Lancaster SolarLancaster Solar
Presentation OverviewPresentation Overview
• Background Information
• Why Solar?
• Site Selection
• Site Details
• Ownership model
• Management
• Next Steps
Background InformationBackground Information
• Lancaster – Worcester County; population 7,026
• Lancaster becomes a Green Community in 2010
- Reduce energy consumption by 20%
• Additional Goal: offset 100% non-enterprise
consumption
- 680,000 kWh/year
• Many innovative measures already taken to
improve efficiency
Why Solar?Why Solar?
• No wind!
• Incentives Available for Solar
- Net Metering
- SRECs
• Land
Available
Site SelectionSite Selection
• Feasibility Study
- All rooftops
- All Municipal land
• Rooftops
- Not enough load capacity
• Landfill was best Municipal Land
- 72 acre parcel
- Abutters are far
- Zoned Appropriately
Site DetailsSite Details
• 72 acre parcel
• 10 acre cap
• Capacity: 0.5 MW
- 610,000 kWh/yr (Goal was
680,000 kWh/yr)
Ownership ModelOwnership Model
REVENUE: $173,000 /yr (SREC
sales at $285)
- SRECs paying the bond
• Net metering avoided cost is
profit (est. $85,400 /yr)
• Taking advantage of low
hanging fruit
COST: $2.5 Million
• Received Congressional
earmark of $0.5 Million
• Town voted to borrow $2 Million
- Bond Cost: $171,000 /yr
(Principal and Interest)
• Renewable Energy Enterprise
(MGL c.44, SS 53F1/2)
• Separate budget & accounting:
• SRECs
• Net Metering
• Isolate debt service from general
fund
• Isolate revenue from Town
operating budget
ManagementManagement
Results: project accountability & simplified success and failure tracking
• Town is authoring guidance on allowable enterprise expenses and
revenues
PROCURE
• Equipment
• Installation Services
• Permits
Next StepsNext Steps
BUILD
• Site Preparation
• Panel Install
• Interconnection
Questions & DiscussionQuestions & Discussion

Lancaster Solar

  • 1.
  • 2.
    Presentation OverviewPresentation Overview •Background Information • Why Solar? • Site Selection • Site Details • Ownership model • Management • Next Steps
  • 3.
    Background InformationBackground Information •Lancaster – Worcester County; population 7,026 • Lancaster becomes a Green Community in 2010 - Reduce energy consumption by 20% • Additional Goal: offset 100% non-enterprise consumption - 680,000 kWh/year • Many innovative measures already taken to improve efficiency
  • 4.
    Why Solar?Why Solar? •No wind! • Incentives Available for Solar - Net Metering - SRECs • Land Available
  • 5.
    Site SelectionSite Selection •Feasibility Study - All rooftops - All Municipal land • Rooftops - Not enough load capacity • Landfill was best Municipal Land - 72 acre parcel - Abutters are far - Zoned Appropriately
  • 6.
    Site DetailsSite Details •72 acre parcel • 10 acre cap • Capacity: 0.5 MW - 610,000 kWh/yr (Goal was 680,000 kWh/yr)
  • 7.
    Ownership ModelOwnership Model REVENUE:$173,000 /yr (SREC sales at $285) - SRECs paying the bond • Net metering avoided cost is profit (est. $85,400 /yr) • Taking advantage of low hanging fruit COST: $2.5 Million • Received Congressional earmark of $0.5 Million • Town voted to borrow $2 Million - Bond Cost: $171,000 /yr (Principal and Interest)
  • 8.
    • Renewable EnergyEnterprise (MGL c.44, SS 53F1/2) • Separate budget & accounting: • SRECs • Net Metering • Isolate debt service from general fund • Isolate revenue from Town operating budget ManagementManagement Results: project accountability & simplified success and failure tracking • Town is authoring guidance on allowable enterprise expenses and revenues
  • 9.
    PROCURE • Equipment • InstallationServices • Permits Next StepsNext Steps BUILD • Site Preparation • Panel Install • Interconnection
  • 10.