Sample Project Close-out Report
By Amin Hadjaran (ahadjaran@yahoo.com)
Sample Project Close-out Report
This Close-out Report has been prepared for an SMP EPC Mining Contract
that has been executed in Western Australia in 2012 – 2014.
By Amin Hadjaran (ahadjaran@yahoo.com)
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
SITE ACCESS
TOTAL 48
LATE 20 42%
EARLY 28 58%
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121 -…
125 -…
131 -…
132 -…
134 -…
141 -…
142 -…
144 -…
146 -…
147 -…
161 - CIL
162 -…
171 -…
172 -…
181 -…
183 -…
211 -…
212 -…
213 -…
214 -…
216 -…
219 -…
232 -…
233 -…
234 -…
235 -…
236 -…
238 -…
241 -…
251 -…
253 -…
261 -…
262 -…
312 -…
325 -…
331 -…
122-C -…
122-S -…
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008…
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
241 - PIPERACKS
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
331 - POWER SUPPLY
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHINGAND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
PROJECT
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
STEEL DELIVERY
TOTAL 34
LATE 30 88%
EARLY 4 12%
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
134
141
144
161
171
172
181
211
212
213
214
216
219
241
251
261
312
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
144 - CARBON SAFETY SCREENING
161 - CIL
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
241 - PIPERACKS
251 - COMPRESSED AIR
261 - FUEL SUPPLY AND DISTRIBUTION
312 - EVENT POND
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
TGP-011
LATE STEEL DELIVERIES
122-C CLADDING
122-S LADDERS AND HANDRAIL
CV001 TRUSS CONNECTION PLATES
CV002 TAIL END GUARDS, TRUSS CONNECTION PLATES
CV003 GUARDS, TRUSS CONNECTION PLATES
CV004 TRUSS CONNECTION PLATES, GUARDS
CV005 TRUSS CONNECTION PLATES, GUARDS
CV006 TRUSS CONNECTION PLATES, GUARDS
CV007 TRUSS CONNECTION PLATES, GUARDS
CV008 TRUSS CONNECTION PLATES, GUARDS
CV009 TRUSS CONNECTION PLATES, GUARDS
CV010 TRUSS CONNECTION PLATES
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
959.58
453.86
820.16
0
200
400
600
800
1,000
1,200
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
01-Jul-12 01-Aug-12 01-Sep-12 01-Oct-12 01-Nov-12 01-Dec-12 01-Jan-13 01-Feb-13 01-Mar-13 01-Apr-13 01-May-13 01-Jun-13 01-Jul-13 01-Aug-13
PROJECT BASELINE PROJECT EOT PROJECT ACTUAL
Example:
In the month of October, 2012, PIC were required to install
959.58 tonnes of steel as per the Rev 0 Baseline; with all
delays incorporated, the expected figure for October was
453.86 tonnes. PIC were actually able to erect 820.16 tonnes in
that time period.
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ME DELIVERIES
TOTAL 47
LATE 24 51%
EARLY 23 49%
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
134
141
142
144
146
147
161
162
171
172
181
183
211
212
213
214
216
219
232
233
234
235
236
238
251
253
261
262
312
325
331
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
331 - POWER SUPPLY
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
TGP-011
LATE ME DELIVERIES
121VOITH COUPLING DELIVERED ON 11/6/13 - 1730-TGP011-HOM-129
1311730-TGP011-HOM-123, HPGR FEEDER METAL DETECTOR
1321730-TGP011-HOM-121, 13-FE-003/4 FLAT BARS DELIVERED ON 5/5/13
1611730-TGP011-HOM-140, BOLTS, NUTS AND WASHERS
1711730-TGP011-HOM-137, BOLTS, NUTS, GASKETS, ELBOWS
1811730-TGP011-HOM-131, DELIVERY OF 18-RO-001/2
CV001 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV002 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV003 1730-TGP011-HOM-132, TAKE UP PULLEY SHEDDER
CV004 1730-TGP011-HOM-134, GUARD POSTS
CV005 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV006 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV008 1730-TGP011-HOM-132, DRIVE FRAME
CV009 1730-TGP011-HOM-123, METAL DETECTOR 13-MD-003
CV010 1730-TGP011-HOM-124, SHEAVE ASSEMBLY
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
LATE PL DELIVERIES
1211730-TGP011-HOM-139 FOR 12-ZM-005 (BOLTS, NUTS, RUBBER, ETC.)
1251730-TGP011-HOM-132, SLIDING GATES, CHAIN AND PINS FOR 12-DU-004
1311730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
1321730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
134SAMPLE CHUTE DISCHARGE BOX DELIVERED ON 8/6/13
1411730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
1441730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
1611730-TGP011-HOM-124, PIPE AND CLAMP PLATE FOR 16-BX-002
1621730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
1721730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
1831730-TGP011-HOM-125, MISSING ITEMS FOR THE DUCTS
2131730-TGP011-HOM-124, MISSING ITEMS
262LPG TANK WAS DELIVERED ON 16/7 AND INSTALLED ON 24/7
122-C 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
122-S 1730-TGP011-HOM-132, SLIDING GATES, PINS AND CHAINS FOR DUCTS
CV001 1730-TGP011-HOM-121, ELBOWS, NIPPLES, ETC.
CV002 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV003 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV004 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV006 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
CV010 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS
PL DELIVERIES
TOTAL 37
LATE 16 43%
EARLY 21 57%
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
134
141
142
144
146
147
161
162
171
172
181
183
211
212
213
216
233
253
261
262
331
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
144 - CARBON SAFETY SCREENING
161 - CIL
162 - CARBON RECOVERY
183 - ELECTROWINNING
213 - FLOCCULANTS
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV010
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
134
141
144
161
171
172
181
211
212
213
214
216
219
241
251
261
312
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
144 - CARBON SAFETY SCREENING
161 - CIL
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
241 - PIPERACKS
251 - COMPRESSED AIR
261 - FUEL SUPPLY AND DISTRIBUTION
312 - EVENT POND
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
TGP-011
EXCLUDING PUNCHLISTING
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
133
134
141
142
144
146
147
161
162
171
172
181
183
211
212
213
214
216
219
232
233
234
235
236
238
251
253
261
262
312
325
331
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
133
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
331 - POWER SUPPLY
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
TGP-011
EXCLUDING PUNCHLISTING
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121
125
131
132
134
141
142
144
146
147
161
162
171
172
181
183
211
212
213
216
233
253
261
262
331
122-C
122-S
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
216 - ACID
233 - PROCESS WATER
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
331 - POWER SUPPLY
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
TGP-011
EXCLUDING PUNCHLISTING
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121 -…
125 -…
131 -…
132 -…
134 -…
141 -…
142 -…
144 -…
146 -…
161 - CIL
162 -…
171 -…
172 -…
181 -…
183 -…
211 -…
212 -…
213 -…
214 -…
216 -…
219 -…
232 -…
233 -…
234 -…
235 -…
236 -…
238 -…
241 -…
251 -…
253 -…
261 -…
262 -…
312 -…
325 -…
122-C -…
122-S -…
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
241 - PIPERACKS
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
PROJECT
EXCLUDING PUNCHLISTING
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121 -…
125 -…
131 -…
132 -…
#N/A
134 -…
141 -…
142 -…
144 -…
146 -…
147 -…
161 - CIL
162 -…
171 -…
172 -…
181 -…
183 -…
211 -…
212 -…
213 -…
214 -…
216 -…
219 -…
232 -…
233 -…
234 -…
235 -…
236 -…
238 -…
241 -…
251 -…
253 -…
261 -…
262 -…
312 -…
325 -…
331 -…
122-C -…
122-S -…
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008…
CV009
CV010
PROJECT
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
#N/A
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
241 - PIPERACKS
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
331 - POWER SUPPLY
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
PROJECT
EXCLUDING PUNCHLISTING
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ACTUAL FINAL EOT BASELINE
121 - PRIMARY CRUSHING
125 - PRIMARY STOCKPILE AND RECLAIM
131 - HPGR
132 - HPGR SCREENING AND GRINDING
134 - FINE ORE STORAGE AND RECLAIM
141 - TRASH SCREENING
142 - THICKENING - FEED
144 - CARBON SAFETY SCREENING
146 - THICKENING - TAILS
147 - TAILS PUMPING
161 - CIL
162 - CARBON RECOVERY
171 - ACID WASH / ELUTION
172 - CARBON REGENERATION
181 - GOLDROOM
183 - ELECTROWINNING
211 - CYANIDE
212 - LIME
213 - FLOCCULANTS
214 - CAUSTIC
216 - ACID
219 - LEAD NITRATE
232 - RAW WATER
233 - PROCESS WATER
234 - POTABLE WATER
235 - GLAND SEAL WATER
236 - COOLING WATER
238 - FIRE WATER
241 - PIPERACKS
251 - COMPRESSED AIR
253 - OXYGEN PLANT
261 - FUEL SUPPLY AND DISTRIBUTION
262 - GAS SUPPLY AND DISTRIBUTION
312 - EVENT POND
325 - WATER TREATMENT PLANT
122-C - SECONDARY CRUSHING
122-S - SECONDARY CRUSHING AND
SCREENING
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008 / 11
CV009
CV010
PROJECT
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
121 -…
125 -…
131 -…
132 -…
134 -…
141 -…
142 -…
144 -…
146 -…
147 -…
161 - CIL
162 -…
171 -…
172 -…
181 -…
183 -…
211 -…
212 -…
213 -…
214 -…
216 -…
219 -…
232 -…
233 -…
234 -…
235 -…
236 -…
238 -…
241 -…
251 -…
253 -…
261 -…
262 -…
312 -…
325 -…
122-C -…
122-S -…
CV001
CV002
CV003
CV004
CV005
CV006
CV007
CV008…
CV009
CV010
PROJECT
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0%
20%
40%
60%
80%
100%
120%
21-Sep-12
5-Oct-12
19-Oct-12
2-Nov-12
16-Nov-12
30-Nov-12
14-Dec-12
28-Dec-12
11-Jan-13
25-Jan-13
8-Feb-13
22-Feb-13
8-Mar-13
22-Mar-13
5-Apr-13
19-Apr-13
3-May-13
17-May-13
31-May-13
14-Jun-13
28-Jun-13
12-Jul-13
26-Jul-13
9-Aug-13
23-Aug-13
REV 0 BASELINE + AFC LINES FINAL EOT ACTUAL
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
374,068
405,276
431,877
532,914
ORIGINAL BUDGET REMEASURED BUDGET REMEASURED BUDGET+SIs ACTUAL
ONSITE AND OFFSITE
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
REV 0
ACTUAL
FINAL EOT
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
110
115
120
125
130
135
140
145
150
155
160
165
170
175
180
185
190
195
200
205
210
215
220
225
230
235
240
245
250
3-Aug-12
10-Aug-12
17-Aug-12
24-Aug-12
31-Aug-12
7-Sep-12
14-Sep-12
21-Sep-12
28-Sep-12
5-Oct-12
12-Oct-12
19-Oct-12
26-Oct-12
2-Nov-12
9-Nov-12
16-Nov-12
23-Nov-12
30-Nov-12
7-Dec-12
14-Dec-12
21-Dec-12
28-Dec-12
4-Jan-13
11-Jan-13
18-Jan-13
25-Jan-13
1-Feb-13
8-Feb-13
15-Feb-13
22-Feb-13
1-Mar-13
8-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
5-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
3-May-13
10-May-13
17-May-13
24-May-13
31-May-13
7-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
5-Jul-13
12-Jul-13
19-Jul-13
26-Jul-13
2-Aug-13
9-Aug-13
16-Aug-13
23-Aug-13
30-Aug-13
6-Sep-13
13-Sep-13
20-Sep-13
27-Sep-13
4-Oct-13
11-Oct-13
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
100,000
200,000
300,000
400,000
500,000
600,000
CONVEYOR
PUNCHLISTING
MECHANICAL PLATEWORK PIPING STRUCTURAL TOTAL
BUDGETED ACTUAL FINAL EOT (INCL. SIs)
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
120 Total 130 Total 140 Total 160 Total 170 Total 180 Total 210 Total 230 Total 240 Total 250 Total 260 Total 310 Total 320 Total 330 Total 340 Total
BUDGETED ACTUAL FINAL EOT (INCL. SIs)
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
INDIRECTS, 212,972, 28%
OFF THE JOB, 24,699, 3%
DIRECTS, 532,914, 69%
ONSITE AND OFFSITE
OFF THE JOB
INDUCTIONS
TOOLBOX & MEETING
INCLEMENT WEATHER
TRAVEL TIME
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
INCLEMENT WEATHER,
10,050, 41%
INDUCTIONS, 3,127,
13%
TOOLBOX & MEETING,
4,307, 17%
TRAVEL TIME, 7,216, 29%
ONSITE ONLY
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
Advanced Rigger,
8,645, 2%
Apprentice, 4,122, 1%
Belt Splicer, 684, 0%
Boilermaker, 63,008, 12% CNC Operator, 103, 0%
CNC Programmer, 227, 0%
Combined, 28,554, 5%
Crane Driver / Operator, 29,179, 5%
Fitter, 16,370, 3%
Machine Operator, 89, 0%
Machinist, 1,493, 0%Mechanical Fitter, 32,335, 6%
Metal Trade, 6,112, 1%
Painter, 4,052, 1%
Pipe Fitter, 77,633, 15%
Poly Welder, 9,977, 2%
Rigger, 103,866, 19%
Rigger / Scaffolder, 1,399, 0%
Roll/Press Operator, 16, 0%
Scaffolder, 13,651, 3%
Sheeters/Cladders, 2,961, 1%
T/A, 79,008, 15%
W/S Foreman, 21, 0%
Welder, 49,412, 9%
ONSITE AND OFFSITE
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ONSITE ONLY
Advanced Rigger, 7,841, 2% Apprentice, 251, 0%
Belt
Splicer,
684, 0%
Boilermaker, 54,430, 11% Combined, 12,468, 3%
Crane Driver /
Operator, 28,218,
6%
Fitter, 16,370, 3%
Mechanical Fitter, 32,304, 7%
Metal Trade, 6,106, 1%
Painter, 4,052, 1%
Pipe Fitter, 77,436, 16%
Poly Welder, 9,235, 2%
Rigger, 101,569, 21%
Rigger / Scaffolder, 1,399, 0%
Scaffolder, 13,621, 3%
Sheeters/Cladders, 2,961, 1%
T/A, 71,293, 15%
Welder, 39,640, 8%
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
AREA MANAGER,
8,204, 4%
BELT SPLICING, 332, 0%
CLADDING, 371, 0%
COST CONTROL, 3,495, 2%
ENGINEERING, 18,707, 9%
MATERIAL RECEIVAL, 25,646, 12%
OUTOTEC, 1,920, 1%
PAINTING, 585, 0%
PLANNING, 3,559, 2%
PROJECT
MANAGEMENT,
8,932, 4%
QA MANAGER, 6,418, 3%
QUANTITY SURVEYING, 6,566, 3%
REFEULING, 3,154, 1%
SAFETY, 16,213, 8%
SITE SERVICES,
12,028, 6%
SUPERINTENDENT, 10,217, 5%
SUPERVISOR, 55,148, 26%
UNKNOWN, 30,303, 14%
VARIATION
WORK, 1,177,
1%
SITE SERVICES
MECHANIC
PEGGY
STORE PERSON
MOB/DEMOB CREW
ONSITE AND OFFSITE
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
ONSITE AND OFFSITE
VARIATIONS, 26,601, 5%
STRUCTURAL, 181,575, 34%
PLATEWORK, 1,574, 0%
MECHANICAL, 123,792, 23%
PIPING, 199,378, 38%
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
20-Jul-12
27-Jul-12
03-Aug-12
10-Aug-12
17-Aug-12
24-Aug-12
31-Aug-12
07-Sep-12
14-Sep-12
21-Sep-12
28-Sep-12
05-Oct-12
12-Oct-12
19-Oct-12
26-Oct-12
02-Nov-12
09-Nov-12
16-Nov-12
23-Nov-12
30-Nov-12
07-Dec-12
14-Dec-12
21-Dec-12
28-Dec-12
04-Jan-13
11-Jan-13
18-Jan-13
25-Jan-13
01-Feb-13
08-Feb-13
15-Feb-13
22-Feb-13
01-Mar-13
08-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
05-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
03-May-13
10-May-13
17-May-13
24-May-13
31-May-13
07-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
05-Jul-13
12-Jul-13
19-Jul-13
26-Jul-13
02-Aug-13
09-Aug-13
16-Aug-13
23-Aug-13
30-Aug-13
06-Sep-13
13-Sep-13
20-Sep-13
27-Sep-13
04-Oct-13
OVERALL PF ONSITE PF
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
08-Feb-13
15-Feb-13
22-Feb-13
01-Mar-13
08-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
05-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
03-May-13
10-May-13
17-May-13
24-May-13
31-May-13
07-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
05-Jul-13
12-Jul-13
Site Overall PIC Outotec CPC QA Pipe Systems SMP
ONSITE ONLY
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
100,000
200,000
300,000
400,000
500,000
600,000
20-Jul-12
27-Jul-12
03-Aug-12
10-Aug-12
17-Aug-12
24-Aug-12
31-Aug-12
07-Sep-12
14-Sep-12
21-Sep-12
28-Sep-12
05-Oct-12
12-Oct-12
19-Oct-12
26-Oct-12
02-Nov-12
09-Nov-12
16-Nov-12
23-Nov-12
30-Nov-12
07-Dec-12
14-Dec-12
21-Dec-12
28-Dec-12
04-Jan-13
11-Jan-13
18-Jan-13
25-Jan-13
01-Feb-13
08-Feb-13
15-Feb-13
22-Feb-13
01-Mar-13
08-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
05-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
03-May-13
10-May-13
17-May-13
24-May-13
31-May-13
07-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
05-Jul-13
12-Jul-13
19-Jul-13
26-Jul-13
02-Aug-13
09-Aug-13
16-Aug-13
23-Aug-13
30-Aug-13
06-Sep-13
13-Sep-13
20-Sep-13
27-Sep-13
04-Oct-13
11-Oct-13
18-Oct-13
OVERALL PLANNED OVERALL EARNED OVERAL ACTUAL FINAL EOT
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
100,000
200,000
300,000
400,000
500,000
600,000
20-Jul-12
27-Jul-12
03-Aug-12
10-Aug-12
17-Aug-12
24-Aug-12
31-Aug-12
07-Sep-12
14-Sep-12
21-Sep-12
28-Sep-12
05-Oct-12
12-Oct-12
19-Oct-12
26-Oct-12
02-Nov-12
09-Nov-12
16-Nov-12
23-Nov-12
30-Nov-12
07-Dec-12
14-Dec-12
21-Dec-12
28-Dec-12
04-Jan-13
11-Jan-13
18-Jan-13
25-Jan-13
01-Feb-13
08-Feb-13
15-Feb-13
22-Feb-13
01-Mar-13
08-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
05-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
03-May-13
10-May-13
17-May-13
24-May-13
31-May-13
07-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
05-Jul-13
12-Jul-13
19-Jul-13
26-Jul-13
02-Aug-13
09-Aug-13
16-Aug-13
23-Aug-13
30-Aug-13
06-Sep-13
13-Sep-13
20-Sep-13
27-Sep-13
04-Oct-13
ONSITE PLANNED ONSITE EARNED ONSITE ACTUAL ONSITE FINAL EOT
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
10,000
20,000
30,000
40,000
50,000
60,000
OFFSITE PLANNED OFFSITE EARNED OFFSITE ACTUAL OFFSITE FINAL EOT
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
13
40
79
50
95
75
122
174
137
81 80
38
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2012 2013
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
SI VALUE $ SI HOURS
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
PC
BL
EOT01
EOT02
EOT03
EOT05 EOT06
EOT04
LAST ME DELIVERY
BL ME DELIVERY
LAST ST DELIVERY
BL ST DELIVERY
BL PL DELIVERY
LAST BL SITE ACCESS
LAST ACTUAL SITE ACCESS
FINAL EOT
20-Nov-12
30-Nov-12
10-Dec-12
20-Dec-12
31-Dec-12
10-Jan-13
20-Jan-13
31-Jan-13
10-Feb-13
20-Feb-13
03-Mar-13
13-Mar-13
23-Mar-13
02-Apr-13
13-Apr-13
23-Apr-13
03-May-13
14-May-13
24-May-13
03-Jun-13
14-Jun-13
24-Jun-13
04-Jul-13
14-Jul-13
25-Jul-13
04-Aug-13
14-Aug-13
25-Aug-13
04-Sep-13
14-Sep-13
25-Sep-13
05-Oct-13
15-Oct-13
25-Oct-13 11-Aug-12
18-Aug-12
25-Aug-12
01-Sep-12
08-Sep-12
15-Sep-12
22-Sep-12
29-Sep-12
06-Oct-12
13-Oct-12
20-Oct-12
27-Oct-12
17-Nov-12
24-Nov-12
30-Nov-12
07-Dec-12
14-Dec-12
21-Dec-12
28-Dec-12
04-Jan-13
11-Jan-13
18-Jan-13
25-Jan-13
01-Feb-13
08-Feb-13
15-Feb-13
22-Feb-13
01-Mar-13
08-Mar-13
15-Mar-13
22-Mar-13
29-Mar-13
05-Apr-13
12-Apr-13
19-Apr-13
26-Apr-13
03-May-13
10-May-13
17-May-13
24-May-13
31-May-13
07-Jun-13
14-Jun-13
21-Jun-13
28-Jun-13
05-Jul-13
12-Jul-13
19-Jul-13
26-Jul-13
02-Aug-13
09-Aug-13
16-Aug-13
23-Aug-13
30-Aug-13
 PROJECT WEEKS 
REVK-->BASELINE
REVB
REVC
REVD
REVH
REVJ
EOT01
EOT03
EOT04
EOT05ANDEOT06
EOT02
PROJECT-BASELINEPC
REVE/F/G
SUB-SYSTEMAPPROACH
Sample Close-out Report by Amin Hadjaran (ahadjaran@yahoo.com)
BASELINE
FACILITY [TGP-011] SUMMARY GANTT
FINAL EOTACTUAL
01-May-12
31-May-12
01-Jul-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
30-Jan-13
02-Mar-13
01-Apr-13
02-May-13
01-Jun-13
02-Jul-13
01-Aug-13
01-Sep-13
01-Oct-13
01-Nov-13
SITEACCESS
DELIVERY -STRUCTURAL
OFFSITEPANELISATION -STRUCTURAL
ONSITEPANELISATION -STRUCTURAL
ONSITECONSTRUCTION -STRUCTURAL
DELIVERY -MECHANICAL
CONSTRUCTION - MECHANICAL
DELIVERY -PLATEWORK
CONSTRUCTION - PLATEWORK
OFFSITEFABRICATION -PIPING
CONSTRUCTION - PIPING
PUNCHLIST- COMMISSIONING
STRUCTURAL COMPLETE
PLATEWORK COMPLETE
MECHANICAL COMPLETE
PIPING COMPLETE
PROJECT- PC
STRUCTURAL COMPLETE
PLATEWORK COMPLETE
MECHANICAL COMPLETE
PIPING COMPLETE
PROJECT - PC

Sample Contract Close-out Report

  • 1.
    Sample Project Close-outReport By Amin Hadjaran (ahadjaran@yahoo.com)
  • 2.
    Sample Project Close-outReport This Close-out Report has been prepared for an SMP EPC Mining Contract that has been executed in Western Australia in 2012 – 2014. By Amin Hadjaran (ahadjaran@yahoo.com)
  • 4.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) SITE ACCESS TOTAL 48 LATE 20 42% EARLY 28 58% ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 -… 125 -… 131 -… 132 -… 134 -… 141 -… 142 -… 144 -… 146 -… 147 -… 161 - CIL 162 -… 171 -… 172 -… 181 -… 183 -… 211 -… 212 -… 213 -… 214 -… 216 -… 219 -… 232 -… 233 -… 234 -… 235 -… 236 -… 238 -… 241 -… 251 -… 253 -… 261 -… 262 -… 312 -… 325 -… 331 -… 122-C -… 122-S -… CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008… CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 241 - PIPERACKS 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 331 - POWER SUPPLY 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHINGAND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 PROJECT
  • 5.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) STEEL DELIVERY TOTAL 34 LATE 30 88% EARLY 4 12% ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 134 141 144 161 171 172 181 211 212 213 214 216 219 241 251 261 312 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 144 - CARBON SAFETY SCREENING 161 - CIL 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 241 - PIPERACKS 251 - COMPRESSED AIR 261 - FUEL SUPPLY AND DISTRIBUTION 312 - EVENT POND 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 TGP-011 LATE STEEL DELIVERIES 122-C CLADDING 122-S LADDERS AND HANDRAIL CV001 TRUSS CONNECTION PLATES CV002 TAIL END GUARDS, TRUSS CONNECTION PLATES CV003 GUARDS, TRUSS CONNECTION PLATES CV004 TRUSS CONNECTION PLATES, GUARDS CV005 TRUSS CONNECTION PLATES, GUARDS CV006 TRUSS CONNECTION PLATES, GUARDS CV007 TRUSS CONNECTION PLATES, GUARDS CV008 TRUSS CONNECTION PLATES, GUARDS CV009 TRUSS CONNECTION PLATES, GUARDS CV010 TRUSS CONNECTION PLATES
  • 6.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 959.58 453.86 820.16 0 200 400 600 800 1,000 1,200 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 01-Jul-12 01-Aug-12 01-Sep-12 01-Oct-12 01-Nov-12 01-Dec-12 01-Jan-13 01-Feb-13 01-Mar-13 01-Apr-13 01-May-13 01-Jun-13 01-Jul-13 01-Aug-13 PROJECT BASELINE PROJECT EOT PROJECT ACTUAL Example: In the month of October, 2012, PIC were required to install 959.58 tonnes of steel as per the Rev 0 Baseline; with all delays incorporated, the expected figure for October was 453.86 tonnes. PIC were actually able to erect 820.16 tonnes in that time period.
  • 7.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ME DELIVERIES TOTAL 47 LATE 24 51% EARLY 23 49% ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 134 141 142 144 146 147 161 162 171 172 181 183 211 212 213 214 216 219 232 233 234 235 236 238 251 253 261 262 312 325 331 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 331 - POWER SUPPLY 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 TGP-011 LATE ME DELIVERIES 121VOITH COUPLING DELIVERED ON 11/6/13 - 1730-TGP011-HOM-129 1311730-TGP011-HOM-123, HPGR FEEDER METAL DETECTOR 1321730-TGP011-HOM-121, 13-FE-003/4 FLAT BARS DELIVERED ON 5/5/13 1611730-TGP011-HOM-140, BOLTS, NUTS AND WASHERS 1711730-TGP011-HOM-137, BOLTS, NUTS, GASKETS, ELBOWS 1811730-TGP011-HOM-131, DELIVERY OF 18-RO-001/2 CV001 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV002 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV003 1730-TGP011-HOM-132, TAKE UP PULLEY SHEDDER CV004 1730-TGP011-HOM-134, GUARD POSTS CV005 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV006 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV008 1730-TGP011-HOM-132, DRIVE FRAME CV009 1730-TGP011-HOM-123, METAL DETECTOR 13-MD-003 CV010 1730-TGP011-HOM-124, SHEAVE ASSEMBLY
  • 8.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) LATE PL DELIVERIES 1211730-TGP011-HOM-139 FOR 12-ZM-005 (BOLTS, NUTS, RUBBER, ETC.) 1251730-TGP011-HOM-132, SLIDING GATES, CHAIN AND PINS FOR 12-DU-004 1311730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 1321730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 134SAMPLE CHUTE DISCHARGE BOX DELIVERED ON 8/6/13 1411730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 1441730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 1611730-TGP011-HOM-124, PIPE AND CLAMP PLATE FOR 16-BX-002 1621730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 1721730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 1831730-TGP011-HOM-125, MISSING ITEMS FOR THE DUCTS 2131730-TGP011-HOM-124, MISSING ITEMS 262LPG TANK WAS DELIVERED ON 16/7 AND INSTALLED ON 24/7 122-C 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS 122-S 1730-TGP011-HOM-132, SLIDING GATES, PINS AND CHAINS FOR DUCTS CV001 1730-TGP011-HOM-121, ELBOWS, NIPPLES, ETC. CV002 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV003 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV004 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV006 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS CV010 1730-TGP011-HOPW-042, BOLTS AND WASHERS FOR SEVERAL ITEMS PL DELIVERIES TOTAL 37 LATE 16 43% EARLY 21 57% ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 134 141 142 144 146 147 161 162 171 172 181 183 211 212 213 216 233 253 261 262 331 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 144 - CARBON SAFETY SCREENING 161 - CIL 162 - CARBON RECOVERY 183 - ELECTROWINNING 213 - FLOCCULANTS 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV010
  • 10.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 134 141 144 161 171 172 181 211 212 213 214 216 219 241 251 261 312 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 144 - CARBON SAFETY SCREENING 161 - CIL 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 241 - PIPERACKS 251 - COMPRESSED AIR 261 - FUEL SUPPLY AND DISTRIBUTION 312 - EVENT POND 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 TGP-011 EXCLUDING PUNCHLISTING
  • 11.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 133 134 141 142 144 146 147 161 162 171 172 181 183 211 212 213 214 216 219 232 233 234 235 236 238 251 253 261 262 312 325 331 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 133 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 331 - POWER SUPPLY 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 TGP-011 EXCLUDING PUNCHLISTING
  • 12.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 125 131 132 134 141 142 144 146 147 161 162 171 172 181 183 211 212 213 216 233 253 261 262 331 122-C 122-S CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 216 - ACID 233 - PROCESS WATER 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 331 - POWER SUPPLY 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 TGP-011 EXCLUDING PUNCHLISTING
  • 13.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 -… 125 -… 131 -… 132 -… 134 -… 141 -… 142 -… 144 -… 146 -… 161 - CIL 162 -… 171 -… 172 -… 181 -… 183 -… 211 -… 212 -… 213 -… 214 -… 216 -… 219 -… 232 -… 233 -… 234 -… 235 -… 236 -… 238 -… 241 -… 251 -… 253 -… 261 -… 262 -… 312 -… 325 -… 122-C -… 122-S -… PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 241 - PIPERACKS 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING PROJECT EXCLUDING PUNCHLISTING
  • 14.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 -… 125 -… 131 -… 132 -… #N/A 134 -… 141 -… 142 -… 144 -… 146 -… 147 -… 161 - CIL 162 -… 171 -… 172 -… 181 -… 183 -… 211 -… 212 -… 213 -… 214 -… 216 -… 219 -… 232 -… 233 -… 234 -… 235 -… 236 -… 238 -… 241 -… 251 -… 253 -… 261 -… 262 -… 312 -… 325 -… 331 -… 122-C -… 122-S -… CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008… CV009 CV010 PROJECT 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING #N/A 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 241 - PIPERACKS 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 331 - POWER SUPPLY 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 PROJECT EXCLUDING PUNCHLISTING
  • 15.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ACTUAL FINAL EOT BASELINE 121 - PRIMARY CRUSHING 125 - PRIMARY STOCKPILE AND RECLAIM 131 - HPGR 132 - HPGR SCREENING AND GRINDING 134 - FINE ORE STORAGE AND RECLAIM 141 - TRASH SCREENING 142 - THICKENING - FEED 144 - CARBON SAFETY SCREENING 146 - THICKENING - TAILS 147 - TAILS PUMPING 161 - CIL 162 - CARBON RECOVERY 171 - ACID WASH / ELUTION 172 - CARBON REGENERATION 181 - GOLDROOM 183 - ELECTROWINNING 211 - CYANIDE 212 - LIME 213 - FLOCCULANTS 214 - CAUSTIC 216 - ACID 219 - LEAD NITRATE 232 - RAW WATER 233 - PROCESS WATER 234 - POTABLE WATER 235 - GLAND SEAL WATER 236 - COOLING WATER 238 - FIRE WATER 241 - PIPERACKS 251 - COMPRESSED AIR 253 - OXYGEN PLANT 261 - FUEL SUPPLY AND DISTRIBUTION 262 - GAS SUPPLY AND DISTRIBUTION 312 - EVENT POND 325 - WATER TREATMENT PLANT 122-C - SECONDARY CRUSHING 122-S - SECONDARY CRUSHING AND SCREENING CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008 / 11 CV009 CV010 PROJECT 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 121 -… 125 -… 131 -… 132 -… 134 -… 141 -… 142 -… 144 -… 146 -… 147 -… 161 - CIL 162 -… 171 -… 172 -… 181 -… 183 -… 211 -… 212 -… 213 -… 214 -… 216 -… 219 -… 232 -… 233 -… 234 -… 235 -… 236 -… 238 -… 241 -… 251 -… 253 -… 261 -… 262 -… 312 -… 325 -… 122-C -… 122-S -… CV001 CV002 CV003 CV004 CV005 CV006 CV007 CV008… CV009 CV010 PROJECT
  • 16.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0% 20% 40% 60% 80% 100% 120% 21-Sep-12 5-Oct-12 19-Oct-12 2-Nov-12 16-Nov-12 30-Nov-12 14-Dec-12 28-Dec-12 11-Jan-13 25-Jan-13 8-Feb-13 22-Feb-13 8-Mar-13 22-Mar-13 5-Apr-13 19-Apr-13 3-May-13 17-May-13 31-May-13 14-Jun-13 28-Jun-13 12-Jul-13 26-Jul-13 9-Aug-13 23-Aug-13 REV 0 BASELINE + AFC LINES FINAL EOT ACTUAL
  • 18.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 374,068 405,276 431,877 532,914 ORIGINAL BUDGET REMEASURED BUDGET REMEASURED BUDGET+SIs ACTUAL ONSITE AND OFFSITE
  • 19.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) REV 0 ACTUAL FINAL EOT 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 165 170 175 180 185 190 195 200 205 210 215 220 225 230 235 240 245 250 3-Aug-12 10-Aug-12 17-Aug-12 24-Aug-12 31-Aug-12 7-Sep-12 14-Sep-12 21-Sep-12 28-Sep-12 5-Oct-12 12-Oct-12 19-Oct-12 26-Oct-12 2-Nov-12 9-Nov-12 16-Nov-12 23-Nov-12 30-Nov-12 7-Dec-12 14-Dec-12 21-Dec-12 28-Dec-12 4-Jan-13 11-Jan-13 18-Jan-13 25-Jan-13 1-Feb-13 8-Feb-13 15-Feb-13 22-Feb-13 1-Mar-13 8-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 5-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 3-May-13 10-May-13 17-May-13 24-May-13 31-May-13 7-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 5-Jul-13 12-Jul-13 19-Jul-13 26-Jul-13 2-Aug-13 9-Aug-13 16-Aug-13 23-Aug-13 30-Aug-13 6-Sep-13 13-Sep-13 20-Sep-13 27-Sep-13 4-Oct-13 11-Oct-13
  • 20.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 100,000 200,000 300,000 400,000 500,000 600,000 CONVEYOR PUNCHLISTING MECHANICAL PLATEWORK PIPING STRUCTURAL TOTAL BUDGETED ACTUAL FINAL EOT (INCL. SIs)
  • 21.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 120 Total 130 Total 140 Total 160 Total 170 Total 180 Total 210 Total 230 Total 240 Total 250 Total 260 Total 310 Total 320 Total 330 Total 340 Total BUDGETED ACTUAL FINAL EOT (INCL. SIs)
  • 22.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) INDIRECTS, 212,972, 28% OFF THE JOB, 24,699, 3% DIRECTS, 532,914, 69% ONSITE AND OFFSITE OFF THE JOB INDUCTIONS TOOLBOX & MEETING INCLEMENT WEATHER TRAVEL TIME
  • 23.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) INCLEMENT WEATHER, 10,050, 41% INDUCTIONS, 3,127, 13% TOOLBOX & MEETING, 4,307, 17% TRAVEL TIME, 7,216, 29% ONSITE ONLY
  • 24.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) Advanced Rigger, 8,645, 2% Apprentice, 4,122, 1% Belt Splicer, 684, 0% Boilermaker, 63,008, 12% CNC Operator, 103, 0% CNC Programmer, 227, 0% Combined, 28,554, 5% Crane Driver / Operator, 29,179, 5% Fitter, 16,370, 3% Machine Operator, 89, 0% Machinist, 1,493, 0%Mechanical Fitter, 32,335, 6% Metal Trade, 6,112, 1% Painter, 4,052, 1% Pipe Fitter, 77,633, 15% Poly Welder, 9,977, 2% Rigger, 103,866, 19% Rigger / Scaffolder, 1,399, 0% Roll/Press Operator, 16, 0% Scaffolder, 13,651, 3% Sheeters/Cladders, 2,961, 1% T/A, 79,008, 15% W/S Foreman, 21, 0% Welder, 49,412, 9% ONSITE AND OFFSITE
  • 25.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ONSITE ONLY Advanced Rigger, 7,841, 2% Apprentice, 251, 0% Belt Splicer, 684, 0% Boilermaker, 54,430, 11% Combined, 12,468, 3% Crane Driver / Operator, 28,218, 6% Fitter, 16,370, 3% Mechanical Fitter, 32,304, 7% Metal Trade, 6,106, 1% Painter, 4,052, 1% Pipe Fitter, 77,436, 16% Poly Welder, 9,235, 2% Rigger, 101,569, 21% Rigger / Scaffolder, 1,399, 0% Scaffolder, 13,621, 3% Sheeters/Cladders, 2,961, 1% T/A, 71,293, 15% Welder, 39,640, 8%
  • 26.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) AREA MANAGER, 8,204, 4% BELT SPLICING, 332, 0% CLADDING, 371, 0% COST CONTROL, 3,495, 2% ENGINEERING, 18,707, 9% MATERIAL RECEIVAL, 25,646, 12% OUTOTEC, 1,920, 1% PAINTING, 585, 0% PLANNING, 3,559, 2% PROJECT MANAGEMENT, 8,932, 4% QA MANAGER, 6,418, 3% QUANTITY SURVEYING, 6,566, 3% REFEULING, 3,154, 1% SAFETY, 16,213, 8% SITE SERVICES, 12,028, 6% SUPERINTENDENT, 10,217, 5% SUPERVISOR, 55,148, 26% UNKNOWN, 30,303, 14% VARIATION WORK, 1,177, 1% SITE SERVICES MECHANIC PEGGY STORE PERSON MOB/DEMOB CREW ONSITE AND OFFSITE
  • 27.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) ONSITE AND OFFSITE VARIATIONS, 26,601, 5% STRUCTURAL, 181,575, 34% PLATEWORK, 1,574, 0% MECHANICAL, 123,792, 23% PIPING, 199,378, 38%
  • 28.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 0.2 0.4 0.6 0.8 1 1.2 1.4 20-Jul-12 27-Jul-12 03-Aug-12 10-Aug-12 17-Aug-12 24-Aug-12 31-Aug-12 07-Sep-12 14-Sep-12 21-Sep-12 28-Sep-12 05-Oct-12 12-Oct-12 19-Oct-12 26-Oct-12 02-Nov-12 09-Nov-12 16-Nov-12 23-Nov-12 30-Nov-12 07-Dec-12 14-Dec-12 21-Dec-12 28-Dec-12 04-Jan-13 11-Jan-13 18-Jan-13 25-Jan-13 01-Feb-13 08-Feb-13 15-Feb-13 22-Feb-13 01-Mar-13 08-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 05-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 03-May-13 10-May-13 17-May-13 24-May-13 31-May-13 07-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 12-Jul-13 19-Jul-13 26-Jul-13 02-Aug-13 09-Aug-13 16-Aug-13 23-Aug-13 30-Aug-13 06-Sep-13 13-Sep-13 20-Sep-13 27-Sep-13 04-Oct-13 OVERALL PF ONSITE PF
  • 29.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 08-Feb-13 15-Feb-13 22-Feb-13 01-Mar-13 08-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 05-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 03-May-13 10-May-13 17-May-13 24-May-13 31-May-13 07-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 12-Jul-13 Site Overall PIC Outotec CPC QA Pipe Systems SMP ONSITE ONLY
  • 31.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 100,000 200,000 300,000 400,000 500,000 600,000 20-Jul-12 27-Jul-12 03-Aug-12 10-Aug-12 17-Aug-12 24-Aug-12 31-Aug-12 07-Sep-12 14-Sep-12 21-Sep-12 28-Sep-12 05-Oct-12 12-Oct-12 19-Oct-12 26-Oct-12 02-Nov-12 09-Nov-12 16-Nov-12 23-Nov-12 30-Nov-12 07-Dec-12 14-Dec-12 21-Dec-12 28-Dec-12 04-Jan-13 11-Jan-13 18-Jan-13 25-Jan-13 01-Feb-13 08-Feb-13 15-Feb-13 22-Feb-13 01-Mar-13 08-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 05-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 03-May-13 10-May-13 17-May-13 24-May-13 31-May-13 07-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 12-Jul-13 19-Jul-13 26-Jul-13 02-Aug-13 09-Aug-13 16-Aug-13 23-Aug-13 30-Aug-13 06-Sep-13 13-Sep-13 20-Sep-13 27-Sep-13 04-Oct-13 11-Oct-13 18-Oct-13 OVERALL PLANNED OVERALL EARNED OVERAL ACTUAL FINAL EOT
  • 32.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 100,000 200,000 300,000 400,000 500,000 600,000 20-Jul-12 27-Jul-12 03-Aug-12 10-Aug-12 17-Aug-12 24-Aug-12 31-Aug-12 07-Sep-12 14-Sep-12 21-Sep-12 28-Sep-12 05-Oct-12 12-Oct-12 19-Oct-12 26-Oct-12 02-Nov-12 09-Nov-12 16-Nov-12 23-Nov-12 30-Nov-12 07-Dec-12 14-Dec-12 21-Dec-12 28-Dec-12 04-Jan-13 11-Jan-13 18-Jan-13 25-Jan-13 01-Feb-13 08-Feb-13 15-Feb-13 22-Feb-13 01-Mar-13 08-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 05-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 03-May-13 10-May-13 17-May-13 24-May-13 31-May-13 07-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 12-Jul-13 19-Jul-13 26-Jul-13 02-Aug-13 09-Aug-13 16-Aug-13 23-Aug-13 30-Aug-13 06-Sep-13 13-Sep-13 20-Sep-13 27-Sep-13 04-Oct-13 ONSITE PLANNED ONSITE EARNED ONSITE ACTUAL ONSITE FINAL EOT
  • 33.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 10,000 20,000 30,000 40,000 50,000 60,000 OFFSITE PLANNED OFFSITE EARNED OFFSITE ACTUAL OFFSITE FINAL EOT
  • 34.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 13 40 79 50 95 75 122 174 137 81 80 38 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2012 2013
  • 35.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 $0 $100,000 $200,000 $300,000 $400,000 $500,000 $600,000 $700,000 $800,000 SI VALUE $ SI HOURS
  • 36.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) PC BL EOT01 EOT02 EOT03 EOT05 EOT06 EOT04 LAST ME DELIVERY BL ME DELIVERY LAST ST DELIVERY BL ST DELIVERY BL PL DELIVERY LAST BL SITE ACCESS LAST ACTUAL SITE ACCESS FINAL EOT 20-Nov-12 30-Nov-12 10-Dec-12 20-Dec-12 31-Dec-12 10-Jan-13 20-Jan-13 31-Jan-13 10-Feb-13 20-Feb-13 03-Mar-13 13-Mar-13 23-Mar-13 02-Apr-13 13-Apr-13 23-Apr-13 03-May-13 14-May-13 24-May-13 03-Jun-13 14-Jun-13 24-Jun-13 04-Jul-13 14-Jul-13 25-Jul-13 04-Aug-13 14-Aug-13 25-Aug-13 04-Sep-13 14-Sep-13 25-Sep-13 05-Oct-13 15-Oct-13 25-Oct-13 11-Aug-12 18-Aug-12 25-Aug-12 01-Sep-12 08-Sep-12 15-Sep-12 22-Sep-12 29-Sep-12 06-Oct-12 13-Oct-12 20-Oct-12 27-Oct-12 17-Nov-12 24-Nov-12 30-Nov-12 07-Dec-12 14-Dec-12 21-Dec-12 28-Dec-12 04-Jan-13 11-Jan-13 18-Jan-13 25-Jan-13 01-Feb-13 08-Feb-13 15-Feb-13 22-Feb-13 01-Mar-13 08-Mar-13 15-Mar-13 22-Mar-13 29-Mar-13 05-Apr-13 12-Apr-13 19-Apr-13 26-Apr-13 03-May-13 10-May-13 17-May-13 24-May-13 31-May-13 07-Jun-13 14-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 12-Jul-13 19-Jul-13 26-Jul-13 02-Aug-13 09-Aug-13 16-Aug-13 23-Aug-13 30-Aug-13  PROJECT WEEKS  REVK-->BASELINE REVB REVC REVD REVH REVJ EOT01 EOT03 EOT04 EOT05ANDEOT06 EOT02 PROJECT-BASELINEPC REVE/F/G SUB-SYSTEMAPPROACH
  • 37.
    Sample Close-out Reportby Amin Hadjaran (ahadjaran@yahoo.com) BASELINE FACILITY [TGP-011] SUMMARY GANTT FINAL EOTACTUAL 01-May-12 31-May-12 01-Jul-12 31-Jul-12 31-Aug-12 30-Sep-12 31-Oct-12 30-Nov-12 31-Dec-12 30-Jan-13 02-Mar-13 01-Apr-13 02-May-13 01-Jun-13 02-Jul-13 01-Aug-13 01-Sep-13 01-Oct-13 01-Nov-13 SITEACCESS DELIVERY -STRUCTURAL OFFSITEPANELISATION -STRUCTURAL ONSITEPANELISATION -STRUCTURAL ONSITECONSTRUCTION -STRUCTURAL DELIVERY -MECHANICAL CONSTRUCTION - MECHANICAL DELIVERY -PLATEWORK CONSTRUCTION - PLATEWORK OFFSITEFABRICATION -PIPING CONSTRUCTION - PIPING PUNCHLIST- COMMISSIONING STRUCTURAL COMPLETE PLATEWORK COMPLETE MECHANICAL COMPLETE PIPING COMPLETE PROJECT- PC STRUCTURAL COMPLETE PLATEWORK COMPLETE MECHANICAL COMPLETE PIPING COMPLETE PROJECT - PC