An introduction to the Risk Management discipline of project management for early career engineers. This lecture was presented to students of Engineering Projects in Community Service (EPICS) classes at Purdue University in fall 2008.
This document discusses various types of risks in project management. It identifies different categories of risk like stakeholder risk, regulatory risk, external risk, execution risk, scope risk, scheduling risk, resource risk, and technology risk. It also describes risk management and techniques to incorporate risk factors in projects, including using a risk adjusted discount rate, certainty equivalent coefficient, sensitivity analysis, probability assignment, standard deviation, coefficient of variation, and decision tree analysis.
This document discusses moving from a risk management approach to performance uncertainty management when dealing with projects and their objectives. It argues that uncertainty management is more effective than separating opportunities from threats. The key points are:
1. Managing uncertainty, rather than just threats or opportunities, allows for a more comprehensive approach that considers all possible impacts.
2. Separating opportunities and threats into different processes is inefficient; a combined uncertainty management approach is better.
3. The ultimate goal is to understand where and why uncertainty is important in a given performance context before seeking to manage it.
The document discusses risk management strategies for projects. It identifies four types of risks: schedule, budget, operational, and technical. Schedule risks can occur due to wrong time estimation or resource issues. Budget risks include wrong cost estimation and overruns. Operational risks stem from priority conflicts and process impacts. Technical risks involve changing requirements, unavailable technology, complexity, and integration difficulties. External risks outside a project's control include funding issues, market changes, and shifting strategies or government rules. The key is to identify risks early to minimize costs and impacts through avoidance, transfer, acceptance, or mitigation approaches.
This document discusses project risk and risk management. It defines project risk as any uncertainty that can negatively or positively impact project objectives. It notes that risk management involves identifying, analyzing, and responding to risks throughout the project life cycle. The document outlines the major steps in developing a risk management plan, including identifying risks, assessing their probability and impact, developing response strategies, and monitoring risks dynamically. It concludes that while risks cannot be eliminated, they can be managed to help complete projects successfully.
Risk analysis for project decision-making
Presented by Keith Gray
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
This document discusses various types of risks in project management. It identifies different categories of risk like stakeholder risk, regulatory risk, external risk, execution risk, scope risk, scheduling risk, resource risk, and technology risk. It also describes risk management and techniques to incorporate risk factors in projects, including using a risk adjusted discount rate, certainty equivalent coefficient, sensitivity analysis, probability assignment, standard deviation, coefficient of variation, and decision tree analysis.
This document discusses moving from a risk management approach to performance uncertainty management when dealing with projects and their objectives. It argues that uncertainty management is more effective than separating opportunities from threats. The key points are:
1. Managing uncertainty, rather than just threats or opportunities, allows for a more comprehensive approach that considers all possible impacts.
2. Separating opportunities and threats into different processes is inefficient; a combined uncertainty management approach is better.
3. The ultimate goal is to understand where and why uncertainty is important in a given performance context before seeking to manage it.
The document discusses risk management strategies for projects. It identifies four types of risks: schedule, budget, operational, and technical. Schedule risks can occur due to wrong time estimation or resource issues. Budget risks include wrong cost estimation and overruns. Operational risks stem from priority conflicts and process impacts. Technical risks involve changing requirements, unavailable technology, complexity, and integration difficulties. External risks outside a project's control include funding issues, market changes, and shifting strategies or government rules. The key is to identify risks early to minimize costs and impacts through avoidance, transfer, acceptance, or mitigation approaches.
This document discusses project risk and risk management. It defines project risk as any uncertainty that can negatively or positively impact project objectives. It notes that risk management involves identifying, analyzing, and responding to risks throughout the project life cycle. The document outlines the major steps in developing a risk management plan, including identifying risks, assessing their probability and impact, developing response strategies, and monitoring risks dynamically. It concludes that while risks cannot be eliminated, they can be managed to help complete projects successfully.
Risk analysis for project decision-making
Presented by Keith Gray
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
Documentation on PMP Risk Management Plan & Template.
If you like a downloaded version, add me to your network on Linkedin
www.linkedin.com/in/alliegentry
and in the invite, please let me know you would like a word copy of this document.
Allie Gentry
PivotLogix
This document discusses project risk management. It defines risk as having possible outcomes that are understood, while uncertainty involves possible outcomes that are not understood. The key aspects of project risk management are risk identification, evaluation, response planning, monitoring and control. Project risk management aims to make projects more predictable and improve their chances of success through better planning and investment decisions.
The risk plan outlines defines how risk management will be conducted for the project. It ensures that the degree, type and visibility of risk management are appropriate for the risks and importance of the project. The risk plan outlines a full list of potential risks for the project, templates and documents for risk management, methods for assessing the probability and impact of risks, prioritization of risks, preventative and mitigative actions for risks, and how risk management will be conducted throughout project stages.
Building business continuity through risk management
Presented by Kimberley Hart
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
Applying risk factors in the strategic selection of portfolio projects
Presented by John MacGregor
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
This document provides information about an upcoming conference on managing risk in construction contracts and projects taking place on January 26-27, 2016 in Toronto. The conference will provide strategies for drafting precise contracts, allocating risk, ensuring appropriate insurance is in place, and more. Speakers will include lawyers, contractors, engineers, project managers and other professionals. Attendees can also choose to attend an additional half-day master class on drafting construction contracts or managing environmental and safety risks on projects. The event aims to help participants effectively plan for and manage risk in their construction contracts and projects.
The document provides instructions for completing a project risk register. The risk register tracks key information about identified project risks such as the risk number, date identified, risk description, category, potential impact, risk owner, probability of occurrence, impact of risk, risk level, response, status, date response invoked, and whether a contingency plan was developed. The document also provides examples of project risks in different phases to help identify risks and memory joggers to aid in the risk identification process.
This document provides an overview of risk and issue management best practices. It discusses key concepts like the differences between risks and issues, how to prioritize them, and the overall process of identifying, analyzing, taking action, monitoring, reviewing, and reporting on risks and issues over the lifecycle of a project. The goal is to familiarize workshop participants with a standardized terminology and approach to proactively manage risks and issues in order to minimize potential impacts on a project.
Project risk management: Techniques and strategiesDebashishDas49
Risk identification techniques and mitigation techniques in the present dynamic scenario of the industry is described here. Also, the recent research area and probable topics that one could choose as a Ph.D. topic are described briefly.
This document discusses construction risk management. It defines risk and identifies types of risks in construction projects, including financial, design, construction-related, and political/environment risks. It then describes construction risk management as identifying and mitigating risks through a six-step process: risk management planning, risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control. Managing risks can reduce costs, losses, and damage to reputation from delays, quality issues, and cost overruns. The benefits of effective risk management include effective resource use, continuous improvement, and reassuring stakeholders.
Where do risks (threats and opportunities) arise from?
Presented by Lynn Stalker
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
Risk management involves identifying potential risks to a project, analyzing their likelihood and impact, and developing plans to mitigate negative risks. Some key risks include staff turnover, requirements changes, and underestimating the time or resources needed. It is important to identify risks early, communicate about them, assign ownership, prioritize risks, and regularly monitor risks and mitigation strategies. Effective risk management can help promote the success of software projects by focusing resources and preventing potential problems.
The document discusses project risk management. It defines risk as a function of uniqueness and experience. There are two types of risks: business risks relating to gains/losses, and pure risks which only have downsides. The risk management process involves identifying risks early and throughout the project. Risks can then be avoided, mitigated, transferred to a third party, or accepted. Common risk responses include changing plans to avoid risks, reducing probability/impact of risks, assigning risks to third parties, and simply accepting small risks. Preparing for risks requires analyzing and prioritizing them based on likelihood and impact.
The document discusses risk management for projects. It defines risk as any uncertain event or condition that could positively or negatively impact a project's objectives. It notes that through risk management, a project manager can identify potential problems, take actions to prevent or minimize risks, and stay in control of the project. The document outlines the key steps in risk management as identifying risks, analyzing them, planning responses, implementing responses, and monitoring risks. It also discusses different ways to handle risks, such as avoiding, mitigating, transferring, accepting, or escalating risks.
This document discusses risk management and analysis. It defines risk management as identifying, analyzing, and responding to risks. Risk analysis helps identify potential problems that could undermine projects or initiatives. The key steps of risk analysis include identifying threats, estimating the likelihood and impact of each threat, and developing risk mitigation strategies. Quantitative techniques like decision trees and expected monetary value analysis can also be used. Ongoing risk monitoring and control is important to evaluate risks and ensure responses remain effective.
The document discusses the risk management framework which includes enterprise, portfolio, program, and project level risk management. It defines key terms like risk, uncertainty, and risk appetite. The framework involves identifying risks, analyzing them both qualitatively and quantitatively, planning responses, implementing responses, and monitoring risks. Risk management is aligned across levels and aims to balance threats and opportunities to achieve organizational objectives.
The presentation about Project Risk Management conducted by Mr. Mohamad Boukhari for the project management community in Lebanon during PMI Lebanon Chapter monthly lecture.
Construction Risk Summit "benefit and pits of Construction Risk Management"bfriday
This document discusses conducting risk management on major projects. It provides an overview of John Holland, an engineering and construction company, and explains why risk management is important for major projects. Some key benefits of risk management mentioned include focusing teams on objectives, protecting balance sheets, gaining alignment on critical risks, and understanding residual uncertainty. The document also outlines some pitfalls to avoid, such as not involving risk information in decision making. It emphasizes the importance of focusing on key risks and matching the appropriate risk tools to each project.
This document provides a summary of project risk management. It begins with introducing the importance of managing risk for project success. It then outlines various project risks from human factors, project design issues, and external dependencies. The document describes a six step overall risk management process including preliminary assessment, planning, identification, analysis, response planning, and monitoring. Each step is explained in one to two sentences. Examples of risk matrices and registers are also provided.
A Comprehensive Overview and Interpretation of Risk and Uncertainty in Projec...Dr. Mustafa Değerli
A Comprehensive Overview and
Interpretation of
Risk and Uncertainty
in Project Management Body of Knowledge, 7th Ed.
Dr. Mustafa Degerli
PhD, PMP, PMI
RMP, PSM, ITIL, CMMI Associate, Lead Auditor
Agenda
•
Risk and Uncertainty
•
Risk as a Project Management Principle (Optimize Risk
•
Uncertainty as a Project Performance Domain
•
Tailoring Details
•
Models, Methods, and Artifacts
This document summarizes the risk management plan for an organization. It outlines 7 key risks including lack of new business in Africa and South Africa, overdue debtors in SIAE, cash flow constraints on the SAPS Tetra project, budget targets for 2014, IT risks, and B-BBEE transformation. For each risk, it describes mitigation actions and timing for addressing the risks, most of which are ongoing. It also provides the organization's B-BBEE scorecards for 2008-2012, targets for 2013-2015, and preferential procurement and transformation strategy action plans with status updates.
Digital businesses are difficult to launch and run even without the challenge of security. And yet, digital business strategies are also being used by hackers to systematically go after lucrative targets. Following up on our release of the 2015 NTT Group Global Threat Intelligence Report, this executive summary highlights key findings from the report that affect today’s digital businesses.
Documentation on PMP Risk Management Plan & Template.
If you like a downloaded version, add me to your network on Linkedin
www.linkedin.com/in/alliegentry
and in the invite, please let me know you would like a word copy of this document.
Allie Gentry
PivotLogix
This document discusses project risk management. It defines risk as having possible outcomes that are understood, while uncertainty involves possible outcomes that are not understood. The key aspects of project risk management are risk identification, evaluation, response planning, monitoring and control. Project risk management aims to make projects more predictable and improve their chances of success through better planning and investment decisions.
The risk plan outlines defines how risk management will be conducted for the project. It ensures that the degree, type and visibility of risk management are appropriate for the risks and importance of the project. The risk plan outlines a full list of potential risks for the project, templates and documents for risk management, methods for assessing the probability and impact of risks, prioritization of risks, preventative and mitigative actions for risks, and how risk management will be conducted throughout project stages.
Building business continuity through risk management
Presented by Kimberley Hart
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
Applying risk factors in the strategic selection of portfolio projects
Presented by John MacGregor
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
This document provides information about an upcoming conference on managing risk in construction contracts and projects taking place on January 26-27, 2016 in Toronto. The conference will provide strategies for drafting precise contracts, allocating risk, ensuring appropriate insurance is in place, and more. Speakers will include lawyers, contractors, engineers, project managers and other professionals. Attendees can also choose to attend an additional half-day master class on drafting construction contracts or managing environmental and safety risks on projects. The event aims to help participants effectively plan for and manage risk in their construction contracts and projects.
The document provides instructions for completing a project risk register. The risk register tracks key information about identified project risks such as the risk number, date identified, risk description, category, potential impact, risk owner, probability of occurrence, impact of risk, risk level, response, status, date response invoked, and whether a contingency plan was developed. The document also provides examples of project risks in different phases to help identify risks and memory joggers to aid in the risk identification process.
This document provides an overview of risk and issue management best practices. It discusses key concepts like the differences between risks and issues, how to prioritize them, and the overall process of identifying, analyzing, taking action, monitoring, reviewing, and reporting on risks and issues over the lifecycle of a project. The goal is to familiarize workshop participants with a standardized terminology and approach to proactively manage risks and issues in order to minimize potential impacts on a project.
Project risk management: Techniques and strategiesDebashishDas49
Risk identification techniques and mitigation techniques in the present dynamic scenario of the industry is described here. Also, the recent research area and probable topics that one could choose as a Ph.D. topic are described briefly.
This document discusses construction risk management. It defines risk and identifies types of risks in construction projects, including financial, design, construction-related, and political/environment risks. It then describes construction risk management as identifying and mitigating risks through a six-step process: risk management planning, risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control. Managing risks can reduce costs, losses, and damage to reputation from delays, quality issues, and cost overruns. The benefits of effective risk management include effective resource use, continuous improvement, and reassuring stakeholders.
Where do risks (threats and opportunities) arise from?
Presented by Lynn Stalker
Monday 10th October 2016
APM North West branch and Risk SIG conference
Alderley Park, Macclesfield
Risk management involves identifying potential risks to a project, analyzing their likelihood and impact, and developing plans to mitigate negative risks. Some key risks include staff turnover, requirements changes, and underestimating the time or resources needed. It is important to identify risks early, communicate about them, assign ownership, prioritize risks, and regularly monitor risks and mitigation strategies. Effective risk management can help promote the success of software projects by focusing resources and preventing potential problems.
The document discusses project risk management. It defines risk as a function of uniqueness and experience. There are two types of risks: business risks relating to gains/losses, and pure risks which only have downsides. The risk management process involves identifying risks early and throughout the project. Risks can then be avoided, mitigated, transferred to a third party, or accepted. Common risk responses include changing plans to avoid risks, reducing probability/impact of risks, assigning risks to third parties, and simply accepting small risks. Preparing for risks requires analyzing and prioritizing them based on likelihood and impact.
The document discusses risk management for projects. It defines risk as any uncertain event or condition that could positively or negatively impact a project's objectives. It notes that through risk management, a project manager can identify potential problems, take actions to prevent or minimize risks, and stay in control of the project. The document outlines the key steps in risk management as identifying risks, analyzing them, planning responses, implementing responses, and monitoring risks. It also discusses different ways to handle risks, such as avoiding, mitigating, transferring, accepting, or escalating risks.
This document discusses risk management and analysis. It defines risk management as identifying, analyzing, and responding to risks. Risk analysis helps identify potential problems that could undermine projects or initiatives. The key steps of risk analysis include identifying threats, estimating the likelihood and impact of each threat, and developing risk mitigation strategies. Quantitative techniques like decision trees and expected monetary value analysis can also be used. Ongoing risk monitoring and control is important to evaluate risks and ensure responses remain effective.
The document discusses the risk management framework which includes enterprise, portfolio, program, and project level risk management. It defines key terms like risk, uncertainty, and risk appetite. The framework involves identifying risks, analyzing them both qualitatively and quantitatively, planning responses, implementing responses, and monitoring risks. Risk management is aligned across levels and aims to balance threats and opportunities to achieve organizational objectives.
The presentation about Project Risk Management conducted by Mr. Mohamad Boukhari for the project management community in Lebanon during PMI Lebanon Chapter monthly lecture.
Construction Risk Summit "benefit and pits of Construction Risk Management"bfriday
This document discusses conducting risk management on major projects. It provides an overview of John Holland, an engineering and construction company, and explains why risk management is important for major projects. Some key benefits of risk management mentioned include focusing teams on objectives, protecting balance sheets, gaining alignment on critical risks, and understanding residual uncertainty. The document also outlines some pitfalls to avoid, such as not involving risk information in decision making. It emphasizes the importance of focusing on key risks and matching the appropriate risk tools to each project.
This document provides a summary of project risk management. It begins with introducing the importance of managing risk for project success. It then outlines various project risks from human factors, project design issues, and external dependencies. The document describes a six step overall risk management process including preliminary assessment, planning, identification, analysis, response planning, and monitoring. Each step is explained in one to two sentences. Examples of risk matrices and registers are also provided.
A Comprehensive Overview and Interpretation of Risk and Uncertainty in Projec...Dr. Mustafa Değerli
A Comprehensive Overview and
Interpretation of
Risk and Uncertainty
in Project Management Body of Knowledge, 7th Ed.
Dr. Mustafa Degerli
PhD, PMP, PMI
RMP, PSM, ITIL, CMMI Associate, Lead Auditor
Agenda
•
Risk and Uncertainty
•
Risk as a Project Management Principle (Optimize Risk
•
Uncertainty as a Project Performance Domain
•
Tailoring Details
•
Models, Methods, and Artifacts
This document summarizes the risk management plan for an organization. It outlines 7 key risks including lack of new business in Africa and South Africa, overdue debtors in SIAE, cash flow constraints on the SAPS Tetra project, budget targets for 2014, IT risks, and B-BBEE transformation. For each risk, it describes mitigation actions and timing for addressing the risks, most of which are ongoing. It also provides the organization's B-BBEE scorecards for 2008-2012, targets for 2013-2015, and preferential procurement and transformation strategy action plans with status updates.
Digital businesses are difficult to launch and run even without the challenge of security. And yet, digital business strategies are also being used by hackers to systematically go after lucrative targets. Following up on our release of the 2015 NTT Group Global Threat Intelligence Report, this executive summary highlights key findings from the report that affect today’s digital businesses.
The document discusses risk assessment and mitigation strategies for a bank. It outlines the process of assessing risk, which includes identifying prevalent risks, assessing their impact and frequency, developing controls, and reassessing exposures. It also evaluates options for mitigating risk, such as periodic assessments, maintaining a risk register, and reviewing contingency plans. Key considerations for selecting mitigation actions include ensuring effectiveness, cost efficiency, alignment with business operations, and consistency with regulatory requirements.
DMSMS Standardization 2011 - Integrated Methods of Counterfeit Risk MitigationRory King
Rory King and Greg Jaknunas provide a briefing on expertise, tools, and best practices to enable anti-counterfeit, supply chain risk mitigation and problem-resolution capabilities within Parts Management. It will discuss methods integrating standards management, predictive and reactive obsolescence forecasting, and counterfeit databases and reporting mechanisms. It will illustrate how GIDEP and ERAI alerts, reports, and analysis can be integrated within traditional BOM obsolescence management processes. It will also illustrate how widely-deployed tools such as IHS Haystack, Standards Expert, and BOM Manager can enable and support efforts such as SAE AS5553 Counterfeit Electronic Parts; Avoidance, Detection, Mitigation, and Disposition. Attendees will learn methods to manage EOL cases, qualify and approve suppliers and parts, as well as methods to minimize cost and avoid risks from counterfeiting and obsolescence.
The document discusses strategic management across a product's lifecycle, which is typically divided into five phases: development, introduction, growth, maturity, and decline. Each phase presents different strategic goals and considerations for factors like competition, pricing, distribution, promotion, and product development. The strategies aim to successfully introduce a product, increase its market share, maintain quality and demand in later phases, and maximize profits before withdrawing the product.
This document outlines a theology discussion group that will take place on May 7th. It includes the following details:
- Four discussion topics on Christianity history, systematic theology, biblical theology, and practical theology throughout May.
- The purpose is to increase knowledge of theology, communicate and learn from others, and foster fellowship.
- Attendees will be split into groups to discuss different eras of church history, with each person presenting on their chosen topic for about 10 minutes.
- Suggestions are provided for the presentation format, including the topic, main developments, references, and a reflection.
- Future workshop topics are also listed, such as eBook development, customer service, and publisher
The document discusses reforms to North Carolina's mental health, developmental disability, and substance abuse services system. It notes the goals of reform are to control finances, increase local governance and accountability, and reduce reliance on institutions. Key components of reform include counties managing services through Local Management Entities (LMEs), developing evidence-based practices, and downsizing hospitals. However, challenges remain around access to services, funding inequities, workforce issues, and measuring quality. Opportunities exist to improve the system through consensus-building, quality monitoring, and advocacy.
This document outlines details of an event called the Panthers Purrsuit, including participating teams and sponsors, pre-event promotion through blogs and videos, media coverage on websites and TV, participant engagement on social media, in-event YouTube clips, and post-event recap blogs. Metrics on social media engagement are provided, such as the number of tweets, Facebook photos and reach, YouTube views, and sponsors trending on Twitter during the event date in Charlotte.
This document summarizes a presentation about minimally invasive image-guided cardiovascular therapies. It discusses various catheter-based imaging technologies like intravascular ultrasound (IVUS) and optical coherence tomography (OCT) that can provide images of the inside of blood vessels and heart structures. These emerging technologies are able to characterize plaque and identify vulnerable plaques through methods like spectroscopy and tissue characterization. The document also discusses potential applications of these imaging technologies in areas like valvular interventions through guidance and visualization of procedures. In general, it promotes the benefits of minimally invasive image-guided approaches for cardiovascular applications.
The document discusses the increasing diagnostic challenges in automotive workshops due to growing vehicle complexity from factors such as rising electronic content, new technologies, and evolving regulations. Vehicle complexity is rising as the number of electronic control units increases each year to accommodate new features, regulations, and customer demands. Diagnosing problems is challenging due to continually changing vehicle behaviors and electrical architectures with multiple bus networks and communication systems. New wireless technologies and emissions/safety regulations also contribute to higher complexity, placing greater demands on repair technicians to diagnose issues quickly and accurately.
Don’t miss your first chance to hear the new
direction in TAV policy!
• Create opportunities for your organization to take part in DoD logistics automation and transformation efforts
• Hear updates from all major services, agencies, and the OSD on current enterprise initiatives
• Discover new technology and trends in AIT and how these will impact the DoD and the defense industry
The document discusses the future of web development with single page applications (SPAs) and web components. It covers current SPA frameworks like AngularJS, EmberJS, and React. It also discusses new technologies like ES6, fetch API, and decorators. Finally, it outlines a workshop to build an app with Aurelia using Flickr data and Polymer components.
TextNoMore is an app that aims to reduce distracted driving by rewarding users for not using their phones while driving. It displays information about missing children to help find them. The app also partners with schools to help raise funds - for every business that sponsors a school through the app, $30 goes to the school each month. This allows schools to raise unlimited funds while helping to save lives from distracted driving.
The IML Connector is a portable audio device available globally since September 2010. It has a high quality microphone and built-in speaker for presentations and debates. The QWERTY keyboard allows for easy text input and it can be used for simultaneous interpretation with multiple audio channels. It also enhances voting solutions through its color screen and smartcard tracking of attendance and responses.
The document instructs the reader to take a 4 question test about their preferences and associations. It asks them to rank 5 animals in order of preference, describe 5 objects with one word each, associate important people in their life with different colors, and write their favorite number and day of the week. It claims answering honestly will reveal insights about the reader's true self, priorities, and personality traits.
El documento presenta una introducción al comercio electrónico y cómo las empresas pueden vender en línea. Se menciona que las empresas deben analizar cada punto de venta digital como su sitio web, correo electrónico y redes sociales, y elegir la opción que mejor se adapte a su negocio. También se enfatiza la importancia de estudiar el mercado, investigar a la competencia y enviar el material de la presentación a los asistentes por correo electrónico.
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net
The document discusses project risk management processes including:
1) Planning risk management to define the approach and ensure sufficient resources.
2) Identifying risks through various techniques like brainstorming and checklists.
3) Analyzing risks qualitatively by assessing probability and impact, and quantitatively using tools like decision trees.
4) Developing responses like mitigation plans, contingency plans and fallbacks to enhance opportunities and reduce threats.
5) Monitoring and controlling risks, residual risks, and the effectiveness of the risk management process.
Project Controls Expo 18th Nov 2014 - "Practical Applications of a Risk Manag...Project Controls Expo
As construction projects continue to increase in size and complexity, so does the inherent risk that organizations must take on to win work. As a result of globalization in the capital construction industry, organizations are faced with the challenge of executing projects under tighter budgets and highly compressed schedules. This has led to thinner profit margins and the increased need for competitive cost positioning. This presentation seeks to demonstrate the value of a robust risk management framework at all levels of an organization. This includes:
• Risk management for identifying corporate strategy and market opportunities
• Using risk assessment to establish corporate risk reserves
• Refining the estimate process at the bid stage by using risk analysis to eliminate the “compounding contingency” effect
• Analyzing and quantifying ongoing project risk exposure
• How to involve your client in the risk management process
The document discusses risk management processes for projects. It defines risk management as proactively identifying risks and developing plans to minimize their impact. The key steps are: 1) identifying risks, 2) assessing their probability and impact, 3) developing responses like mitigating, avoiding, transferring or retaining risks, and 4) controlling risk response through monitoring and contingency plans. Contingency plans are alternative plans to reduce the impact of foreseeable risks. Contingency funding and time buffers are also important risk management tactics.
This document discusses managing enterprise architecture (EA) projects and programs. It covers key topics such as the differences between project and program management, understanding stakeholders and their interests, common challenges for EA including lack of buy-in and skills, managing risk through processes like identifying, analyzing and responding to risks, EA deliverables, and aligning the TOGAF Architecture Development Method (ADM) with project management methodologies. The overall goal is to help understand risk and manage failures in EA programs and projects.
The document provides information on project risk management processes and concepts. It discusses the seven processes of project risk management according to PMBOK, including plan risk management, identify risks, perform qualitative risk analysis, perform quantitative risk analysis, plan risk responses, implement risk responses, and monitor risks. It also covers key concepts such as different types of risks, risk thresholds, and considering stakeholder risk tolerance levels. Additionally, it provides an overview of uncertainty as a performance domain and describes what a tornado diagram is and how it can be used to determine the impact of various risks.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. It is important for improving project success. Some common sources of risk for IT projects include scope changes, inaccurate estimates, lack of resources, and technology risks. Risk management techniques include risk identification, quantification methods like expected monetary value analysis and simulation, developing risk response plans, and tracking risks over the project.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. Some common sources of risk for IT projects include unclear scope, poor estimates, lack of resources, and technology risks. Risk management techniques include risk identification, quantification methods like expected monetary value analysis and simulation, developing risk response plans, and tracking risks over the course of the project. Proper risk management can help improve the chances of project success.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. It is important for improving project success. Some common sources of risk for IT projects include scope changes, inaccurate estimates, lack of resources, and technology risks. Risk management techniques include risk identification, quantification methods like expected monetary value analysis and simulation, developing risk response plans, and tracking risks over the project.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. It is important for improving project success. Some common sources of risk for IT projects include scope changes, inaccurate estimates, lack of resources, and technology risks. Risk management techniques include risk identification, quantification methods like expected monetary value analysis and simulation, developing risk response plans, and tracking risks over the project.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. Some common sources of risk for IT projects include inadequate planning, poorly defined scope, and inaccurate estimates. Risk management techniques include risk identification, quantification methods like expected monetary value analysis, developing risk response plans, and tracking risks over the course of the project. Proper risk management can help improve project success rates.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. Some common sources of risk for IT projects include inadequate planning, poorly defined scope, and inaccurate estimates. Risk management techniques include risk identification, quantification methods like expected monetary value analysis, developing risk response plans, and tracking risks over the course of the project. Proper risk management can help improve project success rates.
Risk management is the process of identifying, assessing and controlling threats to an organization's capital and earnings. These risks stem from a variety of sources, including financial uncertainties, legal liabilities, technology issues, strategic management errors, accidents and natural disasters.
Project risk management involves identifying, analyzing, and responding to risks throughout a project's lifecycle to help meet project objectives. Some common sources of risk for IT projects include inadequate planning, poorly defined scope, and inaccurate estimates. Risk management techniques include risk identification, quantification methods like expected monetary value analysis, developing risk response plans, and tracking risks over the course of the project. Proper risk management can help improve project success rates.
Risk management is a process to minimize the risk of a project not achieving its objectives. It involves identifying risks, analyzing their likelihood and consequences, evaluating their importance, treating risks by reducing likelihood or impact, monitoring risks continuously, and communicating regularly about risks. The risk management process establishes the context of a project, identifies risks, assesses them through qualitative or quantitative analysis, evaluates their importance, treats risks through options like avoidance or transfer, and monitors and reports on risks throughout a project.
The document discusses risk management in software testing projects. It defines risk management and identifies key risks in testing like lack of tester training. It outlines the stages of risk management - risk assessment and risk control. Risk assessment involves identifying, analyzing and prioritizing risks. Risk control involves mitigating risks through actions, planning for significant risks, monitoring risks, and communicating risks. The project manager is responsible for leading risk management.
Public sector risk management faces particular challenges due to increased complexity, partnerships, and public involvement in strategic decision making. A successful enterprise risk management program would involve identifying risks through qualitative and quantitative assessment, monitoring risks, and considering actions like terminating, tolerating, treating, or transferring risks. Senior management buy-in is crucial for an effective risk management program.
Similar to Risk Mitigation Epics Purdue 10 Sept 2008 (20)
1. Project Risk Management Carrie Kendrick Mitigation of Risks to Project Schedule and Cost EPICS Skill Session Purdue University College of Engineering 10 September 2008
It is One of the main knowledge areas of project managementPurpose: Plan for and manage the likelihood and impact on objects of a risk to schedule or cost
It is One of the main knowledge areas of project managementPurpose: Plan for and manage the likelihood and impact on objects of a risk to schedule or cost
Known:What would you do to reduce the PROBABILITY (likelihood) of losing his knowledge? - Give them a retention incentive - Make sure they are happy doing their jobWhat would you do to reduce the IMPACT (severity) of losing his knowledge? - Capture the knowledge in another form: cross-train workers, record the worker doing his job, have others observe him working and ask questions to understand why he does certain activities, have others try to replicate….this is commonly referred to as Hidden Factory Capture, but is a tool used outside of factories also for any kind of process where knowledge lives with the person doing that job.Anyone think of a risk on your current project? We can talk through it together…Known-UnknownOdds are good that you’ll get in a car accident. About 7 million per year! Anyone been in one recently?You don’t really know when, though…or who will be in it. So we buy insurance to reduce the financial impact if/when it does happen.UnknownSometimes have a management reserve – don’t count on it. Or build project schedule slack.