SlideShare a Scribd company logo
PUBLIC WORKS ROAD DEPARTMENT
Construction Supervision Consultancy Services for Improvement
and Upgradation of Road under ASRIP funded by Asian
Infrastructure Investment Bank
MONTHLY PROGRESS REPORT
(OCTOBER 2022)
Construction Supervision Consultant (CSC)
Dohwa Engineering Co. Ltd.
in JV with
MaRS Planning and Engineering Services Private Limited.
Submitted By
EXECUTIVE SUMMARY
Sl
No. Road
Project
Length
Cost of
Project
Construction
Period+ Defect
Notification
Period
Salient Features Milestone Dates Work Contract Details
Km (Rs. In Cr.) Month
1
Dhakuakhana
Butikur Tiniali Telijan
( Dhakuakhana to
Telijan )
A22
32.73 146.33 30+60
Earthwork
GSB/WMM
DBM
BC
Major Bridges
Minor Bridges
Culverts
RCC Drain
11,87,323.96 m3
2,19,690.71 m3
27,311.50 m3
15,527.37 m3
-
1 Nos.
20 Nos.
2.60 Km.
Date of Commencement : 18.04.2022
Milestone I 365 Days : 18.04.2023
Milestone II 548 Days : 18.10.2023
Milestone III 913 Days : 18.10.2024
Contract No. :
CE/ASRIP/09/2021/48
Name of Contractor :
Shivam-Bhartia (JV)
2
Dhodar Ali (
Kamargaon to
Kaamarbandha)
A15
42.09 304.19 30+60
Earthwork
GSB/WMM
DBM
BC
EUP
Minor Bridges
Culverts
RCC Drain
12,94,046.40 m3
2,50,494.17 m3
34,045.12 m3
19,578.98 m3
2 Nos.
1 Nos.
95 Nos.
5.15 Km.
Date of Commencement : 18.04.2022
Milestone I 365 Days : 18.04.2023
Milestone II 548 Days : 18.10.2023
Milestone III 913 Days : 18.10.2024
Contract No. :
CE/ASRIP/10/2021/28
Name of Contractor :
SGCCL-ANPL (JV)
3
Sarthebari Pathsala
Raipur Road
A07
17.65 114.01 24+60
Earthwork
GSB/WMM
DBM
BC
Major Bridges
Minor Bridges
Culverts
RCC Drain
4,20,439.00 m3
97,000.00 m3
11,747.00 m3
7,831.00 m3
1 Nos.
-
32 Nos.
9.172 Km.
Date of Commencement : 18.04.2022
Milestone I 365 Days : 18.04.2023
Milestone II 547 Days : 18.10.2023
Milestone III 730 Days : 18.04.2024
Contract No. :
CE/ASRIP/11/2021/41
Name of Contractor :
Shivam-Bhartia (JV)
EXECUTIVE SUMMARY
Sl
No. Road
Project
Length
Cost of
Project
Construction
Period+ Defect
Notification
Period
Salient Features Milestone Dates Work Contract Details
Km (Rs. In Cr.) Month
4
Moran Naharkatia
Duliajan Digboi
( Moran to Deesang
Kinar Bangali)
A30_1
46.60 215.44 30+60
Earthwork
GSB/WMM
DBM
BC
Major Bridges
Minor Bridges
Culverts
RCC Drain
8,72,420.25 m3
2,64,931.23 m3
35,075.60 m3
19,499.93 m3
-
2 Nos.
55 Nos.
8.912 Km.
Date of Commencement : 18.04.2022
Milestone I 365 Days : 18.04.2023
Milestone II 548 Days : 18.10.2023
Milestone III 913 Days : 18.10.2024
Contract No. :
CE/ASRIP/12/2021/31
Name of Contractor :
SGCCL-ANPL (JV)
5
Moran Naharkatia
Duliajan Digboi
( Deesang Kinar
Bangali to
Kathalguri)
A30_2
23.98 30+60
6
Sivasagar to
Chumoni
A20_1
18.42 121.09 24+60
Earthwork
GSB/WMM
DBM
BC
Major Bridges
Minor Bridges
Culverts
RCC Drain
9,55,671.61 m3
1,02,786.68 m3
19,069.82 m3
7,572.27 m3
-
1 Nos.
13 Nos.
8.52 Km.
Date of Commencement : 19.04.2022
Milestone I 306 Days : 19.02.2023
Milestone II 456 Days : 19.07.2023
Milestone III 730 Days : 19.04.2024
Contract No. :
CE/ASRIP/14/2021/29
Name of Contractor : S&P
- SHIVA (JV)
7
Sivasagar to
Nakachari to
Balighat Tiniali)
A20_2
45.00 30+60
S- CURVE SHOWING PROGRESS OF WORK
PROJECT TARGET VS ACHIEVEMENT
Construction Supervision Consultancy Services for ASRIP
TARGET Vs ACHIEVEMENT STATUS Upto 31
st
October, 2022 ( As per Contractors Work Programme )
Sl.
N
o.
DP
R
No.
Pk
g.
No.
Contrac
t Price
Cumulative till September, 2022 Month October,2022 Cumulative upto 31
st
October, 2022
Remarks
Target (
Based on
Work
Program
me)
Achievem
ent
Achievem
ent w.r.t.
Target
(Col.2)
Achievem
ent w.r.t.
Contract
Price
(Col.1)
Target
for the
Month -
October
2022
Achievem
ent for the
Month
upto 31
st
October,
2022
%age
Achievem
ent w.r.t.
Monthly
Target
Target
Achievem
ent
Achievem
ent w.r.t.
Cumulativ
e Target
(Col.9)
Achievem
ent w.r.t.
Contract
Price
(Col.1)
(Rs. In
Cr.)
(Rs. In
Cr.)
(Rs. In Cr.) (%) (%)
(Rs. In
Cr.)
(Rs. In Cr.) (%)
(Rs. In
Cr.)
(Rs. In Cr.) (%) (%)
(a) (b) (c ) 1 2 3 4=3/2 5=3/1 6 7 8=7/6 9=2+6 10=3+7 11=10/9 12=10/1 13
1
A22
RI-
02
146.33 1.66 0.00 0.00 0.00 2.94 0.00 0.00 4.60 0.00 0.00 0.00
In Preliminary
Stage
2
A15
RI-
03
304.19 1.82 0.00 0.00 0.00 5.48 0.00 0.00 7.30 0.00 0.00 0.00
In Preliminary
Stage
3
A07
RI-
04
114.01 2.20 0.00 0.00 0.00 2.30 0.00 0.00 4.50 0.00 0.00 0.00
Culvert
Started
4
A30
-1
RI-
05
215.44 1.08 0.00 0.00 0.00 1.81 0.00 0.00 2.89 0.00 0.00 0.00
In Preliminary
Stage
5
A-
20_
1
RI-
07
121.01 3.98 0.00 0.00 0.00 5.28 0.00 0.00 9.26 0.00 0.00 0.00
In Preliminary
Stage
PHYSICAL & FINANCIAL PROGRESS OF PROJECT
Physical progress (as per C.A. BOQ)
= 00.10%
Financial progress (as per C.A. BOQ)
= 00.00%
A-22 A-15 A-07 A-30_1 A-20_1 Total
Upto
Sept-22
Upto
Date
1 Earthwork % 0.95 1.50 2.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 GSB % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 WMM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 DBM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 BC % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Culverts % 0.20 0.40 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10
7 RCC Drains % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 Foundation % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9 Substructure % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 Superstructure % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Protection Work % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 Approaches % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 Miscellaneous % 0.04 0.08 0.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Cumm.
Physical
Progress
%
Sr. No.
Key Items of
Work
Unit
Target
Upto
Date
This Month Qty. Financial Progress
Target
Upto
Sept.-
22
Target
for
Oct-22
PHYSICAL PROGRESS OF ROAD WORK
Sr. No.
Key Items of
Work
Unit Upto
Sept-22
Target for
Oct-22 Target
Upto Date
This Month Physical Progress Physical Progress
A-22 A-15 A-07 A-30_1 A-20_1 This Month
Upto
Sept-22
Upto
Date
1 Earthwork % 0.95 1.50 2.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 GSB % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 WMM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 DBM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 BC % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Culverts % 0.20 0.40 0.60 0.00 0.00 0.10 0.00 0.00 0.00 0.10 0.10
7 RCC Drains % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.45%
0.00%
0.00%
0.00%
0.00%
0.60%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.10%
0.00%
0.00% 0.50% 1.00% 1.50% 2.00% 2.50% 3.00%
Earthwork
GSB
WMM
DBM
BC
Culverts
RCC Drains
Achieve
d
Progress in Percentage (%)
PHYSICAL PROGRESS OF STRUCTURE WORK
Sl. No.
Package
No.
Name of Road Section
TYPE OF STRUCTURES
MAJOR BRIDGE / EUP MINOR BRIDGE BOX CULVERTS GRAND TOTAL
Total
Nos.
Completed Balance
Total
Nos.
Completed Balance
Total
Nos.
Completed Balance
Total
Nos.
Completed Balance
1 A22 Dhakuakhana to Telijan 0 NA NA 1 0 1 20 0 20 21 0 21
2 A15
Kamargaon to
Kamaarbandha
2 0 2 1 0 1 95 0 95 98 0 98
3 A07 Sarthebari to Pathsala 1 0 1 0 NA NA 32 3 29 33 3 30
4 A30_1 Moran Naharkatia 0 NA NA 2 0 2 55 0 55 57 0 57
5 A30_2 Moran Kathalguri
6 A20_1 Sivasagar Chumoni 0 NA NA 1 0 1 13 0 13 14 0 14
7 A20_2 Sivasagar Tiniali
DRAWING APPROVAL STATUS
PLAN &
PROFILE
1 Dhakuakhana to Telijan Road (A22) 32.675 - - 32.675
2 Kamargaon to Kamarbandha Road (A15) 42.094 8.000 - 42.094
3 Sarthebari to Pathsala Road (A07) 17.653 - - 17.653
4 Moran to Naharkatia Road (A30-1) 46.581 9.000 - 46.581
5 Sivasagar to Chumoni Road (A20-1) 18.416 - - 18.416
Balance
L
ength (Km.)
Drawing
S
ubmission
(Km.)
S
r. No. Name of Project
Total L
ength
(Km.)
Approved
L
ength (Km.)
DRAWING APPROVAL STATUS
STRUCTURE & MISCELLANEOUS DRAWINGS
Total
Drawing
Submission
Approved Balance
(Nos) (Nos) (Nos) (Nos)
BOX CULVERT DRAWINGS
1 Dhakuakhana to Telijan Road (A22) 20 - - 20
2 Kamargaon to Kamarbandha Road (A15) 95 69 14 81
3 Sarthebari to Pathsala Road (A07) 32 7 7 25
4 Moran to Naharkatia Road (A30-1) 55 36 - 55
5 Sivasagar to Chumoni Road (A20-1) 13 - - 13
MINOR BRIDGE DRAWINGS
1 Dhakuakhana to Telijan Road (A22) 1 - - 1
2 Kamargaon to Kamarbandha Road (A15) 1 - - 1
3 Sarthebari to Pathsala Road (A07) NA - NA NA
4 Moran to Naharkatia Road (A30-1) 2 - - 2
5 Sivasagar to Chumoni Road (A20-1) 1 - - 1
EUP/MAJOR BRIDGE DRAWINGS
1 Dhakuakhana to Telijan Road (A22) NA - NA NA
2 Kamargaon to Kamarbandha Road (A15) 2 2 - 2
3 Sarthebari to Pathsala Road (A07) 1 - - 1
4 Moran to Naharkatia Road (A30-1) NA - NA NA
5 Sivasagar to Chumoni Road (A20-1) NA - NA NA
JUNCTION DEVELOPMENT DRAWINGS
1 Dhakuakhana to Telijan Road (A22)
2 Kamargaon to Kamarbandha Road (A15)
3 Sarthebari to Pathsala Road (A07)
4 Moran to Naharkatia Road (A30-1)
5 Sivasagar to Chumoni Road (A20-1)
Sr. No. Name of Project
MIX DESIGN APPROVAL STATUS
1. Dhakuakhana To Telijan Road (RI-02) : No Progress on Mix Design till date.
2. Kamargaon To Kamarbandha (RI-03) : Trial Mix Done for M-15, M-20 & M-30 Respectively,
Results not Submitted till date.
3. Sarthebari To Pathsala Road (RI-04) : Mix Design Reports submitted for M-15, M-20, M-30
(20 MSA), M-30 (40 MSA), M-35 (20 MSA) & M-35
(40 MSA).
Comments given by CSC on 24-09-2022
Compliance of Contractor on 09-10-2022
Status : Under Review.
4. Moran To Naharkatia Road ( RI-05) : Mix Design for GSB, M-15, M-20 & M-30 in Progress.
5. Sivasagar To Chumoni Road ( RI-07) : No Progress on Mix Design till date.
STATUS OF APPROVAL OF CONSTRUCTION
MATERIAL
Sr. No.
Name of
Material
Location of Source
Proposal
submission
date
AE Comments
Compliance of
contractor
Approval date Remark
1 Stone Subans iri river - - - -
Tes ting in Third party lab is
in progres s .
1 Soil
Km 23+700 (700m from
the exis ting road)
- - - - Tes ting is in progres s .
1 Sika
M/S AKJ Engineers
Private Limited
- - - -
Tes ting in Third party
laboratory is in progres s .
1 Topcem
Meghalaya cement
limited
- - - -
Tes ting in Third party
laboratory is in progres s .
1
Balaji Shakti
TMT
Durgapur, West Bengal - - - -
Credentials s ubmitted by
the Contractor on
17.10.2022.
1 Water
Bore well at Bas e camp
at km 24+000 RHS
- - - -
Tes ting in Third party
laboratory is in progres s .
Soil
Soil
Soil
ADMIXTURE/CURING COMPOUND
CEMENT
FLY ASH
STEEL
Water
Tes ting is in progres s .
4
Km 24+030 (3500m from
the exis ting road)
- - - - Tes ting is in progres s .
3
Km 24+030 (3600m from
the exis ting road)
- - - -
Dhakuakhana to Telijan Road (A22)
QUARRY
BORROW AREA
2
Km 23+700 (500m from
the exis ting road)
- - - - Tes ting is in progres s .
STATUS OF APPROVAL OF CONSTRUCTION
MATERIAL
Sr. No.
Name of
Material
Location of Source
Proposal
submission
date
AE Comments
Compliance of
contractor
Approval date Remark
1
Quarry for
Aggregate,
40mm,
20mm,10mm
Karbi Anglong 20.09.2022 17.10.2022 Approved
Vashudha,
Kokata
Meghalaya Cement Ltd.
Shilong
2 Dalmia Lanka- Hojai 21.07.2022 Under review by CSC
1
SHYAM Steel
Industries
Durgapur, WB 25.08.2022 24.09..2022 Approved
1 Water Base camp 22+100 25.08.2022 Under review by CSC
Dishala marketing Pvt.
Ltd. Lokhara Rd.
Guwahati
Water
FLY ASH
STEEL
2 JSPL 25.08.2022 24.09.2022 Approved
Under review by CSC
CEMENT
1 Topcem 21.07.2022 19.08.2022 Approved
Kamargaon to Kamarbandha Road (A15)
QUARRY
BORROW AREA
ADMIXTURE/CURING COMPOUND
1 Hindcon 25.08.2022
STATUS OF APPROVAL OF CONSTRUCTION
MATERIAL
Sr. No.
Name of
Material
Location of Source
Proposal
submission
date
AE Comments
Compliance of
contractor
Approval date Remark
1 Stone Pall River(MB Crusher 07-06-2022 Approved
2 Sand Pall River(MB Crusher 07-06-2022 Approved
3 Sand Gravel Pall River(MB Crusher 07-06-2022 Approved
1 Soil
Batia Village at K.M-
3+500
24.09.2022
Letter issued
on dt.
26.09.2022
Compliences
submitted
dated.
11.10.2022
Under Review
1 Asian Paint Asian paint Ltd. 05-08-2022 30-08-2022 Approved
2 Sika Sika India Ltd. 06-08-2022 30-08-2022 Approved
1 Ramco The Ramco Cement Ltd. 07-06-2022 15-7-2022 Approved
2 Ultra Tech Ultratech Cement Ltd. 05-08-2022 30-08-2022 Approved
1 Shyam Steel 07-6-2022 30-8-2022 Approved
1 Water
Bore @ RMC Plant
12+450
10-10-2022 Under Review
CEMENT
FLY ASH
STEEL
WATER
Sarthebari to Pathsala Road (A07)
QUARRY
BORROW AREA
ADMIXTURE/CURING COMPOUND
STATUS OF APPROVAL OF CONSTRUCTION
MATERIAL
Sr. No.
Name of
Material
Location of Source
Proposal
submission
date
AE Comments
Compliance of
contractor
Approval date Remark
1 Aggregate Likabari Quarry 13-08-2022 12-09-2022 Approved
2 Aggregate Bihubar Quarry 13-08-2022 12-09-2022 Approved
3 Sand Buridihing River 13-08-2022 27-10-2022 Approved
1 SG & Emb soil Borrow Area 1 16-9-2022 24-09-2022 Approved
2
Embankment
Soil
Borrow Area 2 16-9-2022 24-09-2022 Approved
3
Embankment
Soil
Borrow Area 3 16-9-2022 Under Review
1 Fosroc 25-7-2022 Under Review
1 Ultra Tech Ultratech Cement Ltd. 18-7-2022 10-8-2022 Approved
2 Ramco The Ramco Cement Ltd. 18-07-2022 10-08-2022 Approved
3 Topcem Topcem Cement Ltd. 18-07-2022 19-08-2022 Approved
4 Dalmia Dalmia Cement Ltd. 18-07-2022 Under Review
1 TATA Steel 18-7-2022 24-9-2022 Approved
2 Shyam Steel 18-07-2022 24-09-2022 Approved
3 Jindal Steel 18-07-2022 24-09-2022 Approved
Water
QUARRY
BORROW AREA
ADMIXTURE/CURING COMPOUND
CEMENT
FLY ASH
STEEL
Moran to Naharkatia Road (A30-1)
STATUS OF APPROVAL OF CONSTRUCTION
MATERIAL
Sr. No.
Name of
Material
Location of Source
Proposal
submission
date
AE Comments
Compliance of
contractor
Approval date Remark
CEMENT
FLY ASH
STEEL
Water
Bearing
Sivasagar to Chumoni Road (A20-1)
QUARRY
BORROW AREA
ADMIXTURE/CURING COMPOUND
No Progress on Approval of Construction Material in this
Progress
STATUS OF MOBILIZATION OF KEY PERSONNEL BY
CONTRACTOR
Dhakuakhana- (A22) Golaghat(A15) Pathsala(A07) Moran(A30_1) Nazira(A20_1)
Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel
1 Project Manager Mr.DeepakSingha Mr.Banjit Das Mr.KamleshDeka Akbar Hussain Mr.Md.Sher AfghanKhan
2 Highway Engineer cumDeputy Project Manager - Mr.AlomHussain Mr.Vijaychandrakalita Mr.SamshoolHazarika -
3 Senior Highway Engineer Mr.PintuKumar - Mr.Mehmudur Rahman Mr.AbasDas -
4 MaterialcumQuality controlEngineer Mr.Bidyut BikashSaikia Mr.Biswajit Deori Mr.MuhhamadAli Mr.Rajeswar Doley -
5 LabTechnician Mr.DhaniPradhan
Mr.Achyot Deori
Mr.SagardeepNag
Mr.Nur Amin
Mr.SimanataHazarika
Mr.PritamBhuyan
-
6 Bridge/ StructuralEngineer Mr.JanakDeka - Mr.RashidulIslam
Mr.SitaramBarma
Mr.SidhartaDebnath
-
7 Quantity Surveyor cumPlanningEngineer Mr.LakhiGogoi Mr.PapuBoro - Mr.DaduMuniBorah -
8 Survey Engineer
Mr.Biswajit Dasand
Mr.Gunojit Bhuyan
Md.RaquibulIslam
Mr.MohanChutia
Mr.BrighuKumar
Mr.RiturajBonshi
Mr.MandipKonwar
Mr.Biswajit Adak
Mr.RajuKumar Das
9 Highway DesignEngineer - Mr.MannaDas Mr.ChandanDas - -
10 Environmental,Social,HealthandSafety Expert - - Mr.Gunajit Das Mr.RiyazHussain -
S. No. Position
STATUS OF MOBILIZATION OF PLANT & MACHINERY
Asper CA
Actual asper
site
Asper CA
Actual asper
site
Asper CA
Actual asper
site
Asper CA
Actual asper
site
Asper CA
Actual asper
site
Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos
1
Batch type Central Hot Mix
Plant
100-120 TPH 1 0 1 0 1 0 1 0 1 0
2
Paver finisher hydrostatic
with sensor control
100-120 TPH 2 0 2 0 2 0 2 0 2 0
3
Bitumen/ E
mulsion Pressure
distributor
1750 sqmper hour 1 0 2 0 1 0 1 0 1 0
4 Vibratory roller 8-10 Tonne static weight 3 1 3 1 3 0 3 2 3 0
5
Smooth Wheeled tandem
vibratory roller
8-10 tonnes 1 0 2 0 1 1 1 1 1 0
6 Pneumatic Tyred roller 12-15T 1 0 2 0 1 0 1 0 1 0
7 Motor Grader 3.35 blade 2 1 2 1 2 0 2 2 2 0
8 Hydraulic E
xcavator 0.9 cumbucket size 2 3 2 1 0 2 2 2 2 0
9
Batch type automatic
concrete batching Plant
static
75 cum/ hour 1 0 1 - 1 1 1 0 1 0
10 Tipper rigid axle 10 tonnes 5 0 8 15 5 4 5 7 5 0
11 Water tanker 10 KL 2 0 3 1 2 1 2 1 2 0
12 Air compressor 250 cfm 1 0 2 0 1 0 1 0 1 0
13 Mechanical broom 1250 sqmper hour 1 0 1 0 1 0 1 0 1 0
14 Transit Mixer 6 cum 5 1 8 0 5 2 5 0 5 0
15 Mobile Crushing Plant 30 TPH 1 0 2 0 1 0 1 0 1 0
16 Wet Mix Plant 75 TPH 1 1 1 0 1 0 1 1 1 0
17 Rotovator
Capacity to mix 25cm
depth of granular material
1 0 1 0 1 0 1 0 1 0
18 Mobile Maintenance unit
Truck-mounted with
provision of carrying
portable mechanized
equipment for routine
maintenance operations
1 0 1 0 1 0 1 1 1 0
Moran (A30_1) Nazira (A20_1)
S
.No.
E
quipment Type and
Characteristics
Minimum Capacity
Dhakuakhana (A22) Golaghat (A15) Pathsala (A07)
STATUS OF MOBILIZATION OF KEY PERSONNEL BY CSC
S.
No.
Position Name of the personnel Date of Joining
1 Team Leader cum Senior Highway Engineer Mr. VR. Ramanathan 09-06-2022
2 Senior Material cum Quality control Engineer Dr. Ravindranath Thakur 22-03-2022
3 Senior Quantity Surveyor Mr. Awadhesh Kumar Singh 18-04-2022
4 Senior Contract Specialist Mr. M. Sriniwas 03-06-2022
5 Senior Bridge Engineer - -
6 Bridge Design Engineer - -
7 Pavement Specialist Mr. Harikrishna Bhavsar 29-03-2022
8 Highway Design Engineer Mr. Nirupam Kumar Singh 04-04-2022
9 ESHS Expert - -
10 Road Safety Engineer Mr. Chandan Rajkhowa 29-03-2022
11 Resident Engineer-1 Mr. Anil Kumar panday 03-05-2022
12 Resident Engineer-2 Mr. Sunil Kumar Singh 18-04-2022
13 Resident Engineer-3 Mr. Harihar Sharan Singh 25-04-2022
14 Resident Engineer-4 Mr. Uttam Mendhi 22-03-2022
15 Resident Engineer-5 Mr. Ritesh Sinha 22-03-2022
16 Resident Engineer-6
STATUS OF PERMITS
Dhakuakhna (A22) Golaghat (A15) Pathsala (A07) Moran (A30_1) Nazira (A20_1)
1
Permission of the State Govt. for
extraction of bouldersfromquarry
Not submitted yet. Not submitted yet. Completed Not submitted yet. Not submitted yet.
2
Permission of village Panchayat
and Pollution Control Board for
installation of crushers
Not submitted yet. Not submitted yet. Completed Not submitted yet. Not submitted yet.
3 License for use of explosivesif any. Not submitted yet. Not submitted yet. NA Not submitted yet. Not submitted yet.
4
Permission of the State Govt. for
drawing water fromriver reservoir.
Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet.
5
License fromInspector of factories
or other competent authority for
setting up batching plant.
Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet.
6
Clearance of Pollution Control
Board for setting up Batching Plant.
Not submitted yet. Not submitted yet.
1. Completed
2. Under Process
Not submitted yet. Not submitted yet.
7
Clearance of village Panchayat
and Pollution Control Board for
Asphalt Plant.
Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet.
8
Permission of village Panchayat
and State Gov. for borrow earth.
Not submitted yet. Not submitted yet. Completed Submitted Not submitted yet.
9
Permission of forest department for
cutting of trees.
Not submitted yet. Not submitted yet. Under process Not submitted yet. Not submitted yet.
10
Any other permitsof clearances
required under applicable laws.
Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet.
S. No. Description
Status
MEASURES FOR ENVIRONMENTAL, SOCIAL AND
RESETTLEMENTS
S.
No.
Description Safeguard Measures Taken Remarks
1
2
3
4
5
REASONS FOR DELAY
S.
No.
Activity
Due Date as
per CA
Actual Date of
Completion
Delay in Days Reason for Delay
1 Acquisition of land. - - - -
2
Removal of hindrances
including private houses,
boundary walls, shops,
hotels, tea stalls etc. from
within the ROW
- - - -
3
Shifting of utilities including
the existing Electric
Poles/Lines from within the
ROW. Cutting of Trees from
within the ROW.
- - - -
4 Due to rainfalls - - - -
5
Submission of Drawing by
the Contractor
- - - -
WORK PROGRAM OF UPCOMING MONTH
1. Dhakuakhana To Telijan Road
(A22):
Target Qty
( Nov-22)
1 Embankment Cum 889388.4 0 81801.31 Nil
2 Subgrade Cum 292450.17 0 17932.03 Nil
3 Granular Sub-base Cum 108974.29 0 6692.18 Nil
4 WMM 1st Layer Cum 50858.21 0 Nil Nil
5 WMM 2nd Layer Cum 50858.21 0 Nil Nil
6 Dense Bituminous Macadam Cum 27311.5 0 Nil Nil
7 Bituminous Macadam Cum 15527.37 0 Nil Nil
8 Box Culverts (New/ Reconstruction) Nos 19 0 0 Nil
9 Minor Bridge Nos 1 0 0 Nil
10 Major Bridge Nos Nil 0 0 Nil
Targeted Physical
Progress (%)
Targeted Financial
Progress (%)
ROAD WORKS
7.09
STRUCTURE WORKS
Sl. No Item Description Unit Total
Completed up
to this month
Total Quantity
completion
WORK PROGRAM OF UPCOMING MONTH
2. Kamargaon To Kamarbandha Road
(A15) :
Target Quantity
(Nov-22)
1 Embankment Cum 8,91,025.06 0 4250 Nil
2 Subgrade Cum 2,42,941.24 0 Nil Nil
3 Granular Sub-base Cum 1,26,710.22 0 Nil Nil
4 WMM1st Layer Cum 61,891.98 0 Nil Nil
5 WMM2nd Layer Cum 61,891.98 0 Nil Nil
6 Dense Bituminous Macadam Cum 34,045.12 0 Nil Nil
7 Bituminous Macadam Cum 19,578.98 0 Nil Nil
8 BoxCulverts (New/ Reconstruction) Nos 95 0 0 Nil
9 EUP Nos 2 0 0 Nil
10 Minor Bridge Nos 1 0 0 Nil
Total Quantity
completion
Targeted Physical
Progress (%)
Targeted Financial
Progress (%)
ROAD WORKS
0.6
STRUCTUREWORKS
Sl. No Item Description Unit Total
Completed up
to this month
WORK PROGRAM OF UPCOMING MONTH
3. Sarthebari To Pathsala Road (A07) :
Sl. No Item Description Unit Total
Completed up
to this month
Target Quantity
(Nov-22)
Total Quantity
completion
Targeted Physical
Progress (%)
Targeted Financial
Progress (%)
1 Embankment Cum 254186 0 50500 50500 20%
2 Subgrade Cum 120155 0 2000 2000 2%
3 Granular Sub-base Cum 47414 0 Nil Nil
4 WMM1st Layer Cum 24806.5 0 Nil Nil
5 WMM2nd Layer Cum 24806.5 0 Nil Nil
6 Dense Bituminous Macadam Cum 11747 0 Nil Nil
7 Bituminous Macadam Cum 7831 0 Nil Nil
8 BoxCulverts (New/ Reconstruction) Nos 32 3 3 6 9%
9 Minor Bridge Nos 0 0 0 Nil Nill
10 Major Bridge Nos 1 0 Foundation Work Nil 4%
ROAD WORKS
1.78%
STRUCTUREWORKS
WORK PROGRAM OF UPCOMING MONTH
4. Moran To Naharkatia (A30_1) :
Sl. No Item Description Unit Total
Completed up
to this month
Target Quantity
(November'2022)
Total Quantity
completion
Targeted Physical
Progress (%)
Targeted Financial
Progress (%)
1 Embankment Cum 518596.51 0 37755 Nil 7%
2 Subgrade Cum 388766 0 24840 Nil 6%
3 Granular Sub-base Cum 139707.6 0 4757 Nil
4 WMM1st Layer Cum 62611.86 0 Nil Nil
5 WMM2nd Layer Cum 62611.86 0 Nil Nil
6 Dense Bituminous Macadam Cum 35075.6 0 Nil Nil
7 Bituminous Macadam Cum 19499.93 0 Nil Nil
8 BoxCulverts (New/ Reconstruction) Nos 55 0 4 Nil 7%
9 Minor Bridge Nos 5 0 0 Nil Nill
10 Major Bridge Nos 0 0 Foundation Work Nil Nill
ROAD WORKS
3.60%
STRUCTUREWORKS
WORK PROGRAM OF UPCOMING MONTH
5. Sivasagar To Chumoni Road (A20_1) :
Sl. No Item Description Unit Total
Completed up
to this month
Target Quantity
(Nov-22)
Total Quantity
completion
Targeted Physical
Progress (%)
Targeted Financial
Progress (%)
1 Embankment Cum 839264.37 0 37376.294 37376.294
2 Subgrade Cum 104419.23 0 4650.069 4650.069
3 Granular Sub-base Cum 54568.02 0 3747.107 3747.107
4 WMM Cum 48218.66 0 3069.872 3069.872
6 Dense Bituminous Macadam Cum 19069.82 0 814.547 814.547
7 Bituminous Macadam Cum 7572.27 0 446.978 446.978
8 BoxCulverts (New/ Reconstruction) Nos 13 0 0 0
9 Minor Bridge Nos 2 0 0 0
10 Major Bridge Nos Nil 0 0 0
ROAD WORKS
5.69%
6.9%
STRUCTUREWORKS
CORRESPONDENCE FOR THE MONTH OF OCT-22
Incoming:
Chief Engineer To Team Leader:
SL No Referance No Letter date Subject Address
1
2
Contractor To Team Leader:
S
LNo ReferanceNo Letter date S
ubject Address
1 SVM/ OC/ 4794 17.10.2022 Submis
s
ion of MPR-2022 Shivam Bharatia (JV) Dhakuakhana
2 SVM/ OC/ 4795 17.10.2022 Regarding Submis
s
ion of credential of Balaji Shakti TMT. Shivam Bharatia (JV) Dhakuakhana
3 SVM/ OC/ 4801 28.10.2022 Review of Reinforcement Steel Jai Balaji Indus
triesLtd Shivam Bharatia (JV) Dhakuakhana
4 SVM/ OC/ 4802 28.10.2022 Reques
t for Factory Vis
it of Reinforcement Steel Jai Balaji Indus
triesLtd Shivam Bharatia (JV) Dhakuakhana
5 SVM/ OC/ 4798 26.10.2022
Reques
t for Tes
ting of Cement, Admixture and water for Phys
ical & chemeical Tes
t
along with Mix Des
ign of Concrete
Shivam Bharatia (JV) Dhakuakhana
6 SVM/ OC/ 4798 29.10.2022 Reques
t for Factory Vis
it of Reinforcement Steel Jai Balaji Indus
triesLtd Shivam Bharatia (JV) Dhakuakhana
7 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 61 29.10.2022 Reg. Factory Vis
it Of Ras
mi MetaliksLtd SGCCLANPL(JV) Golaghat
8 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 59 28.10.2022 Submis
s
ion of Temporary Divers
ion Plan of E
UP SGCCLANPL(JV) Golaghat
9 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 60 28.10.2022
Submis
s
ion of Temporary Divers
ion plan (typical ) cons
truction of Box Culvert,
Minor Bridge & Roads
SGCCLANPL(JV) Golaghat
10 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 59 31.10.2022 Submis
s
ion of Plan & Profile from Ch. 34+000 to 42+094 SGCCLANPL(JV) Golaghat
11 SVM/ OC/ 4786 10.10.2022 Reg. Approval of Box Culvert location at Chainage 1+120 Shivam Bharatia (JV) Paths
ala
12 SGCCLANPL(JV)/ PWD/ ASRIP/ A/ RI5/ 2022 / 389/ 27 07.10.2022 Submis
s
ion of Plan & Profile for Ch. 14+000 to 23+000 SGCCLANPL(JV) Moran
13 SGCCLANPL/ AM/ MNRD/ 2022-23/ 105 10.10.2022 Submis
s
ion of Third Party Tes
t Report for Source Approval SGCCLANPL(JV) Moran
14 SGCCLANPL/ AM/ MNRD/ 2022-23/ 109 11.10.2022 Submis
s
ion of Plan & Profile of Road SGCCLANPL(JV) Moran
15 SGCCLANPL/ AM/ MNRD/ 2022-23/ 110 13.10.2022 Submis
s
ion of Mix Des
ign of Concrete M-15 PCC, M-20 PCC& M-30 RCC SGCCLANPL(JV) Moran
16 SGCCLANPL/ AM/ MNRD/ 2022-23/ 115 17.10.2022
Submis
s
ion of Box Culvert drwaingsfor Ch. 16+991, 18+552, 18+737, 21+050,
22+907,23+606, 25+611, 26+525 and 27+488 for approval
SGCCLANPL(JV) Moran
17 SGCCLANPL/ AM/ MNRD/ 2022-23/ 113 17.10.2022 Submis
s
ion of 9km Road Length work Programme SGCCLANPL(JV) Moran
18 SGCCLANPL/ AM/ MNRD/ 2022-23/ 117 20.10.2022 Submis
s
ion of Drawing of Drain work SGCCLANPL(JV) Moran
19 SGCCLANPL/ AM/ MNRD/ 2022-23/ 118 20.10.2022 Submis
s
ion of Nix Des
ign of Wet Mix Macadam (WMM) for approval SGCCLANPL(JV) Moran
20 SGCCLANPL/ AM/ MNRD/ 2022-23/ 119 25.10.2022 Submis
s
ion of Inventory detailsfrom Ch. 37+00 to 46+581 SGCCLANPL(JV) Moran
21 SGCCLANPL/ AM/ MNRD/ 2022-23/ 121 27.10.2022 Submis
s
ion of NGLdata (Ch. 02+970 to 08+600) SGCCLANPL(JV) Moran
22 SGCCLANPL/ AM/ MNRD/ 2022-23/ 122 31.10.2022 Submis
s
ion of Revis
ed R-1) Plan & Profile of Road SGCCLANPL(JV) Moran
CORRESPONDENCE FOR THE MONTH OF OCT-22
Outgoing:
Team Leader To Chief Engineer :
SLNo Referance No Date Subject Address
1 TL/ ASR
IP/ CE
/ PWD/ 2022/ 211 07.10.2022
Informationof working Period of Intermittent Input and Approval of
client
Chief E
ngineer(E
AP) PWR
D, Guwahati
2 TL/ ASR
IP/ CONT/ R
I-4/ 2022/ 219 11.10.2022
R
egarding consent for rearrangement of Box culvert fromCH:
13+405 to CH: 1+120
Chief E
ngineer(E
AP) PWR
D, Guwahati
3 TL/ ASR
IP/ CE
/ PWD/ / 2022/ 220 13.10.2022
Submission of Monthly ProgressR
eport for the month of September,
2022
Chief E
ngineer(E
AP) PWR
D, Guwahati
4 TL/ ASR
IP/ CE
/ PWD/ / 2022/ 221 13.10.2022
R
eg. Permanent Account Number (PAN) and GoodsService Tax
IdentificationNumber (GSTIN) and Withdrawal of Invoice for the
monthAugust-2022.
Chief E
ngineer(E
AP) PWR
D, Guwahati
5 TL/ ASR
IP/ CE
/ PWD/ / 2022/ 222 14.10.2022 R
eg. Submissionof Minutesof Meeting. Chief E
ngineer(E
AP) PWR
D, Guwahati
6 TL/ ASR
IP/ CE
/ PWD/ 2022/ 246 28.10.2022 Informationfor Leave of Highway DesignE
ngineer and SQME Chief E
ngineer(E
AP) PWR
D, Guwahati
CORRESPONDENCE FOR THE MONTH OF OCT-22
Outgoing: Team Leader To Contractor :
S
LNo Referance No Date S
ubject Address
1 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 226 15.10.2022 R
egarding Delay in Submis
s
ion of MPR SHIVAM BHAR
TIA (JV) Dhakuakhana
2 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 229 15.10.2022
R
egarding R
eviewsof CSC R
oad s
afety E
ngineer on Submitted document Traffic
and R
oad Safety Manual.
SHIVAM BHAR
TIA (JV) Dhakuakhana
3 TL
/ ASR
IP/ CONT/ R
I-2/ 2022/ 237 17.10.2022 R
egarding R
eview of R
einforcement Steel- Balaji Shakti TMT SHIVAM BHAR
TIA (JV) Dhakuakhana
4 TL
/ ASR
IP/ CONT/ R
I-3/ 2022/ 214 10.10.2022 R
eview of T
MTbarsof BDG metal & Power Ltd. & SHYAM ME
T
ALICT
MTbars SGCCL
-ANPL (JV) Golaghat
5 TL
/ ASR
IP/ CONT/ R
I-3/ 2022/ 215 10.10.2022 R
eview of TMT BarsR
as
hmi MetaliksL
td SGCCL
-ANPL (JV) Golaghat
6 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 225 15.10.2022 R
egarding Delay in Submis
s
ion of MPR SGCCL
-ANPL (JV) Golaghat
7 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 230 15.10.2022
R
egarding R
eviewsof CSC R
oad s
afety E
ngineer on Submitted document Traffic
and R
oad Safety Manual.
SGCCL
-ANPL (JV) Golaghat
8 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 234 17.10.2022 R
egarding Source Approval of Aggregate SGCCL
-ANPL (JV) Golaghat
9 TL
/ ASR
IP/ CONT/ R
I-3/ 2022/ 241 26.10.2022 Traffic Divers
ion Plan and Safety during Cons
truction at CH: 17763 & CH: 17541 SGCCL ANPL (JV) Golaghat
10 TL
/ ASR
IP/ CONT/ R
I-3/ 2022/ 243 27.10.2022 Source Approval Of Aggregate SGCCL ANPL (JV) Golaghat
11 TL
/ ASR
IP/ CONT/ R
I-3/ 2022/ 245 28.10.2022
Submis
s
ion of Third Party Tes
t R
eportsof Admixture (Hind Plas
t Super HPC) &
Cons
truction water (Camp Bore well)
SGCCL ANPL (JV) Golaghat
12 TL
/ ASR
IP/ CONT/ R
I-4/ 2022/ 218 11.10.2022
R
egarding Temporary Divers
ion Plan at Chainage 1+090 to 1+150, 1+650 to
1+710 & 3+480 to 3+560
SHIVAM BHAR
TIA (JV) Paths
ala
13 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 224 15.10.2022 R
egarding Delay in Submis
s
ion of MPR SHIVAM BHAR
TIA (JV) Paths
ala
14 TL
/ ASR
IP/ CONT/ R
I-4/ 2022/ 242 26.10.2022 R
egarding GSB materialsin Site without proper approval SHIVAM BHAR
TIA (JV) Paths
ala
15 TL
/ ASR
IP/ CONT/ R
I5/ 2022/ 212 07.10.2022 R
eview of Typical Cros
sSection SGCCL
-ANPL (JV) Moran
16 TL
/ ASR
IP/ CONT/ R
I5/ 2022/ 213 07.10.2022 R
eply- R
egarding Manufacture Tes
t certificate of TATA Steel. SGCCL
-ANPL (JV) Moran
17 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 216 10.10.2022 R
eply- R
egarding Hindrance L
is
t from CH: 19+500 to CH: 24+500 SGCCL
-ANPL (JV) Moran
18 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 217 11.10.2022 R
eply- R
egarding R
eview of Plan & Profile from Km. 14+000 to 23+000 SGCCL
-ANPL (JV) Moran
19 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 223 15.10.2022 R
egarding Delay in Submis
s
ion of MPR SGCCL
-ANPL (JV) Moran
20 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 228 15.10.2022
R
egarding detailsof Sampling to Identify the exis
itng R
egarding Detailsof
s
ampling to identify the exis
ting CBRvalue & the R
eviewsof CSC
SGCCL
-ANPL (JV) Moran
21 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 235 17.10.2022 R
egarding Submis
s
ion of Fine Aggregate (Sand) tes
t reportsfor Source Approval. SGCCL
-ANPL (JV) Moran
22 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 236 17.10.2022 R
eg. Submis
s
ion of Granular Sub-Bas
e Mix Des
ign SGCCL
-ANPL (JV) Moran
23 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 244 28.10.2022 Source approval of Fine Aggregates(Sand) SGCCL
-ANPL (JV) Moran
24 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 247 28.10.2022 R
egarding GSB material dumpued in R
oadway without proper approval SGCCL
-ANPL (JV) Moran
25 TL
/ ASR
IP/ CONT/ R
I-5/ 2022/ 227 15.10.2022 R
egarding Delay in Submis
s
ion of MPR S&P SHIVA (JV) Chumoni
26 TL
/ ASR
IP/ CONT/ R
I-7/ 2022/ 248 29.10.2022 R
egarding R
eview meeting at TL office, Fatas
il Ambari, Guwahati S&P-SHIVA (JV) Chumoni
Thank You

More Related Content

What's hot

Herbicide degradation in soil and plants......
Herbicide degradation in soil and plants......Herbicide degradation in soil and plants......
Herbicide degradation in soil and plants......
POOJITHA K
 
soil type and their characteristic
soil type and their characteristicsoil type and their characteristic
soil type and their characteristic
Rudra Narayan Singh
 
Land Degradation Neutrality and adaptation to climate change
Land Degradation Neutrality and adaptation to climate changeLand Degradation Neutrality and adaptation to climate change
Land Degradation Neutrality and adaptation to climate change
NAP Events
 
Composting
Composting Composting
Composting
Muhammed sadiq
 
Production of biofertilizer(anabaena and nostoc) using co2
Production of biofertilizer(anabaena and nostoc) using co2Production of biofertilizer(anabaena and nostoc) using co2
Production of biofertilizer(anabaena and nostoc) using co2
Bharat Singh
 
Microbial diversity of soil
Microbial diversity of soilMicrobial diversity of soil
Microbial diversity of soil
CHANDANA K
 
Measuring biodiversity
Measuring biodiversityMeasuring biodiversity
Measuring biodiversity
Guerillateacher
 
Ecological interactions
Ecological interactions Ecological interactions
Ecological interactions
Shihab Kaniyadukam
 
Composting: stages & factors affecting
Composting: stages & factors affectingComposting: stages & factors affecting
Composting: stages & factors affecting
SankritaShankarGaonk
 
Role of microorganisms in soil fertility
Role of microorganisms in soil fertilityRole of microorganisms in soil fertility
Role of microorganisms in soil fertility
Agriculture and Forestry University
 
Evaporation, transpiration and evapotranspiration
Evaporation, transpiration and evapotranspirationEvaporation, transpiration and evapotranspiration
Evaporation, transpiration and evapotranspiration
Student
 
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
Mr.Allah Dad Khan
 
Principles of aerobic and anaerobic composting - Municipal Solid Wastes
Principles of aerobic and anaerobic composting - Municipal Solid WastesPrinciples of aerobic and anaerobic composting - Municipal Solid Wastes
Principles of aerobic and anaerobic composting - Municipal Solid Wastes
Ezhilkumar, Professor (Asst), Sri Krishna College of Engineering and Technology, Coimbatore.
 
Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)
siva ch
 
Compost
CompostCompost
SOIL AIR AND TEMPERATURE
SOIL AIR AND TEMPERATURE SOIL AIR AND TEMPERATURE
3.4 the soil system.ppt
3.4 the soil system.ppt3.4 the soil system.ppt
3.4 the soil system.ppt
GURU CHARAN KUMAR
 
Landfill, Leachate Treatment and Landfill Gas Managemet
Landfill, Leachate Treatment and Landfill Gas ManagemetLandfill, Leachate Treatment and Landfill Gas Managemet
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomarBio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
Aditya Kumar Singh Tomar
 
Ecology
EcologyEcology
Ecology
cgales
 

What's hot (20)

Herbicide degradation in soil and plants......
Herbicide degradation in soil and plants......Herbicide degradation in soil and plants......
Herbicide degradation in soil and plants......
 
soil type and their characteristic
soil type and their characteristicsoil type and their characteristic
soil type and their characteristic
 
Land Degradation Neutrality and adaptation to climate change
Land Degradation Neutrality and adaptation to climate changeLand Degradation Neutrality and adaptation to climate change
Land Degradation Neutrality and adaptation to climate change
 
Composting
Composting Composting
Composting
 
Production of biofertilizer(anabaena and nostoc) using co2
Production of biofertilizer(anabaena and nostoc) using co2Production of biofertilizer(anabaena and nostoc) using co2
Production of biofertilizer(anabaena and nostoc) using co2
 
Microbial diversity of soil
Microbial diversity of soilMicrobial diversity of soil
Microbial diversity of soil
 
Measuring biodiversity
Measuring biodiversityMeasuring biodiversity
Measuring biodiversity
 
Ecological interactions
Ecological interactions Ecological interactions
Ecological interactions
 
Composting: stages & factors affecting
Composting: stages & factors affectingComposting: stages & factors affecting
Composting: stages & factors affecting
 
Role of microorganisms in soil fertility
Role of microorganisms in soil fertilityRole of microorganisms in soil fertility
Role of microorganisms in soil fertility
 
Evaporation, transpiration and evapotranspiration
Evaporation, transpiration and evapotranspirationEvaporation, transpiration and evapotranspiration
Evaporation, transpiration and evapotranspiration
 
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
Fertilizers types By Mr Allah Dad Khan Visiting Professor the University of A...
 
Principles of aerobic and anaerobic composting - Municipal Solid Wastes
Principles of aerobic and anaerobic composting - Municipal Solid WastesPrinciples of aerobic and anaerobic composting - Municipal Solid Wastes
Principles of aerobic and anaerobic composting - Municipal Solid Wastes
 
Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)
 
Compost
CompostCompost
Compost
 
SOIL AIR AND TEMPERATURE
SOIL AIR AND TEMPERATURE SOIL AIR AND TEMPERATURE
SOIL AIR AND TEMPERATURE
 
3.4 the soil system.ppt
3.4 the soil system.ppt3.4 the soil system.ppt
3.4 the soil system.ppt
 
Landfill, Leachate Treatment and Landfill Gas Managemet
Landfill, Leachate Treatment and Landfill Gas ManagemetLandfill, Leachate Treatment and Landfill Gas Managemet
Landfill, Leachate Treatment and Landfill Gas Managemet
 
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomarBio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
Bio fertilizer and phosphorus use efficiency , by- aditya kumar singh tomar
 
Ecology
EcologyEcology
Ecology
 

Similar to MPR OCT-22 PPT COMBINE.pptx

Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review Report
RamuSekar4
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptx
NaziaBashar
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
FaisalGulzar19
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
r66025007
 
Sabawon presentation final
Sabawon presentation finalSabawon presentation final
Sabawon presentation final
HazratKhan11
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
Ptpg Stuc
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
Munir Hussain
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
Rajkumar Kamarsu
 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
NilayGandhi14
 
BPCL review meeting.pptx
BPCL review meeting.pptxBPCL review meeting.pptx
BPCL review meeting.pptx
Ayazkhan510262
 
Rania Constituency.pptx
Rania Constituency.pptxRania Constituency.pptx
Rania Constituency.pptx
SEBWSCSSA
 
10 final highway (1) baby
10   final highway (1) baby10   final highway (1) baby
10 final highway (1) baby
Sierra Francisco Justo
 
Final highway (1) baby
Final highway (1) babyFinal highway (1) baby
Final highway (1) baby
Sierra Francisco Justo
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
sheikhInayat5
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Venkatesh Dontha
 
Training report 2
Training report 2Training report 2
Training report 2
Sandun Thilina
 
5786 (1).pdf
5786 (1).pdf5786 (1).pdf
5786 (1).pdf
DileepChingan
 
Line Deptt. Convergence Meeting_21-04-23.ppt
Line Deptt. Convergence Meeting_21-04-23.pptLine Deptt. Convergence Meeting_21-04-23.ppt
Line Deptt. Convergence Meeting_21-04-23.ppt
bhadratanusenapati1
 
Capitulo 02 grupo 01
Capitulo 02 grupo 01Capitulo 02 grupo 01
Capitulo 02 grupo 01
Guido Choquehuanca
 
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
IRJET Journal
 

Similar to MPR OCT-22 PPT COMBINE.pptx (20)

Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review Report
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptx
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
 
Sabawon presentation final
Sabawon presentation finalSabawon presentation final
Sabawon presentation final
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
 
BPCL review meeting.pptx
BPCL review meeting.pptxBPCL review meeting.pptx
BPCL review meeting.pptx
 
Rania Constituency.pptx
Rania Constituency.pptxRania Constituency.pptx
Rania Constituency.pptx
 
10 final highway (1) baby
10   final highway (1) baby10   final highway (1) baby
10 final highway (1) baby
 
Final highway (1) baby
Final highway (1) babyFinal highway (1) baby
Final highway (1) baby
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
 
Training report 2
Training report 2Training report 2
Training report 2
 
5786 (1).pdf
5786 (1).pdf5786 (1).pdf
5786 (1).pdf
 
Line Deptt. Convergence Meeting_21-04-23.ppt
Line Deptt. Convergence Meeting_21-04-23.pptLine Deptt. Convergence Meeting_21-04-23.ppt
Line Deptt. Convergence Meeting_21-04-23.ppt
 
Capitulo 02 grupo 01
Capitulo 02 grupo 01Capitulo 02 grupo 01
Capitulo 02 grupo 01
 
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
 

Recently uploaded

CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 

Recently uploaded (20)

CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 

MPR OCT-22 PPT COMBINE.pptx

  • 1. PUBLIC WORKS ROAD DEPARTMENT Construction Supervision Consultancy Services for Improvement and Upgradation of Road under ASRIP funded by Asian Infrastructure Investment Bank MONTHLY PROGRESS REPORT (OCTOBER 2022) Construction Supervision Consultant (CSC) Dohwa Engineering Co. Ltd. in JV with MaRS Planning and Engineering Services Private Limited. Submitted By
  • 2. EXECUTIVE SUMMARY Sl No. Road Project Length Cost of Project Construction Period+ Defect Notification Period Salient Features Milestone Dates Work Contract Details Km (Rs. In Cr.) Month 1 Dhakuakhana Butikur Tiniali Telijan ( Dhakuakhana to Telijan ) A22 32.73 146.33 30+60 Earthwork GSB/WMM DBM BC Major Bridges Minor Bridges Culverts RCC Drain 11,87,323.96 m3 2,19,690.71 m3 27,311.50 m3 15,527.37 m3 - 1 Nos. 20 Nos. 2.60 Km. Date of Commencement : 18.04.2022 Milestone I 365 Days : 18.04.2023 Milestone II 548 Days : 18.10.2023 Milestone III 913 Days : 18.10.2024 Contract No. : CE/ASRIP/09/2021/48 Name of Contractor : Shivam-Bhartia (JV) 2 Dhodar Ali ( Kamargaon to Kaamarbandha) A15 42.09 304.19 30+60 Earthwork GSB/WMM DBM BC EUP Minor Bridges Culverts RCC Drain 12,94,046.40 m3 2,50,494.17 m3 34,045.12 m3 19,578.98 m3 2 Nos. 1 Nos. 95 Nos. 5.15 Km. Date of Commencement : 18.04.2022 Milestone I 365 Days : 18.04.2023 Milestone II 548 Days : 18.10.2023 Milestone III 913 Days : 18.10.2024 Contract No. : CE/ASRIP/10/2021/28 Name of Contractor : SGCCL-ANPL (JV) 3 Sarthebari Pathsala Raipur Road A07 17.65 114.01 24+60 Earthwork GSB/WMM DBM BC Major Bridges Minor Bridges Culverts RCC Drain 4,20,439.00 m3 97,000.00 m3 11,747.00 m3 7,831.00 m3 1 Nos. - 32 Nos. 9.172 Km. Date of Commencement : 18.04.2022 Milestone I 365 Days : 18.04.2023 Milestone II 547 Days : 18.10.2023 Milestone III 730 Days : 18.04.2024 Contract No. : CE/ASRIP/11/2021/41 Name of Contractor : Shivam-Bhartia (JV)
  • 3. EXECUTIVE SUMMARY Sl No. Road Project Length Cost of Project Construction Period+ Defect Notification Period Salient Features Milestone Dates Work Contract Details Km (Rs. In Cr.) Month 4 Moran Naharkatia Duliajan Digboi ( Moran to Deesang Kinar Bangali) A30_1 46.60 215.44 30+60 Earthwork GSB/WMM DBM BC Major Bridges Minor Bridges Culverts RCC Drain 8,72,420.25 m3 2,64,931.23 m3 35,075.60 m3 19,499.93 m3 - 2 Nos. 55 Nos. 8.912 Km. Date of Commencement : 18.04.2022 Milestone I 365 Days : 18.04.2023 Milestone II 548 Days : 18.10.2023 Milestone III 913 Days : 18.10.2024 Contract No. : CE/ASRIP/12/2021/31 Name of Contractor : SGCCL-ANPL (JV) 5 Moran Naharkatia Duliajan Digboi ( Deesang Kinar Bangali to Kathalguri) A30_2 23.98 30+60 6 Sivasagar to Chumoni A20_1 18.42 121.09 24+60 Earthwork GSB/WMM DBM BC Major Bridges Minor Bridges Culverts RCC Drain 9,55,671.61 m3 1,02,786.68 m3 19,069.82 m3 7,572.27 m3 - 1 Nos. 13 Nos. 8.52 Km. Date of Commencement : 19.04.2022 Milestone I 306 Days : 19.02.2023 Milestone II 456 Days : 19.07.2023 Milestone III 730 Days : 19.04.2024 Contract No. : CE/ASRIP/14/2021/29 Name of Contractor : S&P - SHIVA (JV) 7 Sivasagar to Nakachari to Balighat Tiniali) A20_2 45.00 30+60
  • 4. S- CURVE SHOWING PROGRESS OF WORK
  • 5. PROJECT TARGET VS ACHIEVEMENT Construction Supervision Consultancy Services for ASRIP TARGET Vs ACHIEVEMENT STATUS Upto 31 st October, 2022 ( As per Contractors Work Programme ) Sl. N o. DP R No. Pk g. No. Contrac t Price Cumulative till September, 2022 Month October,2022 Cumulative upto 31 st October, 2022 Remarks Target ( Based on Work Program me) Achievem ent Achievem ent w.r.t. Target (Col.2) Achievem ent w.r.t. Contract Price (Col.1) Target for the Month - October 2022 Achievem ent for the Month upto 31 st October, 2022 %age Achievem ent w.r.t. Monthly Target Target Achievem ent Achievem ent w.r.t. Cumulativ e Target (Col.9) Achievem ent w.r.t. Contract Price (Col.1) (Rs. In Cr.) (Rs. In Cr.) (Rs. In Cr.) (%) (%) (Rs. In Cr.) (Rs. In Cr.) (%) (Rs. In Cr.) (Rs. In Cr.) (%) (%) (a) (b) (c ) 1 2 3 4=3/2 5=3/1 6 7 8=7/6 9=2+6 10=3+7 11=10/9 12=10/1 13 1 A22 RI- 02 146.33 1.66 0.00 0.00 0.00 2.94 0.00 0.00 4.60 0.00 0.00 0.00 In Preliminary Stage 2 A15 RI- 03 304.19 1.82 0.00 0.00 0.00 5.48 0.00 0.00 7.30 0.00 0.00 0.00 In Preliminary Stage 3 A07 RI- 04 114.01 2.20 0.00 0.00 0.00 2.30 0.00 0.00 4.50 0.00 0.00 0.00 Culvert Started 4 A30 -1 RI- 05 215.44 1.08 0.00 0.00 0.00 1.81 0.00 0.00 2.89 0.00 0.00 0.00 In Preliminary Stage 5 A- 20_ 1 RI- 07 121.01 3.98 0.00 0.00 0.00 5.28 0.00 0.00 9.26 0.00 0.00 0.00 In Preliminary Stage
  • 6. PHYSICAL & FINANCIAL PROGRESS OF PROJECT Physical progress (as per C.A. BOQ) = 00.10% Financial progress (as per C.A. BOQ) = 00.00% A-22 A-15 A-07 A-30_1 A-20_1 Total Upto Sept-22 Upto Date 1 Earthwork % 0.95 1.50 2.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2 GSB % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3 WMM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4 DBM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 BC % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6 Culverts % 0.20 0.40 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 7 RCC Drains % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8 Foundation % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9 Substructure % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10 Superstructure % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11 Protection Work % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12 Approaches % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13 Miscellaneous % 0.04 0.08 0.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Cumm. Physical Progress % Sr. No. Key Items of Work Unit Target Upto Date This Month Qty. Financial Progress Target Upto Sept.- 22 Target for Oct-22
  • 7. PHYSICAL PROGRESS OF ROAD WORK Sr. No. Key Items of Work Unit Upto Sept-22 Target for Oct-22 Target Upto Date This Month Physical Progress Physical Progress A-22 A-15 A-07 A-30_1 A-20_1 This Month Upto Sept-22 Upto Date 1 Earthwork % 0.95 1.50 2.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2 GSB % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3 WMM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4 DBM % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 BC % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6 Culverts % 0.20 0.40 0.60 0.00 0.00 0.10 0.00 0.00 0.00 0.10 0.10 7 RCC Drains % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.45% 0.00% 0.00% 0.00% 0.00% 0.60% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.10% 0.00% 0.00% 0.50% 1.00% 1.50% 2.00% 2.50% 3.00% Earthwork GSB WMM DBM BC Culverts RCC Drains Achieve d Progress in Percentage (%)
  • 8. PHYSICAL PROGRESS OF STRUCTURE WORK Sl. No. Package No. Name of Road Section TYPE OF STRUCTURES MAJOR BRIDGE / EUP MINOR BRIDGE BOX CULVERTS GRAND TOTAL Total Nos. Completed Balance Total Nos. Completed Balance Total Nos. Completed Balance Total Nos. Completed Balance 1 A22 Dhakuakhana to Telijan 0 NA NA 1 0 1 20 0 20 21 0 21 2 A15 Kamargaon to Kamaarbandha 2 0 2 1 0 1 95 0 95 98 0 98 3 A07 Sarthebari to Pathsala 1 0 1 0 NA NA 32 3 29 33 3 30 4 A30_1 Moran Naharkatia 0 NA NA 2 0 2 55 0 55 57 0 57 5 A30_2 Moran Kathalguri 6 A20_1 Sivasagar Chumoni 0 NA NA 1 0 1 13 0 13 14 0 14 7 A20_2 Sivasagar Tiniali
  • 9. DRAWING APPROVAL STATUS PLAN & PROFILE 1 Dhakuakhana to Telijan Road (A22) 32.675 - - 32.675 2 Kamargaon to Kamarbandha Road (A15) 42.094 8.000 - 42.094 3 Sarthebari to Pathsala Road (A07) 17.653 - - 17.653 4 Moran to Naharkatia Road (A30-1) 46.581 9.000 - 46.581 5 Sivasagar to Chumoni Road (A20-1) 18.416 - - 18.416 Balance L ength (Km.) Drawing S ubmission (Km.) S r. No. Name of Project Total L ength (Km.) Approved L ength (Km.)
  • 10. DRAWING APPROVAL STATUS STRUCTURE & MISCELLANEOUS DRAWINGS Total Drawing Submission Approved Balance (Nos) (Nos) (Nos) (Nos) BOX CULVERT DRAWINGS 1 Dhakuakhana to Telijan Road (A22) 20 - - 20 2 Kamargaon to Kamarbandha Road (A15) 95 69 14 81 3 Sarthebari to Pathsala Road (A07) 32 7 7 25 4 Moran to Naharkatia Road (A30-1) 55 36 - 55 5 Sivasagar to Chumoni Road (A20-1) 13 - - 13 MINOR BRIDGE DRAWINGS 1 Dhakuakhana to Telijan Road (A22) 1 - - 1 2 Kamargaon to Kamarbandha Road (A15) 1 - - 1 3 Sarthebari to Pathsala Road (A07) NA - NA NA 4 Moran to Naharkatia Road (A30-1) 2 - - 2 5 Sivasagar to Chumoni Road (A20-1) 1 - - 1 EUP/MAJOR BRIDGE DRAWINGS 1 Dhakuakhana to Telijan Road (A22) NA - NA NA 2 Kamargaon to Kamarbandha Road (A15) 2 2 - 2 3 Sarthebari to Pathsala Road (A07) 1 - - 1 4 Moran to Naharkatia Road (A30-1) NA - NA NA 5 Sivasagar to Chumoni Road (A20-1) NA - NA NA JUNCTION DEVELOPMENT DRAWINGS 1 Dhakuakhana to Telijan Road (A22) 2 Kamargaon to Kamarbandha Road (A15) 3 Sarthebari to Pathsala Road (A07) 4 Moran to Naharkatia Road (A30-1) 5 Sivasagar to Chumoni Road (A20-1) Sr. No. Name of Project
  • 11. MIX DESIGN APPROVAL STATUS 1. Dhakuakhana To Telijan Road (RI-02) : No Progress on Mix Design till date. 2. Kamargaon To Kamarbandha (RI-03) : Trial Mix Done for M-15, M-20 & M-30 Respectively, Results not Submitted till date. 3. Sarthebari To Pathsala Road (RI-04) : Mix Design Reports submitted for M-15, M-20, M-30 (20 MSA), M-30 (40 MSA), M-35 (20 MSA) & M-35 (40 MSA). Comments given by CSC on 24-09-2022 Compliance of Contractor on 09-10-2022 Status : Under Review. 4. Moran To Naharkatia Road ( RI-05) : Mix Design for GSB, M-15, M-20 & M-30 in Progress. 5. Sivasagar To Chumoni Road ( RI-07) : No Progress on Mix Design till date.
  • 12. STATUS OF APPROVAL OF CONSTRUCTION MATERIAL Sr. No. Name of Material Location of Source Proposal submission date AE Comments Compliance of contractor Approval date Remark 1 Stone Subans iri river - - - - Tes ting in Third party lab is in progres s . 1 Soil Km 23+700 (700m from the exis ting road) - - - - Tes ting is in progres s . 1 Sika M/S AKJ Engineers Private Limited - - - - Tes ting in Third party laboratory is in progres s . 1 Topcem Meghalaya cement limited - - - - Tes ting in Third party laboratory is in progres s . 1 Balaji Shakti TMT Durgapur, West Bengal - - - - Credentials s ubmitted by the Contractor on 17.10.2022. 1 Water Bore well at Bas e camp at km 24+000 RHS - - - - Tes ting in Third party laboratory is in progres s . Soil Soil Soil ADMIXTURE/CURING COMPOUND CEMENT FLY ASH STEEL Water Tes ting is in progres s . 4 Km 24+030 (3500m from the exis ting road) - - - - Tes ting is in progres s . 3 Km 24+030 (3600m from the exis ting road) - - - - Dhakuakhana to Telijan Road (A22) QUARRY BORROW AREA 2 Km 23+700 (500m from the exis ting road) - - - - Tes ting is in progres s .
  • 13. STATUS OF APPROVAL OF CONSTRUCTION MATERIAL Sr. No. Name of Material Location of Source Proposal submission date AE Comments Compliance of contractor Approval date Remark 1 Quarry for Aggregate, 40mm, 20mm,10mm Karbi Anglong 20.09.2022 17.10.2022 Approved Vashudha, Kokata Meghalaya Cement Ltd. Shilong 2 Dalmia Lanka- Hojai 21.07.2022 Under review by CSC 1 SHYAM Steel Industries Durgapur, WB 25.08.2022 24.09..2022 Approved 1 Water Base camp 22+100 25.08.2022 Under review by CSC Dishala marketing Pvt. Ltd. Lokhara Rd. Guwahati Water FLY ASH STEEL 2 JSPL 25.08.2022 24.09.2022 Approved Under review by CSC CEMENT 1 Topcem 21.07.2022 19.08.2022 Approved Kamargaon to Kamarbandha Road (A15) QUARRY BORROW AREA ADMIXTURE/CURING COMPOUND 1 Hindcon 25.08.2022
  • 14. STATUS OF APPROVAL OF CONSTRUCTION MATERIAL Sr. No. Name of Material Location of Source Proposal submission date AE Comments Compliance of contractor Approval date Remark 1 Stone Pall River(MB Crusher 07-06-2022 Approved 2 Sand Pall River(MB Crusher 07-06-2022 Approved 3 Sand Gravel Pall River(MB Crusher 07-06-2022 Approved 1 Soil Batia Village at K.M- 3+500 24.09.2022 Letter issued on dt. 26.09.2022 Compliences submitted dated. 11.10.2022 Under Review 1 Asian Paint Asian paint Ltd. 05-08-2022 30-08-2022 Approved 2 Sika Sika India Ltd. 06-08-2022 30-08-2022 Approved 1 Ramco The Ramco Cement Ltd. 07-06-2022 15-7-2022 Approved 2 Ultra Tech Ultratech Cement Ltd. 05-08-2022 30-08-2022 Approved 1 Shyam Steel 07-6-2022 30-8-2022 Approved 1 Water Bore @ RMC Plant 12+450 10-10-2022 Under Review CEMENT FLY ASH STEEL WATER Sarthebari to Pathsala Road (A07) QUARRY BORROW AREA ADMIXTURE/CURING COMPOUND
  • 15. STATUS OF APPROVAL OF CONSTRUCTION MATERIAL Sr. No. Name of Material Location of Source Proposal submission date AE Comments Compliance of contractor Approval date Remark 1 Aggregate Likabari Quarry 13-08-2022 12-09-2022 Approved 2 Aggregate Bihubar Quarry 13-08-2022 12-09-2022 Approved 3 Sand Buridihing River 13-08-2022 27-10-2022 Approved 1 SG & Emb soil Borrow Area 1 16-9-2022 24-09-2022 Approved 2 Embankment Soil Borrow Area 2 16-9-2022 24-09-2022 Approved 3 Embankment Soil Borrow Area 3 16-9-2022 Under Review 1 Fosroc 25-7-2022 Under Review 1 Ultra Tech Ultratech Cement Ltd. 18-7-2022 10-8-2022 Approved 2 Ramco The Ramco Cement Ltd. 18-07-2022 10-08-2022 Approved 3 Topcem Topcem Cement Ltd. 18-07-2022 19-08-2022 Approved 4 Dalmia Dalmia Cement Ltd. 18-07-2022 Under Review 1 TATA Steel 18-7-2022 24-9-2022 Approved 2 Shyam Steel 18-07-2022 24-09-2022 Approved 3 Jindal Steel 18-07-2022 24-09-2022 Approved Water QUARRY BORROW AREA ADMIXTURE/CURING COMPOUND CEMENT FLY ASH STEEL Moran to Naharkatia Road (A30-1)
  • 16. STATUS OF APPROVAL OF CONSTRUCTION MATERIAL Sr. No. Name of Material Location of Source Proposal submission date AE Comments Compliance of contractor Approval date Remark CEMENT FLY ASH STEEL Water Bearing Sivasagar to Chumoni Road (A20-1) QUARRY BORROW AREA ADMIXTURE/CURING COMPOUND No Progress on Approval of Construction Material in this Progress
  • 17. STATUS OF MOBILIZATION OF KEY PERSONNEL BY CONTRACTOR Dhakuakhana- (A22) Golaghat(A15) Pathsala(A07) Moran(A30_1) Nazira(A20_1) Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel Nameof thepersonnel 1 Project Manager Mr.DeepakSingha Mr.Banjit Das Mr.KamleshDeka Akbar Hussain Mr.Md.Sher AfghanKhan 2 Highway Engineer cumDeputy Project Manager - Mr.AlomHussain Mr.Vijaychandrakalita Mr.SamshoolHazarika - 3 Senior Highway Engineer Mr.PintuKumar - Mr.Mehmudur Rahman Mr.AbasDas - 4 MaterialcumQuality controlEngineer Mr.Bidyut BikashSaikia Mr.Biswajit Deori Mr.MuhhamadAli Mr.Rajeswar Doley - 5 LabTechnician Mr.DhaniPradhan Mr.Achyot Deori Mr.SagardeepNag Mr.Nur Amin Mr.SimanataHazarika Mr.PritamBhuyan - 6 Bridge/ StructuralEngineer Mr.JanakDeka - Mr.RashidulIslam Mr.SitaramBarma Mr.SidhartaDebnath - 7 Quantity Surveyor cumPlanningEngineer Mr.LakhiGogoi Mr.PapuBoro - Mr.DaduMuniBorah - 8 Survey Engineer Mr.Biswajit Dasand Mr.Gunojit Bhuyan Md.RaquibulIslam Mr.MohanChutia Mr.BrighuKumar Mr.RiturajBonshi Mr.MandipKonwar Mr.Biswajit Adak Mr.RajuKumar Das 9 Highway DesignEngineer - Mr.MannaDas Mr.ChandanDas - - 10 Environmental,Social,HealthandSafety Expert - - Mr.Gunajit Das Mr.RiyazHussain - S. No. Position
  • 18. STATUS OF MOBILIZATION OF PLANT & MACHINERY Asper CA Actual asper site Asper CA Actual asper site Asper CA Actual asper site Asper CA Actual asper site Asper CA Actual asper site Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos 1 Batch type Central Hot Mix Plant 100-120 TPH 1 0 1 0 1 0 1 0 1 0 2 Paver finisher hydrostatic with sensor control 100-120 TPH 2 0 2 0 2 0 2 0 2 0 3 Bitumen/ E mulsion Pressure distributor 1750 sqmper hour 1 0 2 0 1 0 1 0 1 0 4 Vibratory roller 8-10 Tonne static weight 3 1 3 1 3 0 3 2 3 0 5 Smooth Wheeled tandem vibratory roller 8-10 tonnes 1 0 2 0 1 1 1 1 1 0 6 Pneumatic Tyred roller 12-15T 1 0 2 0 1 0 1 0 1 0 7 Motor Grader 3.35 blade 2 1 2 1 2 0 2 2 2 0 8 Hydraulic E xcavator 0.9 cumbucket size 2 3 2 1 0 2 2 2 2 0 9 Batch type automatic concrete batching Plant static 75 cum/ hour 1 0 1 - 1 1 1 0 1 0 10 Tipper rigid axle 10 tonnes 5 0 8 15 5 4 5 7 5 0 11 Water tanker 10 KL 2 0 3 1 2 1 2 1 2 0 12 Air compressor 250 cfm 1 0 2 0 1 0 1 0 1 0 13 Mechanical broom 1250 sqmper hour 1 0 1 0 1 0 1 0 1 0 14 Transit Mixer 6 cum 5 1 8 0 5 2 5 0 5 0 15 Mobile Crushing Plant 30 TPH 1 0 2 0 1 0 1 0 1 0 16 Wet Mix Plant 75 TPH 1 1 1 0 1 0 1 1 1 0 17 Rotovator Capacity to mix 25cm depth of granular material 1 0 1 0 1 0 1 0 1 0 18 Mobile Maintenance unit Truck-mounted with provision of carrying portable mechanized equipment for routine maintenance operations 1 0 1 0 1 0 1 1 1 0 Moran (A30_1) Nazira (A20_1) S .No. E quipment Type and Characteristics Minimum Capacity Dhakuakhana (A22) Golaghat (A15) Pathsala (A07)
  • 19. STATUS OF MOBILIZATION OF KEY PERSONNEL BY CSC S. No. Position Name of the personnel Date of Joining 1 Team Leader cum Senior Highway Engineer Mr. VR. Ramanathan 09-06-2022 2 Senior Material cum Quality control Engineer Dr. Ravindranath Thakur 22-03-2022 3 Senior Quantity Surveyor Mr. Awadhesh Kumar Singh 18-04-2022 4 Senior Contract Specialist Mr. M. Sriniwas 03-06-2022 5 Senior Bridge Engineer - - 6 Bridge Design Engineer - - 7 Pavement Specialist Mr. Harikrishna Bhavsar 29-03-2022 8 Highway Design Engineer Mr. Nirupam Kumar Singh 04-04-2022 9 ESHS Expert - - 10 Road Safety Engineer Mr. Chandan Rajkhowa 29-03-2022 11 Resident Engineer-1 Mr. Anil Kumar panday 03-05-2022 12 Resident Engineer-2 Mr. Sunil Kumar Singh 18-04-2022 13 Resident Engineer-3 Mr. Harihar Sharan Singh 25-04-2022 14 Resident Engineer-4 Mr. Uttam Mendhi 22-03-2022 15 Resident Engineer-5 Mr. Ritesh Sinha 22-03-2022 16 Resident Engineer-6
  • 20. STATUS OF PERMITS Dhakuakhna (A22) Golaghat (A15) Pathsala (A07) Moran (A30_1) Nazira (A20_1) 1 Permission of the State Govt. for extraction of bouldersfromquarry Not submitted yet. Not submitted yet. Completed Not submitted yet. Not submitted yet. 2 Permission of village Panchayat and Pollution Control Board for installation of crushers Not submitted yet. Not submitted yet. Completed Not submitted yet. Not submitted yet. 3 License for use of explosivesif any. Not submitted yet. Not submitted yet. NA Not submitted yet. Not submitted yet. 4 Permission of the State Govt. for drawing water fromriver reservoir. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. 5 License fromInspector of factories or other competent authority for setting up batching plant. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. 6 Clearance of Pollution Control Board for setting up Batching Plant. Not submitted yet. Not submitted yet. 1. Completed 2. Under Process Not submitted yet. Not submitted yet. 7 Clearance of village Panchayat and Pollution Control Board for Asphalt Plant. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. 8 Permission of village Panchayat and State Gov. for borrow earth. Not submitted yet. Not submitted yet. Completed Submitted Not submitted yet. 9 Permission of forest department for cutting of trees. Not submitted yet. Not submitted yet. Under process Not submitted yet. Not submitted yet. 10 Any other permitsof clearances required under applicable laws. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. Not submitted yet. S. No. Description Status
  • 21. MEASURES FOR ENVIRONMENTAL, SOCIAL AND RESETTLEMENTS S. No. Description Safeguard Measures Taken Remarks 1 2 3 4 5
  • 22. REASONS FOR DELAY S. No. Activity Due Date as per CA Actual Date of Completion Delay in Days Reason for Delay 1 Acquisition of land. - - - - 2 Removal of hindrances including private houses, boundary walls, shops, hotels, tea stalls etc. from within the ROW - - - - 3 Shifting of utilities including the existing Electric Poles/Lines from within the ROW. Cutting of Trees from within the ROW. - - - - 4 Due to rainfalls - - - - 5 Submission of Drawing by the Contractor - - - -
  • 23. WORK PROGRAM OF UPCOMING MONTH 1. Dhakuakhana To Telijan Road (A22): Target Qty ( Nov-22) 1 Embankment Cum 889388.4 0 81801.31 Nil 2 Subgrade Cum 292450.17 0 17932.03 Nil 3 Granular Sub-base Cum 108974.29 0 6692.18 Nil 4 WMM 1st Layer Cum 50858.21 0 Nil Nil 5 WMM 2nd Layer Cum 50858.21 0 Nil Nil 6 Dense Bituminous Macadam Cum 27311.5 0 Nil Nil 7 Bituminous Macadam Cum 15527.37 0 Nil Nil 8 Box Culverts (New/ Reconstruction) Nos 19 0 0 Nil 9 Minor Bridge Nos 1 0 0 Nil 10 Major Bridge Nos Nil 0 0 Nil Targeted Physical Progress (%) Targeted Financial Progress (%) ROAD WORKS 7.09 STRUCTURE WORKS Sl. No Item Description Unit Total Completed up to this month Total Quantity completion
  • 24. WORK PROGRAM OF UPCOMING MONTH 2. Kamargaon To Kamarbandha Road (A15) : Target Quantity (Nov-22) 1 Embankment Cum 8,91,025.06 0 4250 Nil 2 Subgrade Cum 2,42,941.24 0 Nil Nil 3 Granular Sub-base Cum 1,26,710.22 0 Nil Nil 4 WMM1st Layer Cum 61,891.98 0 Nil Nil 5 WMM2nd Layer Cum 61,891.98 0 Nil Nil 6 Dense Bituminous Macadam Cum 34,045.12 0 Nil Nil 7 Bituminous Macadam Cum 19,578.98 0 Nil Nil 8 BoxCulverts (New/ Reconstruction) Nos 95 0 0 Nil 9 EUP Nos 2 0 0 Nil 10 Minor Bridge Nos 1 0 0 Nil Total Quantity completion Targeted Physical Progress (%) Targeted Financial Progress (%) ROAD WORKS 0.6 STRUCTUREWORKS Sl. No Item Description Unit Total Completed up to this month
  • 25. WORK PROGRAM OF UPCOMING MONTH 3. Sarthebari To Pathsala Road (A07) : Sl. No Item Description Unit Total Completed up to this month Target Quantity (Nov-22) Total Quantity completion Targeted Physical Progress (%) Targeted Financial Progress (%) 1 Embankment Cum 254186 0 50500 50500 20% 2 Subgrade Cum 120155 0 2000 2000 2% 3 Granular Sub-base Cum 47414 0 Nil Nil 4 WMM1st Layer Cum 24806.5 0 Nil Nil 5 WMM2nd Layer Cum 24806.5 0 Nil Nil 6 Dense Bituminous Macadam Cum 11747 0 Nil Nil 7 Bituminous Macadam Cum 7831 0 Nil Nil 8 BoxCulverts (New/ Reconstruction) Nos 32 3 3 6 9% 9 Minor Bridge Nos 0 0 0 Nil Nill 10 Major Bridge Nos 1 0 Foundation Work Nil 4% ROAD WORKS 1.78% STRUCTUREWORKS
  • 26. WORK PROGRAM OF UPCOMING MONTH 4. Moran To Naharkatia (A30_1) : Sl. No Item Description Unit Total Completed up to this month Target Quantity (November'2022) Total Quantity completion Targeted Physical Progress (%) Targeted Financial Progress (%) 1 Embankment Cum 518596.51 0 37755 Nil 7% 2 Subgrade Cum 388766 0 24840 Nil 6% 3 Granular Sub-base Cum 139707.6 0 4757 Nil 4 WMM1st Layer Cum 62611.86 0 Nil Nil 5 WMM2nd Layer Cum 62611.86 0 Nil Nil 6 Dense Bituminous Macadam Cum 35075.6 0 Nil Nil 7 Bituminous Macadam Cum 19499.93 0 Nil Nil 8 BoxCulverts (New/ Reconstruction) Nos 55 0 4 Nil 7% 9 Minor Bridge Nos 5 0 0 Nil Nill 10 Major Bridge Nos 0 0 Foundation Work Nil Nill ROAD WORKS 3.60% STRUCTUREWORKS
  • 27. WORK PROGRAM OF UPCOMING MONTH 5. Sivasagar To Chumoni Road (A20_1) : Sl. No Item Description Unit Total Completed up to this month Target Quantity (Nov-22) Total Quantity completion Targeted Physical Progress (%) Targeted Financial Progress (%) 1 Embankment Cum 839264.37 0 37376.294 37376.294 2 Subgrade Cum 104419.23 0 4650.069 4650.069 3 Granular Sub-base Cum 54568.02 0 3747.107 3747.107 4 WMM Cum 48218.66 0 3069.872 3069.872 6 Dense Bituminous Macadam Cum 19069.82 0 814.547 814.547 7 Bituminous Macadam Cum 7572.27 0 446.978 446.978 8 BoxCulverts (New/ Reconstruction) Nos 13 0 0 0 9 Minor Bridge Nos 2 0 0 0 10 Major Bridge Nos Nil 0 0 0 ROAD WORKS 5.69% 6.9% STRUCTUREWORKS
  • 28. CORRESPONDENCE FOR THE MONTH OF OCT-22 Incoming: Chief Engineer To Team Leader: SL No Referance No Letter date Subject Address 1 2 Contractor To Team Leader: S LNo ReferanceNo Letter date S ubject Address 1 SVM/ OC/ 4794 17.10.2022 Submis s ion of MPR-2022 Shivam Bharatia (JV) Dhakuakhana 2 SVM/ OC/ 4795 17.10.2022 Regarding Submis s ion of credential of Balaji Shakti TMT. Shivam Bharatia (JV) Dhakuakhana 3 SVM/ OC/ 4801 28.10.2022 Review of Reinforcement Steel Jai Balaji Indus triesLtd Shivam Bharatia (JV) Dhakuakhana 4 SVM/ OC/ 4802 28.10.2022 Reques t for Factory Vis it of Reinforcement Steel Jai Balaji Indus triesLtd Shivam Bharatia (JV) Dhakuakhana 5 SVM/ OC/ 4798 26.10.2022 Reques t for Tes ting of Cement, Admixture and water for Phys ical & chemeical Tes t along with Mix Des ign of Concrete Shivam Bharatia (JV) Dhakuakhana 6 SVM/ OC/ 4798 29.10.2022 Reques t for Factory Vis it of Reinforcement Steel Jai Balaji Indus triesLtd Shivam Bharatia (JV) Dhakuakhana 7 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 61 29.10.2022 Reg. Factory Vis it Of Ras mi MetaliksLtd SGCCLANPL(JV) Golaghat 8 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 59 28.10.2022 Submis s ion of Temporary Divers ion Plan of E UP SGCCLANPL(JV) Golaghat 9 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 60 28.10.2022 Submis s ion of Temporary Divers ion plan (typical ) cons truction of Box Culvert, Minor Bridge & Roads SGCCLANPL(JV) Golaghat 10 ANPL/ ASRIP/ A/ RI-3/ 2022/ Golaghat/ 59 31.10.2022 Submis s ion of Plan & Profile from Ch. 34+000 to 42+094 SGCCLANPL(JV) Golaghat 11 SVM/ OC/ 4786 10.10.2022 Reg. Approval of Box Culvert location at Chainage 1+120 Shivam Bharatia (JV) Paths ala 12 SGCCLANPL(JV)/ PWD/ ASRIP/ A/ RI5/ 2022 / 389/ 27 07.10.2022 Submis s ion of Plan & Profile for Ch. 14+000 to 23+000 SGCCLANPL(JV) Moran 13 SGCCLANPL/ AM/ MNRD/ 2022-23/ 105 10.10.2022 Submis s ion of Third Party Tes t Report for Source Approval SGCCLANPL(JV) Moran 14 SGCCLANPL/ AM/ MNRD/ 2022-23/ 109 11.10.2022 Submis s ion of Plan & Profile of Road SGCCLANPL(JV) Moran 15 SGCCLANPL/ AM/ MNRD/ 2022-23/ 110 13.10.2022 Submis s ion of Mix Des ign of Concrete M-15 PCC, M-20 PCC& M-30 RCC SGCCLANPL(JV) Moran 16 SGCCLANPL/ AM/ MNRD/ 2022-23/ 115 17.10.2022 Submis s ion of Box Culvert drwaingsfor Ch. 16+991, 18+552, 18+737, 21+050, 22+907,23+606, 25+611, 26+525 and 27+488 for approval SGCCLANPL(JV) Moran 17 SGCCLANPL/ AM/ MNRD/ 2022-23/ 113 17.10.2022 Submis s ion of 9km Road Length work Programme SGCCLANPL(JV) Moran 18 SGCCLANPL/ AM/ MNRD/ 2022-23/ 117 20.10.2022 Submis s ion of Drawing of Drain work SGCCLANPL(JV) Moran 19 SGCCLANPL/ AM/ MNRD/ 2022-23/ 118 20.10.2022 Submis s ion of Nix Des ign of Wet Mix Macadam (WMM) for approval SGCCLANPL(JV) Moran 20 SGCCLANPL/ AM/ MNRD/ 2022-23/ 119 25.10.2022 Submis s ion of Inventory detailsfrom Ch. 37+00 to 46+581 SGCCLANPL(JV) Moran 21 SGCCLANPL/ AM/ MNRD/ 2022-23/ 121 27.10.2022 Submis s ion of NGLdata (Ch. 02+970 to 08+600) SGCCLANPL(JV) Moran 22 SGCCLANPL/ AM/ MNRD/ 2022-23/ 122 31.10.2022 Submis s ion of Revis ed R-1) Plan & Profile of Road SGCCLANPL(JV) Moran
  • 29. CORRESPONDENCE FOR THE MONTH OF OCT-22 Outgoing: Team Leader To Chief Engineer : SLNo Referance No Date Subject Address 1 TL/ ASR IP/ CE / PWD/ 2022/ 211 07.10.2022 Informationof working Period of Intermittent Input and Approval of client Chief E ngineer(E AP) PWR D, Guwahati 2 TL/ ASR IP/ CONT/ R I-4/ 2022/ 219 11.10.2022 R egarding consent for rearrangement of Box culvert fromCH: 13+405 to CH: 1+120 Chief E ngineer(E AP) PWR D, Guwahati 3 TL/ ASR IP/ CE / PWD/ / 2022/ 220 13.10.2022 Submission of Monthly ProgressR eport for the month of September, 2022 Chief E ngineer(E AP) PWR D, Guwahati 4 TL/ ASR IP/ CE / PWD/ / 2022/ 221 13.10.2022 R eg. Permanent Account Number (PAN) and GoodsService Tax IdentificationNumber (GSTIN) and Withdrawal of Invoice for the monthAugust-2022. Chief E ngineer(E AP) PWR D, Guwahati 5 TL/ ASR IP/ CE / PWD/ / 2022/ 222 14.10.2022 R eg. Submissionof Minutesof Meeting. Chief E ngineer(E AP) PWR D, Guwahati 6 TL/ ASR IP/ CE / PWD/ 2022/ 246 28.10.2022 Informationfor Leave of Highway DesignE ngineer and SQME Chief E ngineer(E AP) PWR D, Guwahati
  • 30. CORRESPONDENCE FOR THE MONTH OF OCT-22 Outgoing: Team Leader To Contractor : S LNo Referance No Date S ubject Address 1 TL / ASR IP/ CONT/ R I-5/ 2022/ 226 15.10.2022 R egarding Delay in Submis s ion of MPR SHIVAM BHAR TIA (JV) Dhakuakhana 2 TL / ASR IP/ CONT/ R I-5/ 2022/ 229 15.10.2022 R egarding R eviewsof CSC R oad s afety E ngineer on Submitted document Traffic and R oad Safety Manual. SHIVAM BHAR TIA (JV) Dhakuakhana 3 TL / ASR IP/ CONT/ R I-2/ 2022/ 237 17.10.2022 R egarding R eview of R einforcement Steel- Balaji Shakti TMT SHIVAM BHAR TIA (JV) Dhakuakhana 4 TL / ASR IP/ CONT/ R I-3/ 2022/ 214 10.10.2022 R eview of T MTbarsof BDG metal & Power Ltd. & SHYAM ME T ALICT MTbars SGCCL -ANPL (JV) Golaghat 5 TL / ASR IP/ CONT/ R I-3/ 2022/ 215 10.10.2022 R eview of TMT BarsR as hmi MetaliksL td SGCCL -ANPL (JV) Golaghat 6 TL / ASR IP/ CONT/ R I-5/ 2022/ 225 15.10.2022 R egarding Delay in Submis s ion of MPR SGCCL -ANPL (JV) Golaghat 7 TL / ASR IP/ CONT/ R I-5/ 2022/ 230 15.10.2022 R egarding R eviewsof CSC R oad s afety E ngineer on Submitted document Traffic and R oad Safety Manual. SGCCL -ANPL (JV) Golaghat 8 TL / ASR IP/ CONT/ R I-5/ 2022/ 234 17.10.2022 R egarding Source Approval of Aggregate SGCCL -ANPL (JV) Golaghat 9 TL / ASR IP/ CONT/ R I-3/ 2022/ 241 26.10.2022 Traffic Divers ion Plan and Safety during Cons truction at CH: 17763 & CH: 17541 SGCCL ANPL (JV) Golaghat 10 TL / ASR IP/ CONT/ R I-3/ 2022/ 243 27.10.2022 Source Approval Of Aggregate SGCCL ANPL (JV) Golaghat 11 TL / ASR IP/ CONT/ R I-3/ 2022/ 245 28.10.2022 Submis s ion of Third Party Tes t R eportsof Admixture (Hind Plas t Super HPC) & Cons truction water (Camp Bore well) SGCCL ANPL (JV) Golaghat 12 TL / ASR IP/ CONT/ R I-4/ 2022/ 218 11.10.2022 R egarding Temporary Divers ion Plan at Chainage 1+090 to 1+150, 1+650 to 1+710 & 3+480 to 3+560 SHIVAM BHAR TIA (JV) Paths ala 13 TL / ASR IP/ CONT/ R I-5/ 2022/ 224 15.10.2022 R egarding Delay in Submis s ion of MPR SHIVAM BHAR TIA (JV) Paths ala 14 TL / ASR IP/ CONT/ R I-4/ 2022/ 242 26.10.2022 R egarding GSB materialsin Site without proper approval SHIVAM BHAR TIA (JV) Paths ala 15 TL / ASR IP/ CONT/ R I5/ 2022/ 212 07.10.2022 R eview of Typical Cros sSection SGCCL -ANPL (JV) Moran 16 TL / ASR IP/ CONT/ R I5/ 2022/ 213 07.10.2022 R eply- R egarding Manufacture Tes t certificate of TATA Steel. SGCCL -ANPL (JV) Moran 17 TL / ASR IP/ CONT/ R I-5/ 2022/ 216 10.10.2022 R eply- R egarding Hindrance L is t from CH: 19+500 to CH: 24+500 SGCCL -ANPL (JV) Moran 18 TL / ASR IP/ CONT/ R I-5/ 2022/ 217 11.10.2022 R eply- R egarding R eview of Plan & Profile from Km. 14+000 to 23+000 SGCCL -ANPL (JV) Moran 19 TL / ASR IP/ CONT/ R I-5/ 2022/ 223 15.10.2022 R egarding Delay in Submis s ion of MPR SGCCL -ANPL (JV) Moran 20 TL / ASR IP/ CONT/ R I-5/ 2022/ 228 15.10.2022 R egarding detailsof Sampling to Identify the exis itng R egarding Detailsof s ampling to identify the exis ting CBRvalue & the R eviewsof CSC SGCCL -ANPL (JV) Moran 21 TL / ASR IP/ CONT/ R I-5/ 2022/ 235 17.10.2022 R egarding Submis s ion of Fine Aggregate (Sand) tes t reportsfor Source Approval. SGCCL -ANPL (JV) Moran 22 TL / ASR IP/ CONT/ R I-5/ 2022/ 236 17.10.2022 R eg. Submis s ion of Granular Sub-Bas e Mix Des ign SGCCL -ANPL (JV) Moran 23 TL / ASR IP/ CONT/ R I-5/ 2022/ 244 28.10.2022 Source approval of Fine Aggregates(Sand) SGCCL -ANPL (JV) Moran 24 TL / ASR IP/ CONT/ R I-5/ 2022/ 247 28.10.2022 R egarding GSB material dumpued in R oadway without proper approval SGCCL -ANPL (JV) Moran 25 TL / ASR IP/ CONT/ R I-5/ 2022/ 227 15.10.2022 R egarding Delay in Submis s ion of MPR S&P SHIVA (JV) Chumoni 26 TL / ASR IP/ CONT/ R I-7/ 2022/ 248 29.10.2022 R egarding R eview meeting at TL office, Fatas il Ambari, Guwahati S&P-SHIVA (JV) Chumoni