SlideShare a Scribd company logo
Greig Consulting, Norway and the UAE
W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061,
No Networked Baseline?
Then Create One by Untangling a Later Update!
A paper by David Greig of Greig Consulting
Delay analysts are frequently frustrated when a client does not retain a
softcopyversionof theirbaseline programme. Here,David Greig of Greig
Consulting examines how a networked baseline programme can possibly
be constructed by rolling backwards a later produced update programme.
Introduction
Baseline programmes are often considered an essential prerequisite for conducting delay
analysis exercises or simply for assessing the value that a damage caused. If however, a
baseline programme is not available in soft copy format1
, but a later update programme2
is, it
may be possible to remove update data from the update and so roll it backwards to reconstruct
a networked baseline programme upon which the update was likely based.
Procedure
Typically, when updating a programme, project planners do not alter the activity Original
Duration3
(OD) nor change the activity to activity logic4
(SS Start-to-Start, FF Finish-to-Finish
1 If a programme is onlyavailable in hard copy of fixed PDF only the information thatis visuallyrecorded can be
deduced. It is common thatsuch hard copy will include:(Early) Start and (Early) Finish dates and Total Float and
perhaps identifycertain inter-activity linkage only.
2
Updated programmes are usually,though not always,prepared based on earlier update programmes or the
original baseline programme.
3
An activity mightbe executed in a longer period than planned. However,the planning software usuallyretains
the OD unless specificallyaltered.
4
The actual sequence ofworks is usually,to some degree,variantfrom the originallyplanned,usuallythe la g
period is different, though less so,the activity link type.
Greig Consulting, Norway and the UAE
W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061,
or FS Finish-to-Start) to reflect revised works sequences or logic changes.Similarly, Variations
works, if added, are often incorporated as stand-alone Fragnets5
.
AACE No. 29R-03 (2.1, D, 3)6
provides a general procedure to recreate the baseline
programme by such a process, which I have modified and extended as follows:
i) Establish an updated programmein soft copy format, closet to project commencement.
ii) Identify all activities with Activity Progress >0%, remove any Actual Start (AS) status
and Actual Finish (AF) status. (Note: The dates may during this step).
iii) Set all activities to illustrate 0% Progress Completion.
iv) Set all activity Remaining Durations (RD) to equal to the Original Duration (OD)7
.
v) Set the programme’s Data Date (DD) to the start of the project. (i.e. Such as the Notice
to Proceed).
v) Re-schedule the programme.
v) Compare the programme dates and Total Float period to those on the hard copy of the
baseline programme and identify any variances (if any).
vi) If necessary, adjust the programme, by altering the activity durations and logic to
create a best-fit to the hard copy version of the Baseline Programme. Initially,
concentrate only on the early dates, and start at the beginning of the programme and
working forwards in time8
, rescheduling after each alteration working through until
completion. Once the correct Completion Date is established (by the early dates),
work backwards from the end altering the activity link lag periods such that only the
Late Dates and periods of Total Float (after each reschedule) are affected though do
not implement any significant changes that alter the Early Dates9
.
vii) When presenting the Recreated Baseline Programme in soft copy format narrate its
origins and composition per the procedure described herein.
Note: Before commencing the above process it might to worthwhile to establish exactly how
variant the Update Programme is from the Baseline Programme. Though the latter is only
available in hard copy format one should establish through visual desktop analysis only what:
i) activities have been added, if any;
ii) which activities have been removed, if any,
iii) which activity IDs have altered;
5 A fragnetis a self-contained routine,or mini-programme,often introduced into a programme to representa
specific elementchanged works.
6
https://web.aacei.org/
7
The Original Durations are often recorded on the hard copy (or PDF) of the Baseline Programme,thus adopted
directly if the Update Programme activity Original Durations are different.
8
This practise is referred to as conducting a Forward Pass.
9
This practise is referred to as conducting a Backward Pass.
Greig Consulting, Norway and the UAE
W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061,
iv) activity descriptions that have been altered, or;
v) whether the WBS or Activity Codes have been altered.
Such variances, if significant, it might well mean it is not possible to attain a meaningful
recreated Baseline Programme. But heh, sometimes it’s fun to just try!
About Us
Greig Consulting routinely undertake the above procedure in order to derive at a workable
networked Baseline Programme which is then used as the basis for delay analysis. If you
would, like assistance to undertake such an exercise, to prepare a detailed delays analysis,
full claim preparation or review, please call David Greig on +47 45418061 or email us on
Info@GreigConsulting.Com.
May 2020

More Related Content

What's hot

DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
SHAZEBALIKHAN1
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
Kevin West
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systems
skillern
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
PM SOLUTION PRO| Risk-based Management and Services Inc.
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
Glen Alleman
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
sneha saranya
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
Glen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
Glen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
Glen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
Glen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
Glen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
Glen Alleman
 
Online primavera p6 advanced topics training
Online primavera p6 advanced topics trainingOnline primavera p6 advanced topics training
Online primavera p6 advanced topics training
Ten Six Consulting
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
Glen Alleman
 
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
Association for Project Management
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)
Glen Alleman
 
Applying Monte Carlo Simulation to Microsoft Project Schedules
Applying Monte Carlo Simulation to Microsoft Project SchedulesApplying Monte Carlo Simulation to Microsoft Project Schedules
Applying Monte Carlo Simulation to Microsoft Project Schedules
jimparkpmp
 

What's hot (20)

DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systems
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Online primavera p6 advanced topics training
Online primavera p6 advanced topics trainingOnline primavera p6 advanced topics training
Online primavera p6 advanced topics training
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
Schedule quality – detailed analysis of the main metrics webinar, 27 June 2017
 
Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)Probabilistic Risk Management (With Notes)
Probabilistic Risk Management (With Notes)
 
Applying Monte Carlo Simulation to Microsoft Project Schedules
Applying Monte Carlo Simulation to Microsoft Project SchedulesApplying Monte Carlo Simulation to Microsoft Project Schedules
Applying Monte Carlo Simulation to Microsoft Project Schedules
 

Similar to No Networked Baseline? Then Create One by Untangling a Later Update!

Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docxAppendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
festockton
 
Production Deployment of the New Integrator Project C.docx
Production Deployment of the New Integrator  Project C.docxProduction Deployment of the New Integrator  Project C.docx
Production Deployment of the New Integrator Project C.docx
briancrawford30935
 
Managing ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software ToolsManaging ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software Tools
Ricardo Viana Vargas
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
Plunkettz
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Jaafer Saeed
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Velocity enhanced support- SAP
Velocity enhanced support- SAPVelocity enhanced support- SAP
Velocity enhanced support- SAP
Deepa Nair
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Rapid Application Development & Prototyping
Rapid Application Development & PrototypingRapid Application Development & Prototyping
Rapid Application Development & Prototyping
Median Rupawan
 
Application Transformation Workshop
Application Transformation WorkshopApplication Transformation Workshop
Application Transformation Workshop
VMware Tanzu
 
DMAIC addressed Bearnson S-N tracking for all product.
DMAIC addressed Bearnson S-N tracking for all product.DMAIC addressed Bearnson S-N tracking for all product.
DMAIC addressed Bearnson S-N tracking for all product.
Bill Bearnson
 
Project Management (Business case) asta powerproject 12
Project Management (Business case)  asta powerproject 12Project Management (Business case)  asta powerproject 12
Project Management (Business case) asta powerproject 12
Jeffrey Quevedo
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
Theodore Van Patten, Jr.
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paper
p6academy
 
Executing Deployment & Release Strategies
Executing Deployment & Release StrategiesExecuting Deployment & Release Strategies
Executing Deployment & Release Strategies
OpenSense Labs
 
Software engineering project(srs)!!
Software engineering project(srs)!!Software engineering project(srs)!!
Software engineering project(srs)!!
sourav verma
 
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISONSTATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
ijseajournal
 
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
Software AG
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
carolinef5
 

Similar to No Networked Baseline? Then Create One by Untangling a Later Update! (20)

Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docxAppendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
 
Production Deployment of the New Integrator Project C.docx
Production Deployment of the New Integrator  Project C.docxProduction Deployment of the New Integrator  Project C.docx
Production Deployment of the New Integrator Project C.docx
 
Managing ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software ToolsManaging ERP Implementation Using Basic Software Tools
Managing ERP Implementation Using Basic Software Tools
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Velocity enhanced support- SAP
Velocity enhanced support- SAPVelocity enhanced support- SAP
Velocity enhanced support- SAP
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Rapid Application Development & Prototyping
Rapid Application Development & PrototypingRapid Application Development & Prototyping
Rapid Application Development & Prototyping
 
Application Transformation Workshop
Application Transformation WorkshopApplication Transformation Workshop
Application Transformation Workshop
 
DMAIC addressed Bearnson S-N tracking for all product.
DMAIC addressed Bearnson S-N tracking for all product.DMAIC addressed Bearnson S-N tracking for all product.
DMAIC addressed Bearnson S-N tracking for all product.
 
Project Management (Business case) asta powerproject 12
Project Management (Business case)  asta powerproject 12Project Management (Business case)  asta powerproject 12
Project Management (Business case) asta powerproject 12
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paper
 
Executing Deployment & Release Strategies
Executing Deployment & Release StrategiesExecuting Deployment & Release Strategies
Executing Deployment & Release Strategies
 
Software engineering project(srs)!!
Software engineering project(srs)!!Software engineering project(srs)!!
Software engineering project(srs)!!
 
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISONSTATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
 
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 

Recently uploaded

Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 

Recently uploaded (20)

Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 

No Networked Baseline? Then Create One by Untangling a Later Update!

  • 1. Greig Consulting, Norway and the UAE W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061, No Networked Baseline? Then Create One by Untangling a Later Update! A paper by David Greig of Greig Consulting Delay analysts are frequently frustrated when a client does not retain a softcopyversionof theirbaseline programme. Here,David Greig of Greig Consulting examines how a networked baseline programme can possibly be constructed by rolling backwards a later produced update programme. Introduction Baseline programmes are often considered an essential prerequisite for conducting delay analysis exercises or simply for assessing the value that a damage caused. If however, a baseline programme is not available in soft copy format1 , but a later update programme2 is, it may be possible to remove update data from the update and so roll it backwards to reconstruct a networked baseline programme upon which the update was likely based. Procedure Typically, when updating a programme, project planners do not alter the activity Original Duration3 (OD) nor change the activity to activity logic4 (SS Start-to-Start, FF Finish-to-Finish 1 If a programme is onlyavailable in hard copy of fixed PDF only the information thatis visuallyrecorded can be deduced. It is common thatsuch hard copy will include:(Early) Start and (Early) Finish dates and Total Float and perhaps identifycertain inter-activity linkage only. 2 Updated programmes are usually,though not always,prepared based on earlier update programmes or the original baseline programme. 3 An activity mightbe executed in a longer period than planned. However,the planning software usuallyretains the OD unless specificallyaltered. 4 The actual sequence ofworks is usually,to some degree,variantfrom the originallyplanned,usuallythe la g period is different, though less so,the activity link type.
  • 2. Greig Consulting, Norway and the UAE W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061, or FS Finish-to-Start) to reflect revised works sequences or logic changes.Similarly, Variations works, if added, are often incorporated as stand-alone Fragnets5 . AACE No. 29R-03 (2.1, D, 3)6 provides a general procedure to recreate the baseline programme by such a process, which I have modified and extended as follows: i) Establish an updated programmein soft copy format, closet to project commencement. ii) Identify all activities with Activity Progress >0%, remove any Actual Start (AS) status and Actual Finish (AF) status. (Note: The dates may during this step). iii) Set all activities to illustrate 0% Progress Completion. iv) Set all activity Remaining Durations (RD) to equal to the Original Duration (OD)7 . v) Set the programme’s Data Date (DD) to the start of the project. (i.e. Such as the Notice to Proceed). v) Re-schedule the programme. v) Compare the programme dates and Total Float period to those on the hard copy of the baseline programme and identify any variances (if any). vi) If necessary, adjust the programme, by altering the activity durations and logic to create a best-fit to the hard copy version of the Baseline Programme. Initially, concentrate only on the early dates, and start at the beginning of the programme and working forwards in time8 , rescheduling after each alteration working through until completion. Once the correct Completion Date is established (by the early dates), work backwards from the end altering the activity link lag periods such that only the Late Dates and periods of Total Float (after each reschedule) are affected though do not implement any significant changes that alter the Early Dates9 . vii) When presenting the Recreated Baseline Programme in soft copy format narrate its origins and composition per the procedure described herein. Note: Before commencing the above process it might to worthwhile to establish exactly how variant the Update Programme is from the Baseline Programme. Though the latter is only available in hard copy format one should establish through visual desktop analysis only what: i) activities have been added, if any; ii) which activities have been removed, if any, iii) which activity IDs have altered; 5 A fragnetis a self-contained routine,or mini-programme,often introduced into a programme to representa specific elementchanged works. 6 https://web.aacei.org/ 7 The Original Durations are often recorded on the hard copy (or PDF) of the Baseline Programme,thus adopted directly if the Update Programme activity Original Durations are different. 8 This practise is referred to as conducting a Forward Pass. 9 This practise is referred to as conducting a Backward Pass.
  • 3. Greig Consulting, Norway and the UAE W: GreigConsulting.Com, E: David@Greig.Com, T: 00 47 45418061, iv) activity descriptions that have been altered, or; v) whether the WBS or Activity Codes have been altered. Such variances, if significant, it might well mean it is not possible to attain a meaningful recreated Baseline Programme. But heh, sometimes it’s fun to just try! About Us Greig Consulting routinely undertake the above procedure in order to derive at a workable networked Baseline Programme which is then used as the basis for delay analysis. If you would, like assistance to undertake such an exercise, to prepare a detailed delays analysis, full claim preparation or review, please call David Greig on +47 45418061 or email us on Info@GreigConsulting.Com. May 2020