenses.
The document summarizes the construction of the Votonosi Bridge in Greece. Some key points:
- The bridge forms part of the Egnatia motorway project and has a main span of 230m, the longest for balanced cantilever bridges in Greece.
- It consists of two independent box girder decks supported by tall concrete piers founded on rock sockets up to 25m deep.
- Construction began in 2000 and was completed in 2005, utilizing cantilever construction and temporary supports during erection. Challenges included the remote location and adverse winter weather.
This document discusses the foundation design processes for two major bridge projects - the Vasco da Gama Bridge in Lisbon, Portugal and the Rion-Antirion Bridge in Greece. For the Vasco da Gama Bridge, the foundations consisted of vertical large diameter bored concrete piles due to favorable soil conditions and design requirements. For the Rion-Antirion Bridge, the soil conditions were less favorable so an innovative foundation concept was developed and implemented, which allowed for some permanent displacement under seismic loading. The additional time for design of the Rion-Antirion Bridge was crucial to developing and validating this new foundation solution.
Analysis of stability of rock column between cut & cover Metro Station and NA...IRJET Journal
This document analyzes the stability of the rock column between an underground metro station constructed using the cut-and-cover method and a platform tunnel constructed using the NATM method. It studies the impact of varying the width of the rock column between 2.6m and 5m based on updated geotechnical information. Finite element analysis is conducted to model the soil-structure interaction and evaluate stresses around the tunnel opening to check stability during excavation. The analysis considers parameters like lateral earth pressure coefficients, Mohr-Coulomb soil modeling, water table level, secant pile retaining system geometry and material properties.
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
One of the most important factors influencing the decision whether and how a tunnel is to be built are the estimated time and costs of construction. This study is based on construction time analysis for different steps in drill-and-blast method of hydro power tunnel excavation in working phase of 6.256,00 meters of tunnels which have different diameters varying from 4,20 to 7,60. There are made 737 field measurements and it is seen that many of the machinery and workmanship productions rates per unit time are significantly lower, varying from 35% to 50%, of that defined in their technical specifications, measurements indicate that highest performance is reached in 7,60m diameter tunnel excavation. It is believed that these data will be helpful for planning and management process of tunnel construction projects, especially those planned to be built in Albania where labor market carries similar features.
paper presented at:
BRIDGE ENGINEERING – Challenges in the 21st Century
1-3 November 2006, Hong Kong
The International Conference on Bridge Engineering – Challenges in the 21st Century is aimed at providing a forum
for dissemination of technical advances as well as exchanges of experiences and ideas among engineers, architects,
academics, researchers, developers, regulatory agents and project managers at an international level. A number of
keynote lectures presented by world renowned experts and parallel sessions will be organised to address both the
recent developments and experiences on a wide range of technical, social, environmental, financial and management
topics in the bridge engineering and construction.
Konstantinos E. Seferoglou is a senior civil engineer and geotechnical expert with over 35 years of experience leading complex infrastructure projects including tunnels, bridges, and retaining structures. He has extensive experience in geotechnical consulting, design, and construction management for transportation and tunnel projects. Currently he works as a geotechnical expert for Qatar Rail on the Doha Metro project reviewing tunnel and excavation designs.
DYNAMIC ANALYSIS OF CONCRETE GIRDER BRIDGES UNDER STRONG EARTHQUAKES: THE EFF...IAEME Publication
This paper presents the dynamic analysis of concrete girder bridges taking into account the effect of collision on parapet wall. In addition, adopting of seismic isolation rubber on pier structure and wing wall on parapet were analyzed. Two spans concrete girder bridges with variation of gap were examined in theoretically by 3D FEM model of ABAQUS. The abutment was simplified by parapet wall which was modeled by 3D reinforced concrete structure. In order to examine the seismic behavior of bridge, six different inputs of seismic ground accelerations were applied at footing of pier structure.
Innovative solutions for complex geotechnical and tunnelling projects, april ...Dr Mazin Alhamrany
Dr Mazin Alhamrany has experience of more than 25 years in the field of Geotechnical and Tunneling Engineering. Dr Mazin is specialist in the field of applications of Finite Element Method for tackling complex soil-structure interaction problems.
This document discusses the challenges of building a 390m bridge over an active landslide in southern Greece. An instrumentation and monitoring system was set up to track the landslide's movement, which averages 1.5-2.0mm/month but increases during winter rains. Temporary infrastructure like steel towers up to 60m high were constructed on pile foundations within the sliding mass to support arch assembly. Monitoring showed movement varies by location from 13-40mm/year depending on depth and bedrock slope. The bridge design allowed for 30mm/year transverse and 15mm/year longitudinal differential movement during the two-year construction period.
This document discusses the challenges of building a bridge over an active landslide in Greece. An arched steel bridge was designed to span the moving landslide. Temporary infrastructure projects like tower foundations and bridges were necessary during construction. An extensive instrumentation, monitoring, and early warning system was implemented to track landslide movement rates up to 30mm/month. Foundation designs for temporary projects considered landslide movements, using 3D and 2D modeling to optimize pile reinforcement. Close monitoring ensured safety during the two-year construction period over the active landslide.
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...IJERA Editor
In the recent decades, the construction of tunnels has been increased vastly in all over the world. Despite all the
efforts have been put into the geotechnical investigation, determining the precise and reliable design parameters
is a difficult task to accomplish. Therefore, using back analysis techniques to modify geotechnical parameters
and optimize the design of initial and final supports is more effective and even less expensive nowadays. In this
paper, the results of monitoring and instrumentation of Isfahan subway have been investigated. Moreover, two
important parameters for stability analysis, the modulus of elasticity of rock mass and the coefficient of the
lateral earth pressure, are modified based on the measured convergence by using the direct method. Results show
the Young modulus of rock mass and the lateral earth coefficient are less than the initial values from
geotechnical investigation.
Rates of Soft Ground Tunneling in Vicinity of Existing StructuresIJAEMSJORNAL
Soft ground tunneling in the vicinity of existing structures is a major challenge to tunneling engineers. Tunneling works cause inevitable ground movements that may lead to unrecoverable damages to adjacent structures. Tunneling rates significantly affect such risks. However, a guideline that determines appropriate tunneling rates and accounts for the effects of tunneling on the structures existing in the vicinity is not available. Tunneling records in terms of TBM advance speed (AS), utilization factor (U), and advance rate (AR) for tunnels constructed without causing significant risks on the existing structures are presented in the paper.These records are discussed for different types of existing structures.Ranges of these records for tunneling without causing detrimental effects on different types existing structures are recommended.Useful observations are also made on the variation of these records with the ground type and composition and the precautions to be adopted to mitigate the tunneling risks on existing structures.
Similar to Paper European Conference Athens 2011 (20)
Rates of Soft Ground Tunneling in Vicinity of Existing Structures
Paper European Conference Athens 2011
1. Tunnelling Projects in Greece, Challenges, Gained
Experiences and Achievements
Tunnels en Grèce, Défis, Expériences acquises et
Réalisationsitre
Ilias K. MICHALIS1
Tunnel and Geotechnical Expert N.T.U.A., MSc, DIC
ABSTRACT
Tunnelling in Greece has shown a remarkable development in the last 20 years and this is due to the real “cosmogony”, which
was occurred during the aforesaid period, in the infrastructure projects. Indeed, since the early 1990’s and until even recently, a
very large number of motorway and railway projects (i.e. Egnatia Motorway, Motorways Concession Projects, Athens and Thes-
saloniki Metros, ERGOSE railway lines, etc.), either were fully constructed or are in the stage of their completion. As a conse-
quence, significant design and construction experiences, which are related directly to the tunnels’ excavation schemes, primary
support measures and different types of final lining (i.e reinforced, lightly reinforced or unreinforced) in a wide variety of geo-
logical / geotechnical conditions, were gained. The obvious merit from all these experiences, is that if they will be applied within
reasonable frameworks of application, can offer significantly to the necessary tunnels designs’ optimisations and to the rationali-
sation of the corresponding tunnels’ construction costs. The future of tunnelling in Greece seems promising through new financ-
ing models (i.e. concession agreements), since one of the obvious mid-term “antidote” to the economic recession is the invest-
ment to the construction of new but necessary infrastructure projects. Some of these new projects are the extensions of Athens
and Thessaloniki Metros, new urban and suburban motorways and new railway lines.
RÉSUMÉ
Les tunnels en Grèce ont connu un développement remarquable pendant les 20 dernières années grâce à la «cosmogonie» réelle,
qui a été produite au cours de la période susmentionnée, aux projets d’infrastructure. En effet, depuis le début des années 1990 et
jusqu'à récemment, un très grand nombre des projets autoroutiers et ferroviaires (p.ex. Egnatia Autoroute, Autoroutes pour les
Projets de Concession, Métros d’Athènes et Thessalonique, voies ferrées pour ERGOSE etc.) ont été entièrement construits ou
sont en voie d’achèvement. En conséquence l’expérience acquise au niveau étude et construction des tunnels sur des sujets de
soutènement provisoire et des différents types de revêtement définitif (p.ex. béton renforcé, béton peu renforcé ou béton non ar-
mé) pour une grande variété de conditions géologiques / géotechniques a été très importante. Le mérite évident de toute cette ex-
périence, c’est qu’elle peut être appliquée, dans un cadre raisonnable, pour l’optimisation des études nécessaires du tunnel et à la
rationalisation du coût constructif des tunnels correspondants. L'avenir des tunnels en Grèce semble prometteur par l’application
des nouveaux modèles de financement (p.ex. conventions de concession), puisque l’investissement à la construction des nou-
veaux mais plutôt nécessaires projets d'infrastructure est considéré comme un "antidote" évident à la récession économique. Cer-
tains de ces nouveaux projets d’infrastructure sont les extensions du Métro d'Athènes et de Thessalonique, les nouvelles auto-
routes urbaines et banlieues et les nouvelles lignes de chemin de fer.
Keywords: tunnelling, metros, geological strength index, tunnel stability factor, micro-tunnelling, jet grouting, weak rock, final
lining
1
Corresponding Author.
2. 1 RECENT HISTORICAL BACKGROUND
OF TRANSPORTATION TUNNELLING
IN GREECE
Since the early 1990s, numerous challenges in
designing and completing successfully the con-
struction of a significant number of large scale
infrastructure projects have been faced in Greece.
In these projects, tunnelling was a significant
part, mostly related to real challenging engineer-
ing problems. The solutions of these problems
demanded the combination of the detailed
knowledge of the in-situ geological and geotech-
nical conditions, with the implementation of in-
novative design ideas and construction tech-
niques.
The most significant infrastructure projects of
the last 20 years in Greece, which either were
successfully constructed, or presently are at the
stage of their completion are:
Egnatia Motorway It is a 670 km motorway,
connecting the north western coastline of
Greece, at Igoumenitsa port, with the north-
eastern borders with Turkey, at Alexan-
droupolis city (Figure 1).
Attiki Odos. It is the modern northern pe-
ripheral motorway of the city of Athens,
with a total length of 65km, serving the
scope of the main connection of Attika re-
gion with the international airport Eleft-
herios Venizelos (Figure 2).
Athens Metro. The metro network is pres-
ently consisting of three main fully operat-
ing lines, with a total length of 51km. Sig-
nificant network’s extensions are currently
under construction.
Thessaloniki Metro. The project is under
construction and is comprised of one line,
having a length of 9.6km, which connects
the west and the east edges of the second
largest city of Greece.
Concession Highways. They are sections of
already existing and new highways having
1415km of alignment’s total length, with
50% of their aforesaid length constructed
and in full operation.
High speed railway axis. It consists of
500km new alignment of the main south to
north railway axis Patras – Athens – Thessa-
loniki.
Table 1 summarises all the previously men-
tioned infrastructure projects, by presenting the
total tunnels’ lengths, which correspond to each
one of these projects. In conclusion, the total
length of the motorway and railway tunnels,
which were constructed in the last 20 years in
Greece, is 347.5km. This indisputable engineer-
ing achievement classifies Greece as the fourth
country (after Italy, Austria and Germany),
among all the countries of the European Union,
on the basis of the existing motorway tunnels
having length greater than 500m [1].
Figure 1. Egnatia Motorway axis.
Figure 2. Attiki Odos. Athens northern peripheral motorway.
3. Table 1. Tunnels’ lengths of the recent major infrastructure
projects in Greece
2 GAINED TUNNELLING DESIGN
EXPERIENCES
2.1 General
The significant number of the recent tunnelling
projects in Greece created the basis on which
new tunnel design methodologies were devel-
oped. These methodologies aimed to provide
technically sound solutions to numerous chal-
lenging engineering problems, which were re-
lated not only to the better understanding of the
adverse and complex geological and geotechnical
conditions of Greece, but also to the need of con-
trolling sufficiently and economically the inher-
ent geotechnical risk factor, in complicated un-
derground projects.
Such design methodologies or tools are the
Geological Strength Index (GSI) [2], [3] and the
Tunnel Stability Factor (TSF) [4]. The GSI is an
evolving rock mass rating system, aiming to the
derivation of reliable rock mass strength and de-
formability input parameters for the numerical
analyses or closed form solutions of tunnelling
problems. The TSF is an engineering index for
the qualitative and quantitative assessments of
tunnel stability problems, continuously being
calibrated on the basis of reliable data from re-
corded tunnels’ behaviours.
2.2 Geological Strength Index
Since 1998, Evert Hoek and Paul Marinos, deal-
ing with incredibly difficult geo- materials, en-
countered in tunnelling projects in Greece, devel-
oped the GSI system, scoping to the possibility of
rating geologically, even poor quality heteroge-
neous rock masses. Typical GSI charts (among
others), which can be used for the rating purposes
of rock masses are presented in Figures 3 and 4.
GSI system places greater emphasis on basic
geological observations of rock mass characteris-
tics; reflects the rock mass structure and geologi-
cal history and has been developed specifically
for the estimation of rock mass engineering
properties, rather than for providing in direct
way guidelines for tunnels’ primary support
measures and final lining reinforcement.
The “heart” of the GSI classification is a care-
ful engineering geological description of the rock
mass, which is essentially qualitative and com-
bines the two fundamental parameters of the geo-
logical process: (a) the blockiness and (b) the
condition of discontinuities of the mass. It is thus
a geologically sound index that is estimated on
the basis of available charts (Figures 3, 4), after
careful visual examination of the rock masses,
exposed in natural outcrops and man-made exca-
vations, such as road cuts and tunnel faces.
In dealing with specific rock masses, it is
suggested that the selection of the appropriate
case in the available GSI charts should not be
limited to the visual similarity with the sketches
of the structure of the rock mass, as they appear
in the charts. The associated descriptions must
also be read carefully, so that the most suitable
structure is chosen. The most appropriate case
may well lie at some intermediate point between
the limited number of sketches or description in-
cluded in the charts.
Excavated slope and tunnel faces are probably
the most reliable source of information for GSI
estimates, provided that these faces are reasona-
bly close to and in the same rock mass as the ex-
cavation under investigation.
The assessment of GSI on the basis of the
visual inspection of available borehole core sam-
ples must be made always with certain caution,
since the borehole drilling techniques may affect
4. the final recovered quality of the rock masses,
guiding their rating process to unnecessary un-
derestimations. Additionally, it is pointed out that
although borehole core samples are the best
source of data at depth, these one dimensional in-
formation (provided by the cores) must be always
extrapolated to the three dimensional in-situ rock
mass conditions. Without any doubt, the success-
ful rating process of rock masses with the GSI
system, demands sound knowledge and previous
experience.
For stability analysis of a slope, the evalua-
tion is based on the rock mass through which it is
anticipated that a potential failure plane could
pass. The estimation of GSI values in these cases
requires considerable judgment, particularly
when the failure plane can pass through several
zones having shearing characteristics of different
quality. It is noted that mean values may not be
appropriate in the aforesaid case.
For tunnels, the index should be assessed for
the volume of rock involved in carrying loads,
e.g. for about one to two diameters around the
tunnel periphery, in the case of tunnel behaviour
or more locally in the case of a structure, such as
the elephant foot of a steel arch.
Once the GSI rating system has been applied
for any rock mass, the estimated range of GSI
values can be used, as input data, to a set of em-
pirically developed equations (e.g. Hoek – Brown
failure criterion), which provide reasonable esti-
mations of the compressive strength (σcm), shear
strength parameters (c, φ) and deformability
modulus (Em) of the rock mass. The aforesaid set
of parameters can be used in complex numerical
analyses and closed form solutions of tunnelling
problems. It has to be noted that the use of GSI
values in the previously mentioned mathematical
expressions, is being made in conjunction with
the appropriate values for both the unconfined
compressive strength of the intact rock (σci) and
the relevant petrographic constant (mi).
Although GSI is a totally independent system,
in the earlier period of its application, it was pro-
posed that correlations of “adjusted” RMR and Q
values with GSI be used for providing the neces-
sary input data, for the Hoek – Brown criterion.
Although, this process may work with the better
quality rock masses, it is unreliable in the range
of weak (e.g. GSI<35), very weak and heteroge-
neous rock masses, where these correlations are
not recommended [3].
The major assumption, which exists behind
the successful application of GSI, is that the rock
mass, to be rated, has to be characterised by a
sufficient number of “randomly” oriented discon-
tinuities, and as a consequence of this, it behaves
as a homogeneous isotropic mass. Therefore, GSI
should not be applied to those rock masses, in
which clearly defined structural orientation
dominates and / or the existence of structurally
dependent gravitational instability mechanisms
can be easily recognised.
Another limitation of GSI application is in
rock masses, such as claystones, siltstones and
weak sandstones, which were developed in geo-
logically stable conditions, in a post tectonic en-
vironment, and they usually present a simple
structure with no or very few discontinuities. In
case that these rock masses are continuous with
no discontinuities, the rock mass can be treated as
intact, with its engineering parameters estimated
directly by the relevant laboratory and in-situ
testing results.
The influence of the groundwater in the ap-
plication of GSI rating system is significant for
the categories of discontinuities, covering the
range between “fair” to “very poor”. The down-
grade of the assigned GSI values, by their appro-
priate shifting to the right of the appropriate
chart, is considered necessary in wet conditions,
since the presence of groundwater, along the sur-
faces of the aforesaid type of discontinuities, may
lead to further deterioration of their infilling ma-
terials.
5. Figure3. General GSI chart for rock mass ratings based on geological observations
6. Figure 4. GSI chart for heterogeneous rock masses (such as flysch).
7. 2.3 Tunnel Stability Factor
Hoek [5] argued that the severity of the tunnels
stability problems, mainly in weak rock condi-
tions, depend upon the ratio of the value of in-
situ rock mass strength, σcm, to the in-situ geo-
static vertical stress level, p0=γΗ. This argument
was originally verified by the construction of
two dimensionless plots (Figures 5, 6), based on
the results of a Monte Carlo analysis, in which
the input parameters for the rock mass strength
and the tunnel deformation were varied at ran-
dom in 2000 iterations. The upper and lower
bounds of the used parameters in Hoek’s analysis
were as follows: (a) Intact rock strength, σci=1-
30MPa, (b) Hoek-Brown constant, mi=5-12, (c)
Geological Strength Index, GSI=10-35, (d) In-
situ hydrostatic stress=2-20MPa and (e) Tunnel
radius, r0=2-8m.
Figure 5 presents the plot of the ratio of plas-
tic zone radius to tunnel radius (rp/r0) versus the
ratio of rock-mass strength to the in-situ geostatic
vertical stress (σcm/p0). Figure 6 presents the vari-
ation of the ratio of the tunnel’s periphery con-
vergence to tunnel radius (ui/r0) against the ratio
of rockmass strength to the in-situ geostatic verti-
cal stress (σcm/p0). In spite of the wide range of
the examined conditions, the reasonably well-
fitted curves of both diagrams can show a good
indication of the average trend.
Figure 5. Relationship between size of plastic zone and ratio
of rock-mass strength to in-situ stress
An important conclusion derived from Fig-
ures 5 and 6 is that the dimensionless quantities
rp/r0 and ui/r0, increase very rapidly, once the
rock-mass strength falls below 20% of the in-situ
stress. According to Hoek [5], the aforesaid limit
of σcm/p0≤0.20 can be considered as one general
criterion, which defines the limit between the
practically stable tunnelling conditions in sound
rock masses, from the unstable ones, mainly in
the weak rock masses.
Figure 6. Tunnel deformation versus ratio of rock-mass
strength to in-situ stress.
Following Hoek’s original idea of adopting
the ratio σcm/p0, as the controlling parameter of
the tunnels general stability conditions, Mihalis et
al [4] made a further extension, by including the
size of the underground openings in the deriva-
tion of a new parameter, the so-called Tunnel
Stability Factor (TSF). TSF is expressed mathe-
matically by Equation 1.
The inclusion of the size (equivalent diameter
D) of the underground openings in TSF, results
from the tunnelling experience, that in similar
geological / geotechnical environment and at the
same overburden heights, tunnels of different
size, exhibit modes of deformational behavior
having different scale and degree of criticality.
)1(25.075.0
D
cmTSF
8. The role of TSF in the tunnels stability con-
ditions was examined by numerically analyzing
74 cases, with the following lower and upper
bounds of the parameters used in this parametric
numerical study: (a) Intact rock strength, σci=5-
50MPa, (b) Hoek-Brown constant, mi=10, (c)
Geological Strength Index, GSI=10-50, (d) Initial
geostatic stress field of gravitational type with Κ0
= 0.5 – 1.0 and (e) Tunnel radius, r0=2-5m.
The performed numerical analyses were fo-
cused on to the examination of the deformation
patterns and shear failure modes of the rock
mass, surrounding unsupported tunnel circular
sections of different size. The factors: (i) tunnel‘s
periphery convergence / tunnel equivalent radius
and (ii) plastic zone radius / tunnel equivalent ra-
dius were derived in all the examined cases and a
unifying framework was developed to account
for the severity of tunnel stability problems in
terms of the corresponding TSF calculated val-
ues. The governing role of the proposed factor
TSF in deriving the tunnels stability conditions,
was verified in Figures 7 and 8, where the ratios
rp/r0 and ui/r0 are plotted against the correspond-
ing TSF values.
Figure 7. Ratio of plastic zone radius to equivalent tunnel ra-
dius versus TSF
It is remarkable the fact that in spite of the
very wide range of conditions, included in the
performed numerical analyses, the results in both
figures tend to follow a very similar trend. In ad-
dition, the fitted curves are considered that can
give a satisfactory indication of the average tun-
nel behavior, without including the effects from
the installation of any primary support measures.
Figure 8 gives a set of approximate guidelines
on the criticality of tunnels stability conditions,
which can be encountered for different limits of
the ratio ui/r0. These limits can be considered that
give a first estimate of tunnel squeezing prob-
lems. It is noted that from Figure 8 the following
limiting tunnel stability cases can be derived:
Figure 8. Ratio of tunnel’s periphery convergence to equiva-
lent tunnel radius versus TSF
For TSF≤0.20, 5%<ui/r0≤10% ,very severe
squeezing problems. Detailed analyses are
necessary. Ground improvement techniques
with partial excavations of adequately small
size must be examined, in conjunction to the
installation of very heavy primary support
measures. Time sequence of the primary
support measures and final lining is very es-
sential.
For 0.20<TSF≤0.30, 2.5%<ui/r0≤5%, severe
squeezing problems. The installation of very
heavy primary support measures is neces-
sary on the basis of detailed analyses. Time
sequence of the primary support measures is
very essential.
For 0.30<TSF≤0.60, 1%<ui/r0≤2.5%, minor
squeezing problems. The installation of typ-
ical primary support measures is considered
necessary to establish adequate stability
conditions.
For TSF>0.60, ui/r0 ≤1%, few support prob-
lems. The installation of minor primary
rp /r0 = 1,79xTSF-0,43
0,00
0,50
1,00
1,50
2,00
2,50
3,00
3,50
4,00
4,50
5,00
0,00 0,25 0,50 0,75 1,00 1,25 1,50 1,75 2,00 2,25 2,50
TSF = σcm /{γH
0.75
D
0.25
}
rp/ro
ui /r0 = 0,0053xTSF -1,31
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
11%
12%
0,00 0,25 0,50 0,75 1,00 1,25 1,50 1,75 2,00 2,25 2,50
TSF = σcm /{γΗ
0.75
D
0.25
}
ui/ro
ui /r0 between 5% and 10%
Very severe squeezing
ui /r0 between 2.5% and
5% Severe squeezing
ui /r0 between 1% and 2.5%
Minor squeezing
ui /r0 less than 1%
Few support
problems
9. support measures can control easily any
possible instabilities.
The curves shown in Figures 7 and 8 are de-
fined by Equations (2) and (3):
3 CONSTRUCTION CHALLENGES IN
TUNNELLING
3.1 General
It is well recognised that the main reason for the
successful tunnelling applications in Greece was
the good understanding of the existing relation-
ship between the chosen to be applied construc-
tion techniques, which in most of the cases in-
cluded advanced technological methodologies,
and the encountered geotechnical conditions.
More specifically, the gained experiences from a
number of tunnelling construction challenges in
Greece are related to useful conclusions, which
describe the successful and economic application
frameworks of innovative techniques, aiming to
control the geotechnical risk in adverse ground
conditions.
In the following paragraphs two tunnelling
cases of Athens Metro [6], [7] and one tunnelling
case of Egnatia Motorway [9] are presented in
more detail. All of them, among numerous oth-
ers, are considered that they have provided useful
experiences of successful applications of innova-
tive tunnelling construction technologies in real
challenging soft ground and weak rock condi-
tions.
3.2 Microtunnelling application for Athens
Metro
A microtunneling application was attempted for
the construction needs of Monastiraki under-
ground station complex of Athens Metro.
Monastiraki is a very densely populated area at
the historical centre of Athens, downhill of
Acropolis ancient monument.
The general dimensions of the station are: (a)
length = 180m, (b) underground cavern diameter
= 16.20m. The depth of the excavations from the
ground surface was 18m approximately.
Except of the underground cavern, the com-
plete realisation of the station complex included a
number of excavations, related to an access shaft,
a cross – over and the stairway galleries.
The geotechnical conditions in the area of
Monastiraki station were evaluated as very ad-
verse, where highly weathered graphitic and
chloritic phyllites, alternating with meta-
sedimentary shales dominate. These geo - materi-
als have usually a dark grey to green-grey color
("black Athenian schist") and are characterized
by very low shear strength and deformability pa-
rameters.
The criticality of the situation became very
obvious immediately after the completion of the
excavations of the vertical access shaft, as the
surface settlements exceeded 80mm, by creating
a great deal of skepticism about the safe support-
ing methodology to be applied in the next con-
struction steps.
The microtunnelling, aiming to the construc-
tion of 22 steel pipes of 1.2m diameter, along the
outer periphery of the main cavern, was decided
as the proper method, which could create the
necessary stiff crown support, prior to the contin-
uation of the underground excavations (Figure 9).
The design of the microtunnelling was made by
using very sophisticated 3-D finite element soft-
ware (Figure 10).
The whole application was successful and the
scope of controlling the ground movements, dur-
ing the excavations, to acceptable serviceability
limits for the existing superstructures was finally
achieved.
)2(79.1
43.0
25.075.0
0
Dr
r cmp
)3(0053.0
31.1
25.075.0
0
DHr
u cmi
10. Figure 9. Microtunnelling application in Monastiraki, for the
pre-support of the main station cavern.
Figure 10. 3-D finite element model for the numerical simula-
tion of the microtunnelling in Monastiraki.
3.3 Jet grouting application in weak rock
conditions for Athens Metro
Jet grouting techniques were extensively applied
in one location of the Athens Metro project with
poor sub-ground conditions; the tunnel stretch
along the alignment of Aghiou Konstantinou
street in the historic centre of Athens. This case
has been extensively presented by Mihalis et al
[7]. At this particular site, TBM was operating
with an extremely poor performance, resulting to
an overall advance rate less than 2.0m/day. This
was due to the occurring large, occasionally un-
controlled, over-break failures (Figure 11), which
caused major delays, while freeing the machine
and grouting the cavities.
Figure 11. Significant over-break failure at Aghiou
Konstantinou street. Athens Metro project.
The main reasons for the observed ravelling
tendency of the ground strata, (above the TBM
cutterhead), were attributed mainly to the insuffi-
cient cohesion, along the locally existing highly
weathered and intensely tectonised zones, in con-
junction with the large muck openings of the
TBM cutter head, which could not control the
muck-flow. According to the findings of the per-
formed geotechnical investigation, the existing
ground conditions at Aghiou Konstantinou area
are summarized as follows:
The overburden layer, which varies between
2 and 6m in thickness, mainly consists of al-
luvial deposits and backfill materials of
brownish sandy silty clay with fragments of
limestone and siltstone.
The first layer of the substratum, with
thickness between 4 to 8m approximately,
consists of greenish - greyish fractured
weak metasiltstone with medium to high
degree of weathering.
The second layer of the substratum consists
of greyish - black highly weathered, very
11. weak phyllite and fractured very weak
metasiltstone.
Figure 12 presents the results of Menard type
pressuremeter tests, performed in the jet grouting
area for the purposes of the ground investigation.
According to Figure 12 there is a clear tendency
of the Menard modulus EM (in MPa) to increase
with depth. The average values of the Menard
modulus in the zone of influence above the tun-
nel crown is EM=40MPa, while those at the tun-
nel’s excavation limits are somewhat higher, with
average value EM=70MPa.
Figure 12. Athens Metro. Distributon of measured Menard
moduli EM with depth
Considering the fact that only minor align-
ment changes of the running tunnel could be im-
plemented and future TBM tunnelling operations
had to proceed for a length of 180m approximate-
ly, in close proximity and below buildings at very
shallow depths (13m approximately), the imple-
mentation of certain ground improvement
measures for the efficient control of the existing
high risk of the over-break failure incidents was
of crucial importance for the safety of the exist-
ing superstructures. Under these circumstances,
the construction of a dense pattern (~ 1.10m x
2.0m) of jet grout columns, in producing a 3.0m
thick, relatively stiff arch of grouted soil (with
grout to soil fraction 25% - 40%), above the top
heading of the tunnel (Figure 13), was considered
as the most efficient solution for: (i) controlling
the risk of the over - break failures, (ii) minimiz-
ing the ground losses at the surface and (iii) ac-
celerating the TBM advance rates.
Figure 13. Athens Metro. Jet grouting application
The applicability of the various jet grouting
techniques in the geotechnical conditions of the
previously mentioned tunnel stretch was decided
upon the evaluation of results from extended full-
scale trial testing programs, including:
Vertical and horizontal single jet grouting
tests
Vertical and horizontal double (water-cut)
jet grouting tests with and without water
pre-cutting,
Vertical triple jet grouting tests with water
pre-cutting.
The evaluation of the performed trial test re-
sults was made by correlating the applied specific
jet grouting energy values Es with the achieved
grouted columns diameter D. It is explained that
for a unit length of a column, the specific jet
grouting energy Es (MJ/m) depends mainly on
the: (i) grout pressure P (MPa), (ii) grout flow
rate Q (m3
/hr), and (iii) withdrawal speed Vt
(m/hr) and is mathematically expressed by the
equation (4):
)4(
t
s V
PQE
The derived relationship between the
achieved grouted columns diameter, D (cm) and
12. the specific jet grouting energy, Es (MJ/m) is
remarkably fitted with the curve of Figure 14.
This curve is mathematically expressed by equa-
tion (5) [7] :
)5(0101.0 02.2
DEs
Figure 14. Athens Metro. Specific Jet grouting energy Es ver-
sus grouted column diameter D
According to Figure 14, the successful exe-
cution of the various jet grouting techniques can
be related to the different ranges of the applied
specific jet grouting energy, but always it is re-
lated to the encountered geotechnical conditions.
More specifically, for the aforesaid weak rock
conditions of the jet grouting application area of
the Athens Metro project, the following conclu-
sions can be safely drawn:
Single jet grouting can be executed with spe-
cific energy levels between 17MJ/m -
30MJ/m. Grouted columns with dianeter of
40cm approximately can be successfully
achieved.
The successful application of double jet
grouting needs specific energy levels ranging
between 40MJ/m to 80MJ/m. Especially, if
the specific jet grouting energy of double jet
grouting system (water-cut) without water
pre-cutting is at 40MJ/m - 45MJ/m, grouted
columns with diameter of 60cm can be suc-
cessfully produced.
Triple jet grouting can be executed with en-
ergy not in exceed of 130MJ/m approximate-
ly. In this type of jet grouting application,
grouted columns with diameter of 100cm are
expected to be finally achieved.
The finally adopted jet grouting system for
the needs of ground pre-treatment program along
the Aghiou Konstantinou TBM tunnel section
was the one of the double water-cut system with-
out water pre-cutting. It is noted, that this tech-
nique was proved that can produce faster and
more economically grouted columns of satisfac-
tory dimensions (approximate diameter D=0.6m).
After the completion of the ground pre-
treatment program, TBM restarted its operations
and achieved an average advance rate of approx-
imately 12m/day, with a maximum of 28m in a
single day. The effect of ground treatment on
controlling the occurrence of over-breaks was
obvious, since large scale failure incidents were
eliminated.
A clear overall picture of the distribution of
the maximum surface settlements and the relative
ground losses along the aforesaid jet grouting
zone is given in Figure 15 [8]. The maximum ob-
served settlement did not exceed 43mm and the
corresponding relative ground loss was equal to
1% approximately. The appreciable increase of
the settlements and the corresponding amounts of
relative ground loss, towards the end of the jet
grouting pre-treated area, is attributed mainly to
the decrease of the grout-to-soil replacement ratio
from 40% to 25%.
Figures 16 and 17 present the evaluated
shapes of the normalized surface settlement
troughs obtained from measurement points offset
with respect to the axis of Aghiou Konstantinou
tunnel, in the areas where the grout – to – soil re-
placement ratio was 40% and 25% respectively.
The decrease of the distance i from 8.0m (in the
area with replacement ratio 40%) to 6.5m (in the
area with replacement ratio of 25%) could be di-
rectly related to the emerged reductions of rela-
tive ground losses (as these are shown in Figure
15) since the depth of TBM operations was unal-
tered. In addition, the application of the following
approximate linear expression (6) between the
best fit values i and the depth of the tunnel axis H
for both pre-treated areas:
)6(kHi
13. estimates k values equal to 0.37 (for soil re-
placement ratio 25%) and 0.45 (for soil replace-
ment ratio 40%).
Figure 15. Surface settlement and ground loss distributions
along jet grouting zone.
Figure 16. Normalized surface settlement trough in jet grout-
ing
Figure 17. Normalized surface settlement trough in jet grout-
ing area with ground improvement ration 25%.
3.4 Tunnelling construction through a
landslide zone --- Tunnel S3 of Egnatia
Motorway
Tunnel S3 is located at the central section of Eg-
natia Motorway (Figure 18), west of Thessalo-
niki, close to Veroia city.
Figure 18. Location of tunnel S3 along Egnatia motorway
axis.
The major characteristics of tunnel S3 are
summarized as follows:
It is a relatively shallow twin bored hill
slope tunnel. The hill slope has a mild incli-
nation of 20 degrees parallel to the tunnel
axis (Figure 19).
Figure 19. A view of the tunnel S3 entrance portal.
The tunnel total length is 230m.
The tunnel excavated width is 12m.
The axial average distance between the two
tunnel bores is 30m.
The maximum overburden height is 30m
approximately.
14. The encountered geological and geotechnical
conditions can be summarised as follows:
Highly tectonised alterations of thin-bedded
to mid-bedded limestones and argillaceous
phyllites are the dominating geotechnical
units along the tunnel axis.
Highly weathered phyllites are the main
type of geomaterial at the tunnel entrance
portal area. Locally they are converted to
soil-like material. Small to medium size
fragments of strong rock are present. The
overall mass has been extensively relaxed
with open structural discontinuities in
places.
In the tunnel exit portal, the existing phyl-
lites are of better quality, but still with open
structure. However, the layered structure of
the phyllites materials is mostly retained.
No groundwater was found at the under-
ground excavation level.
Overall, it is very difficult to adopt a strictly
confirmed geotechnical model, in terms of detect-
ing the specific generative causes for the situation
of the geological formations in the tunnel’s area.
It must be emphasized that the geologic surface
formation in the vicinity of the tunnel are in limit
post – equilibrium situation, characterised also by
a significant slope relaxation process in the geo-
logic history and meta – stability marginal condi-
tions
The critical stability conditions were recog-
nised immediately after the initiation of the un-
derground excavations, as: (a) significant damage
of the tunnel’s temporary invert (Figure 20) and
(b) extended tensional cracking on the ground
surface upstream of the hill (Figure 21), were
evolved even during the stoppage of all the con-
struction activities. It became obvious, from the
evaluation of the results of the installed instru-
mentation, that an instability mechanism was
triggered with the characteristics of a cross slope
downhill circular failure.
Figure 22 presents the recorded ground sur-
face displacements along the tunnel’s complete
length, immediately over the two tunnel bores.
The major conclusion, which can be derived from
Figure 22, is that the directional hill movement,
towards its toe, was characterised by large total
displacements, at the range between 200mm to
600mm. The instability phenomenon was devel-
oped with less degree of severity in the tunnel
exit, something which has to be attributed to the
better quality of the phyllites formation in this
area.
Figure 20. Significant cracking of temporary invert.
Figure 21. Extended tensional cracking of the ground surface
upstream on the hill.
The need to stabilise long-term the already
activated sliding mechanism, without considering
any beneficial effect from the tunnel’s final lin-
15. ing, was considered as the only solution for the
restart of the underground works and the comple-
tion of the tunnel’s construction. The applied sta-
bilisation solution (Figure 23) was comprised of:
The construction of 30m long concrete re-
taining pile wall of 1.0m in diameter, an-
chored every 2.0m (in the longitudinal di-
rection) in the sound bed rock. This pile
wall aimed to function as an upstream “bar-
rier” of the occurred ground movements at
the top of the failure mechanism.
The stabilisation cement grouting from in-
side of the tunnel bores. This practice aimed
to the improvement of strength and deform-
ability characteristics of the surrounding de-
stabilised ground masses.
The simultaneous construction of permanent
30m long pre- stressed anchorages, with
pre-stressed forces of 600KN, from the right
bottom peripheral sides of the two bores.
These anchorages and more specifically
their forces were considered necessary for
providing the beneficial stabilising mo-
ments, against the occurred instability
mechanism.
.
Figure 22. Recorded ground surface movements over the two
bores of S3 tunnel.
The available measurements, covering a pe-
riod of almost 6 years after the completion of
tunnel S3, provide enough confidence that the
applied solution has achieved its scope of stabi-
lising the occurred failure mechanism.
Figure 23. Applied stabilisation solution for tunnel S3.
4 TUNNEL UNREINFORCED FINAL
LINING – APPLICATIONS AND
LIMITATIONS
The “rising up” of the “tunnel unreinforced
final lining” concept in Greece has been directly
linked with the design and cost optimisations’
needs of the concession highway projects in the
last five years. The main scope of the concept ‘s
application is to limit the construction budgets of
the aforesaid projects, at reasonable levels, by
avoiding unnecessary over designs in tunnelling,
however without risking the final quality and the
long term safety and serviceability conditions of
the structures.
The existing design and construction experi-
ences in tunnelling worldwide have shown that
the concept of the “tunnel unreinforced final lin-
ing” is not a prohibitive one. A number of high-
way and railway tunnels structures, with unrein-
forced final linings, were constructed
successfully and are in full operation over the last
30 years in Europe. However, the recent increas-
ing demand for design and cost optimisation in
tunnelling projects, in combination with the re-
cent very restrict design codes’ regulations and
construction specifications for high level long
term safety and serviceability conditions of the
16. underground structures, dictate the need to evalu-
ate in detail the application limits of the concept.
These limits are related to the geotechnical envi-
ronment, the seismic / tectonic regimes and the
topographies that tunnels will be constructed.
The relevant European design codes, recom-
mendations and guidelines which offer the neces-
sary design framework of the tunnel unreinforced
tunnel final linings are:
Eurocode 2 EN 1992-1 / Section 12, which
defines a number of provisions for plain and
lightly reinforced concrete structural mem-
bers, regarding the concrete properties and
the appropriate factors of safety for the ma-
terials strength.
AFTES recommendations focus on to the
design of the tunnel final lining members,
by imposing a restriction on the possibly
developed crack depth (<hw/2) and by limit-
ing the allowable eccentricity (e<0.3hw) for
all load cases, that result in high axial forces
N in relation to the concrete strength
(N>2.7% (bxhwxfck), where: (i) hw is the
overall height of the tunnel cross-section,
(ii) b is the overall width of the tunnel cross-
section and (iii) fck is the characteristic con-
crete strength in compression.
Michalis et al [10] performed a parametric 3-D
numerical analysis aiming to examine thoroughly
the “safe” application limits of the tunnels unre-
inforced final linings, within the aforesaid design
codes framework. This analysis considered the
“three lane” typical open and closed sections of
the 2km double tunnel, along Maliakos – Kleidi
concession motorway project in central Greece
(Figures 24 and 25). The analysis examined only
typical Eurocode static design load cases, cover-
ing all possible range, from the lining construc-
tion stage (at the time of de- moulding with the
adoption of the effects of the “young” concrete
properties and the concrete’s hydration heat
emission) to the possible occurrence of an acci-
dental explosion, inside the tunnel, during its op-
erational period. The analysis focused in homo-
geneous and in mixed face rock mass conditions,
where their deformation moduli varied between
150MPa to 1000MPa.
Figure 24. Typical open tunnel section.
Figure 25. Typical closed tunnel section.
Typical finite models, used in the parametric
study, are presented in Figures 26 and 27. The
complete dynamic analysis of the tunnel unrein-
forced final lining, by considering real time his-
tory earthquake events, is currently under exten-
sive numerical investigation [11]. However some
preliminary conclusions from this sensitivity nu-
merical study are presented in the next final
paragraphs of the present paper.
The numerical simulation of the constitutive
behaviour of the unreinforced concrete was made
with the adoption of Willam and Warnke model
[12] and by considering the EC-2 stress – strain
curve, as well as the EC-2 concrete characteristic
strengths and relevant safety factors. The tunnel
lining – rock mass interaction was simulated, in
detail, with the use of “stick – slip” elastic
17. springs, where their stiffness values were calcu-
lated by considering both the surrounding rock
mass deformability properties and the lining ge-
ometries (Figure 28).
Figure 26. 3-D finite element model of the tunnel final lining
Figure 27. Detail of the 3-D finite element model of the tun-
nel final lining
The major conclusions drawn from the previ-
ously described parametric analysis can be sum-
marised as follows:
Figure 28. Tunnel lining – rock mass interaction model with “
stick – slip” elastic springs, adopted in the parametric analy-
ses
The structural integrity of the examined tun-
nel unreinforced (in the vault) final lining
sections has been verified in the case of rela-
tively sound rock mass conditions, character-
ised by deformability modulus Em ≥ 800MPa
- 1000MPa, as it fulfils Eurocode 2 Part 1-1 /
Section 12 provisions, regarding plain and
lightly reinforced concrete members, and
AFTES aforesaid design limiting criterion, in
respect to the crack depths and the load ec-
centricities. The aforesaid range of the sur-
rounding rock mass Em values create enough
confidence that the unreinforced (in vault)
final linings can be applied even for tunnels
that cross high seismic areas, or areas with
adverse topographic morphology and rela-
tively low covers.
In cases where the surrounding rock mass
conditions are characterised by deformability
modulus 300MPa< Em < 800MPa, significant
cracking depth occurs in the unreinforced
tunnel vault, which exceeds the half of the
tunnel section’s height, in combination to the
formulation of secondary horizontal cracking
(Figure 29), thus jeopardizing the initiation
of spalling phenomena. The long term struc-
tural integrity of the tunnel unreinforced
18. vault final lining can not be achieved, espe-
cially in seismic areas.
In cases, where the surrounding rock mass
conditions are characterised by deformability
modulus Em≤300MPa, the unreinforced con-
crete sections cannot be applied, because of
the high risk of the concrete crushing (Figure
30).
The footings areas and the invert sections (if
exist) must be reinforced for any quality of
the surrounding rock masses.
An accidental explosion, inside the tunnel,
will result to severe cracking of the unrein-
forced final lining at the lower bottom arches
of the vault (Figure 31). However, by con-
sidering the locations that these cracks are
expected to appear and the calculated dis-
placement patterns, no collapse mechanism
of the lining can be formulated. However,
repairing works after the explosion will be
necessary.
In tunnel portal areas the tunnel unreinforced
final lining must be avoided, as well as in ar-
eas where the existence of nearby or crossing
active faults have been recognised.
Figure 29. Cracking formation of the unreinforced vault of the
final lining. Rock mass deformability modulus
300MPa<Em<800MPa
Figure 30. Extensive and severe cracking of unreinforced tun-
nel final lining in rock mass conditions with E<300 MPa.
Figure 31. Pattern of crracking of unreinforced tunnel final
lining due to explosion
5 CONCLUSIONS
Since the early 1990s, numerous challenges in
designing and completing successfully the con-
struction of a significant number of large scale
19. infrastructure projects have been faced in Greece.
In these projects, tunnelling was a significant
part, mostly related to real challenging engineer-
ing problems. The solutions of these problems
demanded the combination of the detailed
knowledge of the in-situ geological and geotech-
nical conditions, with the implementation of in-
novative design ideas and construction tech-
niques.
New design methodologies were developed
aiming to provide technically sound solutions to
challenging tunnelling cases. These methodolo-
gies focused on to the better understanding of the
real complex and adverse geological and geo-
technical conditions of Greece, as well as to the
more accurate qualitative and quantitative appre-
ciation of the criticality of the tunnelling prob-
lems.
The gained experiences from the successful
construction of difficult tunnel cases in Greece
can provide the successful and economic applica-
tion frameworks of innovative techniques, aiming
to control the geotechnical risk in adverse ground
conditions.
These experiences, accompanying with the
corresponding design methodologies, are ready to
be transferred in future tunnelling projects
worldwide.
ACKNOWLEDGEMENT
The author wishes to express his special thanks to
Professor Emeritus A. Anagnostopoulos of
NTUA, Professor Emeritus P. Marinos of NTUA,
Professor M. Kavvadas of NTUA, Dr. G.
Kouretzis, as well as Mr. N. Koronakis and Mr.
P. Kontothanassis of Omikron Kappa CON-
SULTING Ltd, for their numerous constructive
comments and encouragement during the prepa-
ration of the present work.
The author expresses also his gratitude to Mr
G. Vlavianos of Hellenic Ministry of Public
Works, for all his useful remarks aiming to the
improvement of the present work’s quality.
REFERENCES
[1] European Commission, Safety in European tunnels,
PGTREN Information and Communication Paper
(2001).
[2] P. Marinos, E. Hoek, GSI a geologically friendly tool
for rock mass strength estimation, Proc. “GeoEng 2000
at the Int. Conference on Geomechanical and Geologi-
cal Engineering”, Melbourne, Victoria, Australia, Lan-
caster PA: Technomic Publishers, 2000, 1422 – 1446.
[3] V. Marinos, P. Marinos, E. Hoek, The geological
strength index: applications and limitations, Bull Eng
Geol Environ, 64 (2005), 55-65.
[4] I. Mihalis, A. Anagnostopoulos, M. Kavvadas, Tunnel
Stability Factor – A new parameter for weak rock tun-
neling, Proc. “ΧVth
Int. Conference on Soil Mech. Ge-
otechnical Engineering”, Istanbul, Turkey, 2001, Vol. 2,
1403-1406.
[5] E. Hoek, Tunnel support in weak rock, Lecture notes
presented at NTUA, Athens, Greece (1999).
[6] M. Kavvadas, L.R. Hewison, P.G. Laskaratos, C.
Seferoglou, I. Michalis, Experiences from the construc-
tion of the Athens Metro, Proc. “Geotechnical aspects
of underground construction in soft ground”, London,
United Kingdom, 1996, 277 – 282.
[7] I. Mihalis, G. Tsiambaos, A. Anagnostopoulos, Jet
Grouting applications in soft rocks: the Athens Metro
case, Proceedings of the Institution of Civil Engineer-
ing, 157 (2004), 219 – 228.
[8] I. Mihalis, M. Kavvadas, Ground movements caused by
TBM tunneling in Athens Metro Project, Proceedings of
the International Symposium on Geotechnical aspects
ofunderground costruction in soft ground”, Tokyo, Ja-
pan, 1999, 269 – 274.
[9] N. Koronakis, P. Kontothanassis, Personal communica-
tion (2011).
[10] I. Mihalis, G. Kouretzis, P.A.TH.E Section Maliakos –
Kleidi Project, Category III check of tunnel T1 – North
final lining design in unreinforced concrete sections &
Independent Engineer’s proposal regarding application
criteria of tunnel final lining sections, unpublished
Intenal Report (2009).
[11] G. Kouretzis, Personal communication (2012).
[12] K. Willam, E.P. Warnke, Constitutive model for the
triaxial behavior of concrete, Proc. “International Asso-
ciation for Bridge and Structural Engineering”, Berga-
mo, Italy, ISMES, 1975, Vol . 19, 174.