SlideShare a Scribd company logo
Project Management Good Practices
Presented by
Hari Prasad Thapliyal
Agilest & Project Management Trainer, Coach & Consultant
(MBA, MCA, PGDOM, PGDFM, CIC, PMP, PMI-ACP, CSM, SCPO, SDC
PRINCE2-Trainer, Scrum Certified Trainer, Microsoft Certified Trainer, ZED Master Trainer)
This presentation is for the Practicing Project Managers. In
this presentation I have discussed some tips for making
project successful from the day one.
1. Define Project Success Criteria- At the start of project
2. Identify Project Drivers, Constraints and degree of freedom – At the start of
project
3. Identify Product Release Criteria – During Planning
4. Negotiate achievable commitments – At the start of project & when estimation
is complete
5. While Planning the Project
6. While Estimating the Work
7. While Tracking Project’s Progress
Major Activities in Project Life Cycle – for Project Success
Success Criteria from Product Perspective May be
 Profit Increase %
 Market Share %
 Sales Volume %
 Customer Satisfaction Index %
 Saving money %
 Reducing transaction time %
 Increasing transaction %
Success Criteria from Project Perspective May be
 Schedule Variance
 Cost Variance
 Scope
 Quality (defects, reviews, issues etc)
While working on project you are responsible to meet “Success Criteria from Project Perspective” but keep doing business
justification keeping “Success Criteria from Product Perspective”
1. Define Project Success Criteria
 Schedule
 Cost
 Quality
 Features
 Staff
Everything is not equally limited. One can be negotiated with respect to others.
Know what is negotiable in your project.
2. Identify Project Drivers, Constraints & Degree of Freedom
 Should contain release note
 No open critical defects
 No of defects decreased %
 Specific functionality fully working
 N% of test cases passed
 Specific legal, contractual or regulatory goals met
 All UA test cases passes
3. Define Product Release Criteria
 No open critical defects
 No of defects decreased %
 Specific functionality fully working
 N% of test cases passed
 Specific legal, contractual or regulatory goals met
 All UA test cases passes
4. Negotiate Achievable commitments
 Write a Plan not only schedule
 Decompose task into traceable granularity 8/80 rule
 Develop planning worksheet for common large tasks
 Plan to do rework after a quality control activity
 Manage Project Risks
 Plan time for process improvement
 Respect the learning curve. Everything cannot be planned in great
detail at the start.
5. While Planning the Project
 Estimate based on efforts, not calendar times
 Generally don’t schedule multi-tasking people
 Do not schedule more than 80% of available time (risk, improvement,
rework will consume remaining time)
 Build training time into schedule
 Record estimates & basis of estimates
 Use estimation tools
 Plan contingency buffer towards the end of milestone
6. While Estimating the Work
 Record actuals and estimates
 Count tasks as complete only when 100% complete
 Track project status openly and honestly
7. While Tracking Project Progress
 Conduct Project Retrospectives
8. Learning for the future
 Surrender to the long pipe of requirements. They will keep coming…
You can manage this but not stop.
 Always assume that there is high probability of initial set
requirements being wrong. But it does not mean that you start only
when requirements are frozen. They will keep changing…
 Accept that all requirements change, so do not be panic. Plan
accordingly knowing this fact.
 Simplify your change-management approach. Learn to manage
requirements and getting those validated using different delivery
methods.
Reality of the Requirement Management
 Poor Alignment
 Bad Planning
 Lack of executive support
 Incomplete requirements
 Unclear expectations
 Scope creep
 Lack of resources
 Choice of technology
 Inexperience
Why Project Fails?
1. A bad idea executed to perfection is still a bad idea. A good idea poorly executed is of no use to
anyone. Augustine's Law
2. Failing to plan is planning to fail. Lakein's Law
3. Perfection is achieved, not when there is nothing more to add, but when there is nothing left to
take away. Saint Exupery's Law
4. There are two states to any larg project -too early to tell or too late to stop. Fitzgerald's Law
5. Work will expand to fill the time available. Parkinson's Law
6. A fool with a tool is still fool. Constantine's Law
7. If they know nothing of what you are doing they suspect you are doing nothing. Graham's Law
8. If anything can go wrong, it will. Murphy's Law
9. Project Management is about applying common sense with uncommon discipline. O'Brochta's
Law
10. About the time you finish doing something, you know enough to start. Kinser's Law
Project Management Laws
hari.prasad@vedavit-ps.com
+91 9535999336
https://in.linkedin.com/in/harithapliyal
http://twitter.com/pmlogy
http://pmlogy.com/
http://facebook.com/harithapliyalpage
https://in.pinterest.com/harithapliyal
https://www.instagram.com/thapliyal.h

More Related Content

What's hot

Project management
Project managementProject management
Project management
Erin Mucci
 
Uncertainty in agile projects
Uncertainty in agile projectsUncertainty in agile projects
Uncertainty in agile projects
Skills Matter
 
The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...
Association for Project Management
 

What's hot (19)

A Budgeting & Forecasting Roundtable
A Budgeting & Forecasting RoundtableA Budgeting & Forecasting Roundtable
A Budgeting & Forecasting Roundtable
 
Root Cause Analysis
Root Cause AnalysisRoot Cause Analysis
Root Cause Analysis
 
5 whys nhsiq 2014
5 whys   nhsiq 20145 whys   nhsiq 2014
5 whys nhsiq 2014
 
Why we work Late Hours
Why we work Late HoursWhy we work Late Hours
Why we work Late Hours
 
Estimating software development
Estimating software developmentEstimating software development
Estimating software development
 
Scrum
ScrumScrum
Scrum
 
Information Technology - Discover the Root Cause and Develop a solution throu...
Information Technology - Discover the Root Cause and Develop a solution throu...Information Technology - Discover the Root Cause and Develop a solution throu...
Information Technology - Discover the Root Cause and Develop a solution throu...
 
What agile is not
What agile is notWhat agile is not
What agile is not
 
Project management
Project managementProject management
Project management
 
Lessons about experiments
Lessons about experiments Lessons about experiments
Lessons about experiments
 
Project planning 101 for publicsectorpm v2
Project planning 101 for publicsectorpm v2Project planning 101 for publicsectorpm v2
Project planning 101 for publicsectorpm v2
 
Uncertainty in agile projects
Uncertainty in agile projectsUncertainty in agile projects
Uncertainty in agile projects
 
Planning your project
Planning your projectPlanning your project
Planning your project
 
A3 Process intro
A3 Process introA3 Process intro
A3 Process intro
 
Root Cause Analysis (RCA) Tools
Root Cause Analysis (RCA) ToolsRoot Cause Analysis (RCA) Tools
Root Cause Analysis (RCA) Tools
 
Epm case study
Epm case studyEpm case study
Epm case study
 
Constraints Task 2
Constraints Task 2Constraints Task 2
Constraints Task 2
 
Introduction to Lean and Kaizen
Introduction to Lean and KaizenIntroduction to Lean and Kaizen
Introduction to Lean and Kaizen
 
The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...The real reason that projects fail and how to fix it - An introduction to Cri...
The real reason that projects fail and how to fix it - An introduction to Cri...
 

Viewers also liked

Spanish Grammar book
Spanish Grammar bookSpanish Grammar book
Spanish Grammar book
Dylan Morgan
 
My lx business_executive_program_v4
My lx business_executive_program_v4My lx business_executive_program_v4
My lx business_executive_program_v4
alayonruth
 
Becoming a worthy leader
Becoming a worthy leaderBecoming a worthy leader
Becoming a worthy leader
Atty Garfinkel
 
Manual administrativo conquistadores 2014 pdf
Manual administrativo conquistadores 2014   pdfManual administrativo conquistadores 2014   pdf
Manual administrativo conquistadores 2014 pdf
Perú
 

Viewers also liked (20)

Project Managment Thinking
Project Managment ThinkingProject Managment Thinking
Project Managment Thinking
 
Managing Agile Software Development Projects
Managing Agile Software Development ProjectsManaging Agile Software Development Projects
Managing Agile Software Development Projects
 
Prince 2: project managment Document Risk log
Prince 2: project managment Document Risk logPrince 2: project managment Document Risk log
Prince 2: project managment Document Risk log
 
Nine best practices of project management
Nine best practices of project managementNine best practices of project management
Nine best practices of project management
 
Project managment ppt
Project managment pptProject managment ppt
Project managment ppt
 
Spanish Grammar book
Spanish Grammar bookSpanish Grammar book
Spanish Grammar book
 
Vacunasvet
VacunasvetVacunasvet
Vacunasvet
 
My lx business_executive_program_v4
My lx business_executive_program_v4My lx business_executive_program_v4
My lx business_executive_program_v4
 
Story Boards- Definitive.
Story Boards- Definitive.Story Boards- Definitive.
Story Boards- Definitive.
 
And credit
And creditAnd credit
And credit
 
Fintech for students
Fintech for studentsFintech for students
Fintech for students
 
Becoming a worthy leader
Becoming a worthy leaderBecoming a worthy leader
Becoming a worthy leader
 
Alt solunum yolu enfeksi̇yonlarinda opti̇mal örnek alim yerleri̇
Alt solunum yolu enfeksi̇yonlarinda  opti̇mal örnek alim yerleri̇Alt solunum yolu enfeksi̇yonlarinda  opti̇mal örnek alim yerleri̇
Alt solunum yolu enfeksi̇yonlarinda opti̇mal örnek alim yerleri̇
 
Genome
GenomeGenome
Genome
 
Case study 3 schemes
Case study 3   schemesCase study 3   schemes
Case study 3 schemes
 
Manual administrativo conquistadores 2014 pdf
Manual administrativo conquistadores 2014   pdfManual administrativo conquistadores 2014   pdf
Manual administrativo conquistadores 2014 pdf
 
Gr
GrGr
Gr
 
DiscoverText: Tools for Text
DiscoverText: Tools for TextDiscoverText: Tools for Text
DiscoverText: Tools for Text
 
Leigh Winterbottom Portfolio
Leigh Winterbottom PortfolioLeigh Winterbottom Portfolio
Leigh Winterbottom Portfolio
 
Final presentation
Final presentationFinal presentation
Final presentation
 

Similar to Project Managment Good Practices

success and failure of project chapter 5.pptx
success and failure of project chapter 5.pptxsuccess and failure of project chapter 5.pptx
success and failure of project chapter 5.pptx
abdiazizsheikhomar
 
Jayanto bose prashantshrivastava
Jayanto bose prashantshrivastavaJayanto bose prashantshrivastava
Jayanto bose prashantshrivastava
PMI2011
 
Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01
PMI_IREP_TP
 
Managing your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environmentManaging your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environment
Stephen Hightower
 

Similar to Project Managment Good Practices (20)

Project Management Toolkit
Project Management ToolkitProject Management Toolkit
Project Management Toolkit
 
Executing Successful Projects
Executing  Successful  ProjectsExecuting  Successful  Projects
Executing Successful Projects
 
You have a project manager yay
You have a project manager   yayYou have a project manager   yay
You have a project manager yay
 
Project Management How To
Project Management How ToProject Management How To
Project Management How To
 
10 reasons why projects fail or common mistakes to avoid
10 reasons why projects fail or common mistakes to avoid10 reasons why projects fail or common mistakes to avoid
10 reasons why projects fail or common mistakes to avoid
 
Project Management
Project ManagementProject Management
Project Management
 
success and failure of project chapter 5.pptx
success and failure of project chapter 5.pptxsuccess and failure of project chapter 5.pptx
success and failure of project chapter 5.pptx
 
Project Management For The Curious
Project Management For The CuriousProject Management For The Curious
Project Management For The Curious
 
Agile And Your Business V2
Agile And Your Business V2Agile And Your Business V2
Agile And Your Business V2
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
Project management slide show
Project management slide showProject management slide show
Project management slide show
 
Lean Projects with A3 Method
Lean Projects with A3 MethodLean Projects with A3 Method
Lean Projects with A3 Method
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project Managers
 
Agile estimates - Insights about the basic
Agile estimates -  Insights about the basicAgile estimates -  Insights about the basic
Agile estimates - Insights about the basic
 
ETCA_1
ETCA_1ETCA_1
ETCA_1
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
Jayanto bose prashantshrivastava
Jayanto bose prashantshrivastavaJayanto bose prashantshrivastava
Jayanto bose prashantshrivastava
 
Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01Jayantobose prashantshrivastava-131008015757-phpapp01
Jayantobose prashantshrivastava-131008015757-phpapp01
 
Managing your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environmentManaging your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environment
 

More from Hari Thapliyal

More from Hari Thapliyal (10)

Project Professional 2016 - Reports
Project Professional 2016 - ReportsProject Professional 2016 - Reports
Project Professional 2016 - Reports
 
Microsoft Project Online with PowerBI
Microsoft Project Online with PowerBIMicrosoft Project Online with PowerBI
Microsoft Project Online with PowerBI
 
Power BI Reporting & Project Online
Power BI Reporting & Project OnlinePower BI Reporting & Project Online
Power BI Reporting & Project Online
 
Project Professional 2016 - reports
Project Professional 2016 - reportsProject Professional 2016 - reports
Project Professional 2016 - reports
 
How good is my project management framework
How good is my project management frameworkHow good is my project management framework
How good is my project management framework
 
Introduction to PMI and PMP
Introduction to PMI and PMPIntroduction to PMI and PMP
Introduction to PMI and PMP
 
Microsoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsMicrosoft Project Course with PMP Concepts
Microsoft Project Course with PMP Concepts
 
Benefits of EPM
Benefits of EPMBenefits of EPM
Benefits of EPM
 
Relationship Business-Projects-Operations
Relationship Business-Projects-OperationsRelationship Business-Projects-Operations
Relationship Business-Projects-Operations
 
Value of Project Management Trainings
Value of Project Management TrainingsValue of Project Management Trainings
Value of Project Management Trainings
 

Project Managment Good Practices

  • 1. Project Management Good Practices Presented by Hari Prasad Thapliyal Agilest & Project Management Trainer, Coach & Consultant (MBA, MCA, PGDOM, PGDFM, CIC, PMP, PMI-ACP, CSM, SCPO, SDC PRINCE2-Trainer, Scrum Certified Trainer, Microsoft Certified Trainer, ZED Master Trainer)
  • 2. This presentation is for the Practicing Project Managers. In this presentation I have discussed some tips for making project successful from the day one.
  • 3. 1. Define Project Success Criteria- At the start of project 2. Identify Project Drivers, Constraints and degree of freedom – At the start of project 3. Identify Product Release Criteria – During Planning 4. Negotiate achievable commitments – At the start of project & when estimation is complete 5. While Planning the Project 6. While Estimating the Work 7. While Tracking Project’s Progress Major Activities in Project Life Cycle – for Project Success
  • 4. Success Criteria from Product Perspective May be  Profit Increase %  Market Share %  Sales Volume %  Customer Satisfaction Index %  Saving money %  Reducing transaction time %  Increasing transaction % Success Criteria from Project Perspective May be  Schedule Variance  Cost Variance  Scope  Quality (defects, reviews, issues etc) While working on project you are responsible to meet “Success Criteria from Project Perspective” but keep doing business justification keeping “Success Criteria from Product Perspective” 1. Define Project Success Criteria
  • 5.  Schedule  Cost  Quality  Features  Staff Everything is not equally limited. One can be negotiated with respect to others. Know what is negotiable in your project. 2. Identify Project Drivers, Constraints & Degree of Freedom
  • 6.  Should contain release note  No open critical defects  No of defects decreased %  Specific functionality fully working  N% of test cases passed  Specific legal, contractual or regulatory goals met  All UA test cases passes 3. Define Product Release Criteria
  • 7.  No open critical defects  No of defects decreased %  Specific functionality fully working  N% of test cases passed  Specific legal, contractual or regulatory goals met  All UA test cases passes 4. Negotiate Achievable commitments
  • 8.  Write a Plan not only schedule  Decompose task into traceable granularity 8/80 rule  Develop planning worksheet for common large tasks  Plan to do rework after a quality control activity  Manage Project Risks  Plan time for process improvement  Respect the learning curve. Everything cannot be planned in great detail at the start. 5. While Planning the Project
  • 9.  Estimate based on efforts, not calendar times  Generally don’t schedule multi-tasking people  Do not schedule more than 80% of available time (risk, improvement, rework will consume remaining time)  Build training time into schedule  Record estimates & basis of estimates  Use estimation tools  Plan contingency buffer towards the end of milestone 6. While Estimating the Work
  • 10.  Record actuals and estimates  Count tasks as complete only when 100% complete  Track project status openly and honestly 7. While Tracking Project Progress
  • 11.  Conduct Project Retrospectives 8. Learning for the future
  • 12.  Surrender to the long pipe of requirements. They will keep coming… You can manage this but not stop.  Always assume that there is high probability of initial set requirements being wrong. But it does not mean that you start only when requirements are frozen. They will keep changing…  Accept that all requirements change, so do not be panic. Plan accordingly knowing this fact.  Simplify your change-management approach. Learn to manage requirements and getting those validated using different delivery methods. Reality of the Requirement Management
  • 13.  Poor Alignment  Bad Planning  Lack of executive support  Incomplete requirements  Unclear expectations  Scope creep  Lack of resources  Choice of technology  Inexperience Why Project Fails?
  • 14. 1. A bad idea executed to perfection is still a bad idea. A good idea poorly executed is of no use to anyone. Augustine's Law 2. Failing to plan is planning to fail. Lakein's Law 3. Perfection is achieved, not when there is nothing more to add, but when there is nothing left to take away. Saint Exupery's Law 4. There are two states to any larg project -too early to tell or too late to stop. Fitzgerald's Law 5. Work will expand to fill the time available. Parkinson's Law 6. A fool with a tool is still fool. Constantine's Law 7. If they know nothing of what you are doing they suspect you are doing nothing. Graham's Law 8. If anything can go wrong, it will. Murphy's Law 9. Project Management is about applying common sense with uncommon discipline. O'Brochta's Law 10. About the time you finish doing something, you know enough to start. Kinser's Law Project Management Laws