BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
1
COURSE / WORKSHOP
PROJECT MANAGEMENT TOOLS FOR
SHIPYARD PROJECT MANAGERS
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
2
COURSE / WORKSHOP OBJECTIVE
To provide Shipyard Project Managers and Shipyard personnel
with project management tools for planning and controlling
projects, using recognized project management standards applied
on ship repair industry. Through this course learning experience
will be improved by practicing concepts through a real-world ship
repair project.
“This will increase the chance of success on your projects”
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
3
• Module 0. Project Management Standards and overview (1 hour): Definition of Project
Management. Project Management Standards, Knowledge Areas and Process groups. Project Management
in Shipyard industry overview.
• Module 1. WBS for Ship Repair Projects – (4 hours): What is a WBS?. Components of a WBS. Steps to
create a WBS for a ship repair project. WBS top 4 Benefits in Ship Repair industry. WBS Manual exercise.
Create the WBS for project QUEEN ANDREA using a WBS software.
• Module 2. Critical Path / Ms Project for Ship Repair Projects – (4 to 5 hours): Basic concepts for
project scheduling. What is critical path? How to use it in Ship Repair Projects. Critical path Top 5 benefits.
Aspects on which the Ship Repair Project Manager should focus in project scheduling. Critical Path Exercise.
Steps to Create a project schedule in Ms Project. How to monitor the schedule in Ms Project. Schedule
Accuracy level in ship repair projects based on uncertainty. Create the project schedule for project QUEEN
ANDREA using Ms Project.
COURSE / WORKSHOP CONTENT
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
4
• Module 3. Time and Cost Control with EVM Ship Repair Projects – (4 to 5 hours): What is EVM?.
EVM formulas (Variance, KPIs and Forecast). How to use EVM in Ship Repair Projects to control cost and time
(calculations and reports). Relationship between the WBS, Project Schedule (Ms Project) and EVM. Use EVM
calculations and reports for the project QUEEN ANDREA.
• Module 4. Risk Management in Ship Repair Projects – (4 hours): What is Risk Management?. Steps
for risk management in ship repair projects. Understanding the Risk Register and Risk Assessment Matrix for
Ship Repair Projects. Apply Risk Management for project QUEEN ANDREA.
• Module 5. Stakeholders Management in Ship Repair Projects – (4 hours): What is Stakeholder
Management?. Identify and analyze ship repair stakeholders. Manage ship repair stakeholders engagement.
Identify and analyze stakeholders for project QUEEN ANDREA.
COURSE / WORKSHOP CONTENT
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
5
• Module 6. Ship Repair Project Manager Soft Skills (1 to 2 hours): The 3 propeller blades of knowledge
for the Ship Repair Project Manager. Recognized Project Management Certifications. Coordination skills.
Overview on negotiation skills.
• Module 7. Multi-Projects (Program) Control using Ms-Project and EVM (3 to 4 hours): What is
Multi-Project / Program Management in the ship repair industry. Planning the Program. Controlling the
Program. The benefits of controlling the program. Then need of a Program or Project Management Manager
in the ship repair industry. Practical exercise using Ms Project and EVM
COURSE / WORKSHOP CONTENT
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
6
COURSE / WORKSHOP METHODOLOGY
The course / workshop methodology is based on “experiential
learning”.
Theory + subject specific exercise + real-world ship repair project practice
MV “QUEEN ANDREA”
IMO number: 0000000
Length Overall: 250 m
Breadth: 40.06 m
Gross Tonnage: 120.000
Vessel Type: Tanker
shipyardpm@gmail.com
6th March 2017
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
7
COURSE / WORKSHOP
FOUNDATION
• PMBOK guide from PMI
• My upcoming book “Shipyard Project
Management”
Coming soon May 2017
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
8
EDUCATIONAL BACKGROUND
• Industrial Engineer
• Post Graduate - Diploma in Project Management
• Project Management for Engineering projects course from Delft
University
• Certified as Project Management Professional - PMP by the Project
Management Institute (PMI) since 2011.
EXPERIENCE
• 10 years of experience in the industry
• Positions held: Project Manager, Risk Engineer, Production
Superintendent (Shipbuilding), Marine Maintenance Supervisor.
• 6 years of experience using PMI Standard in Ship Repair Projects
• Author and speaker about Project Management focused on Ship
Repair
6th March 2017shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
9
…… based on PMI Standard
MODULE 0
PROJECT
MANAGEMENT
STANDARDS
AND OVERVIEW
“….What is Project Management about? Project Management is about how to organize yourself, your team
and your project….”
PMBOK - PMI
APMBOK - APM PRINCE2 - AXELOS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
1
0
…… based on PMI Standard
MODULE 0
PROJECT
MANAGEMENT
STANDARDS
AND OVERVIEW
EXISTING PROJECT
MANAGEMENT WAY
OF THINKING IN
SHIPREPAIR
INDUSTRY
OLD FASHIONED
MANAGEMENT
STYLE
QUALITYMANAGEMENT
HUMANRESOURCEMANAGEMENT
COMMUNICATIONMANAGEMENT
RISKMANAGEMENT
PROCUREMENTMANAGEMENT
STAKEHOLDERMANAGEMENT
Cost
ScopeTime
SHIPS
TECHNICAL
KNOWLEDGE
PROJECT MANAGEMENT STANDARDS
SUSTAINIBILITY
THE CORRECT WAY
TO MANAGE
SHIPREPAIR
PROJECTS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
11
…… based on PMI Standard
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
MODULE 0
PROJECT
MANAGEMENT
STANDARDS
AND OVERVIEW
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
1
2
…… based on PMI Standard
MODULE 1
WBS – WORK
BREAKDOWN
STRUCTURE
APPLIED TO SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
1
3
…… based on PMI Standard
MODULE 1
WBS – WORK
BREAKDOWN
STRUCTURE
APPLIED TO SHIP
REPAIR
PROJECTS
Vessel Location /
Deliverable
Work Packages
Main Deliverable or Project
Figure 13. WBS example
1
1.1
1.1.1
1.2
1.1.2 1.2.1
LEVEL 1
LEVEL 2
LEVEL 3
WBS COMPONENTS
• Deliverable: is what we are going to deliver, either a service or a product requested by the client.
• Work package: is the lowest level of decomposition. As from the work packages you can define the activities
• ID number: is the number located on each component for easy identification
• Level of decomposition: is related how deep you decompose each element
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
14
…… based on PMI Standard
MODULE 1
WBS – WORK
BREAKDOWN
STRUCTURE
APPLIED TO SHIP
REPAIR
PROJECTS
HOW TO CREATE AND USE A WBS FOR SHIP REPAIR PROJECTS
STEP 1.
Collect
input
documents
STEP 2.
Divide ship
per
locations
and systems
STEP 3.
Define the
software to
be used
STEP 4.
Create the
WBS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
15
…… based on PMI Standard
MODULE 1
WBS – WORK
BREAKDOWN
STRUCTURE
APPLIED TO SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
16
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
CRITICAL PATH – MS PROJECT
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
17
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
CRITICAL PATH METHOD
Critical Path is the longest path from the beginning to the end of the project. A path is a sequence of activities in a
certain time frame and the longest path is the one leading the finish of the project
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
18
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
IN WHAT ASPECTS THE SHIPREPAIR PROJECT MANAGER SHOULD FOCUS WHILE PLANNING AND
CONTROLLING THE PROJECT SCHEDULE?
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
19
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
STEPS TO CREATE A SCHEDULE IN MS-PROJECT
Transfer WBS information into MS PROJECT
Adjust initial settings: Calendar and Project start date
Define activities and milestones
Define activity duration and sequence the activities
Calculate the critical path
Save baseline
1
2
3
5
6
4
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
20
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
STEPS TO CREATE A SCHEDULE IN MS-PROJECT
Define activity duration and sequence the activities4
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
21
…… based on PMI Standard
MODULE 2
CRITICAL PATH –
MS PROJECT
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
22
…… based on PMI Standard
MODULE 3
TIME AND COST
CONTROL WITH
EVM
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
23
…… based on PMI Standard
MODULE 3
TIME AND COST
CONTROL WITH
EVM
Project information
Project estimates: Price / MH /
Materials / Contractor invoice price /
Contractor prices / SC % margin
Monitoring dates: PV, EV, AC,
Variance for Man hours and
Materials
Jobs description +
Control account
Totals: Revenues,
MH, Materials,
Subcontractors
Totals per date: PV,
EV, AC, Variance
for MH and
Materials
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
24
…… based on PMI Standard
MODULE 3
TIME AND COST
CONTROL WITH
EVM
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
25
…… based on PMI Standard
MODULE 3
TIME AND COST
CONTROL WITH
EVM
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
26
…… based on PMI Standard
MODULE 4
RISK
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
27
…… based on PMI Standard
MODULE 4
RISK
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
STEPS FOR PROJECT RISK MANAGEMENT IN SHIP REPAIR PROJECTS
1. Identify Risks: Once the scope is known a risk identification can be performed. Risk can be identified during
project initiation till the end.
This are the most important aspects to consider when you are identifying Risk and Causes:
• The Risks must be identified based on the Project Objectives
• The Risks cannot be a constraint (a constraint is something that already exists and should be responded with
a contingency plan)
• When the risk is going to be identified you should ask yourself: What can go wrong that can impact the
project objectives?
• The cause of the risk could be a constraint, an assumption, requirement or condition that originates the
unwanted or wished event.
Example 1: Lack of man power, due to interference with other projects, impacting undocking date and departure
date.
Example 2: To not finish Hull blasting on planned date, due to extreme weather conditions on April, impacting
dry-docking time of the vessel
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
28
…… based on PMI Standard
MODULE 4
RISK
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
29
…… based on PMI Standard
MODULE 4
RISK
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
30
…… based on PMI Standard
MODULE 5
STAKEHOLDER
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
STAKEHOLDER
MANAGEMENT FOR
SHIP REPAIR PROJECTS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
31
…… based on PMI Standard
MODULE 5
STAKEHOLDER
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
Stakeholder Identification
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
32
…… based on PMI Standard
MODULE 5
STAKEHOLDER
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
Figure 12. Stakeholders Analysis Matrix
shipyardpm@gmail.com
Stakeholder Analysis Matrix
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
33
…… based on PMI Standard
MODULE 5
STAKEHOLDER
MANAGEMENT
FOR SHIP
REPAIR
PROJECTS
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
34
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR
SHIPREPAIR
PROJECT
MANAGERS
Project Management
TechnicalBusiness
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
35
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR
SHIPREPAIR
PROJECT
MANAGERS
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
36
…… based on PMI Standard
MODULE 6
SOFT SKILLS FOR
SHIPREPAIR
PROJECT
MANAGERS
shipyardpm@gmail.com
IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE
PLEASE CONTACT ME shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
37
…… based on PMI Standard
MODULE 7
MULTI-
PROJECTS
CONTROL
USING EVM
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
38
…… based on PMI Standard
MODULE 7
MULTI-
PROJECTS
CONTROL
USING EVM
Figure 26. Program planning in MS Project
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
39
…… based on PMI Standard
MODULE 7
MULTI-
PROJECTS
CONTROL
USING EVM
1 765432 1098 1211
13
Figure 27. Program EVM report
shipyardpm@gmail.com
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS
4
0
IF YOU ARE INTERESTED FOR AN ON-SITE TRAINING FOR
ONE OF THE MODULES OR THE ENTIRE COURSE /
WORKSHOP JUST CONTACT ME:
shipyardpm@gmail.com
shipyardpm@gmail.com

More Related Content

What's hot

Loksa Shipyard presentation
Loksa Shipyard presentationLoksa Shipyard presentation
Loksa Shipyard presentationLoksaShipyard
 
Shell and deck plating
Shell and deck platingShell and deck plating
Shell and deck platingCorrodere
 
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEA
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEADESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEA
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEAEagle .
 
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIEnergy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIMohammud Hanif Dewan M.Phil.
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project managementPartha Chakraborty
 
Shipyard Project Management Book - Pictures from reader around the world
Shipyard Project Management Book - Pictures from reader around the worldShipyard Project Management Book - Pictures from reader around the world
Shipyard Project Management Book - Pictures from reader around the worldFernando Remolina, PMP
 
Design of a 20,000 t double acting ice class general cargo ship of service ...
Design of a 20,000 t double acting ice class general cargo ship   of service ...Design of a 20,000 t double acting ice class general cargo ship   of service ...
Design of a 20,000 t double acting ice class general cargo ship of service ...Md. Ashifur Rahaman
 
Continuous machinery survey
Continuous machinery surveyContinuous machinery survey
Continuous machinery surveyViktor Bily
 
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu sajiSHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu sajiJishnu Saji
 
Ship Building (parts of ship)
Ship Building (parts of ship)Ship Building (parts of ship)
Ship Building (parts of ship)Abood Mohgazy
 
[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particularsSyaifullah Hamim
 
MOORING STATIONS - FOR MARITIME CADETS
MOORING STATIONS -    FOR MARITIME  CADETSMOORING STATIONS -    FOR MARITIME  CADETS
MOORING STATIONS - FOR MARITIME CADETSCapt.Vivek Trivedi
 

What's hot (20)

Loksa Shipyard presentation
Loksa Shipyard presentationLoksa Shipyard presentation
Loksa Shipyard presentation
 
Shell and deck plating
Shell and deck platingShell and deck plating
Shell and deck plating
 
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEA
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEADESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEA
DESIGN AND ANALYSIS OF COMPOSITE PROPELLER/DRIVEN SHAFT USING FEA
 
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIEnergy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project management
 
Shipyard Project Management Book - Pictures from reader around the world
Shipyard Project Management Book - Pictures from reader around the worldShipyard Project Management Book - Pictures from reader around the world
Shipyard Project Management Book - Pictures from reader around the world
 
Small angle stability longitudinal
Small angle stability longitudinal Small angle stability longitudinal
Small angle stability longitudinal
 
Hsl project
Hsl projectHsl project
Hsl project
 
Ship resistance in confined water
Ship resistance in confined waterShip resistance in confined water
Ship resistance in confined water
 
Motion Response Project pdf
Motion Response Project pdfMotion Response Project pdf
Motion Response Project pdf
 
Proyecto y producción de buques petroleros
Proyecto y producción de buques petrolerosProyecto y producción de buques petroleros
Proyecto y producción de buques petroleros
 
Design of a 20,000 t double acting ice class general cargo ship of service ...
Design of a 20,000 t double acting ice class general cargo ship   of service ...Design of a 20,000 t double acting ice class general cargo ship   of service ...
Design of a 20,000 t double acting ice class general cargo ship of service ...
 
Continuous machinery survey
Continuous machinery surveyContinuous machinery survey
Continuous machinery survey
 
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu sajiSHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
 
Ship Construction by Jayan Pillai
Ship Construction by Jayan PillaiShip Construction by Jayan Pillai
Ship Construction by Jayan Pillai
 
Ship Building (parts of ship)
Ship Building (parts of ship)Ship Building (parts of ship)
Ship Building (parts of ship)
 
Thesis defense
Thesis defenseThesis defense
Thesis defense
 
Structural Design of Drill Ships
Structural Design of Drill ShipsStructural Design of Drill Ships
Structural Design of Drill Ships
 
[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars[5] ptk 2014 2015 ship main particulars
[5] ptk 2014 2015 ship main particulars
 
MOORING STATIONS - FOR MARITIME CADETS
MOORING STATIONS -    FOR MARITIME  CADETSMOORING STATIONS -    FOR MARITIME  CADETS
MOORING STATIONS - FOR MARITIME CADETS
 

Similar to PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

Formal Project Management and Lean Manufacturing as tools to solve some today...
Formal Project Management and Lean Manufacturing as tools to solve some today...Formal Project Management and Lean Manufacturing as tools to solve some today...
Formal Project Management and Lean Manufacturing as tools to solve some today...Michele Lauriero
 
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesRussell Archibald
 
Pm0010 – introduction to project management
Pm0010 – introduction to project managementPm0010 – introduction to project management
Pm0010 – introduction to project managementsmumbahelp
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process Charles Cotter, PhD
 
Pm0010 – introduction to project management
Pm0010 – introduction to project managementPm0010 – introduction to project management
Pm0010 – introduction to project managementsmumbahelp
 
Project Management For Shipyards (professional corporate education plan)
Project Management For Shipyards (professional corporate education plan)Project Management For Shipyards (professional corporate education plan)
Project Management For Shipyards (professional corporate education plan)Michele Lauriero
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
Ignite_VR Course Guide
Ignite_VR Course GuideIgnite_VR Course Guide
Ignite_VR Course GuideCameron
 
Certified Quality Project Management
Certified Quality Project ManagementCertified Quality Project Management
Certified Quality Project ManagementDigiLEAF Inc
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmoErin Jones
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and ProcessCharles Cotter, PhD
 
Agility : a Velvet Glove in an Iron FIst
Agility : a Velvet Glove in an Iron FIstAgility : a Velvet Glove in an Iron FIst
Agility : a Velvet Glove in an Iron FIstHSBC Private Bank
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
Project Management for Training - Class 2
Project Management for Training - Class 2Project Management for Training - Class 2
Project Management for Training - Class 2Jeffrey Keefer
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overviewhouserdah
 

Similar to PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop (20)

Formal Project Management and Lean Manufacturing as tools to solve some today...
Formal Project Management and Lean Manufacturing as tools to solve some today...Formal Project Management and Lean Manufacturing as tools to solve some today...
Formal Project Management and Lean Manufacturing as tools to solve some today...
 
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
 
Pm0010 – introduction to project management
Pm0010 – introduction to project managementPm0010 – introduction to project management
Pm0010 – introduction to project management
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
 
Pm0010 – introduction to project management
Pm0010 – introduction to project managementPm0010 – introduction to project management
Pm0010 – introduction to project management
 
Project Management For Shipyards (professional corporate education plan)
Project Management For Shipyards (professional corporate education plan)Project Management For Shipyards (professional corporate education plan)
Project Management For Shipyards (professional corporate education plan)
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Pmo
PmoPmo
Pmo
 
PM FrameWork: Module 1
PM FrameWork: Module 1PM FrameWork: Module 1
PM FrameWork: Module 1
 
Ignite_VR Course Guide
Ignite_VR Course GuideIgnite_VR Course Guide
Ignite_VR Course Guide
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
 
Certified Quality Project Management
Certified Quality Project ManagementCertified Quality Project Management
Certified Quality Project Management
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
 
Agility : a Velvet Glove in an Iron FIst
Agility : a Velvet Glove in an Iron FIstAgility : a Velvet Glove in an Iron FIst
Agility : a Velvet Glove in an Iron FIst
 
20130411 velvet gloveagile
20130411 velvet gloveagile20130411 velvet gloveagile
20130411 velvet gloveagile
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Project Management for Training - Class 2
Project Management for Training - Class 2Project Management for Training - Class 2
Project Management for Training - Class 2
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overview
 

Recently uploaded

Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...afaqsaeed463
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 

Recently uploaded (17)

Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...self respect is very important in this crual word where everyone in just thin...
self respect is very important in this crual word where everyone in just thin...
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 

PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

  • 1. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 1 COURSE / WORKSHOP PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS shipyardpm@gmail.com
  • 2. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 2 COURSE / WORKSHOP OBJECTIVE To provide Shipyard Project Managers and Shipyard personnel with project management tools for planning and controlling projects, using recognized project management standards applied on ship repair industry. Through this course learning experience will be improved by practicing concepts through a real-world ship repair project. “This will increase the chance of success on your projects” shipyardpm@gmail.com
  • 3. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 3 • Module 0. Project Management Standards and overview (1 hour): Definition of Project Management. Project Management Standards, Knowledge Areas and Process groups. Project Management in Shipyard industry overview. • Module 1. WBS for Ship Repair Projects – (4 hours): What is a WBS?. Components of a WBS. Steps to create a WBS for a ship repair project. WBS top 4 Benefits in Ship Repair industry. WBS Manual exercise. Create the WBS for project QUEEN ANDREA using a WBS software. • Module 2. Critical Path / Ms Project for Ship Repair Projects – (4 to 5 hours): Basic concepts for project scheduling. What is critical path? How to use it in Ship Repair Projects. Critical path Top 5 benefits. Aspects on which the Ship Repair Project Manager should focus in project scheduling. Critical Path Exercise. Steps to Create a project schedule in Ms Project. How to monitor the schedule in Ms Project. Schedule Accuracy level in ship repair projects based on uncertainty. Create the project schedule for project QUEEN ANDREA using Ms Project. COURSE / WORKSHOP CONTENT shipyardpm@gmail.com
  • 4. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 4 • Module 3. Time and Cost Control with EVM Ship Repair Projects – (4 to 5 hours): What is EVM?. EVM formulas (Variance, KPIs and Forecast). How to use EVM in Ship Repair Projects to control cost and time (calculations and reports). Relationship between the WBS, Project Schedule (Ms Project) and EVM. Use EVM calculations and reports for the project QUEEN ANDREA. • Module 4. Risk Management in Ship Repair Projects – (4 hours): What is Risk Management?. Steps for risk management in ship repair projects. Understanding the Risk Register and Risk Assessment Matrix for Ship Repair Projects. Apply Risk Management for project QUEEN ANDREA. • Module 5. Stakeholders Management in Ship Repair Projects – (4 hours): What is Stakeholder Management?. Identify and analyze ship repair stakeholders. Manage ship repair stakeholders engagement. Identify and analyze stakeholders for project QUEEN ANDREA. COURSE / WORKSHOP CONTENT shipyardpm@gmail.com
  • 5. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 5 • Module 6. Ship Repair Project Manager Soft Skills (1 to 2 hours): The 3 propeller blades of knowledge for the Ship Repair Project Manager. Recognized Project Management Certifications. Coordination skills. Overview on negotiation skills. • Module 7. Multi-Projects (Program) Control using Ms-Project and EVM (3 to 4 hours): What is Multi-Project / Program Management in the ship repair industry. Planning the Program. Controlling the Program. The benefits of controlling the program. Then need of a Program or Project Management Manager in the ship repair industry. Practical exercise using Ms Project and EVM COURSE / WORKSHOP CONTENT shipyardpm@gmail.com
  • 6. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 6 COURSE / WORKSHOP METHODOLOGY The course / workshop methodology is based on “experiential learning”. Theory + subject specific exercise + real-world ship repair project practice MV “QUEEN ANDREA” IMO number: 0000000 Length Overall: 250 m Breadth: 40.06 m Gross Tonnage: 120.000 Vessel Type: Tanker shipyardpm@gmail.com
  • 7. 6th March 2017 BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 7 COURSE / WORKSHOP FOUNDATION • PMBOK guide from PMI • My upcoming book “Shipyard Project Management” Coming soon May 2017 shipyardpm@gmail.com
  • 8. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 8 EDUCATIONAL BACKGROUND • Industrial Engineer • Post Graduate - Diploma in Project Management • Project Management for Engineering projects course from Delft University • Certified as Project Management Professional - PMP by the Project Management Institute (PMI) since 2011. EXPERIENCE • 10 years of experience in the industry • Positions held: Project Manager, Risk Engineer, Production Superintendent (Shipbuilding), Marine Maintenance Supervisor. • 6 years of experience using PMI Standard in Ship Repair Projects • Author and speaker about Project Management focused on Ship Repair 6th March 2017shipyardpm@gmail.com
  • 9. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 9 …… based on PMI Standard MODULE 0 PROJECT MANAGEMENT STANDARDS AND OVERVIEW “….What is Project Management about? Project Management is about how to organize yourself, your team and your project….” PMBOK - PMI APMBOK - APM PRINCE2 - AXELOS shipyardpm@gmail.com
  • 10. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 1 0 …… based on PMI Standard MODULE 0 PROJECT MANAGEMENT STANDARDS AND OVERVIEW EXISTING PROJECT MANAGEMENT WAY OF THINKING IN SHIPREPAIR INDUSTRY OLD FASHIONED MANAGEMENT STYLE QUALITYMANAGEMENT HUMANRESOURCEMANAGEMENT COMMUNICATIONMANAGEMENT RISKMANAGEMENT PROCUREMENTMANAGEMENT STAKEHOLDERMANAGEMENT Cost ScopeTime SHIPS TECHNICAL KNOWLEDGE PROJECT MANAGEMENT STANDARDS SUSTAINIBILITY THE CORRECT WAY TO MANAGE SHIPREPAIR PROJECTS shipyardpm@gmail.com
  • 11. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 11 …… based on PMI Standard IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com MODULE 0 PROJECT MANAGEMENT STANDARDS AND OVERVIEW shipyardpm@gmail.com
  • 12. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 1 2 …… based on PMI Standard MODULE 1 WBS – WORK BREAKDOWN STRUCTURE APPLIED TO SHIP REPAIR PROJECTS shipyardpm@gmail.com
  • 13. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 1 3 …… based on PMI Standard MODULE 1 WBS – WORK BREAKDOWN STRUCTURE APPLIED TO SHIP REPAIR PROJECTS Vessel Location / Deliverable Work Packages Main Deliverable or Project Figure 13. WBS example 1 1.1 1.1.1 1.2 1.1.2 1.2.1 LEVEL 1 LEVEL 2 LEVEL 3 WBS COMPONENTS • Deliverable: is what we are going to deliver, either a service or a product requested by the client. • Work package: is the lowest level of decomposition. As from the work packages you can define the activities • ID number: is the number located on each component for easy identification • Level of decomposition: is related how deep you decompose each element shipyardpm@gmail.com
  • 14. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 14 …… based on PMI Standard MODULE 1 WBS – WORK BREAKDOWN STRUCTURE APPLIED TO SHIP REPAIR PROJECTS HOW TO CREATE AND USE A WBS FOR SHIP REPAIR PROJECTS STEP 1. Collect input documents STEP 2. Divide ship per locations and systems STEP 3. Define the software to be used STEP 4. Create the WBS shipyardpm@gmail.com
  • 15. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 15 …… based on PMI Standard MODULE 1 WBS – WORK BREAKDOWN STRUCTURE APPLIED TO SHIP REPAIR PROJECTS shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 16. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 16 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT CRITICAL PATH – MS PROJECT shipyardpm@gmail.com
  • 17. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 17 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT CRITICAL PATH METHOD Critical Path is the longest path from the beginning to the end of the project. A path is a sequence of activities in a certain time frame and the longest path is the one leading the finish of the project shipyardpm@gmail.com
  • 18. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 18 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT IN WHAT ASPECTS THE SHIPREPAIR PROJECT MANAGER SHOULD FOCUS WHILE PLANNING AND CONTROLLING THE PROJECT SCHEDULE? shipyardpm@gmail.com
  • 19. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 19 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT STEPS TO CREATE A SCHEDULE IN MS-PROJECT Transfer WBS information into MS PROJECT Adjust initial settings: Calendar and Project start date Define activities and milestones Define activity duration and sequence the activities Calculate the critical path Save baseline 1 2 3 5 6 4 shipyardpm@gmail.com
  • 20. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 20 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT STEPS TO CREATE A SCHEDULE IN MS-PROJECT Define activity duration and sequence the activities4 shipyardpm@gmail.com
  • 21. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 21 …… based on PMI Standard MODULE 2 CRITICAL PATH – MS PROJECT shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 22. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 22 …… based on PMI Standard MODULE 3 TIME AND COST CONTROL WITH EVM shipyardpm@gmail.com
  • 23. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 23 …… based on PMI Standard MODULE 3 TIME AND COST CONTROL WITH EVM Project information Project estimates: Price / MH / Materials / Contractor invoice price / Contractor prices / SC % margin Monitoring dates: PV, EV, AC, Variance for Man hours and Materials Jobs description + Control account Totals: Revenues, MH, Materials, Subcontractors Totals per date: PV, EV, AC, Variance for MH and Materials shipyardpm@gmail.com
  • 24. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 24 …… based on PMI Standard MODULE 3 TIME AND COST CONTROL WITH EVM shipyardpm@gmail.com
  • 25. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 25 …… based on PMI Standard MODULE 3 TIME AND COST CONTROL WITH EVM shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 26. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 26 …… based on PMI Standard MODULE 4 RISK MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com
  • 27. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 27 …… based on PMI Standard MODULE 4 RISK MANAGEMENT FOR SHIP REPAIR PROJECTS STEPS FOR PROJECT RISK MANAGEMENT IN SHIP REPAIR PROJECTS 1. Identify Risks: Once the scope is known a risk identification can be performed. Risk can be identified during project initiation till the end. This are the most important aspects to consider when you are identifying Risk and Causes: • The Risks must be identified based on the Project Objectives • The Risks cannot be a constraint (a constraint is something that already exists and should be responded with a contingency plan) • When the risk is going to be identified you should ask yourself: What can go wrong that can impact the project objectives? • The cause of the risk could be a constraint, an assumption, requirement or condition that originates the unwanted or wished event. Example 1: Lack of man power, due to interference with other projects, impacting undocking date and departure date. Example 2: To not finish Hull blasting on planned date, due to extreme weather conditions on April, impacting dry-docking time of the vessel shipyardpm@gmail.com
  • 28. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 28 …… based on PMI Standard MODULE 4 RISK MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com
  • 29. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 29 …… based on PMI Standard MODULE 4 RISK MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 30. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 30 …… based on PMI Standard MODULE 5 STAKEHOLDER MANAGEMENT FOR SHIP REPAIR PROJECTS STAKEHOLDER MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com
  • 31. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 31 …… based on PMI Standard MODULE 5 STAKEHOLDER MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com Stakeholder Identification
  • 32. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 32 …… based on PMI Standard MODULE 5 STAKEHOLDER MANAGEMENT FOR SHIP REPAIR PROJECTS Figure 12. Stakeholders Analysis Matrix shipyardpm@gmail.com Stakeholder Analysis Matrix
  • 33. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 33 …… based on PMI Standard MODULE 5 STAKEHOLDER MANAGEMENT FOR SHIP REPAIR PROJECTS shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 34. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 34 …… based on PMI Standard MODULE 6 SOFT SKILLS FOR SHIPREPAIR PROJECT MANAGERS Project Management TechnicalBusiness shipyardpm@gmail.com
  • 35. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 35 …… based on PMI Standard MODULE 6 SOFT SKILLS FOR SHIPREPAIR PROJECT MANAGERS shipyardpm@gmail.com
  • 36. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 36 …… based on PMI Standard MODULE 6 SOFT SKILLS FOR SHIPREPAIR PROJECT MANAGERS shipyardpm@gmail.com IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME shipyardpm@gmail.com
  • 37. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 37 …… based on PMI Standard MODULE 7 MULTI- PROJECTS CONTROL USING EVM shipyardpm@gmail.com
  • 38. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 38 …… based on PMI Standard MODULE 7 MULTI- PROJECTS CONTROL USING EVM Figure 26. Program planning in MS Project shipyardpm@gmail.com
  • 39. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 39 …… based on PMI Standard MODULE 7 MULTI- PROJECTS CONTROL USING EVM 1 765432 1098 1211 13 Figure 27. Program EVM report shipyardpm@gmail.com
  • 40. BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 4 0 IF YOU ARE INTERESTED FOR AN ON-SITE TRAINING FOR ONE OF THE MODULES OR THE ENTIRE COURSE / WORKSHOP JUST CONTACT ME: shipyardpm@gmail.com shipyardpm@gmail.com