SlideShare a Scribd company logo
Risk Factor
Identified, Quantified, and Build-In impacts in Schedule Risk Analysis
Commonpractice:ScheduleRiskAnalysis process
• All identified risks that have impact on schedule are basically assigned
into activities on schedule.
• Some risks may assigned to multiple activities, hence an activity can be
influenced by multiple risks. However, many users are not aware that
prior assigning process, risks need to be categorized either Risk Event or
Risk Factor.
• Ignoring Risk Factor is “risk” to schedule risk analysis process, that will
lead to distorted results.
• This paper intended to briefly shown how much the variance could
derived from the simulation output “with” and “without” Risk Factor
AND also hoping for feedback on how to improve the process.
• Primavera Risk Analysis is a tool used for this presentation and it is
assumed that the reader(s) has understanding and experiences of using
it.
RiskFactor VS RiskEvent
• Risk Event
Is an incident/occasion that may or may not happen, that affects through
impacts on particular activities in the project.
• Risk Factor
Is an unknown element that affects the project. It is expressed as % and
resulting from it, reduces or increases the activities it affects.
Examples
Risk Events Risk Factors
Unavailability of Resources Weather
Nobody is willing to do casting, hence
casting works shall delayed.
All Offshore installation activities will
prolonged 50% longer than planned
duration.
Land Subside Productivity Labor
Zone A1/D1 has weak ground, piling work
may get effected in case soil strengthening
not properly done.
Fabrication time will takes 20% longer than
initial planned.
Transportation Strike Vendor Performance
Delivery time of materials may extended by
2 weeks, due to strike attack planned by
workers union
LD Exposure will goes up by 50% if work
progressing continue on a flat line.
“Without”RiskFactor
Allrisksaretakenasriskevents.
SimulationonProjectA(dummy).
Constructionof 25Storey CeylonServiceApartment
All risks (Risk Factor + Risk Events) are assigned to activities in quantitative tab
49%
49%
49%
50%
50%
50%
53%
54%
54%
55%ELAEIS-RSRC LDD-A6680:012 - Landslide and Subside
ELAEIS-RSRC LDD-A6690:012 - Landslide and Subside
ELAEIS-RSRC LDD-A6680 - Water Reticulation
ELAEIS-RSRC LDD-A6690 - Road Work & Lighting
ELAEIS-RSRC LDD-A7530 - Formworkon Columns
ELAEIS-RSRC LDD-A6930 - Formworkon Columns
ELAEIS-RSRC LDD-A2370 - Formwork Pile Cap & Install Reinforcing
ELAEIS-RSRC LDD-A7230 - Formworkon Columns
ELAEIS-RSRC LDD-A2330 - Formwork on Column
ELAEIS-RSRC LDD-A2090 - Formwork Pile Cap & Install Reinforcing
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity: Entire Plan - All tasks
Water Reticulation and Road Work
& Lighting tasks have highest duration
sensitivity. Noted these two activities
(Infrastructure) are planned at the last
quarter of project duration.
2%
-2%
3%
5%
-7%
9%
16%
16%
23%
25%006 - Availability of Resources
012 - Landslide and Subside
005 - Late drawing & Instructions
009 - Suitability of Materials
001 - Changes in Work
002 - Subsurfaces Geological
013 - Soil availability of Land Fill
001 - Changes in Work
001 - Changes in Work
014 - Insolvency of Subcontractor
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity
Risk affects multiple activities. In
This presentation, Risk Availability
of resources and Landslide &
Subside gives effect most.
P80 stands at 17 April 2015
“With”RiskFactor
Impactplanmodelisacombinationofriskevents
andriskfactors.
SimulationonProjectA(dummy).
Constructionof 25Storey CeylonServiceApartment
DetermineRiskFactor
Take out Risk Events (Risk Factor )from
Quantitative tab. Edit Risk Factor
dialogue box.
Set 3 point estimates in %
ranges and % likelihood.
In this example, we
set zero likelihood
of correlation
Assigning Risk Factor to task. In this example, we apply risk to entire section of the
WBS (Summaries). Indirectly it reflects correlation due to common cause.
Important Notes to understand. Sources from Primavera Risk Analysis Help.
04/04/2015 17:00 27/06/2015 01:00 18/09/2015 09:00
Distribution (start of interval)
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
Hits
0% 18/02/2015 16:00
5% 17/03/2015 17:00
10% 02/04/2015 09:00
15% 13/04/2015 09:00
20% 20/04/2015 09:00
25% 27/04/2015 09:00
30% 01/05/2015 11:00
35% 08/05/2015 09:00
40% 13/05/2015 17:00
45% 18/05/2015 17:00
50% 25/05/2015 09:00
55% 01/06/2015 09:00
60% 05/06/2015 14:00
65% 11/06/2015 14:00
70% 18/06/2015 14:00
75% 24/06/2015 15:00
80% 01/07/2015 16:00
85% 13/07/2015 09:00
90% 29/07/2015 14:00
95% 24/08/2015 09:00
100% 30/11/2015 10:00
CumulativeFrequency
Elaeis Condominium (Pre-mitigated)
EntirePlan: FinishDate
P80 now stands at 1 July 2015
72%
72%
72%
72%
72%
72%
73%
73%
73%
74%ELAEIS-RSRC LDD-A7080 - Reinforcement for Beam/Slab
ELAEIS-RSRC LDD-A7040 - Reinforcement works on Column
ELAEIS-RSRC LDD-A7190 - Formwork for Beam/Slab
ELAEIS-RSRC LDD-A7100 - Reinforcement works on Column
ELAEIS-RSRC LDD-A7010 - Formwork for Beam/Slab
ELAEIS-RSRC LDD-A7110 - Formwork on Column
ELAEIS-RSRC LDD-A7000 - Concrete for Column
ELAEIS-RSRC LDD-A7020 - Reinforcement for Beam/Slab
ELAEIS-RSRC LDD-A7050 - Formwork for Column
ELAEIS-RSRC LDD-A7030 - Concrete for Beam/Slab
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity: Entire Plan - All tasks
2%
-2%
3%
5%
-7%
9%
16%
16%
23%
25%006- Availabilityof Resources
012- LandslideandSubside
005- Latedrawing& Instructions
009- Suitabilityof Materials
001- Changes inWork
002- Subsurfaces Geological
013- Soilavailabilityof LandFill
001- Changes inWork
001- Changes inWork
014- Insolvencyof Subcontractor
4-Storey Elaeis Condominium for Sime Darby Development(Pre-mitigated)
Duration Sensitivity
Not much changes as observed
on the criticality rank
More activities are sensitive to the risk
Impact. Noted at this time,
that they are those activities (Structure)
that planned at earlier stage of construction
Risk: Availability of Resources confirmed “driving” project schedule.
Pull out from Risk Factor menu – Show Tornado
Conclusions.
• P80 for both models have different suggestion dates
“With” Risk Factor = 17 April 2015
“Without” Risk Factor = 1 July 2015
Variance = 75 days
• The output of Risk Factor model had indicated that, Major Construction
Works are critical to manage properly with Risk: Availability Resources
and Risk: Productivity Labor tagged along with, rather than having
Infrastructure works as crucial.
• Incorporating Risk Factor would enabling The User to bring true reality
of the project environment into the model AND give some excellent
reflection of risk exposure.
ThankYou

More Related Content

Viewers also liked

Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risksGerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Vanbreda Risk & Benefits
 
Panda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion GuidePanda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion Guide
Panda Security
 
Panda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malwarePanda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malware
Panda Security
 
CS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & FraudCS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & Fraud
Paige Rasid
 
risk management presentation
risk management presentationrisk management presentation
risk management presentationJonathan Gubler
 
MHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary ProgramMHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary Program
Margolis Healy
 
Effects of Domestic Violence in Children
Effects of Domestic Violence in ChildrenEffects of Domestic Violence in Children
Effects of Domestic Violence in Children
therapistfinder com
 
Domestic violence
Domestic violence Domestic violence
Domestic violence
albireno
 
Tips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnappingTips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnapping
Usman Farooq
 
IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708
Global Risk Forum GRFDavos
 
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...robine
 
Read 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesRead 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesGabeochoa
 
Negative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsNegative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsJames Coyne
 
Society for Risk Analysis On Transnational Risk & Terrorism
Society for Risk Analysis  On Transnational Risk & TerrorismSociety for Risk Analysis  On Transnational Risk & Terrorism
Society for Risk Analysis On Transnational Risk & Terrorism
John Marke
 
The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010 The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010
Enterprise Security Risk Management
 
Girls, Gangs, & Sex
Girls, Gangs, & SexGirls, Gangs, & Sex
Girls, Gangs, & Sexrisat528
 
Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...
James Coyne
 
e-Extortion Trends and Defense
e-Extortion Trends and Defensee-Extortion Trends and Defense
e-Extortion Trends and Defense
Erik Iker
 
Hotels restaurants security
Hotels restaurants securityHotels restaurants security
Hotels restaurants security
zaffar abbasi
 

Viewers also liked (20)

Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risksGerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
 
Plep inteligencia humana
Plep inteligencia humanaPlep inteligencia humana
Plep inteligencia humana
 
Panda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion GuidePanda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion Guide
 
Panda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malwarePanda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malware
 
CS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & FraudCS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & Fraud
 
risk management presentation
risk management presentationrisk management presentation
risk management presentation
 
MHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary ProgramMHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary Program
 
Effects of Domestic Violence in Children
Effects of Domestic Violence in ChildrenEffects of Domestic Violence in Children
Effects of Domestic Violence in Children
 
Domestic violence
Domestic violence Domestic violence
Domestic violence
 
Tips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnappingTips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnapping
 
IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708
 
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
 
Read 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesRead 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industries
 
Negative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsNegative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehps
 
Society for Risk Analysis On Transnational Risk & Terrorism
Society for Risk Analysis  On Transnational Risk & TerrorismSociety for Risk Analysis  On Transnational Risk & Terrorism
Society for Risk Analysis On Transnational Risk & Terrorism
 
The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010 The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010
 
Girls, Gangs, & Sex
Girls, Gangs, & SexGirls, Gangs, & Sex
Girls, Gangs, & Sex
 
Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...
 
e-Extortion Trends and Defense
e-Extortion Trends and Defensee-Extortion Trends and Defense
e-Extortion Trends and Defense
 
Hotels restaurants security
Hotels restaurants securityHotels restaurants security
Hotels restaurants security
 

Similar to Risk factor

APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
nkarthik21
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
nkarthik21
 
Management Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation SlidesManagement Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation Slides
SlideTeam
 
Network Diagram
Network DiagramNetwork Diagram
Concept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation SlidesConcept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation Slides
SlideTeam
 
Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides
SlideTeam
 
Turag Presentation
Turag PresentationTurag Presentation
Turag PresentationSourav Das
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_prices
Charles Santos
 
When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?
ISA Interchange
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
ignitetribes
 
Detailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation SlidesDetailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation Slides
SlideTeam
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
Project Controls Expo
 
Security Operational Scorecard EX2
Security Operational Scorecard EX2Security Operational Scorecard EX2
Security Operational Scorecard EX2Alice E. Nordwall
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
Mohammad IFTAKHAR
 
Indicative budget for SHP development
Indicative budget for SHP developmentIndicative budget for SHP development
Indicative budget for SHP development
Nikhil Jaipurkar
 
Sdcch drop rate
Sdcch drop rateSdcch drop rate
Sdcch drop rate
Terra Sacrifice
 
Global Cyber Security Or Critical Risk Dashboard
Global Cyber Security Or Critical Risk DashboardGlobal Cyber Security Or Critical Risk Dashboard
Global Cyber Security Or Critical Risk Dashboard
SlideTeam
 

Similar to Risk factor (20)

SIP PPT
SIP PPTSIP PPT
SIP PPT
 
JTP - EV Presentation
JTP - EV PresentationJTP - EV Presentation
JTP - EV Presentation
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
Management Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation SlidesManagement Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation Slides
 
Network Diagram
Network DiagramNetwork Diagram
Network Diagram
 
Concept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation SlidesConcept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation Slides
 
Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides
 
Turag Presentation
Turag PresentationTurag Presentation
Turag Presentation
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_prices
 
When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Detailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation SlidesDetailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation Slides
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Security Operational Scorecard EX2
Security Operational Scorecard EX2Security Operational Scorecard EX2
Security Operational Scorecard EX2
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
Indicative budget for SHP development
Indicative budget for SHP developmentIndicative budget for SHP development
Indicative budget for SHP development
 
Sdcch drop rate
Sdcch drop rateSdcch drop rate
Sdcch drop rate
 
Global Cyber Security Or Critical Risk Dashboard
Global Cyber Security Or Critical Risk DashboardGlobal Cyber Security Or Critical Risk Dashboard
Global Cyber Security Or Critical Risk Dashboard
 

Recently uploaded

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 

Recently uploaded (20)

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 

Risk factor

  • 1. Risk Factor Identified, Quantified, and Build-In impacts in Schedule Risk Analysis
  • 2. Commonpractice:ScheduleRiskAnalysis process • All identified risks that have impact on schedule are basically assigned into activities on schedule. • Some risks may assigned to multiple activities, hence an activity can be influenced by multiple risks. However, many users are not aware that prior assigning process, risks need to be categorized either Risk Event or Risk Factor. • Ignoring Risk Factor is “risk” to schedule risk analysis process, that will lead to distorted results. • This paper intended to briefly shown how much the variance could derived from the simulation output “with” and “without” Risk Factor AND also hoping for feedback on how to improve the process. • Primavera Risk Analysis is a tool used for this presentation and it is assumed that the reader(s) has understanding and experiences of using it.
  • 3. RiskFactor VS RiskEvent • Risk Event Is an incident/occasion that may or may not happen, that affects through impacts on particular activities in the project. • Risk Factor Is an unknown element that affects the project. It is expressed as % and resulting from it, reduces or increases the activities it affects.
  • 4. Examples Risk Events Risk Factors Unavailability of Resources Weather Nobody is willing to do casting, hence casting works shall delayed. All Offshore installation activities will prolonged 50% longer than planned duration. Land Subside Productivity Labor Zone A1/D1 has weak ground, piling work may get effected in case soil strengthening not properly done. Fabrication time will takes 20% longer than initial planned. Transportation Strike Vendor Performance Delivery time of materials may extended by 2 weeks, due to strike attack planned by workers union LD Exposure will goes up by 50% if work progressing continue on a flat line.
  • 6. All risks (Risk Factor + Risk Events) are assigned to activities in quantitative tab
  • 7. 49% 49% 49% 50% 50% 50% 53% 54% 54% 55%ELAEIS-RSRC LDD-A6680:012 - Landslide and Subside ELAEIS-RSRC LDD-A6690:012 - Landslide and Subside ELAEIS-RSRC LDD-A6680 - Water Reticulation ELAEIS-RSRC LDD-A6690 - Road Work & Lighting ELAEIS-RSRC LDD-A7530 - Formworkon Columns ELAEIS-RSRC LDD-A6930 - Formworkon Columns ELAEIS-RSRC LDD-A2370 - Formwork Pile Cap & Install Reinforcing ELAEIS-RSRC LDD-A7230 - Formworkon Columns ELAEIS-RSRC LDD-A2330 - Formwork on Column ELAEIS-RSRC LDD-A2090 - Formwork Pile Cap & Install Reinforcing Elaeis Condominium (Pre-mitigated) Duration Sensitivity: Entire Plan - All tasks Water Reticulation and Road Work & Lighting tasks have highest duration sensitivity. Noted these two activities (Infrastructure) are planned at the last quarter of project duration. 2% -2% 3% 5% -7% 9% 16% 16% 23% 25%006 - Availability of Resources 012 - Landslide and Subside 005 - Late drawing & Instructions 009 - Suitability of Materials 001 - Changes in Work 002 - Subsurfaces Geological 013 - Soil availability of Land Fill 001 - Changes in Work 001 - Changes in Work 014 - Insolvency of Subcontractor Elaeis Condominium (Pre-mitigated) Duration Sensitivity Risk affects multiple activities. In This presentation, Risk Availability of resources and Landslide & Subside gives effect most.
  • 8. P80 stands at 17 April 2015
  • 10. DetermineRiskFactor Take out Risk Events (Risk Factor )from Quantitative tab. Edit Risk Factor dialogue box. Set 3 point estimates in % ranges and % likelihood. In this example, we set zero likelihood of correlation
  • 11. Assigning Risk Factor to task. In this example, we apply risk to entire section of the WBS (Summaries). Indirectly it reflects correlation due to common cause.
  • 12. Important Notes to understand. Sources from Primavera Risk Analysis Help.
  • 13. 04/04/2015 17:00 27/06/2015 01:00 18/09/2015 09:00 Distribution (start of interval) 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 Hits 0% 18/02/2015 16:00 5% 17/03/2015 17:00 10% 02/04/2015 09:00 15% 13/04/2015 09:00 20% 20/04/2015 09:00 25% 27/04/2015 09:00 30% 01/05/2015 11:00 35% 08/05/2015 09:00 40% 13/05/2015 17:00 45% 18/05/2015 17:00 50% 25/05/2015 09:00 55% 01/06/2015 09:00 60% 05/06/2015 14:00 65% 11/06/2015 14:00 70% 18/06/2015 14:00 75% 24/06/2015 15:00 80% 01/07/2015 16:00 85% 13/07/2015 09:00 90% 29/07/2015 14:00 95% 24/08/2015 09:00 100% 30/11/2015 10:00 CumulativeFrequency Elaeis Condominium (Pre-mitigated) EntirePlan: FinishDate P80 now stands at 1 July 2015
  • 14. 72% 72% 72% 72% 72% 72% 73% 73% 73% 74%ELAEIS-RSRC LDD-A7080 - Reinforcement for Beam/Slab ELAEIS-RSRC LDD-A7040 - Reinforcement works on Column ELAEIS-RSRC LDD-A7190 - Formwork for Beam/Slab ELAEIS-RSRC LDD-A7100 - Reinforcement works on Column ELAEIS-RSRC LDD-A7010 - Formwork for Beam/Slab ELAEIS-RSRC LDD-A7110 - Formwork on Column ELAEIS-RSRC LDD-A7000 - Concrete for Column ELAEIS-RSRC LDD-A7020 - Reinforcement for Beam/Slab ELAEIS-RSRC LDD-A7050 - Formwork for Column ELAEIS-RSRC LDD-A7030 - Concrete for Beam/Slab Elaeis Condominium (Pre-mitigated) Duration Sensitivity: Entire Plan - All tasks 2% -2% 3% 5% -7% 9% 16% 16% 23% 25%006- Availabilityof Resources 012- LandslideandSubside 005- Latedrawing& Instructions 009- Suitabilityof Materials 001- Changes inWork 002- Subsurfaces Geological 013- Soilavailabilityof LandFill 001- Changes inWork 001- Changes inWork 014- Insolvencyof Subcontractor 4-Storey Elaeis Condominium for Sime Darby Development(Pre-mitigated) Duration Sensitivity Not much changes as observed on the criticality rank More activities are sensitive to the risk Impact. Noted at this time, that they are those activities (Structure) that planned at earlier stage of construction
  • 15. Risk: Availability of Resources confirmed “driving” project schedule. Pull out from Risk Factor menu – Show Tornado
  • 16. Conclusions. • P80 for both models have different suggestion dates “With” Risk Factor = 17 April 2015 “Without” Risk Factor = 1 July 2015 Variance = 75 days • The output of Risk Factor model had indicated that, Major Construction Works are critical to manage properly with Risk: Availability Resources and Risk: Productivity Labor tagged along with, rather than having Infrastructure works as crucial. • Incorporating Risk Factor would enabling The User to bring true reality of the project environment into the model AND give some excellent reflection of risk exposure.