SlideShare a Scribd company logo
Deliver Fast – with
Governance and
Control
Mini PID
Manoj Agarwal
January, 2017
The purpose of this style of PID is to enable the good management practices that are employed
on larger projects to be used on smaller projects and consultancy assignments including
IA’s.
This document contains the minimal set of PID information that is considered viable to allow a
smaller project still conform to the PRINCE2 philosophy.
If you need more than one page for each of the sections identified then you are probably
supplying too much information - The philosophy behind the PowerPoint PID is to minimise
the amount of text written and speed up the process of Project Initiation. However, feel free
to add additional slides that are diagrammatic in nature (e.g. scope charts, process
diagrams etc). The old adage “a picture paints a thousand words” is particularly relevant to
this approach.
The front cover has deliberately been left sparse to allow you to customise it for your particular
project.
Guidance text has been added to some of the slides - use it, modify it, or delete to suit your
need.
Please delete this slide before you complete this document.
PHILOSOPHY, HINTS & TIPS
Area Page
1 Document Format 4
2 Introduction & Background 5
3 Project Definition
3.1 Objectives 6
3.2 Scope 7
3.3 Approach 8
3.4 Timescales 9
3.5 Major Products 10
3.6 Constraints / Assumptions / Interface / Quality 11
4 Initial Business Case 12
5 Organisation 13
6 Project Controls 14
7 Approvals 15
CONTENTS
This document provides details on the definition of the project, to form the basis for its management and the assessment of
overall success. It is a short form version of a full scale Project Initiation Document and is meant for use on small projects or
individual consultancy assignments.
To ease presentation the document has been broken down into 6 major areas as follows:
• Introduction & Background: This introduces the document, details its purpose and provides information on the
context of the project, and how we have arrived at the current position of requiring a project.
• Project Definition: Explains what the project needs to achieve. Under this heading are the following sub-headings
• Project Objectives
• Project Scope
• Method Of Approach
• Timescales
• Major Products
• Constraints/Assumptions/Interfaces/Quality
• Initial Business Case: Explains why the project is being undertaken
• Organisation: Explains who will be on the Project Management Team:
• Project Controls: lays down how control is to be exercised within the project, and the reporting and monitoring
mechanisms which will support this. This section also includes a statement on the approach to be taken for issue and
risk management.
• Approvals: Allows for formal sign-off of the document by the Project Board and the Project Manager
1 - DOCUMENT FORMAT
2 - INTRODUCTION & BACKGROUND
INTRODUCTION
The purpose of this document is to define the project, to form the basis for its management and the assessment of overall success. There
are two primary uses of the document:
 to ensure that the project has a sound basis before asking the Project Board to make any major commitment to the project
 to act as a base document against which the Project Board and Project Manager can assess progress, change management
issues, and on-going viability questions.
BACKGROUND
3.1 - PROJECT OBJECTIVES
3 - PROJECT DEFINITION
Included: Excluded:
3.2 - PROJECT SCOPE
3 - PROJECT DEFINITION
Stage 1:
Stage 2:
3.3 - METHOD OF APPROACH
3 - PROJECT DEFINITION
3.4 - TIMESCALES
3 - PROJECT DEFINITION
Reference Description Purpose
<ref. no> Project Initiation Document To define the project, to form the basis for its management and the
assessment of overall success.
<ref. no> End Project Report To report to the Project Board on how well the project has performed
against its Project Initiation Document.
3.5 - MAJOR PRODUCTS
3 - PROJECT DEFINITION
Please delete this comment before publication
The two major products shown above are the minimum considered to allow a project to conform to PRINCE2.
They should exist in some form or another - not necessarily with the same names.
CONSTRAINTS
ASSUMPTIONS
INTERFACES
QUALITY
3.6 - CONSTRAINTS / ASSUMPTIONS / INTERFACES / QUALITY
3 - PROJECT DEFINITION
INFORMATION
4 - INITIAL BUSINESS CASE
INFORMATION
5 - ORGANISATION
INFORMATION
6 - PROJECT CONTROLS
Reporting
Meetings
Risk Management
A log of risks and issues will be maintained by the Project Manager
INFORMATION
7 - APPROVALS
Project Executive: _________________________________________
 Date: _____________
Senior User: _________________________________________
 Date: _____________
Senior Supplier: _________________________________________
 Date: _____________
Project Manager: _________________________________________

More Related Content

What's hot

Project Management Paper
Project Management PaperProject Management Paper
Project Management Paper
Pam Simpson
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creep
Onkar Tendulkar
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
Sanjay Vaij
 
Project charter for Six Sigma Project
Project charter for Six Sigma ProjectProject charter for Six Sigma Project
Project charter for Six Sigma Project
ShabanaTasneem2
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
Mudassir Iqbal
 
3 proj plan handouts
3 proj plan handouts3 proj plan handouts
3 proj plan handouts
Tony
 
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
Irawan Herwidjojoadi Haditomo
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and Scoping
Ciprian Rusen
 
Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report Template
Techno-PM PTY LTD
 
03ch
03ch03ch
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
DiptoDey3
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
SAJID ALI RUK
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a project
Keely Killpack, PhD
 
Presentation kick off Presentstion by MM Rahman
Presentation kick off Presentstion by MM RahmanPresentation kick off Presentstion by MM Rahman
Presentation kick off Presentstion by MM Rahman
STM-Skill That Matters
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
Michael James Cyrus
 
How to close a project
How to close a projectHow to close a project
How to close a project
Emmanuel Mwagomba
 
Scope management plan
Scope management planScope management plan
Scope management plan
Sanjay Patel
 
Common Sense Project Management Methodology
Common Sense Project Management MethodologyCommon Sense Project Management Methodology
Common Sense Project Management Methodology
Vasantha Gullapalli
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
Waqar Ali
 

What's hot (20)

Project Management Paper
Project Management PaperProject Management Paper
Project Management Paper
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creep
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Project charter for Six Sigma Project
Project charter for Six Sigma ProjectProject charter for Six Sigma Project
Project charter for Six Sigma Project
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
3 proj plan handouts
3 proj plan handouts3 proj plan handouts
3 proj plan handouts
 
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and Scoping
 
Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report Template
 
03ch
03ch03ch
03ch
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a project
 
Presentation kick off Presentstion by MM Rahman
Presentation kick off Presentstion by MM RahmanPresentation kick off Presentstion by MM Rahman
Presentation kick off Presentstion by MM Rahman
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
 
How to close a project
How to close a projectHow to close a project
How to close a project
 
Scope management plan
Scope management planScope management plan
Scope management plan
 
Common Sense Project Management Methodology
Common Sense Project Management MethodologyCommon Sense Project Management Methodology
Common Sense Project Management Methodology
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 

Similar to Mini PID

Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
Mary Stevenson
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
Sharad Srivastava
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
SabrinaScott22
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
Bogdan Gorka
 
Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management Playbook
Demand Metric
 
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
mayank272369
 
Status reports
Status reportsStatus reports
Status reports
Samir Sami
 
Day 2 scope
Day 2 scopeDay 2 scope
Day 2 scope
Ahmed Elgazzar
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
Renee Jones
 
Pm chapter 7...
Pm chapter 7...Pm chapter 7...
Pm chapter 7...
Golam Bitonsir
 
Pm chapter 7
Pm chapter 7Pm chapter 7
Pm chapter 7
Golam Bitonsir
 
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdfyour-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
hiwotmengistu3
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
GoharSaeed6
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
jessiehampson
 
Project Estimating....The Squeeze is On
Project Estimating....The Squeeze is OnProject Estimating....The Squeeze is On
Project Estimating....The Squeeze is On
Shirley Sartin, PBA, BSAC, CBAP, PMP, CSM
 
I have to submit this assignment after one hour Scope Management Plan.docx
I have to submit this assignment after one hour  Scope Management Plan.docxI have to submit this assignment after one hour  Scope Management Plan.docx
I have to submit this assignment after one hour Scope Management Plan.docx
JacobUasThomsoni
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
Laguna State Polytechnic University
 
A guide for project managers prince2
A guide for project managers prince2A guide for project managers prince2
A guide for project managers prince2
Balasubramanian.C PMP®,ITIL®,PRINCE2®,COBIT®5
 
Scope management term paper
Scope management term paperScope management term paper
Scope management term paper
Muhammad Umar
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptx
DrRRajalakshmi
 

Similar to Mini PID (20)

Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 
Project Management Playbook
Project Management PlaybookProject Management Playbook
Project Management Playbook
 
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
#1 Assignment ObjectivesManaging a Project Schedule400 words.docx
 
Status reports
Status reportsStatus reports
Status reports
 
Day 2 scope
Day 2 scopeDay 2 scope
Day 2 scope
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
Pm chapter 7...
Pm chapter 7...Pm chapter 7...
Pm chapter 7...
 
Pm chapter 7
Pm chapter 7Pm chapter 7
Pm chapter 7
 
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdfyour-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
Project Estimating....The Squeeze is On
Project Estimating....The Squeeze is OnProject Estimating....The Squeeze is On
Project Estimating....The Squeeze is On
 
I have to submit this assignment after one hour Scope Management Plan.docx
I have to submit this assignment after one hour  Scope Management Plan.docxI have to submit this assignment after one hour  Scope Management Plan.docx
I have to submit this assignment after one hour Scope Management Plan.docx
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
 
A guide for project managers prince2
A guide for project managers prince2A guide for project managers prince2
A guide for project managers prince2
 
Scope management term paper
Scope management term paperScope management term paper
Scope management term paper
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptx
 

More from Manoj Agarwal

How to define Your Product Roadmap - Talk at Product School
How to define Your Product Roadmap - Talk at Product SchoolHow to define Your Product Roadmap - Talk at Product School
How to define Your Product Roadmap - Talk at Product School
Manoj Agarwal
 
MVP Demystified - 7 Steps guide to help define your minimum Viable Product
MVP Demystified - 7 Steps guide to help define your minimum Viable ProductMVP Demystified - 7 Steps guide to help define your minimum Viable Product
MVP Demystified - 7 Steps guide to help define your minimum Viable Product
Manoj Agarwal
 
Product management - 7 Steps guide to create your Product Roadmap
Product management - 7 Steps guide to create your Product RoadmapProduct management - 7 Steps guide to create your Product Roadmap
Product management - 7 Steps guide to create your Product Roadmap
Manoj Agarwal
 
Feature Prioritisation - NIMBLE FRAMEWORK
Feature Prioritisation - NIMBLE FRAMEWORKFeature Prioritisation - NIMBLE FRAMEWORK
Feature Prioritisation - NIMBLE FRAMEWORK
Manoj Agarwal
 
Nimble framework product definition v1
Nimble framework   product definition v1Nimble framework   product definition v1
Nimble framework product definition v1
Manoj Agarwal
 
Practical Product Management - Product Definition - NIMBLE FRAMEWORK
Practical Product Management - Product Definition - NIMBLE FRAMEWORKPractical Product Management - Product Definition - NIMBLE FRAMEWORK
Practical Product Management - Product Definition - NIMBLE FRAMEWORK
Manoj Agarwal
 
Digital Transformation - Holistitic Delivery Framework
Digital Transformation - Holistitic Delivery FrameworkDigital Transformation - Holistitic Delivery Framework
Digital Transformation - Holistitic Delivery Framework
Manoj Agarwal
 
Continuous Delivery1
Continuous Delivery1Continuous Delivery1
Continuous Delivery1
Manoj Agarwal
 
Horizon Planning using sliding window - to manage business demand1
Horizon Planning using sliding window -  to manage business demand1Horizon Planning using sliding window -  to manage business demand1
Horizon Planning using sliding window - to manage business demand1
Manoj Agarwal
 
Manoj - IT Oranisation Transformation using POPIT
Manoj - IT Oranisation Transformation using POPITManoj - IT Oranisation Transformation using POPIT
Manoj - IT Oranisation Transformation using POPIT
Manoj Agarwal
 

More from Manoj Agarwal (10)

How to define Your Product Roadmap - Talk at Product School
How to define Your Product Roadmap - Talk at Product SchoolHow to define Your Product Roadmap - Talk at Product School
How to define Your Product Roadmap - Talk at Product School
 
MVP Demystified - 7 Steps guide to help define your minimum Viable Product
MVP Demystified - 7 Steps guide to help define your minimum Viable ProductMVP Demystified - 7 Steps guide to help define your minimum Viable Product
MVP Demystified - 7 Steps guide to help define your minimum Viable Product
 
Product management - 7 Steps guide to create your Product Roadmap
Product management - 7 Steps guide to create your Product RoadmapProduct management - 7 Steps guide to create your Product Roadmap
Product management - 7 Steps guide to create your Product Roadmap
 
Feature Prioritisation - NIMBLE FRAMEWORK
Feature Prioritisation - NIMBLE FRAMEWORKFeature Prioritisation - NIMBLE FRAMEWORK
Feature Prioritisation - NIMBLE FRAMEWORK
 
Nimble framework product definition v1
Nimble framework   product definition v1Nimble framework   product definition v1
Nimble framework product definition v1
 
Practical Product Management - Product Definition - NIMBLE FRAMEWORK
Practical Product Management - Product Definition - NIMBLE FRAMEWORKPractical Product Management - Product Definition - NIMBLE FRAMEWORK
Practical Product Management - Product Definition - NIMBLE FRAMEWORK
 
Digital Transformation - Holistitic Delivery Framework
Digital Transformation - Holistitic Delivery FrameworkDigital Transformation - Holistitic Delivery Framework
Digital Transformation - Holistitic Delivery Framework
 
Continuous Delivery1
Continuous Delivery1Continuous Delivery1
Continuous Delivery1
 
Horizon Planning using sliding window - to manage business demand1
Horizon Planning using sliding window -  to manage business demand1Horizon Planning using sliding window -  to manage business demand1
Horizon Planning using sliding window - to manage business demand1
 
Manoj - IT Oranisation Transformation using POPIT
Manoj - IT Oranisation Transformation using POPITManoj - IT Oranisation Transformation using POPIT
Manoj - IT Oranisation Transformation using POPIT
 

Mini PID

  • 1. Deliver Fast – with Governance and Control Mini PID Manoj Agarwal January, 2017
  • 2. The purpose of this style of PID is to enable the good management practices that are employed on larger projects to be used on smaller projects and consultancy assignments including IA’s. This document contains the minimal set of PID information that is considered viable to allow a smaller project still conform to the PRINCE2 philosophy. If you need more than one page for each of the sections identified then you are probably supplying too much information - The philosophy behind the PowerPoint PID is to minimise the amount of text written and speed up the process of Project Initiation. However, feel free to add additional slides that are diagrammatic in nature (e.g. scope charts, process diagrams etc). The old adage “a picture paints a thousand words” is particularly relevant to this approach. The front cover has deliberately been left sparse to allow you to customise it for your particular project. Guidance text has been added to some of the slides - use it, modify it, or delete to suit your need. Please delete this slide before you complete this document. PHILOSOPHY, HINTS & TIPS
  • 3. Area Page 1 Document Format 4 2 Introduction & Background 5 3 Project Definition 3.1 Objectives 6 3.2 Scope 7 3.3 Approach 8 3.4 Timescales 9 3.5 Major Products 10 3.6 Constraints / Assumptions / Interface / Quality 11 4 Initial Business Case 12 5 Organisation 13 6 Project Controls 14 7 Approvals 15 CONTENTS
  • 4. This document provides details on the definition of the project, to form the basis for its management and the assessment of overall success. It is a short form version of a full scale Project Initiation Document and is meant for use on small projects or individual consultancy assignments. To ease presentation the document has been broken down into 6 major areas as follows: • Introduction & Background: This introduces the document, details its purpose and provides information on the context of the project, and how we have arrived at the current position of requiring a project. • Project Definition: Explains what the project needs to achieve. Under this heading are the following sub-headings • Project Objectives • Project Scope • Method Of Approach • Timescales • Major Products • Constraints/Assumptions/Interfaces/Quality • Initial Business Case: Explains why the project is being undertaken • Organisation: Explains who will be on the Project Management Team: • Project Controls: lays down how control is to be exercised within the project, and the reporting and monitoring mechanisms which will support this. This section also includes a statement on the approach to be taken for issue and risk management. • Approvals: Allows for formal sign-off of the document by the Project Board and the Project Manager 1 - DOCUMENT FORMAT
  • 5. 2 - INTRODUCTION & BACKGROUND INTRODUCTION The purpose of this document is to define the project, to form the basis for its management and the assessment of overall success. There are two primary uses of the document:  to ensure that the project has a sound basis before asking the Project Board to make any major commitment to the project  to act as a base document against which the Project Board and Project Manager can assess progress, change management issues, and on-going viability questions. BACKGROUND
  • 6. 3.1 - PROJECT OBJECTIVES 3 - PROJECT DEFINITION
  • 7. Included: Excluded: 3.2 - PROJECT SCOPE 3 - PROJECT DEFINITION
  • 8. Stage 1: Stage 2: 3.3 - METHOD OF APPROACH 3 - PROJECT DEFINITION
  • 9. 3.4 - TIMESCALES 3 - PROJECT DEFINITION
  • 10. Reference Description Purpose <ref. no> Project Initiation Document To define the project, to form the basis for its management and the assessment of overall success. <ref. no> End Project Report To report to the Project Board on how well the project has performed against its Project Initiation Document. 3.5 - MAJOR PRODUCTS 3 - PROJECT DEFINITION Please delete this comment before publication The two major products shown above are the minimum considered to allow a project to conform to PRINCE2. They should exist in some form or another - not necessarily with the same names.
  • 11. CONSTRAINTS ASSUMPTIONS INTERFACES QUALITY 3.6 - CONSTRAINTS / ASSUMPTIONS / INTERFACES / QUALITY 3 - PROJECT DEFINITION
  • 12. INFORMATION 4 - INITIAL BUSINESS CASE
  • 14. INFORMATION 6 - PROJECT CONTROLS Reporting Meetings Risk Management A log of risks and issues will be maintained by the Project Manager
  • 15. INFORMATION 7 - APPROVALS Project Executive: _________________________________________  Date: _____________ Senior User: _________________________________________  Date: _____________ Senior Supplier: _________________________________________  Date: _____________ Project Manager: _________________________________________