Project Research Proposal
Project Research Proposal
Design of 4.5km Nawakilli to Balili check post
link Road
Submitted by
(FALL-2010)
• AMJAD PERVEZ: 13380 (Group Leader)
• ASSADULLAH: 12816
• HAZOOR ALI SHAH: 12699
• RIAZ KHAN: 15265
• BILAWAL IBRAHIM: 15628
• SHARAF UD DIN: 12562
Supervised by
ENGR. NAWAZ ALI
Lecturer
Department of Civil Engineering
Faculty of Engineering
Supervised by Nawaz Ali Kakar Page 1 of 6
Project Research Proposal
Table of Content
PROJECT RESEARCH PROPOSAL...............................................................1
TABLE OF CONTENT.......................................................................................2
1.TITLE:.............................................................................................................3
3.CHECKED BY................................................................................................3
4.APPROVED BY .............................................................................................3
5.SCOPE:..........................................................................................................4
6.COPYRIGHTS:...............................................................................................4
7.ABSTRACT: ..................................................................................................5
8.OBJECTIVES.................................................................................................5
9.REFERENCES...............................................................................................5
10.RESEARCH METHODOLOGY:...................................................................6
11.POTENTIAL BENEFITS...............................................................................6
Supervised by Nawaz Ali Kakar Page 2 of 6
Project Research Proposal
1. Title:
Design of 4.5km Nawakilli to Balili ceck post link Road
2. Prepared by:
• AMJAD PERVEZ: 13380 (Group Leader)
• ASSADULLAH: 12816
• HAZOOR ALI SHAH: 12699
• RIAZ KHAN: 15265
• BILAWAL IBRAHIM: 15628
• SHARAF UD DIN: 12562
3. Checked by
NAWAZ ALI KAKAR
Project Supervisor
Lecturer
Department of Civil Engineering
4. Approved by
Dr. Gul Ahmed Jokhio
Assistant Professor
Chairman Department of Civil Engineering
Supervised by Nawaz Ali Kakar Page 3 of 6
Project Research Proposal
5. Scope:
This research project covers the following:
5.1. Survey (preliminary & secondary) and levelling of the road.
5.2. Geometrical designs (Long Sections & cross Sections).
5.3. Different types of Soil Tests:
5.3.1. Moisture Content test.
5.3.2. Liquid Limit test.
5.3.3. Plastic Limit test.
5.3.4. Shrinkage Limit test.
5.3.5. Proctor Test.
5.3.6. California Bearing Ratio (CBR) Test.
5.4. Design of culverts (pipe, box).
5.5. Design of causeway.
5.6. Design of curve.
5.7. Road Finishing (Alignment).
5.8. Estimation and Costing.
6. Copyrights:
The copyrights of the project will remain with Department of Civil
Engineering, Faculty of Engineering, Baluchistan University of
Information Technology, Engineering and Management Sciences Quetta.
Supervised by Nawaz Ali Kakar Page 4 of 6
Project Research Proposal
7. Abstract:
A road is a thoroughfare route, or way on the land between two places
which has been paved or otherwise improved to allow travel by some
conveyance, including a horse, cart, or motorcycle vehicle. Designing of
our road is based upon the AASHTO specifications under the following
standards, Geometric design: AASHTO 2001 and Pavement design:
AASHTO 1986-Road note 31-1993.
By carrying out survey & levelling collected the road data which is
further required to draw the long-sections & cross-sections. By gathering
the soil samples from the road site we then performed specified tests. All
the above information will be used to design the road.
8. Objectives
The prime objective of this project is to connect the rural area (Shah
wali) with Nawakilli and Saraghurgai.
The aim of this project work is to fulfil the demand of the road for the
sake of increasing population, for which we will have to plan and design
the road. In this project we will work on the Softwares related to
Transportation engineering e.g. GPS for finding the coordinates of the
proposed road. AutoCAD for drawing L-sections & Cross sections.
9. References
9.1. AASHTO standards.
9.1.1.1. Geometric design: AASHTO 2001
9.1.1.2. Pavement design: AASHTO 1986-Road note
31-1993.
9.2 Fundamentals of Transportation Engineering book
Supervised by Nawaz Ali Kakar Page 5 of 6
Project Research Proposal
10. Research Methodology:
The project will include following methodology for completion
10.1. Planning to Carrey the project.
10.2. Weather forecasting to Carrey the survey.
10.3. Collection of data through preliminary & secondary survey &
levelling
10.4. Tests for checking the characteristics of the soil (moisture
content Test, liquid limit test, plastic limit test, CBR test, proctor
test.)
10.5. Analysis of the data obtained by survey & tests.
10.6. Implementation of the data.
10.7. Use of Softwares (GPS for finding coordinates, & AutoCAD for
Drawing the L & cross sections).
10.8. Designing of culverts, curve, cause way.
10.9. Estimation and costing.
10.10. Road finishing (Alignments).
11. Potential Benefits
11.1. The Potential benefit of the project is to develop the Linking road
between the villages nearby.
11.2. Economic way of approach for the local people.
_______ THE END______
Supervised by Nawaz Ali Kakar Page 6 of 6
Project Research Proposal
10. Research Methodology:
The project will include following methodology for completion
10.1. Planning to Carrey the project.
10.2. Weather forecasting to Carrey the survey.
10.3. Collection of data through preliminary & secondary survey &
levelling
10.4. Tests for checking the characteristics of the soil (moisture
content Test, liquid limit test, plastic limit test, CBR test, proctor
test.)
10.5. Analysis of the data obtained by survey & tests.
10.6. Implementation of the data.
10.7. Use of Softwares (GPS for finding coordinates, & AutoCAD for
Drawing the L & cross sections).
10.8. Designing of culverts, curve, cause way.
10.9. Estimation and costing.
10.10. Road finishing (Alignments).
11. Potential Benefits
11.1. The Potential benefit of the project is to develop the Linking road
between the villages nearby.
11.2. Economic way of approach for the local people.
_______ THE END______
Supervised by Nawaz Ali Kakar Page 6 of 6

More Related Content

What's hot

PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
GLA University
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
KHUSHBU SHAH
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
AKANSHA GURELE
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
Md. Abdul Kader
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
Sowjanya Gannoju
 
Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)
Ahmed Ferdous Ankon
 
Activities used in road construction
Activities used in road constructionActivities used in road construction
Activities used in road construction
Ahsan Awan
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNINGintan fatihah
 
Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
mohammad danish anwar
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTION
Rising Sher
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
Anis Rahman Khokan
 
On street and off street parking
On street and off street parkingOn street and off street parking
On street and off street parking
Sagar Vekariya
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
Junaid Jamadar
 
Urban transportation planning
Urban transportation planningUrban transportation planning
Urban transportation planning
Piter Biswas
 
Road Construction
Road ConstructionRoad Construction
Road Construction
Danish Mohd
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
Shubham Sadh
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Road construction report
Road construction reportRoad construction report
Road construction report
mohammad danish anwar
 
Chapter 6 Fundamentals of traffic flow
Chapter 6 Fundamentals of traffic flowChapter 6 Fundamentals of traffic flow
Chapter 6 Fundamentals of traffic flow
Fayaz Rashid
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
Kavin Raval
 

What's hot (20)

PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)Roadway condition survey full report(BUET)
Roadway condition survey full report(BUET)
 
Activities used in road construction
Activities used in road constructionActivities used in road construction
Activities used in road construction
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNING
 
Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTION
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
On street and off street parking
On street and off street parkingOn street and off street parking
On street and off street parking
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Urban transportation planning
Urban transportation planningUrban transportation planning
Urban transportation planning
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Road construction report
Road construction reportRoad construction report
Road construction report
 
Chapter 6 Fundamentals of traffic flow
Chapter 6 Fundamentals of traffic flowChapter 6 Fundamentals of traffic flow
Chapter 6 Fundamentals of traffic flow
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 

Similar to Project Research Proposal Design of 4.5km road

UNDERPASS DESIGN
UNDERPASS DESIGNUNDERPASS DESIGN
UNDERPASS DESIGN
SAMPATH SADANANDA NAYAK
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORT
ATUL SHUKLA
 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
Nishant Pandey
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavement
TAHIR HUSEN
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
Lars Forslöf
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
Sukhdeep Jat
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
AnshuRaj51911
 
Design of expressway
Design of expresswayDesign of expressway
Design of expressway
SujitkumarMahto
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
ragabata
 
World’s largest undeveloped tin deposit in Kazakhstan
World’s largest undeveloped tin deposit in KazakhstanWorld’s largest undeveloped tin deposit in Kazakhstan
World’s largest undeveloped tin deposit in Kazakhstan
Syrymbet JSC
 
A Meganathan - Traffic cum Pavement Expert
A Meganathan - Traffic cum Pavement ExpertA Meganathan - Traffic cum Pavement Expert
A Meganathan - Traffic cum Pavement ExpertMeganathan Andiappan
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
Subhendu Samui
 

Similar to Project Research Proposal Design of 4.5km road (20)

UNDERPASS DESIGN
UNDERPASS DESIGNUNDERPASS DESIGN
UNDERPASS DESIGN
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORT
 
cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavement
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Muhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CVMuhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CV
 
CV_Anil Malagi
CV_Anil MalagiCV_Anil Malagi
CV_Anil Malagi
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
 
Bridge report
Bridge reportBridge report
Bridge report
 
Design of expressway
Design of expresswayDesign of expressway
Design of expressway
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 
ToR
ToRToR
ToR
 
World’s largest undeveloped tin deposit in Kazakhstan
World’s largest undeveloped tin deposit in KazakhstanWorld’s largest undeveloped tin deposit in Kazakhstan
World’s largest undeveloped tin deposit in Kazakhstan
 
A Meganathan - Traffic cum Pavement Expert
A Meganathan - Traffic cum Pavement ExpertA Meganathan - Traffic cum Pavement Expert
A Meganathan - Traffic cum Pavement Expert
 
Moshtak CV 2016 Pic
Moshtak CV 2016  PicMoshtak CV 2016  Pic
Moshtak CV 2016 Pic
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
 

Recently uploaded

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 

Recently uploaded (20)

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 

Project Research Proposal Design of 4.5km road

  • 1. Project Research Proposal Project Research Proposal Design of 4.5km Nawakilli to Balili check post link Road Submitted by (FALL-2010) • AMJAD PERVEZ: 13380 (Group Leader) • ASSADULLAH: 12816 • HAZOOR ALI SHAH: 12699 • RIAZ KHAN: 15265 • BILAWAL IBRAHIM: 15628 • SHARAF UD DIN: 12562 Supervised by ENGR. NAWAZ ALI Lecturer Department of Civil Engineering Faculty of Engineering Supervised by Nawaz Ali Kakar Page 1 of 6
  • 2. Project Research Proposal Table of Content PROJECT RESEARCH PROPOSAL...............................................................1 TABLE OF CONTENT.......................................................................................2 1.TITLE:.............................................................................................................3 3.CHECKED BY................................................................................................3 4.APPROVED BY .............................................................................................3 5.SCOPE:..........................................................................................................4 6.COPYRIGHTS:...............................................................................................4 7.ABSTRACT: ..................................................................................................5 8.OBJECTIVES.................................................................................................5 9.REFERENCES...............................................................................................5 10.RESEARCH METHODOLOGY:...................................................................6 11.POTENTIAL BENEFITS...............................................................................6 Supervised by Nawaz Ali Kakar Page 2 of 6
  • 3. Project Research Proposal 1. Title: Design of 4.5km Nawakilli to Balili ceck post link Road 2. Prepared by: • AMJAD PERVEZ: 13380 (Group Leader) • ASSADULLAH: 12816 • HAZOOR ALI SHAH: 12699 • RIAZ KHAN: 15265 • BILAWAL IBRAHIM: 15628 • SHARAF UD DIN: 12562 3. Checked by NAWAZ ALI KAKAR Project Supervisor Lecturer Department of Civil Engineering 4. Approved by Dr. Gul Ahmed Jokhio Assistant Professor Chairman Department of Civil Engineering Supervised by Nawaz Ali Kakar Page 3 of 6
  • 4. Project Research Proposal 5. Scope: This research project covers the following: 5.1. Survey (preliminary & secondary) and levelling of the road. 5.2. Geometrical designs (Long Sections & cross Sections). 5.3. Different types of Soil Tests: 5.3.1. Moisture Content test. 5.3.2. Liquid Limit test. 5.3.3. Plastic Limit test. 5.3.4. Shrinkage Limit test. 5.3.5. Proctor Test. 5.3.6. California Bearing Ratio (CBR) Test. 5.4. Design of culverts (pipe, box). 5.5. Design of causeway. 5.6. Design of curve. 5.7. Road Finishing (Alignment). 5.8. Estimation and Costing. 6. Copyrights: The copyrights of the project will remain with Department of Civil Engineering, Faculty of Engineering, Baluchistan University of Information Technology, Engineering and Management Sciences Quetta. Supervised by Nawaz Ali Kakar Page 4 of 6
  • 5. Project Research Proposal 7. Abstract: A road is a thoroughfare route, or way on the land between two places which has been paved or otherwise improved to allow travel by some conveyance, including a horse, cart, or motorcycle vehicle. Designing of our road is based upon the AASHTO specifications under the following standards, Geometric design: AASHTO 2001 and Pavement design: AASHTO 1986-Road note 31-1993. By carrying out survey & levelling collected the road data which is further required to draw the long-sections & cross-sections. By gathering the soil samples from the road site we then performed specified tests. All the above information will be used to design the road. 8. Objectives The prime objective of this project is to connect the rural area (Shah wali) with Nawakilli and Saraghurgai. The aim of this project work is to fulfil the demand of the road for the sake of increasing population, for which we will have to plan and design the road. In this project we will work on the Softwares related to Transportation engineering e.g. GPS for finding the coordinates of the proposed road. AutoCAD for drawing L-sections & Cross sections. 9. References 9.1. AASHTO standards. 9.1.1.1. Geometric design: AASHTO 2001 9.1.1.2. Pavement design: AASHTO 1986-Road note 31-1993. 9.2 Fundamentals of Transportation Engineering book Supervised by Nawaz Ali Kakar Page 5 of 6
  • 6. Project Research Proposal 10. Research Methodology: The project will include following methodology for completion 10.1. Planning to Carrey the project. 10.2. Weather forecasting to Carrey the survey. 10.3. Collection of data through preliminary & secondary survey & levelling 10.4. Tests for checking the characteristics of the soil (moisture content Test, liquid limit test, plastic limit test, CBR test, proctor test.) 10.5. Analysis of the data obtained by survey & tests. 10.6. Implementation of the data. 10.7. Use of Softwares (GPS for finding coordinates, & AutoCAD for Drawing the L & cross sections). 10.8. Designing of culverts, curve, cause way. 10.9. Estimation and costing. 10.10. Road finishing (Alignments). 11. Potential Benefits 11.1. The Potential benefit of the project is to develop the Linking road between the villages nearby. 11.2. Economic way of approach for the local people. _______ THE END______ Supervised by Nawaz Ali Kakar Page 6 of 6
  • 7. Project Research Proposal 10. Research Methodology: The project will include following methodology for completion 10.1. Planning to Carrey the project. 10.2. Weather forecasting to Carrey the survey. 10.3. Collection of data through preliminary & secondary survey & levelling 10.4. Tests for checking the characteristics of the soil (moisture content Test, liquid limit test, plastic limit test, CBR test, proctor test.) 10.5. Analysis of the data obtained by survey & tests. 10.6. Implementation of the data. 10.7. Use of Softwares (GPS for finding coordinates, & AutoCAD for Drawing the L & cross sections). 10.8. Designing of culverts, curve, cause way. 10.9. Estimation and costing. 10.10. Road finishing (Alignments). 11. Potential Benefits 11.1. The Potential benefit of the project is to develop the Linking road between the villages nearby. 11.2. Economic way of approach for the local people. _______ THE END______ Supervised by Nawaz Ali Kakar Page 6 of 6