1) The document describes a procedure for reconstructing a baseline program from a later updated program when the original baseline is unavailable in soft copy format. 2) It involves removing progress information and actual dates from the updated program, resetting durations and the data date, and rescheduling to align with the hard copy baseline through iterative forward and backward passes. 3) The goal is to derive a networked baseline program that can be used for delay analysis by fitting the updated program logic and dates to match those in the hard copy baseline as closely as possible.