SlideShare a Scribd company logo
ID Task
Mode
Task Name Duration Start Finish
1 Preliminary Design Phase 286 days Mon 2/3/14 Mon 3/9/15
8 Pre‐Construction ‐ Bid Pac A (Demo/Site/Modular Units 125 days Tue 3/10/15 Mon 8/31/15
9 Complete Construction Documents (Site, Demolition) 115 days Tue 3/10/15 Mon 8/17/15
10 Prepare and Bid Modular Units 30 days Tue 7/7/15 Mon 8/17/15
11 EDiS Completes Plan Check 5 days Tue 7/7/15 Mon 7/13/15
12 Architect Incorporates Plan Check Comments 30 days Tue 7/14/15 Mon 8/24/15
13 Architect submits final CDʹs to EDiS 5 days Tue 8/25/15 Mon 8/31/15
14 EDiS Bidding Phase ‐ Bid Pac A (Parking Dept. Bldg. & 
Demo City Hall)
40 days Tue 9/1/15 Mon 10/26/15
15 EDiS Prepares bidding documents 1 day Tue 9/1/15 Tue 9/1/15
16 EDiS Bids Bid Pac A 30 days Wed 9/2/15 Tue 10/13/15
17 EDiS Receives Bids for Bid Pac A 1 day Wed 10/14/15 Wed 10/14/15
18 EDiS Evaluates Bids and make recommendations 5 days Thu 10/15/15 Wed 10/21/15
19 EDiS Awards Contracts 3 days Thu 10/22/15 Mon 10/26/15
20 Construction ‐ Phase I / Bid Pac A (Parking Dept. Bldg. & 
Demo City Hall)
209 days Tue 8/4/15 Fri 5/20/16
21 Mobilize to the site 20 days Tue 8/4/15 Mon 8/31/15
22 Fab/Deliver/Install Modular units 44 days Tue 9/15/15 Fri 11/13/15
23 Move City Hall Employees to Modular units  5 days Mon 11/16/15 Fri 11/20/15
24 Move Parking Dept. Staff & Tech Services to Temp Location  5 days Mon 10/5/15 Fri 10/9/15
25 Close Convention Center 0 days Mon 11/9/15 Mon 11/9/15
26 Demo Paving, Parking Dept. Bldg. & Tech Services 10 days Mon 10/12/15 Fri 10/23/15
27 Construct New Parking Dept. Building  135 days Mon 10/26/15 Fri 4/29/16
28 Occupy Parking Dept. Building 15 days Mon 5/2/16 Fri 5/20/16
29 Relocate Electrical Service 20 days Mon 9/21/15 Fri 10/16/15
30 Demo City Hall Building  15 days Mon 11/23/15 Fri 12/11/15
31 Pre‐Construction ‐ Bid Pac B (Remaining Construction) 157 days Tue 3/10/15 Wed 10/14/15
32 Complete Construction Documents (CDʹs) 141 days Tue 3/10/15 Tue 9/22/15
33 EDiS Prepares 75% CD Estimate 10 days Mon 8/3/15 Fri 8/14/15
34 EDiS Provides VE recommendations 10 days Mon 8/17/15 Fri 8/28/15
35 EDiS completes Plan Check  10 days Wed 9/23/15 Tue 10/6/15
36 Architect incorporates Plan Check Comments 5 days Wed 10/7/15 Tue 10/13/15
37 Architect submits final CDʹs to EDiS 1 day Wed 10/14/15 Wed 10/14/15
38 EDiS Bidding Phase ‐ Bid Pac B (Remaining Construction) 48 days Thu 10/15/15 Mon 12/21/15
39 EDiS Prepares bidding documents 10 days Thu 10/15/15 Wed 10/28/15
40 EDiS Bids project Bid Pac B 31 days Thu 10/29/15 Thu 12/10/15
41 EDiS Receives bids 1 day Fri 12/11/15 Fri 12/11/15
42 EDiS evaluates bids and make recommendations 5 days Mon 12/14/15 Fri 12/18/15
43 EDiS Awards Contracts 1 day Mon 12/21/15 Mon 12/21/15
11/9
Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Rehoboth Beach Convention Center and City Hall Renovations & Additions
Master Schedule
July 8, 2015
Exhibit B
Page 1
Project: RBCH Master Schedule 7 
Date: Wed 7/8/15
ID Task
Mode
Task Name Duration Start Finish
44 Construction ‐ Phase II / Bid Pac B (Remaining Construction) 300 days Tue 12/22/15 Mon 2/13/17
45 Construct New City Hall Building  270 days Tue 12/22/15 Mon 1/2/17
46 Occupy New City Hall Building  20 days Tue 1/3/17 Mon 1/30/17
47 Open Convention Center 10 days Tue 1/31/17 Mon 2/13/17
48 Substantial Completion 0 days Mon 2/13/17 Mon 2/13/17 2/13
Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Rehoboth Beach Convention Center and City Hall Renovations & Additions
Master Schedule
July 8, 2015
Exhibit B
Page 2
Project: RBCH Master Schedule 7 
Date: Wed 7/8/15

More Related Content

Viewers also liked

City Council July 19, 2011 City Hall Construction Update
City Council July 19, 2011 City Hall Construction UpdateCity Council July 19, 2011 City Hall Construction Update
City Council July 19, 2011 City Hall Construction UpdateCity of San Angelo Texas
 
City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City of San Angelo Texas
 
Demolished City Halls of America
Demolished City Halls of AmericaDemolished City Halls of America
Demolished City Halls of America
DoctorSequoia
 
DS-16-135 City Hall Assessment
DS-16-135 City Hall AssessmentDS-16-135 City Hall Assessment
DS-16-135 City Hall Assessment
CityofKilleen
 
12 11-28 - perth city hall - outline development proposal low resolution...
12 11-28 - perth city hall - outline development proposal low resolution...12 11-28 - perth city hall - outline development proposal low resolution...
12 11-28 - perth city hall - outline development proposal low resolution...ChrisJCook
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Frank.
 
Magazine construction schedule
Magazine construction scheduleMagazine construction schedule
Magazine construction schedulepaulosalles55
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
Mereia Kali
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 

Viewers also liked (12)

City Council July 19, 2011 City Hall Construction Update
City Council July 19, 2011 City Hall Construction UpdateCity Council July 19, 2011 City Hall Construction Update
City Council July 19, 2011 City Hall Construction Update
 
City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012
 
Cityhall_Identity
Cityhall_IdentityCityhall_Identity
Cityhall_Identity
 
Chicago j douillard
Chicago j douillardChicago j douillard
Chicago j douillard
 
Demolished City Halls of America
Demolished City Halls of AmericaDemolished City Halls of America
Demolished City Halls of America
 
DS-16-135 City Hall Assessment
DS-16-135 City Hall AssessmentDS-16-135 City Hall Assessment
DS-16-135 City Hall Assessment
 
12 11-28 - perth city hall - outline development proposal low resolution...
12 11-28 - perth city hall - outline development proposal low resolution...12 11-28 - perth city hall - outline development proposal low resolution...
12 11-28 - perth city hall - outline development proposal low resolution...
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016
 
Magazine construction schedule
Magazine construction scheduleMagazine construction schedule
Magazine construction schedule
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Construction process
Construction processConstruction process
Construction process
 

Similar to Rehoboth Beach City Hall Construction Schedule

Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleGary Hayes
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Projec
ProjecProjec
Climate change video project plan
Climate change video project planClimate change video project plan
Climate change video project plan
velgot
 
program
programprogram
Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement SchedulingRonald Rhodes
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
PT. ANSI MEGA INSTRUMENINDO, Gunawan Widihardjo
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
maoanderton
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)
Lúcia Dénis
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
Dhawal Thakkar PMP
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart final
Dan Palmer
 
bb.pdf
bb.pdfbb.pdf
bb.pdf
LeTiencruise
 
network diagram.pdf
network diagram.pdfnetwork diagram.pdf
network diagram.pdf
jazzcashlimit
 
Shneha single page
Shneha single pageShneha single page
Shneha single pageshneha patel
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
wilcockiris
 
- Project.pdf
- Project.pdf- Project.pdf
- Project.pdf
Hemin Refiq
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortKevin C. McCormack, PMP
 
In the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docxIn the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docx
jaggernaoma
 

Similar to Rehoboth Beach City Hall Construction Schedule (20)

Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Projec
ProjecProjec
Projec
 
Climate change video project plan
Climate change video project planClimate change video project plan
Climate change video project plan
 
program
programprogram
program
 
Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement Scheduling
 
Standard Competition 12 Months
Standard Competition 12 MonthsStandard Competition 12 Months
Standard Competition 12 Months
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart final
 
bb.pdf
bb.pdfbb.pdf
bb.pdf
 
network diagram.pdf
network diagram.pdfnetwork diagram.pdf
network diagram.pdf
 
Shneha single page
Shneha single pageShneha single page
Shneha single page
 
WBS
WBSWBS
WBS
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
 
- Project.pdf
- Project.pdf- Project.pdf
- Project.pdf
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure Effort
 
In the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docxIn the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docx
 

More from rehobothbeachde

Draft rehoboth beach reopening plan 14 may 2020
Draft rehoboth beach reopening plan   14 may 2020Draft rehoboth beach reopening plan   14 may 2020
Draft rehoboth beach reopening plan 14 may 2020
rehobothbeachde
 
Final dd rehoboth_menu_10.11.19
Final dd rehoboth_menu_10.11.19Final dd rehoboth_menu_10.11.19
Final dd rehoboth_menu_10.11.19
rehobothbeachde
 
Rb joint meeting survey reveal presentation 10.28.2019 final
Rb joint meeting survey reveal presentation 10.28.2019 finalRb joint meeting survey reveal presentation 10.28.2019 final
Rb joint meeting survey reveal presentation 10.28.2019 final
rehobothbeachde
 
City of Rehoboth Beach Proposed Water and Wastewater Rate Structure
City of Rehoboth Beach Proposed Water and Wastewater Rate StructureCity of Rehoboth Beach Proposed Water and Wastewater Rate Structure
City of Rehoboth Beach Proposed Water and Wastewater Rate Structure
rehobothbeachde
 
Resilient community project overview for rehoboth commissioners
Resilient community project overview for rehoboth commissionersResilient community project overview for rehoboth commissioners
Resilient community project overview for rehoboth commissioners
rehobothbeachde
 
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
rehobothbeachde
 
Sussex sewer district presentation to city 11262018
Sussex sewer district  presentation to city   11262018Sussex sewer district  presentation to city   11262018
Sussex sewer district presentation to city 11262018
rehobothbeachde
 
Garden of the Navigators Enhancement 2018
Garden of the Navigators Enhancement 2018Garden of the Navigators Enhancement 2018
Garden of the Navigators Enhancement 2018
rehobothbeachde
 
Mayor's City Hall Complex Cost Review
Mayor's City Hall Complex Cost ReviewMayor's City Hall Complex Cost Review
Mayor's City Hall Complex Cost Review
rehobothbeachde
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Project
rehobothbeachde
 
Rehoboth Beach, DE - Funding the Proposed City Hall
Rehoboth Beach, DE - Funding the Proposed City Hall Rehoboth Beach, DE - Funding the Proposed City Hall
Rehoboth Beach, DE - Funding the Proposed City Hall
rehobothbeachde
 

More from rehobothbeachde (11)

Draft rehoboth beach reopening plan 14 may 2020
Draft rehoboth beach reopening plan   14 may 2020Draft rehoboth beach reopening plan   14 may 2020
Draft rehoboth beach reopening plan 14 may 2020
 
Final dd rehoboth_menu_10.11.19
Final dd rehoboth_menu_10.11.19Final dd rehoboth_menu_10.11.19
Final dd rehoboth_menu_10.11.19
 
Rb joint meeting survey reveal presentation 10.28.2019 final
Rb joint meeting survey reveal presentation 10.28.2019 finalRb joint meeting survey reveal presentation 10.28.2019 final
Rb joint meeting survey reveal presentation 10.28.2019 final
 
City of Rehoboth Beach Proposed Water and Wastewater Rate Structure
City of Rehoboth Beach Proposed Water and Wastewater Rate StructureCity of Rehoboth Beach Proposed Water and Wastewater Rate Structure
City of Rehoboth Beach Proposed Water and Wastewater Rate Structure
 
Resilient community project overview for rehoboth commissioners
Resilient community project overview for rehoboth commissionersResilient community project overview for rehoboth commissioners
Resilient community project overview for rehoboth commissioners
 
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
Rehoboth beach mobility center public private partnership (p3) - 04 feb 2019
 
Sussex sewer district presentation to city 11262018
Sussex sewer district  presentation to city   11262018Sussex sewer district  presentation to city   11262018
Sussex sewer district presentation to city 11262018
 
Garden of the Navigators Enhancement 2018
Garden of the Navigators Enhancement 2018Garden of the Navigators Enhancement 2018
Garden of the Navigators Enhancement 2018
 
Mayor's City Hall Complex Cost Review
Mayor's City Hall Complex Cost ReviewMayor's City Hall Complex Cost Review
Mayor's City Hall Complex Cost Review
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Project
 
Rehoboth Beach, DE - Funding the Proposed City Hall
Rehoboth Beach, DE - Funding the Proposed City Hall Rehoboth Beach, DE - Funding the Proposed City Hall
Rehoboth Beach, DE - Funding the Proposed City Hall
 

Recently uploaded

一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 

Recently uploaded (20)

一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 

Rehoboth Beach City Hall Construction Schedule

  • 1. ID Task Mode Task Name Duration Start Finish 1 Preliminary Design Phase 286 days Mon 2/3/14 Mon 3/9/15 8 Pre‐Construction ‐ Bid Pac A (Demo/Site/Modular Units 125 days Tue 3/10/15 Mon 8/31/15 9 Complete Construction Documents (Site, Demolition) 115 days Tue 3/10/15 Mon 8/17/15 10 Prepare and Bid Modular Units 30 days Tue 7/7/15 Mon 8/17/15 11 EDiS Completes Plan Check 5 days Tue 7/7/15 Mon 7/13/15 12 Architect Incorporates Plan Check Comments 30 days Tue 7/14/15 Mon 8/24/15 13 Architect submits final CDʹs to EDiS 5 days Tue 8/25/15 Mon 8/31/15 14 EDiS Bidding Phase ‐ Bid Pac A (Parking Dept. Bldg. &  Demo City Hall) 40 days Tue 9/1/15 Mon 10/26/15 15 EDiS Prepares bidding documents 1 day Tue 9/1/15 Tue 9/1/15 16 EDiS Bids Bid Pac A 30 days Wed 9/2/15 Tue 10/13/15 17 EDiS Receives Bids for Bid Pac A 1 day Wed 10/14/15 Wed 10/14/15 18 EDiS Evaluates Bids and make recommendations 5 days Thu 10/15/15 Wed 10/21/15 19 EDiS Awards Contracts 3 days Thu 10/22/15 Mon 10/26/15 20 Construction ‐ Phase I / Bid Pac A (Parking Dept. Bldg. &  Demo City Hall) 209 days Tue 8/4/15 Fri 5/20/16 21 Mobilize to the site 20 days Tue 8/4/15 Mon 8/31/15 22 Fab/Deliver/Install Modular units 44 days Tue 9/15/15 Fri 11/13/15 23 Move City Hall Employees to Modular units  5 days Mon 11/16/15 Fri 11/20/15 24 Move Parking Dept. Staff & Tech Services to Temp Location  5 days Mon 10/5/15 Fri 10/9/15 25 Close Convention Center 0 days Mon 11/9/15 Mon 11/9/15 26 Demo Paving, Parking Dept. Bldg. & Tech Services 10 days Mon 10/12/15 Fri 10/23/15 27 Construct New Parking Dept. Building  135 days Mon 10/26/15 Fri 4/29/16 28 Occupy Parking Dept. Building 15 days Mon 5/2/16 Fri 5/20/16 29 Relocate Electrical Service 20 days Mon 9/21/15 Fri 10/16/15 30 Demo City Hall Building  15 days Mon 11/23/15 Fri 12/11/15 31 Pre‐Construction ‐ Bid Pac B (Remaining Construction) 157 days Tue 3/10/15 Wed 10/14/15 32 Complete Construction Documents (CDʹs) 141 days Tue 3/10/15 Tue 9/22/15 33 EDiS Prepares 75% CD Estimate 10 days Mon 8/3/15 Fri 8/14/15 34 EDiS Provides VE recommendations 10 days Mon 8/17/15 Fri 8/28/15 35 EDiS completes Plan Check  10 days Wed 9/23/15 Tue 10/6/15 36 Architect incorporates Plan Check Comments 5 days Wed 10/7/15 Tue 10/13/15 37 Architect submits final CDʹs to EDiS 1 day Wed 10/14/15 Wed 10/14/15 38 EDiS Bidding Phase ‐ Bid Pac B (Remaining Construction) 48 days Thu 10/15/15 Mon 12/21/15 39 EDiS Prepares bidding documents 10 days Thu 10/15/15 Wed 10/28/15 40 EDiS Bids project Bid Pac B 31 days Thu 10/29/15 Thu 12/10/15 41 EDiS Receives bids 1 day Fri 12/11/15 Fri 12/11/15 42 EDiS evaluates bids and make recommendations 5 days Mon 12/14/15 Fri 12/18/15 43 EDiS Awards Contracts 1 day Mon 12/21/15 Mon 12/21/15 11/9 Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Rehoboth Beach Convention Center and City Hall Renovations & Additions Master Schedule July 8, 2015 Exhibit B Page 1 Project: RBCH Master Schedule 7  Date: Wed 7/8/15
  • 2. ID Task Mode Task Name Duration Start Finish 44 Construction ‐ Phase II / Bid Pac B (Remaining Construction) 300 days Tue 12/22/15 Mon 2/13/17 45 Construct New City Hall Building  270 days Tue 12/22/15 Mon 1/2/17 46 Occupy New City Hall Building  20 days Tue 1/3/17 Mon 1/30/17 47 Open Convention Center 10 days Tue 1/31/17 Mon 2/13/17 48 Substantial Completion 0 days Mon 2/13/17 Mon 2/13/17 2/13 Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Rehoboth Beach Convention Center and City Hall Renovations & Additions Master Schedule July 8, 2015 Exhibit B Page 2 Project: RBCH Master Schedule 7  Date: Wed 7/8/15