SEBASTIAN APENG,
No 21,Kampung Sampun Gerunggang,
94600 Asajaya,Kota Samarahan,
Sarawak,Malaysia.
Contact No: +60111-9870084
To Whom It May Concern,
I believe it is interesting and challenging to pursue a career and professional growth in your organization.
2. Currently, I’m working with GRANITE SERVICES INTERNATIONAL as a Mechanical Technician
since October 2014 and my previous company is SERBA DINAMIK Sdn Bhd as Rotating Equipment
Mechanical/Workshop Supervisor since July 2008 which involved in various plant shutdown, project and
offshore maintenance services. I’m familiar with work permit system HSE policy.
3. You can expect the hard work ethic that I will bring to your organization to be a valuable asset. I will
be sure provided you with high quality worthy of ever increasing responsibility.
4. Herewith I enclosed my resume as a first step in exploring for possibilities of employment with your
organization.
Greatly appreciate your time and consideration. I hope to meet with a favorable response.
Best Regards,
SEBASTIAN APENG.
RESUME
SEBASTIAN APENG
Telephone no: +60111-9870084
E-mail Address:sebt84@yahoo.com
:sebastiansebt@gmail.com
PERSONAL PARTICULARS
DATE OF BIRTH : 20TH
MARCH 1984
PLACE OF BIRTH : KUCHING, SARAWAK
NATIONALITY : MALAYSIAN
AGE : 31 YEARS OLD
MARITAL STATUS : MARRIED
RELIGION : CHRISTIAN
RACE : IBAN/BIDAYUH
PERM ADDRESS : 21, KAMPUNG SAMPUN GERUNGGANG,94600 ASAJAYA,
KOTA SAMARAHAN, SARAWAK,MALAYSIA.
HEALTH : EXCELLENT
OBJECTIVE
Willing to do the job as a maintenance technician in a reputed organization to utilize my skills and
knowledge and experience for the growth of the organization.
ACADEMIC QUALIFICATIONS
 Competence Certificate in Rotating Equipment Maintenance Specialist, 2008
(Certificate Of Basic engineering skills and Basic plant maintenance)
The City & Guilds of London Institute.
 Certificate in Industrial Technician Level 1 & 2 , 2004
(Tools & Die Making)
Kota Samarahan Industrial Training Institute (ILPKS)
PERSONALITY
 Knowledge & compliance of Health, Safety & Environment Policy.
 Familiar & knowledge of full compliance of PPE at work site.
 Excellent cross-cultural communication skills.
 Committed and enthusiastic in solving work related problems with in depth understanding of
employee-manager's duty and company culture.
 Able to work under critical time pressure & willing to learn.
 Computer skill Ms office
 Good communication and writing in English/BahasaMelayu.
 Familiar with standard code API/ASME.
 Familiar & comply of work permit systems.
WORKING EXPERIENCES
OCTHOBER 2014-Present
GRANITE SERVICES INTERNATIONAL(M)
Mechanical Technician
 Work with Supervisor/Maintenance teams to do equipment service/repair, disassembly/assembly various
types of rotating equipment such as GE Gas Turbine HGPI/MI (Frame 5,6b,6Fa,7,9E,9FA)steam turbine,
generator, pump, compressor at power plant and oil and gas plant.
 To perform shaft alignment on driven Rotating Equipment.
 To perform troubleshooting on mechanical equipment.
 Respond to standby/call out for emergency/urgent repairs outside working hours.
 To perform any task given / instructed by immediate superior and the management.
 EHS and quality is meeting as per company and costumer expectation.
Nov 2013 – Sept 14
SERBA DINAMIK SDN BHD (LABUAN SERVICE CENTRE)
Senior Mechanical Technician/Mechanical Workshop Supervisor
Responsibilities:
.
 To assist and report duty to Engineer for Workshop activity.
 Work with maintenance teams to investigate and troubleshoot various types of rotating equipment such
as pump, compressor, turbine at workshop, plant and offshore.
 Specify and review drawings and data for rotating equipment for offshore and plant applications.
 Perform alignment for rotating equipment as a requirement of maintenance procedure to prevent
vibration during startup and operation.
 Develop and execute QA/QC standards for rotating equipment.
 Supervised repair and equipment installation activities in the workshop and plant.
 Preparation of requisitions for Rotating Equipment packages.
 Preparing inspection reports, commissioning procedure, supervising other maintenance activities specific
to the rotating equipment technical area.
 Maintains safe and clean working environment by enforcing procedures, rules and regulations.
 Ensure EHS and quality is meeting as per company and costumer expectation.
Feb 2012 – Oct 2013
SERBA DINAMIK SDN BHD (LABUAN SERVICE CENTRE)
Senior Mechanical Technician (Mechanical Coordinator)-offshore/onshore.
Responsibilities:
 To perform maintenance and repairs of multistage pumps, compressors, steam turbines, gas turbine and
standby generators and prepare report in offshore and onshore.
 To assist supervisor for any task/equipment repair, service, installation commissioning at offshore
/onshore.
 To perform shaft alignment on driven Rotating Equipment.
 To perform troubleshooting on mechanical equipment
 To carry out pressure test
 To Conduct on Job Training (OJT) for junior technicians
 Respond to standby/call out for emergency/urgent repairs outside working hours.
 To perform any task given / instructed by immediate superior and the management.
Oct 2008 – Nov 2012
SERBA DINAMIK SDN BHD (BINTULU SERVICE CENTRE)
Junior Rotating Equipment Maintenance Executive/Mechanical Technician.-offshore/ onshore.
Supply Manpower for ROVING GANG Crew SKO (Sarawak Water).
Responsibilities:
 To assist and perform maintenance and repairs of rotating equipment such as multistage pumps,
compressors, steam turbines, gas turbine and standby generators and prepare report.
 To assist and to perform shaft alignment on driven Rotating Equipment.
 To assist and to perform troubleshooting on mechanical equipment
 Respond to standby/call out for emergency/urgent repairs outside working hours.
 To perform any other task given/instructed by immediate Superior and the management.
PROJECT INVOLVE &PRESENT
ONSITE PROJECT-POWER PLANT & OIL AND GAS PLANT.
 Sepangar Bay Power Plant- Frame 6B GE Gas Turbine-HGPI from 26th
March 2016 –05th
April 2016 .
 Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 9E HGPI GT4(Hot Gas Path
Inspection) from 25rd
February 2016 -22th
March 2016.
 Thailand , Rayong GPSC CUP 1 Frame 6BGT 14 GE Gas Turbine-Major Inspection(MI) from
02nd
February2016 -16th February2016.
 Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 6FA GTG 297160
CI(Combustion Inspection) from 08th January 2016 -22nd
January 2016.
 Sembcorp Pulau Sakra Co-generation,Singapore - Frame 9FA GE Gas Turbine-Hot Gas Path
Inspection(HGPI) from 17th
December 15 -2nd
Januaryr 15.
 Rugarding Powertron RP2 Kota Kinabalu - Frame 6FA GE Gas Turbine-Major Inspection from 05th
November 15 -30th
November 15.
 Sepangar Bay Power Plant- Frame 6B GE Gas Turbine-HGPI from 16th
October 15 -30th
October 15.
 Prai Power PPSB-Force Outage(MI) Frame 9FA GE Gas Turbine-Force Outage from 29th
July 15 -
28th
September 15.
 Prai Power PPSB-Enchance Boroscope Inspection Frame 9FA GE Gas Turbine-Force Outage from 11th
June 15 -20th
June 15.
 Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 9E HGPI GT3 (Hot Gas Path
Inspection)& Generator(magic) from 23rd
February 2015 -24th
March 2015.
 Port Dickson Power Berhad-To do GE Gas Turbine 9E HGPI(Hot Gas Path Inspection) from 24th
October 2014 -07th
November 2014.
PROJECT INVOLVE&PAST
OFFSHORE PROJECT:SABAH WATER(Petronas platform)
Location: TembungoA(SBO-Kota Kinabalu)
 P130- Mol Pump retrieve activity, installation new pump, alignment check and commissioning activity
from 18th
March 2014-22nd
March2014.
 P130-Mol Pump installation, alignment check and commissioning activity from 18th
February 2014-22th
February2014.
 C620- Reciprocating compressor alignment check activity from 07th
January 2014-12th
January2014.
 Diesel Fire Water Pump 400 installation and alignment check activity from 17th
September 2013-25th
September2013.
 Diesel fire water pump P410 installation and alignment check activity from 13th
February-22nd
February
2013.
 Electric water pump(EWP)P330 installation and commissioning from 24th
July 2012-25th
July 2012.
Location: ERB West A(SBO-Kota Kinabalu)
 Crude Oil Transfer Pump P802 installation, alignment check and commissioning activity from 15th
June
2014-21st
June2014.
 Crude Oil Transfer Pump P804 installation, alignment check and commissioning activity from 26th
January
2014-01st
February2014.
 Service water pump P6770 retrieve activity/ G6720 alignment check activity 03rd
November 2013-06th
November 2013.
 Service water pump) P6770 retrieve activity from 20th
August 2013-21th
August 2013.
 Gearbox G6720 remove, major overhaul and installation activity from 05th
April 2013- 04th
May 2013.
 Service water pump(grunfos) P6760 installation and commissioning activity from 25th
Jan 2013-30th
Jan
2013.
 Crude oil transfer pump805 installation and alignment check activity from 27th
Dec 2012-05th
Jan 2013.
 Sea Water PumpP6770 installation and commissioning from 26th
July 2012-31st
July 2012.
 Sea Water PumpP6770 installation, alignment and commissioning activity from 02nd
March 2012-09th
March 2012.
Location: Samarang A, B,C(SBO-Labuan)
 Crude oil transfer pump P803 SMPB installation and alignment check activity from 31th July -05th
August
2014.
 Crude oil transfer pump P803 SMPA troubleshoot and alignment check activity from 28th
July 2014-30th
July 2014.
 Crude oil transfer pump P801 SMPB troubleshoots activity from 29th
June 2014-04thJuly 2014.
 Crude oil transfer pump P804A installation and commissioning activity 20th
April 2014-25th
April 2013.
 Crude oil transfer pump P805A installation and commissioning activity 01st
December 2013-07th
December
2013.
 Crude oil transfer pump P804A installation and commissioning/SMPA P801 alignment check activity 21st
October 2013-31th
October 2013.
 Crude oil transfer pump P801A installation and alignment check (engine to gearbox,gearbox to pump)
activity from 25th
August 2013-30th
August 2013.
 Crude oil transfer pump P805 B installation and alignment check activity from 26th
June 2013-01th
July
2013.
 Crude oil transfer pump P804A and P805A installation and alignment check activity from 11th
May 2013-
20th
May 2013.
 Crude oil transfer pump P803A installation and alignment check activity from 26th
March 2013- 29th
March
2013.
 Crude Oil Transfer Pump P804 B (NouvoPignone) installation and alignment check from 21th
Nov 2012-
27th
Nov 2012.
 Crude Oil Transfer Pump P801A installation and alignment check from 14th
October 2012-19th
October
2012.
 Sea Water PumpP3630A installation and commissioning from 15th
September 2012-22nd
September 2012.
 Crude Oil Transfer Pump P805B installation and alignment activity from 07th
August 2012-10th
August
2012.
 Sea Water Pump P3640A installation and commissioning activity from 10th
March 2012-13th
March 2012.
 Crude Oil Transfer PumpP810A installation and alignment activity from 03rd
February 2012-05th
February
2012.
Location: Sumandak A(SBO-Labuan)
 Sea Water Lift Pump 4090B installation and commissioning activity from 10th
October 2013- 13th
October
2013.
 Crude oil transfer pump P1320A, B and C installation and alignment check activity from 27th
September
2013- 03rd
October 2013.
 Sea Water Lift Pump P4090A installation and commissioning activity from 12th
Jan 2013-20th
Jan 2013.
 Sea water Lift Pump P4090A installation and retrieve back activity from 29rd
Nov 2012-10th
Dec 2012.
 Sea Water Lift Pump P4090B retrieves activity from 23rd
May 2012-24th
May 2012.
 Sea Water Lift Pump P4090C installation and commissioning activity from 25th
January 2012-29th
January
2012.
Location: Knnag B A(SBO-Labuan)
 Generator G7700 alignment check activity from 27th
March 2014- 28th
March 2014.
Offshore Project:SABAH WATER(Shell Platform)
Location: St Joseph A(SBO
 Fan cooler shaft and bearing replacement for K2400 1stage
OFFSHORE PROJECT:SARAWAK WATER (Petronas Platform)
Location: Temana A,B (SKO)
 K560C (Reciprocating) 2nd stage piston inspection from 14th
Dec2011-19th
Dec2011.
 K2400 (Booster) check and inspection Temana B from 30th
Sept 2011-11th
October 2011.
 K560 C (Gas Lift) check and inspection from 27th
August 2011- 30th
August 2011.
 K560A 8KPPM Gas Lift from 19th
Nov 2010 – 08th
Dec 2010.
 K560B 8KPPM Gas Lift from 08th
Sept 2010 – 21st
Sept 2010.
 K560 B alignment check from 16th
April 2010-18th
April 2010.
 K560A Lufkin Gearbox inspection from 19th
Nov 2010 – 08th
Dec 2010.
Location: Bayan A (SKO)
 K722 (Centrifugal Compressor LP & HP) Re-instatement from 26th
October 2011-06th
Sept 2011.
Location: Baram A,B (SKO)
 K7240 (Reciprocating Gas Lift) check and inspection Baram B from 14th
October 2011-20th
October 2011
 P13 alignment check Baram B from 27th
July 2011 – 27th
July 2011.
 P8020A alignment checkBaram A from 01st
Sept 2010-02nd
Sept 2010.
 P8020B alignment checkBaram A from 27th
August 2010-27th
August 2010.
Location: West Lutong (SKO)
 K7140 (Reciprocating Gas Lift) check and inspection from 17th
September 2011- 25th
September 2011.
 K7140 8KPPM (Reciprocating Gas Lift) from 14th
Dec 2010 – 18th
Dec 2010.
 K7140 valve leak inspection from 24th
March 2010- 26th
March 2010.
Location: D18 (SKO)
 P810A alignment check from 06th
Nov 2010 – 13th
Nov 2010.
 P810A Lufkin Gearbox inspection from 06th
Nov 2010 – 13th
Nov 2010.
 P801C alignment check from 10th
August 2010-14th
August 2010.
 P801C Lufkin Gearbox inspection from 10th
August 2010-14th
August 2010.
Location: Baronia B (SKO)
 P8210 alignment check from 18th
July 2011 – 22nd
July 2011.
 K7600 8KPPM (Reinjection Compressor) from 19th
Dec 2010 – 22nd
Dec 2010.
 P8210 Lufkin Gearbox inspection from 18th
July 2011 – 22nd
July 2011.
Location: Bokor A (SKO)
 k7700 8kppm (Reciprocating) from 29th
July 2011 – 04th
August 2011
 P802 alignment check from 29th
January 2011 to 01st
Feb 2011.
 K-7600 (Reciprocating) alignment check from 28th
August 2010-29th
August 2010.
Location: D35 (SKO)
 Solar Turbine D 35 (PG-A)-GT400, GT401, GT740 and GT790 for 8KPPM from 16th
Nov 2011-10th
Dec
2011.
Offshore Project:SARAWAK WATER(Murphy Oil Platform)
Location: West Patricia (SKO)
 G7710 Top End Overhaul from 06th
January 2010 – 20th
January 2010.
ONSHORE PROJECT
Location: Labuan Crude Oil Terminal (LCOT Shell)
 P102 Feed Pump installation and alignment check from 14th
Nov 2012-15th
Nov 2012.
 P100 Feed Pump installation and alignment check from 06th
Nov 2012-08th
Nov 2012.
 P102 Feed Pump inspection & major overhaul from 25th
Sep 2012-25th
Sep 2012.
 P102 Feed Pump alignment check from 17th
July 2012-18th
July 2012.
 P100 Feed Pump installation and alignment check from 15th
July 2012-15th
July 2012.
 P100 Feed Pump inspection and major overhaul from 07th
July 2012-13th
July 2012.
 P53 installation and alignment check from 27th
June 2012-28th
June 2012
 P101 Feed Pump installation and alignment check from 19th
June 2012-20th
June 2012.
Location: Labuan Gas Terminal (LGAST PETRONAS)
 K5675 (blower) troubleshoot activity from 05th
February 2014-08th
February 2014.
 P5560A (circulation pump)retrieval and installation activity from 08th
October 2012-10th
October 2012.
 K-2401 B(Booster Compressor) reinstatement activity from 27th
September 2012- 06th
October 2012.
Location: MLNG Bintulu
 Shutdown Module (1) for De Force Fan-5110, 20, 30 (Baby Steam Turbine) Major Overhaul from
02nd
August 2010- 24th
August 2010.
 Sea Cooling Water Pump P4205 Refurbishment from 17th
March 2010 – 01st
April 2010.
 Fire Water Pump P6030 Overhaul from 07th
– 19th
January, 2010.
 Fire Water Pump P6040 overhaul on 29th
September – 26th
October 2009.
 Shutdown Module (1) for De Force Fan-5110, 20, 30 (Baby Steam Turbine)Major Overhaul from 20th
July
2009-11th
August 2009.
 Ventilation Fan-(Belt and Bearing inspection) at (Module 5) from 13th
August 2009-08th
September 2009.
Location: Sejingkat Power Cooperation(Kuching)
 Module 4 shutdown for Minor Overhaul from 13th
June 2011-26th
June 2011.
-Feed water pump(B) check valve.
-Return Vale(ECV1201).
-Control Valve (Mv1201, Mv1401, Mv1501 and Mv1601).
-Automatic Control Valve(Lcv2302).
-Control valve for cooling(generator) piping.
 Module 4 Shutdown Steam Turbine Minor overhaul from 13th
June 11-26th
June 11.
 Module 2 Shutdown Steam Turbine Major Overhaul from 24th
Nov 08-17th
Dec 08.
 Module 2 Shutdown-Generator Major Inspection from 24th
Nov 08-17th
Dec 08
Location: Malaysian Peninsular
 TITAN PETROCHEMICAL (TanjungLangsat)-Blower-BR 1800(B),BR 1801(C),BR 1071(A),C-
221,C-220.-Major Overhaul(Mechanical seal services & Bearing Inspection.from 03rd
October 2010- 02nd
November 2010.
-(silo mixer)-110(A),110(B),201,202-Mechanical Seal Services & belting changed new from 03rd
October
2010- 02nd
November 2010.
 NUR KULIM (Kedah)- Generator NO 2 Major Overhaul from 07th
December 2009-14th
December 2009.
 NUR KULIM (Kedah)-Gas Turbine 2&3(Hot Gas Path Inspection) from 03rd
November 2009-24th
November 2009.
 NUR (KULIM) - Air fan cooler(Philadelphia) inspection from 26th
November 2009- 28th
November 2009.
 PPM (Melaka) -K30230 (EBARA Centrifugal Compressor)-Minor inspection, governor services and
alignment check.
-K31203 C HP Compressor-(2nd
stage)-Major Inspection.
-K3120 C LP Compressor-(2nd
& 4th
stage)-Major Inspection.
-K3120 B LP Compressor-(2nd
& 4th
stage)-Major Inspection.
 CUF Kerteh (Terengganu) - GE Frame 6 GTG Combustion Inspection August 2010 as a millwright.
 CUF Kerteh (Terengganu) - Dec 2008 involved in HGPI U#1 job as millwright.
 PETLIN (TA) –Hyper(nouvopignone) and reciprocating LD1-11-K-102 & K-103-1&2) Major Overhaul
from 18th
May 2009-19th
un 2009.
 PETLIN(TA)- (LD1-13-X-207,LD1-31-X 301,303,LD1-32-X 350,351,352,353,354,633,LD1-33-X 635
A/B(Major Inspection) from 18th
May 2009-19th
Jun 2009.
 PETLIN(TA) - Water Pump P256A & B Overhaul and alignment.
OVERSEA PROJECT
Location: DAS ISLAND, ABU DHABI
 Being a Maintenance Supervisor during Train 1 REMitsubishi Steam Turbine & Centrifugal Compressor
Major and Minor Overhaul year 2011 from 28th
March 2011 -21st
April 2011.
-1 KT 101-Operation Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
-6 KT 101-Opertion Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
-1 KT 102-Opertion Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
-1 KT 101-Minor Overhaul HP Compressor.
 Being a Maintenance Supervisor during Train 2 REMitsubishi Steam Turbine & Centrifugal Compressor
Major and Minor Overhaul activity from 07th
April 2012 -10th
May 2012.
-1 KT 101-Operating Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
-6 KT 101-Operting Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
-1 KT 102-Operting Cylinder, Trip TrottleValve(TTV), Gavenor Valve.
COURSE ATTENDED
 Precision tools & equipment course
 Rigging & slinging course
 Safety awareness course
 Confine space safety course(ITC Singapore Workforce skills Qualification)
 Basic first aid
 Alignment course using dial guage, pda and rotalign(Laser)
 Permit to work (Pertronas)
Valid from 24th
October2012 -24th
October 2015.
 PETRONAS PTW Applicant Course
 Bolting course(Hytorc, Riverhawk ,Ith).
 NTSP Level 1(Niosh Tenaga Safety Passport)

SUPPLEMENTARY
Basic Salary Negociate
Expected Monthly Basic Salary
Possess own transport Yes
Availability 1 month notice
Willing to traveling Yes
REFERENCES
1. MARTIN GANJAR
BME/3003 (Rotating – Roving Gang)
SKO Maintenance Engineering Department
Email: martinganjar@petronas.com.my
Contact No:019-8552403.
2. JURGAO ANAK MANGAI.
Mechanical Supervisor
Granite Services International(Malaysia)
Email:Jurgao.Mangai@ge.com/jurgao.mangai@gmail.com
Contact No:016-8119359
3. Edwin Cheng(Rotating Engineer)
PCSB SKO SRM/323
Maintenance Engineering Department
Cont No: 012-7542200
Email: Edwin_cheng@petronas.com.my,
4.) MR. MuazBinNordin
ServiceEngineer
SERBA DINAMIK SDN BHD
Direct Line: 087-411063
Email: muaz@e-serbadk.

More Related Content

What's hot

Resume- Rotating Equipment supervisor
Resume- Rotating Equipment supervisorResume- Rotating Equipment supervisor
Resume- Rotating Equipment supervisornitin mokal
 
CV as Maintenance Technician (Armando Malasan)
CV as Maintenance Technician (Armando Malasan)CV as Maintenance Technician (Armando Malasan)
CV as Maintenance Technician (Armando Malasan)Armando Malasan
 
SuryaMohan_Resume_2016
SuryaMohan_Resume_2016SuryaMohan_Resume_2016
SuryaMohan_Resume_2016Surya Mohan
 
00-Mechanical Technician---
00-Mechanical Technician---00-Mechanical Technician---
00-Mechanical Technician---rohan contractor
 
Presentation for SPCO
Presentation for SPCOPresentation for SPCO
Presentation for SPCOPerabakaran .
 
Mario V. Clariza Resume Automotive Technician
Mario V. Clariza Resume Automotive TechnicianMario V. Clariza Resume Automotive Technician
Mario V. Clariza Resume Automotive TechnicianMario Clariza
 
Selvan CM Technician CV
Selvan CM Technician CVSelvan CM Technician CV
Selvan CM Technician CVkalki selvan
 
RESUME - Abhay Paranjape
RESUME - Abhay ParanjapeRESUME - Abhay Paranjape
RESUME - Abhay ParanjapeAbhay Paranjape
 
Resume of Marc Richards - Mechanical Supervisor
Resume of Marc Richards - Mechanical SupervisorResume of Marc Richards - Mechanical Supervisor
Resume of Marc Richards - Mechanical SupervisorMarc Richards
 
Executive Engineer with 5 Years Exp. in Maintenance & PPC
Executive Engineer with 5 Years Exp. in Maintenance & PPC Executive Engineer with 5 Years Exp. in Maintenance & PPC
Executive Engineer with 5 Years Exp. in Maintenance & PPC Makarand Pachpande
 
SuryaMohan_Resume_2015
SuryaMohan_Resume_2015SuryaMohan_Resume_2015
SuryaMohan_Resume_2015Surya Mohan
 
Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)JOHN PRINCE
 
Nasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNaseem Ansari
 
23-01-2015(Millwright Technicion)
23-01-2015(Millwright Technicion)23-01-2015(Millwright Technicion)
23-01-2015(Millwright Technicion)Shine K U
 

What's hot (20)

Resume- Rotating Equipment supervisor
Resume- Rotating Equipment supervisorResume- Rotating Equipment supervisor
Resume- Rotating Equipment supervisor
 
CV as Maintenance Technician (Armando Malasan)
CV as Maintenance Technician (Armando Malasan)CV as Maintenance Technician (Armando Malasan)
CV as Maintenance Technician (Armando Malasan)
 
SuryaMohan_Resume_2016
SuryaMohan_Resume_2016SuryaMohan_Resume_2016
SuryaMohan_Resume_2016
 
00-Mechanical Technician---
00-Mechanical Technician---00-Mechanical Technician---
00-Mechanical Technician---
 
mechanical technician (1)
mechanical technician (1)mechanical technician (1)
mechanical technician (1)
 
sourabh_jain
sourabh_jainsourabh_jain
sourabh_jain
 
Presentation for SPCO
Presentation for SPCOPresentation for SPCO
Presentation for SPCO
 
RESUME
RESUMERESUME
RESUME
 
resume-mr.vidallo
resume-mr.vidalloresume-mr.vidallo
resume-mr.vidallo
 
Mario V. Clariza Resume Automotive Technician
Mario V. Clariza Resume Automotive TechnicianMario V. Clariza Resume Automotive Technician
Mario V. Clariza Resume Automotive Technician
 
Selvan CM Technician CV
Selvan CM Technician CVSelvan CM Technician CV
Selvan CM Technician CV
 
RESUME - Abhay Paranjape
RESUME - Abhay ParanjapeRESUME - Abhay Paranjape
RESUME - Abhay Paranjape
 
Resume of Marc Richards - Mechanical Supervisor
Resume of Marc Richards - Mechanical SupervisorResume of Marc Richards - Mechanical Supervisor
Resume of Marc Richards - Mechanical Supervisor
 
Executive Engineer with 5 Years Exp. in Maintenance & PPC
Executive Engineer with 5 Years Exp. in Maintenance & PPC Executive Engineer with 5 Years Exp. in Maintenance & PPC
Executive Engineer with 5 Years Exp. in Maintenance & PPC
 
SuryaMohan_Resume_2015
SuryaMohan_Resume_2015SuryaMohan_Resume_2015
SuryaMohan_Resume_2015
 
Mohamed Zubair Sharieff
Mohamed Zubair SharieffMohamed Zubair Sharieff
Mohamed Zubair Sharieff
 
Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)Resume of John Prince (Rotating Equipment Technician)
Resume of John Prince (Rotating Equipment Technician)
 
RESUME
RESUMERESUME
RESUME
 
Nasheem CV- Commissioning Technician
Nasheem CV- Commissioning TechnicianNasheem CV- Commissioning Technician
Nasheem CV- Commissioning Technician
 
23-01-2015(Millwright Technicion)
23-01-2015(Millwright Technicion)23-01-2015(Millwright Technicion)
23-01-2015(Millwright Technicion)
 

Viewers also liked

Trish M. Patton Resume
Trish M. Patton ResumeTrish M. Patton Resume
Trish M. Patton Resumetrishpatton
 
A rosario resume_2013_a
A rosario resume_2013_aA rosario resume_2013_a
A rosario resume_2013_avsanchez1963
 
Práctica VI
Práctica VIPráctica VI
Práctica VIlaurafh
 
India is Incredible - Have a Look
India is Incredible - Have a LookIndia is Incredible - Have a Look
India is Incredible - Have a LookAshok Kumar Patra
 
Resume for plant head suresh khake
Resume for plant head suresh khakeResume for plant head suresh khake
Resume for plant head suresh khakesureshkhake
 
Sonu resume 2015
Sonu resume 2015Sonu resume 2015
Sonu resume 2015Sonu Singh
 
Storytime Travel Series: South America
Storytime Travel Series: South AmericaStorytime Travel Series: South America
Storytime Travel Series: South AmericaSamantha Colwell
 
Protocolo de negociacion japon (1) (1)
Protocolo de negociacion japon (1) (1)Protocolo de negociacion japon (1) (1)
Protocolo de negociacion japon (1) (1)blanca1919
 
Hannah Ungricht Portfolio
Hannah Ungricht PortfolioHannah Ungricht Portfolio
Hannah Ungricht PortfolioHannah Ungricht
 
Mapa lingüístico de italia
Mapa lingüístico de italiaMapa lingüístico de italia
Mapa lingüístico de italiaDavidC99
 
Excellent Print advertisements
  Excellent Print advertisements   Excellent Print advertisements
Excellent Print advertisements Guerillateacher
 
alltel 3q 07_supplement
alltel  3q 07_supplementalltel  3q 07_supplement
alltel 3q 07_supplementfinance27
 
Sixth Grade Writing Curriculum Map
Sixth Grade Writing Curriculum Map Sixth Grade Writing Curriculum Map
Sixth Grade Writing Curriculum Map Isaac_Schools_5
 
Genre, audience, purpose and style
Genre, audience, purpose and styleGenre, audience, purpose and style
Genre, audience, purpose and styleGuerillateacher
 

Viewers also liked (20)

Trish M. Patton Resume
Trish M. Patton ResumeTrish M. Patton Resume
Trish M. Patton Resume
 
A rosario resume_2013_a
A rosario resume_2013_aA rosario resume_2013_a
A rosario resume_2013_a
 
Práctica VI
Práctica VIPráctica VI
Práctica VI
 
TOEFL VOCABULARY
TOEFL VOCABULARYTOEFL VOCABULARY
TOEFL VOCABULARY
 
India is Incredible - Have a Look
India is Incredible - Have a LookIndia is Incredible - Have a Look
India is Incredible - Have a Look
 
Resume for plant head suresh khake
Resume for plant head suresh khakeResume for plant head suresh khake
Resume for plant head suresh khake
 
Sonu resume 2015
Sonu resume 2015Sonu resume 2015
Sonu resume 2015
 
Storytime Travel Series: South America
Storytime Travel Series: South AmericaStorytime Travel Series: South America
Storytime Travel Series: South America
 
TOEFL VOCABULARY
TOEFL VOCABULARYTOEFL VOCABULARY
TOEFL VOCABULARY
 
What is marketing
What is marketingWhat is marketing
What is marketing
 
Protocolo de negociacion japon (1) (1)
Protocolo de negociacion japon (1) (1)Protocolo de negociacion japon (1) (1)
Protocolo de negociacion japon (1) (1)
 
Hannah Ungricht Portfolio
Hannah Ungricht PortfolioHannah Ungricht Portfolio
Hannah Ungricht Portfolio
 
Mapa lingüístico de italia
Mapa lingüístico de italiaMapa lingüístico de italia
Mapa lingüístico de italia
 
Selected works by nayj
Selected works by nayjSelected works by nayj
Selected works by nayj
 
Excellent Print advertisements
  Excellent Print advertisements   Excellent Print advertisements
Excellent Print advertisements
 
alltel 3q 07_supplement
alltel  3q 07_supplementalltel  3q 07_supplement
alltel 3q 07_supplement
 
13A Portfolio
13A Portfolio13A Portfolio
13A Portfolio
 
Sixth Grade Writing Curriculum Map
Sixth Grade Writing Curriculum Map Sixth Grade Writing Curriculum Map
Sixth Grade Writing Curriculum Map
 
Business size
Business sizeBusiness size
Business size
 
Genre, audience, purpose and style
Genre, audience, purpose and styleGenre, audience, purpose and style
Genre, audience, purpose and style
 

Similar to SEBASTIAN RESUME (20)

CV2016 NasseerQusyairi
CV2016 NasseerQusyairiCV2016 NasseerQusyairi
CV2016 NasseerQusyairi
 
Rahmad Hidayat CV Update_2
Rahmad Hidayat CV Update_2Rahmad Hidayat CV Update_2
Rahmad Hidayat CV Update_2
 
Mohd Fadhil - Resume
Mohd Fadhil - ResumeMohd Fadhil - Resume
Mohd Fadhil - Resume
 
Cv rici johana aux spv
Cv rici johana aux spvCv rici johana aux spv
Cv rici johana aux spv
 
Willy Jr CV - Sept 2016
Willy Jr CV - Sept 2016Willy Jr CV - Sept 2016
Willy Jr CV - Sept 2016
 
1 - NEW RESUME OKT 2016
1 - NEW RESUME OKT 20161 - NEW RESUME OKT 2016
1 - NEW RESUME OKT 2016
 
Alaa_Abdul_Aziz_Ibrahim_Zaki_-_CV_GASCO_1_
Alaa_Abdul_Aziz_Ibrahim_Zaki_-_CV_GASCO_1_Alaa_Abdul_Aziz_Ibrahim_Zaki_-_CV_GASCO_1_
Alaa_Abdul_Aziz_Ibrahim_Zaki_-_CV_GASCO_1_
 
ASF CV 2016
ASF CV 2016ASF CV 2016
ASF CV 2016
 
K BHASKARA ELECTRICAL LEAD RESUME
K BHASKARA ELECTRICAL LEAD RESUMEK BHASKARA ELECTRICAL LEAD RESUME
K BHASKARA ELECTRICAL LEAD RESUME
 
Jordan CV
Jordan CVJordan CV
Jordan CV
 
assistance engineer rsume
assistance engineer  rsumeassistance engineer  rsume
assistance engineer rsume
 
Suntharesar Shummugham Resume
Suntharesar Shummugham ResumeSuntharesar Shummugham Resume
Suntharesar Shummugham Resume
 
Iqbal cv...final
Iqbal cv...finalIqbal cv...final
Iqbal cv...final
 
JEFF CV
JEFF CVJEFF CV
JEFF CV
 
Mohamad Rizal resume
Mohamad Rizal resumeMohamad Rizal resume
Mohamad Rizal resume
 
Resume Michael James Piagola
Resume Michael James PiagolaResume Michael James Piagola
Resume Michael James Piagola
 
CV Daru S
CV Daru SCV Daru S
CV Daru S
 
CV Ngurah Ari updated 1st April 2016 Rev1
CV Ngurah Ari updated 1st April 2016 Rev1CV Ngurah Ari updated 1st April 2016 Rev1
CV Ngurah Ari updated 1st April 2016 Rev1
 
CVBGS AJP 2016
CVBGS AJP 2016CVBGS AJP 2016
CVBGS AJP 2016
 
CV_Ivan Shamonaev_Nov_2015
CV_Ivan Shamonaev_Nov_2015CV_Ivan Shamonaev_Nov_2015
CV_Ivan Shamonaev_Nov_2015
 

Recently uploaded

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

SEBASTIAN RESUME

  • 1. SEBASTIAN APENG, No 21,Kampung Sampun Gerunggang, 94600 Asajaya,Kota Samarahan, Sarawak,Malaysia. Contact No: +60111-9870084 To Whom It May Concern, I believe it is interesting and challenging to pursue a career and professional growth in your organization. 2. Currently, I’m working with GRANITE SERVICES INTERNATIONAL as a Mechanical Technician since October 2014 and my previous company is SERBA DINAMIK Sdn Bhd as Rotating Equipment Mechanical/Workshop Supervisor since July 2008 which involved in various plant shutdown, project and offshore maintenance services. I’m familiar with work permit system HSE policy. 3. You can expect the hard work ethic that I will bring to your organization to be a valuable asset. I will be sure provided you with high quality worthy of ever increasing responsibility. 4. Herewith I enclosed my resume as a first step in exploring for possibilities of employment with your organization. Greatly appreciate your time and consideration. I hope to meet with a favorable response. Best Regards, SEBASTIAN APENG.
  • 2. RESUME SEBASTIAN APENG Telephone no: +60111-9870084 E-mail Address:sebt84@yahoo.com :sebastiansebt@gmail.com PERSONAL PARTICULARS DATE OF BIRTH : 20TH MARCH 1984 PLACE OF BIRTH : KUCHING, SARAWAK NATIONALITY : MALAYSIAN AGE : 31 YEARS OLD MARITAL STATUS : MARRIED RELIGION : CHRISTIAN RACE : IBAN/BIDAYUH PERM ADDRESS : 21, KAMPUNG SAMPUN GERUNGGANG,94600 ASAJAYA, KOTA SAMARAHAN, SARAWAK,MALAYSIA. HEALTH : EXCELLENT OBJECTIVE Willing to do the job as a maintenance technician in a reputed organization to utilize my skills and knowledge and experience for the growth of the organization. ACADEMIC QUALIFICATIONS  Competence Certificate in Rotating Equipment Maintenance Specialist, 2008 (Certificate Of Basic engineering skills and Basic plant maintenance) The City & Guilds of London Institute.  Certificate in Industrial Technician Level 1 & 2 , 2004 (Tools & Die Making) Kota Samarahan Industrial Training Institute (ILPKS) PERSONALITY  Knowledge & compliance of Health, Safety & Environment Policy.  Familiar & knowledge of full compliance of PPE at work site.  Excellent cross-cultural communication skills.  Committed and enthusiastic in solving work related problems with in depth understanding of employee-manager's duty and company culture.  Able to work under critical time pressure & willing to learn.  Computer skill Ms office  Good communication and writing in English/BahasaMelayu.  Familiar with standard code API/ASME.  Familiar & comply of work permit systems.
  • 3. WORKING EXPERIENCES OCTHOBER 2014-Present GRANITE SERVICES INTERNATIONAL(M) Mechanical Technician  Work with Supervisor/Maintenance teams to do equipment service/repair, disassembly/assembly various types of rotating equipment such as GE Gas Turbine HGPI/MI (Frame 5,6b,6Fa,7,9E,9FA)steam turbine, generator, pump, compressor at power plant and oil and gas plant.  To perform shaft alignment on driven Rotating Equipment.  To perform troubleshooting on mechanical equipment.  Respond to standby/call out for emergency/urgent repairs outside working hours.  To perform any task given / instructed by immediate superior and the management.  EHS and quality is meeting as per company and costumer expectation. Nov 2013 – Sept 14 SERBA DINAMIK SDN BHD (LABUAN SERVICE CENTRE) Senior Mechanical Technician/Mechanical Workshop Supervisor Responsibilities: .  To assist and report duty to Engineer for Workshop activity.  Work with maintenance teams to investigate and troubleshoot various types of rotating equipment such as pump, compressor, turbine at workshop, plant and offshore.  Specify and review drawings and data for rotating equipment for offshore and plant applications.  Perform alignment for rotating equipment as a requirement of maintenance procedure to prevent vibration during startup and operation.  Develop and execute QA/QC standards for rotating equipment.  Supervised repair and equipment installation activities in the workshop and plant.  Preparation of requisitions for Rotating Equipment packages.  Preparing inspection reports, commissioning procedure, supervising other maintenance activities specific to the rotating equipment technical area.  Maintains safe and clean working environment by enforcing procedures, rules and regulations.  Ensure EHS and quality is meeting as per company and costumer expectation. Feb 2012 – Oct 2013 SERBA DINAMIK SDN BHD (LABUAN SERVICE CENTRE) Senior Mechanical Technician (Mechanical Coordinator)-offshore/onshore. Responsibilities:  To perform maintenance and repairs of multistage pumps, compressors, steam turbines, gas turbine and standby generators and prepare report in offshore and onshore.  To assist supervisor for any task/equipment repair, service, installation commissioning at offshore /onshore.  To perform shaft alignment on driven Rotating Equipment.  To perform troubleshooting on mechanical equipment  To carry out pressure test  To Conduct on Job Training (OJT) for junior technicians  Respond to standby/call out for emergency/urgent repairs outside working hours.  To perform any task given / instructed by immediate superior and the management.
  • 4. Oct 2008 – Nov 2012 SERBA DINAMIK SDN BHD (BINTULU SERVICE CENTRE) Junior Rotating Equipment Maintenance Executive/Mechanical Technician.-offshore/ onshore. Supply Manpower for ROVING GANG Crew SKO (Sarawak Water). Responsibilities:  To assist and perform maintenance and repairs of rotating equipment such as multistage pumps, compressors, steam turbines, gas turbine and standby generators and prepare report.  To assist and to perform shaft alignment on driven Rotating Equipment.  To assist and to perform troubleshooting on mechanical equipment  Respond to standby/call out for emergency/urgent repairs outside working hours.  To perform any other task given/instructed by immediate Superior and the management. PROJECT INVOLVE &PRESENT ONSITE PROJECT-POWER PLANT & OIL AND GAS PLANT.  Sepangar Bay Power Plant- Frame 6B GE Gas Turbine-HGPI from 26th March 2016 –05th April 2016 .  Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 9E HGPI GT4(Hot Gas Path Inspection) from 25rd February 2016 -22th March 2016.  Thailand , Rayong GPSC CUP 1 Frame 6BGT 14 GE Gas Turbine-Major Inspection(MI) from 02nd February2016 -16th February2016.  Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 6FA GTG 297160 CI(Combustion Inspection) from 08th January 2016 -22nd January 2016.  Sembcorp Pulau Sakra Co-generation,Singapore - Frame 9FA GE Gas Turbine-Hot Gas Path Inspection(HGPI) from 17th December 15 -2nd Januaryr 15.  Rugarding Powertron RP2 Kota Kinabalu - Frame 6FA GE Gas Turbine-Major Inspection from 05th November 15 -30th November 15.  Sepangar Bay Power Plant- Frame 6B GE Gas Turbine-HGPI from 16th October 15 -30th October 15.  Prai Power PPSB-Force Outage(MI) Frame 9FA GE Gas Turbine-Force Outage from 29th July 15 - 28th September 15.  Prai Power PPSB-Enchance Boroscope Inspection Frame 9FA GE Gas Turbine-Force Outage from 11th June 15 -20th June 15.  Exxon Mobil Jurong Island(Singapore)-To do GE Gas Turbine 9E HGPI GT3 (Hot Gas Path Inspection)& Generator(magic) from 23rd February 2015 -24th March 2015.  Port Dickson Power Berhad-To do GE Gas Turbine 9E HGPI(Hot Gas Path Inspection) from 24th October 2014 -07th November 2014. PROJECT INVOLVE&PAST OFFSHORE PROJECT:SABAH WATER(Petronas platform) Location: TembungoA(SBO-Kota Kinabalu)  P130- Mol Pump retrieve activity, installation new pump, alignment check and commissioning activity from 18th March 2014-22nd March2014.  P130-Mol Pump installation, alignment check and commissioning activity from 18th February 2014-22th February2014.  C620- Reciprocating compressor alignment check activity from 07th January 2014-12th January2014.  Diesel Fire Water Pump 400 installation and alignment check activity from 17th September 2013-25th September2013.  Diesel fire water pump P410 installation and alignment check activity from 13th February-22nd February 2013.  Electric water pump(EWP)P330 installation and commissioning from 24th July 2012-25th July 2012.
  • 5. Location: ERB West A(SBO-Kota Kinabalu)  Crude Oil Transfer Pump P802 installation, alignment check and commissioning activity from 15th June 2014-21st June2014.  Crude Oil Transfer Pump P804 installation, alignment check and commissioning activity from 26th January 2014-01st February2014.  Service water pump P6770 retrieve activity/ G6720 alignment check activity 03rd November 2013-06th November 2013.  Service water pump) P6770 retrieve activity from 20th August 2013-21th August 2013.  Gearbox G6720 remove, major overhaul and installation activity from 05th April 2013- 04th May 2013.  Service water pump(grunfos) P6760 installation and commissioning activity from 25th Jan 2013-30th Jan 2013.  Crude oil transfer pump805 installation and alignment check activity from 27th Dec 2012-05th Jan 2013.  Sea Water PumpP6770 installation and commissioning from 26th July 2012-31st July 2012.  Sea Water PumpP6770 installation, alignment and commissioning activity from 02nd March 2012-09th March 2012. Location: Samarang A, B,C(SBO-Labuan)  Crude oil transfer pump P803 SMPB installation and alignment check activity from 31th July -05th August 2014.  Crude oil transfer pump P803 SMPA troubleshoot and alignment check activity from 28th July 2014-30th July 2014.  Crude oil transfer pump P801 SMPB troubleshoots activity from 29th June 2014-04thJuly 2014.  Crude oil transfer pump P804A installation and commissioning activity 20th April 2014-25th April 2013.  Crude oil transfer pump P805A installation and commissioning activity 01st December 2013-07th December 2013.  Crude oil transfer pump P804A installation and commissioning/SMPA P801 alignment check activity 21st October 2013-31th October 2013.  Crude oil transfer pump P801A installation and alignment check (engine to gearbox,gearbox to pump) activity from 25th August 2013-30th August 2013.  Crude oil transfer pump P805 B installation and alignment check activity from 26th June 2013-01th July 2013.  Crude oil transfer pump P804A and P805A installation and alignment check activity from 11th May 2013- 20th May 2013.  Crude oil transfer pump P803A installation and alignment check activity from 26th March 2013- 29th March 2013.  Crude Oil Transfer Pump P804 B (NouvoPignone) installation and alignment check from 21th Nov 2012- 27th Nov 2012.  Crude Oil Transfer Pump P801A installation and alignment check from 14th October 2012-19th October 2012.  Sea Water PumpP3630A installation and commissioning from 15th September 2012-22nd September 2012.  Crude Oil Transfer Pump P805B installation and alignment activity from 07th August 2012-10th August 2012.  Sea Water Pump P3640A installation and commissioning activity from 10th March 2012-13th March 2012.  Crude Oil Transfer PumpP810A installation and alignment activity from 03rd February 2012-05th February 2012. Location: Sumandak A(SBO-Labuan)  Sea Water Lift Pump 4090B installation and commissioning activity from 10th October 2013- 13th October 2013.  Crude oil transfer pump P1320A, B and C installation and alignment check activity from 27th September 2013- 03rd October 2013.  Sea Water Lift Pump P4090A installation and commissioning activity from 12th Jan 2013-20th Jan 2013.  Sea water Lift Pump P4090A installation and retrieve back activity from 29rd Nov 2012-10th Dec 2012.  Sea Water Lift Pump P4090B retrieves activity from 23rd May 2012-24th May 2012.  Sea Water Lift Pump P4090C installation and commissioning activity from 25th January 2012-29th January 2012.
  • 6. Location: Knnag B A(SBO-Labuan)  Generator G7700 alignment check activity from 27th March 2014- 28th March 2014. Offshore Project:SABAH WATER(Shell Platform) Location: St Joseph A(SBO  Fan cooler shaft and bearing replacement for K2400 1stage OFFSHORE PROJECT:SARAWAK WATER (Petronas Platform) Location: Temana A,B (SKO)  K560C (Reciprocating) 2nd stage piston inspection from 14th Dec2011-19th Dec2011.  K2400 (Booster) check and inspection Temana B from 30th Sept 2011-11th October 2011.  K560 C (Gas Lift) check and inspection from 27th August 2011- 30th August 2011.  K560A 8KPPM Gas Lift from 19th Nov 2010 – 08th Dec 2010.  K560B 8KPPM Gas Lift from 08th Sept 2010 – 21st Sept 2010.  K560 B alignment check from 16th April 2010-18th April 2010.  K560A Lufkin Gearbox inspection from 19th Nov 2010 – 08th Dec 2010. Location: Bayan A (SKO)  K722 (Centrifugal Compressor LP & HP) Re-instatement from 26th October 2011-06th Sept 2011. Location: Baram A,B (SKO)  K7240 (Reciprocating Gas Lift) check and inspection Baram B from 14th October 2011-20th October 2011  P13 alignment check Baram B from 27th July 2011 – 27th July 2011.  P8020A alignment checkBaram A from 01st Sept 2010-02nd Sept 2010.  P8020B alignment checkBaram A from 27th August 2010-27th August 2010. Location: West Lutong (SKO)  K7140 (Reciprocating Gas Lift) check and inspection from 17th September 2011- 25th September 2011.  K7140 8KPPM (Reciprocating Gas Lift) from 14th Dec 2010 – 18th Dec 2010.  K7140 valve leak inspection from 24th March 2010- 26th March 2010. Location: D18 (SKO)  P810A alignment check from 06th Nov 2010 – 13th Nov 2010.  P810A Lufkin Gearbox inspection from 06th Nov 2010 – 13th Nov 2010.  P801C alignment check from 10th August 2010-14th August 2010.  P801C Lufkin Gearbox inspection from 10th August 2010-14th August 2010. Location: Baronia B (SKO)  P8210 alignment check from 18th July 2011 – 22nd July 2011.  K7600 8KPPM (Reinjection Compressor) from 19th Dec 2010 – 22nd Dec 2010.  P8210 Lufkin Gearbox inspection from 18th July 2011 – 22nd July 2011. Location: Bokor A (SKO)  k7700 8kppm (Reciprocating) from 29th July 2011 – 04th August 2011  P802 alignment check from 29th January 2011 to 01st Feb 2011.  K-7600 (Reciprocating) alignment check from 28th August 2010-29th August 2010. Location: D35 (SKO)  Solar Turbine D 35 (PG-A)-GT400, GT401, GT740 and GT790 for 8KPPM from 16th Nov 2011-10th Dec 2011. Offshore Project:SARAWAK WATER(Murphy Oil Platform) Location: West Patricia (SKO)  G7710 Top End Overhaul from 06th January 2010 – 20th January 2010.
  • 7. ONSHORE PROJECT Location: Labuan Crude Oil Terminal (LCOT Shell)  P102 Feed Pump installation and alignment check from 14th Nov 2012-15th Nov 2012.  P100 Feed Pump installation and alignment check from 06th Nov 2012-08th Nov 2012.  P102 Feed Pump inspection & major overhaul from 25th Sep 2012-25th Sep 2012.  P102 Feed Pump alignment check from 17th July 2012-18th July 2012.  P100 Feed Pump installation and alignment check from 15th July 2012-15th July 2012.  P100 Feed Pump inspection and major overhaul from 07th July 2012-13th July 2012.  P53 installation and alignment check from 27th June 2012-28th June 2012  P101 Feed Pump installation and alignment check from 19th June 2012-20th June 2012. Location: Labuan Gas Terminal (LGAST PETRONAS)  K5675 (blower) troubleshoot activity from 05th February 2014-08th February 2014.  P5560A (circulation pump)retrieval and installation activity from 08th October 2012-10th October 2012.  K-2401 B(Booster Compressor) reinstatement activity from 27th September 2012- 06th October 2012. Location: MLNG Bintulu  Shutdown Module (1) for De Force Fan-5110, 20, 30 (Baby Steam Turbine) Major Overhaul from 02nd August 2010- 24th August 2010.  Sea Cooling Water Pump P4205 Refurbishment from 17th March 2010 – 01st April 2010.  Fire Water Pump P6030 Overhaul from 07th – 19th January, 2010.  Fire Water Pump P6040 overhaul on 29th September – 26th October 2009.  Shutdown Module (1) for De Force Fan-5110, 20, 30 (Baby Steam Turbine)Major Overhaul from 20th July 2009-11th August 2009.  Ventilation Fan-(Belt and Bearing inspection) at (Module 5) from 13th August 2009-08th September 2009. Location: Sejingkat Power Cooperation(Kuching)  Module 4 shutdown for Minor Overhaul from 13th June 2011-26th June 2011. -Feed water pump(B) check valve. -Return Vale(ECV1201). -Control Valve (Mv1201, Mv1401, Mv1501 and Mv1601). -Automatic Control Valve(Lcv2302). -Control valve for cooling(generator) piping.  Module 4 Shutdown Steam Turbine Minor overhaul from 13th June 11-26th June 11.  Module 2 Shutdown Steam Turbine Major Overhaul from 24th Nov 08-17th Dec 08.  Module 2 Shutdown-Generator Major Inspection from 24th Nov 08-17th Dec 08 Location: Malaysian Peninsular  TITAN PETROCHEMICAL (TanjungLangsat)-Blower-BR 1800(B),BR 1801(C),BR 1071(A),C- 221,C-220.-Major Overhaul(Mechanical seal services & Bearing Inspection.from 03rd October 2010- 02nd November 2010. -(silo mixer)-110(A),110(B),201,202-Mechanical Seal Services & belting changed new from 03rd October 2010- 02nd November 2010.  NUR KULIM (Kedah)- Generator NO 2 Major Overhaul from 07th December 2009-14th December 2009.  NUR KULIM (Kedah)-Gas Turbine 2&3(Hot Gas Path Inspection) from 03rd November 2009-24th November 2009.  NUR (KULIM) - Air fan cooler(Philadelphia) inspection from 26th November 2009- 28th November 2009.  PPM (Melaka) -K30230 (EBARA Centrifugal Compressor)-Minor inspection, governor services and alignment check. -K31203 C HP Compressor-(2nd stage)-Major Inspection. -K3120 C LP Compressor-(2nd & 4th stage)-Major Inspection. -K3120 B LP Compressor-(2nd & 4th stage)-Major Inspection.  CUF Kerteh (Terengganu) - GE Frame 6 GTG Combustion Inspection August 2010 as a millwright.  CUF Kerteh (Terengganu) - Dec 2008 involved in HGPI U#1 job as millwright.  PETLIN (TA) –Hyper(nouvopignone) and reciprocating LD1-11-K-102 & K-103-1&2) Major Overhaul from 18th May 2009-19th un 2009.  PETLIN(TA)- (LD1-13-X-207,LD1-31-X 301,303,LD1-32-X 350,351,352,353,354,633,LD1-33-X 635 A/B(Major Inspection) from 18th May 2009-19th Jun 2009.  PETLIN(TA) - Water Pump P256A & B Overhaul and alignment.
  • 8. OVERSEA PROJECT Location: DAS ISLAND, ABU DHABI  Being a Maintenance Supervisor during Train 1 REMitsubishi Steam Turbine & Centrifugal Compressor Major and Minor Overhaul year 2011 from 28th March 2011 -21st April 2011. -1 KT 101-Operation Cylinder, Trip TrottleValve(TTV), Gavenor Valve. -6 KT 101-Opertion Cylinder, Trip TrottleValve(TTV), Gavenor Valve. -1 KT 102-Opertion Cylinder, Trip TrottleValve(TTV), Gavenor Valve. -1 KT 101-Minor Overhaul HP Compressor.  Being a Maintenance Supervisor during Train 2 REMitsubishi Steam Turbine & Centrifugal Compressor Major and Minor Overhaul activity from 07th April 2012 -10th May 2012. -1 KT 101-Operating Cylinder, Trip TrottleValve(TTV), Gavenor Valve. -6 KT 101-Operting Cylinder, Trip TrottleValve(TTV), Gavenor Valve. -1 KT 102-Operting Cylinder, Trip TrottleValve(TTV), Gavenor Valve. COURSE ATTENDED  Precision tools & equipment course  Rigging & slinging course  Safety awareness course  Confine space safety course(ITC Singapore Workforce skills Qualification)  Basic first aid  Alignment course using dial guage, pda and rotalign(Laser)  Permit to work (Pertronas) Valid from 24th October2012 -24th October 2015.  PETRONAS PTW Applicant Course  Bolting course(Hytorc, Riverhawk ,Ith).  NTSP Level 1(Niosh Tenaga Safety Passport)  SUPPLEMENTARY Basic Salary Negociate Expected Monthly Basic Salary Possess own transport Yes Availability 1 month notice Willing to traveling Yes REFERENCES 1. MARTIN GANJAR BME/3003 (Rotating – Roving Gang) SKO Maintenance Engineering Department Email: martinganjar@petronas.com.my Contact No:019-8552403. 2. JURGAO ANAK MANGAI. Mechanical Supervisor Granite Services International(Malaysia) Email:Jurgao.Mangai@ge.com/jurgao.mangai@gmail.com Contact No:016-8119359 3. Edwin Cheng(Rotating Engineer) PCSB SKO SRM/323 Maintenance Engineering Department Cont No: 012-7542200 Email: Edwin_cheng@petronas.com.my, 4.) MR. MuazBinNordin ServiceEngineer SERBA DINAMIK SDN BHD Direct Line: 087-411063 Email: muaz@e-serbadk.