McGraw-Hill/Irwin Copyright © 2013 by The McGraw-Hill Companies, Inc. All rights reserved.
NPV, Internal Rate of Return (IRR), and the
Profitability Index (PI)
Module 2.3
5-2
5.4 The Internal Rate of Return
 IRR: the discount rate that sets NPV to zero
 IRR the rate that yields a break-even NPV
 Minimum Acceptance Criteria:
 Accept if the IRR exceeds the required return
 Ranking Criteria:
 Select alternative with the highest IRR
 Reinvestment assumption:
 All future cash flows are assumed to be
reinvested at the IRR
5-3
Internal Rate of Return (IRR)
 Disadvantages:
 IRR may not exist
 There may be multiple IRRs
 Problems with mutually exclusive investments
 Advantages:
 Easy to understand and communicate
5-4
IRR: Example
Consider the following project:
0 1 2 3
$50 $100 $150
-$200
The internal rate of return for this project is 19.44%
3
2
)
1
(
150
$
)
1
(
100
$
)
1
(
50
$
200
0
IRR
IRR
IRR
NPV









5-5
IRR example (spreadsheet)
 I used ‘Goal Seek’ to
change the rate cell,
such that my target cell
(NPV cell) is equal to
zero.
 My pink rate cell is the
cell that I ask to change
in Goal Seek. I set the
other rate cells to change
with the pink rate cell.
FV r t PV
50 0.194377042 1 41.86282743
100 0.194377042 2 70.09985282
150 0.194377042 3 88.03734124
Initial Investment
= -200
NPV = 2.14811E-05
5-6
NPV Payoff Profile
0% $100.00
4% $73.88
8% $51.11
12% $31.13
16% $13.52
20% ($2.08)
24% ($15.97)
28% ($28.38)
32% ($39.51)
36% ($49.54)
40% ($58.60)
44% ($66.82)
If we graph NPV versus the discount rate, we can see the IRR
as the x-axis intercept.
IRR = 19.44%
($100.00)
($50.00)
$0.00
$50.00
$100.00
$150.00
-1% 9% 19% 29% 39%
Discount rate
NPV
5-7
Calculating IRR with Spreadsheets
 You start with the same cash flows as you did for the NPV.
 You may use the IRR function:
 You first enter your range of cash flows, beginning with the
initial cash flow.
 You can enter a guess, but it is not necessary.
 The default format is a whole percent – you will normally
want to increase the decimal places to at least two.
Again, I prefer to not use the IRR function, and
instead use “goal seek” to find IRR, but using
the IRR function is fine
5-8
5.5 Problems with IRR
 Multiple IRRs
 The Scale Problem
 The Timing Problem
5-9
Mutually Exclusive vs. Independent
 Mutually Exclusive Projects: only ONE of several
potential projects can be chosen, e.g., acquiring an
accounting system.
 RANK all alternatives, and select the best one.
 Independent Projects: accepting or rejecting one
project does not affect the decision of the other
projects.
 Must exceed a MINIMUM acceptance criteria
5-10
Multiple IRRs
There are two IRRs for this project:
0 1 2 3
$200
$800
-$200 - $800
($100.00)
($50.00)
$0.00
$50.00
$100.00
-50% 0% 50% 100% 150% 200%
Discount rate
N
P
V
100% = IRR2
0% = IRR1
Which one should
we use?
5-11
The Scale Problem
Would you rather make 100% or 50% on your
investments?
What if the 100% return is on a $1
investment, while the 50% return is on a
$1,000 investment?
5-12
The Timing Problem
0 1 2 3
$10,000 $1,000
$1,000
-$10,000
Project A
0 1 2 3
$1,000 $1,000 $12,000
-$10,000
Project B
5-13
The Timing Problem
($5,000.00)
($4,000.00)
($3,000.00)
($2,000.00)
($1,000.00)
$0.00
$1,000.00
$2,000.00
$3,000.00
$4,000.00
$5,000.00
0% 10% 20% 30% 40%
Discount rate
NPV
Project A
Project B
10.55% = crossover rate
16.04% = IRRA
12.94% = IRRB
5-14
Note on interest rate sensitivity
 See on prior slide that NPV of project B is
more sensitive to interest rates.
 This is because it’s cash flows are more
heavily weighted in the future.
 We will see this concept again with bond
valuation
 Bonds with longer maturity (or more heavy
weight of cash flows going to holder in the
future) will have valuations more sensitive to
interest rate changes
5-15
Calculating the Crossover Rate
Compute the IRR for either project “A-B” or “B-A”
Year Project A Project B Project A-B Project B-A
0 ($10,000) ($10,000) $0 $0
1 $10,000 $1,000 $9,000 ($9,000)
2 $1,000 $1,000 $0 $0
3 $1,000 $12,000 ($11,000) $11,000
($3,000.00)
($2,000.00)
($1,000.00)
$0.00
$1,000.00
$2,000.00
$3,000.00
0% 5% 10% 15% 20%
Discount rate
N
P
V
A-B
B-A
10.55% = IRR
5-16
NPV versus IRR
 NPV and IRR will generally give the same
decision.
 Exceptions:
 Non-conventional cash flows – cash flow signs
change more than once
 Mutually exclusive projects
 Initial investments are substantially different
 Timing of cash flows is substantially different
5-17
5.6 The Profitability Index (PI)
 Minimum Acceptance Criteria:
 Accept if PI > 1
 Ranking Criteria:
 Select alternative with highest PI
5-18
The Profitability Index
 Disadvantages:
 Problems with mutually exclusive investments
 Advantages:
 May be useful when available investment funds
are limited
 Easy to understand and communicate
 Correct decision when evaluating independent
projects
 Obviously a close cousin to the NPV
5-19
Example of Investment Rules
Compute the IRR, NPV, PI, and payback period
for the following two projects. Assume the
required return is 10%.
Year Project A Project B
0 -$200 -$150
1 $200 $50
2 $800 $100
3 -$800 $150
5-20
Example of Investment Rules
Project A Project B
CF0 -$200.00 -$150.00
PV0 of CF1-3 $241.92 $240.80
NPV = $41.92 $90.80
IRR = 0%, 100% 36.19%
PI = 1.2096 1.6053
Payback = 1 year (3?) 2 years
5-21
Project A
Project B
($200)
($100)
$0
$100
$200
$300
$400
-15% 0% 15% 30% 45% 70% 100% 130% 160% 190%
Discount rates
NPV
IRR 1(A) IRR (B)
NPV profiles of both projects
IRR 2(A)
Cross-over Rate
5-22
5.7 The Practice of Capital Budgeting
 Varies by industry:
 A few firms may use payback if they are in need of
cash (liquidity).
 The most frequently used technique for large
corporations is a combination of NPV and
IRR.
 It is common to build out NPV profiles (which
incoporates IRRs) and conduct sensitivity
analysis (covered in module 3)
5-23
Summary – Discounted Cash Flow
 Net present value
 Difference between market value and cost
 Accept the project if the NPV is positive
 Has no serious problems
 Preferred decision criterion
 Internal rate of return
 Discount rate that makes NPV = 0
 Take the project if the IRR is greater than the required return
 Same decision as NPV with conventional cash flows
 IRR is unreliable with non-conventional cash flows or mutually exclusive
projects
 Profitability Index
 Benefit-cost ratio
 Take investment if PI > 1
 Cannot be used to rank mutually exclusive projects
 May be used to rank projects in the presence of capital rationing
5-24
Summary – Payback Criteria
 Payback period
 Length of time until initial investment is recovered
 Take the project if it pays back in some specified period
 Does not account for time value of money, and there is an
arbitrary cutoff period
 Discounted payback period
 Length of time until initial investment is recovered on a
discounted basis
 Take the project if it pays back in some specified period
 There is an arbitrary cutoff period

Mosedddddddddddddddddddddddddddule-2_3-1eentzy.pptx

  • 1.
    McGraw-Hill/Irwin Copyright ©2013 by The McGraw-Hill Companies, Inc. All rights reserved. NPV, Internal Rate of Return (IRR), and the Profitability Index (PI) Module 2.3
  • 2.
    5-2 5.4 The InternalRate of Return  IRR: the discount rate that sets NPV to zero  IRR the rate that yields a break-even NPV  Minimum Acceptance Criteria:  Accept if the IRR exceeds the required return  Ranking Criteria:  Select alternative with the highest IRR  Reinvestment assumption:  All future cash flows are assumed to be reinvested at the IRR
  • 3.
    5-3 Internal Rate ofReturn (IRR)  Disadvantages:  IRR may not exist  There may be multiple IRRs  Problems with mutually exclusive investments  Advantages:  Easy to understand and communicate
  • 4.
    5-4 IRR: Example Consider thefollowing project: 0 1 2 3 $50 $100 $150 -$200 The internal rate of return for this project is 19.44% 3 2 ) 1 ( 150 $ ) 1 ( 100 $ ) 1 ( 50 $ 200 0 IRR IRR IRR NPV         
  • 5.
    5-5 IRR example (spreadsheet) I used ‘Goal Seek’ to change the rate cell, such that my target cell (NPV cell) is equal to zero.  My pink rate cell is the cell that I ask to change in Goal Seek. I set the other rate cells to change with the pink rate cell. FV r t PV 50 0.194377042 1 41.86282743 100 0.194377042 2 70.09985282 150 0.194377042 3 88.03734124 Initial Investment = -200 NPV = 2.14811E-05
  • 6.
    5-6 NPV Payoff Profile 0%$100.00 4% $73.88 8% $51.11 12% $31.13 16% $13.52 20% ($2.08) 24% ($15.97) 28% ($28.38) 32% ($39.51) 36% ($49.54) 40% ($58.60) 44% ($66.82) If we graph NPV versus the discount rate, we can see the IRR as the x-axis intercept. IRR = 19.44% ($100.00) ($50.00) $0.00 $50.00 $100.00 $150.00 -1% 9% 19% 29% 39% Discount rate NPV
  • 7.
    5-7 Calculating IRR withSpreadsheets  You start with the same cash flows as you did for the NPV.  You may use the IRR function:  You first enter your range of cash flows, beginning with the initial cash flow.  You can enter a guess, but it is not necessary.  The default format is a whole percent – you will normally want to increase the decimal places to at least two. Again, I prefer to not use the IRR function, and instead use “goal seek” to find IRR, but using the IRR function is fine
  • 8.
    5-8 5.5 Problems withIRR  Multiple IRRs  The Scale Problem  The Timing Problem
  • 9.
    5-9 Mutually Exclusive vs.Independent  Mutually Exclusive Projects: only ONE of several potential projects can be chosen, e.g., acquiring an accounting system.  RANK all alternatives, and select the best one.  Independent Projects: accepting or rejecting one project does not affect the decision of the other projects.  Must exceed a MINIMUM acceptance criteria
  • 10.
    5-10 Multiple IRRs There aretwo IRRs for this project: 0 1 2 3 $200 $800 -$200 - $800 ($100.00) ($50.00) $0.00 $50.00 $100.00 -50% 0% 50% 100% 150% 200% Discount rate N P V 100% = IRR2 0% = IRR1 Which one should we use?
  • 11.
    5-11 The Scale Problem Wouldyou rather make 100% or 50% on your investments? What if the 100% return is on a $1 investment, while the 50% return is on a $1,000 investment?
  • 12.
    5-12 The Timing Problem 01 2 3 $10,000 $1,000 $1,000 -$10,000 Project A 0 1 2 3 $1,000 $1,000 $12,000 -$10,000 Project B
  • 13.
    5-13 The Timing Problem ($5,000.00) ($4,000.00) ($3,000.00) ($2,000.00) ($1,000.00) $0.00 $1,000.00 $2,000.00 $3,000.00 $4,000.00 $5,000.00 0%10% 20% 30% 40% Discount rate NPV Project A Project B 10.55% = crossover rate 16.04% = IRRA 12.94% = IRRB
  • 14.
    5-14 Note on interestrate sensitivity  See on prior slide that NPV of project B is more sensitive to interest rates.  This is because it’s cash flows are more heavily weighted in the future.  We will see this concept again with bond valuation  Bonds with longer maturity (or more heavy weight of cash flows going to holder in the future) will have valuations more sensitive to interest rate changes
  • 15.
    5-15 Calculating the CrossoverRate Compute the IRR for either project “A-B” or “B-A” Year Project A Project B Project A-B Project B-A 0 ($10,000) ($10,000) $0 $0 1 $10,000 $1,000 $9,000 ($9,000) 2 $1,000 $1,000 $0 $0 3 $1,000 $12,000 ($11,000) $11,000 ($3,000.00) ($2,000.00) ($1,000.00) $0.00 $1,000.00 $2,000.00 $3,000.00 0% 5% 10% 15% 20% Discount rate N P V A-B B-A 10.55% = IRR
  • 16.
    5-16 NPV versus IRR NPV and IRR will generally give the same decision.  Exceptions:  Non-conventional cash flows – cash flow signs change more than once  Mutually exclusive projects  Initial investments are substantially different  Timing of cash flows is substantially different
  • 17.
    5-17 5.6 The ProfitabilityIndex (PI)  Minimum Acceptance Criteria:  Accept if PI > 1  Ranking Criteria:  Select alternative with highest PI
  • 18.
    5-18 The Profitability Index Disadvantages:  Problems with mutually exclusive investments  Advantages:  May be useful when available investment funds are limited  Easy to understand and communicate  Correct decision when evaluating independent projects  Obviously a close cousin to the NPV
  • 19.
    5-19 Example of InvestmentRules Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 10%. Year Project A Project B 0 -$200 -$150 1 $200 $50 2 $800 $100 3 -$800 $150
  • 20.
    5-20 Example of InvestmentRules Project A Project B CF0 -$200.00 -$150.00 PV0 of CF1-3 $241.92 $240.80 NPV = $41.92 $90.80 IRR = 0%, 100% 36.19% PI = 1.2096 1.6053 Payback = 1 year (3?) 2 years
  • 21.
    5-21 Project A Project B ($200) ($100) $0 $100 $200 $300 $400 -15%0% 15% 30% 45% 70% 100% 130% 160% 190% Discount rates NPV IRR 1(A) IRR (B) NPV profiles of both projects IRR 2(A) Cross-over Rate
  • 22.
    5-22 5.7 The Practiceof Capital Budgeting  Varies by industry:  A few firms may use payback if they are in need of cash (liquidity).  The most frequently used technique for large corporations is a combination of NPV and IRR.  It is common to build out NPV profiles (which incoporates IRRs) and conduct sensitivity analysis (covered in module 3)
  • 23.
    5-23 Summary – DiscountedCash Flow  Net present value  Difference between market value and cost  Accept the project if the NPV is positive  Has no serious problems  Preferred decision criterion  Internal rate of return  Discount rate that makes NPV = 0  Take the project if the IRR is greater than the required return  Same decision as NPV with conventional cash flows  IRR is unreliable with non-conventional cash flows or mutually exclusive projects  Profitability Index  Benefit-cost ratio  Take investment if PI > 1  Cannot be used to rank mutually exclusive projects  May be used to rank projects in the presence of capital rationing
  • 24.
    5-24 Summary – PaybackCriteria  Payback period  Length of time until initial investment is recovered  Take the project if it pays back in some specified period  Does not account for time value of money, and there is an arbitrary cutoff period  Discounted payback period  Length of time until initial investment is recovered on a discounted basis  Take the project if it pays back in some specified period  There is an arbitrary cutoff period

Editor's Notes

  • #7 Click on the Excel icon to go to an embedded spreadsheet so that you can illustrate how to compute IRR on a spreadsheet.
  • #10 It is good to mention that the number of IRRs is equivalent to the number of sign changes in the cash flows.
  • #12 The preferred project in this case depends on the discount rate, not the IRR.
  • #13 The cross-over rate is the IRR of project A-B