SlideShare a Scribd company logo
1 of 89
BY
ABHINAW KUMAR RAI
ADITYA MISHRA
VISHAL SINGH
SAMBUJ KUMAR
SONA JAMAL HUSSAIN
NANDLAL MANDAL
AJAY KUMAR
RAHUL RANJAN
ELECTRICAL ENGINEERING
BANKURA UNNAYANI INSTITUTE OF
ENGINEERING
2
ACKNOWLEDGEMENT
The dissertation has been prepared based on the vocational
training undergone in a highly esteemed organization of
Eastern region, Maithon Hydel Power Station (MHPS) is located
on the river Barakar about 12.9 km above its confluence with
the Damodar near the border of Dhanbad & Burdwan districts
of the states of Jharkhand & West Bengal respectively. The
unique feature of this is that it is located underground in the
left bank of the river and is the first of its kind in India. The
power station has a total generating capacity of 60 MW with 3
units of 20 MW each. MHPS is located at almost 1000 feet
below the water level,and is the first of its kind, in South East
Asia. I would like to express my heartfelt gratitude to the
authorities of MAITHON HYDEL POWER STATION
and BANKURA UNNAYANI INSTITUTE OF
ENGINEERING for providing me such an opportunity to
undergo training in the Hydel power plant of DVC, MHPS. I
would also like to thank the Engineers, highly experienced
without whom such type of concept building in respect of
Hydel power plantwould not have been possible.
Some of them are:
1: P.GHOSH (Assistant Engineer CLD,DVC MAITHON)
2:NAUSAD HUSSAIN(Chief Engineer G.M.O.D-II KALYANESWARI 220KV SUBSTAION)
3
CONTENT
 TRAINING REPORT FOR PUBLIC RELATION OFFICE 5-20
 DAMODAR VALLEY CORPORATION
 MISSION & VISION
 PIONEERING ROLE
 DVC INFRASTRUCTURES
 DVC POWER STATION
 POWER MAP
 DAMS & BARAGES
 INITIATIVES FOR SOCIAL SECTOR DEVLOPMENT
 TRAINING REPORT FOR CENTRAL LOAD DISPATCH 21-31
 NATIONAL LOAD DISPATCH CENTRE
 THERMAL GENERATION
 CLD MAITHON
 DEMAND FORECASTING & SHEDULING
 HYDEL GENERATION
 TIE LINES
 POWER SYSTEM OPERATION CORPORATON
 SINGLE LINE DAIGRAM OF 220/132KV DVC GRID
 SCADA
 TRAINING REPORT FOR TRANSMISSION DEPARTMENT 32-53
 220 KV KALYANESWARI SUBSTATION
 SINGLE LINE DAIGRAM OF 220 KV
 KALYANESWARI SUB STATION G.O.M.D –II, D.V.C
 RATINGS
 220 KV KALYANESWARI SUBSTATION
 BASIC COMPONENTS OF SUBSTATION
 TRANSMISSION SYSTEM
 GRIDMAP
 SUBSTATION
 ELECTRICAL SUBSTATION MODEL(SIDE VIEW)
 REPORT FOR TRANSMISSION 54-73
SYSTEM CONSTRUCTION
 PROCEDURE OF TSC
 TRANSMISSION ROUTE
 SUREVY OF LINES
 APPROVAL REQUIREMENT
 MINIMUM CLEARANCE
 APPLICATION OF SAG TEMPLATE ON PROFILE
 TOWER CONSTRUCTION : EXCAVATION
MARKING CHART
 TOWER FOUNDATION : PYRAMID
CHIMNEY TYPE
 STRINGING OF CONDUCTORS AND EARTHWIRE
 MINIMUM CLEARANCE : IS: 5613 (Part II/Sec-1)-1976
 TOWER USED FOR TRANSMISSION LINE
4
 TOWER CONSTRUCTION : EXCAVATION MARKING CHART
 STRINGING OF CONDUCTORS AND EARTHWIRE
 Substation construction
 EARTHING OF SUB STATION-
 TRAINING REPORT FOR CENTRAL TESTING CENTER 75-87
 Central Testing Center
 TRANSFORMER OIL
 On-site testing
 DGA or Dissolved Gas Analysis of Transformer Oil
 DGA TESTING OF TRNSFORMERS OF DVC
 MINIMUM DETECTION LIMIT
 ADVANTAGES THAT DGA CAN PROVIDE
 Protective Relay
-.-.-.-.-.-.-.-.-.-.-.-.-.-
5
TRAINING REPORT FOR
PROGRAMME NO. 1 - P.R.O
PUBLIC RELATION OFFICE
06/07/2015 TO 07/07/2015
PRO office,Combined Administrative Building (2nd Floor),Area-6
Damodar Valley Corporation
6
DAMODAR VALLEY CORPORATION
Damodar Valley Corporation is the first ever multipurpose river valley
project of independent India which came into being on July 7, 1948 by an Act
of the constituent Assembly ( Act no. Xiv, 1948).Having command area of 24,325
sq.kms spreading across the damodar basin , boundaries of which transcends
the state of Jharkhand & West Bengal . The upper valley consists of two
entirely districts ( Dhanbad & Bokaro) & eight districts partly ( Hazaribagh,
Koderma, Giridih, chhatra, Palamu, Ranchi, Lohardaga & dumka) in the state of
Jharkhand .The lower valley on the other hand consist of five districts partly
( Burdwan & Hoogly, Howrah,Bankura,& purulia) in the state of West Bengal.Since
the beginning, DVC has given due emphasis on power generation & distribution,
besides flood control and irrigation, eco conservation & socio- economic
development.
Today DVC power is a vital input to core sectors including Steel plants , Railways,
collieries along with State Electricity Boards of Jharkhand & West Bengal, big &
medium industries within & beyond the Damodar Valley.
DVC was set up with the intent of promoting & operating the schemes which may
cause social and economic uplift in the valley region. DVC has already established
it existence in discharging its obligations for more than five decades in perfect
harmony. The difficult but effective water management by Corporation has
turned the devastating river Damodar from ‘River of Sorrow’ to ‘River of
Prospects and opportunities’.Proficient management of water resources through
dams ,canals & barrage, DVC facilitates irrigation as well as industrial & domestic
water supply which at large benefited the region as a whole. It has also
contributed significantly in conservation of soil & promotion of schemes of social
integration in valley area.
7
MISSION & VISION
THE MISSION
The mission at the time of its inception was :
 Flood control
 Promotion & operation of schemes for irrigation
 Water supply for industrial& domestic use
 Navigation & drainage
 Generation , Transmission & Distribution of electrical energy
 Promotion of a forestation and control of soil erosion in valley area
 Promotion of public health , agriculture, industrial, economic & general
well-being in damodar valley
In keeping with industrialisation in DVC command area ,power generation ,
transmission & distribution gained priority for providing electricity to the
core industries like steel , railways , coal & other industrial& consumers
through respective State Electricity Boards .
However other mandated objectives also received equal importance as
part of overallresponsibility and commitment of DVC.
Capacity addition programmefor power generation gained a new direction
when ministry of power, Govt. Of India started advocating for setting up of
thermal power plants at or near pit heads & transmitpower rather than
transporting coal and advising DVC to world towards adequate capacity
addition during the Tenth and Eleventh plan in order to meet the power
vision. In addition to programmeof capacity addition of 1210MW in Tenth
Five year plan and 6000MW in Eleventh plan , DVC has decided to
rejuvenatethe existing unit through comprehensiveoverhauling and
refurbishment. Besides this , extension and augmentation of transmission
network of DVC, devised with the assistanceof CEA and also strengthening
of existing transmission and distribution network are also under process
of implementation. DVCis implementing ruralelectrification project in
states of West Bengal & Jharkhand under “ Rajiv Gandhi Grameen
vidyutikaran yojna ”
8
THE VISION
To establish DVC as one of the largest power majors of Eastern India while
discharging the responsibilities of its other objects adequately .
In order to achieve this goal against the backdrop of competitive market scenario
in the power sector, the objectives of the corporation havebeen redefined.
CORPORATE OBJECTIVES
 Generate more power at lowest possible costby improving
operational efficiencies of the existing plants, rejuvenating old
generating units through comprehensiveoverhauling as well as by
installing new generating plants
 Transmit , distribute and supply reliable and quality power at
competitive tariff.
 Improvethefinancial health of corporation by adoption of efficient
industrial , commercial and human resourcemanagement practices.
 Ensureoptimum utilization of available water resources through
effective and
 Efficient management and harness theremaining potential of
Damodar basin to extent possible.
 Fortify measures for environmentalprotection at plant levels and to
continue with activities of conservation in the valley area.
 Strengthen socio-economic development for the inhabitants of
villages neighbouring major projects of DVC.
9
PIONEERING ROLE
 First multipurpose river valley project of Governmentof India .
 A Govt. Of India organisation generating power utilizing two sources –
Coal and water
 FirstGovt. Of India projectmanaging generation transmission and
distribution of electricity
 Firstunderground hydel station at Maithon
 Bokaro Thermal Power station , biggest thermal power plant of the nation
in 50’s of last century
 Bokaro Thermal Power Station boilers, first to burn pulverized coal in India.
 Firstre-heat units in India utilizing high steam parameter at Chandrapura
Thermal Power station
 Mejia Thermal Power Station , first in eastern India for the application of
Direct Ignition of Pulverized coal (DIPC) systemfor reducing oil
consumption in the boiler.
 Mejia Thermal Power Station , Firstof its kind in eastern India with tube
mills
10
DVC INFRASTRUCTURES
With the time DVC developed and expanded its infrastructure Five
thermal power stations with a capacity of 2570 MW, three hydro-
electric power stations with a capacity of 144 MW and one gas
turbine station with a capacity of 82.5 MW contribute to a total
installed capacity of 2796.5 MW. Presently DVC has 60 sub-
stations and receiving stations more than 5500-circuit km of
transmission and distribution lines. DVC has also four dams, a
barrage and a network of canals that play an effective role in
water management. The construction of check dams,
development of forests and farms and upland and wasteland
treatment developed by DVC play a vital role in eco conservation.
DVC Command Area 24,235 Sq. Kms
POWER MANAGEMENT
Total Installed Capacity 2796.5 MW
Thermal Power Stations Five Capacity 2570 MW
Hydel Power Stations Three Capacity 144 MW
Gas Turbine Station One Capacity 82.5 MW
Sub-stations and Receiving
Stations
At 220 KV– 11 nos.
At 132 KV– 33 nos.
At 33 KV– 16 nos.
Transmission Lines
220 KV– 1500 ckt kms
132 KV– 3415 ckt kms
33 KV– 1070 ckt kms
11
Water Management
Major Dams and Barrage
Tilaiya,Konar, Maithon
Panchet dams and Durgapur
Barrage
Irrigation Command Area
(gross)
5.69 lakh hectares
Irrigation Potential Created 3.64 lakh hectares
Flood Reserve Capacity 1292 millionCu.m.
Canals 2494 kms
Soil Conservation
Forests, Farms, Upland and
Wasteland Treatment
4 lakh hectares (approx)
Check Dams 16,000 (approx)
12
DVC POWER STATION
Name Location Capacity Commissioning
THERMAL
Bokaro 'B' Dist- Bokaro
State- Jharkhand
630 MW
(3 X 210 MW)
U-I Mar 86
U-II Nov90
U-IIIAug 93
Chandrapura Dist- Bokaro
State- Jharkhand
890 MW
(3 X 130 MW)+
(2 X 250 MW)
U-I Oct 64
U-II May 65
U-IIIJuly68
U-VIINov11
U-VIIIJul 11
Durgapur Dist.- Barddhaman
State- WestBengal
350 MW
(1X140 MW)+
(1X210 MW)
U-IIIDec 66
U-IV Sept82
Mejia Dist.- Bankura
State- WestBengal
2340 MW
(4 X 210 MW) +
(2 X 250 MW)+
(2 X 500 MW)
U-I Mar 96
U-II Mar 98
U-IIISept99
U-IV Feb05
U-V Feb08
U-VISept08
U-VIIAug11
U-VIIIAug12
DSTPS Dist.- Bardhaman
State- WestBengal
1000 MW
(2 X 500 MW)
U-I May 12
U-II Mar 13
KTPS Dist.- Koderma
State- Jharkhand
500 MW
(1 X 500 MW)
U-I July13
Total Thermal 5710 MW
Name Location Capacity Commissioning
HYDEL
Tilaiya River- Barakar
Dist.-Hazaribagh
State- Jharkhand
4 MW
(2 X 2 MW)
U-I Feb’53
U-II July’53
Maithon River- Barakar
Dist.- Burdhaman
State- West Bengal
63.2 MW
(2 X 20 MW)
+
(1 X 23.2 MW)
U-I Oct’57
U-II Mar’58
U-II Dec’58
Panchet River- Damodar
Dist.- Dhanbad
State -Jhankhand
80 MW
(2 X 40 MW)
U-I Dec’59
U-II Mar’91
Total Hydel . 147.2 MW
GRAND TOTAL 5857.2 MW
13
POWER MAP
14
DAMS & BARAGES
FRONT VIEW OF SPILLWAYS OF MAITHON DAM
Tilaiya Konar Maithon Panchet
Inauguration 21.02.53 15.10.55 27.09.57 06.12.59
On River Barakar Konar Barakar Damodar
District Hazaribagh Hazaribagh Dhanbad Dhanbad
State Jharkhand Jharkhand Jharkhand
/W.B
Jharkhand
/W.B
Height above river bed (meters) 30.18 48.77 50.00* 40.84*
44.00** 45.00**
Length (meters) 366 4535 4860 6777
Width of roadway (meters) 3.81 5.79 6.78 10.67
Power generating capacity 2 x 2 MW - 3 x 20
MW
2 x 40
MW
Storage capacity (million cu.m.)
To dead storage 75.25 60.4 207.24 170.37
To top of gates 394.74 336.76 1361.84 1497.54
Allocation of storage capacities (MCM)
For irrigation & power 141.86 220.81 611.84 228.21
For flood control 177.63 55.51 542.76 1086.76
Drainage area (sq. km.) 984.2 997.1 6293.17 10966.1
Reservoir (sq. km.)
At dead storage level 15.38 7.49 24.28 27.92
At maximum conservation pool 38.45 23.15 71.35 121.81
Area top of gates 74.46 27.92 107.16 153.38
15
Durgapur Barrage
Details of Canal Network.
Length
(Km)
Discharge at Head
Regulator (Cumec)
LBMC (Left Bank Main Canal)(Canal
originating from Durgapur Barrage)
136.8 260
RBMC (Right Bank Main Canal) (Canal
originating from Durgapur Barrage)
88.5 64.3
Total length of main and branch canals 2494
DURGAPUR BARRAGE
Year of construction 1955
Length 692 m
Number of gates 34 (including under sluice)
Size of gates 18.3m x 4.9m [60 ft x 16 ft]
Left & right under sluice 18.3m x 5.5 m [60 ft x 18 ft]
Operating levels
Between RL. 64.5 m [211.5 ft] to RL. 63.4
m [208.0 ft]
16
INITIATIVES FOR SOCIAL SECTOR DEVLOPMENT
Social Integration Programme
DVC launched its Social Integration Programme(SIP) in 1981.SIP is basically an
expression of DVC’s deep commitment to socio-economic and infrastructural
development of the communities residing within a 10 Km radius of its main
projects.
The programmestarted with 25 villages. At presentit operates in 375 villages
covering 70 Panchayats in 12 blocks of Dhanbad, Giridih, Bokaro and Hazaribagh
districts of Jharkhand and Barddhaman, Purulia and Bankura districts of West
Bengal.
Areascovered under the programme:
·Education
·Agriculture
·Health
·InfrastructuralDevelopment
·Sportsand Culture
·RuralElectrification
·Self- employment
·SocialForestry
EDUCATION
DVC’s Social IntegrationProgramme (SIP) offers the following facilities:
 Non-formaladult education centers, rurallibraries and community centers
run by DVCto help spread literacy among the communities residing within
a 10 km radius of DVC’s main projects. All inputs are fed by DVC
 DVCruns 43 Sishu Siksha Kendras for imparting primary level education to
children of economically disadvantaged families and also to dropouts and
those over aged. At present 1200-1300students aregetting free primary
education.
 In these Kendras students get reading and writing materials free of cost.
Even Keroseneoil is provided to run these Kendras in the remote areas of
Panchet, Konar and Tilaiya projects.
17
 Children belonging to SIP villages are eligible to study in the schools meant
for the children of DVC’s employees.
Social Development
DVC implements integrated social development work in villages situated with in
10 km area of it's major projects through it's social integration programme.
Environment Management
The Environment Management work of DVC consists of two parts the firstpart
DVC is installing proper equipment and augmenting majors to follow the
pollution norms in it's thermal power plants the second part consists of a
forestations and other conservation work for preservation of eco systemof
Damodar Valley area.
Soil Conservation
Soil Conservation work of DVCaims to check soil erosion, and siltation of dams,
improveagricultural production, afforestation and reserves ecological balance.
Rural Electrification
DVC has been entrusted with the responsibility of implementing rural
electrification projectin selected district of West Bengal and Jharkhand
under'RAJIV GANDHI GRAMINVIDYUTIKARANYOJANA'.
Welfare
DVC provides various facilities for the well being of it's employees and their
dependents. Some of the facilities are also being extended to the villagers
covered under the social integration programme
18
AGRCULTURAL
DVC is engagedin the following activities toincrease agricultural yieldfrom
fields:
 Initiation of micro-lift irrigation programmes in the upper valley
 Digging of irrigation wells
 Construction of check dams
 Renovation of ponds
 Arranging training programmes for farmers
DVC has constructedmore than16,000 check dams
Farmers of the local villages are encouraged to adoptmodern scientific farming
practices, Experts fromKVK, Sindri, Holy Cross KrishiVigyan Kendra, Hazaribagh
and Birsa Agricultural University, Ranchiand R.K. Mission of Amarkanan Sewa
Ashram, Purulia impart training in this regard.
HEALTH
DVC’s health programmes under SIP are basically preventive as well as
curative in nature
Preventive Health Services:
DVC organizes from time to time various camps
 Pulse-polio immunization camp.
 Family welfare and operation camp.
 Anti-malaria camp.
 Aids and HIV awareness camp.
 Anti-diarrhea camp.
 Eye (cataract) operation camp.
 TB awareness and detection camp.
19
INFRASTRUCTURAL
DEVLOPMENT
Infrastructural development worksareessentially need-based activities:
 Drinking water
Safe drinking water facilities through tap points, hand pumps and wells.
 Communication
Construction of roads (WBM/ bituminous / PCC), culverts, drainage
system, passenger shelters etc.
 Education and HealthCare
Construction of schoolbuildings along with boundary walls, community
buildings, adult education centers and dispensary buildings
 IrrigationFacilities
Installation of micro lift irrigation/RL
Renovation and construction of ponds
Construction of check dams and irrigation wells.
 Others
Construction of toilets, urinals, washing and bathing ghats and burning
ghats.
SELF EMPLOYMENT
Training Programme and Self-employment
DVC is actively engaged in helping local unemployed youths find meaningful
occupations. For this the following facilities are offered:
 Training centers at Maithon, CTPS, BTPS, DTPS and Panchet.
 Youths sent to differentcentres run by outside organizations for training
on poultry, duckary, goattery, para-veterinary,plantpropagation, dairy,
diesel pump mechanic, mushroomcultivation, piggery etc.
 Firsttime assistanceby DVCin terms of raw materials and kits to help
trained youths set up their own business/enterprises.
20
ENVIROMENT MAMAGEMENT
We care for the Earth
DVC strongly believes that excellence in the environmental fields is of prime
importance. DVCstrives to work with environmental issues in a consistentand
systematic manner.
DVC’s environmentalmanagement programmeconsists of
 Pollution control at its thermal power stations and
 Combating soil erosion and soil decay in order to restoreand preserve
the quality of the land.
PollutionControl
Pollutants in the formof ash and emissions fromstack arethe major sources
of pollution at coal-based thermal power stations. In old units, of DVC, at
Bokaro, Chandrapura and Durgapur, which werecommissioned, before
pollution control standards becamestringent, the following measures have
been taken to bring the pollutants within the limits:
 Initiation / installation of ESPs with additional fields to bring down
emission within limits.
 Renovation of de-ashing and ash handling system.
 Installation of oil and grease separator.
 Plantation in and around plant areas, ash disposalareas and outside the
projectareas.
Modern units at MTPS, commissioned during 1990s, comply with latest
pollution control norms, including the provision of reuse and recycling of
maximum affluent to conserveland and water.
DVC’s solid wastemanagement systemconsists of evacuation of ash
fromthe ash ponds at BTPS, CTPS and DTPS, transported in protective
manner and dumped into abandoned open castcoal mines of CCL, BCCL
and ECL respectively. After filling up of the mines is over, the top surface
is covered with earth of sufficientthickness to facilitate growth of
vegetation
21
TRAINING REPORT FOR
PROGRAMME NO. 2 - C.L.D
CENTRAL LOAD DISPATCH
08/07/2015 TO 10/07/2015
CLD office, Combined Administrative Building (2nd Floor)
Area-6
Damodar Valley Corporation
22
NATIONAL LOAD DISPATCH CENTRE
supervise regional load dispatch centres according to Sec-26(2)- act of Ministry of Power
(2005).
These five regions are
NATIONAL LOAD DISPATCH CENTER
ER-EAST REGION WR-WESTREGION NR-NORTH REGION SR-SOUTH REGION NER-NORTH EASTREGION
Bihar Chhattisgarh Punjab Andhra
Pradesh
Arunachal
Pradesh
DVC Gujarat Haryana Telangana Assam
Jharkhand MP Rajasthan Karnataka Manipur
Odisha Maharashtra Delhi Kerala Meghalaya
W.B Goa U.P Tamil Nadu Mizoram
Sikkim DD Uttarakhand Pondy Nagaland
DNH H.P Tripura
Essar steel J&K
Chandigarh
CLD- MAITHON comes under ER
23
CLD MAITHON IS RESPONSIBLE FOR :
 Optimum Scheduling and dispatch of Electricity within the
region.
 Monitor grid operation.
 Accounts of quantity of electricity transmitted through the
regional grid.
 Supervise & control over Inter-State Transmission System.
 Real Time Operation of grid control & dispatch of electricity
through secure & economic operations according with grid
standard & grid code.
A ULDC/load Dispatch Centre of Damodar Valley Corporation is the
ModernComputerized on-line data monitoring system of DVC.
Main Display at Central Load Dispatch
Date 08-JUL-2015 TIME 11:50:52
24
DEMAND FORECASTING & SHEDULING
08-JUL-2015
SUMMARY DAIGRAM-DVC 08-JUL-2015 11:50:52
FREQUENCY 50.05 UI RATE(PAISE) 261.36
DEV(MW) 33 TOTAL SCHEDULED 571
MAX. ADDITIONAL RATE/PENALTY RATE(OVER INJECTION)-0
BSEB JSEB DVC GRIDCO WBSEB SIKKIM
GENERATION 1 0 2711 1857 3311
DRWL SCHD -2050 -482 571 -848 -2081
ACT. DRAWL -2385 -87 604 6397 -2068
DEMAND 2385 87 2107 -4540 5379
ACTUAL GEN. SHARE OF DVC
RANGIT 61 6
CHUKHA 251 26
TEESTA 515 44
TALA 1079 60
KURICHU 38 19
FARAKKA 326 25
TALCHER 470 1
ACTUAL CONTROL ERROR = 36 K▲F= -2.63
VOL.BTW 12%-15% = 0.00
VOL.BTW 15%-20% = 0.00
VOL. BEYOND 20 % = 0.00
DVC GENERATION MW
THERMAL GEN 2635
HYDRO GEN 76
TOTAL GEN 2711TOTAL CS GEN :- 6220
NET EXPORT =1199
EXPORT RATE (PAISE/kwh)=101
CONSR CD(MVA) ACT(MW
NET IMPORT = -103
IMPORT RATE (PAISE/kwh)= 218
BSL
TISCO
DSP
IISCO
200
120
190
100
126
-30
WL 27
55
NET UI (mwh) = 1096
[ COMULATIVE SINCE 00:00 HRS]
25
HYDEL GENERATION
MHS PHS TILAIYA TIME BLOCK AVG.
FREQ(HZ)
RATE
(PAISE/KWH
)
UI(m
wh)
TSL
UNIT 1 15 28 2 1100-1115 49.99 220 2 -34
UNIT 2 17 0 0 1115-1130 49.92 366 7 -33
UNIT 3 14 -- -- 1130-1145 50.08 71 0 -35
TOTAL 46 28 2 1145-1150 50.02 107 1 -32
THERMAL GENERATION
DSTPS BOKARO-
B
MEJIA WARIA CTPS132 CTPS
B
KTPS RTPS
GEN. GEN. GEN. GEN. GEN. GEN. GEN. GEN.
U#1 386 0 151 0 --- 0 0
U#2 0 0 165 84 --- 376 0
U#3 --- 0 152 87 91 ---
U#4 --- --- 0 0 0 ---
U#5 --- --- 0 --- --- ---
U#6 --- --- 182 --- --- ---
U#7 --- --- 372 --- --- 0
U#8 --- --- 383 --- --- 206
TOTAL
386 0 1405 87 175 206 376 0
26
TIE LINES
Lines MW Lines MW
CENTRAL SECTOR GRIDCO
PURLIA-PURLIA PG-I -84 JAMSHEDP-JODA -39
PURLIA-PURLIA PG-I -76 TOTAL 39
KALYA-MAITHON PG-I -71 WBSEB
KALYA-MAITHON PG-II -70 WARIA-BIDHAN’R-I 34
DHN-MATHN-PG-I -112 WARIA-BIDHAN’R-II 33
DHN-MATHN-PG-II -117 KOLAG-KOLAG 0
MEJIA B-JAM’PUR PG 190 TOTAL 67
DSTPS- JAM’PUR PG –I 146 JSEB
DSTPS- JAM’PUR PG –II 140 PATRATU- PATRATU TPS -1 0
MEJIA B- MAITHON PG-I 210 PATRATU- PATRATU TPS -2 0
MEJIA B- MAITHON PG-II 209 CHANDIL –MAINIKUI 0
MEJIA B- MAITHON PG-III 140 MAITTHON- JAMTARA 39
TISCO(DVC)-BARIPADA 206 TOTAL 39
TISCO(DVC)- JAM’PUR PG -347
BSEB
KODERMA-B’SARIF-PG-I -65 BARHI – B’SHARIF 0
KODERMA-B’SARIF-PG-II -64 BARHI - RAJGIR 0
KODERMA-GAYA-I 0 TOTAL 0
KODERMA-GAYA-II 224 NET INTERCHANGE 604
RTPS-RANCHI-PG-I 41
RTPS-MAITHON-PG 36
TOTAL 530
27
IMPORTANT LINES MW
JAMALPUR –MEJIA B1 -178
DURGAPUR- JAMALPUR -44
MAITHON- KHSTPP-I -76
MAITHON - KHSTPP -II -79
DURGAPUR-FSTPP- I -278
DURGAPUR- FSTPP-II -281
MAITHON-JAMALPUR-I -178
MAITHON-JAMALPUR-II -48
PURULIYA-JAMALPUR -44
JAMALPUR- ROURKELA-II I
ROURKELA-RAIGHAR- I -41
ROURKELA- TSTPP –I I
ROURKELA-TSTPP-II 0
KHSTPP- B’SHARIF- I 46
KHSTPP –B’SHARIF-II I
B’SHARIF-SASARAM-1 I
B’SHARIF-SHASARAM-II I
SASARAM- ALLAHABAD-I 193
SASARAM-ALLAHABAD- II 138
RENGALI-TSTPP-I 150
RENGALI-TSTPP-II -283
RENGALI- INDRAVATI -283
INDRAVATI- JAYPORE 290
JAYPORE-GAJUWAKA-I 394
JAYPORE-GAJUWAKA-II 27
MAITHON-RANCHI-I -34
RANCHI-ROURKELA-I -34
RANCHI- ROURKELA-II 282
28
DEMANDFORE CAST
(FOR TODAY) 08 jul 2015
TIME
BLOCK
DEMAND
1130-1145 2253
1145-1200 2256
1200-1215 2255
1215-1230 2268
1230-1245 2209
1245-1300 2215
1300-1315 2228
1315-1330 2243
1330-1345 2235
1345-1400 2226
1400-1415 2188
1415-1430 2194
REGION UI RATE(PAIS) FREQ
SR/WR/WR 261 50.11
INTER REG. EXCHANGE
ACTUAL SCHEDULED
ER-WR 365
651 ER-SR 2686
2633 ER-NER
-300 81
ER-NR 1838
1614
DSTPS-RTPS-I 38
DSTPS-RTPS-II 38
KTPS-BOKARO-I 90
KTPS-BOKARO-II 89
DVC BUS VOLTAGE
KV
MEJIA B 420
DSTPS 420
KODERMA 412
TISCO 413
RTPS 467
BOKARO B 220
CTPS 220 218
JAMSHEDPUR 222
KALYANESHWARI 225
MEJIA- TPS 229
PURULIYA 229
WARIA 227
ASP 139
CTPS 132 133
MAITHON (H) 137
MOSABANI 131
PANCHET 135
29
Power System Operation Corporation
Power System Operation Corporation Limited (POSOCO) is a wholly owned subsidiary of Power Grid Corporation of
India Limited (PGCIL). It was formed in March 2010 to handle the power management functions of PGCIL. It is
responsible to ensure the integrated operation of the Grid in a reliable, efficient and secure manner. It consists of
5 Regional Load Despatch Centres and a National Load Despatch Centre (NLDC). The subsidiary may eventually be
made a separate company, leaving the parent firm with only the task of setting up transmission links. The load
despatch functions,earlier handled by PGCIL, will now come up to POSOCO.
Power Grid Corporation ofIndiaLimited (aGovernment Company)shall operate National Load Despatch Centre and thefive Regional Load
Despatch Centers, with effect from October 1, 2010.
30
SINGLE LINE DAIGRAM OF 220/132KV DVC GRID
31
SCADA
Supervisory control and data acquisition (SCADA) systems have traditionally
played a vital role by providing utilities with valuable knowledge and capabilities
that are key to a primary business function – delivering power in a reliable and
safe manner. A quality SCADA solution is central to effective operation of a
utility's most critical and costly distribution, transmission, and generation assets.
The challenging issues for SCADA systems and projects today are not the same as
they were a few years ago. Today, there is much more importance placed on
integration, use of new communication and network technologies, access to
information by more users, and other purposes.
Today’s SCADA systems, in response to changing business needs, have added new
functionalities and are aids for strategic advancements towards interactive, self
healing smart grids of the future. A modern SCADA system is also a strategic
investment which is a must-have for utilities of all sizes facing the challenges of
the competitive market and increased levels of real time data exchange that
comes with it (independent market operator, regional transmission operator,
major C&I establishments, etc.). A well planned and implemented SCADA system
not only helps utilities deliver power reliably and safely to their customers but
also helps to lower costs and achieve higher customer satisfaction and retention.
Modern SCADA systems are already contributing and playing a key role at many
utilities towards achieving:
 New levels in electric grid reliability
 Increased revenue.
 Proactiveproblem detection and resolution
 Higher reliability.
 Meeting the mandated power quality requirements
 Increased customer satisfaction.
 Real time strategic decision making costreductions and increased revenue.
32
TRAINING REPORT FOR
PROGRAMME NO. 3 - TRANS.
TRANSMISSION DEPARTMENT
13/07/2015 TO 16/07/2015
220 KV KALYANESWARI SUB-STATION
Damodar Valley Corporation
33
220 KV KALYANESWARI SUB-STATION
Substation
 An Electrical Substation is a subsidiary station of an electricity Generation , Transmission
And Distribution System where voltage is transformed high to low or reverse using
transformer.
 Examples of Substation:-
 400kV/220kV substation
 220kV/132kV substation
 132kV/33kV substation
 33kV/11kV substation
 33kV/.4kV substation
34
220 KV KALYANESWARI SUBSTATION
201 202 228 229 239 240 237 238
C T P S
M T P S
VIA BURNPUR
PGCIL
220 KV
ATR 1
150 MVA
ATR 2
160 MVA
ATR 3
150 MVA
18 19
KLP
MHS
132 KV
68 69
MAL
PWR TR
50 MVA
PWR TR
50 MVA
33 KV
0.415 KV
250 KVA 250 KVAANP1 HIRA UM NKITA BMA MPLANP2
AUX PWR
35
SINGLE LINE DAIGRAM OF 220 KV KALYANESWARI SUB STATION G.O.M.D –II, D.V.C
36
Ratings
ATR 1 BHEL
SCHEMATIC DAIGRAM
VECTOR DAIGRAM
37
ATR 2 BHARAT BIJLLE
38
The basic components of a substation are
as follows:
AUTO TRANSFORMER
An autotransformer (sometimes called autostep down transformer) is an
electrical transformer with only one winding. The "auto" (Greek for "self") prefix
refers to the single coil acting on itself and not to any kind of automatic
mechanism. In an autotransformer portions of the same winding act as both the
primary and secondary transformer. The winding has at least three taps where
electrical connections are made. Autotransformers have the advantages of often
being smaller, lighter, and cheaper than typical dual-winding transformers, but
autotransformers havethedisadvantageof not providing electrical isolation.
WORKING
The primary voltage is applied across two of the terminals, and the secondary
voltage taken from two terminals, almost always having one terminal in common
with the primary voltage. The primary and secondary circuits therefore have a
number of windings turns in common. Since the volts-per-turn is the same in both
windings, each develops a voltage in proportion to its number of turns. In an
autotransformer part of the current flows directly from the input to the output,
and only part is transferred inductively, allowing a smaller, lighter, cheaper core
to be used as well as requiring only a single winding. One end of the winding is
usually connected in common to both the voltage source and the electrical load.
The other end of the sourceand load are connected to taps along the winding.
Different taps on the winding correspond to different voltages, measured from
the common end. In a step-down transformer the source is usually connected
across the entire winding while the load is connected by a tap across only a
portion of the winding. In a step up transformer, conversely, the load is attached
across the full winding while the source is connected to a tap across a portion of
the winding.
39
POWER TRANSFORMER:
The use of power transformer in a switchyard is to change the voltage level. At the sending and
usually step up transformers are used to evacuate power at transmission voltage level. On
the other hand at the receiving end step down transformers are installed to match the voltage
to sub transmission or distribution level. In many switchyards autotransformers are used
widely for interconnecting two switchyards with different voltage level (such as 132 and 220
KV)
1-Main tank 2-Radiator 3-Reservoir tank 4-Bushing 5-WTI & OTI Index 6-Breather 7-Buccholz relay
CIRCUIT BREAKER
A circuit breaker is an equipment that breaks a circuit either manually or
automatically under all conditions at no load, full load or short circuit. Oil circuit
breakers, vacuum circuit breakers and SF6 circuit breakers are a few types of
circuit breakers.
40
ISOLATOR
Isolators are switches which isolate the circuit at times and thus serve the
purposeof protection during off load operation.
CURRENT TRANSFORMER
These transformers used serve the purpose of protection and metering.
Generally the same transformer can be used as a current or potential
transformer depending on the type of connection with the main circuit that is
series or parallel respectively. In electrical system it is necessary to
a) Read current and power factor
b) Meter power consumption.
c) Detect abnormalities and feed impulse to protective devices.
POTENTIAL TRANSFORMER
In any electrical power system it is necessary to
a) Monitor voltage and power factor,
b) Meter power consumption,
c) Feed power to control and indication circuit and
d) Detect abnormalities
41
(i.e. under/over voltage, direction of power flow etc) and feed impulse to
protective device/alarm circuit. Standard relay and metering equipments does not
permit them to be connected directly to the high voltage system.Potential
transformers therefore play a key role by performing the following functions.
a) Electrically isolating the instruments and relays fromHV side.
b) By transferring voltage from higher values to proportional standardized lower
values.
CONDUCTORS
Steel cored Aluminium (A.C.S.R)
Aluminium has low tensile strength, as a result produce greater sag which
prohibits their use for longer spans and makes them unsuitable for long distance
transmissions. So in order to increase the tensile strength of the aluminium
conductor, it is used with a core of galvanized steel wires. The combinational
conductor thus obtained is called as A.C.S.R. (Aluminium Conductor Steel
Reinforced)
42
The above figure shows, one steel cored conductor wire surrounded by 18 wires
of aluminium. The aluminium carries bulk of current while the steel core takes a
greater percentage of mechanical stress.
 Produces smalllag and therefore can be used for longer spans.
 A.C.S.R. Conductor gets deteriorated in service due to atmospheric
corrosion.
Cadmium copper
Sometimes copper alloyed with cadmium is used. When 1 or 2 percentage of
cadmium is added to copper it increases the tensile strength by about 40
percentages but reduces the conductivity only by 17 percentages. Cadmium
copper is expensive than copper.
 Economical for a line with long spans and small crosssection.
43
Insulator
The live equipments are mounted over the steel structures or suspended
from gantries with sufficient insulation in between them. In outdoor use
electrical porcelain insulators are most widely used.
Types of insulators
(a)Pin type insulators. (b)Suspension type insulators. (c)Strain typeinsulators.
(d)Shackleinsulators.
(a)Pin type insulators A pin type insulator is designed to be mounted on a pin,
which in turn is installed on cross-armof thepole. The insulator on the pin and
electrical conductor is placed in the grooveat the top of the insulator and soft
aluminium binding wire according to the material of the conductor.
 Pin type insulators made of glass aregenerally used for low voltages.
 Pin type insulators made of porcelain can be used up to 90kV but are rarely
used on lines above60kV
Suspension type insulators
 In a pin type insulator its cost is increased rapidly as the working voltageis
increased. Therefore pin type insulator is not economical beyond 33kV. So
it is as usualpractice to use suspension typeinsulators for voltagehigher
than 33kV.
 A pin type insulator sits on top of the cross arm, whereas a suspension
insulator hangs fromthe cross arm. The line conductor is attached to its
44
lower end. Few advantages of suspension typeinsulators over Pin type
insulators are:
 Usually cheaper in cost for operating voltage above 50kV.
 Flexibility is increased with suspension insulators.
 If line insulation needs to be increased, the additional insulators can be
easily added to the string. In casethere is damage in any insulator, the
damaged insulator can be easily replaced.
45
Bushing
A bushing is a hollow insulating liner through which a conductor maypass.
Bushings appear on switchgear, transformers, circuitbreakers and other high
voltage equipment .The bushing is a hollow insulator, allowing a conductor to
pass along its center and connect at both ends to other equipment. Bushings are
often made of wet-process fired porcelain, and may be coated with
semiconducting gglaze to assistin equalizing the electrical stress along the
length of the bushing. The inside of the bushing may contain paper insulation and
the bushing is often filled with oil to provideadditional insulation. Bushings for
medium-voltage and low-voltageapparatus may be made of resins reinforced
with paper. The useof polymer bushings for high voltage applications is becoming
more common.
46
Capacitor voltage transformer
A capacitor voltagetransformer (CVT or CCVT),is a transformer used
in power systems to step down extra high voltage signals and provide a low
voltage signal, for metering or operating aprotective relay.
CVTs in combinationwith wave traps are used for filtering high-frequency
communication signals from power frequency.
WAVE TRAP
Wave Traps areused at sub-stations using Power Line Carrier Communication
(PLCC). PLCCis used to transmitcommunication and control information at a high
frequency over the power lines. This reduces need for a separate infra for
communication between sub-stations.
The Wave Traps extract the high frequency information fromthe power lines and
route it to the telecomm panels. They also block any surges frompassing through.
Wave Traps aresimply resonantcircuits that producea high impedance against
PLCC carrier frequencies (24kHz - 500kHz) whileallowing power frequency (50Hz -
60Hz).
47
Pebbles flat flooring at substation
Two terms defined regarding floor of earthing system
 Touch potential(potb/w hand and structurals (gnd) when a person is
touching a grounded body like structure in switchyard.
 Steppotential(potdiff b/w the feet of a person walking in the switchyard)
now to minimize these potentials we put pebbles in place of flat flooring.
 To reduce the magnatic field in between ground and conductor.
 To reduce the growth of gress.
 To aviod entry of animals like Rats, snakes etc
 To reduce water storagein the yard in the rainy season.
Lighting Arrestor
Lightning arresters areprotective devices for limiting surgevoltages due
to lightning strikes or equipment faults or other events, to prevent
damage to equipment and disruption of service. Also called surge
arresters.
Lightning arresters areinstalled on many different pieces of equipment
such as power poles and towers, power transformers,circuitbreakers,
bus structures, and steel superstructures in substations
48
Substation Batteries
The heart of a substation is the battery bank. If this were to fail, an electric utility
could expose all feeders associated with the station to a condition where they
could not ever trip in a fault. Not only that, but any backup devices, such as the
main breaker on the low-voltage side or the high-voltage side protection of the
power transformer, would all be inoperative, leaving the transmission grid
protection as the only possiblebackup.
In many cases, however, the transmission grid cannot perform this function
because a fault on the low-voltage side of a Delta Wye transformer, especially a
phase-to-ground fault, will convert to a phase-to-phase fault on the high side. This
would be particularly true if the fault was out a few miles from the station. This
could then cause such catastrophic consequences as burning wire down across
town and eventually destroying the substation transformer. After the smoke
clears, much of the substation could be heavily damaged and the power
transformer could be in flames. This is not to mention the hazard it would cause
to the public.
49
TRANSMISSION SYSTEM
Charged with the responsibilities of providing electricity, the vital input for industrial growth
inthe resource-rich Damodar Valley region, DVC over the last 60 years has developed a big
androbust transmission network consisting of 132 KV and 220 KV grids. DVC grids operates
inunison with the eastern regional grid through 132 KV and 220 KV tie lines. All the power
stationsand substations of DVC are connected with the DVC grids. DVC power consumers are
providedsupply at 25 KV, 33 KV, 132 KV and 220 KV pressure.
DVC Transmission Lines in service at a glance
Interconnecting Tie Lines with DVC Network
*Out of service.
DVC Substations in service (Nos.) at a glance
50
Transmission & Distribution Projects
New Projects under construction
New Projects being taken up for construction
51
GRIDMAP
52
Substations
At 33KV Receiving Stations
53
Electrical substation model (side view)
54
TRAINING REPORT FOR
PROGRAMME NO. 4 – TSC
TRANSMISSION SYSTEM CONSTRUCTION
17/07/2015 TO 20/07/1015
Damodar Valley Corporation
55
PROCEDURE OF TSC
PRELIMINARY WORKS
 Selection of Route
 ReconnaissanceSurvey
 Preliminary Survey
 Approvals & Clearances for the Line Route
CONSTRUCTION ACTIVITIES
 Detailed Survey & Plotting of Profile
 Tower Spotting & Tower Schedule
 Check Survey & Location Marking
 Stub Setting
 Erection of Towers & Fixing of Accessories
 Stringing of Conductors & Earth Wire
 Earthing
 Protection of Tower Footings
 Clearing of Right of Way
 Final Checking
 Testing & Commissioning
56
TRANSMISSION ROUTE
The route of a transmission line is decided from the following main
considerations:
 Shortestlength, hence least capital cost.
 Route near roads for easy approach & accessibility during construction and
maintenance.
 Requirement of future loads near the proposed routeso that the line can
easily be connected to the loads and optimal use of line.
 Required separation distance fromparallel communication lines (P&T,
Railways, etc.) for meeting the conditions of induced voltage for obtaining
PTCC approval.
 Avoiding of forestareas as well as wild life sanctuaries as far as possible.
 Cost of securing and clearing right of way (ROW).
 Maintaining statutory distances fromAirports / Helipads
AVOID
 Tough inaccessibleareas
 Towns and villages, leaving sufficient margin for their growth
 Swamps and shallow lands subjectto flood, marshy areas, low lying
lands, river beds and land slide zones, etc. involving risk of stability for
foundations
 Rifle shooting areas and other protected areas such as army / defence
installations and ammunition depots.
 Buildings / Storage areas for explosives or inflammable materials, bulk
oil storagetanks, oil or gas pipelines etc.
57
SUREVY OF LINES
 METHOD : Theodolite , Total Station ,SatellitewithTotal Station
 PLOTTING OF ROUTE PROFILE: Manual , PLSCAD
APPROVAL REQUIREMENT
 Forestclearance
 Railway clearance
 Clearance frommining authority
 NH Clearance
 Power and Telecommunication Coordination Committee (PTCC)
clearance
 CEA Clearance
MINIMUM CLEARANCE
58
MINIMUM CLEARANCE : IS: 5613 (Part II/Sec-1)-1976
MINIMUM CLEARANCE : AS PER - IS :5613 (PART II/SEC I) -
1976
59
APPLICATION OF SAG TEMPLATE ON PROFILE
60
TOWER USED FOR TRANSMISSION LINE
 Lattice type tower
 A2, S15, B30, C60, D90 –132&220KV line
 A2, B15, C30, D60 – 400KV line
 Wide base tower
 Narrow basetower
 Multi circuit Tower
 Special Crossing Tower
TOWER CONSTRUCTION : EXCAVATION
MARKING CHART
61
 The excavation pit marking drawing indicates the distance of centres, sides
and corners of the pits with reference to the centre point of the tower
 From the dimensions shown in the drawing, the triangle ABC is first
marked with the help of a measuring tape. The distance CD, equal to F
(width of the pit) is marked on the ground.
The triangle AB'C is then marked by shifting the point B and without changing the
points A and C. The distance CD', equal to F, is then marked. The sides DE and D'E,
both equal to F, are then marked. The procedure is repeated for marking the
other three pits.
 The dimension G shown in the drawing is the centre to centre distance
between stubs of the tower at their lowest point. The dimension M is the
diagonal distance between the ends of the stubs of the tower. The
excavation pit marking drawing is prepared on the basis of these
dimensions.
TOWER FOUNDATION : PYRAMID CHIMNEY TYPE
62
63
64
FOLLOW THE STEPS TO ERECT THE TOWER
 Erection of Tower body - first story
 Erection of Tower body - second story upwards
 Erection of cross arms
Conclusion: Pulley and guy ropes are the minimum accessories to erect a
tower.
65
STRINGING OF CONDUCTORS AND
EARTHWIRE
HOSTING OF INSULATOR STRING
 Single / Doublesuspension insulator strings areused on suspension towers
and single / double tension insulator strings are used on angle and dead
end towers. This is indicated in the tower schedule.
 Before hoisting, all insulators are cleaned in a manner that will not spoil,
injureor scratch the surfaceof the insulator, but in no caseshall any oil be
used for the purpose.
 Disc insulators shall be examined for any cracks / chipping, etc. Disc
insulators having any hair cracks or chipping or defective glazing or any
other defect shall not be used .
NO. OF DISC / E&M STRENGTH (KN)
400kv 220kv 132kv
single suspension –I
string
1 X 23 120 KN 1 X 13 70 KN 1 X 9 45 KN
Double suspension-I
String
2 X 24 120 KN 2 X 13 70KN 2 X 9 45 KN
Single suspension- v
string
2 X 23 120 KN N.A N.A
Double suspension v
string
2 X 2 X 23 120KN N.A N.A
Single tension string 1 X 23 120 KN 1 X 14 120 KN 1 X 10 120KN
Double tension string 2 X 23 160KN 2 X 14 120KN 2 X 10 120KN
Single suspension pilot
string
2 X 23 120KN 1 X 13 70KN 1 X 9 45KN
66
67
68
69
Substation construction
Selectionofsite
 As near the load centre as possible.
 As far as possiblerectangular or squarein shapefor ease of proper
orientation of bus – bars and feeders.
 Far away from obstructions, to permit easy and safe approach / termination
of high voltage overhead transmission lines.
 Free frommaster plans / layouts or future development activities to have
free line corridors for the presentand in future.
 Easily accessibleto the public road to facilitate transportof material
 As far as possiblenear a town and away frommunicipal dumping grounds,
burial grounds, tanneries and other obnoxious areas.
 Preferably fairly leveled ground. This facilitates reduction in leveling
expenditure.
 Abovehighest flood level (HFL) so that there is no water logging.
 Sufficiently away fromareas wherepolice and military rifle practices are
held.
70
Main Equipments of Sub-station:
 Transformer
 LA
 CVT/PT
 Isolator
 CT
 Circuit Breaker
 Control & Relay Panel
Sub station layout
71
Note : These layouts were essentially used in
220kv/ 132kv/ 33kv Dhanbad sub station
( TSE VT – 09-01-2014 AT D.S.S , DVC )
72
SECTION 132KV & 220KV TRANSFORMER
BAY,DHANBAD S/S
73
BAY LAYOUTS OF 132KV AND 220 KV , DHANBAD S/S
74
EARTHING OF SUB STATION-
75
TRAINING REPORT FOR
PROGRAMME NO. 5 – CTC
CENTRAL TESTING CENTER
CRITL MAITHON
Damodar Valley Corporation
76
Central Testing Center at Maithon
has two distinct divisions namely
1.Central Relay and Instrument Testing Laboratory
(CRITL) and
2.Central Relay and Instrument Testing Mobile
(CRITM).
The above two divisionstake care of commissioning and proper
maintenanceof the entire protection and metering system,
fault analysisas well as periodicaltesting of all types of relays
and meters includingtariff meters of the entire DVC network
includingpower houses.
77
TRANSFORMER OIL
Transformer oil or insulating oil is usually a highly refined mineral oil that is stable
at high temperatures and has excellent electrical insulating properties. It is used
in oil filled transformers, some types of high voltage capacitors, fluorescent lamp
ballasts, and some types of high voltage switches and circuit breakers .Its
functions are to insulate, suppress corona and arcing, and to serveas a coolant.
On-site testing
Some transformer oil tests can be carried out in the field, using portable test
apparatus. Other tests, such as dissolved gas, normally require a sample to be
sent to a laboratory. Electronic on-line dissolved gas detectors can be
connected to important or distressed transformers to continually monitor gas
generation trends.To determine the insulating property of the dielectric oil, an
oil sample is taken from the device under test, and its breakdown voltage is
measured on-site according the following test sequence:
 In the vessel, two standard-compliant test electrodes with a typical
clearance of 2.5 mm are surrounded by the insulating oil.
 During the test, a test voltage is applied to the electrodes. The test voltage
is continuously increased up to the breakdown voltage with a constant slew
rate of e.g. 2 kV/s.
 Breakdown occurs in an electric arc, leading to a collapse of the test
voltage.
 Immediately after ignition of the arc, the test voltage is switched off
automatically.
 Ultra fast switch off is crucial, as the energy that is brought into the oil and
is burning it during the breakdown, must be limited to keep the additional
pollution by carbonisation as low as possible.
 The root mean square value of the test voltage is measured at the very
instant of the breakdown andis reported as the breakdown voltage.
 After the test is completed, the insulating oil is stirred automatically and
the test sequence isperformed repeatedly.
 The resulting breakdown voltage is calculated as mean value of the
individual measurements.
78
DGA or Dissolved Gas Analysis of
Transformer Oil
Whenever electrical power transformer goes under abnormal thermal
and electrical stresses, certain gases are produced due to
decomposition of transformer insulating oil, when the fault is major,
the production of decomposed gases are more and they get collected in
Buchholz relay. But when abnormal thermal and electrical stresses are
not significantly high the gasses due to decomposition of transformer
insulating oil will get enough time to dissolve in the oil. Hence by only
monitoring the Buchholz relay it is not possible to predict the condition
of the total internal healthiness of electrical power transformer. That is
why it becomes necessary to analyse the quantity of different gasses
dissolved in transformer oil in service. From dissolved gas analysis of
transformer Oil or DGA of transformer oil, one can predict the actual
condition of internal health of a transformer. It is preferable to conduct
the DGA test of transformer oil in routine manner to get prior
information about the trend of deterioration of transformer health and
life.
Actually in dissolved gas analysis of transformer oil or DGA of
transformer oil test, the gases in oil are extracted from oil and analyze
the quantity of gasses in a specific amount of oil. By observing
percentages of different gasses present in the oil, one can predict the
internal condition of transformer.
Generally the gasses found in the oil in service are hydrogen (H2),
methane (CH4), Ethane (C2H6), ethylene (C2H4), acetylene (C2H3), carbon
monoxide (CO), carbon dioxide (CO2), nitrogen(N2) and oxygen(O2).
Generally it is found that hydrogen and methane are produced in large
quantity if internal temperature of power transformer rises up to 150°C
to 300°C due to abnormal thermal stresses. If temperature goes above
300°C, ethylene (C2H4) are produced in large quantity. At the
79
temperature is higher than 700°C large amount of hydrogen (H2) and
ethylene (C2H4) are produced.
DGA TESTING OF TRNSFORMERS OF DVC
DGA 3 STEPS
 OIL SAMPLE EXTRACTION as per standard IS 9434: 1992 and ASTM
3613.
 EXTRACTION OF THE GASES (fully computerized ALIGENT
TECHNOLOGIES U.S.A made using the Agilent 7697A Headspace
Sampler.)
 GAS SEPERATION AND MEASURMENT (GAS CHROMATOGRAPHY)
ALIGENT TECHNOLOGIES
80
MINIMUM DETECTION LIMIT
ADVANTAGES THAT DGA CAN PROVIDE
 Advance warning of developing faults
 Determining warning of the improper use of units
 Statuschecks on new and repaired units
 Convenient scheduling of repairs
 Monitoring of units under overload
GAS DETECTION LIMIT in
ppm
HYDROGENH2 0.60
OXYGEN02 11.0
NITROGENN2 11.2
MEATHANE CH4 0.50
CARBON MONO OXIDE
CO
0.10
CARBON DIOXIDECO2 0.10
ACETYLENE C2H2 0.05
ETHYLENE C2H4 0.04
ETHANE C2H6 0.04
PROPANEC3H8 0.20
81
Losses of Transformers
The transformers aremade of 2 types of materials: Iron and Copper. The core of a
transformer is made of Iron whereas thewinding which is wrapped over the iron
core is made up of Copper.
Correspondingly there are 2 types of losses: Iron Loss and Copper Loss. Iron and
Copper losses are measuredby open circuit andshort circuit tests.
TESTS OF DISTRIBUTION TRANSFORMERS
Two tests are conducted for testing transformers. These tests are known by
different names as describedinthe table below.
82
Protective Relay
A relay is automatic device which senses an abnormal condition of electrical
circuit and closes its contacts. These contacts in turns close and complete the
circuit breaker trip coil circuit hence make the circuit breaker tripped for
disconnecting the faulty portion of the electrical circuit from rest of the healthy
circuit.
Types of Relays
Types of protection relays are mainly based on their characteristic, logic, on
actuating parameter and operation mechanism.
Based on operation mechanism protection relay can be categorized as
electromagnetic relay, static relay and mechanical relay. Actually relay is nothing
but a combination of one or more open or closed contacts. These all or some
specific contacts the relay change their state when actuating parameters are
applied to the relay. That means open contacts become closed and closed
contacts become open. In electromagnetic relay these closing and opening of
relay contacts are done by electromagnetic action of a solenoid.
In mechanical relay these closing and opening of relay contacts are done by
mechanical displacement of different gear level system.
In static relay it is mainly done by semiconductor switches like thyristor. In digital
relay on and off state can be referred as 1 and 0 state.
Basedon Characteristic the protectionrelay canbe categorizedas-
 Definite time relays
 Inversetime relays with definite minimum time(IDMT)
 Instantaneous relays.
 IDMTwith inst.
 Stepped characteristic.
 Programmed switches.
 Voltage restraint over current relay.
83
Basedon of logic the protectionrelay canbe categorizedas-
Differential.
 Unbalance.
 Neutral displacement.
 Directional.
 Restricted earth fault.
 Over fluxing.
 Distance schemes.
 Bus bar protection.
 Reversepower relays.
 Loss of excitation.
 Negative phasesequence relays etc.
Basedon actuating parameter the protectionrelay canbe categorizedas-
 Currentrelays.
 Voltage relays.
 Frequency relays.
 Power relays etc.
Basedon applicationthe protectionrelay canbe categorizedas-
 Primary relay.
 Backup relay. Primary relay or primary protection relay is the first line of
power system protection whereas backup relay is operated only when
primary relay fails to be operated during fault. Hence backup relay is slower
in action than primary relay. Any relay may fail to be operated due to any of
the following reasons,
 The protective relay itself is defective.
 DC Trip voltage supply to the relay is unavailable.
 Trip lead from relay panel to circuit breaker is disconnected.
 Trip coil in the circuit breaker is disconnected or defective.
 Currentor voltage signals fromCT or PT respectively is unavailable.
As because backup relay operates only when primary relay fails, backup
protection relay should not have anything common with primary protection relay.
84
Some examples of Mechanical Relay are-
 Thermal
 OT trip (Oil Temperature Trip)
 WT trip (Winding Temperature Trip)
 Bearing temp trip etc.
 Float type
 Buchholz
 OSR
 PRV
 Water level Controls etc.
 Pressureswitches.
 Mechanical interlocks.
 Pole discrepancy relay.
85
List Different Protective Relays are used for
Different Power System Equipment Protection
Now let’s have a look on which different protective relays are used in different
power systemequipment protection schemes.
Relays for Transmission& DistributionLines Protection
Relays for Transformer Protection
86
87
 No Buchholz relay for transformers below500 KVA capacity.
 Transformers upto 1500 KVA shall have only Horn gap protection.
 Transformers above 1500 KVA and upto 8000 KVA of 33/11KV ratio shall
have one group control breaker on HV side and individual LV breakers if
there is more than one transformer.
 Transformers above 8000 KVA shall have individual HV and LV circuit
breakers.
 The relays indicate above shall be providedon HV and LV.
88
 LAs to be provided on HV & LV for transformers of all capacities and
voltage class.
 OLTC out of step protection is to be provided where master follower
scheme is in operation.
 Fans failure and pumps failure alarms tobe connected.
 Alarms for O.T., W.T., Buchholz (Maintank & OLTC) should be connected.
TAP CHANGER
A tap changer is a connection point selection mechanism along a
power transformer winding that allows a variable number of turns to be selected in
discrete steps. A transformer with a variable turns ratio is produced, enabling
stepped voltage regulation of the output. The tap selection may be made via an
automatic or manual tap changer mechanism.
TAP CHANGING
Off-circuit designs (NLTC or DETC)
Also called No-Load Tap Changer (NLTC), off-circuit tap changer, or De-
Energized Tap Changer (DETC).
In low power, low voltage transformers, the tap point can take the form of a
connection terminal, requiring a power lead to be disconnected by hand and
connected to the new terminal. Alternatively, the process may be assisted by
means of a rotary or slider switch.
Since the different tap points are at different voltages, the two connections can
not be made simultaneously, as this would short-circuit a number of turns in the
winding and produce excessive circulating current. Consequently, the power to
the device must be interrupted during the switchover event. Off-circuit or de-
energized tap changing (DETC) is sometimes employed in high voltage
transformer designs, although for regular use, it is only applicable to installations
89
in which the loss of supply can be tolerated. In power distribution networks,
transformers commonly include an off-circuit tap changer on the primary winding
to accommodate system variations within a narrow band around the nominal
rating. The tap changer will often be set just once, at the time of installation,
although it may be changed later during a scheduled outage to accommodate a
long-term change in the system voltage profile.
On-load designs (OLTC)
Also called on circuit tap changer or On Load Tap Changer (OLTC)
For many power transformer applications, a supply interruption during a tap
change is unacceptable, and the transformer is often fitted with a more expensive
and complex on-load tap-changing (OLTC, sometimes LTC) mechanism. On-
load tap changers may be generally classified as either mechanical,
electronically assisted, or fully electronic.

More Related Content

What's hot

Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipatpratikguptateddy
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdfAjay Bhatnagar
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in IndiaMahim Srivastava
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCADITYA ARYAN
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid indiaVaibhav Jain
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
 
Training Report
Training Report Training Report
Training Report Pintu Khan
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
presentation on Nepal electricity authority (NEA)
  presentation on Nepal electricity authority  (NEA)  presentation on Nepal electricity authority  (NEA)
presentation on Nepal electricity authority (NEA)Sudarshan Pandey
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppclSunny Daksh
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONRajeev Kumar
 
KUDANKULAM POWERPLANT by Khan
KUDANKULAM POWERPLANT by KhanKUDANKULAM POWERPLANT by Khan
KUDANKULAM POWERPLANT by KhanKapoorKHAN
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training ReportSWAPNILKUMARGUPTA
 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3Naresh Thakur
 

What's hot (20)

Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
DLW Electrical Engineering industrial training Report
DLW Electrical Engineering industrial training Report DLW Electrical Engineering industrial training Report
DLW Electrical Engineering industrial training Report
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
IEEE 1547
IEEE 1547IEEE 1547
IEEE 1547
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
Training Report
Training Report Training Report
Training Report
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
presentation on Nepal electricity authority (NEA)
  presentation on Nepal electricity authority  (NEA)  presentation on Nepal electricity authority  (NEA)
presentation on Nepal electricity authority (NEA)
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
Tidal Power in India
Tidal Power in IndiaTidal Power in India
Tidal Power in India
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
 
KUDANKULAM POWERPLANT by Khan
KUDANKULAM POWERPLANT by KhanKUDANKULAM POWERPLANT by Khan
KUDANKULAM POWERPLANT by Khan
 
Energy project report on hydropower
Energy project report on hydropowerEnergy project report on hydropower
Energy project report on hydropower
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
 
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEWEHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
 

Viewers also liked

Power failure presentation
Power failure presentationPower failure presentation
Power failure presentationSatyendra Arora
 
Survey & ts for ehv lines
Survey & ts for ehv linesSurvey & ts for ehv lines
Survey & ts for ehv linesMahesh Sontyal
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Acknowledgement
AcknowledgementAcknowledgement
Acknowledgementrehan1991
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch centerddxdharmesh
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage gourav1245
 
E5 cn manual_esp
E5 cn manual_espE5 cn manual_esp
E5 cn manual_espPedro Roman
 
controlador manual
controlador manual controlador manual
controlador manual Pedro Roman
 
Effect of secondary phase precipitation on the corrosion behavior of duplex ...
Effect of secondary  phase precipitation on the corrosion behavior of duplex ...Effect of secondary  phase precipitation on the corrosion behavior of duplex ...
Effect of secondary phase precipitation on the corrosion behavior of duplex ...Pedro Roman
 
Creep fatigue interaction testing
Creep fatigue interaction testingCreep fatigue interaction testing
Creep fatigue interaction testingPedro Roman
 
Refrigeration system
Refrigeration systemRefrigeration system
Refrigeration systemGaurav Gunjan
 

Viewers also liked (20)

Power failure presentation
Power failure presentationPower failure presentation
Power failure presentation
 
tower spotting
tower spottingtower spotting
tower spotting
 
Survey & ts for ehv lines
Survey & ts for ehv linesSurvey & ts for ehv lines
Survey & ts for ehv lines
 
Project report
Project reportProject report
Project report
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Acknowledgement
AcknowledgementAcknowledgement
Acknowledgement
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
Power Scenario in India
Power Scenario in IndiaPower Scenario in India
Power Scenario in India
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
 
Solar modelcar
Solar modelcarSolar modelcar
Solar modelcar
 
Ruchi panwar
Ruchi panwarRuchi panwar
Ruchi panwar
 
E5 cn manual_esp
E5 cn manual_espE5 cn manual_esp
E5 cn manual_esp
 
Omrom e5cn i
Omrom e5cn iOmrom e5cn i
Omrom e5cn i
 
controlador manual
controlador manual controlador manual
controlador manual
 
Night vision car
Night vision carNight vision car
Night vision car
 
Gaurav ppt
Gaurav pptGaurav ppt
Gaurav ppt
 
Effect of secondary phase precipitation on the corrosion behavior of duplex ...
Effect of secondary  phase precipitation on the corrosion behavior of duplex ...Effect of secondary  phase precipitation on the corrosion behavior of duplex ...
Effect of secondary phase precipitation on the corrosion behavior of duplex ...
 
Creep fatigue interaction testing
Creep fatigue interaction testingCreep fatigue interaction testing
Creep fatigue interaction testing
 
Welded joints
Welded jointsWelded joints
Welded joints
 
Refrigeration system
Refrigeration systemRefrigeration system
Refrigeration system
 

Similar to MHPS(DVC) PROJECT REPORT

26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptxSukantaMandal17
 
Hydro potential of india
Hydro potential of indiaHydro potential of india
Hydro potential of indiaRohil Kumar
 
Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhandijsrd.com
 
Hydro power scenario in india 2013
Hydro power scenario in india 2013Hydro power scenario in india 2013
Hydro power scenario in india 2013Vipul Kumar
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in IndiaIPPAI
 
Srsp Microhydel Initiatives
Srsp Microhydel Initiatives Srsp Microhydel Initiatives
Srsp Microhydel Initiatives SRSP
 
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptx
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptxDiscussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptx
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptxRAFSUNJANY2
 
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptx
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptxhydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptx
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptxlakshmanaraoJeeru1
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
The future of hydro power in kenya
The future of hydro power in kenyaThe future of hydro power in kenya
The future of hydro power in kenyaSammy Jamar
 
PGVCL Training Report
PGVCL Training ReportPGVCL Training Report
PGVCL Training ReportPriten Vasa
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plantRaj Kumar Parihar
 
Wind energy its potential in india
Wind energy  its potential in indiaWind energy  its potential in india
Wind energy its potential in indiafarsoiya
 
Kuching | Jan-15 | Micro Hydro Project For Rural Electrification
Kuching | Jan-15 |  Micro Hydro Project For Rural ElectrificationKuching | Jan-15 |  Micro Hydro Project For Rural Electrification
Kuching | Jan-15 | Micro Hydro Project For Rural ElectrificationSmart Villages
 

Similar to MHPS(DVC) PROJECT REPORT (20)

Project report1
Project report1Project report1
Project report1
 
26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx
 
Hydro potential of india
Hydro potential of indiaHydro potential of india
Hydro potential of india
 
Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhand
 
REPORT-NHPC
REPORT-NHPCREPORT-NHPC
REPORT-NHPC
 
Hydro power scenario in india 2013
Hydro power scenario in india 2013Hydro power scenario in india 2013
Hydro power scenario in india 2013
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in India
 
Srsp Microhydel Initiatives
Srsp Microhydel Initiatives Srsp Microhydel Initiatives
Srsp Microhydel Initiatives
 
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptx
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptxDiscussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptx
Discussion on Sub-Station Equipment and Power Grid System in Bangladesh.pptx
 
Small
SmallSmall
Small
 
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptx
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptxhydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptx
hydroelectricityandhydropowerplant-141015231355-conversion-gate02.pptx
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
The future of hydro power in kenya
The future of hydro power in kenyaThe future of hydro power in kenya
The future of hydro power in kenya
 
Hydro Power in India
Hydro Power in IndiaHydro Power in India
Hydro Power in India
 
Hydro power presentation
Hydro power presentationHydro power presentation
Hydro power presentation
 
Construction of PCC Parapet
Construction of PCC Parapet Construction of PCC Parapet
Construction of PCC Parapet
 
PGVCL Training Report
PGVCL Training ReportPGVCL Training Report
PGVCL Training Report
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
 
Wind energy its potential in india
Wind energy  its potential in indiaWind energy  its potential in india
Wind energy its potential in india
 
Kuching | Jan-15 | Micro Hydro Project For Rural Electrification
Kuching | Jan-15 |  Micro Hydro Project For Rural ElectrificationKuching | Jan-15 |  Micro Hydro Project For Rural Electrification
Kuching | Jan-15 | Micro Hydro Project For Rural Electrification
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

MHPS(DVC) PROJECT REPORT

  • 1. BY ABHINAW KUMAR RAI ADITYA MISHRA VISHAL SINGH SAMBUJ KUMAR SONA JAMAL HUSSAIN NANDLAL MANDAL AJAY KUMAR RAHUL RANJAN ELECTRICAL ENGINEERING BANKURA UNNAYANI INSTITUTE OF ENGINEERING
  • 2. 2 ACKNOWLEDGEMENT The dissertation has been prepared based on the vocational training undergone in a highly esteemed organization of Eastern region, Maithon Hydel Power Station (MHPS) is located on the river Barakar about 12.9 km above its confluence with the Damodar near the border of Dhanbad & Burdwan districts of the states of Jharkhand & West Bengal respectively. The unique feature of this is that it is located underground in the left bank of the river and is the first of its kind in India. The power station has a total generating capacity of 60 MW with 3 units of 20 MW each. MHPS is located at almost 1000 feet below the water level,and is the first of its kind, in South East Asia. I would like to express my heartfelt gratitude to the authorities of MAITHON HYDEL POWER STATION and BANKURA UNNAYANI INSTITUTE OF ENGINEERING for providing me such an opportunity to undergo training in the Hydel power plant of DVC, MHPS. I would also like to thank the Engineers, highly experienced without whom such type of concept building in respect of Hydel power plantwould not have been possible. Some of them are: 1: P.GHOSH (Assistant Engineer CLD,DVC MAITHON) 2:NAUSAD HUSSAIN(Chief Engineer G.M.O.D-II KALYANESWARI 220KV SUBSTAION)
  • 3. 3 CONTENT  TRAINING REPORT FOR PUBLIC RELATION OFFICE 5-20  DAMODAR VALLEY CORPORATION  MISSION & VISION  PIONEERING ROLE  DVC INFRASTRUCTURES  DVC POWER STATION  POWER MAP  DAMS & BARAGES  INITIATIVES FOR SOCIAL SECTOR DEVLOPMENT  TRAINING REPORT FOR CENTRAL LOAD DISPATCH 21-31  NATIONAL LOAD DISPATCH CENTRE  THERMAL GENERATION  CLD MAITHON  DEMAND FORECASTING & SHEDULING  HYDEL GENERATION  TIE LINES  POWER SYSTEM OPERATION CORPORATON  SINGLE LINE DAIGRAM OF 220/132KV DVC GRID  SCADA  TRAINING REPORT FOR TRANSMISSION DEPARTMENT 32-53  220 KV KALYANESWARI SUBSTATION  SINGLE LINE DAIGRAM OF 220 KV  KALYANESWARI SUB STATION G.O.M.D –II, D.V.C  RATINGS  220 KV KALYANESWARI SUBSTATION  BASIC COMPONENTS OF SUBSTATION  TRANSMISSION SYSTEM  GRIDMAP  SUBSTATION  ELECTRICAL SUBSTATION MODEL(SIDE VIEW)  REPORT FOR TRANSMISSION 54-73 SYSTEM CONSTRUCTION  PROCEDURE OF TSC  TRANSMISSION ROUTE  SUREVY OF LINES  APPROVAL REQUIREMENT  MINIMUM CLEARANCE  APPLICATION OF SAG TEMPLATE ON PROFILE  TOWER CONSTRUCTION : EXCAVATION MARKING CHART  TOWER FOUNDATION : PYRAMID CHIMNEY TYPE  STRINGING OF CONDUCTORS AND EARTHWIRE  MINIMUM CLEARANCE : IS: 5613 (Part II/Sec-1)-1976  TOWER USED FOR TRANSMISSION LINE
  • 4. 4  TOWER CONSTRUCTION : EXCAVATION MARKING CHART  STRINGING OF CONDUCTORS AND EARTHWIRE  Substation construction  EARTHING OF SUB STATION-  TRAINING REPORT FOR CENTRAL TESTING CENTER 75-87  Central Testing Center  TRANSFORMER OIL  On-site testing  DGA or Dissolved Gas Analysis of Transformer Oil  DGA TESTING OF TRNSFORMERS OF DVC  MINIMUM DETECTION LIMIT  ADVANTAGES THAT DGA CAN PROVIDE  Protective Relay -.-.-.-.-.-.-.-.-.-.-.-.-.-
  • 5. 5 TRAINING REPORT FOR PROGRAMME NO. 1 - P.R.O PUBLIC RELATION OFFICE 06/07/2015 TO 07/07/2015 PRO office,Combined Administrative Building (2nd Floor),Area-6 Damodar Valley Corporation
  • 6. 6 DAMODAR VALLEY CORPORATION Damodar Valley Corporation is the first ever multipurpose river valley project of independent India which came into being on July 7, 1948 by an Act of the constituent Assembly ( Act no. Xiv, 1948).Having command area of 24,325 sq.kms spreading across the damodar basin , boundaries of which transcends the state of Jharkhand & West Bengal . The upper valley consists of two entirely districts ( Dhanbad & Bokaro) & eight districts partly ( Hazaribagh, Koderma, Giridih, chhatra, Palamu, Ranchi, Lohardaga & dumka) in the state of Jharkhand .The lower valley on the other hand consist of five districts partly ( Burdwan & Hoogly, Howrah,Bankura,& purulia) in the state of West Bengal.Since the beginning, DVC has given due emphasis on power generation & distribution, besides flood control and irrigation, eco conservation & socio- economic development. Today DVC power is a vital input to core sectors including Steel plants , Railways, collieries along with State Electricity Boards of Jharkhand & West Bengal, big & medium industries within & beyond the Damodar Valley. DVC was set up with the intent of promoting & operating the schemes which may cause social and economic uplift in the valley region. DVC has already established it existence in discharging its obligations for more than five decades in perfect harmony. The difficult but effective water management by Corporation has turned the devastating river Damodar from ‘River of Sorrow’ to ‘River of Prospects and opportunities’.Proficient management of water resources through dams ,canals & barrage, DVC facilitates irrigation as well as industrial & domestic water supply which at large benefited the region as a whole. It has also contributed significantly in conservation of soil & promotion of schemes of social integration in valley area.
  • 7. 7 MISSION & VISION THE MISSION The mission at the time of its inception was :  Flood control  Promotion & operation of schemes for irrigation  Water supply for industrial& domestic use  Navigation & drainage  Generation , Transmission & Distribution of electrical energy  Promotion of a forestation and control of soil erosion in valley area  Promotion of public health , agriculture, industrial, economic & general well-being in damodar valley In keeping with industrialisation in DVC command area ,power generation , transmission & distribution gained priority for providing electricity to the core industries like steel , railways , coal & other industrial& consumers through respective State Electricity Boards . However other mandated objectives also received equal importance as part of overallresponsibility and commitment of DVC. Capacity addition programmefor power generation gained a new direction when ministry of power, Govt. Of India started advocating for setting up of thermal power plants at or near pit heads & transmitpower rather than transporting coal and advising DVC to world towards adequate capacity addition during the Tenth and Eleventh plan in order to meet the power vision. In addition to programmeof capacity addition of 1210MW in Tenth Five year plan and 6000MW in Eleventh plan , DVC has decided to rejuvenatethe existing unit through comprehensiveoverhauling and refurbishment. Besides this , extension and augmentation of transmission network of DVC, devised with the assistanceof CEA and also strengthening of existing transmission and distribution network are also under process of implementation. DVCis implementing ruralelectrification project in states of West Bengal & Jharkhand under “ Rajiv Gandhi Grameen vidyutikaran yojna ”
  • 8. 8 THE VISION To establish DVC as one of the largest power majors of Eastern India while discharging the responsibilities of its other objects adequately . In order to achieve this goal against the backdrop of competitive market scenario in the power sector, the objectives of the corporation havebeen redefined. CORPORATE OBJECTIVES  Generate more power at lowest possible costby improving operational efficiencies of the existing plants, rejuvenating old generating units through comprehensiveoverhauling as well as by installing new generating plants  Transmit , distribute and supply reliable and quality power at competitive tariff.  Improvethefinancial health of corporation by adoption of efficient industrial , commercial and human resourcemanagement practices.  Ensureoptimum utilization of available water resources through effective and  Efficient management and harness theremaining potential of Damodar basin to extent possible.  Fortify measures for environmentalprotection at plant levels and to continue with activities of conservation in the valley area.  Strengthen socio-economic development for the inhabitants of villages neighbouring major projects of DVC.
  • 9. 9 PIONEERING ROLE  First multipurpose river valley project of Governmentof India .  A Govt. Of India organisation generating power utilizing two sources – Coal and water  FirstGovt. Of India projectmanaging generation transmission and distribution of electricity  Firstunderground hydel station at Maithon  Bokaro Thermal Power station , biggest thermal power plant of the nation in 50’s of last century  Bokaro Thermal Power Station boilers, first to burn pulverized coal in India.  Firstre-heat units in India utilizing high steam parameter at Chandrapura Thermal Power station  Mejia Thermal Power Station , first in eastern India for the application of Direct Ignition of Pulverized coal (DIPC) systemfor reducing oil consumption in the boiler.  Mejia Thermal Power Station , Firstof its kind in eastern India with tube mills
  • 10. 10 DVC INFRASTRUCTURES With the time DVC developed and expanded its infrastructure Five thermal power stations with a capacity of 2570 MW, three hydro- electric power stations with a capacity of 144 MW and one gas turbine station with a capacity of 82.5 MW contribute to a total installed capacity of 2796.5 MW. Presently DVC has 60 sub- stations and receiving stations more than 5500-circuit km of transmission and distribution lines. DVC has also four dams, a barrage and a network of canals that play an effective role in water management. The construction of check dams, development of forests and farms and upland and wasteland treatment developed by DVC play a vital role in eco conservation. DVC Command Area 24,235 Sq. Kms POWER MANAGEMENT Total Installed Capacity 2796.5 MW Thermal Power Stations Five Capacity 2570 MW Hydel Power Stations Three Capacity 144 MW Gas Turbine Station One Capacity 82.5 MW Sub-stations and Receiving Stations At 220 KV– 11 nos. At 132 KV– 33 nos. At 33 KV– 16 nos. Transmission Lines 220 KV– 1500 ckt kms 132 KV– 3415 ckt kms 33 KV– 1070 ckt kms
  • 11. 11 Water Management Major Dams and Barrage Tilaiya,Konar, Maithon Panchet dams and Durgapur Barrage Irrigation Command Area (gross) 5.69 lakh hectares Irrigation Potential Created 3.64 lakh hectares Flood Reserve Capacity 1292 millionCu.m. Canals 2494 kms Soil Conservation Forests, Farms, Upland and Wasteland Treatment 4 lakh hectares (approx) Check Dams 16,000 (approx)
  • 12. 12 DVC POWER STATION Name Location Capacity Commissioning THERMAL Bokaro 'B' Dist- Bokaro State- Jharkhand 630 MW (3 X 210 MW) U-I Mar 86 U-II Nov90 U-IIIAug 93 Chandrapura Dist- Bokaro State- Jharkhand 890 MW (3 X 130 MW)+ (2 X 250 MW) U-I Oct 64 U-II May 65 U-IIIJuly68 U-VIINov11 U-VIIIJul 11 Durgapur Dist.- Barddhaman State- WestBengal 350 MW (1X140 MW)+ (1X210 MW) U-IIIDec 66 U-IV Sept82 Mejia Dist.- Bankura State- WestBengal 2340 MW (4 X 210 MW) + (2 X 250 MW)+ (2 X 500 MW) U-I Mar 96 U-II Mar 98 U-IIISept99 U-IV Feb05 U-V Feb08 U-VISept08 U-VIIAug11 U-VIIIAug12 DSTPS Dist.- Bardhaman State- WestBengal 1000 MW (2 X 500 MW) U-I May 12 U-II Mar 13 KTPS Dist.- Koderma State- Jharkhand 500 MW (1 X 500 MW) U-I July13 Total Thermal 5710 MW Name Location Capacity Commissioning HYDEL Tilaiya River- Barakar Dist.-Hazaribagh State- Jharkhand 4 MW (2 X 2 MW) U-I Feb’53 U-II July’53 Maithon River- Barakar Dist.- Burdhaman State- West Bengal 63.2 MW (2 X 20 MW) + (1 X 23.2 MW) U-I Oct’57 U-II Mar’58 U-II Dec’58 Panchet River- Damodar Dist.- Dhanbad State -Jhankhand 80 MW (2 X 40 MW) U-I Dec’59 U-II Mar’91 Total Hydel . 147.2 MW GRAND TOTAL 5857.2 MW
  • 14. 14 DAMS & BARAGES FRONT VIEW OF SPILLWAYS OF MAITHON DAM Tilaiya Konar Maithon Panchet Inauguration 21.02.53 15.10.55 27.09.57 06.12.59 On River Barakar Konar Barakar Damodar District Hazaribagh Hazaribagh Dhanbad Dhanbad State Jharkhand Jharkhand Jharkhand /W.B Jharkhand /W.B Height above river bed (meters) 30.18 48.77 50.00* 40.84* 44.00** 45.00** Length (meters) 366 4535 4860 6777 Width of roadway (meters) 3.81 5.79 6.78 10.67 Power generating capacity 2 x 2 MW - 3 x 20 MW 2 x 40 MW Storage capacity (million cu.m.) To dead storage 75.25 60.4 207.24 170.37 To top of gates 394.74 336.76 1361.84 1497.54 Allocation of storage capacities (MCM) For irrigation & power 141.86 220.81 611.84 228.21 For flood control 177.63 55.51 542.76 1086.76 Drainage area (sq. km.) 984.2 997.1 6293.17 10966.1 Reservoir (sq. km.) At dead storage level 15.38 7.49 24.28 27.92 At maximum conservation pool 38.45 23.15 71.35 121.81 Area top of gates 74.46 27.92 107.16 153.38
  • 15. 15 Durgapur Barrage Details of Canal Network. Length (Km) Discharge at Head Regulator (Cumec) LBMC (Left Bank Main Canal)(Canal originating from Durgapur Barrage) 136.8 260 RBMC (Right Bank Main Canal) (Canal originating from Durgapur Barrage) 88.5 64.3 Total length of main and branch canals 2494 DURGAPUR BARRAGE Year of construction 1955 Length 692 m Number of gates 34 (including under sluice) Size of gates 18.3m x 4.9m [60 ft x 16 ft] Left & right under sluice 18.3m x 5.5 m [60 ft x 18 ft] Operating levels Between RL. 64.5 m [211.5 ft] to RL. 63.4 m [208.0 ft]
  • 16. 16 INITIATIVES FOR SOCIAL SECTOR DEVLOPMENT Social Integration Programme DVC launched its Social Integration Programme(SIP) in 1981.SIP is basically an expression of DVC’s deep commitment to socio-economic and infrastructural development of the communities residing within a 10 Km radius of its main projects. The programmestarted with 25 villages. At presentit operates in 375 villages covering 70 Panchayats in 12 blocks of Dhanbad, Giridih, Bokaro and Hazaribagh districts of Jharkhand and Barddhaman, Purulia and Bankura districts of West Bengal. Areascovered under the programme: ·Education ·Agriculture ·Health ·InfrastructuralDevelopment ·Sportsand Culture ·RuralElectrification ·Self- employment ·SocialForestry EDUCATION DVC’s Social IntegrationProgramme (SIP) offers the following facilities:  Non-formaladult education centers, rurallibraries and community centers run by DVCto help spread literacy among the communities residing within a 10 km radius of DVC’s main projects. All inputs are fed by DVC  DVCruns 43 Sishu Siksha Kendras for imparting primary level education to children of economically disadvantaged families and also to dropouts and those over aged. At present 1200-1300students aregetting free primary education.  In these Kendras students get reading and writing materials free of cost. Even Keroseneoil is provided to run these Kendras in the remote areas of Panchet, Konar and Tilaiya projects.
  • 17. 17  Children belonging to SIP villages are eligible to study in the schools meant for the children of DVC’s employees. Social Development DVC implements integrated social development work in villages situated with in 10 km area of it's major projects through it's social integration programme. Environment Management The Environment Management work of DVC consists of two parts the firstpart DVC is installing proper equipment and augmenting majors to follow the pollution norms in it's thermal power plants the second part consists of a forestations and other conservation work for preservation of eco systemof Damodar Valley area. Soil Conservation Soil Conservation work of DVCaims to check soil erosion, and siltation of dams, improveagricultural production, afforestation and reserves ecological balance. Rural Electrification DVC has been entrusted with the responsibility of implementing rural electrification projectin selected district of West Bengal and Jharkhand under'RAJIV GANDHI GRAMINVIDYUTIKARANYOJANA'. Welfare DVC provides various facilities for the well being of it's employees and their dependents. Some of the facilities are also being extended to the villagers covered under the social integration programme
  • 18. 18 AGRCULTURAL DVC is engagedin the following activities toincrease agricultural yieldfrom fields:  Initiation of micro-lift irrigation programmes in the upper valley  Digging of irrigation wells  Construction of check dams  Renovation of ponds  Arranging training programmes for farmers DVC has constructedmore than16,000 check dams Farmers of the local villages are encouraged to adoptmodern scientific farming practices, Experts fromKVK, Sindri, Holy Cross KrishiVigyan Kendra, Hazaribagh and Birsa Agricultural University, Ranchiand R.K. Mission of Amarkanan Sewa Ashram, Purulia impart training in this regard. HEALTH DVC’s health programmes under SIP are basically preventive as well as curative in nature Preventive Health Services: DVC organizes from time to time various camps  Pulse-polio immunization camp.  Family welfare and operation camp.  Anti-malaria camp.  Aids and HIV awareness camp.  Anti-diarrhea camp.  Eye (cataract) operation camp.  TB awareness and detection camp.
  • 19. 19 INFRASTRUCTURAL DEVLOPMENT Infrastructural development worksareessentially need-based activities:  Drinking water Safe drinking water facilities through tap points, hand pumps and wells.  Communication Construction of roads (WBM/ bituminous / PCC), culverts, drainage system, passenger shelters etc.  Education and HealthCare Construction of schoolbuildings along with boundary walls, community buildings, adult education centers and dispensary buildings  IrrigationFacilities Installation of micro lift irrigation/RL Renovation and construction of ponds Construction of check dams and irrigation wells.  Others Construction of toilets, urinals, washing and bathing ghats and burning ghats. SELF EMPLOYMENT Training Programme and Self-employment DVC is actively engaged in helping local unemployed youths find meaningful occupations. For this the following facilities are offered:  Training centers at Maithon, CTPS, BTPS, DTPS and Panchet.  Youths sent to differentcentres run by outside organizations for training on poultry, duckary, goattery, para-veterinary,plantpropagation, dairy, diesel pump mechanic, mushroomcultivation, piggery etc.  Firsttime assistanceby DVCin terms of raw materials and kits to help trained youths set up their own business/enterprises.
  • 20. 20 ENVIROMENT MAMAGEMENT We care for the Earth DVC strongly believes that excellence in the environmental fields is of prime importance. DVCstrives to work with environmental issues in a consistentand systematic manner. DVC’s environmentalmanagement programmeconsists of  Pollution control at its thermal power stations and  Combating soil erosion and soil decay in order to restoreand preserve the quality of the land. PollutionControl Pollutants in the formof ash and emissions fromstack arethe major sources of pollution at coal-based thermal power stations. In old units, of DVC, at Bokaro, Chandrapura and Durgapur, which werecommissioned, before pollution control standards becamestringent, the following measures have been taken to bring the pollutants within the limits:  Initiation / installation of ESPs with additional fields to bring down emission within limits.  Renovation of de-ashing and ash handling system.  Installation of oil and grease separator.  Plantation in and around plant areas, ash disposalareas and outside the projectareas. Modern units at MTPS, commissioned during 1990s, comply with latest pollution control norms, including the provision of reuse and recycling of maximum affluent to conserveland and water. DVC’s solid wastemanagement systemconsists of evacuation of ash fromthe ash ponds at BTPS, CTPS and DTPS, transported in protective manner and dumped into abandoned open castcoal mines of CCL, BCCL and ECL respectively. After filling up of the mines is over, the top surface is covered with earth of sufficientthickness to facilitate growth of vegetation
  • 21. 21 TRAINING REPORT FOR PROGRAMME NO. 2 - C.L.D CENTRAL LOAD DISPATCH 08/07/2015 TO 10/07/2015 CLD office, Combined Administrative Building (2nd Floor) Area-6 Damodar Valley Corporation
  • 22. 22 NATIONAL LOAD DISPATCH CENTRE supervise regional load dispatch centres according to Sec-26(2)- act of Ministry of Power (2005). These five regions are NATIONAL LOAD DISPATCH CENTER ER-EAST REGION WR-WESTREGION NR-NORTH REGION SR-SOUTH REGION NER-NORTH EASTREGION Bihar Chhattisgarh Punjab Andhra Pradesh Arunachal Pradesh DVC Gujarat Haryana Telangana Assam Jharkhand MP Rajasthan Karnataka Manipur Odisha Maharashtra Delhi Kerala Meghalaya W.B Goa U.P Tamil Nadu Mizoram Sikkim DD Uttarakhand Pondy Nagaland DNH H.P Tripura Essar steel J&K Chandigarh CLD- MAITHON comes under ER
  • 23. 23 CLD MAITHON IS RESPONSIBLE FOR :  Optimum Scheduling and dispatch of Electricity within the region.  Monitor grid operation.  Accounts of quantity of electricity transmitted through the regional grid.  Supervise & control over Inter-State Transmission System.  Real Time Operation of grid control & dispatch of electricity through secure & economic operations according with grid standard & grid code. A ULDC/load Dispatch Centre of Damodar Valley Corporation is the ModernComputerized on-line data monitoring system of DVC. Main Display at Central Load Dispatch Date 08-JUL-2015 TIME 11:50:52
  • 24. 24 DEMAND FORECASTING & SHEDULING 08-JUL-2015 SUMMARY DAIGRAM-DVC 08-JUL-2015 11:50:52 FREQUENCY 50.05 UI RATE(PAISE) 261.36 DEV(MW) 33 TOTAL SCHEDULED 571 MAX. ADDITIONAL RATE/PENALTY RATE(OVER INJECTION)-0 BSEB JSEB DVC GRIDCO WBSEB SIKKIM GENERATION 1 0 2711 1857 3311 DRWL SCHD -2050 -482 571 -848 -2081 ACT. DRAWL -2385 -87 604 6397 -2068 DEMAND 2385 87 2107 -4540 5379 ACTUAL GEN. SHARE OF DVC RANGIT 61 6 CHUKHA 251 26 TEESTA 515 44 TALA 1079 60 KURICHU 38 19 FARAKKA 326 25 TALCHER 470 1 ACTUAL CONTROL ERROR = 36 K▲F= -2.63 VOL.BTW 12%-15% = 0.00 VOL.BTW 15%-20% = 0.00 VOL. BEYOND 20 % = 0.00 DVC GENERATION MW THERMAL GEN 2635 HYDRO GEN 76 TOTAL GEN 2711TOTAL CS GEN :- 6220 NET EXPORT =1199 EXPORT RATE (PAISE/kwh)=101 CONSR CD(MVA) ACT(MW NET IMPORT = -103 IMPORT RATE (PAISE/kwh)= 218 BSL TISCO DSP IISCO 200 120 190 100 126 -30 WL 27 55 NET UI (mwh) = 1096 [ COMULATIVE SINCE 00:00 HRS]
  • 25. 25 HYDEL GENERATION MHS PHS TILAIYA TIME BLOCK AVG. FREQ(HZ) RATE (PAISE/KWH ) UI(m wh) TSL UNIT 1 15 28 2 1100-1115 49.99 220 2 -34 UNIT 2 17 0 0 1115-1130 49.92 366 7 -33 UNIT 3 14 -- -- 1130-1145 50.08 71 0 -35 TOTAL 46 28 2 1145-1150 50.02 107 1 -32 THERMAL GENERATION DSTPS BOKARO- B MEJIA WARIA CTPS132 CTPS B KTPS RTPS GEN. GEN. GEN. GEN. GEN. GEN. GEN. GEN. U#1 386 0 151 0 --- 0 0 U#2 0 0 165 84 --- 376 0 U#3 --- 0 152 87 91 --- U#4 --- --- 0 0 0 --- U#5 --- --- 0 --- --- --- U#6 --- --- 182 --- --- --- U#7 --- --- 372 --- --- 0 U#8 --- --- 383 --- --- 206 TOTAL 386 0 1405 87 175 206 376 0
  • 26. 26 TIE LINES Lines MW Lines MW CENTRAL SECTOR GRIDCO PURLIA-PURLIA PG-I -84 JAMSHEDP-JODA -39 PURLIA-PURLIA PG-I -76 TOTAL 39 KALYA-MAITHON PG-I -71 WBSEB KALYA-MAITHON PG-II -70 WARIA-BIDHAN’R-I 34 DHN-MATHN-PG-I -112 WARIA-BIDHAN’R-II 33 DHN-MATHN-PG-II -117 KOLAG-KOLAG 0 MEJIA B-JAM’PUR PG 190 TOTAL 67 DSTPS- JAM’PUR PG –I 146 JSEB DSTPS- JAM’PUR PG –II 140 PATRATU- PATRATU TPS -1 0 MEJIA B- MAITHON PG-I 210 PATRATU- PATRATU TPS -2 0 MEJIA B- MAITHON PG-II 209 CHANDIL –MAINIKUI 0 MEJIA B- MAITHON PG-III 140 MAITTHON- JAMTARA 39 TISCO(DVC)-BARIPADA 206 TOTAL 39 TISCO(DVC)- JAM’PUR PG -347 BSEB KODERMA-B’SARIF-PG-I -65 BARHI – B’SHARIF 0 KODERMA-B’SARIF-PG-II -64 BARHI - RAJGIR 0 KODERMA-GAYA-I 0 TOTAL 0 KODERMA-GAYA-II 224 NET INTERCHANGE 604 RTPS-RANCHI-PG-I 41 RTPS-MAITHON-PG 36 TOTAL 530
  • 27. 27 IMPORTANT LINES MW JAMALPUR –MEJIA B1 -178 DURGAPUR- JAMALPUR -44 MAITHON- KHSTPP-I -76 MAITHON - KHSTPP -II -79 DURGAPUR-FSTPP- I -278 DURGAPUR- FSTPP-II -281 MAITHON-JAMALPUR-I -178 MAITHON-JAMALPUR-II -48 PURULIYA-JAMALPUR -44 JAMALPUR- ROURKELA-II I ROURKELA-RAIGHAR- I -41 ROURKELA- TSTPP –I I ROURKELA-TSTPP-II 0 KHSTPP- B’SHARIF- I 46 KHSTPP –B’SHARIF-II I B’SHARIF-SASARAM-1 I B’SHARIF-SHASARAM-II I SASARAM- ALLAHABAD-I 193 SASARAM-ALLAHABAD- II 138 RENGALI-TSTPP-I 150 RENGALI-TSTPP-II -283 RENGALI- INDRAVATI -283 INDRAVATI- JAYPORE 290 JAYPORE-GAJUWAKA-I 394 JAYPORE-GAJUWAKA-II 27 MAITHON-RANCHI-I -34 RANCHI-ROURKELA-I -34 RANCHI- ROURKELA-II 282
  • 28. 28 DEMANDFORE CAST (FOR TODAY) 08 jul 2015 TIME BLOCK DEMAND 1130-1145 2253 1145-1200 2256 1200-1215 2255 1215-1230 2268 1230-1245 2209 1245-1300 2215 1300-1315 2228 1315-1330 2243 1330-1345 2235 1345-1400 2226 1400-1415 2188 1415-1430 2194 REGION UI RATE(PAIS) FREQ SR/WR/WR 261 50.11 INTER REG. EXCHANGE ACTUAL SCHEDULED ER-WR 365 651 ER-SR 2686 2633 ER-NER -300 81 ER-NR 1838 1614 DSTPS-RTPS-I 38 DSTPS-RTPS-II 38 KTPS-BOKARO-I 90 KTPS-BOKARO-II 89 DVC BUS VOLTAGE KV MEJIA B 420 DSTPS 420 KODERMA 412 TISCO 413 RTPS 467 BOKARO B 220 CTPS 220 218 JAMSHEDPUR 222 KALYANESHWARI 225 MEJIA- TPS 229 PURULIYA 229 WARIA 227 ASP 139 CTPS 132 133 MAITHON (H) 137 MOSABANI 131 PANCHET 135
  • 29. 29 Power System Operation Corporation Power System Operation Corporation Limited (POSOCO) is a wholly owned subsidiary of Power Grid Corporation of India Limited (PGCIL). It was formed in March 2010 to handle the power management functions of PGCIL. It is responsible to ensure the integrated operation of the Grid in a reliable, efficient and secure manner. It consists of 5 Regional Load Despatch Centres and a National Load Despatch Centre (NLDC). The subsidiary may eventually be made a separate company, leaving the parent firm with only the task of setting up transmission links. The load despatch functions,earlier handled by PGCIL, will now come up to POSOCO. Power Grid Corporation ofIndiaLimited (aGovernment Company)shall operate National Load Despatch Centre and thefive Regional Load Despatch Centers, with effect from October 1, 2010.
  • 30. 30 SINGLE LINE DAIGRAM OF 220/132KV DVC GRID
  • 31. 31 SCADA Supervisory control and data acquisition (SCADA) systems have traditionally played a vital role by providing utilities with valuable knowledge and capabilities that are key to a primary business function – delivering power in a reliable and safe manner. A quality SCADA solution is central to effective operation of a utility's most critical and costly distribution, transmission, and generation assets. The challenging issues for SCADA systems and projects today are not the same as they were a few years ago. Today, there is much more importance placed on integration, use of new communication and network technologies, access to information by more users, and other purposes. Today’s SCADA systems, in response to changing business needs, have added new functionalities and are aids for strategic advancements towards interactive, self healing smart grids of the future. A modern SCADA system is also a strategic investment which is a must-have for utilities of all sizes facing the challenges of the competitive market and increased levels of real time data exchange that comes with it (independent market operator, regional transmission operator, major C&I establishments, etc.). A well planned and implemented SCADA system not only helps utilities deliver power reliably and safely to their customers but also helps to lower costs and achieve higher customer satisfaction and retention. Modern SCADA systems are already contributing and playing a key role at many utilities towards achieving:  New levels in electric grid reliability  Increased revenue.  Proactiveproblem detection and resolution  Higher reliability.  Meeting the mandated power quality requirements  Increased customer satisfaction.  Real time strategic decision making costreductions and increased revenue.
  • 32. 32 TRAINING REPORT FOR PROGRAMME NO. 3 - TRANS. TRANSMISSION DEPARTMENT 13/07/2015 TO 16/07/2015 220 KV KALYANESWARI SUB-STATION Damodar Valley Corporation
  • 33. 33 220 KV KALYANESWARI SUB-STATION Substation  An Electrical Substation is a subsidiary station of an electricity Generation , Transmission And Distribution System where voltage is transformed high to low or reverse using transformer.  Examples of Substation:-  400kV/220kV substation  220kV/132kV substation  132kV/33kV substation  33kV/11kV substation  33kV/.4kV substation
  • 34. 34 220 KV KALYANESWARI SUBSTATION 201 202 228 229 239 240 237 238 C T P S M T P S VIA BURNPUR PGCIL 220 KV ATR 1 150 MVA ATR 2 160 MVA ATR 3 150 MVA 18 19 KLP MHS 132 KV 68 69 MAL PWR TR 50 MVA PWR TR 50 MVA 33 KV 0.415 KV 250 KVA 250 KVAANP1 HIRA UM NKITA BMA MPLANP2 AUX PWR
  • 35. 35 SINGLE LINE DAIGRAM OF 220 KV KALYANESWARI SUB STATION G.O.M.D –II, D.V.C
  • 36. 36 Ratings ATR 1 BHEL SCHEMATIC DAIGRAM VECTOR DAIGRAM
  • 37. 37 ATR 2 BHARAT BIJLLE
  • 38. 38 The basic components of a substation are as follows: AUTO TRANSFORMER An autotransformer (sometimes called autostep down transformer) is an electrical transformer with only one winding. The "auto" (Greek for "self") prefix refers to the single coil acting on itself and not to any kind of automatic mechanism. In an autotransformer portions of the same winding act as both the primary and secondary transformer. The winding has at least three taps where electrical connections are made. Autotransformers have the advantages of often being smaller, lighter, and cheaper than typical dual-winding transformers, but autotransformers havethedisadvantageof not providing electrical isolation. WORKING The primary voltage is applied across two of the terminals, and the secondary voltage taken from two terminals, almost always having one terminal in common with the primary voltage. The primary and secondary circuits therefore have a number of windings turns in common. Since the volts-per-turn is the same in both windings, each develops a voltage in proportion to its number of turns. In an autotransformer part of the current flows directly from the input to the output, and only part is transferred inductively, allowing a smaller, lighter, cheaper core to be used as well as requiring only a single winding. One end of the winding is usually connected in common to both the voltage source and the electrical load. The other end of the sourceand load are connected to taps along the winding. Different taps on the winding correspond to different voltages, measured from the common end. In a step-down transformer the source is usually connected across the entire winding while the load is connected by a tap across only a portion of the winding. In a step up transformer, conversely, the load is attached across the full winding while the source is connected to a tap across a portion of the winding.
  • 39. 39 POWER TRANSFORMER: The use of power transformer in a switchyard is to change the voltage level. At the sending and usually step up transformers are used to evacuate power at transmission voltage level. On the other hand at the receiving end step down transformers are installed to match the voltage to sub transmission or distribution level. In many switchyards autotransformers are used widely for interconnecting two switchyards with different voltage level (such as 132 and 220 KV) 1-Main tank 2-Radiator 3-Reservoir tank 4-Bushing 5-WTI & OTI Index 6-Breather 7-Buccholz relay CIRCUIT BREAKER A circuit breaker is an equipment that breaks a circuit either manually or automatically under all conditions at no load, full load or short circuit. Oil circuit breakers, vacuum circuit breakers and SF6 circuit breakers are a few types of circuit breakers.
  • 40. 40 ISOLATOR Isolators are switches which isolate the circuit at times and thus serve the purposeof protection during off load operation. CURRENT TRANSFORMER These transformers used serve the purpose of protection and metering. Generally the same transformer can be used as a current or potential transformer depending on the type of connection with the main circuit that is series or parallel respectively. In electrical system it is necessary to a) Read current and power factor b) Meter power consumption. c) Detect abnormalities and feed impulse to protective devices. POTENTIAL TRANSFORMER In any electrical power system it is necessary to a) Monitor voltage and power factor, b) Meter power consumption, c) Feed power to control and indication circuit and d) Detect abnormalities
  • 41. 41 (i.e. under/over voltage, direction of power flow etc) and feed impulse to protective device/alarm circuit. Standard relay and metering equipments does not permit them to be connected directly to the high voltage system.Potential transformers therefore play a key role by performing the following functions. a) Electrically isolating the instruments and relays fromHV side. b) By transferring voltage from higher values to proportional standardized lower values. CONDUCTORS Steel cored Aluminium (A.C.S.R) Aluminium has low tensile strength, as a result produce greater sag which prohibits their use for longer spans and makes them unsuitable for long distance transmissions. So in order to increase the tensile strength of the aluminium conductor, it is used with a core of galvanized steel wires. The combinational conductor thus obtained is called as A.C.S.R. (Aluminium Conductor Steel Reinforced)
  • 42. 42 The above figure shows, one steel cored conductor wire surrounded by 18 wires of aluminium. The aluminium carries bulk of current while the steel core takes a greater percentage of mechanical stress.  Produces smalllag and therefore can be used for longer spans.  A.C.S.R. Conductor gets deteriorated in service due to atmospheric corrosion. Cadmium copper Sometimes copper alloyed with cadmium is used. When 1 or 2 percentage of cadmium is added to copper it increases the tensile strength by about 40 percentages but reduces the conductivity only by 17 percentages. Cadmium copper is expensive than copper.  Economical for a line with long spans and small crosssection.
  • 43. 43 Insulator The live equipments are mounted over the steel structures or suspended from gantries with sufficient insulation in between them. In outdoor use electrical porcelain insulators are most widely used. Types of insulators (a)Pin type insulators. (b)Suspension type insulators. (c)Strain typeinsulators. (d)Shackleinsulators. (a)Pin type insulators A pin type insulator is designed to be mounted on a pin, which in turn is installed on cross-armof thepole. The insulator on the pin and electrical conductor is placed in the grooveat the top of the insulator and soft aluminium binding wire according to the material of the conductor.  Pin type insulators made of glass aregenerally used for low voltages.  Pin type insulators made of porcelain can be used up to 90kV but are rarely used on lines above60kV Suspension type insulators  In a pin type insulator its cost is increased rapidly as the working voltageis increased. Therefore pin type insulator is not economical beyond 33kV. So it is as usualpractice to use suspension typeinsulators for voltagehigher than 33kV.  A pin type insulator sits on top of the cross arm, whereas a suspension insulator hangs fromthe cross arm. The line conductor is attached to its
  • 44. 44 lower end. Few advantages of suspension typeinsulators over Pin type insulators are:  Usually cheaper in cost for operating voltage above 50kV.  Flexibility is increased with suspension insulators.  If line insulation needs to be increased, the additional insulators can be easily added to the string. In casethere is damage in any insulator, the damaged insulator can be easily replaced.
  • 45. 45 Bushing A bushing is a hollow insulating liner through which a conductor maypass. Bushings appear on switchgear, transformers, circuitbreakers and other high voltage equipment .The bushing is a hollow insulator, allowing a conductor to pass along its center and connect at both ends to other equipment. Bushings are often made of wet-process fired porcelain, and may be coated with semiconducting gglaze to assistin equalizing the electrical stress along the length of the bushing. The inside of the bushing may contain paper insulation and the bushing is often filled with oil to provideadditional insulation. Bushings for medium-voltage and low-voltageapparatus may be made of resins reinforced with paper. The useof polymer bushings for high voltage applications is becoming more common.
  • 46. 46 Capacitor voltage transformer A capacitor voltagetransformer (CVT or CCVT),is a transformer used in power systems to step down extra high voltage signals and provide a low voltage signal, for metering or operating aprotective relay. CVTs in combinationwith wave traps are used for filtering high-frequency communication signals from power frequency. WAVE TRAP Wave Traps areused at sub-stations using Power Line Carrier Communication (PLCC). PLCCis used to transmitcommunication and control information at a high frequency over the power lines. This reduces need for a separate infra for communication between sub-stations. The Wave Traps extract the high frequency information fromthe power lines and route it to the telecomm panels. They also block any surges frompassing through. Wave Traps aresimply resonantcircuits that producea high impedance against PLCC carrier frequencies (24kHz - 500kHz) whileallowing power frequency (50Hz - 60Hz).
  • 47. 47 Pebbles flat flooring at substation Two terms defined regarding floor of earthing system  Touch potential(potb/w hand and structurals (gnd) when a person is touching a grounded body like structure in switchyard.  Steppotential(potdiff b/w the feet of a person walking in the switchyard) now to minimize these potentials we put pebbles in place of flat flooring.  To reduce the magnatic field in between ground and conductor.  To reduce the growth of gress.  To aviod entry of animals like Rats, snakes etc  To reduce water storagein the yard in the rainy season. Lighting Arrestor Lightning arresters areprotective devices for limiting surgevoltages due to lightning strikes or equipment faults or other events, to prevent damage to equipment and disruption of service. Also called surge arresters. Lightning arresters areinstalled on many different pieces of equipment such as power poles and towers, power transformers,circuitbreakers, bus structures, and steel superstructures in substations
  • 48. 48 Substation Batteries The heart of a substation is the battery bank. If this were to fail, an electric utility could expose all feeders associated with the station to a condition where they could not ever trip in a fault. Not only that, but any backup devices, such as the main breaker on the low-voltage side or the high-voltage side protection of the power transformer, would all be inoperative, leaving the transmission grid protection as the only possiblebackup. In many cases, however, the transmission grid cannot perform this function because a fault on the low-voltage side of a Delta Wye transformer, especially a phase-to-ground fault, will convert to a phase-to-phase fault on the high side. This would be particularly true if the fault was out a few miles from the station. This could then cause such catastrophic consequences as burning wire down across town and eventually destroying the substation transformer. After the smoke clears, much of the substation could be heavily damaged and the power transformer could be in flames. This is not to mention the hazard it would cause to the public.
  • 49. 49 TRANSMISSION SYSTEM Charged with the responsibilities of providing electricity, the vital input for industrial growth inthe resource-rich Damodar Valley region, DVC over the last 60 years has developed a big androbust transmission network consisting of 132 KV and 220 KV grids. DVC grids operates inunison with the eastern regional grid through 132 KV and 220 KV tie lines. All the power stationsand substations of DVC are connected with the DVC grids. DVC power consumers are providedsupply at 25 KV, 33 KV, 132 KV and 220 KV pressure. DVC Transmission Lines in service at a glance Interconnecting Tie Lines with DVC Network *Out of service. DVC Substations in service (Nos.) at a glance
  • 50. 50 Transmission & Distribution Projects New Projects under construction New Projects being taken up for construction
  • 54. 54 TRAINING REPORT FOR PROGRAMME NO. 4 – TSC TRANSMISSION SYSTEM CONSTRUCTION 17/07/2015 TO 20/07/1015 Damodar Valley Corporation
  • 55. 55 PROCEDURE OF TSC PRELIMINARY WORKS  Selection of Route  ReconnaissanceSurvey  Preliminary Survey  Approvals & Clearances for the Line Route CONSTRUCTION ACTIVITIES  Detailed Survey & Plotting of Profile  Tower Spotting & Tower Schedule  Check Survey & Location Marking  Stub Setting  Erection of Towers & Fixing of Accessories  Stringing of Conductors & Earth Wire  Earthing  Protection of Tower Footings  Clearing of Right of Way  Final Checking  Testing & Commissioning
  • 56. 56 TRANSMISSION ROUTE The route of a transmission line is decided from the following main considerations:  Shortestlength, hence least capital cost.  Route near roads for easy approach & accessibility during construction and maintenance.  Requirement of future loads near the proposed routeso that the line can easily be connected to the loads and optimal use of line.  Required separation distance fromparallel communication lines (P&T, Railways, etc.) for meeting the conditions of induced voltage for obtaining PTCC approval.  Avoiding of forestareas as well as wild life sanctuaries as far as possible.  Cost of securing and clearing right of way (ROW).  Maintaining statutory distances fromAirports / Helipads AVOID  Tough inaccessibleareas  Towns and villages, leaving sufficient margin for their growth  Swamps and shallow lands subjectto flood, marshy areas, low lying lands, river beds and land slide zones, etc. involving risk of stability for foundations  Rifle shooting areas and other protected areas such as army / defence installations and ammunition depots.  Buildings / Storage areas for explosives or inflammable materials, bulk oil storagetanks, oil or gas pipelines etc.
  • 57. 57 SUREVY OF LINES  METHOD : Theodolite , Total Station ,SatellitewithTotal Station  PLOTTING OF ROUTE PROFILE: Manual , PLSCAD APPROVAL REQUIREMENT  Forestclearance  Railway clearance  Clearance frommining authority  NH Clearance  Power and Telecommunication Coordination Committee (PTCC) clearance  CEA Clearance MINIMUM CLEARANCE
  • 58. 58 MINIMUM CLEARANCE : IS: 5613 (Part II/Sec-1)-1976 MINIMUM CLEARANCE : AS PER - IS :5613 (PART II/SEC I) - 1976
  • 59. 59 APPLICATION OF SAG TEMPLATE ON PROFILE
  • 60. 60 TOWER USED FOR TRANSMISSION LINE  Lattice type tower  A2, S15, B30, C60, D90 –132&220KV line  A2, B15, C30, D60 – 400KV line  Wide base tower  Narrow basetower  Multi circuit Tower  Special Crossing Tower TOWER CONSTRUCTION : EXCAVATION MARKING CHART
  • 61. 61  The excavation pit marking drawing indicates the distance of centres, sides and corners of the pits with reference to the centre point of the tower  From the dimensions shown in the drawing, the triangle ABC is first marked with the help of a measuring tape. The distance CD, equal to F (width of the pit) is marked on the ground. The triangle AB'C is then marked by shifting the point B and without changing the points A and C. The distance CD', equal to F, is then marked. The sides DE and D'E, both equal to F, are then marked. The procedure is repeated for marking the other three pits.  The dimension G shown in the drawing is the centre to centre distance between stubs of the tower at their lowest point. The dimension M is the diagonal distance between the ends of the stubs of the tower. The excavation pit marking drawing is prepared on the basis of these dimensions. TOWER FOUNDATION : PYRAMID CHIMNEY TYPE
  • 62. 62
  • 63. 63
  • 64. 64 FOLLOW THE STEPS TO ERECT THE TOWER  Erection of Tower body - first story  Erection of Tower body - second story upwards  Erection of cross arms Conclusion: Pulley and guy ropes are the minimum accessories to erect a tower.
  • 65. 65 STRINGING OF CONDUCTORS AND EARTHWIRE HOSTING OF INSULATOR STRING  Single / Doublesuspension insulator strings areused on suspension towers and single / double tension insulator strings are used on angle and dead end towers. This is indicated in the tower schedule.  Before hoisting, all insulators are cleaned in a manner that will not spoil, injureor scratch the surfaceof the insulator, but in no caseshall any oil be used for the purpose.  Disc insulators shall be examined for any cracks / chipping, etc. Disc insulators having any hair cracks or chipping or defective glazing or any other defect shall not be used . NO. OF DISC / E&M STRENGTH (KN) 400kv 220kv 132kv single suspension –I string 1 X 23 120 KN 1 X 13 70 KN 1 X 9 45 KN Double suspension-I String 2 X 24 120 KN 2 X 13 70KN 2 X 9 45 KN Single suspension- v string 2 X 23 120 KN N.A N.A Double suspension v string 2 X 2 X 23 120KN N.A N.A Single tension string 1 X 23 120 KN 1 X 14 120 KN 1 X 10 120KN Double tension string 2 X 23 160KN 2 X 14 120KN 2 X 10 120KN Single suspension pilot string 2 X 23 120KN 1 X 13 70KN 1 X 9 45KN
  • 66. 66
  • 67. 67
  • 68. 68
  • 69. 69 Substation construction Selectionofsite  As near the load centre as possible.  As far as possiblerectangular or squarein shapefor ease of proper orientation of bus – bars and feeders.  Far away from obstructions, to permit easy and safe approach / termination of high voltage overhead transmission lines.  Free frommaster plans / layouts or future development activities to have free line corridors for the presentand in future.  Easily accessibleto the public road to facilitate transportof material  As far as possiblenear a town and away frommunicipal dumping grounds, burial grounds, tanneries and other obnoxious areas.  Preferably fairly leveled ground. This facilitates reduction in leveling expenditure.  Abovehighest flood level (HFL) so that there is no water logging.  Sufficiently away fromareas wherepolice and military rifle practices are held.
  • 70. 70 Main Equipments of Sub-station:  Transformer  LA  CVT/PT  Isolator  CT  Circuit Breaker  Control & Relay Panel Sub station layout
  • 71. 71 Note : These layouts were essentially used in 220kv/ 132kv/ 33kv Dhanbad sub station ( TSE VT – 09-01-2014 AT D.S.S , DVC )
  • 72. 72 SECTION 132KV & 220KV TRANSFORMER BAY,DHANBAD S/S
  • 73. 73 BAY LAYOUTS OF 132KV AND 220 KV , DHANBAD S/S
  • 74. 74 EARTHING OF SUB STATION-
  • 75. 75 TRAINING REPORT FOR PROGRAMME NO. 5 – CTC CENTRAL TESTING CENTER CRITL MAITHON Damodar Valley Corporation
  • 76. 76 Central Testing Center at Maithon has two distinct divisions namely 1.Central Relay and Instrument Testing Laboratory (CRITL) and 2.Central Relay and Instrument Testing Mobile (CRITM). The above two divisionstake care of commissioning and proper maintenanceof the entire protection and metering system, fault analysisas well as periodicaltesting of all types of relays and meters includingtariff meters of the entire DVC network includingpower houses.
  • 77. 77 TRANSFORMER OIL Transformer oil or insulating oil is usually a highly refined mineral oil that is stable at high temperatures and has excellent electrical insulating properties. It is used in oil filled transformers, some types of high voltage capacitors, fluorescent lamp ballasts, and some types of high voltage switches and circuit breakers .Its functions are to insulate, suppress corona and arcing, and to serveas a coolant. On-site testing Some transformer oil tests can be carried out in the field, using portable test apparatus. Other tests, such as dissolved gas, normally require a sample to be sent to a laboratory. Electronic on-line dissolved gas detectors can be connected to important or distressed transformers to continually monitor gas generation trends.To determine the insulating property of the dielectric oil, an oil sample is taken from the device under test, and its breakdown voltage is measured on-site according the following test sequence:  In the vessel, two standard-compliant test electrodes with a typical clearance of 2.5 mm are surrounded by the insulating oil.  During the test, a test voltage is applied to the electrodes. The test voltage is continuously increased up to the breakdown voltage with a constant slew rate of e.g. 2 kV/s.  Breakdown occurs in an electric arc, leading to a collapse of the test voltage.  Immediately after ignition of the arc, the test voltage is switched off automatically.  Ultra fast switch off is crucial, as the energy that is brought into the oil and is burning it during the breakdown, must be limited to keep the additional pollution by carbonisation as low as possible.  The root mean square value of the test voltage is measured at the very instant of the breakdown andis reported as the breakdown voltage.  After the test is completed, the insulating oil is stirred automatically and the test sequence isperformed repeatedly.  The resulting breakdown voltage is calculated as mean value of the individual measurements.
  • 78. 78 DGA or Dissolved Gas Analysis of Transformer Oil Whenever electrical power transformer goes under abnormal thermal and electrical stresses, certain gases are produced due to decomposition of transformer insulating oil, when the fault is major, the production of decomposed gases are more and they get collected in Buchholz relay. But when abnormal thermal and electrical stresses are not significantly high the gasses due to decomposition of transformer insulating oil will get enough time to dissolve in the oil. Hence by only monitoring the Buchholz relay it is not possible to predict the condition of the total internal healthiness of electrical power transformer. That is why it becomes necessary to analyse the quantity of different gasses dissolved in transformer oil in service. From dissolved gas analysis of transformer Oil or DGA of transformer oil, one can predict the actual condition of internal health of a transformer. It is preferable to conduct the DGA test of transformer oil in routine manner to get prior information about the trend of deterioration of transformer health and life. Actually in dissolved gas analysis of transformer oil or DGA of transformer oil test, the gases in oil are extracted from oil and analyze the quantity of gasses in a specific amount of oil. By observing percentages of different gasses present in the oil, one can predict the internal condition of transformer. Generally the gasses found in the oil in service are hydrogen (H2), methane (CH4), Ethane (C2H6), ethylene (C2H4), acetylene (C2H3), carbon monoxide (CO), carbon dioxide (CO2), nitrogen(N2) and oxygen(O2). Generally it is found that hydrogen and methane are produced in large quantity if internal temperature of power transformer rises up to 150°C to 300°C due to abnormal thermal stresses. If temperature goes above 300°C, ethylene (C2H4) are produced in large quantity. At the
  • 79. 79 temperature is higher than 700°C large amount of hydrogen (H2) and ethylene (C2H4) are produced. DGA TESTING OF TRNSFORMERS OF DVC DGA 3 STEPS  OIL SAMPLE EXTRACTION as per standard IS 9434: 1992 and ASTM 3613.  EXTRACTION OF THE GASES (fully computerized ALIGENT TECHNOLOGIES U.S.A made using the Agilent 7697A Headspace Sampler.)  GAS SEPERATION AND MEASURMENT (GAS CHROMATOGRAPHY) ALIGENT TECHNOLOGIES
  • 80. 80 MINIMUM DETECTION LIMIT ADVANTAGES THAT DGA CAN PROVIDE  Advance warning of developing faults  Determining warning of the improper use of units  Statuschecks on new and repaired units  Convenient scheduling of repairs  Monitoring of units under overload GAS DETECTION LIMIT in ppm HYDROGENH2 0.60 OXYGEN02 11.0 NITROGENN2 11.2 MEATHANE CH4 0.50 CARBON MONO OXIDE CO 0.10 CARBON DIOXIDECO2 0.10 ACETYLENE C2H2 0.05 ETHYLENE C2H4 0.04 ETHANE C2H6 0.04 PROPANEC3H8 0.20
  • 81. 81 Losses of Transformers The transformers aremade of 2 types of materials: Iron and Copper. The core of a transformer is made of Iron whereas thewinding which is wrapped over the iron core is made up of Copper. Correspondingly there are 2 types of losses: Iron Loss and Copper Loss. Iron and Copper losses are measuredby open circuit andshort circuit tests. TESTS OF DISTRIBUTION TRANSFORMERS Two tests are conducted for testing transformers. These tests are known by different names as describedinthe table below.
  • 82. 82 Protective Relay A relay is automatic device which senses an abnormal condition of electrical circuit and closes its contacts. These contacts in turns close and complete the circuit breaker trip coil circuit hence make the circuit breaker tripped for disconnecting the faulty portion of the electrical circuit from rest of the healthy circuit. Types of Relays Types of protection relays are mainly based on their characteristic, logic, on actuating parameter and operation mechanism. Based on operation mechanism protection relay can be categorized as electromagnetic relay, static relay and mechanical relay. Actually relay is nothing but a combination of one or more open or closed contacts. These all or some specific contacts the relay change their state when actuating parameters are applied to the relay. That means open contacts become closed and closed contacts become open. In electromagnetic relay these closing and opening of relay contacts are done by electromagnetic action of a solenoid. In mechanical relay these closing and opening of relay contacts are done by mechanical displacement of different gear level system. In static relay it is mainly done by semiconductor switches like thyristor. In digital relay on and off state can be referred as 1 and 0 state. Basedon Characteristic the protectionrelay canbe categorizedas-  Definite time relays  Inversetime relays with definite minimum time(IDMT)  Instantaneous relays.  IDMTwith inst.  Stepped characteristic.  Programmed switches.  Voltage restraint over current relay.
  • 83. 83 Basedon of logic the protectionrelay canbe categorizedas- Differential.  Unbalance.  Neutral displacement.  Directional.  Restricted earth fault.  Over fluxing.  Distance schemes.  Bus bar protection.  Reversepower relays.  Loss of excitation.  Negative phasesequence relays etc. Basedon actuating parameter the protectionrelay canbe categorizedas-  Currentrelays.  Voltage relays.  Frequency relays.  Power relays etc. Basedon applicationthe protectionrelay canbe categorizedas-  Primary relay.  Backup relay. Primary relay or primary protection relay is the first line of power system protection whereas backup relay is operated only when primary relay fails to be operated during fault. Hence backup relay is slower in action than primary relay. Any relay may fail to be operated due to any of the following reasons,  The protective relay itself is defective.  DC Trip voltage supply to the relay is unavailable.  Trip lead from relay panel to circuit breaker is disconnected.  Trip coil in the circuit breaker is disconnected or defective.  Currentor voltage signals fromCT or PT respectively is unavailable. As because backup relay operates only when primary relay fails, backup protection relay should not have anything common with primary protection relay.
  • 84. 84 Some examples of Mechanical Relay are-  Thermal  OT trip (Oil Temperature Trip)  WT trip (Winding Temperature Trip)  Bearing temp trip etc.  Float type  Buchholz  OSR  PRV  Water level Controls etc.  Pressureswitches.  Mechanical interlocks.  Pole discrepancy relay.
  • 85. 85 List Different Protective Relays are used for Different Power System Equipment Protection Now let’s have a look on which different protective relays are used in different power systemequipment protection schemes. Relays for Transmission& DistributionLines Protection Relays for Transformer Protection
  • 86. 86
  • 87. 87  No Buchholz relay for transformers below500 KVA capacity.  Transformers upto 1500 KVA shall have only Horn gap protection.  Transformers above 1500 KVA and upto 8000 KVA of 33/11KV ratio shall have one group control breaker on HV side and individual LV breakers if there is more than one transformer.  Transformers above 8000 KVA shall have individual HV and LV circuit breakers.  The relays indicate above shall be providedon HV and LV.
  • 88. 88  LAs to be provided on HV & LV for transformers of all capacities and voltage class.  OLTC out of step protection is to be provided where master follower scheme is in operation.  Fans failure and pumps failure alarms tobe connected.  Alarms for O.T., W.T., Buchholz (Maintank & OLTC) should be connected. TAP CHANGER A tap changer is a connection point selection mechanism along a power transformer winding that allows a variable number of turns to be selected in discrete steps. A transformer with a variable turns ratio is produced, enabling stepped voltage regulation of the output. The tap selection may be made via an automatic or manual tap changer mechanism. TAP CHANGING Off-circuit designs (NLTC or DETC) Also called No-Load Tap Changer (NLTC), off-circuit tap changer, or De- Energized Tap Changer (DETC). In low power, low voltage transformers, the tap point can take the form of a connection terminal, requiring a power lead to be disconnected by hand and connected to the new terminal. Alternatively, the process may be assisted by means of a rotary or slider switch. Since the different tap points are at different voltages, the two connections can not be made simultaneously, as this would short-circuit a number of turns in the winding and produce excessive circulating current. Consequently, the power to the device must be interrupted during the switchover event. Off-circuit or de- energized tap changing (DETC) is sometimes employed in high voltage transformer designs, although for regular use, it is only applicable to installations
  • 89. 89 in which the loss of supply can be tolerated. In power distribution networks, transformers commonly include an off-circuit tap changer on the primary winding to accommodate system variations within a narrow band around the nominal rating. The tap changer will often be set just once, at the time of installation, although it may be changed later during a scheduled outage to accommodate a long-term change in the system voltage profile. On-load designs (OLTC) Also called on circuit tap changer or On Load Tap Changer (OLTC) For many power transformer applications, a supply interruption during a tap change is unacceptable, and the transformer is often fitted with a more expensive and complex on-load tap-changing (OLTC, sometimes LTC) mechanism. On- load tap changers may be generally classified as either mechanical, electronically assisted, or fully electronic.