SlideShare a Scribd company logo
11/21/2018
1
Presented by: Albert YEU FCIArb MRICS MICE
20 November 2018
NEC Case Law Review
2
• Asbestos survey case - Northern Ireland Housing Executive v Healthy
Buildings (Ireland) Limited [2017] NIQB 43, [2018] BLR 157
• Ground treatment case - Arcadis UK Ltd v May and Baker Limited (t/a
Sanofi) [2013] EWHC 87 (TCC), [2013] BLR 210
• Pothole case – Atkins Limited v Secretary of State for Transport [2013] EWHC
139 (TCC). [2013] BLR 193
• Requirement of completion – RWE NPower Renewables Ltd v J N
Bentley Ltd [2014] EWCA Civ 150, [2014] CILL 3488
• Lagging work case – Arbitration Application No. 2 of 2016 [2017] CSOH 23,
2017 GWD 6-79
• Hydroelectric scheme – SSE Generation Limited v Hochtief Solutions AG
[2016] CSOH 177, 2017 GWD 3-39
Cases
3
Fact of the case (Asbestos Case)
Employer Northern Ireland Housing Executive (NIHE) (Claimant)
Consultant Healthy Building (Ireland) Limited (HB) (Respondent)
Contract type NEC3 Professional Services Contract
Work Asbestos surveying services
Background 1. Dec 2012 – NIHE awarded HB two asbestos surveying services
2. Jan 2013 – NIHE issued an instruction requiring more asbestos survey
3. Mar 2013 – HB notified NIHE under cl 61.3
4. Aug~Oct 2013 – NIHE requested HB to submit a quotation
5. Nov 2013 – NIHE rejected HB’s quotation
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited [2014] & [2017]
11/21/2018
2
4
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
Issue 1
“Dividing Date”
5
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
NEC3
Professional
Service
Contract
6
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
NEC3
Professional
Service
Contract
11/21/2018
3
7
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
Issue
Is the assessment of the effect of the compensation event
calculated by reference to the forecast Time Charge or the
actual cost incurred by the consultant?
Adjudication
HB argued NIHE should have instructed HB to submit
quotation on 10 January 2013. Therefore, the “quotation”
after this dividing date is in the form of a “forecast”
Apart from Cl 63.1, HB also relied on the Cl 63.6, Cl 63.7
and Cl 65.2.
8
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
“If one looks at 65.1 and 65.2 together it seems to me that what it means is
that if there is an employer’s assessment, and assessment is by the employer
not the consultant, which is based on a forecast from the consultant, the
employer cannot subsequently revise the assessment if it turns out that he
had accepted a forecast from the consultant which was unduly pessimistic,
even “wrong”; because it fact the consultant was put to less trouble and
expense than it had forecast. That is to achieve a meaning consistent with
business common sense…”
Court’s
view to
Cll 65.1
and 65.2
9
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
“evidence, from time sheet and other material, of what HB actually did in that
period, particularly with reference to the change in instructions, was not only
relevant evidence but clearly the best evidence to assist the court in
calculating the “compensation” to which HB was entitled.”
11/21/2018
4
10
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
Issue 2
“Cl 61.3 Time Bar”
11
Northern Ireland Housing Executive v Healthy
Buildings(Ireland)Limited
NEC3
Professional
Service
Contract
12
- Fact:
- Employer: May and Baker
- Contractor: Arcadis
- Contract type: NEC3 ECC Contract
- Work: Remediation work on site
- Background: 1) Some work was required beyond the
northern and southern boundaries of the site on land
Arcadis UK Ltd v May and Baker Limited [2013]
Fact of the case (Ground Treatment Case)
Employer May and Baker (Respondent)
Contractor Arcadis UK Limited (Claimant)
Contract type NEC3 ECC Contract
Work Earthwork and soil improvement works (including soil washing, chemical treatment and off-site
disposal methods)
Background 1. End of 2011 – Additional work beyond the Northern and Southern
boundaries
2. PM issued the Claimant PM’s Instructions
3. Re Northern Boundary – PM made his own assessment of
compensation event. Part payment made.
4. PM purported to withdraw PM instructions in respect of Northern and
Southern Boundary works
11/21/2018
5
13
Arcadis UK Ltd v May and Baker Limited [2013]
Adjudication 1
- Is the PM entitled to reverse his decision of compensation event for
Northern Boundary work?
- Adjudicator found in favor of claimant
“prior to the implementation of the compensation event, the PM may reverse
his decision that the matter constituted a compensation event. However, after
the compensation event has been implemented, as defined in the Contract, the
PM may neither reverse his decision that the matter is a compensation event,
nor reassess the effects of the compensation event.”
- Cl. 65.1, if PM made his own assessment and notified it, a compensation
event is said to be implemented
14
Atkins Limited v The Secretary of State for Transport [2013]
Fact of the case (Pothole Case)
Employer The Secretary of State for Transport (Respondent)
Contractor Atkins Limited (Claimant)
Contract type NEC3 ECC Contract – Lump Sum Contract
Work Maintenance of road surface, including repairing potholes, in a highway network
Background 1. Atkins was appointed as contractor to for maintain the roads, including
repairing potholes, in a highway network
2. Atkins claimed that the presence of potholes on the network was
significantly greater than it anticipated
3. Adjudicator held: Compensation Event
4. Arbitrator held: Not Compensation Event
5. Court held: Arbitrator was correct in his overall reasoning and
conclusion
15
Bespoke Cl 60.1(11) stated that a compensation event
arose where:
“The Provider encounters a defect in the physical condition of the Area Network which:
• is not revealed by the Network Information or by any other publicly available
information referred to in the Network Information;
• was not evident from a visual inspection or routine survey of the Area
Network at the Contract Date;
• an experienced contractor or consultant acting with reasonable diligence
could not reasonably have discovered prior to the Contract Date; and
• an experienced contractor or consultant would have judged at the Contract
Date to have such a small chance of being present that it would have been
unreasonable for him to have allowed for it.”
Atkins Limited v The Secretary of State for Transport [2013]
11/21/2018
6
16
Atkins Limited v The Secretary of State for Transport [2013]
Argument made by Claimant
(Contractor) - it is a Compensation
Event
Argument made by Respondent
(PM) – it is not a Compensation
Event
Not reasonable for contractor to
allow excessive volume of defect . It
is CE under Cl 60.1(11)
The clause refer to the type of
defect. The parties could have used
“defects” here which would assist the
Contractor, but here the contract use
of singular words “a defect”
Not reasonable for contractor to
allow the defect present at the
Contract date
The word “being present” means the
any time up to the end of the
Contract date
17
Arbitrator’s view
1. Cl. 60.1(11) only applies to defects which appear after the
contract date due to a cause which existed at the contract date
(being present) and which could not have been foreseen by the
contractor. (Latent/unknown defects)
2. A construction of cl.60.1(11) treating “defect” as meaning “volume
of defect” removes the point of a lump sum contract and makes
no commercial sense.
3. The correct test is “whether it would have been unreasonable to
have allowed for the defect at all” because there was “such a
small chance of [it] being present” which applies to type not
volume.
4. Practical problems with each defect in excess to be notified as a
CE.
Atkins Limited v The Secretary of State for Transport [2013]
18
Atkins Limited v The Secretary of State for Transport [2013]
NEC3 ECC
Contract
Clause
- In NEC3 ECC Contract Clause 60.1(12)
- the word “physical conditions” is used, and
- “only the difference between the physical conditions encountered
and those for…” is in the content of the contract clause
11/21/2018
7
19
RWE N Power Renewables Ltd v J N Bentley Ltd [2013]
Fact of the case (Requirement of Completion)
Employer RWE N Power Renewables Ltd (Claimant)
Contractor J N Bentley Ltd (Respondent)
Contract type NEC3 ECC Contract
Work Civil engineering works on a hydroelectrical plant in Scotland, including the construction of
3.5km penstock pipeline for channelling water to the powerhouse and a tailrace to return the
water. The hydro plant equipment was to be provided and installed by others
Background 1. Bentley carried out civil engineering works for RWE N Power
Renewables Ltd on a hydroelectrical plant in Scotland
2. A dispute arose over the date for completion of hydroelectrical plant
3. The crux of the dispute was whether J N Benley’s obligation was
governed by Option X5 of Part 1 of the Contract Data or clause 6.2 of
the Works Information
20
RWE N Power Renewables Ltd v J N Bentley Ltd [2013]
Option X5 in Part 1 of the Contract Data Clause 6.2 of Works Information
“Completion, including testing, of the intake,
penstock pipeline and tailrace and the power
house (including building services) to allow
Hydro Plant to be installed”
Completion, including testing, of the intakes,
penstock pipelines and tailrace, and the power
house (including building services) to be
completed to allow the hydro plant to be tested
and commissioned.
Completion of section 2 is defined as
completion of the following items of the works:
all of the intakes and associated facilities;
• All of the penstock pipelines and associated
facilities;
• All of the tailrace,
…
It requires completion of the penstock pipeline
only to the extent necessary to enable the
hydro plant to be installed
All the work described as forming part of
section 2 had to be finished before the section
as a whole could be regarded as complete. It
means the intake, penstock pipeline and
tailrace all had to have been completed and
tested
21
RWE N Power Renewables Ltd v J N Bentley Ltd [2013]
Adjudication
Decision: Inconsistency between two clauses, and part 1 of
the contract data took precedence.
Court of Appeal
Held: The contract shall be read as a whole and construed
so far as possible to avoid inconsistencies. The case finally
go to the Court of Appeal. The court held that despite
difference in detail between two clauses, one would expect
the two provisions to complement each other, because it is
a single obligation towards completion. The correct
approach is to resolve discrepancies relating to individual
obligations rather than forcing a choice between one clause
and another.
11/21/2018
8
22
Scottish Arbitration No. 2 of 2016
Fact of the case (Lagging Work Case)
Contract type NEC3 ECC, Option C Contract
Work Lagging work amongst others
Background 1. The Employer and main contractor entered into a construction
contract to provide some lagging work.
2. The main contractor sub-contracted the lagging work for a fixed
price which was accepted by the employer.
3. For some reasons, the subcontractor did not carry out all of the
work it had contracted to do and the main contractor carried out the
remainder of lagging work, resulting in a total price exceeding the
fixed price in the sub-contract
4. The dispute related to the lagging work was how the main
contractor should be paid for the lagging work
23
Scottish Arbitration No. 2 of 2016
Lagging work
Subcontracted to
Subcontractor
Remainder
carried out by
Main Contractor
itself
Fixed price in
sub-
contractor,
agreed by
Employer
How this
amount of
money should
be paid?
24
Scottish Arbitration No. 2 of 2016
- The employer argued that any amount in excess of the fixed price
of the subcontract shall not be recoverable as Defined Cost
- In arbitration, it was held it shall also be Defined Cost, and that
the contract was a target cost contract, and this risk of works
costing more than parties expected would have been shared
between the parties. The arbitrator ruled that the amount of
payment shall not be deducted
- The court upheld the arbitrator’s decision, saying the main
contractor were not bound to use sub-contractor or carry out the
lagging work themselves
11/21/2018
9
25
Scottish Arbitration No. 2 of 2016
Note:
- For work carried out by sub-contractor, the profit gained from sub
contractor will be from the subcontracted percentage, while the work
carried out by contractor, the profit gained will be the direct fee
percentage
- In NEC3 contract, the direct fee percentage and sub-contracted
percentage can be different, while in NEC4 contract, single fee
percentage was adopted
26
SSE Generation Limited v Hochitef Solutions AG &Another
Fact of the case (Hydroelectric Scheme)
Employer SSE Generation Limited (Claimant)
Contractor Hochitef Solutions AG & Another (Respondent)
Contract type NEC2 ECC Contract
Work Tunnel construction
Background 1. Glendoe hydroelectric scheme was constructed between 2006 and 2008 in Scotland.
It failed eight months after take over. A collapse occurred in the main tunnel.
2. The owner was anxious to recover its asset as soon as possible, but they failed to
reach agreement with contractor. In consequence, the owner instructed another
engineering firm to undertake the remedial work
3. The litigation arises out of the collapse. The owner seeks to recover about £130
million
4. It was found that the cause of the tunnel collapse was because there was not
enough support: poor rock conditions coincided with insufficient shortcrete and rockbolts
27
- The owner argued the cause of the tunnel collapse was because
the Contractor did not conform with the accepted design. There
was not enough support provided by the Contractor, as well as
insufficient shortcrete and rockbolts.
- The contractor relied on an Option Clause M, which states, “The
Contractor is not liable for Defects in the works due to his design
so far as he proves that he used reasonable skill and care to
ensure that it complied with the Works Information.”
- The court held that Option M placed an important brake on liability.
The contractor’s assumption of a more limited degree of risk would
have been reflected in the contract price and the level of its
insurance premiums
SSE Generation Limited v Hochitef Solutions AG &Another
11/21/2018
10
28
- The Contractor further argued that they had agreed the rock mass
classification by 4 types with Employer, by reference to ground
condition report. There was no concerns in relation to the tunnel
during its construction
- The court held the contractor did exercise reasonable skill and care
with respect to design and construction
- The Contractor counterclaimed they shall have made the profit if
they made the remedial work
- The court held that the contractor was in breach of Clause 82.1,
which states, “Until the Defects Certificate has been issued and
unless otherwise instructed by the Project Manager, the Contractor
promptly replaces loss of and repairs damages to the works, Plant
and Materials”
- Implication: Importance of clause of restricting design liability (i.e.
Option M in NEC2 or Option X15 in NEC3)
SSE Generation Limited v Hochitef Solutions AG &Another
29
30
Thank you!
Q & A

More Related Content

What's hot

NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
Browne Jacobson LLP
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
Rae Davies
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
Association for Project Management
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
Browne Jacobson LLP
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
Sarah Fox
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
Browne Jacobson LLP
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
Project Controls Expo
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
Lenson Mhango
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Project Controls Expo
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
Weero Koster
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
Iffat Al Gharbi
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
Essam Lotffy, PMP®, CCP®
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
Delhi Technological University
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 

What's hot (20)

NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 

Similar to Recent NEC3 Case Review and its Application

Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236
Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236
Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236Rolf Warburton
 
February 2019 newsletter
February 2019 newsletterFebruary 2019 newsletter
The need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projectsThe need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projects
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Ceca Caselaw
Ceca Caselaw Ceca Caselaw
Ceca Caselaw
watsonburton
 
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law UpdateAndrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
PAS_Team
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
chandrats
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
SeanGibbs12
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
Robert MacDonald
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
Lin Hui
 
Latent conditions and the experienced contractor test
Latent conditions and the experienced contractor testLatent conditions and the experienced contractor test
Latent conditions and the experienced contractor test
Resolution Institute
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
SeanGibbs12
 
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
Oupa Teke
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
Project Controls Expo
 
UK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletterUK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 

Similar to Recent NEC3 Case Review and its Application (20)

Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236
Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236
Golden Rock Products Inc. v. British Columbia 2014 BCSC 1355, 2014 BCSC 2236
 
February 2019 newsletter
February 2019 newsletterFebruary 2019 newsletter
February 2019 newsletter
 
The need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projectsThe need for dispute boards on international waste to energy projects
The need for dispute boards on international waste to energy projects
 
Ceca Caselaw
Ceca Caselaw Ceca Caselaw
Ceca Caselaw
 
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law UpdateAndrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law Conference
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Latent conditions and the experienced contractor test
Latent conditions and the experienced contractor testLatent conditions and the experienced contractor test
Latent conditions and the experienced contractor test
 
UK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 NewsletterUK Adjudicators January 2022 Newsletter
UK Adjudicators January 2022 Newsletter
 
Student ID Number 150578905
Student ID Number 150578905Student ID Number 150578905
Student ID Number 150578905
 
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
Castle Terminal Co. (Pty) Ltd & Oupa Teke responding to the Department of Pub...
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
Project Controls Expo 2012 - Litigation & Claims Facts & Figures By Paul Loma...
 
UK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletterUK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletter
 

More from Ir Albert YEU FCIArb MICE

CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
Ir Albert YEU FCIArb MICE
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
Ir Albert YEU FCIArb MICE
 
CIArb Promotional Talk
CIArb Promotional TalkCIArb Promotional Talk
CIArb Promotional Talk
Ir Albert YEU FCIArb MICE
 
Adjudication Talk at Chun Wo Group
Adjudication Talk at Chun Wo GroupAdjudication Talk at Chun Wo Group
Adjudication Talk at Chun Wo Group
Ir Albert YEU FCIArb MICE
 
Construction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services ContractConstruction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services Contract
Ir Albert YEU FCIArb MICE
 
ICE Mentoring and CPR Skills
ICE Mentoring and CPR SkillsICE Mentoring and CPR Skills
ICE Mentoring and CPR Skills
Ir Albert YEU FCIArb MICE
 
NEC3 compensation events
NEC3 compensation eventsNEC3 compensation events
NEC3 compensation events
Ir Albert YEU FCIArb MICE
 
NEC3 programme
NEC3 programmeNEC3 programme
Construction Adjudication
Construction AdjudicationConstruction Adjudication
Construction Adjudication
Ir Albert YEU FCIArb MICE
 

More from Ir Albert YEU FCIArb MICE (9)

CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
CIArb Promotional Talk
CIArb Promotional TalkCIArb Promotional Talk
CIArb Promotional Talk
 
Adjudication Talk at Chun Wo Group
Adjudication Talk at Chun Wo GroupAdjudication Talk at Chun Wo Group
Adjudication Talk at Chun Wo Group
 
Construction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services ContractConstruction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services Contract
 
ICE Mentoring and CPR Skills
ICE Mentoring and CPR SkillsICE Mentoring and CPR Skills
ICE Mentoring and CPR Skills
 
NEC3 compensation events
NEC3 compensation eventsNEC3 compensation events
NEC3 compensation events
 
NEC3 programme
NEC3 programmeNEC3 programme
NEC3 programme
 
Construction Adjudication
Construction AdjudicationConstruction Adjudication
Construction Adjudication
 

Recently uploaded

Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Syed Muhammad Humza Hussain
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
Wendy Couture
 
Roles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John CavittRoles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John Cavitt
johncavitthouston
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
PelayoGilbert
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
bhavenpr
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
Abdul-Hakim Shabazz
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
Finlaw Consultancy Pvt Ltd
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
o6ov5dqmf
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
9ib5wiwt
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
ssuser0576e4
 
new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.
niputusriwidiasih
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
ShivkumarIyer18
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
nehatalele22st
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
anvithaav
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
BridgeWest.eu
 

Recently uploaded (20)

Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
 
Roles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John CavittRoles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John Cavitt
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976Ease of Paying Tax Law Republic Act 11976
Ease of Paying Tax Law Republic Act 11976
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
 
new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.new victimology of indonesian law. Pptx.
new victimology of indonesian law. Pptx.
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
 

Recent NEC3 Case Review and its Application

  • 1. 11/21/2018 1 Presented by: Albert YEU FCIArb MRICS MICE 20 November 2018 NEC Case Law Review 2 • Asbestos survey case - Northern Ireland Housing Executive v Healthy Buildings (Ireland) Limited [2017] NIQB 43, [2018] BLR 157 • Ground treatment case - Arcadis UK Ltd v May and Baker Limited (t/a Sanofi) [2013] EWHC 87 (TCC), [2013] BLR 210 • Pothole case – Atkins Limited v Secretary of State for Transport [2013] EWHC 139 (TCC). [2013] BLR 193 • Requirement of completion – RWE NPower Renewables Ltd v J N Bentley Ltd [2014] EWCA Civ 150, [2014] CILL 3488 • Lagging work case – Arbitration Application No. 2 of 2016 [2017] CSOH 23, 2017 GWD 6-79 • Hydroelectric scheme – SSE Generation Limited v Hochtief Solutions AG [2016] CSOH 177, 2017 GWD 3-39 Cases 3 Fact of the case (Asbestos Case) Employer Northern Ireland Housing Executive (NIHE) (Claimant) Consultant Healthy Building (Ireland) Limited (HB) (Respondent) Contract type NEC3 Professional Services Contract Work Asbestos surveying services Background 1. Dec 2012 – NIHE awarded HB two asbestos surveying services 2. Jan 2013 – NIHE issued an instruction requiring more asbestos survey 3. Mar 2013 – HB notified NIHE under cl 61.3 4. Aug~Oct 2013 – NIHE requested HB to submit a quotation 5. Nov 2013 – NIHE rejected HB’s quotation Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited [2014] & [2017]
  • 2. 11/21/2018 2 4 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited Issue 1 “Dividing Date” 5 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited NEC3 Professional Service Contract 6 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited NEC3 Professional Service Contract
  • 3. 11/21/2018 3 7 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited Issue Is the assessment of the effect of the compensation event calculated by reference to the forecast Time Charge or the actual cost incurred by the consultant? Adjudication HB argued NIHE should have instructed HB to submit quotation on 10 January 2013. Therefore, the “quotation” after this dividing date is in the form of a “forecast” Apart from Cl 63.1, HB also relied on the Cl 63.6, Cl 63.7 and Cl 65.2. 8 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited “If one looks at 65.1 and 65.2 together it seems to me that what it means is that if there is an employer’s assessment, and assessment is by the employer not the consultant, which is based on a forecast from the consultant, the employer cannot subsequently revise the assessment if it turns out that he had accepted a forecast from the consultant which was unduly pessimistic, even “wrong”; because it fact the consultant was put to less trouble and expense than it had forecast. That is to achieve a meaning consistent with business common sense…” Court’s view to Cll 65.1 and 65.2 9 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited “evidence, from time sheet and other material, of what HB actually did in that period, particularly with reference to the change in instructions, was not only relevant evidence but clearly the best evidence to assist the court in calculating the “compensation” to which HB was entitled.”
  • 4. 11/21/2018 4 10 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited Issue 2 “Cl 61.3 Time Bar” 11 Northern Ireland Housing Executive v Healthy Buildings(Ireland)Limited NEC3 Professional Service Contract 12 - Fact: - Employer: May and Baker - Contractor: Arcadis - Contract type: NEC3 ECC Contract - Work: Remediation work on site - Background: 1) Some work was required beyond the northern and southern boundaries of the site on land Arcadis UK Ltd v May and Baker Limited [2013] Fact of the case (Ground Treatment Case) Employer May and Baker (Respondent) Contractor Arcadis UK Limited (Claimant) Contract type NEC3 ECC Contract Work Earthwork and soil improvement works (including soil washing, chemical treatment and off-site disposal methods) Background 1. End of 2011 – Additional work beyond the Northern and Southern boundaries 2. PM issued the Claimant PM’s Instructions 3. Re Northern Boundary – PM made his own assessment of compensation event. Part payment made. 4. PM purported to withdraw PM instructions in respect of Northern and Southern Boundary works
  • 5. 11/21/2018 5 13 Arcadis UK Ltd v May and Baker Limited [2013] Adjudication 1 - Is the PM entitled to reverse his decision of compensation event for Northern Boundary work? - Adjudicator found in favor of claimant “prior to the implementation of the compensation event, the PM may reverse his decision that the matter constituted a compensation event. However, after the compensation event has been implemented, as defined in the Contract, the PM may neither reverse his decision that the matter is a compensation event, nor reassess the effects of the compensation event.” - Cl. 65.1, if PM made his own assessment and notified it, a compensation event is said to be implemented 14 Atkins Limited v The Secretary of State for Transport [2013] Fact of the case (Pothole Case) Employer The Secretary of State for Transport (Respondent) Contractor Atkins Limited (Claimant) Contract type NEC3 ECC Contract – Lump Sum Contract Work Maintenance of road surface, including repairing potholes, in a highway network Background 1. Atkins was appointed as contractor to for maintain the roads, including repairing potholes, in a highway network 2. Atkins claimed that the presence of potholes on the network was significantly greater than it anticipated 3. Adjudicator held: Compensation Event 4. Arbitrator held: Not Compensation Event 5. Court held: Arbitrator was correct in his overall reasoning and conclusion 15 Bespoke Cl 60.1(11) stated that a compensation event arose where: “The Provider encounters a defect in the physical condition of the Area Network which: • is not revealed by the Network Information or by any other publicly available information referred to in the Network Information; • was not evident from a visual inspection or routine survey of the Area Network at the Contract Date; • an experienced contractor or consultant acting with reasonable diligence could not reasonably have discovered prior to the Contract Date; and • an experienced contractor or consultant would have judged at the Contract Date to have such a small chance of being present that it would have been unreasonable for him to have allowed for it.” Atkins Limited v The Secretary of State for Transport [2013]
  • 6. 11/21/2018 6 16 Atkins Limited v The Secretary of State for Transport [2013] Argument made by Claimant (Contractor) - it is a Compensation Event Argument made by Respondent (PM) – it is not a Compensation Event Not reasonable for contractor to allow excessive volume of defect . It is CE under Cl 60.1(11) The clause refer to the type of defect. The parties could have used “defects” here which would assist the Contractor, but here the contract use of singular words “a defect” Not reasonable for contractor to allow the defect present at the Contract date The word “being present” means the any time up to the end of the Contract date 17 Arbitrator’s view 1. Cl. 60.1(11) only applies to defects which appear after the contract date due to a cause which existed at the contract date (being present) and which could not have been foreseen by the contractor. (Latent/unknown defects) 2. A construction of cl.60.1(11) treating “defect” as meaning “volume of defect” removes the point of a lump sum contract and makes no commercial sense. 3. The correct test is “whether it would have been unreasonable to have allowed for the defect at all” because there was “such a small chance of [it] being present” which applies to type not volume. 4. Practical problems with each defect in excess to be notified as a CE. Atkins Limited v The Secretary of State for Transport [2013] 18 Atkins Limited v The Secretary of State for Transport [2013] NEC3 ECC Contract Clause - In NEC3 ECC Contract Clause 60.1(12) - the word “physical conditions” is used, and - “only the difference between the physical conditions encountered and those for…” is in the content of the contract clause
  • 7. 11/21/2018 7 19 RWE N Power Renewables Ltd v J N Bentley Ltd [2013] Fact of the case (Requirement of Completion) Employer RWE N Power Renewables Ltd (Claimant) Contractor J N Bentley Ltd (Respondent) Contract type NEC3 ECC Contract Work Civil engineering works on a hydroelectrical plant in Scotland, including the construction of 3.5km penstock pipeline for channelling water to the powerhouse and a tailrace to return the water. The hydro plant equipment was to be provided and installed by others Background 1. Bentley carried out civil engineering works for RWE N Power Renewables Ltd on a hydroelectrical plant in Scotland 2. A dispute arose over the date for completion of hydroelectrical plant 3. The crux of the dispute was whether J N Benley’s obligation was governed by Option X5 of Part 1 of the Contract Data or clause 6.2 of the Works Information 20 RWE N Power Renewables Ltd v J N Bentley Ltd [2013] Option X5 in Part 1 of the Contract Data Clause 6.2 of Works Information “Completion, including testing, of the intake, penstock pipeline and tailrace and the power house (including building services) to allow Hydro Plant to be installed” Completion, including testing, of the intakes, penstock pipelines and tailrace, and the power house (including building services) to be completed to allow the hydro plant to be tested and commissioned. Completion of section 2 is defined as completion of the following items of the works: all of the intakes and associated facilities; • All of the penstock pipelines and associated facilities; • All of the tailrace, … It requires completion of the penstock pipeline only to the extent necessary to enable the hydro plant to be installed All the work described as forming part of section 2 had to be finished before the section as a whole could be regarded as complete. It means the intake, penstock pipeline and tailrace all had to have been completed and tested 21 RWE N Power Renewables Ltd v J N Bentley Ltd [2013] Adjudication Decision: Inconsistency between two clauses, and part 1 of the contract data took precedence. Court of Appeal Held: The contract shall be read as a whole and construed so far as possible to avoid inconsistencies. The case finally go to the Court of Appeal. The court held that despite difference in detail between two clauses, one would expect the two provisions to complement each other, because it is a single obligation towards completion. The correct approach is to resolve discrepancies relating to individual obligations rather than forcing a choice between one clause and another.
  • 8. 11/21/2018 8 22 Scottish Arbitration No. 2 of 2016 Fact of the case (Lagging Work Case) Contract type NEC3 ECC, Option C Contract Work Lagging work amongst others Background 1. The Employer and main contractor entered into a construction contract to provide some lagging work. 2. The main contractor sub-contracted the lagging work for a fixed price which was accepted by the employer. 3. For some reasons, the subcontractor did not carry out all of the work it had contracted to do and the main contractor carried out the remainder of lagging work, resulting in a total price exceeding the fixed price in the sub-contract 4. The dispute related to the lagging work was how the main contractor should be paid for the lagging work 23 Scottish Arbitration No. 2 of 2016 Lagging work Subcontracted to Subcontractor Remainder carried out by Main Contractor itself Fixed price in sub- contractor, agreed by Employer How this amount of money should be paid? 24 Scottish Arbitration No. 2 of 2016 - The employer argued that any amount in excess of the fixed price of the subcontract shall not be recoverable as Defined Cost - In arbitration, it was held it shall also be Defined Cost, and that the contract was a target cost contract, and this risk of works costing more than parties expected would have been shared between the parties. The arbitrator ruled that the amount of payment shall not be deducted - The court upheld the arbitrator’s decision, saying the main contractor were not bound to use sub-contractor or carry out the lagging work themselves
  • 9. 11/21/2018 9 25 Scottish Arbitration No. 2 of 2016 Note: - For work carried out by sub-contractor, the profit gained from sub contractor will be from the subcontracted percentage, while the work carried out by contractor, the profit gained will be the direct fee percentage - In NEC3 contract, the direct fee percentage and sub-contracted percentage can be different, while in NEC4 contract, single fee percentage was adopted 26 SSE Generation Limited v Hochitef Solutions AG &Another Fact of the case (Hydroelectric Scheme) Employer SSE Generation Limited (Claimant) Contractor Hochitef Solutions AG & Another (Respondent) Contract type NEC2 ECC Contract Work Tunnel construction Background 1. Glendoe hydroelectric scheme was constructed between 2006 and 2008 in Scotland. It failed eight months after take over. A collapse occurred in the main tunnel. 2. The owner was anxious to recover its asset as soon as possible, but they failed to reach agreement with contractor. In consequence, the owner instructed another engineering firm to undertake the remedial work 3. The litigation arises out of the collapse. The owner seeks to recover about £130 million 4. It was found that the cause of the tunnel collapse was because there was not enough support: poor rock conditions coincided with insufficient shortcrete and rockbolts 27 - The owner argued the cause of the tunnel collapse was because the Contractor did not conform with the accepted design. There was not enough support provided by the Contractor, as well as insufficient shortcrete and rockbolts. - The contractor relied on an Option Clause M, which states, “The Contractor is not liable for Defects in the works due to his design so far as he proves that he used reasonable skill and care to ensure that it complied with the Works Information.” - The court held that Option M placed an important brake on liability. The contractor’s assumption of a more limited degree of risk would have been reflected in the contract price and the level of its insurance premiums SSE Generation Limited v Hochitef Solutions AG &Another
  • 10. 11/21/2018 10 28 - The Contractor further argued that they had agreed the rock mass classification by 4 types with Employer, by reference to ground condition report. There was no concerns in relation to the tunnel during its construction - The court held the contractor did exercise reasonable skill and care with respect to design and construction - The Contractor counterclaimed they shall have made the profit if they made the remedial work - The court held that the contractor was in breach of Clause 82.1, which states, “Until the Defects Certificate has been issued and unless otherwise instructed by the Project Manager, the Contractor promptly replaces loss of and repairs damages to the works, Plant and Materials” - Implication: Importance of clause of restricting design liability (i.e. Option M in NEC2 or Option X15 in NEC3) SSE Generation Limited v Hochitef Solutions AG &Another 29 30 Thank you! Q & A