1. Key deliverables :
Run plant as profit centre with team work
Optimize the resources allocated to the factory in order to meet business requirements in
terms of quality, delivery timeframe, and cost.
To meet customer’s demand and satisfy them.
To meet the targets, decide / participate in long range plan
Take corrective actions where and when needed in matters of factory Operations
To have complete charge of Gate entry to Gate exit including material planning and
inventory control
Identify clientele’s needs and industry trends to constantly update offering of innovative,
high quality, and cost effective range of products and services.
Implement cost reduction measures.
Ensure optimal production efficiency and design and implement advanced industrial
techniques to be used for various manufacturing processes.
To contribute the raising of the overall professionalism in the factory.
New Product development from drawing board to Market. Handled export orders like
USA, China, Brazil, Canada, UAE etc.
Develop and communicate the factory strategies for all Departments under management.
Manage staff responsibilities, authorities and accountabilities.
Provide direction and guidance necessary to ensure efficient and cost effective business
operations, within annually approved operating and capital budgets.
2. Prepare short and medium term plans for operations and production to meet the
given factory objectives.
Manage the preventive maintenance system for machinery, tools, vehicles, and
other assets of the factory.
Assure adequate supply of raw materials and produce quality products in a timely
and effective manner.
To monitor customer satisfaction levels in terms of product quality and speed of
delivery.
Will be able to run and implement ERP in the plant and can be catalyst to
implement required module like Material management , Engineering , stores
distribution module etc. and have fair knowledge of costing , account receivable
and account payable module and it’s integration with each other.
Project management, have thorough knowledge of issue, problem and solution
for continuous line production , achieve yearly production target levels.
Production planning for the conduct of manufacturing in its complete production
cycle; Order placement, Engineering and Design, Production, and Quality control.
3. Strength
Strong Engineering back ground
Firm believer in process than people
Have fair idea of material flow from gate entry to gate exist
Data analysis , good communicator
Analytical , problem solving
Strong knowledge of ISO 9001-QMS , 14001-ESH and OHSAS18000-Safety
Hard working and tough task master, if required.
Project management and vendor development
Good listener .
Have handled Export and domestic client including inter company .
Strong Link between Plant and Service team
4. Profile Summary
A competent professional with over 30 years of experience in Operation, Project Management,
Warehouse management / parts operation OEM Development & Quality Assurance. Adept at
managing Engineering Operations involving design & development, developing detailed
drawing for transmission production, co-ordination with internal departments and Complete
launch of the product.
Capabilities in implementing various strategies for achievement of project target, operational
excellence & value engineering initiatives. Exposure in coordinating Manufacturing / Product
Development processes. Skilled in performing engineering duties as well as implementing
application of standard engineering principles and practices. Successfully managed multiple
projects and milestones while ensuring projects complied with all cost, design and standard
specifications.
Capabilities in building dynamic teams across operational areas spanning manufacturing,
materials, systems implementation and product development. Excellent relationship
management, analytical & negotiation skills with deftness in swiftly ramping up projects in co-
ordination with clients
5. Major Projects Executed :
Developed and launched more than 25 models in small reciprocating compressors.
One of the key team member for Global parts development.
Design , developed and installed EPC compressor Packaged for customer like Petrobras –Brazil ,China ,
Fabtech-BPCL , UDHE , APL , Toyo , Reliance, Essar etc.
MRP II facilitator, have implemented “Fourth-shift” and “Mfg-Pro” system from Gate Entry to gate Exit.
Implemented completed Order processing system and it is legacy system, which also links with main system .
This was mainly for sales team with option selection.
Supply chain cum vendor development.
Using oracle base system for order placing on Ingersoll rand intranet.
Complete running of warehouse management
Implemented complete Ware house at Bhiwandi (Mumbai) thru out side agency “ Expeditor”(Outside
Ingersoll Rand plant)
Implementation and driving kanban and other kaizen activity
Running plant on MRP or any other ERP system
Parts management – pricing, development of parts, reverse Engineering, part list, facility and imparting
training in house, support channel partner and customer
Sarbans Oxly Auditor (tester) ISO 9000 auditor, trained in six sigma under yellow belt, Driving Kaizen concept,
Facilitator and auditor for ISO 14000 ESH and OHSAS 18000 for safety
BOM and drawing conformance with Ingersoll rand USA
Developed and made profitable service center cum warehouse and training center with state of art tools,
instruments Global part development at low cost.
Gained extensive of Geometric tolerance ANSI 14.5 (GD&T)
Developed Web base Article of stores item (Catalogue items) with technology like WAP, Ajax, PHP 5.0, Google
doc, etc.
Have taken training in “ 7 Habits of Highly effective people” , “ Quality of leadership”,
Keeping stock control system up to date and planning future capacity requirements
Inventory management , coordinating for obsolesce of parts with SCM and Engg team
Green belt champion
Inventory management
6. Previous Experience
July 2007 – till today Dresser rand India pvt ltd – Manager project Engineering
Nov 86 - jun’07 Ingersoll Rand India ltd as Asst Manager – Service center and Engg- small recip and rotary
Jan'85 – Nov'86: Kolsite Industries, Mumbai as Design Engineer
Feb'84 - Dec'84: Formac Engg. Ltd., Mumbai as Design Engineer
Aug'82 - Feb'84: Mysore Kirloskar Ltd. Harihar as Supervisor (SPM Design Dept.)
Nov'80 - Jun'82: Wipro Products Ltd., Fluid Power Division, Bangalore as Technical Assistant
Jul'80 - Nov'80: Ashok Leyland, Hosur, Tamil Nadu as Jr. Executive
Education
1.0 Graduate in Materials Management, I.I.M.M, Bangalore, 1999 - (Recognized by Ministry of HRD)
http://www.iimm.org/education/graduate_dip_materialsmanagement.htm
2.0 Diploma in Management, IGNOU, Ahmedabad Center, 1994 http://www.ignou.ac.in/
3.0 Post graduate Diploma in Production Management, 1982
St. Josheph College, Bangalore
4.0 National Forman ship course, FTI, Bangalore, 1980 - (Govt. of India, Ministry of labor, DGE &T0)
http://dget.nic.in/ , http://www.studentsguide.in/technical-training-courses/foremen-training-institute-bangalore.html
5.0 Diploma in Mechanical Engg, Gujarat Education Board, 1978
Other Courses
Oracle/Developer 2000 from SSI Ahmedabad in Feb’99
Trainings /Additional Courses
IR-USA: Engineering and quality for 15 months
IR- Singapore: TAVANT training – ( Global Warranty system)
IR B’lore: Sarbanes oxely tester, VFD and air end rebuilt.
IR, DR Naroda:Management development program , Six sigma yellow belt , ISO 9000 internal auditor,
Communication skill, team building crosby’s quality concept , Internal auditor for ISO 14000 & OSHAS 18000
DR Malaysia: Quality of Leader ship -2010
IT Skills
Design Tools: AutoCAD
Operating System: WinNT, WIN 2000, Window XP
Others: Exposure to VA/VE. MFG-Pro (ERP system)
Packages: MS-Office (Word, Excel, PowerPoint, Access), Win Projects, Primavera
Personal Details
Date of Birth: 25th February 1959
Address: 502 , Abhijyot Apartment, Near Neha Park society, near Bileshwar mahadev temple, Jodh pur Gam, Satellite
Ahmedabad-380015
http://www.linkedin.com/home?trk=hb_tab_home