THE INDUS HOSPITAL Construction Project Technical Proposal
1.
1
THE INDUS HOSPITAL
Construction of Grey Structure (Core & Shell)
Extension Phase 1
Technical Proposal Package
2.
2
CONTENT
SHEET NO DESCRIPTION
01 ~ 04 PROJECT METHODOLOGY
05 ~ 08 PROJECT SCHEDULE
09 DEPLOYMENT SCHEDULE OF STAFF
10 ~ 11 DEPLOYMENT SCHEDULE OF EQUIPMENT
12 PROJECT ORGANOGRAM
13 TOWER CRANES WORKING ENVELOP
14 TOWER CRANES IN ELEVATION
15 SITE ESTABLISHMENT PLAN
16 PROPRIETARY RMD SYSTEM FORMWORK
3. 3
PROJECT METHODOLOGY
SITE ESTABLISHMENT:
SITE OFFICE, STORES, SITE WORKSHOPS:
It is proposed to use three 20ft and two 40ft office containers to accommodate the Project Manager, Construction Managers, Site Engineers, Accounts and Other Officers. Two 40ft container will be
used as tools and general items store as well as store office. Bulk items, scaffolding, timber, steel forms will be stored in an adjacent Open Store Area levelled and prepared for the purpose.
Site workshop will comprise of scaffold frame and corrugated G.I. sheeting sheds with adjacent prepared open work areas.
ELECTRIC POWER:
Diesel generators, along with the requisite mains switches, cabling and distribution boards will be installed to supply electric power.
WATER:
Potable water acquired in 5000 gallon tankers, and stored in PVC or steel overhead tanks in the camp areas. The water will be distributed through PVC piping to toilets, showers and kitchens. The water
will be filtered for drinking purposes.
Also Water for earth fill works and concrete works will be obtained, in 5000 gallon tankers through water purchase agreements with the existing suppliers.
MANAGEMENT PLAN
SITE ORGANIZATION CHART:
Please refer to attached Site Organization Chart.
COMMUNICATION & COORDINATION PLAN:
Site Coordinating Person:
Project manager will be the key coordinating person for the project.
4. 4
Highest Coordinating Person:
For owner representative, contact reference will be the Project Director (Mr. Hamid Naqvi). Project Manager reports directly to the Project Director.
In-house Communication:
Telephone/ Internet facilities will be installed at the Site and will be used for voice / data communications..
INVOICES, SHOP DRAWINGS & SUBMITTALS:
Invoice Raising:
Quantity Surveyor will work on invoices and it will be raised by Project Manager to owner representative.
Drawings & Documents / As Built Drawings:
Drawings & Documents will be received at site by the Planning Engineer from the owner representative in accordance with a mutually agreed procedure. All data received will be distributed,
filed, and periodically updated by the draftsman under the supervision of the Planning Engineer. "As built" drawings will be prepared by Draftsman working under Planning Engineer, who will
report to Project Manager.
Submittals:
All submittals will be raised by Project Manager through the Planning Engineer. Planning Engineer will be responsible to handle the submittals.
TRANSPORT:
Well maintained vehicles will be used for site supervision, staff transport, and materials procurement duties. It is proposed to use owned / hired vehicles. All vehicles shall be driven only by
licensed and trained drivers.
CONSTRUCTION/SITE HEALTH & SAFETY:
There will be a permanent health & safety supervisor on site. Safety facilities on site will include:
1. Personal protective equipment.
2. Firefighting equipment.
3. First aid facilities.
4. Arrangements for injury and other treatment with Indus Hospital.
5. Housekeeping facilities including waste drums, collection, and disposals in a safe manner.
6. Safe drinking water and sanitation facilities.
CONSTRUCTION QUALITY CONTROL:
There will be QA / QC supervisors to implement the Project Quality Control Plan. They will work under Project Manager. The project specific quality plan will be prepared prior to start of work
at site. As a sample please refer to attach Construction Quality Control Plan.
5. 5
SECURITY:
Security for the work sites, site facilities area, and staff / labor camps will be provided through day and night watchmen, entry posts and adequate area lighting for night time use.
WORK METHODOLOGY:
Survey Control and Set-out:
It is proposed to use four (4) survey teams, comprising one qualified senior surveyor and two survey assistants each, for the project works. The survey teams will establish and maintain survey
monuments, temporary markers, property lines, reference base lines, and perform all survey work necessary to achieve the design formations, elevations and grades.
Plant Maintenance:
A workshop will be established for the purposes of servicing and routine maintenance of plant only. No major repairs shall be carried out on site. The workshop will be housed in a shed
structure within the camp premises and equipped for lubrication, filter changes, tyre filling, and minor repairs.
Diesel for the construction plant will be stored on site in a 15,00liters steel tank installed in accordance with the safety requirements for fuel storage.
Material Handling & Lifting:
1) Tower Crane It is proposed to use three (3) static tower cranes The HUH is 35 m, jib length 50m, and lifting capacity is 10 ton with 2 ton Tip load whose seems to be adequate for
Project.
2) Construction Passenger Hoist single cabin with 2 ton capacity – 2 Nos.
3) Construction Cargo Hoist single cabin with 2 ton capacity – 2 Nos.
Concrete Pumps:
Two stationary pumps 60 Cu-m/Hr are proposed for concrete placement in the floor slabs. The 125mm diameter delivery line shall be attached to the building structure (columns or lift core)
through steel profiles and expansion bolts. It is also proposed to use a mobile pump during ground level and low level concreting.
System Formwork:
The proposed system formwork will comprise of:
1) Panel forms for internal walls and columns.
2) Panel forms for lift cores and stair walls.
3) Slab form systems for floor slabs, drop panels & beams.
4) Site fabricated forms for staircases and special shapes.
It is proposed to use the RMD Kwikform system we already own and which has been successfully used on several high profile projects. All formwork and accessories shall be designed for the
imposed loads of the concrete and for specified off-form finishes.
Formwork for Slab, Drop Panels and Beams:
We propose to have 80,000 Sft of proprietary RMD system formwork and 40,000 Sft of conventional formwork at site for Slab, Drop Panels & Beams. Form face would be 18mm thick quality
plywood.
6. 6
Formwork for Columns and Walls:
We propose to have 45 sets of Columns Formwork.
Other Equipment:
Other equipment for building construction shall include excavation and backfill compaction machinery, material handling equipment, power generating sets , dewatering equipment, re-bar
fabrication equipment and conventional scaffolding for access / miscellanies uses..
Manpower Deployment / Supervision:
Efficient and productive deployment of labor and supervisory staff on building construction is achieved by:
1. Speedy transport to floor levels of personnel, tools, and materials.
2. An efficient communication system between ground facilities such as stores, laboratory, batch plants, workshops etc.
3. Easy access to facilities such as toilets and drinking water.
For communication between the works crews on floor levels and the ground facilities hand-held radio sets shall be used.
The above measures shall ensure quick deployment of work crews to floor levels, timely availability of tools and materials, and a minimum of non-productive labor time due to toilet breaks and
water breaks.
Plant & Equipment Proposed:
Please refer to attach Equipment Deployment Plan.
Material Procurement:
Procurement of all permanent material will be the responsibility of the site management team. They will be responsible for submittals, approvals, ordering, delivery and warehousing.
Concrete Batch Plant:
Concrete will be delivered to the site from selected approved pre-mix concrete suppliers
7. Activity Name Original
Duration
Start Finish
Total 720d 02-Nov-2015 21-Oct-2017
Construction of Gery Structure (Core 720d 02-Nov-2015 21-Oct-2017
Mobilazation 720d 02-Nov-2015 21-Oct-2017
Start Of Work 0d 02-Nov-2015
Mobilazation and Site Set-Up /Approval of Mix Des 45d 02-Nov-2015 16-Dec-2015
Sub Structure Works 248d 07-Nov-2015 11-Jul-2016
Excavation Work 50d 07-Nov-2015 26-Dec-2015
Pile Bracking 30d 12-Nov-2015 11-Dec-2015
Pcc for Raft 45d 22-Nov-2015 05-Jan-2016
Pile Cap Reinf 45d 02-Dec-2015 15-Jan-2016
Pouring 45d 02-Dec-2015 15-Jan-2016
Retaining Wall & Columns 100d 05-Dec-2015 13-Mar-2016
Under Ground Water Tank 50d 24-Nov-2015 12-Jan-2016
Ground Floor Slab 160d 03-Feb-2016 11-Jul-2016
Ramp Slab from B-1 to Ground 25d 17-Jun-2016 11-Jul-2016
Water Proofing 90d 03-Feb-2016 02-May-2016
Package-A (Basment, Hospiatl Building & He 488d 23-May-2016 22-Sep-2017
F-1 & Meeznine 125d 23-May-2016 24-Sep-2016
Floor Column & Walls 40d 23-May-2016 01-Jul-2016
Floor Slabe 100d 17-Jun-2016 24-Sep-2016
F-2 100d 01-Aug-2016 08-Nov-2016
Floor Column & Walls 35d 01-Aug-2016 05-Sep-2016
Floor Slabe 80d 21-Aug-2016 08-Nov-2016
F-3 95d 10-Oct-2016 12-Jan-2017
Floor Column & Walls 30d 10-Oct-2016 08-Nov-2016
Floor Slabe 80d 25-Oct-2016 12-Jan-2017
F-4 95d 24-Nov-2016 26-Feb-2017
Floor Column & Walls 30d 24-Nov-2016 24-Dec-2016
Floor Slabe 80d 09-Dec-2016 26-Feb-2017
F-5 85d 08-Jan-2017 02-Apr-2017
Floor Column & Walls 30d 08-Jan-2017 07-Feb-2017
Floor Slabe 70d 23-Jan-2017 02-Apr-2017
F-6 70d 15-Feb-2017 25-Apr-2017
Floor Column & Walls 25d 15-Feb-2017 12-Mar-2017
Floor Slabe 60d 25-Feb-2017 25-Apr-2017
F-7 70d 12-Mar-2017 20-May-2017
Floor Column & Walls 25d 12-Mar-2017 06-Apr-2017
Floor Slabe 60d 22-Mar-2017 20-May-2017
F-8 70d 06-Apr-2017 14-Jun-2017
Floor Column & Walls 25d 06-Apr-2017 01-May-2017
Floor Slabe 60d 16-Apr-2017 14-Jun-2017
F-9 70d 01-May-2017 09-Jul-2017
Floor Column & Walls 25d 01-May-2017 26-May-2017
Floor Slabe 60d 11-May-2017 09-Jul-2017
F-10 70d 26-May-2017 03-Aug-2017
Floor Column & Walls 25d 26-May-2017 20-Jun-2017
Floor Slabe 60d 05-Jun-2017 03-Aug-2017
Roof 95d 20-Jun-2017 22-Sep-2017
Floor Column & Walls 25d 20-Jun-2017 15-Jul-2017
Floor Slabe 60d 30-Jun-2017 28-Aug-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
-2015 21-Oct-2017
-2015 21-Oct-2017
-2015 21-Oct-2017
Start Of Work
v-2015 11-Jul-2016
23-May-2016 22-Sep-2017
23-May-2016 24-Sep-2016
01-Aug-2016 08-Nov-2016
10-Oct-2016 12-Jan-2017
24-Nov-2016 26-Feb-2017
08-Jan-2017 02-Apr-2017
15-Feb-2017 25-Apr-2017
12-Mar-2017 20-May-2017
06-Apr-2017 14-Jun-2017
01-May-2017 09-Jul-2017
26-May-2017 03-Aug-2017
20-Jun-2017 22-Sep-2017
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...
8. Activity Name Original
Duration
Start Finish
Upper Roof Slab Works 40d 14-Aug-2017 22-Sep-2017
Package-B ( ECOL Building) 338d 12-Jun-2016 15-May-2017
F-1 100d 12-Jun-2016 19-Sep-2016
Floor Column & Walls 30d 12-Jun-2016 11-Jul-2016
Floor Slabe 70d 27-Jun-2016 04-Sep-2016
Ramp GF to F-1 15d 05-Sep-2016 19-Sep-2016
F-2 85d 22-Jul-2016 14-Oct-2016
Floor Column & Walls 25d 22-Jul-2016 16-Aug-2016
Floor Slabe 60d 01-Aug-2016 29-Sep-2016
Ramp F-1 ~ F-2 15d 30-Sep-2016 14-Oct-2016
F-3 85d 16-Aug-2016 08-Nov-2016
Floor Column & Walls 25d 16-Aug-2016 10-Sep-2016
Floor Slabe 60d 26-Aug-2016 24-Oct-2016
Ramp F-2 ~ F-3 15d 25-Oct-2016 08-Nov-2016
F-4 85d 10-Sep-2016 03-Dec-2016
Floor Column & Walls 25d 10-Sep-2016 05-Oct-2016
Floor Slabe 60d 20-Sep-2016 18-Nov-2016
Ramp F-3 ~ F-4 15d 19-Nov-2016 03-Dec-2016
F-5 85d 05-Oct-2016 28-Dec-2016
Floor Column & Walls 25d 05-Oct-2016 30-Oct-2016
Floor Slabe 60d 15-Oct-2016 13-Dec-2016
Ramp F-4 ~ F-5 15d 14-Dec-2016 28-Dec-2016
F-6 85d 28-Oct-2016 20-Jan-2017
Floor Column & Walls 25d 28-Oct-2016 22-Nov-2016
Floor Slabe 60d 07-Nov-2016 05-Jan-2017
Ramp Slab F-5 ~ F-6 15d 06-Jan-2017 20-Jan-2017
F-7 85d 22-Nov-2016 14-Feb-2017
Floor Column & Walls 25d 22-Nov-2016 17-Dec-2016
Floor Slabe 60d 02-Dec-2016 30-Jan-2017
Ramp Slab F-6 ~ F-7 15d 31-Jan-2017 14-Feb-2017
F-8 70d 17-Dec-2016 24-Feb-2017
Floor Column & Walls 25d 17-Dec-2016 11-Jan-2017
Floor Slabe 60d 27-Dec-2016 24-Feb-2017
F-9 70d 11-Jan-2017 21-Mar-2017
Floor Column & Walls 25d 11-Jan-2017 05-Feb-2017
Floor Slabe 60d 21-Jan-2017 21-Mar-2017
Roof 95d 10-Feb-2017 15-May-2017
Floor Column & Walls 25d 10-Feb-2017 07-Mar-2017
Floor Slabe 60d 20-Feb-2017 20-Apr-2017
Upper Roof Slab Works 40d 06-Apr-2017 15-May-2017
Finishing Work 557d 13-Apr-2016 21-Oct-2017
Block Work 530d 13-Apr-2016 24-Sep-2017
Basment ( Hospital & ECOL) 120d 13-Apr-2016 10-Aug-2016
F-1 (Hospital & ECOL) 50d 23-May-2016 11-Jul-2016
F-2 (Hospital & ECOL) 50d 02-Jul-2016 20-Aug-2016
F-3 (Hospital & ECOL) 50d 11-Aug-2016 29-Sep-2016
F-3 (Hospital & ECOL) 50d 20-Sep-2016 08-Nov-2016
F-4 (Hospital & ECOL) 50d 30-Oct-2016 18-Dec-2016
F-5 (Hospital & ECOL) 50d 09-Dec-2016 27-Jan-2017
F-6 (Hospital & ECOL) 50d 18-Jan-2017 08-Mar-2017
F-7 (Hospital & ECOL) 50d 27-Feb-2017 17-Apr-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
12-Jun-2016 15-May-2017
12-Jun-2016 19-Sep-2016
22-Jul-2016 14-Oct-2016
16-Aug-2016 08-Nov-2016
10-Sep-2016 03-Dec-2016
05-Oct-2016 28-Dec-2016
28-Oct-2016 20-Jan-2017
22-Nov-2016 14-Feb-2017
17-Dec-2016 24-Feb-2017
11-Jan-2017 21-Mar-2017
10-Feb-2017 15-May-2017
13-Apr-2016 21-Oct-2017
13-Apr-2016 24-Sep-2017
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...
9. Activity Name Original
Duration
Start Finish
F-8 (Hospital & ECOL) 50d 08-Apr-2017 27-May-2017
F-9 (Hospital & ECOL) 50d 18-May-2017 06-Jul-2017
F-10 (Hospital & ECOL Roof) 50d 27-Jun-2017 15-Aug-2017
F-11 (Hospital Roof ) 50d 06-Aug-2017 24-Sep-2017
Plaster Work 527d 13-May-2016 21-Oct-2017
Basment ( Hospital & ECOL) 130d 13-May-2016 19-Sep-2016
F-1 (Hospital & ECOL) 50d 22-Jun-2016 10-Aug-2016
F-2 (Hospital & ECOL) 50d 01-Aug-2016 19-Sep-2016
F-3 (Hospital & ECOL) 50d 10-Sep-2016 29-Oct-2016
F-3 (Hospital & ECOL) 50d 20-Oct-2016 08-Dec-2016
F-4 (Hospital & ECOL) 50d 29-Nov-2016 17-Jan-2017
F-5 (Hospital & ECOL) 50d 08-Jan-2017 26-Feb-2017
F-6 (Hospital & ECOL) 50d 17-Feb-2017 07-Apr-2017
F-7 (Hospital & ECOL) 50d 29-Mar-2017 17-May-2017
F-8 (Hospital & ECOL) 50d 08-May-2017 26-Jun-2017
F-9 (Hospital & ECOL) 50d 17-Jun-2017 05-Aug-2017
F-10 (Hospital & ECOL Roof) 70d 27-Jul-2017 04-Oct-2017
F-11 (Hospital Roof ) 47d 05-Sep-2017 21-Oct-2017
Project Complate 0d 21-Oct-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
13-May-2016 21-Oct-2017
Project Complat
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...