This document outlines the steps and timeline for developing a new network system. It involved the following phases: 1) Preparation and Planning from November to December 2003, which included developing a project proposal, approving the proposal, and recruiting a project team. 2) Development and Testing from January to March 2004, consisting of specifying requirements, developing a prototype, approving the prototype, and developing a beta version. 3) Implementation from April to June 2004, including testing the beta version, applying final corrections, approving the final version, training users, and rolling out the final version. The document provides a detailed Gantt chart scheduling each task within the project phases.