SlideShare a Scribd company logo
1 of 2
The Manjung coal-fired power plant, sponsored by Tenaga Janamanjung, is located on a man-
made island off the coast of Perak in Malaysia. It generates 2,100MW from its three 700MW
units.
The plant is located 4.5m above sea level, making coal imports easier. Construction began in
September 1999 and the three 700MW units became operational in 2004.
The project suffered some delay as a result of the 1997/98 Asian economic crisis. It was
completed at a cost of about $1.8bn.
The plant was built to meet the 80% electricity demand of Malaysia on natural gas. The three
700MW units, with a rotating speed of 3,000rpm, use clean coal combustion technology and
environmental control systems provided by Alstom to cut down emission levels.
Manjung coal-fired power plant make-up
"Tenaga Nasional Berhad's subsidiary, TNB Janamanjung, was originally the sole owner of the
plant. In August 1999, the Perak state government announced it would take a 20% stake."
The island on which the site is located is off the coast of Perak. The land was reclaimed between
September 1997 and May 1999, which meant ABB could start construction in July 1999.
A consortium formed by ABB Alstom Power Plants and Peremba Construction was selected as
the engineering, procurement and construction (EPC) contractor for the project. ABB Alstom
owns 75%, while the Malaysian Peremba owns the rest.
Lekir Bulk Terminal (LBT) built a terminal to offload the six million tons of coal the plant should
use each year. The jetty serves vessels of as much as 150,000t. The plant was built on 254ha of
the total 320ha of reclaimed land on the island. Of the 254ha, 70ha was for the power plant and
175ha for the ash pond. The rest was used for the terminal facilities.
Leighton Asia designed and constructed the jetty, which was completed in September 2002. The
estimated cost was RM310 million (€93m).
ABB Alstom Power supplied the main equipment. It included the boilers, steam turbines and
generators. Peremba was concerned with the erection, the civil works elements and the main
electrical and I&C equipment.
The plant's transmission link to the Malaysian mainland was provided by ABB. Bachy Soletanche
Malaysia designed an alternative construction for the pump house, as the original design proved
too costly (the design was greatly complicated by the geology of the site). The coal yard
equipment was supplied by Koch.
Project finances, bank loans and TNB's agreement with the state of Perak
The plant's cost was eventually estimated at $1.8bn, up from the original estimate of $1.3bn.
The main reason was the adverse change in the exchange rate. Roughly 30% of the cost came
from equity financing.
"The project suffered some delay as a result of the 1997/98 Asian economic crisis. It was
completed at a cost of about $1.8bn."
The rest came from various forms of borrowing, including export credit. A major element in the
deal was a $684m loan from HSBC's Midland Bank subsidiary. The HSBC loan was underwritten
by the UK's export credit guarantee agency. The French export credit insurer COFACE was also
involved.
Tenaga Nasional Berhad's subsidiary, TNB Janamanjung, was originally the sole owner of the
plant. In August 1999, the Perak state government announced it would take a 20% stake. TNB
was happy with the proposal as the company had a long-term strategy of reducing its power
generation exposure to focus on transmission and distribution.
Pollution issues for Tenaga Janamanjung's Malaysian facility
The plant uses low sulphur and low bitumen coal (pulverised for burning) to minimise pollution.
The resulting ash is valuable for the cement industry, while most of the ash is caught by
electrostatic precipitators. Dust control is also an important feature (the conveyor belt is
covered and sprinkler systems remove up to 99.9%).
The plant has a wastewater treatment facility to treat its effluent before it is released into the
sea. The plant also helps in reinvigorating decayed mangrove swamps in the area.
The plant exceeds the emission standards set by the World Bank in Malaysia. It operates to
particulate levels of 50mg/Nm³ while the expected ASEAN level is 400mg/Nm³. It uses low NOx
burners and a flue gas desulpherisation facility, to keep NOx and SOx emissions low.

More Related Content

What's hot

Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive Director
Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive DirectorEnergy Policies of IEA Countries Ireland 2012 Review - IEA Executive Director
Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive DirectorInternational Energy Agency
 
Sources of Renewable Energy in Romania - by Ana Dicu and Irina Ionescu
Sources of Renewable Energy in Romania - by Ana Dicu and Irina IonescuSources of Renewable Energy in Romania - by Ana Dicu and Irina Ionescu
Sources of Renewable Energy in Romania - by Ana Dicu and Irina IonescuIoana Stancut
 
Low carbon andy technology
Low  carbon    andy  technologyLow  carbon    andy  technology
Low carbon andy technologygoogle
 
Coal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaCoal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaGalih Honggo Baskoro
 
Indonesia's coal based power market
Indonesia's coal based power marketIndonesia's coal based power market
Indonesia's coal based power marketSuparn Kuer
 
Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)VR M
 
Premier of victoria ted baillieu
Premier of victoria ted baillieuPremier of victoria ted baillieu
Premier of victoria ted baillieulewisshannon
 
Renewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonRenewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonAlejo Etchart Ortiz
 
Indonesia ina002 1366765311
Indonesia ina002 1366765311Indonesia ina002 1366765311
Indonesia ina002 1366765311Nurul Yakin
 
Cng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sCng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sFurqon Hanief
 
Environmental Effects of Rampal Power Plant.
Environmental Effects of Rampal Power Plant.Environmental Effects of Rampal Power Plant.
Environmental Effects of Rampal Power Plant.Psyful Bappi
 
Rampal power plant environmental & economic impact
Rampal power plant environmental & economic impactRampal power plant environmental & economic impact
Rampal power plant environmental & economic impactNur E Sowrove
 
Indonesia power plant on gas supply to lombok gas fired power plant using cng...
Indonesia power plant on gas supply to lombok gas fired power plant using cng...Indonesia power plant on gas supply to lombok gas fired power plant using cng...
Indonesia power plant on gas supply to lombok gas fired power plant using cng...Furqon Hanief
 

What's hot (20)

Coal
CoalCoal
Coal
 
Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive Director
Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive DirectorEnergy Policies of IEA Countries Ireland 2012 Review - IEA Executive Director
Energy Policies of IEA Countries Ireland 2012 Review - IEA Executive Director
 
07.06.2013, NEWSWIRE, Issue 277
07.06.2013, NEWSWIRE, Issue 27707.06.2013, NEWSWIRE, Issue 277
07.06.2013, NEWSWIRE, Issue 277
 
Sources of Renewable Energy in Romania - by Ana Dicu and Irina Ionescu
Sources of Renewable Energy in Romania - by Ana Dicu and Irina IonescuSources of Renewable Energy in Romania - by Ana Dicu and Irina Ionescu
Sources of Renewable Energy in Romania - by Ana Dicu and Irina Ionescu
 
Low carbon andy technology
Low  carbon    andy  technologyLow  carbon    andy  technology
Low carbon andy technology
 
Pln cng
Pln cngPln cng
Pln cng
 
Coal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaCoal Fired Power Plant in Indonesia
Coal Fired Power Plant in Indonesia
 
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
 
Indonesia's coal based power market
Indonesia's coal based power marketIndonesia's coal based power market
Indonesia's coal based power market
 
Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)
 
Premier of victoria ted baillieu
Premier of victoria ted baillieuPremier of victoria ted baillieu
Premier of victoria ted baillieu
 
Eco2 - A Sector Perspective
Eco2 - A Sector PerspectiveEco2 - A Sector Perspective
Eco2 - A Sector Perspective
 
Renewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And LondonRenewable Energies In Practice- Ashton Green And London
Renewable Energies In Practice- Ashton Green And London
 
Indonesia ina002 1366765311
Indonesia ina002 1366765311Indonesia ina002 1366765311
Indonesia ina002 1366765311
 
Coal 2 electricity
Coal 2 electricityCoal 2 electricity
Coal 2 electricity
 
Cng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 sCng marine for gas distribution in indonesia 2012 s
Cng marine for gas distribution in indonesia 2012 s
 
Environmental Effects of Rampal Power Plant.
Environmental Effects of Rampal Power Plant.Environmental Effects of Rampal Power Plant.
Environmental Effects of Rampal Power Plant.
 
Rampal power plant environmental & economic impact
Rampal power plant environmental & economic impactRampal power plant environmental & economic impact
Rampal power plant environmental & economic impact
 
Introduction to Cofely and Southampton
Introduction to Cofely and SouthamptonIntroduction to Cofely and Southampton
Introduction to Cofely and Southampton
 
Indonesia power plant on gas supply to lombok gas fired power plant using cng...
Indonesia power plant on gas supply to lombok gas fired power plant using cng...Indonesia power plant on gas supply to lombok gas fired power plant using cng...
Indonesia power plant on gas supply to lombok gas fired power plant using cng...
 

Similar to TNB Manjung Power Plant

MedupiFactSheetSept2013
MedupiFactSheetSept2013MedupiFactSheetSept2013
MedupiFactSheetSept2013Matthew Wright
 
medupi-kusile-south-africa-editorial
medupi-kusile-south-africa-editorialmedupi-kusile-south-africa-editorial
medupi-kusile-south-africa-editorialRiaan Barwise
 
Moranbah Coal Seam Power Station
Moranbah Coal Seam Power StationMoranbah Coal Seam Power Station
Moranbah Coal Seam Power StationAshley Rogers
 
Surathgarh thermal powerplant
Surathgarh thermal powerplantSurathgarh thermal powerplant
Surathgarh thermal powerplantAAKASH DEEP SINGH
 
Paper energy analysis of a cement plant jesa 2002 final 2
Paper energy analysis of a cement plant jesa 2002 final 2Paper energy analysis of a cement plant jesa 2002 final 2
Paper energy analysis of a cement plant jesa 2002 final 2Patrick VanSchijndel
 
EIA POWER PLANT.pptx
EIA POWER PLANT.pptxEIA POWER PLANT.pptx
EIA POWER PLANT.pptxsunilghosh11
 
New base special 20 march 2014
New base special  20 march 2014New base special  20 march 2014
New base special 20 march 2014Khaled Al Awadi
 
FECTO CFPP Presentation Updated 13-3-15
FECTO CFPP Presentation Updated 13-3-15FECTO CFPP Presentation Updated 13-3-15
FECTO CFPP Presentation Updated 13-3-15NAVEED SABIR
 
Abengoa Kaxu Solar One in South Africa
Abengoa Kaxu Solar One in South AfricaAbengoa Kaxu Solar One in South Africa
Abengoa Kaxu Solar One in South AfricaAbengoa
 
Water Treatment
Water TreatmentWater Treatment
Water TreatmentSite Web
 
Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Nieza Noordin
 
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...haxxo24
 

Similar to TNB Manjung Power Plant (20)

MedupiFactSheetSept2013
MedupiFactSheetSept2013MedupiFactSheetSept2013
MedupiFactSheetSept2013
 
medupi-kusile-south-africa-editorial
medupi-kusile-south-africa-editorialmedupi-kusile-south-africa-editorial
medupi-kusile-south-africa-editorial
 
Moranbah Coal Seam Power Station
Moranbah Coal Seam Power StationMoranbah Coal Seam Power Station
Moranbah Coal Seam Power Station
 
report
reportreport
report
 
OmanPower&Water2017_Brochure-2
OmanPower&Water2017_Brochure-2OmanPower&Water2017_Brochure-2
OmanPower&Water2017_Brochure-2
 
Surathgarh thermal powerplant
Surathgarh thermal powerplantSurathgarh thermal powerplant
Surathgarh thermal powerplant
 
gilgel gibe dam
gilgel gibe damgilgel gibe dam
gilgel gibe dam
 
Alu Plant
Alu PlantAlu Plant
Alu Plant
 
Paper energy analysis of a cement plant jesa 2002 final 2
Paper energy analysis of a cement plant jesa 2002 final 2Paper energy analysis of a cement plant jesa 2002 final 2
Paper energy analysis of a cement plant jesa 2002 final 2
 
BCM NewsWire Issue 449
BCM NewsWire Issue 449BCM NewsWire Issue 449
BCM NewsWire Issue 449
 
SRWF PR4
SRWF PR4SRWF PR4
SRWF PR4
 
EIA POWER PLANT.pptx
EIA POWER PLANT.pptxEIA POWER PLANT.pptx
EIA POWER PLANT.pptx
 
New base special 20 march 2014
New base special  20 march 2014New base special  20 march 2014
New base special 20 march 2014
 
FECTO CFPP Presentation Updated 13-3-15
FECTO CFPP Presentation Updated 13-3-15FECTO CFPP Presentation Updated 13-3-15
FECTO CFPP Presentation Updated 13-3-15
 
Abengoa Kaxu Solar One in South Africa
Abengoa Kaxu Solar One in South AfricaAbengoa Kaxu Solar One in South Africa
Abengoa Kaxu Solar One in South Africa
 
Water Treatment
Water TreatmentWater Treatment
Water Treatment
 
Stps report
Stps reportStps report
Stps report
 
Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)
 
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
 
BTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdfBTE-Digital-Brochure.pdf
BTE-Digital-Brochure.pdf
 

TNB Manjung Power Plant

  • 1. The Manjung coal-fired power plant, sponsored by Tenaga Janamanjung, is located on a man- made island off the coast of Perak in Malaysia. It generates 2,100MW from its three 700MW units. The plant is located 4.5m above sea level, making coal imports easier. Construction began in September 1999 and the three 700MW units became operational in 2004. The project suffered some delay as a result of the 1997/98 Asian economic crisis. It was completed at a cost of about $1.8bn. The plant was built to meet the 80% electricity demand of Malaysia on natural gas. The three 700MW units, with a rotating speed of 3,000rpm, use clean coal combustion technology and environmental control systems provided by Alstom to cut down emission levels. Manjung coal-fired power plant make-up "Tenaga Nasional Berhad's subsidiary, TNB Janamanjung, was originally the sole owner of the plant. In August 1999, the Perak state government announced it would take a 20% stake." The island on which the site is located is off the coast of Perak. The land was reclaimed between September 1997 and May 1999, which meant ABB could start construction in July 1999. A consortium formed by ABB Alstom Power Plants and Peremba Construction was selected as the engineering, procurement and construction (EPC) contractor for the project. ABB Alstom owns 75%, while the Malaysian Peremba owns the rest. Lekir Bulk Terminal (LBT) built a terminal to offload the six million tons of coal the plant should use each year. The jetty serves vessels of as much as 150,000t. The plant was built on 254ha of the total 320ha of reclaimed land on the island. Of the 254ha, 70ha was for the power plant and 175ha for the ash pond. The rest was used for the terminal facilities. Leighton Asia designed and constructed the jetty, which was completed in September 2002. The estimated cost was RM310 million (€93m). ABB Alstom Power supplied the main equipment. It included the boilers, steam turbines and generators. Peremba was concerned with the erection, the civil works elements and the main electrical and I&C equipment. The plant's transmission link to the Malaysian mainland was provided by ABB. Bachy Soletanche Malaysia designed an alternative construction for the pump house, as the original design proved too costly (the design was greatly complicated by the geology of the site). The coal yard equipment was supplied by Koch. Project finances, bank loans and TNB's agreement with the state of Perak The plant's cost was eventually estimated at $1.8bn, up from the original estimate of $1.3bn. The main reason was the adverse change in the exchange rate. Roughly 30% of the cost came from equity financing. "The project suffered some delay as a result of the 1997/98 Asian economic crisis. It was completed at a cost of about $1.8bn." The rest came from various forms of borrowing, including export credit. A major element in the deal was a $684m loan from HSBC's Midland Bank subsidiary. The HSBC loan was underwritten by the UK's export credit guarantee agency. The French export credit insurer COFACE was also involved. Tenaga Nasional Berhad's subsidiary, TNB Janamanjung, was originally the sole owner of the plant. In August 1999, the Perak state government announced it would take a 20% stake. TNB was happy with the proposal as the company had a long-term strategy of reducing its power generation exposure to focus on transmission and distribution. Pollution issues for Tenaga Janamanjung's Malaysian facility
  • 2. The plant uses low sulphur and low bitumen coal (pulverised for burning) to minimise pollution. The resulting ash is valuable for the cement industry, while most of the ash is caught by electrostatic precipitators. Dust control is also an important feature (the conveyor belt is covered and sprinkler systems remove up to 99.9%). The plant has a wastewater treatment facility to treat its effluent before it is released into the sea. The plant also helps in reinvigorating decayed mangrove swamps in the area. The plant exceeds the emission standards set by the World Bank in Malaysia. It operates to particulate levels of 50mg/Nm³ while the expected ASEAN level is 400mg/Nm³. It uses low NOx burners and a flue gas desulpherisation facility, to keep NOx and SOx emissions low.