SoberIT
Software Business and Engineering Institute
Requirements
Change Management
SoberIT
Software Business and Engineering Institute
Agenda
• Introduction
• Requirements Change Management Process
• Traceability
• Summary
SoberIT
Software Business and Engineering Institute
Introduction (1/3)
requirements
definition
specification &
design &
coding &
testing
acceptance
testing
requirements management
Requirements management is the process of managing changes to a
system’s requirements [Kot98], and it is an important part of
requirements engineering.
SoberIT
Software Business and Engineering Institute
Introduction (2/3)
• It is often the case that more than 50% of a system’s
requirements will be modified before it is put into service [Kot98].
• New requirements emerge and existing change due to
• errors
• increased understanding
• change in external circumstances.
SoberIT
Software Business and Engineering Institute
Introduction (3/3)
Changes to the requirements should be
documented and controlled formally.
Change management process ensures that
• changes are made systematically
•similar information is collected for each proposed change
•overall analysis is made about the costs, benefits and
timing
• the requirements document is updated.
SoberIT
Software Business and Engineering Institute
Requirements Change Management
Process (1/5)
requirements
change management
process
• updated user requirements document
• change history
recording analysing deciding implementing
• approved user requirements document
• change proposal
SoberIT
Software Business and Engineering Institute
Requirements Change Management
Process (2/5)
Recording a change proposal:
• Stakeholders submit proposals for requirements changes using a
pre-defined form.
SoberIT
Software Business and Engineering Institute
Requirements Change Management
Process (3/5)
Analysing a change request:
• The proposed change is analysed to see
• if it is valid. Sometimes stakeholders misunderstand the
requirements and suggest unnecessary changes.
• how many requirements and system components are affected
• how much it would cost, in both time and money, to make
the change
• what the benefits of the change are.
SoberIT
Software Business and Engineering Institute
Requirements Change Management
Process (4/5)
Deciding on a change request:
• Change requests are considered formally by a group or a person
who decide whether or not the change should be accepted.
SoberIT
Software Business and Engineering Institute
Requirements Change Management
Process (5/5)
Implementing a change:
• Updating the requirements document.
• Informing all the necessary people.
SoberIT
Software Business and Engineering Institute
Traceability
• Requirements cannot be managed effectively without
requirements traceability [Kot98].
• Traceability types [Som97]
• requirements - sources
• requirements - rationale
• requirements - requirements
• requirements - architecture
• requirements - test cases
SoberIT
Software Business and Engineering Institute
Summary (1/2)
User
requirements
definition
User requirements management
Design, coding and
system testing
Acceptance
testing
Requirements Engineering
Useful and Successful Products
SoberIT
Software Business and Engineering Institute
Summary (2/2)
Systematic requirements change management ensures that
product development produces useful and succesful
systems.
SoberIT
Software Business and Engineering Institute
References
• [Kot98] G. Kotonya and I. Sommerville, Requirements Engineering -
Processes and Techniques, John Wiley & Sons, New York, 1998.
• [Som97] I. Sommerville and P. Sawyer, Requirements Engineering -
A Good Practice Guide, John Wiley & Sons, New York, 1997.

Requirement change management

  • 1.
    SoberIT Software Business andEngineering Institute Requirements Change Management
  • 2.
    SoberIT Software Business andEngineering Institute Agenda • Introduction • Requirements Change Management Process • Traceability • Summary
  • 3.
    SoberIT Software Business andEngineering Institute Introduction (1/3) requirements definition specification & design & coding & testing acceptance testing requirements management Requirements management is the process of managing changes to a system’s requirements [Kot98], and it is an important part of requirements engineering.
  • 4.
    SoberIT Software Business andEngineering Institute Introduction (2/3) • It is often the case that more than 50% of a system’s requirements will be modified before it is put into service [Kot98]. • New requirements emerge and existing change due to • errors • increased understanding • change in external circumstances.
  • 5.
    SoberIT Software Business andEngineering Institute Introduction (3/3) Changes to the requirements should be documented and controlled formally. Change management process ensures that • changes are made systematically •similar information is collected for each proposed change •overall analysis is made about the costs, benefits and timing • the requirements document is updated.
  • 6.
    SoberIT Software Business andEngineering Institute Requirements Change Management Process (1/5) requirements change management process • updated user requirements document • change history recording analysing deciding implementing • approved user requirements document • change proposal
  • 7.
    SoberIT Software Business andEngineering Institute Requirements Change Management Process (2/5) Recording a change proposal: • Stakeholders submit proposals for requirements changes using a pre-defined form.
  • 8.
    SoberIT Software Business andEngineering Institute Requirements Change Management Process (3/5) Analysing a change request: • The proposed change is analysed to see • if it is valid. Sometimes stakeholders misunderstand the requirements and suggest unnecessary changes. • how many requirements and system components are affected • how much it would cost, in both time and money, to make the change • what the benefits of the change are.
  • 9.
    SoberIT Software Business andEngineering Institute Requirements Change Management Process (4/5) Deciding on a change request: • Change requests are considered formally by a group or a person who decide whether or not the change should be accepted.
  • 10.
    SoberIT Software Business andEngineering Institute Requirements Change Management Process (5/5) Implementing a change: • Updating the requirements document. • Informing all the necessary people.
  • 11.
    SoberIT Software Business andEngineering Institute Traceability • Requirements cannot be managed effectively without requirements traceability [Kot98]. • Traceability types [Som97] • requirements - sources • requirements - rationale • requirements - requirements • requirements - architecture • requirements - test cases
  • 12.
    SoberIT Software Business andEngineering Institute Summary (1/2) User requirements definition User requirements management Design, coding and system testing Acceptance testing Requirements Engineering Useful and Successful Products
  • 13.
    SoberIT Software Business andEngineering Institute Summary (2/2) Systematic requirements change management ensures that product development produces useful and succesful systems.
  • 14.
    SoberIT Software Business andEngineering Institute References • [Kot98] G. Kotonya and I. Sommerville, Requirements Engineering - Processes and Techniques, John Wiley & Sons, New York, 1998. • [Som97] I. Sommerville and P. Sawyer, Requirements Engineering - A Good Practice Guide, John Wiley & Sons, New York, 1997.