2. Agenda
01. Location 02. Chronology
03. Development
Plan & Cost
04. Sandakan
Industrial Park
05. Infrastructure &
Utilities
2 POIC, Sandakan January 12, 2022
3. Location
Located in the world's
largest palm oil
producing region –
South East Asia
ensures sustainable
supply of renewable
feedstock
90% of World Production
COLOMBIA
(1,280,000 mt)
THAILAND
(2,300,000 mt)
INDONESIA
(35,000,000 mt)
MALAYSIA
(18,000,000 mt)
7. Chronology
CHRONOLOGY
2006 With the primary objective to attract investment
in palm oil downstream activities, the development on
627 acres of land started in 2006
2017 Construction of temporary jetty and bulking installations
completed
2018 Rebranded as a Sandakan Furniture Park in December
2018 by the previous Chief Minister Datuk Seri
Panglima Shafie bin Apdal. Total land area dedicated for
furniture and light industry is 367 acres
2019 Construction of permanent jetty completed
8. Sandakan
Industrial Park
• 15 lots (1,2,3,4,5,6,15,16,23,24,25,26,35,43,46)
•Biomass, packaging, metal & machinery
manufacturing/assembly, biochemical, logistic, etc.
NON FOOD
BASED
• 8 lots (17,18,19,20,21,22,38,39)
•Mixed development, etc.
COMMERCIAL
DEVELOPMENT
• 5 lots (7,8,14,27,28)
•Electricity, water, gas, internet accessibility, etc.
UTILITY
• 4 lots (9,13,29,30)
•Food & beverages manufacturing, etc.
FOOD BASED
• 7 lots (10,11,12,31A,31B,32,33)
•Palm oil related industries (e.g refinery,
oleochemical)
•Jetty (Lot.33) & bulking facilities (Lot.32)
PALM OIL
RELATED
7
48
33
21
22 20
19
17
27
28
29
18
30
39
38
47
34
8
9
10
11
13
14
12
32
31A
31B
43
1
2
3
4
5
6
16
24
25
26
23
15
46
35
10. Infrastructure & Utilities
Basic Infrastructure
Internal Road • 15 km Road
• 24 km Drainage
Water
• Treated water: 12 Mil Litre water tank
• 11 km water pipeline
Telecommunication • 40 km telecommunication cables
Sewerage System • 3,000 PE Sewerage treatment & 6.6 km drainage
Streetlights • 15 km Streetlights
Power Supply • 2 x 33/11kV Power connection (PPU)
• 7x11/0.415kV Distribution (PE)
• 18km x 33kV underground cabling
• 35km x 11kV underground cabling
• 4km x 33kV Suspended cabling
Security • 24 Hours patrolling
11. Infrastructure & Utilities
External Infrastructure & Utilities
Water • 5km water pipeline with booster pump station from nearest
water treatment plant to POIC water tank
Power • 132 kV connected via POIC PMU
Telecommunication • Fibre Optic (Fast data communication)
Accessibility • 15.1 km to Sandakan port
• 16.6 km to Sandakan city
• 16.8 km to Sandakan Airport
12. Infrastructure & Utilities
Current Facilities
Dedicated Palm Oil Jetty • Up to 50,000 Deadweight tonnage (DWT)
• Berthing for tankers and barges with conveyor systems and
Palm Methyl Ester (PME) pipelines
• PKE warehouse storage: 5,000 MT
Bulking Installation
• Bulking connected to jetty
• 15 tanks with capacity of 46,600 MT
• Pumping rate: 280 MT/ hr
Pipe Rack • Pipeline connected to bulking and jetty