SlideShare a Scribd company logo
1 of 1
Download to read offline
INPUTS OUTPUTS
Financials NOTES CAPEX / Costs NOTES
General Capital (Direct) Cost ($/kWp) $825.00 OCC- Overnight Construction Cost Effective Tax Rate 0.00%
Analysis Period 25 Customs Duty (%) 0.00% Credit Basis - Federal $860.00
Inflation Rate 1.250000% % of Capital (Direct) Cost Custom Duty Applies 0.00% Credit Basis - State $860.00
Real Discount Rate 5.68% Capital (Direct) Cost ($) $825.00 OCC- Overnight Construction Cost Nominal Discount Rate 7.00%
Nominal Discount Rate 7.0000000% Contingency (%) 0.00% Included in EPC Price First Costs $129.00
Taxes, Depreciation, and Insurance Total Capital (Direct) Cost ($) $825.00 Adjusted Installed Costs $860.00
Tax 1 (federal) 0.00% Total Indirect Cost ($) $35.00 Project Development, etc. Decommissioning Cost Yr 25 $0.00
Tax 2 (local state) 0.00% % of Direct Costs Sales Tax Applies 0% Salvage Value Yr 25 $132.00
PropertyTax 0.00% Total Installed Cost ($) $860.00
Sales Tax 0.00% OPEX / O&M NPV(Nominal,Costflow) -559.26
Depreciation Method N/A (A) Fixed O&M ($/kWp-yr) $10.00 Mgt, Labor, Parts, Consum., Lease, Ins, Int-Hedge, X-Hedge, etc. NPV(Nominal,Output) 23,135.35
Apply Depreciation Yes/No No Fixed O&M Real Esc. 0.00% in addition to inflation NPV(Real,Output) 26,081.51
Insurance (Yr 1, Yr 2 onwads is inflation Adiusted) 0.00% included in OPEX Aux Pwr Cost - Fixed (Annual) O&M ($/yr) $0.00
Loan, DSCR, DSRA, MIRR (B) Auxiliary Power Cost - Fixed (Annual) O&M ($/kWp-yr) $0.00
Loan (Debt) Percentage of TotalAdj. Inst. Costs 85.00% Senior Debt 1 Aux Pwr Annual Esc. - Fixed (Annual) O&M Real Esc. 0.00% Equals PPA Esc.,in addition to inflation Real 2.6389
Term (Yr) 24 Senior Debt 1 Total(A)+(B) $/kWp-yr $10.00 Total Fixed O&M, inflation adjusted Nominal 2.9749
Rate 2.20% Senior Debt 1, fixed rate (or LIBOR+Margin, m-perm, etc.) Variable O&M ($/MWh) $0.00
Loan Amount $731.00 Variable O&M Real Esc. 0% in addition to inflation
Equity Amount $129.00 Fuel Cost ($/MMBtu) $0.00 Simple Payback 17.9278
Debt Payment ($/Yr) -$39.53 Fuel Cost Real Esc. 0% in addition to inflation Discounted Payback >25 years
WACC 2.92% Decommissioning Cost Year 25 (% of Capital Direct Cost) 0.00%
Positive Operating Cashflow Yes/No Yes Salvage Value Year 25 (% of Capital Direct Cost) 16.00% (Net, after Decomm Expenses)
Min. Required DSCR 1.2 @ P50, Account or Sculpting CER Carbon Price ($/tCO2) $10.00 NPV ($0.0000)
Min. Required IRR 7.00% Carbon Reduction (tCO2/MWh) 0.6000 Based on country power generation profile
MIRR Finance Rate 0.00% System Carbon Revenue from CER Year 1 ($) $12.54 with auxiliary consumption adjustment
MIRR Reinvestment Rate 0.00% System Carbon Revenue from CER Year 1 ($/kWh) $0.006000 with auxiliary consumption adjustment IRR 7.0000% OK
DSRA Cover (Months) 6 Apply System Carbon Reveue from CER in LCOE Calculation No MIRR 3.9410%
DSRA Amount ($) -$19.76 @ PCOD PV Power Plant Min. DSCR w/o DSRA 1.0326 LOW
DSRA Acc Type (Acceptable Credit Support) PG Cash/PG/LC/Loan/Cashflow System Size (kWp) 1.00 Avg. DSCR w/o DSRA 1.1757
DSRA Loan Amount NA Estimated Annual Yield Output P50 (kWh/kWp) 2100.00 based on PVSYST simulation, including Aux. Power Max. DSCR w/o DSRA 1.3195
DSRA Loan Term (Yr) NA Capacity Utilization Factor 23.97%
DSRA Loan Rate NA Annual Yield Degradation Year 1 (%/year) 0.00% Positive Cashflow Y/N Yes OK
DSRA Debt Payment ($/Yr) NA Annual Yield Degradation Year 2 to 25 (%/year) 0.60% CFADS
Utility PPA System Annual Availability (%) 99.50% excluding auxiliary consumption DSRA (6 Months) Credit Support C/PG/LC/CF PG
PPA Rate Yr-1 ($/kWh) $0.029749 Gross Annual Yield Output Year 1 (kWh) 2,089.50 without auxiliary consumption adjustment LLCR
PPA Annual Esc. (%) 0.00% Net Annual Yield Output Year 1 (kWh), with Aux. 2,089.50 with auxiliary consumption adjustment PLCR
Other Revenues System Carbon Reduction CER Year 1 (tCO2) 1.25 with auxiliary consumption adjustment MRA/MMRA
Other Revenue-A, Yr-1 ($/kWh) $0.000000 RE Certificates Heat Rate (MMBtus/MWh) 0 WC
Other Revenue-A, Annual Esc. (%) 0.00% Fixed Aux Power for Plant MEP, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr SBYWC
Other Revenue-B, Yr-1 ($/kWh) $0.000000 Summer Peak PPA Escalation / ToY r Shelter Heat Gain, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr EBL
Other Revenue-B, Annual Esc. (%) 0.00% Fixed Aux Power for HVAC for Inverters, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr SBYE
Other Revenue-C, Interest on Acconts Balance NA Applicable Accounts Fixed Total Aux Power Consumption (kWh/yr) 0.00 kWh/yr
Other Revenue-C, Interest (%) NA pq/pa Aux Power Cost Rate ($/kWh) PPA
Aux Power Cost Annual Esc. Rate (%) PPA Esc.
SOLAR PV PROJECT LCOE
ECONOMIC FEASIBILITY ANALYSIS - BASELINE CASE
Intermediate Values
Results LCOE (¢/kWh)
Results Payback (years) - excl debt & tax considerations, incl expenses
Results NPV (nominal dollars)
Results IRR & DSCR
‐129.00
‐49.53
‐49.65
‐49.78
‐49.91
‐50.04
‐50.17
‐50.30
‐50.44
‐50.57
‐50.71
‐50.85
‐50.99
‐51.14
‐51.28
‐51.43
‐51.58
‐51.73
‐51.88
‐52.04
‐52.19
‐52.35
‐52.51
‐52.67
‐52.84
118.53
‐150.00
‐100.00
‐50.00
0.00
50.00
100.00
150.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Dollars
Year
After Tax Cost Flow
62.16
61.79
61.42
61.05
60.68
60.32
59.96
59.60
59.24
58.88
58.53
58.18
57.83
57.48
57.14
56.80
56.45
56.12
55.78
55.44
55.11
54.78
54.45
54.13
53.80
48
50
52
54
56
58
60
62
64
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Dollars
Year
Operating Revenue 
10.00
10.13
10.25
10.38
10.51
10.64
10.77
10.91
11.04
11.18
11.32
11.46
11.61
11.75
11.90
12.05
12.20
12.35
12.51
12.66
12.82
12.98
13.14
13.31
‐118.53
‐140
‐120
‐100
‐80
‐60
‐40
‐20
0
20
40
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Dollars
Year
Operating Expenses
‐129.00
12.63
12.13
11.64
11.14
10.64
10.15
9.65
9.16
8.66
8.17
7.68
7.19
6.69
6.20
5.71
5.22
4.73
4.23
3.74
3.25
2.76
2.27
1.78
1.29
172.33
‐150.00
‐100.00
‐50.00
0.00
50.00
100.00
150.00
200.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Dollars
Year
After Tax Net Cash Flow
52.16
51.66
51.17
50.67
50.17
49.68
49.18
48.69
48.19
47.70
47.21
46.72
46.22
45.73
45.24
44.75
44.26
43.76
43.27
42.78
42.29
41.80
41.31
40.82
172.33
0
20
40
60
80
100
120
140
160
180
200
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Dollars
Year
Operating Income Cash Flow
‐860.00
‐807.84
‐756.18
‐705.01
‐654.34
‐604.17
‐554.49
‐505.31
‐456.62
‐408.42
‐360.72
‐313.51
‐266.80
‐220.58
‐174.85
‐129.61
‐84.86
‐40.60
3.16
46.43
89.22
131.51
173.31
214.62
255.44
‐1,000.00
‐800.00
‐600.00
‐400.00
‐200.00
0.00
200.00
400.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Dollars
Year
Cummulative Simple Payback Cash Flow
1.32
1.31
1.29
1.28
1.27
1.26
1.24
1.23
1.22
1.21
1.19
1.18
1.17
1.16
1.14
1.13
1.12
1.11
1.09
1.08
1.07
1.06
1.05
1.03
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DSCR
Year
Pre‐Tax DSCR
1.33
1.33
1.33
1.33
1.33
1.34
1.34
1.35
1.36
1.37
1.38
1.40
1.42
1.44
1.48
1.52
1.57
1.64
1.74
1.87
2.08
2.44
3.15
5.30
0.80
1.30
1.80
2.30
2.80
3.30
3.80
4.30
4.80
5.30
5.80
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PLCR
Year
PLCR
1.19
1.18
1.17
1.17
1.16
1.15
1.15
1.14
1.13
1.12
1.12
1.11
1.10
1.10
1.09
1.08
1.08
1.07
1.06
1.06
1.05
1.05
1.04
1.03
0.80
0.85
0.90
0.95
1.00
1.05
1.10
1.15
1.20
1.25
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
LLCR
Year
LLCR
1.22
1.21
1.20
1.20
1.19
1.19
1.18
1.17
1.17
1.16
1.16
1.16
1.15
1.15
1.15
1.15
1.15
1.15
1.15
1.16
1.18
1.22
1.30
1.54
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
LLCR
Year
LLCR w/ DSRA
1.35
1.35
1.36
1.36
1.36
1.37
1.38
1.38
1.39
1.41
1.42
1.44
1.47
1.50
1.53
1.58
1.64
1.72
1.83
1.98
2.22
2.61
3.41
5.81
0.80
1.80
2.80
3.80
4.80
5.80
6.80
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PLCR
Year
PLCR w/ DSRA
1.82
1.81
1.79
1.78
1.77
1.76
1.74
1.73
1.72
1.71
1.69
1.68
1.67
1.66
1.64
1.63
1.62
1.61
1.59
1.58
1.57
1.56
1.55
1.53
0.80
1.00
1.20
1.40
1.60
1.80
2.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DSCR
Year
Pre‐Tax DSCR w/ DSRA
16-LCOE-Template-Final-UAE-170228
25 Years Analysis- Baseline
Fadi Maalouf
Rev-16 28/02/2017 1 of 1

More Related Content

What's hot

Energy sector contribution to climate action
Energy sector contribution to climate actionEnergy sector contribution to climate action
Energy sector contribution to climate actionIEA-ETSAP
 
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...IEA-ETSAP
 
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...IEA-ETSAP
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemIEA-ETSAP
 
Industrial Sector in Jordan– Energy Use Current Status and Future Opportunities
Industrial Sector in Jordan– Energy Use Current Status and Future OpportunitiesIndustrial Sector in Jordan– Energy Use Current Status and Future Opportunities
Industrial Sector in Jordan– Energy Use Current Status and Future OpportunitiesSamer Zawaydeh
 
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...IEA-ETSAP
 
Samit Jain - Advit Foundation
Samit Jain - Advit FoundationSamit Jain - Advit Foundation
Samit Jain - Advit Foundationguest17a0764
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Bill St. Arnaud
 
Modelling of offshore wind
Modelling of offshore windModelling of offshore wind
Modelling of offshore windIEA-ETSAP
 
Capital Power March 2016 Investor Presentation
Capital Power March 2016 Investor PresentationCapital Power March 2016 Investor Presentation
Capital Power March 2016 Investor PresentationCapital Power
 
How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...IEA-ETSAP
 
Natural Gas Roundtable - GTI Presentation
Natural Gas Roundtable - GTI PresentationNatural Gas Roundtable - GTI Presentation
Natural Gas Roundtable - GTI PresentationWisconsin Clean Cities
 
Pushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenariosPushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenariosIEA-ETSAP
 
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy ManagementThe Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy ManagementVeritatis Advisors, Inc.
 
Life cycle costing and modeling
Life cycle costing and modelingLife cycle costing and modeling
Life cycle costing and modelingDr. Pradip Chanda
 
Hydrogen policy regulations and standards
Hydrogen policy regulations and standardsHydrogen policy regulations and standards
Hydrogen policy regulations and standardsDr. Pradip Chanda
 
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...IEA-ETSAP
 
Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021SustainableEnergyAut
 

What's hot (20)

Energy sector contribution to climate action
Energy sector contribution to climate actionEnergy sector contribution to climate action
Energy sector contribution to climate action
 
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
Hydrogen modelling in TIMES – a summary of the inputs, outputs, and best prac...
 
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
Introducing external costs for Local Atmospheric Pollution in TIAM-MACRO to s...
 
Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy system
 
Industrial Sector in Jordan– Energy Use Current Status and Future Opportunities
Industrial Sector in Jordan– Energy Use Current Status and Future OpportunitiesIndustrial Sector in Jordan– Energy Use Current Status and Future Opportunities
Industrial Sector in Jordan– Energy Use Current Status and Future Opportunities
 
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
Incorporating Homeowners’ Preferences for Heating Systems in the UK TIMES wit...
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Samit Jain - Advit Foundation
Samit Jain - Advit FoundationSamit Jain - Advit Foundation
Samit Jain - Advit Foundation
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4
 
Modelling of offshore wind
Modelling of offshore windModelling of offshore wind
Modelling of offshore wind
 
Capital Power March 2016 Investor Presentation
Capital Power March 2016 Investor PresentationCapital Power March 2016 Investor Presentation
Capital Power March 2016 Investor Presentation
 
How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...How do changes to future technology and fuel developments affect the optimal ...
How do changes to future technology and fuel developments affect the optimal ...
 
Natural Gas Roundtable - GTI Presentation
Natural Gas Roundtable - GTI PresentationNatural Gas Roundtable - GTI Presentation
Natural Gas Roundtable - GTI Presentation
 
Pushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenariosPushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenarios
 
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy ManagementThe Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
 
Life cycle costing and modeling
Life cycle costing and modelingLife cycle costing and modeling
Life cycle costing and modeling
 
Hydrogen policy regulations and standards
Hydrogen policy regulations and standardsHydrogen policy regulations and standards
Hydrogen policy regulations and standards
 
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
 
Seca seminar 2013 dn v - harald gundersen
Seca seminar 2013   dn v - harald gundersenSeca seminar 2013   dn v - harald gundersen
Seca seminar 2013 dn v - harald gundersen
 
Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021
 

Similar to PV Project Development Economic Feasibility Financial Model Baseline Case

Well_Economics_Forcast_Back_In__W_I
Well_Economics_Forcast_Back_In__W_IWell_Economics_Forcast_Back_In__W_I
Well_Economics_Forcast_Back_In__W_IAngelo Gasendo
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Projectrehobothbeachde
 
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides SlideTeam
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesSlideTeam
 
Financial Annual Report Common Size
Financial Annual Report Common SizeFinancial Annual Report Common Size
Financial Annual Report Common SizeTaylor Wiley
 
Plan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesPlan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesSlideTeam
 
Laundromat business plan
Laundromat business planLaundromat business plan
Laundromat business planmanishprotek
 
Real Estate and Investments: Property Investment Analysis on The Edge
Real Estate and Investments: Property Investment Analysis on The EdgeReal Estate and Investments: Property Investment Analysis on The Edge
Real Estate and Investments: Property Investment Analysis on The EdgeSoubreenWilliams
 
2Q14 Results Presentation
2Q14 Results Presentation2Q14 Results Presentation
2Q14 Results PresentationAluparRI
 
Apresentação sem discurso 2 t10 aes eletropaulo final_eng
Apresentação sem discurso 2 t10 aes eletropaulo final_engApresentação sem discurso 2 t10 aes eletropaulo final_eng
Apresentação sem discurso 2 t10 aes eletropaulo final_engAES Eletropaulo
 
Commercial Sample Proposal
Commercial Sample ProposalCommercial Sample Proposal
Commercial Sample ProposalCooper Bortz
 
Actual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesActual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesSlideTeam
 
Actual Cost Vs Budget PowerPoint Presentation Slides
Actual Cost Vs Budget PowerPoint Presentation Slides Actual Cost Vs Budget PowerPoint Presentation Slides
Actual Cost Vs Budget PowerPoint Presentation Slides SlideTeam
 
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019al karajo jr
 
FSAE-A Business Presentation - Redback Racing 2017
FSAE-A Business Presentation - Redback Racing 2017FSAE-A Business Presentation - Redback Racing 2017
FSAE-A Business Presentation - Redback Racing 2017Albert Chau
 

Similar to PV Project Development Economic Feasibility Financial Model Baseline Case (20)

proforma sample
proforma sampleproforma sample
proforma sample
 
Well_Economics_Forcast_Back_In__W_I
Well_Economics_Forcast_Back_In__W_IWell_Economics_Forcast_Back_In__W_I
Well_Economics_Forcast_Back_In__W_I
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Project
 
CNR_DCF(USD)
CNR_DCF(USD)CNR_DCF(USD)
CNR_DCF(USD)
 
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
 
Final Exam 2014 - Financial Model
Final Exam 2014 - Financial ModelFinal Exam 2014 - Financial Model
Final Exam 2014 - Financial Model
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
 
Financial Annual Report Common Size
Financial Annual Report Common SizeFinancial Annual Report Common Size
Financial Annual Report Common Size
 
Plan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesPlan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation Slides
 
Laundromat business plan
Laundromat business planLaundromat business plan
Laundromat business plan
 
02 Project Summary
02 Project Summary02 Project Summary
02 Project Summary
 
Real Estate and Investments: Property Investment Analysis on The Edge
Real Estate and Investments: Property Investment Analysis on The EdgeReal Estate and Investments: Property Investment Analysis on The Edge
Real Estate and Investments: Property Investment Analysis on The Edge
 
2Q14 Results Presentation
2Q14 Results Presentation2Q14 Results Presentation
2Q14 Results Presentation
 
Apresentação sem discurso 2 t10 aes eletropaulo final_eng
Apresentação sem discurso 2 t10 aes eletropaulo final_engApresentação sem discurso 2 t10 aes eletropaulo final_eng
Apresentação sem discurso 2 t10 aes eletropaulo final_eng
 
Commercial Sample Proposal
Commercial Sample ProposalCommercial Sample Proposal
Commercial Sample Proposal
 
Actual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesActual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation Slides
 
Actual Cost Vs Budget PowerPoint Presentation Slides
Actual Cost Vs Budget PowerPoint Presentation Slides Actual Cost Vs Budget PowerPoint Presentation Slides
Actual Cost Vs Budget PowerPoint Presentation Slides
 
American Eagle presentation
American Eagle presentationAmerican Eagle presentation
American Eagle presentation
 
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019
Pavilion Condo Analysis Budget 2019 jan 1 26 2019 vs dec 31 2019
 
FSAE-A Business Presentation - Redback Racing 2017
FSAE-A Business Presentation - Redback Racing 2017FSAE-A Business Presentation - Redback Racing 2017
FSAE-A Business Presentation - Redback Racing 2017
 

More from Fadi Maalouf, PMP

Green Ammonia Financial Model Toolkit LCOA
Green Ammonia Financial Model Toolkit LCOAGreen Ammonia Financial Model Toolkit LCOA
Green Ammonia Financial Model Toolkit LCOAFadi Maalouf, PMP
 
Project Finance Management Plan
Project Finance Management PlanProject Finance Management Plan
Project Finance Management PlanFadi Maalouf, PMP
 
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!Fadi Maalouf, PMP
 
Strategic Business Plan for IPP / EPC Renewable Energy Company
Strategic Business Plan for IPP / EPC Renewable Energy CompanyStrategic Business Plan for IPP / EPC Renewable Energy Company
Strategic Business Plan for IPP / EPC Renewable Energy CompanyFadi Maalouf, PMP
 
IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapFadi Maalouf, PMP
 
PV Project Development Pre-Feasibility Financial Model
PV Project Development Pre-Feasibility Financial ModelPV Project Development Pre-Feasibility Financial Model
PV Project Development Pre-Feasibility Financial ModelFadi Maalouf, PMP
 

More from Fadi Maalouf, PMP (9)

Green Ammonia Financial Model Toolkit LCOA
Green Ammonia Financial Model Toolkit LCOAGreen Ammonia Financial Model Toolkit LCOA
Green Ammonia Financial Model Toolkit LCOA
 
SunBurn Test
SunBurn TestSunBurn Test
SunBurn Test
 
Project Finance Management Plan
Project Finance Management PlanProject Finance Management Plan
Project Finance Management Plan
 
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!
New Era: Renewable Energy Beyond Distributed Generation and Utility Scale!
 
Dii Toolkit Initiative
Dii Toolkit InitiativeDii Toolkit Initiative
Dii Toolkit Initiative
 
Strategic Business Plan for IPP / EPC Renewable Energy Company
Strategic Business Plan for IPP / EPC Renewable Energy CompanyStrategic Business Plan for IPP / EPC Renewable Energy Company
Strategic Business Plan for IPP / EPC Renewable Energy Company
 
IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development Roadmap
 
PV Project Development Pre-Feasibility Financial Model
PV Project Development Pre-Feasibility Financial ModelPV Project Development Pre-Feasibility Financial Model
PV Project Development Pre-Feasibility Financial Model
 
Unirac PV Racking Basics
Unirac PV Racking BasicsUnirac PV Racking Basics
Unirac PV Racking Basics
 

Recently uploaded

(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...Call Girls in Nagpur High Profile
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)RaviPrajapat11
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130Suhani Kapoor
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...Suhani Kapoor
 
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130Suhani Kapoor
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Servicesexy call girls service in goa
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BHbill846304
 
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 

Recently uploaded (20)

(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
 
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
VIP Call Girls Service Tolichowki Hyderabad Call +91-8250192130
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BH
 
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 

PV Project Development Economic Feasibility Financial Model Baseline Case

  • 1. INPUTS OUTPUTS Financials NOTES CAPEX / Costs NOTES General Capital (Direct) Cost ($/kWp) $825.00 OCC- Overnight Construction Cost Effective Tax Rate 0.00% Analysis Period 25 Customs Duty (%) 0.00% Credit Basis - Federal $860.00 Inflation Rate 1.250000% % of Capital (Direct) Cost Custom Duty Applies 0.00% Credit Basis - State $860.00 Real Discount Rate 5.68% Capital (Direct) Cost ($) $825.00 OCC- Overnight Construction Cost Nominal Discount Rate 7.00% Nominal Discount Rate 7.0000000% Contingency (%) 0.00% Included in EPC Price First Costs $129.00 Taxes, Depreciation, and Insurance Total Capital (Direct) Cost ($) $825.00 Adjusted Installed Costs $860.00 Tax 1 (federal) 0.00% Total Indirect Cost ($) $35.00 Project Development, etc. Decommissioning Cost Yr 25 $0.00 Tax 2 (local state) 0.00% % of Direct Costs Sales Tax Applies 0% Salvage Value Yr 25 $132.00 PropertyTax 0.00% Total Installed Cost ($) $860.00 Sales Tax 0.00% OPEX / O&M NPV(Nominal,Costflow) -559.26 Depreciation Method N/A (A) Fixed O&M ($/kWp-yr) $10.00 Mgt, Labor, Parts, Consum., Lease, Ins, Int-Hedge, X-Hedge, etc. NPV(Nominal,Output) 23,135.35 Apply Depreciation Yes/No No Fixed O&M Real Esc. 0.00% in addition to inflation NPV(Real,Output) 26,081.51 Insurance (Yr 1, Yr 2 onwads is inflation Adiusted) 0.00% included in OPEX Aux Pwr Cost - Fixed (Annual) O&M ($/yr) $0.00 Loan, DSCR, DSRA, MIRR (B) Auxiliary Power Cost - Fixed (Annual) O&M ($/kWp-yr) $0.00 Loan (Debt) Percentage of TotalAdj. Inst. Costs 85.00% Senior Debt 1 Aux Pwr Annual Esc. - Fixed (Annual) O&M Real Esc. 0.00% Equals PPA Esc.,in addition to inflation Real 2.6389 Term (Yr) 24 Senior Debt 1 Total(A)+(B) $/kWp-yr $10.00 Total Fixed O&M, inflation adjusted Nominal 2.9749 Rate 2.20% Senior Debt 1, fixed rate (or LIBOR+Margin, m-perm, etc.) Variable O&M ($/MWh) $0.00 Loan Amount $731.00 Variable O&M Real Esc. 0% in addition to inflation Equity Amount $129.00 Fuel Cost ($/MMBtu) $0.00 Simple Payback 17.9278 Debt Payment ($/Yr) -$39.53 Fuel Cost Real Esc. 0% in addition to inflation Discounted Payback >25 years WACC 2.92% Decommissioning Cost Year 25 (% of Capital Direct Cost) 0.00% Positive Operating Cashflow Yes/No Yes Salvage Value Year 25 (% of Capital Direct Cost) 16.00% (Net, after Decomm Expenses) Min. Required DSCR 1.2 @ P50, Account or Sculpting CER Carbon Price ($/tCO2) $10.00 NPV ($0.0000) Min. Required IRR 7.00% Carbon Reduction (tCO2/MWh) 0.6000 Based on country power generation profile MIRR Finance Rate 0.00% System Carbon Revenue from CER Year 1 ($) $12.54 with auxiliary consumption adjustment MIRR Reinvestment Rate 0.00% System Carbon Revenue from CER Year 1 ($/kWh) $0.006000 with auxiliary consumption adjustment IRR 7.0000% OK DSRA Cover (Months) 6 Apply System Carbon Reveue from CER in LCOE Calculation No MIRR 3.9410% DSRA Amount ($) -$19.76 @ PCOD PV Power Plant Min. DSCR w/o DSRA 1.0326 LOW DSRA Acc Type (Acceptable Credit Support) PG Cash/PG/LC/Loan/Cashflow System Size (kWp) 1.00 Avg. DSCR w/o DSRA 1.1757 DSRA Loan Amount NA Estimated Annual Yield Output P50 (kWh/kWp) 2100.00 based on PVSYST simulation, including Aux. Power Max. DSCR w/o DSRA 1.3195 DSRA Loan Term (Yr) NA Capacity Utilization Factor 23.97% DSRA Loan Rate NA Annual Yield Degradation Year 1 (%/year) 0.00% Positive Cashflow Y/N Yes OK DSRA Debt Payment ($/Yr) NA Annual Yield Degradation Year 2 to 25 (%/year) 0.60% CFADS Utility PPA System Annual Availability (%) 99.50% excluding auxiliary consumption DSRA (6 Months) Credit Support C/PG/LC/CF PG PPA Rate Yr-1 ($/kWh) $0.029749 Gross Annual Yield Output Year 1 (kWh) 2,089.50 without auxiliary consumption adjustment LLCR PPA Annual Esc. (%) 0.00% Net Annual Yield Output Year 1 (kWh), with Aux. 2,089.50 with auxiliary consumption adjustment PLCR Other Revenues System Carbon Reduction CER Year 1 (tCO2) 1.25 with auxiliary consumption adjustment MRA/MMRA Other Revenue-A, Yr-1 ($/kWh) $0.000000 RE Certificates Heat Rate (MMBtus/MWh) 0 WC Other Revenue-A, Annual Esc. (%) 0.00% Fixed Aux Power for Plant MEP, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr SBYWC Other Revenue-B, Yr-1 ($/kWh) $0.000000 Summer Peak PPA Escalation / ToY r Shelter Heat Gain, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr EBL Other Revenue-B, Annual Esc. (%) 0.00% Fixed Aux Power for HVAC for Inverters, % of Sys Ann. Energy Yield (kWh/yr) 0% 0.00 kWh/yr SBYE Other Revenue-C, Interest on Acconts Balance NA Applicable Accounts Fixed Total Aux Power Consumption (kWh/yr) 0.00 kWh/yr Other Revenue-C, Interest (%) NA pq/pa Aux Power Cost Rate ($/kWh) PPA Aux Power Cost Annual Esc. Rate (%) PPA Esc. SOLAR PV PROJECT LCOE ECONOMIC FEASIBILITY ANALYSIS - BASELINE CASE Intermediate Values Results LCOE (¢/kWh) Results Payback (years) - excl debt & tax considerations, incl expenses Results NPV (nominal dollars) Results IRR & DSCR ‐129.00 ‐49.53 ‐49.65 ‐49.78 ‐49.91 ‐50.04 ‐50.17 ‐50.30 ‐50.44 ‐50.57 ‐50.71 ‐50.85 ‐50.99 ‐51.14 ‐51.28 ‐51.43 ‐51.58 ‐51.73 ‐51.88 ‐52.04 ‐52.19 ‐52.35 ‐52.51 ‐52.67 ‐52.84 118.53 ‐150.00 ‐100.00 ‐50.00 0.00 50.00 100.00 150.00 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Dollars Year After Tax Cost Flow 62.16 61.79 61.42 61.05 60.68 60.32 59.96 59.60 59.24 58.88 58.53 58.18 57.83 57.48 57.14 56.80 56.45 56.12 55.78 55.44 55.11 54.78 54.45 54.13 53.80 48 50 52 54 56 58 60 62 64 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Dollars Year Operating Revenue  10.00 10.13 10.25 10.38 10.51 10.64 10.77 10.91 11.04 11.18 11.32 11.46 11.61 11.75 11.90 12.05 12.20 12.35 12.51 12.66 12.82 12.98 13.14 13.31 ‐118.53 ‐140 ‐120 ‐100 ‐80 ‐60 ‐40 ‐20 0 20 40 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Dollars Year Operating Expenses ‐129.00 12.63 12.13 11.64 11.14 10.64 10.15 9.65 9.16 8.66 8.17 7.68 7.19 6.69 6.20 5.71 5.22 4.73 4.23 3.74 3.25 2.76 2.27 1.78 1.29 172.33 ‐150.00 ‐100.00 ‐50.00 0.00 50.00 100.00 150.00 200.00 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Dollars Year After Tax Net Cash Flow 52.16 51.66 51.17 50.67 50.17 49.68 49.18 48.69 48.19 47.70 47.21 46.72 46.22 45.73 45.24 44.75 44.26 43.76 43.27 42.78 42.29 41.80 41.31 40.82 172.33 0 20 40 60 80 100 120 140 160 180 200 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Dollars Year Operating Income Cash Flow ‐860.00 ‐807.84 ‐756.18 ‐705.01 ‐654.34 ‐604.17 ‐554.49 ‐505.31 ‐456.62 ‐408.42 ‐360.72 ‐313.51 ‐266.80 ‐220.58 ‐174.85 ‐129.61 ‐84.86 ‐40.60 3.16 46.43 89.22 131.51 173.31 214.62 255.44 ‐1,000.00 ‐800.00 ‐600.00 ‐400.00 ‐200.00 0.00 200.00 400.00 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Dollars Year Cummulative Simple Payback Cash Flow 1.32 1.31 1.29 1.28 1.27 1.26 1.24 1.23 1.22 1.21 1.19 1.18 1.17 1.16 1.14 1.13 1.12 1.11 1.09 1.08 1.07 1.06 1.05 1.03 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 DSCR Year Pre‐Tax DSCR 1.33 1.33 1.33 1.33 1.33 1.34 1.34 1.35 1.36 1.37 1.38 1.40 1.42 1.44 1.48 1.52 1.57 1.64 1.74 1.87 2.08 2.44 3.15 5.30 0.80 1.30 1.80 2.30 2.80 3.30 3.80 4.30 4.80 5.30 5.80 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 PLCR Year PLCR 1.19 1.18 1.17 1.17 1.16 1.15 1.15 1.14 1.13 1.12 1.12 1.11 1.10 1.10 1.09 1.08 1.08 1.07 1.06 1.06 1.05 1.05 1.04 1.03 0.80 0.85 0.90 0.95 1.00 1.05 1.10 1.15 1.20 1.25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 LLCR Year LLCR 1.22 1.21 1.20 1.20 1.19 1.19 1.18 1.17 1.17 1.16 1.16 1.16 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.16 1.18 1.22 1.30 1.54 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 1.60 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 LLCR Year LLCR w/ DSRA 1.35 1.35 1.36 1.36 1.36 1.37 1.38 1.38 1.39 1.41 1.42 1.44 1.47 1.50 1.53 1.58 1.64 1.72 1.83 1.98 2.22 2.61 3.41 5.81 0.80 1.80 2.80 3.80 4.80 5.80 6.80 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 PLCR Year PLCR w/ DSRA 1.82 1.81 1.79 1.78 1.77 1.76 1.74 1.73 1.72 1.71 1.69 1.68 1.67 1.66 1.64 1.63 1.62 1.61 1.59 1.58 1.57 1.56 1.55 1.53 0.80 1.00 1.20 1.40 1.60 1.80 2.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 DSCR Year Pre‐Tax DSCR w/ DSRA 16-LCOE-Template-Final-UAE-170228 25 Years Analysis- Baseline Fadi Maalouf Rev-16 28/02/2017 1 of 1