SlideShare a Scribd company logo
 Dredging Program and Project Background
 Project Benefits
 Royal Lake Conditions
 Phased Approach
 Dredging Methods and Alternatives
 Park Access and Community Coordination
 Next Steps
Royal Lake: Meeting Agenda
 History
– Lakes previously dredged by DPWES Stormwater
– Limited to small quantities
– Dewatered on site
 Lake Barton completed in 2011
 Currently working on:
– Huntsman Lake, Woodglen Lake, Royal Lake
Dredging and Lake Restoration Program
 Completed Data Collection
 Developing Lake Dredging and Management Plan
 Community coordination at design and construction
phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: Pardon Our Dust meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (July 2014)
Royal Lake Dredging and Restoration
Project Timeline and Coordination
 Restore sediment pool capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
 Improve lake water quality and habitat
 Provide long term maintenance improvements
Project Goals and Benefit
Lake Barton Dredging and Restoration
Area Treated
(acres)
Phosphorous Removal Nitrogen Removal Sediment Removal
544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged
Annual benefit from
increased trapping
efficiency
130 lbs/year 200 lbs/year 65 tons/year
Royal Lake Facts
 Drainage area =
2,477 acres (3.67 square miles)
 Lake surface area =
37.5 acres
 Sediment pool capacity =
416,000 cubic yards (CY)
 Current sediment in lake =
100,400 CY
 Estimated annual sediment load =
4,400 CY
50 feet
100,400 CY
Royal Lake
Royal Lake: Sediment Thickness
Royal Lake: Water Depth
Royal Lake: Dredging Areas
 Phase 1: Base Dredge = 40,000 CY
 Phase 2: Up to an additional 60,000 CY
Zone D
12,400 CY
Royal Lake: Partial Drawdown
Dredging Methods and Alternatives
1. Mechanically dredge
deposited sediment and
haul wet
2. Drain lake and dry
deposited sediment in
place before hauling
PRE-DREDGING:
An estimated
35,000 cubic yards
of sediment had
accumulated in
the lake, forming
islands and
reducing water
levels to less than
three feet in most
areas.
Lake Barton Example
Lake Barton Example: Pre-Dredging
LakeBartonExample: DredginginProgress
Dredging:
Dredging took
place without
draining the lake.
LakeBartonExample: DredginginProgress
Lake Barton Example: Disposal Site
North Park Lake Example Allegheny County, Pennsylvania
Dredging:
The lake was drained
and the sediment was
dried in-place.
North Park Lake Example Allegheny County, Pennsylvania
Temporary Diversion
Channels
Equipment Working
on Next Slide
North Park Lake: Dredging Allegheny County, Pennsylvania
Truck Wash
Temporary
Diversion Channel
Low Pressure
Excavator
Bulldozer
Bulldozer
Excavator
and DozerTruck Access
Staging
 General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
 Benefits
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
 Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Dredge Alternative – In the Wet
 General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
 Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
 Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Typically more odor from sediment exposed
– Need to relocate/salvage fish
Dredge Alternative – In the Dry
 In-lake forebay
 Wetland planting
 Shoreline stabilization
 Fish habitat
 Fish stocking
Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
Royal Lake: Shoreline Restoration
Royal Lake: Shoreline Restoration
Royal Lake
Existing
Conditions
Shoreline Protection Options
Fish Habitat Structures
Royal Lake: Site Access and Staging
Optional?
Royal Lake: Site Access and Staging
Staging Area 1 Potential Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
Royal Lake: Dewatering Basin
Inactive
Dewatering Basin
Access During Construction
Public Access:
The park will remain
open and existing
parking lot will be
available.
Access During Construction
Public Access:
Pedestrian gates will be
provided. Access
through work areas and
trails around the lake
after work hours.
 Community coordination at design and construction phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: “Pardon Our Dust” meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (Starts July 2014)
 Project Duration:
– Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months
Royal Lake Dredging and Restoration
Project Timeline and Coordination
Contacts:
 Martin Chang, Project Manager
703-324-5825 | Martin.Chang@fairfaxcounty.gov
 Dipmani Kumar, Section Chief
703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov
 http://www.fairfaxcounty.gov/dpwes/stormwater/
Royal Lake DredgingandRestoration
http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/

More Related Content

What's hot

Technology in education
Technology in educationTechnology in education
Technology in education
Steven Miner
 
Technology in education
Technology in educationTechnology in education
Technology in education
Shafeeque Pm
 
Report on Air Pollution
Report on Air PollutionReport on Air Pollution
Report on Air Pollution
Jheane Candido
 
Social Media and the Future of Education
Social Media and the Future of EducationSocial Media and the Future of Education
Social Media and the Future of Education
HotRod007
 
Technology in education
Technology in educationTechnology in education
Technology in education
aynnarcena
 
The role of inflibnet in improving teaching learning
The role of inflibnet in improving teaching learningThe role of inflibnet in improving teaching learning
The role of inflibnet in improving teaching learning
Sruthi M. Pappachan
 
Ozone layer depletion
Ozone layer depletionOzone layer depletion
Ozone layer depletion
Haseena Hameed
 
AIR POLLUTION
AIR POLLUTIONAIR POLLUTION
AIR POLLUTION
Hemanth Krishnan R
 
Environment and pollution
Environment and pollutionEnvironment and pollution
Environment and pollution
Niharika Pande
 
Air Pollution Effect on Animals & Plants
Air Pollution Effect on Animals & PlantsAir Pollution Effect on Animals & Plants
Air Pollution Effect on Animals & Plants
Hiten Patel
 
REFLECTION OF TEACHING ON THE USE OF ICT IN CLASSROOM
REFLECTION OF TEACHING  ON THE USE OF ICT IN CLASSROOMREFLECTION OF TEACHING  ON THE USE OF ICT IN CLASSROOM
REFLECTION OF TEACHING ON THE USE OF ICT IN CLASSROOM
profesorjulioperez
 
Environmental pollution
Environmental  pollutionEnvironmental  pollution
Environmental pollution
karan saini
 
ENVIRONMENT
ENVIRONMENTENVIRONMENT
ENVIRONMENT
nassirajimenez
 
Inclusive Design 101
Inclusive Design 101Inclusive Design 101
Inclusive Design 101
Sooshin Choi
 
Coursera
CourseraCoursera
Coursera
Mohammad Alyan
 
Current Trends in Educational Technology
Current Trends in Educational TechnologyCurrent Trends in Educational Technology
Current Trends in Educational Technology
EDUCAUSE
 
Adolescents & media challenges in 21 st century
Adolescents & media challenges in 21 st centuryAdolescents & media challenges in 21 st century
Adolescents & media challenges in 21 st century
shhajira
 
Ict u5
Ict u5Ict u5
Air pollution
Air pollutionAir pollution
Air pollution
ebchandar
 
Air pollution
Air pollution Air pollution
Air pollution
Dr. Tanuja Nautiyal
 

What's hot (20)

Technology in education
Technology in educationTechnology in education
Technology in education
 
Technology in education
Technology in educationTechnology in education
Technology in education
 
Report on Air Pollution
Report on Air PollutionReport on Air Pollution
Report on Air Pollution
 
Social Media and the Future of Education
Social Media and the Future of EducationSocial Media and the Future of Education
Social Media and the Future of Education
 
Technology in education
Technology in educationTechnology in education
Technology in education
 
The role of inflibnet in improving teaching learning
The role of inflibnet in improving teaching learningThe role of inflibnet in improving teaching learning
The role of inflibnet in improving teaching learning
 
Ozone layer depletion
Ozone layer depletionOzone layer depletion
Ozone layer depletion
 
AIR POLLUTION
AIR POLLUTIONAIR POLLUTION
AIR POLLUTION
 
Environment and pollution
Environment and pollutionEnvironment and pollution
Environment and pollution
 
Air Pollution Effect on Animals & Plants
Air Pollution Effect on Animals & PlantsAir Pollution Effect on Animals & Plants
Air Pollution Effect on Animals & Plants
 
REFLECTION OF TEACHING ON THE USE OF ICT IN CLASSROOM
REFLECTION OF TEACHING  ON THE USE OF ICT IN CLASSROOMREFLECTION OF TEACHING  ON THE USE OF ICT IN CLASSROOM
REFLECTION OF TEACHING ON THE USE OF ICT IN CLASSROOM
 
Environmental pollution
Environmental  pollutionEnvironmental  pollution
Environmental pollution
 
ENVIRONMENT
ENVIRONMENTENVIRONMENT
ENVIRONMENT
 
Inclusive Design 101
Inclusive Design 101Inclusive Design 101
Inclusive Design 101
 
Coursera
CourseraCoursera
Coursera
 
Current Trends in Educational Technology
Current Trends in Educational TechnologyCurrent Trends in Educational Technology
Current Trends in Educational Technology
 
Adolescents & media challenges in 21 st century
Adolescents & media challenges in 21 st centuryAdolescents & media challenges in 21 st century
Adolescents & media challenges in 21 st century
 
Ict u5
Ict u5Ict u5
Ict u5
 
Air pollution
Air pollutionAir pollution
Air pollution
 
Air pollution
Air pollution Air pollution
Air pollution
 

Similar to Royal Lake Dredging and Restoration

Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
Fairfax County
 
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Fairfax County
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
Fairfax County
 
Flood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseFlood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt Machielse
YourAlberta
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
Michael Josselyn
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Fairfax County
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
Healthy Lakes, Healthy Lives
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
Fairfax County
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
MCDEP
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
Expresso das Idéias Produções
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
Expresso das Idéias Produções
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
Fairfax County
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
Environmental Protection Agency, Ireland
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
Fairfax County
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
SWCNabi
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Phillip Rury
 
Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11
Northwest Indian Fisheries Commission
 
Lake shady plans
Lake shady plansLake shady plans
Lake shady plans
Post-Bulletin Co.
 

Similar to Royal Lake Dredging and Restoration (20)

Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
 
Flood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseFlood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt Machielse
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
 
Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11
 
Lake shady plans
Lake shady plansLake shady plans
Lake shady plans
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
Fairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Fairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
Fairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Fairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
Fairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Fairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Fairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Fairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Fairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

bombay-hc-hamare-baraah-film-june-19.pdf
bombay-hc-hamare-baraah-film-june-19.pdfbombay-hc-hamare-baraah-film-june-19.pdf
bombay-hc-hamare-baraah-film-june-19.pdf
bhavenpr
 
Polarised Media Framing of Climate Protests
Polarised Media Framing of Climate ProtestsPolarised Media Framing of Climate Protests
Polarised Media Framing of Climate Protests
Axel Bruns
 
15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
On the Wrong Track | Recent Increasing Train Accidents in India | News
On the Wrong Track | Recent Increasing Train Accidents in India | NewsOn the Wrong Track | Recent Increasing Train Accidents in India | News
On the Wrong Track | Recent Increasing Train Accidents in India | News
Harsh Kumar
 
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
Axel Bruns
 
Manual-of-Finance-and-Accounts-22012020.pdf
Manual-of-Finance-and-Accounts-22012020.pdfManual-of-Finance-and-Accounts-22012020.pdf
Manual-of-Finance-and-Accounts-22012020.pdf
bhavenpr
 
21062024_First India Newspaper Jaipur.pdf
21062024_First India Newspaper Jaipur.pdf21062024_First India Newspaper Jaipur.pdf
21062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
bhavenpr
 
projet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdfprojet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdf
EdouardHusson
 
17062024_First India Newspaper Jaipur.pdf
17062024_First India Newspaper Jaipur.pdf17062024_First India Newspaper Jaipur.pdf
17062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
TN-Students-Caste-Discrimination-Chandru-Commission.pdf
TN-Students-Caste-Discrimination-Chandru-Commission.pdfTN-Students-Caste-Discrimination-Chandru-Commission.pdf
TN-Students-Caste-Discrimination-Chandru-Commission.pdf
bhavenpr
 
22062024_First India Newspaper Jaipur.pdf
22062024_First India Newspaper Jaipur.pdf22062024_First India Newspaper Jaipur.pdf
22062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
JOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínimaJOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínima
AlexisTorres963861
 
一比一原版美国宾夕法尼亚州立大学毕业证如何办理
一比一原版美国宾夕法尼亚州立大学毕业证如何办理一比一原版美国宾夕法尼亚州立大学毕业证如何办理
一比一原版美国宾夕法尼亚州立大学毕业证如何办理
guevtut
 
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
The Lifesciences Magazine
 
Bombay-hc-hamare-baraah-order-june-7.pdf
Bombay-hc-hamare-baraah-order-june-7.pdfBombay-hc-hamare-baraah-order-june-7.pdf
Bombay-hc-hamare-baraah-order-june-7.pdf
bhavenpr
 
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
rittaajmal71
 
JOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínimaJOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínima
AlexisTorres963861
 
bombay-hc-hamare-baraah-film-June-6.pdfde
bombay-hc-hamare-baraah-film-June-6.pdfdebombay-hc-hamare-baraah-film-June-6.pdfde
bombay-hc-hamare-baraah-film-June-6.pdfde
bhavenpr
 
16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 

Recently uploaded (20)

bombay-hc-hamare-baraah-film-june-19.pdf
bombay-hc-hamare-baraah-film-june-19.pdfbombay-hc-hamare-baraah-film-june-19.pdf
bombay-hc-hamare-baraah-film-june-19.pdf
 
Polarised Media Framing of Climate Protests
Polarised Media Framing of Climate ProtestsPolarised Media Framing of Climate Protests
Polarised Media Framing of Climate Protests
 
15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf
 
On the Wrong Track | Recent Increasing Train Accidents in India | News
On the Wrong Track | Recent Increasing Train Accidents in India | NewsOn the Wrong Track | Recent Increasing Train Accidents in India | News
On the Wrong Track | Recent Increasing Train Accidents in India | News
 
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
“What Else Are They Talking About?”: A Large-Scale Longitudinal Analysis of M...
 
Manual-of-Finance-and-Accounts-22012020.pdf
Manual-of-Finance-and-Accounts-22012020.pdfManual-of-Finance-and-Accounts-22012020.pdf
Manual-of-Finance-and-Accounts-22012020.pdf
 
21062024_First India Newspaper Jaipur.pdf
21062024_First India Newspaper Jaipur.pdf21062024_First India Newspaper Jaipur.pdf
21062024_First India Newspaper Jaipur.pdf
 
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
 
projet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdfprojet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdf
 
17062024_First India Newspaper Jaipur.pdf
17062024_First India Newspaper Jaipur.pdf17062024_First India Newspaper Jaipur.pdf
17062024_First India Newspaper Jaipur.pdf
 
TN-Students-Caste-Discrimination-Chandru-Commission.pdf
TN-Students-Caste-Discrimination-Chandru-Commission.pdfTN-Students-Caste-Discrimination-Chandru-Commission.pdf
TN-Students-Caste-Discrimination-Chandru-Commission.pdf
 
22062024_First India Newspaper Jaipur.pdf
22062024_First India Newspaper Jaipur.pdf22062024_First India Newspaper Jaipur.pdf
22062024_First India Newspaper Jaipur.pdf
 
JOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínimaJOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínima
 
一比一原版美国宾夕法尼亚州立大学毕业证如何办理
一比一原版美国宾夕法尼亚州立大学毕业证如何办理一比一原版美国宾夕法尼亚州立大学毕业证如何办理
一比一原版美国宾夕法尼亚州立大学毕业证如何办理
 
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
 
Bombay-hc-hamare-baraah-order-june-7.pdf
Bombay-hc-hamare-baraah-order-june-7.pdfBombay-hc-hamare-baraah-order-june-7.pdf
Bombay-hc-hamare-baraah-order-june-7.pdf
 
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
 
JOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínimaJOH pide al juez Castel 40 años como sentencia mínima
JOH pide al juez Castel 40 años como sentencia mínima
 
bombay-hc-hamare-baraah-film-June-6.pdfde
bombay-hc-hamare-baraah-film-June-6.pdfdebombay-hc-hamare-baraah-film-June-6.pdfde
bombay-hc-hamare-baraah-film-June-6.pdfde
 
16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf
 

Royal Lake Dredging and Restoration

  • 1.
  • 2.  Dredging Program and Project Background  Project Benefits  Royal Lake Conditions  Phased Approach  Dredging Methods and Alternatives  Park Access and Community Coordination  Next Steps Royal Lake: Meeting Agenda
  • 3.  History – Lakes previously dredged by DPWES Stormwater – Limited to small quantities – Dewatered on site  Lake Barton completed in 2011  Currently working on: – Huntsman Lake, Woodglen Lake, Royal Lake Dredging and Lake Restoration Program
  • 4.  Completed Data Collection  Developing Lake Dredging and Management Plan  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: Pardon Our Dust meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (July 2014) Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 5.  Restore sediment pool capacity – Downstream water quality benefits – Lake water quality – Aesthetics  Improve lake water quality and habitat  Provide long term maintenance improvements Project Goals and Benefit
  • 6. Lake Barton Dredging and Restoration Area Treated (acres) Phosphorous Removal Nitrogen Removal Sediment Removal 544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged Annual benefit from increased trapping efficiency 130 lbs/year 200 lbs/year 65 tons/year
  • 7. Royal Lake Facts  Drainage area = 2,477 acres (3.67 square miles)  Lake surface area = 37.5 acres  Sediment pool capacity = 416,000 cubic yards (CY)  Current sediment in lake = 100,400 CY  Estimated annual sediment load = 4,400 CY 50 feet 100,400 CY
  • 11. Royal Lake: Dredging Areas  Phase 1: Base Dredge = 40,000 CY  Phase 2: Up to an additional 60,000 CY Zone D 12,400 CY
  • 13. Dredging Methods and Alternatives 1. Mechanically dredge deposited sediment and haul wet 2. Drain lake and dry deposited sediment in place before hauling
  • 14. PRE-DREDGING: An estimated 35,000 cubic yards of sediment had accumulated in the lake, forming islands and reducing water levels to less than three feet in most areas. Lake Barton Example
  • 15. Lake Barton Example: Pre-Dredging
  • 18. Lake Barton Example: Disposal Site
  • 19. North Park Lake Example Allegheny County, Pennsylvania Dredging: The lake was drained and the sediment was dried in-place.
  • 20. North Park Lake Example Allegheny County, Pennsylvania Temporary Diversion Channels Equipment Working on Next Slide
  • 21. North Park Lake: Dredging Allegheny County, Pennsylvania Truck Wash Temporary Diversion Channel Low Pressure Excavator Bulldozer Bulldozer Excavator and DozerTruck Access Staging
  • 22.  General Sequence – Establish access and staging areas – Conduct dredging utilizing barges – Haul wet sediment to disposal site for drying  Benefits – Less weather dependent – Quicker initial start to dredging – Less potential for schedule extensions or delay  Concerns – Increased sediment handling effort at disposal area – Potentially higher cost Dredge Alternative – In the Wet
  • 23.  General Sequence – Initiate drawdown of lake – Establish access and staging areas – Establish diversion channels within lake – Conduct dredging  Benefits – Higher daily sediment removal rates – Minimal sediment handling effort at disposal area – Potentially lower cost  Concerns – Very weather dependent – Higher potential for delays due to weather – Typically more odor from sediment exposed – Need to relocate/salvage fish Dredge Alternative – In the Dry
  • 24.  In-lake forebay  Wetland planting  Shoreline stabilization  Fish habitat  Fish stocking Lake Restoration Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 25. Royal Lake: Shoreline Restoration
  • 26. Royal Lake: Shoreline Restoration Royal Lake Existing Conditions
  • 29. Royal Lake: Site Access and Staging Optional?
  • 30. Royal Lake: Site Access and Staging
  • 31. Staging Area 1 Potential Expansion Berm/Cofferdam to be built Area to be dewatered and backfilled to expand staging area after berm/cofferdam is built
  • 32. Royal Lake: Dewatering Basin Inactive Dewatering Basin
  • 33. Access During Construction Public Access: The park will remain open and existing parking lot will be available.
  • 34. Access During Construction Public Access: Pedestrian gates will be provided. Access through work areas and trails around the lake after work hours.
  • 35.  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: “Pardon Our Dust” meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (Starts July 2014)  Project Duration: – Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months – Phase 2, Full Dredge: 9 to 12 Months Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 36. Contacts:  Martin Chang, Project Manager 703-324-5825 | Martin.Chang@fairfaxcounty.gov  Dipmani Kumar, Section Chief 703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov  http://www.fairfaxcounty.gov/dpwes/stormwater/ Royal Lake DredgingandRestoration http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/