World FLNG Market Forecast 2015-2021 Leaflet + ContentsDouglas-Westwood
Despite a current pause in commitments to new projects, the capital expenditure (Capex) for FLNG vessels is expected to amount to $35.5bn over 2015-2021. Spending on FSRUs will total $22.8bn over the same period, taking the combined expenditure for the Floating LNG market to $58.3bn. The World FLNG Market Forecast 2015-2021 forecasts activity through to 2021.
Draft Permit Conditions for Proposed Crestwood LPG Storage Facility at Seneca...Marcellus Drilling News
The proposed conditions set for by the NY Dept. of Environmental Conservation if they decide to allow a LPG storage facility to be built in depleted salt caverns along the shores of Seneca Lake, NY. Issued on Nov. 10. The next step in the process will be an issues conference in Horseheads, NY on Feb. 12, 2015.
World FLNG Market Forecast 2015-2021 Leaflet + ContentsDouglas-Westwood
Despite a current pause in commitments to new projects, the capital expenditure (Capex) for FLNG vessels is expected to amount to $35.5bn over 2015-2021. Spending on FSRUs will total $22.8bn over the same period, taking the combined expenditure for the Floating LNG market to $58.3bn. The World FLNG Market Forecast 2015-2021 forecasts activity through to 2021.
Draft Permit Conditions for Proposed Crestwood LPG Storage Facility at Seneca...Marcellus Drilling News
The proposed conditions set for by the NY Dept. of Environmental Conservation if they decide to allow a LPG storage facility to be built in depleted salt caverns along the shores of Seneca Lake, NY. Issued on Nov. 10. The next step in the process will be an issues conference in Horseheads, NY on Feb. 12, 2015.
Descon Engineering, UAE recently completed ENOC Refinery Shutdown-2016 and this Case Study is being written to share the success story with industry professionals. The case study include the introduction, challenges we faced and solution for these challenges. The conclusion include the appreciation from ENOC for completing the project in time, and with highest standard of safety and quality.
2. Offshore Savings
Operator As Contractor Saves
Offshore Installation Costs
Included in the work spread was a 116 ft. by 52 ft. by 9.5 ft. barge equipped with
a 90-ton crawler crane for lifting and pile driving, installing risers and pipeline
tie-ins, and providing a working surface for infield fabrication.
by Scott Hagood, Anadarko
Algeria Corp., Houston;
Edward Perera, lntec Engi-
neering, Houston; and Tahar
Hadji, Tunisian British Ser-
vice, Sfax, Tunisia
C
ercina oil field. loc:ited in the
hallo"· 'aters off hore Sf:tx.
Tunisia. is operated Tunisian
British Sen-ices <TBS>. a joint ,·enrure
company O'ned by BritL"h Gas Tuni-
sia. Ltd. and Enterprise Tuni·ienn1:
d'Activities Pecrolieres CETAPl. Field de·
velopmem began in early 1993 " ·ith
initial production achie,·ed in ~fa·
199-1. Economic viability of thb project
" ·as maintained by optimizing rhe de-
velopment plan. panicubrly h~· inswll·
22 Pipeline & Gas Journal Augu~1 199">
ing pipdines and rel:ned foc:ilitie-,.
: prim1:· example of project opti-
mization 'a:. in the decision to -;eJf-
direct the installation rather than con-
tract ir to an off-.hore in"t:tll:11ion con-
'itructor. ~df-directing the in-.talbtion
pro,·ided the ac.h'antage-, of lower
co~r....•1n.·eleration of the project
schedule. flexibility and imprcl·ed
co111rol o f operation'. c1p:1hilit,· of
using loc:JI -.upplil:r:-. anJ '>en ice~.
and an opportunity to tr:in-,fer tech-
nolog~· from a fe kl'~· exp:ttrbte per-
sonn1.:I to Tuni...ian 'taff member-;.
Utim:llely. tol.ll co' t of the off-
-;hore in.;tall:nion and hookup of four
platform-, and two pipeline hundk'
was :,3. 1 million. Thi:- rvpre~ent;. a
~:ffing-, of · =;."1::, million or 02"• :i-,
compared to :in "8.H"i million lump-
'Ulll hudgL't prit'I.' de d oped for the
::.aml.' ~cop1.: of ork.
Sa,· ing~ of l-t0 11 Wl.'n:: realized in
the o,·er:tll project budget.
Development Plan
''ater dl:'pths in the Cc.:rcina fide!
cont:lin1:•d 'ithin the Kl.'rkenn:th X11.'St
Pl'rmit of onshore and offshore Sfax
,·:iry from six to l 1 f1. TB . the joint
,·enturL' oper:l!or. disco,·ered the
Kerkenn:th ''orth =I <KK:-1) ·ell in
February 1992. This was followed by
the sub~equem sun:e~~ful exploration
wells. KK:'-2 and KK''-3. Aftl.'r fur-
ther appr:1isal drilling. the field was
determined to be economically ·iable
:ind a de,·elopment pl:tn 'as submit-
ted and :tppron•d in February 199j.
.- t o-ph:tse :tppro:tch was called
out in the dl.''elopment plan. Phase I
would consist of an early production
s~ stem <EPSl ro prm ·ide an acceler-
.tted c:tsh flow. Acqui~ition of reser-
'Oir d:ll:t during Ph:tse I ·ould allo'
further field "''·aluation prior to com-
mitting capital exp<:nditurcs for Phase
II. The EPS schem<: utilized tht' three
original discon~ry wells. each 'ith its
o·n wellhead protector platform .
Each ·ell would produce 'ia a +in.
production tlm'line co :t central gath-
ering facility for pro t.'Ssing crnde oil.
After prrn:e1>sing. oil 'Ould he loaded
onto shuttle hargl.'s for transport.
In:>tflll11L'nt gas. and. e·entu:illy.
gaslifr g:t~ 'a~ w be ddi'ered to each
wellhead ,·ia :1 2-in. pipeline bundled
with the 1-in. tlo'lirn.:. X'ith thesl.! acl-
clition..<;. the entire off~hore dl.'n:lop-
mem ':t~ to con~bt of three '1.'llhe:td
pl:trforms. a manifold gathering pl:tt-
form. a sdf-ell.',·:ning production h:trge
'ith proce,sing equipment. and two
-t-in. x 2-in. pipeline bundles " ·ith a
tot:tl length o f fin~ miles. Leased
equipmc-nc " oukl bl' us..:d w henen :!r
possible to minimizl' capital outlay.
Thb accelerated the project by elimi-
nating time:: required to design and
fabricate nc::w. site-specific equipment.
Installation o f the:: platforms.
l:'quipm<:nt. ~ind pipelines was seen
·'' a typical :-.h:illow-'ater project
" ·hich could he done hy rendering a
turnk<:y projl'ct 10 a qualified offshore
3. contractor. It ·as en'isioned th:u
platforms ,,·ould be installed "ith a
conv<::ntional shallo w-draft. crane
barge and pipe laying by laybarge.
The budget price. utilizing input from
various interested contracto rs. of
58.85 million ·::is de,·eloped for the
total workscope.
ince no experienced offshore in-
stallation contractors 'Crt: located in
Tunisia. a lump- um. turnkey tender
packaged was generated and issued
to ,·arious established. pre-qualified
contractors in Europe and the U. . Si-
multaneously. a TBS project team de-
veloped a cost estimate for self-direc-
tion of the acti'ities as an alternati·e.
Evaluation of tender responses
sho·ed agreement with the budgeted
costs whereas a self-direct installation
wa expected to co·t 5-1.') million.
Advantages and Cost Savings
The high tender price dearly ·as
not feasible ·o. therefore. the alter-
nate self-directed plan was proposed
to management. Advantages of this
plan 'S. the lump-sum. turnkey ten-
der ,,·ere:
£. Cost. 'elf-directed in ·tallation
was estimated at a maximum of 5-1.5
million vs. 58.85 million from con-
work with lm:al
contr:tctors. Thi~
allows payment in
local curn:m:y
<minimizing ex-
penditures in h:.trd
curn::ncy ). pro-
'ides employment
( 2.700 m:m-days
for this project >.
and drects a tmns-
fer of technology
so that the country
can continuallY in-
crease its self-~uffi
ciencv.
£.· Flexibility.
tractors tender ·. In a self-directed in-
·t:ilbtion. there i- no requirement for
profit. A profe sional contractor usu-
allv achie,·es a minimum of 20°0
profit on each job to cm·er m·erhe:id
expenses. This amounts to i.-- mil-
lion on the budgeted contract.
-s..."'llulllllMiolt
cosl&, ...,,,,,, mobllizo-
"°"ofOlltnMpent>wl
111111 equlpnlnl, 111111 lllllS of
r,ompkliml ~ rNllW by
•lf-tllNdlng II# o./fslltn
Jtll#ll•projfJCI.
·econdly. there are no high costs
of mobilizing outside personnel and
equipment ince TI3 wa located in
Tunisia. local markt:ts wen: sl!arched
for equipment and Tunisian national ·
fulfilled personnel requiremt:nts. ~lo
bilizarion costs ,,·ere trimmed by
1.23 million.
TBS would install the pipeline by
tow rather than with co1wentional
pipelaying barge . Contractors pre-
pared tenders based on installing the
pipeline hy com·erting a cargo barge
to :.i spud lay barge and calking the
pipe join~ in a con'entional manner.
This is a slow method clue 10 the time
required for " ·elding and radiography.
Also. this method is susceptible to in-
terruptions due to severe weather.
thus increasing cost to the operator.
In TB · plan. pipeline installation
was done ,.ia a series of tmvs. All
pipe welding :tnd makeup activities
occurred onshore. 15 miles from the
installation site. Onshore fabrication
u ·eel 100°0 local labor and experi-
enced minimal exposure to adverse
weather conditions. Actual offshore
inst~illation required l-1 days with
towing ,.s. a bidder's estimate of ten
days ,·ia con,·encio nal pipe laying
methods. Total cost for the pipeline
installation was S-183.615 compared
l o the budget price of 52.23 million.
£. Accelerated schedule. The
contractor who proposed the least
co ·t projected offshore installation
during the summer of 199-+. A self-di-
rected schedule pre pared by TB
showed completion in May. thus ac-
celerating the schedule by as much as
three months.
£. Local Content. As with all na-
tions. Tunisia wants to accomplish
work and lifting
'essds: locating.
procuring . ;ind
preparing a n un-
an:t'pt;1hlc o n-
shore lm::llion for
pipelint.: to"; and
dendoping :1
projt'ct contract
philosophy.
TBS's contract
philosophy ls
summarized by
the following:
£. When pos-
sible. contr:tl'ts
would he exernrcd
on a lump-sum ba-
sb.
With an emphasis
on cost control.
self-directed instal-
lation prm ·ide<l a
great amount of
flexibility. Br elimi-
nating possible pre-
Pipeline welding began in December 1993 by fabricating 21 strings each of 4-
in. and 2-in. pipe. Each string was 1,345 ft. long.
£. Paym ent
wo uld be made
o nly upon com-
pletion of work to
provide maximummium charges for additions or chani.ws
to the original work scope. Tl3S could
cominuallr mcxlify and impro,·e the fa-
cility for no additional rnst. Also. when
we;ither or material dcliwies impacted
progress. the installation plan could hi:.'
mcxlified and work continued r:tther
than incurring downtiim: costs.
Preparation for Installation
After managemc111 appro,·ed the
self-directed installation acti·ities. a
proj1:<.'t tl'am was formed. key pcrson-
nL'I idt.:ntified. and joh re~ponsihilities
,,·1:rc a~sign1:d. Initial work fon1~1:c.I
on lm::iri ng and contracting suitahl1::
inn~nti,·1: for timely compktion. Since
indi,·idual wo rk scopes were ex-
pected to require a maximum of two
months for completion. TllS deemed
it reasonable that a contrnctor would
prn,·id c required working capital
with no immc::diatc:: p:1ymc::nts.
4. • Penalry clauses " ·ould he applied
for schedule deht'S.
• Use of subc~nrracrors 'Ould be
minimized to ensure projecr conrrol
and eliminare o,·erhead cosrs inciden-
tal to SLtbconrracting.
Where required. conrr:icrs Yere
execurecl on a clay rare or unit rare
basis. Day rates included offshore la-
bor. inspection ser'ices. constrncrion
vessels. offshore posirioning. and pile
clri'ing. Unir rates were c:illed out for
accommocl:itions :incl meals.
A tender package describing rhe
scope of wo rk and minimum re-
quirements for construction ,.e sels
<;•;as prepared and issued to
Tunisienne. Jlecliterranean. and Eu-
ropean broker " Follo wing sire 'isits
to Malta, Sicily. and France. a con-
rracr was ler for the construction
spread. Incluclecl in rhe spread was
a 116 fr. by 52 fr . by 9.5 fr. barge
equipped with a 90-to n crawler
crane for lifting and pile dri'ing. in-
sralling risers and pipeline tie-ins.
and providing a working surface for
infield fabrication.
Two small tugs of .+oohp. and 750
hp. were contracted for transporting
personnel, moving the barge. and
pipe towing. Also, a smaller. self-pro-
pelled barge <65.5 ft x 23 ft. x 5.5 ft..
260 hp.) was included to supplemenr
the larger barge during hookup op-
erations. Both barges were fitted " ·ith
spud wells rather than anchors for
ease of mooring.
Concurrent with contracting and
mobilization of constructio n ves·els.
a parcel of land was located and
contracted for use 'hile weld ing
and assembling pipeline bundles.
The selected site measured 1.--175 fr.
x 245 ft . and would accommodate
desired piping and 'Ork arrange-
ments. Requirements for this X'Ork
site included: C1> a steep nearshore
region to allo"'· tOYing 'essei(sl to
approach near to rhe pipe end. (2>
easy access under all x·eather con-
ditions. C3l positioned so as to mini-
mize length of the to' ro ure ro rhe
field , (4 ) located in an area 'X-hich
avoided hea')' sea traffic. and (5) a
single lando'X·ner "·ith which ro ne-
gotiate.
A compromise "·as reached since
the site had an extremely shallow
nearshore region. Ho 'e·er. this
was reaso na ble since areas 'irh
steep nears hore regions 'ere al-
ready used as ports and harbors.
Site preparation began immediately
with le·eling follo'ecl by construc-
tion of sa nd berms ro sen-e as
Construction of the platforms was completed in February. Installation and
pile driving on four permanent platforms required 14 days after which the
jackup barge/production facility was towed to the site and installed.
piperacks. After stringing pipe o n
the sand berms. a lump-sum conrract
'as ex<:cutt!d for pipe·elding and
radiographic inspection serYices.
Pipeline Yelcling began in De-
cemher 1995 and included fahrica-
rio n of 21 strings each of +in. and
2-in. pipe.Each string 'as 1..3--1'1 ft.
long and 'Ork ':ts to he completed
in .30 days. A lump-sum payment
·ould IK· made at that time. During
the follo'ing .J;1nuary and February
l99 1. pipe strings " ·ere cleaned by
pigging to ensure remo,·al of debris
which could affecr post installario n
pigging. Also . a holida y derecror
was used ro inspecr and ,·crify in-
tegrity of the pipeline coating and
any necessary repairs ,,·ere made.
Bracl.!ld-rype anode:, 'ere installed
for corrosion protecrion and pipe
bundll's co nsisring of o ne 1-in. and
one +in. pipdine srring were steel
banded. Flotation de·ices " ·ere in-
srallcd e·e ry 10 fr. as required to
achie'e huoya ncy.
Construction of the rlatforms 'aS
completed in February and an order to
mobilize 'as issued to the construc-
tion n.'ssel surrlier. Jnsra!lation and
pill' dri'ing on the fou r 1x ·r111anenr
platforms required l--1 clays :1fter Yhich
rhe jackup h:trge production facility
':ts tm·ed to rhe site and insr:tlled.
Onh· 18 cl:t'S 'ere needed ro in ·tall
rhe pl:mned. fiw plarform srrucrures.
After installing rhe platforms. pipe-
line WYs began. A - 50 hp. tug ro'cd
1..3-1'1-ft. pipe bundles into rhe field
·here a crane barge would perform
tie-ins. In a parallel operation. the
smaller. self-propelled barge was
completing hookup of the platform.
Pipdine to'ing depended upon high
tide condirions since the onshore site
had a gradual slope in the nearshore
region. This required the towing ves-
sel to remain a half mile offshore .
Tm'ing began with the placement of
a pipe bundle on the launchway roll-
ers and rhen pulling/pushing it off-
shore 'ith a rractor and cleaclman ar-
rangement. Local fishing boats were
hired to hold tension on the pipe
pulling head and to direct the pipe to
a 'airing tug.
Onshore pipeline tie-ins could not
be made prio r to the to'X· so. upon
pulling one 1..3--15 ft. bundle off the
launchway. a second bundle was at-
tached to the first 'ith a cable.
shackle. and swi,·el. The acrual to'
route 'as straight. 15.5 miles long.
and had a minimum interaction 'ith
other ·esscls. All tO'S were com-
plered une,·enrfully in 19 clays. Fol-
lo'ing installation. all pipelines were
pigged and hydrotestecl prior ro com-
missioning.
The Cercina field Yas commis-
sioned on ;lay 19. 199'1. Not only was
it a significant e·enr for Tunisia. but
also ir prodded :111 example of a joinr
n ·nture company successfully com-
bining incountry kno'leclge and abil-
ity 'ith specialized expatriate exper-
tise to achie'C project goals in an effi-
cienr manner. P&GJ