This document compares two cement plant revamp projects - Rezzato in Italy and Devnya in Bulgaria. Both were brownfield projects with similar strategic goals. Rezzato used direct execution with European contractors, while Devnya used a lump sum EPC contract with a Chinese contractor. Rezzato had better cost control and schedule performance due to direct management, while Devnya faced challenges with communication, standards gaps, and delays. Lessons highlight the importance of project context in strategy and additional effort needed for cross-cultural projects.
The Construction Industry Productivity Dilemma
Elements of a Successful Project Delivery
Advanced Work Packaging (AWP)
Structure
Deliverables
Practice Model
A vision for our Industry
The federal perspective on transportation funding, research and partnering with the construction industry to advance mobility, sustainability, equity and other goals and what that means for California. Presenters: Chris Long and Chu Wei, FHWA. Presentation made at the CalAPA Fall Asphalt Pavement Conference, Oct. 13, 2021 in Sacramento.
The Construction Industry Productivity Dilemma
Elements of a Successful Project Delivery
Advanced Work Packaging (AWP)
Structure
Deliverables
Practice Model
A vision for our Industry
The federal perspective on transportation funding, research and partnering with the construction industry to advance mobility, sustainability, equity and other goals and what that means for California. Presenters: Chris Long and Chu Wei, FHWA. Presentation made at the CalAPA Fall Asphalt Pavement Conference, Oct. 13, 2021 in Sacramento.
Years in the development, the head of the University of California Pavement Research Center (UCPRC) and the City & County Pavement Improvement Center (CCPIC) discusses the Hot Mix Asphalt specification created specifically for use by cities and counties on local routes with mix properties and testing appropriate for roads that experience a lower volume of traffic. Presented by Dr. John Harvey, Director, University of California Pavement Research Center. at teh
A brief overview of the Perpetual Asphalt Pavement Awards by the Asphalt Pavement Alliance. Presenter: Bob Humer, Asphalt Institute. Presentation delivered Oct. 13, 2021 at the CalAPA Fall Asphalt Pavement Conference in Sacramento.
Caltrans presentation by Jeremy Peterson-Self on the centralization of the Independent Assurance program and impacts to shtakeholders. Delivered May 6, 2020 to the CalAPA Technical Committee webinar.
An overview of the industry efforts to secure long-term Federal funding for roadway improvements, plus highlights of various initiatives underway on the national level, supported by CalAPA, to advance the asphalt pavement industry. Presenter: NAPA President & CEO Audrey Copeland. Presentation delivered Oct. 13, 2021 at the CalAPA Fall Asphalt Pavement Conference in Sacramento.
Private and Public Partnerships Move MainstreamKerry Carey
All across the country, infrastructure projects are in need of repair, and creative organizational solutions are in-demand. Public-Private Partnerships are long-term contracts between a private party and a government entity allowing for an alternative approach to federal, state and municipal construction projects. The private party bears a large share of risk and management responsibility, and remuneration is linked directly to performance. This webinar discusses the nature of this collaboration across sectors.
Presented by:
Gregory Fitch
Black and Veatch
View the on-demand webinar: http://cpe-wpi.hs-sites.com/construction-project-management-webinar-series
This is a presentation created for midwifery students to increase their knowledge and awareness about professionalism, code of ethics of midwives in the Philippines and code of good governance.
In the 21st Century, it has become crucial for leaders to become more responsible. This presentation talks about the importance and the minority research. It continues to integrate culture and how Leaders are required to influence, motivate, and be a role-model for its followers. An interesting presentation to start a discussion.
Years in the development, the head of the University of California Pavement Research Center (UCPRC) and the City & County Pavement Improvement Center (CCPIC) discusses the Hot Mix Asphalt specification created specifically for use by cities and counties on local routes with mix properties and testing appropriate for roads that experience a lower volume of traffic. Presented by Dr. John Harvey, Director, University of California Pavement Research Center. at teh
A brief overview of the Perpetual Asphalt Pavement Awards by the Asphalt Pavement Alliance. Presenter: Bob Humer, Asphalt Institute. Presentation delivered Oct. 13, 2021 at the CalAPA Fall Asphalt Pavement Conference in Sacramento.
Caltrans presentation by Jeremy Peterson-Self on the centralization of the Independent Assurance program and impacts to shtakeholders. Delivered May 6, 2020 to the CalAPA Technical Committee webinar.
An overview of the industry efforts to secure long-term Federal funding for roadway improvements, plus highlights of various initiatives underway on the national level, supported by CalAPA, to advance the asphalt pavement industry. Presenter: NAPA President & CEO Audrey Copeland. Presentation delivered Oct. 13, 2021 at the CalAPA Fall Asphalt Pavement Conference in Sacramento.
Private and Public Partnerships Move MainstreamKerry Carey
All across the country, infrastructure projects are in need of repair, and creative organizational solutions are in-demand. Public-Private Partnerships are long-term contracts between a private party and a government entity allowing for an alternative approach to federal, state and municipal construction projects. The private party bears a large share of risk and management responsibility, and remuneration is linked directly to performance. This webinar discusses the nature of this collaboration across sectors.
Presented by:
Gregory Fitch
Black and Veatch
View the on-demand webinar: http://cpe-wpi.hs-sites.com/construction-project-management-webinar-series
This is a presentation created for midwifery students to increase their knowledge and awareness about professionalism, code of ethics of midwives in the Philippines and code of good governance.
In the 21st Century, it has become crucial for leaders to become more responsible. This presentation talks about the importance and the minority research. It continues to integrate culture and how Leaders are required to influence, motivate, and be a role-model for its followers. An interesting presentation to start a discussion.
iemens Project Manager, Dana Cogocari, and Director with The Colorado High Performance Transportation Enterprise, David Spector, share results and advice on how to keep infrastructure projects on track. Learn how to use technology to break scope into manageable sections, use data to your project’s advantage and collaborate across the entire project team.
A responsive satellite-industry_ka2015_lisi_v02Marco Lisi
Presentation of my paper "A Responsive Satellite Industry for Responsive and Timely Delivered Satellite Systems" at the 21st Ka and Broadband Communications Conference in Bologna, 12-14 October 2015.
Clean Energy Finance and Investment Roadmap OECD.pdfOECD Environment
Third OECD-DOE Workshop: Unlocking finance and investment in offshore wind power and energy efficiency in public buildings in the Philippines, 6-7 March 2024, Makati, Philippines
RPN Manila 2022: Session 2.6 Raffaele della Croce OECD.pdfOECD Environment
This presentation was delivered during the 6th Meeting of the OECD Southeast Asia Regional Programme’s Regional Policy Network on Sustainable Infrastructure, which took place on 25-26 April 2022 in Manila, the Philippines. The OECD’s Public Governance Directorate and Environment Directorate teamed up with the OECD Korea Policy Centre to organise the event. The National Economic and Development Authority (NEDA) of the Philippines co-chaired the event alongside the United States, and the Public Private Partnership Centre of the Philippines graciously provided the venue. For more details about the meeting, including the agenda and a short summary record, please visit: https://www.oecd.org/site/sipa/events/sipa-searp-philippines-2022.htm.
Seminar series for executives in the EPC, AEC, and environmental services sectors. Covers growth strategies that incorporate sustainability and cleantech initiatives.
DISTRCTplus project Good practice guide summarising the 43 selected good practices.
A cross reference showing the relevance of the sub projects to Horizon 2020.
See http://www.districtplus.eu for more information on the project.
Flexibility needs at system level and how RD&I projects are leveraging these ...Leonardo ENERGY
Recording at https://youtu.be/cd5bRnSM0zI
The presentation provides an introduction to flexibility solutions, which can be used to increase efficiency in power systems. The solutions considered for the webinar are network level solutions. This introduction is followed by the presentation of FlexPlan and CoordiNet as examples of RD&I projects where flexibility solutions are being developed to change the power system landscape.
This e-brochure presents the stage of development and future offers for courses and consultancy as resulting from Train-to-nZEB project , financed by HORIZON 2020.
Job Order Contracting and Efficient Construction Project Delivery for Infrastructure Renovation, Repair, Maintenance, Sustainability, and Minor New Construction
2. 2
Italcementi Group at a glance
The world’s fifth largest cement producer
A worldwide presence in 22 countries
An overall staff of 18,000 people
A consolidated production capacity of
approximately 61 million tons
2014 annual sales exceeding 4.1 billion Euro
The first cement company to be listed
on the Italian Stock Exchange since 1925
Over 150 years-old successful business strategy
implemented by a family-driven company at its fifth
generation
3. Italcementi Group
subsidiary organized into 2
main Divisions
CTG – Centro Tecnico di Gruppo
3
Research
&
Development
Technical
Operations
Strategic R&D projects:
materials, products, solutions,
applications and technologies;
environmental impact reduction
and support to the Sustainable
Development action plan.
Monitoring of operating plants
performance
Operational support and technical
assistance to Group Subsidiaries
Management of strategic industrial
Investments
5. 5
Similar Context for Both the Projects
Brownfield projects
Revamping of existing obsolete production lines with marginal capacity
increase
Congested areas and complex tie-in with the existing facilities
6. 6
Similar Context for Both the Projects
Brownfield projects
Revamping of existing obsolete production lines with marginal capacity
increase
Congested areas and complex tie-in with the existing facilities
Similar strategic background
Raw material availability
Strategic position
Reduction of variable costs – readjustment of industrial network
substantial reduction of the actual environmental footprint
7. 7
Similar Context for Both the Projects
Brownfield projects
Revamping of existing obsolete production lines with marginal capacity
increase
Congested areas and complex tie-in with the existing facilities
Similar strategic background
Raw material availability
Strategic position
Reduction of variable costs – readjustment of industrial network
substantial reduction of the actual environmental footprint
Complex relation with local community and local authorities
Many local constraints superimposed to both the projects
Stakeholders management
REZZATO
DEVNYA
8. 8
Similar Context for Both the Projects
Brownfield projects
Revamping of existing obsolete production lines with marginal capacity
increase
Congested areas and complex tie-in with the existing facilities
Similar strategic background
Raw material availability
Strategic position
Reduction of variable costs – readjustment of industrial network
substantial reduction of the actual environmental footprint
Complex relation with local community and local authorities
Many local constraints superimposed to both the projects
Stakeholders management
Stringent Owner requirements
Minimization of the total investment cost within a given target
Minimization of production cost
Utilization of innovative technical solutions
Respect of present BAT being ready for future SD evolution
10. 1
REZZATO
Direct Execution with central interface
coordination by ITALCEMENTI/CTG
35 main purchase orders with 5 major
packages covering 90% of the investment:
Detailed Design
[one multidisciplinary Italian contractor]
Technology Equipment
[one European supplier selected
through competitive bid]
Main Control System
Medium Voltage Distribution
Construction
[one Italian General Contractor
covering the whole construction scope]
EUROPEAN MAIN CONTENT
[made in Italy centered]
DEVNYA
Full Scope EPC Contract on Lump Sum
Turn Key basis assigned through
competitive bid
ITALCEMENTI/CTG Project
Management and Supervision
CHINESE MAIN CONTENT
Project Execution Strategy
10
11. 1
REZZATO
Direct control over the planning and
execution
Higher flexibility/shorter decision
process
Easier communications
DEVNYA
Risk transfer on EPC Contractor
Lighter Project Management
Organization
Single reference for all Project
aspects with integral responsibility
Higher risk of cost overrun
Complex coordination of interfaces
Huge organization effort and higher
Project Management cost
Complex contract management
Very complex communication
(language + cultural background)
Integration of Chinese contractor with
local reality (contractors and
regulations)
Reduced control and visibility over
decisional process
Strength/weakness of the two approaches
11
12. REZZATO
Common reference on EU standards
DEVNYA
Single point of responsibility on the
EPC contractor
Complex coordination of several
subcontractors
Management of congested areas
(due to local lay-out constraints) and
concurrent operation of existing plant
Communication
Gap between Chinese and European
standards
Difficult interface with local
bureaucracy
Big effort from owner Project
Management team to ensure proper
working conditions
12
Health, Safety and Environment
13. REZZATO
Direct control over the engineering
execution
Familiarity with EU standards and
local norms
Easier inspection and quality control
DEVNYA
Single point of responsibility on the
EPC contractor
Owner direct responsibility in front of
the Construction Contractor
Complex interface management
between vendors and construction
Very complex communication due to
different techincal approach and
geographical distance
Difficult and time consuming
management of the local content
(“bulgarization” of the design through
local engineering companies)
Limited control on expediting and
inspection of the material and quality
control
13
Engineering and Supply
14. REZZATO
General Contractor representing a
single point of responsibility for all the
construction disciplines (integrated
approach)
Strict control on planning and
progress and wider room for owner
direct intervention
DEVNYA
Experienced Chinese manpower
installing “their own” equipment (high
productivity)
Integrated management and
responsibility over the supply chain
Complex contract management
Owner direct responsibility to grant
the availability of engineering and
equipment
Lack of “cement experienced”
subcontractors (learning curve)
Limited possibility to import Chinese
manpower
Complex management of local
subcontractors
Difficult integration of Chinese
manpower with local sub-contractors
(language and cultural background
gap)
14
Construction
17. 1
RAW GRINDING + BURNING LINE COST
NOMINAL ANNUAL CLINKER PRODUCTION
COMPARISON OF UNITARY RATES FOR MAIN COST VOICES
DEVNYA REZZATO
[ratio vs. DEVNYA]
Unit Rates for Civil Construction
(Euro/m3 materials + manpower)
557 1305
[2,34]
Unit rates for equipment (Euro/kg) 4,6 7,1
[1,54]
Unit rates for structural steel
(Euro/kg)
1,6 2,7
[1,69]
Labor Cost “all in” (Euro/MHR) 19,5 50,4
[2,58]
Erection Productivity (hours/ton steel) 74,3 41,7
[0,56]
Erection unit rate
(Euro/kg steel)
1,4 2,1
[1,5]
DEVNYA = 82,2 €/Ton
REZZATO = 111,8 €/Ton [1,36 x Devnya]
Costs
17
18. 1
REZZATO PROJECT COMPLETED IN
LINE WITH THE BASELINE SCHEDULE
[start up 25 months from equipment
purchase order]
DEVNYA PROJECT CUMULATED
5 MONTHS OVERALL DELAY AGAINST
THE CONTRACTUAL BASELINE
[baseline = 26 months from Contract –
Actual duration = 31 months from
Contract signature]
Difficult start up - excellent respect of
the updated forecast since May 2013
Substantial respect of the baseline with
few minor adjustments along the execution
– progress gap in the close out mainly due
to postponement of ancillary activities after
start up
18
Time
19. REZZATO
NEED OF VERY ACCURATE BASIC
DESIGN AND MANAGEMENT
TOOLS: Positive return on the
approach provided that a very
accurate and detailed preparation
and planning is carried out before the
start of the execution phase
Packaged approach is a winning
strategy BUT maximum attention to
the RISK OF FORCING SUPPLIERS
OUT OF THEIR “USUAL” SCOPE
LIMITS
DEVNYA
Ensure the IN DEEP
UNDERSTANDING OF THE
PROJECT CONTEXT by the EPC
contractor through the definition of
pre-agreements with local contractors
INVEST IN COMMUNICATION
SKILLS through cultural mediators
able to facilitate the mutual
understanding
Detailed verification and joint review
of the project schedule before the
signature of the contract to ensure
ADEQUATE CONTROL TOOLS ARE
IN PLACE SINCE DAY 1
19
Lessons learnt
21. 2121
Conclusions
The correct choice of the purchasing and execution strategy in addition
to a very strict control of engineering, construction and commissioning
is fundamental to respect time and costs
The projects of the new line in Rezzato and Devnya represent a strong
effort to arrange technological innovation, sustainability and project
execution proceeding at the same pace for the success of the initiative
The Project context plays a key role in the definition of the Project
Execution Strategy
Adoption of Chinese contractors requires an additional Project
Management effort and wider time contingencies usually not properly
taken into account in the selection process and cost comparison
Virtuous integration of Chinese and European content is possible
provided that adequate preparation work is carried out
For innovative technology applications and complex revamping/brownfield
works, European/Italian suppliers/contractors do have a significant
advantage vs. low cost countries competitors