THE INDUS HOSPITAL
Construction of Grey Structure (Core & Shell)
Extension Phase 1
Technical Proposal Package
                                                
         
 
 
2 
 
CONTENT  
SHEET NO  DESCRIPTION
01 ~ 04  PROJECT METHODOLOGY 
05 ~ 08  PROJECT SCHEDULE  
09  DEPLOYMENT SCHEDULE OF STAFF  
10 ~ 11  DEPLOYMENT SCHEDULE OF EQUIPMENT 
12   PROJECT ORGANOGRAM  
13  TOWER CRANES WORKING ENVELOP 
14  TOWER CRANES IN ELEVATION 
15  SITE ESTABLISHMENT PLAN  
16  PROPRIETARY RMD SYSTEM FORMWORK 
3
PROJECT METHODOLOGY
SITE ESTABLISHMENT:
SITE OFFICE, STORES, SITE WORKSHOPS:
It is proposed to use three 20ft and two 40ft office containers to accommodate the Project Manager, Construction Managers, Site Engineers, Accounts and Other Officers. Two 40ft container will be
used as tools and general items store as well as store office. Bulk items, scaffolding, timber, steel forms will be stored in an adjacent Open Store Area levelled and prepared for the purpose.
Site workshop will comprise of scaffold frame and corrugated G.I. sheeting sheds with adjacent prepared open work areas.
ELECTRIC POWER:
Diesel generators, along with the requisite mains switches, cabling and distribution boards will be installed to supply electric power.
WATER:
Potable water acquired in 5000 gallon tankers, and stored in PVC or steel overhead tanks in the camp areas. The water will be distributed through PVC piping to toilets, showers and kitchens. The water
will be filtered for drinking purposes.
Also Water for earth fill works and concrete works will be obtained, in 5000 gallon tankers through water purchase agreements with the existing suppliers.
MANAGEMENT PLAN
SITE ORGANIZATION CHART:
Please refer to attached Site Organization Chart.
COMMUNICATION & COORDINATION PLAN:
Site Coordinating Person:
Project manager will be the key coordinating person for the project.
4
Highest Coordinating Person:
For owner representative, contact reference will be the Project Director (Mr. Hamid Naqvi). Project Manager reports directly to the Project Director.
In-house Communication:
Telephone/ Internet facilities will be installed at the Site and will be used for voice / data communications..
INVOICES, SHOP DRAWINGS & SUBMITTALS:
Invoice Raising:
Quantity Surveyor will work on invoices and it will be raised by Project Manager to owner representative.
Drawings & Documents / As Built Drawings:
Drawings & Documents will be received at site by the Planning Engineer from the owner representative in accordance with a mutually agreed procedure. All data received will be distributed,
filed, and periodically updated by the draftsman under the supervision of the Planning Engineer. "As built" drawings will be prepared by Draftsman working under Planning Engineer, who will
report to Project Manager.
Submittals:
All submittals will be raised by Project Manager through the Planning Engineer. Planning Engineer will be responsible to handle the submittals.
TRANSPORT:
Well maintained vehicles will be used for site supervision, staff transport, and materials procurement duties. It is proposed to use owned / hired vehicles. All vehicles shall be driven only by
licensed and trained drivers.
CONSTRUCTION/SITE HEALTH & SAFETY:
There will be a permanent health & safety supervisor on site. Safety facilities on site will include:
1. Personal protective equipment.
2. Firefighting equipment.
3. First aid facilities.
4. Arrangements for injury and other treatment with Indus Hospital.
5. Housekeeping facilities including waste drums, collection, and disposals in a safe manner.
6. Safe drinking water and sanitation facilities.
CONSTRUCTION QUALITY CONTROL:
There will be QA / QC supervisors to implement the Project Quality Control Plan. They will work under Project Manager. The project specific quality plan will be prepared prior to start of work
at site. As a sample please refer to attach Construction Quality Control Plan.
5
SECURITY:
Security for the work sites, site facilities area, and staff / labor camps will be provided through day and night watchmen, entry posts and adequate area lighting for night time use.
WORK METHODOLOGY:
Survey Control and Set-out:
It is proposed to use four (4) survey teams, comprising one qualified senior surveyor and two survey assistants each, for the project works. The survey teams will establish and maintain survey
monuments, temporary markers, property lines, reference base lines, and perform all survey work necessary to achieve the design formations, elevations and grades.
Plant Maintenance:
A workshop will be established for the purposes of servicing and routine maintenance of plant only. No major repairs shall be carried out on site. The workshop will be housed in a shed
structure within the camp premises and equipped for lubrication, filter changes, tyre filling, and minor repairs.
Diesel for the construction plant will be stored on site in a 15,00liters steel tank installed in accordance with the safety requirements for fuel storage.
Material Handling & Lifting:
1) Tower Crane It is proposed to use three (3) static tower cranes The HUH is 35 m, jib length 50m, and lifting capacity is 10 ton with 2 ton Tip load whose seems to be adequate for
Project.
2) Construction Passenger Hoist single cabin with 2 ton capacity – 2 Nos.
3) Construction Cargo Hoist single cabin with 2 ton capacity – 2 Nos.
Concrete Pumps:
Two stationary pumps 60 Cu-m/Hr are proposed for concrete placement in the floor slabs. The 125mm diameter delivery line shall be attached to the building structure (columns or lift core)
through steel profiles and expansion bolts. It is also proposed to use a mobile pump during ground level and low level concreting.
System Formwork:
The proposed system formwork will comprise of:
1) Panel forms for internal walls and columns.
2) Panel forms for lift cores and stair walls.
3) Slab form systems for floor slabs, drop panels & beams.
4) Site fabricated forms for staircases and special shapes.
It is proposed to use the RMD Kwikform system we already own and which has been successfully used on several high profile projects. All formwork and accessories shall be designed for the
imposed loads of the concrete and for specified off-form finishes.
Formwork for Slab, Drop Panels and Beams:
We propose to have 80,000 Sft of proprietary RMD system formwork and 40,000 Sft of conventional formwork at site for Slab, Drop Panels & Beams. Form face would be 18mm thick quality
plywood.
6
Formwork for Columns and Walls:
We propose to have 45 sets of Columns Formwork.
Other Equipment:
Other equipment for building construction shall include excavation and backfill compaction machinery, material handling equipment, power generating sets , dewatering equipment, re-bar
fabrication equipment and conventional scaffolding for access / miscellanies uses..
Manpower Deployment / Supervision:
Efficient and productive deployment of labor and supervisory staff on building construction is achieved by:
1. Speedy transport to floor levels of personnel, tools, and materials.
2. An efficient communication system between ground facilities such as stores, laboratory, batch plants, workshops etc.
3. Easy access to facilities such as toilets and drinking water.
For communication between the works crews on floor levels and the ground facilities hand-held radio sets shall be used.
The above measures shall ensure quick deployment of work crews to floor levels, timely availability of tools and materials, and a minimum of non-productive labor time due to toilet breaks and
water breaks.
Plant & Equipment Proposed:
Please refer to attach Equipment Deployment Plan.
Material Procurement:
Procurement of all permanent material will be the responsibility of the site management team. They will be responsible for submittals, approvals, ordering, delivery and warehousing.
Concrete Batch Plant:
Concrete will be delivered to the site from selected approved pre-mix concrete suppliers
Activity Name Original
Duration
Start Finish
Total 720d 02-Nov-2015 21-Oct-2017
Construction of Gery Structure (Core 720d 02-Nov-2015 21-Oct-2017
Mobilazation 720d 02-Nov-2015 21-Oct-2017
Start Of Work 0d 02-Nov-2015
Mobilazation and Site Set-Up /Approval of Mix Des 45d 02-Nov-2015 16-Dec-2015
Sub Structure Works 248d 07-Nov-2015 11-Jul-2016
Excavation Work 50d 07-Nov-2015 26-Dec-2015
Pile Bracking 30d 12-Nov-2015 11-Dec-2015
Pcc for Raft 45d 22-Nov-2015 05-Jan-2016
Pile Cap Reinf 45d 02-Dec-2015 15-Jan-2016
Pouring 45d 02-Dec-2015 15-Jan-2016
Retaining Wall & Columns 100d 05-Dec-2015 13-Mar-2016
Under Ground Water Tank 50d 24-Nov-2015 12-Jan-2016
Ground Floor Slab 160d 03-Feb-2016 11-Jul-2016
Ramp Slab from B-1 to Ground 25d 17-Jun-2016 11-Jul-2016
Water Proofing 90d 03-Feb-2016 02-May-2016
Package-A (Basment, Hospiatl Building & He 488d 23-May-2016 22-Sep-2017
F-1 & Meeznine 125d 23-May-2016 24-Sep-2016
Floor Column & Walls 40d 23-May-2016 01-Jul-2016
Floor Slabe 100d 17-Jun-2016 24-Sep-2016
F-2 100d 01-Aug-2016 08-Nov-2016
Floor Column & Walls 35d 01-Aug-2016 05-Sep-2016
Floor Slabe 80d 21-Aug-2016 08-Nov-2016
F-3 95d 10-Oct-2016 12-Jan-2017
Floor Column & Walls 30d 10-Oct-2016 08-Nov-2016
Floor Slabe 80d 25-Oct-2016 12-Jan-2017
F-4 95d 24-Nov-2016 26-Feb-2017
Floor Column & Walls 30d 24-Nov-2016 24-Dec-2016
Floor Slabe 80d 09-Dec-2016 26-Feb-2017
F-5 85d 08-Jan-2017 02-Apr-2017
Floor Column & Walls 30d 08-Jan-2017 07-Feb-2017
Floor Slabe 70d 23-Jan-2017 02-Apr-2017
F-6 70d 15-Feb-2017 25-Apr-2017
Floor Column & Walls 25d 15-Feb-2017 12-Mar-2017
Floor Slabe 60d 25-Feb-2017 25-Apr-2017
F-7 70d 12-Mar-2017 20-May-2017
Floor Column & Walls 25d 12-Mar-2017 06-Apr-2017
Floor Slabe 60d 22-Mar-2017 20-May-2017
F-8 70d 06-Apr-2017 14-Jun-2017
Floor Column & Walls 25d 06-Apr-2017 01-May-2017
Floor Slabe 60d 16-Apr-2017 14-Jun-2017
F-9 70d 01-May-2017 09-Jul-2017
Floor Column & Walls 25d 01-May-2017 26-May-2017
Floor Slabe 60d 11-May-2017 09-Jul-2017
F-10 70d 26-May-2017 03-Aug-2017
Floor Column & Walls 25d 26-May-2017 20-Jun-2017
Floor Slabe 60d 05-Jun-2017 03-Aug-2017
Roof 95d 20-Jun-2017 22-Sep-2017
Floor Column & Walls 25d 20-Jun-2017 15-Jul-2017
Floor Slabe 60d 30-Jun-2017 28-Aug-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
-2015 21-Oct-2017
-2015 21-Oct-2017
-2015 21-Oct-2017
Start Of Work
v-2015 11-Jul-2016
23-May-2016 22-Sep-2017
23-May-2016 24-Sep-2016
01-Aug-2016 08-Nov-2016
10-Oct-2016 12-Jan-2017
24-Nov-2016 26-Feb-2017
08-Jan-2017 02-Apr-2017
15-Feb-2017 25-Apr-2017
12-Mar-2017 20-May-2017
06-Apr-2017 14-Jun-2017
01-May-2017 09-Jul-2017
26-May-2017 03-Aug-2017
20-Jun-2017 22-Sep-2017
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...
Activity Name Original
Duration
Start Finish
Upper Roof Slab Works 40d 14-Aug-2017 22-Sep-2017
Package-B ( ECOL Building) 338d 12-Jun-2016 15-May-2017
F-1 100d 12-Jun-2016 19-Sep-2016
Floor Column & Walls 30d 12-Jun-2016 11-Jul-2016
Floor Slabe 70d 27-Jun-2016 04-Sep-2016
Ramp GF to F-1 15d 05-Sep-2016 19-Sep-2016
F-2 85d 22-Jul-2016 14-Oct-2016
Floor Column & Walls 25d 22-Jul-2016 16-Aug-2016
Floor Slabe 60d 01-Aug-2016 29-Sep-2016
Ramp F-1 ~ F-2 15d 30-Sep-2016 14-Oct-2016
F-3 85d 16-Aug-2016 08-Nov-2016
Floor Column & Walls 25d 16-Aug-2016 10-Sep-2016
Floor Slabe 60d 26-Aug-2016 24-Oct-2016
Ramp F-2 ~ F-3 15d 25-Oct-2016 08-Nov-2016
F-4 85d 10-Sep-2016 03-Dec-2016
Floor Column & Walls 25d 10-Sep-2016 05-Oct-2016
Floor Slabe 60d 20-Sep-2016 18-Nov-2016
Ramp F-3 ~ F-4 15d 19-Nov-2016 03-Dec-2016
F-5 85d 05-Oct-2016 28-Dec-2016
Floor Column & Walls 25d 05-Oct-2016 30-Oct-2016
Floor Slabe 60d 15-Oct-2016 13-Dec-2016
Ramp F-4 ~ F-5 15d 14-Dec-2016 28-Dec-2016
F-6 85d 28-Oct-2016 20-Jan-2017
Floor Column & Walls 25d 28-Oct-2016 22-Nov-2016
Floor Slabe 60d 07-Nov-2016 05-Jan-2017
Ramp Slab F-5 ~ F-6 15d 06-Jan-2017 20-Jan-2017
F-7 85d 22-Nov-2016 14-Feb-2017
Floor Column & Walls 25d 22-Nov-2016 17-Dec-2016
Floor Slabe 60d 02-Dec-2016 30-Jan-2017
Ramp Slab F-6 ~ F-7 15d 31-Jan-2017 14-Feb-2017
F-8 70d 17-Dec-2016 24-Feb-2017
Floor Column & Walls 25d 17-Dec-2016 11-Jan-2017
Floor Slabe 60d 27-Dec-2016 24-Feb-2017
F-9 70d 11-Jan-2017 21-Mar-2017
Floor Column & Walls 25d 11-Jan-2017 05-Feb-2017
Floor Slabe 60d 21-Jan-2017 21-Mar-2017
Roof 95d 10-Feb-2017 15-May-2017
Floor Column & Walls 25d 10-Feb-2017 07-Mar-2017
Floor Slabe 60d 20-Feb-2017 20-Apr-2017
Upper Roof Slab Works 40d 06-Apr-2017 15-May-2017
Finishing Work 557d 13-Apr-2016 21-Oct-2017
Block Work 530d 13-Apr-2016 24-Sep-2017
Basment ( Hospital & ECOL) 120d 13-Apr-2016 10-Aug-2016
F-1 (Hospital & ECOL) 50d 23-May-2016 11-Jul-2016
F-2 (Hospital & ECOL) 50d 02-Jul-2016 20-Aug-2016
F-3 (Hospital & ECOL) 50d 11-Aug-2016 29-Sep-2016
F-3 (Hospital & ECOL) 50d 20-Sep-2016 08-Nov-2016
F-4 (Hospital & ECOL) 50d 30-Oct-2016 18-Dec-2016
F-5 (Hospital & ECOL) 50d 09-Dec-2016 27-Jan-2017
F-6 (Hospital & ECOL) 50d 18-Jan-2017 08-Mar-2017
F-7 (Hospital & ECOL) 50d 27-Feb-2017 17-Apr-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
12-Jun-2016 15-May-2017
12-Jun-2016 19-Sep-2016
22-Jul-2016 14-Oct-2016
16-Aug-2016 08-Nov-2016
10-Sep-2016 03-Dec-2016
05-Oct-2016 28-Dec-2016
28-Oct-2016 20-Jan-2017
22-Nov-2016 14-Feb-2017
17-Dec-2016 24-Feb-2017
11-Jan-2017 21-Mar-2017
10-Feb-2017 15-May-2017
13-Apr-2016 21-Oct-2017
13-Apr-2016 24-Sep-2017
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...
Activity Name Original
Duration
Start Finish
F-8 (Hospital & ECOL) 50d 08-Apr-2017 27-May-2017
F-9 (Hospital & ECOL) 50d 18-May-2017 06-Jul-2017
F-10 (Hospital & ECOL Roof) 50d 27-Jun-2017 15-Aug-2017
F-11 (Hospital Roof ) 50d 06-Aug-2017 24-Sep-2017
Plaster Work 527d 13-May-2016 21-Oct-2017
Basment ( Hospital & ECOL) 130d 13-May-2016 19-Sep-2016
F-1 (Hospital & ECOL) 50d 22-Jun-2016 10-Aug-2016
F-2 (Hospital & ECOL) 50d 01-Aug-2016 19-Sep-2016
F-3 (Hospital & ECOL) 50d 10-Sep-2016 29-Oct-2016
F-3 (Hospital & ECOL) 50d 20-Oct-2016 08-Dec-2016
F-4 (Hospital & ECOL) 50d 29-Nov-2016 17-Jan-2017
F-5 (Hospital & ECOL) 50d 08-Jan-2017 26-Feb-2017
F-6 (Hospital & ECOL) 50d 17-Feb-2017 07-Apr-2017
F-7 (Hospital & ECOL) 50d 29-Mar-2017 17-May-2017
F-8 (Hospital & ECOL) 50d 08-May-2017 26-Jun-2017
F-9 (Hospital & ECOL) 50d 17-Jun-2017 05-Aug-2017
F-10 (Hospital & ECOL Roof) 70d 27-Jul-2017 04-Oct-2017
F-11 (Hospital Roof ) 47d 05-Sep-2017 21-Oct-2017
Project Complate 0d 21-Oct-2017
O N D J F March April May June July A S O N D J F March April May June July A S O N D
2016 2017
13-May-2016 21-Oct-2017
Project Complat
INDUS HOSPITAL EXTENSION PHASE-1
CONSTRUCTION OF GREY STRUCTURE (Package-A & B)
Note:-Will be Review after Reciving of IFC Drawings Actual Work
Remaining Work
Critical Remaining Work
Milestone
% Co...
Sum...
Description M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 Man Hours
Project Director (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760
Planning Engineer (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760
Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760
Planning Engineer (Site) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,280
Quantity Surveyor 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 10,320
Ass.Q.S/Cad Operator - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,080
Plant /Mech Incharge 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520
Material Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520
Lab Asst. 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 1 1 18,480
HSE Coordinator 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 1 19,920
Safety Inspector 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 - 19,200
Admin Officer - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,280
Timekeeper/Payrool - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520
Camp /Housekeeping Supervisor - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040
Site Accountant - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520
Account Assistant 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,320
Procurement Manager - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 4,800
Site Purchaser - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040
StoreKeeper - 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,560
Construction Manager 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 10,320
Site Engineers 1 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 2 25,200
Asst.Site Engineers 2 4 4 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 8 4 2 48,000
Surveyor 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 11,040
Assistant Surveyor 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 21,120
Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520
Site Engineers 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 15,360
Asst.Site Engineers - 2 2 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 28,320
Surveyor - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,320
Assistant Surveyor - 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 19,440
TOTAL 20 40 52 66 69 71 71 71 71 71 71 71 71 71 71 71 71 71 71 69 68 57 39 19 358,320
FOR PACKAGE-A (BASMENT, HOSPITAL BUILDING, HEAD HOUSE WORKS)
FOR PACKAGE-B (ECOL BUILDING WORKS)
ASSOCIATED CONSTRUCTORS LIMITED
DEPLOYMENT SCHEDULE OF STAFF FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT
(FOR COMMON/SHARED WORKS )
Associated constructor Ltd
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 E.M.
1 Concrete Pump (Stationary) Owned 2 0 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 44
2 External Climbing Tower Crane Owned 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 23
3 Internal Climbing Tower Crane Owned 2 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 46
4 Hydraulic Mobile Crane Rental 2 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 36
5 Construction Hoist
6 Passenger Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32
7 Cargo Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32
8 Generators (Diesel 250 ) Owned 3 0 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 62
9 Generators (Diesel 100 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24
10 Generators (Diesel 80 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24
11 Air Compressor Owned 3 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 59
12 Welding Plant Owned 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 46
13
Concrete Screeding / Floating Equipment for
floors (Set)
Owned 2 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 42
14
Power Tools (Drills, Grinders, Breakers,
Scabblers) (Lots)
Owned
As
Required
A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.
15 Concrete Vibrators Owned
As
Required
A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.
16 Total Station Owned 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 45
17 Surveyors Level Owned 6 2 2 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 124
19 Carpentery Shop (Set) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24
20 Proprietary Formwork System (Sft) 80,000 40,000 60,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 60,000 50,000 A.R.
21 Conventional Formwork (Sft) 40,000 20,000 30,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 30,000 30,000 A.R.
22
Scaffolding Pipe & Joints for All-round &
temporary works
Owned
As
Required
A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R.
23 Columns (Nos.) Owned 45 30 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 1065
24 Re-Bar Bending Machine Owned 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 46
25 Re-Bar Cutting Owned 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 1 67
* Concrete will be delivered to the site from selected approved pre-mix concrete suppliers
Steel Yard
Formwork
Max.
Concrete Works
Cranes, Access Equipment & Transport
Air Compressor & Generator
Small Power Tools & Plants
Status
ASSOCIATED CONSTRUCTORS LIMITED
DEPLOYMENT SCHEDULE OF EQUIPMENT FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT
MONTHS
S.N Description
Carpentery & Fabrication Shop
Associated constructor Ltd
PROPOSED PROJECT ORGANOGRAM FOR CONSTRUCTION OF GREY STRUCTURE (Core & Shell)
INDUS HOSPITAL EXTENSION PHASE‑1 PROJECTAssociated constructor Ltd
PROJECT DIRECTOR
+ 
PLANNING MANAGER
CONSTRUCTION MANAGER                                            
(FOR ECOL BUILDING )
SITE
SUPERVISOR
ASSISTANT
SITE SUPERVISOR
SURVEYORS
ASSISTANT 
SURVEYORS
SURVEYOR 
HELPERS
UN‑SKILLED 
WORKER 
GANG 
SKILLED WORKER 
GANG 
CARPENTER/
SCAFFOLDER/ 
MASON
PLANNING 
ENGINEER
QUANTITY 
SURVEYORS
ASST  QUANTITY 
SURVEYORS & AUTO 
CAD OPERATOR
ADMINISTRATI
ON OFFICER
CAMP /
HOUSEKEEPING 
SUPERVISOR
TIME/PAYROLL 
SUPERVISOR
HSE 
COORDINATOR
MEDIC
SAFETY 
INSPECTORS
QA/QC 
SUPERVISOR
MECH/PLANT
INCHARGE
MECHANICS/ 
OPERATOR/ 
ELECTRICIAN 
PROCUREMENT 
MANAGER  
PURCHASERS
ACCOUNTANT  
OFFICER
ASST   
ACCOUNTANT
STORE
INCHARGE
CONSTRUCTION MANAGER   
(FOR  BASMENT,HOSPITAL BUILDING 
& HEAD HOUSE)
SITE SUPERVISOR
ASST‑SITE 
ENGINEERS
SURVEYORS
SURVEYOR 
HELPERS
UN‑SKILLED 
WORKER 
GANG 
SKILLED 
WORKER 
GANG 
CARPENTER/
SCAFFOLDER/ 
MASON
SURVEYORS
PROJECT 
MANAGER
LABORATORY 
INCHARGE
ASST‑
LABORATORY
THE INDUS HOSPITAL Construction Project Technical Proposal
THE INDUS HOSPITAL Construction Project Technical Proposal
THE INDUS HOSPITAL Construction Project Technical Proposal
THE INDUS HOSPITAL Construction Project Technical Proposal

More Related Content

What's hot

What's hot (19)

Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)
 
newCHris Resume
newCHris ResumenewCHris Resume
newCHris Resume
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.
 
Riaz Cv
Riaz CvRiaz Cv
Riaz Cv
 
NAIYAR CV 1st FEB 2015
NAIYAR CV 1st  FEB 2015NAIYAR CV 1st  FEB 2015
NAIYAR CV 1st FEB 2015
 
Cv english
Cv englishCv english
Cv english
 
Mahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCVMahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCV
 
Muhammed RAFI 2016 SD
Muhammed RAFI 2016 SDMuhammed RAFI 2016 SD
Muhammed RAFI 2016 SD
 
GEC presentation
GEC  presentationGEC  presentation
GEC presentation
 
CV Alberto Uribe English
CV Alberto Uribe EnglishCV Alberto Uribe English
CV Alberto Uribe English
 
last updated khaled CV
last updated khaled CV last updated khaled CV
last updated khaled CV
 
Mustafa cv 2016
Mustafa cv 2016Mustafa cv 2016
Mustafa cv 2016
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
CV -mosleh
CV -moslehCV -mosleh
CV -mosleh
 
Mohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MMohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.M
 
Mohamed Ahmed (2008)
Mohamed Ahmed  (2008)Mohamed Ahmed  (2008)
Mohamed Ahmed (2008)
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Sobhy C V 2015 Rev Q S
Sobhy C V  2015 Rev  Q S  Sobhy C V  2015 Rev  Q S
Sobhy C V 2015 Rev Q S
 
R.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.docR.muthukumar piping design engineer.doc
R.muthukumar piping design engineer.doc
 

Viewers also liked

Project Of Rafah Central Hospital
Project Of Rafah Central HospitalProject Of Rafah Central Hospital
Project Of Rafah Central HospitalHemdan Elshaer
 
ALL IN ONE MOCKUP ROOMS
ALL IN ONE MOCKUP ROOMS ALL IN ONE MOCKUP ROOMS
ALL IN ONE MOCKUP ROOMS muhammad usman
 
Hospital Project by Vasundhara Trust
Hospital Project by Vasundhara TrustHospital Project by Vasundhara Trust
Hospital Project by Vasundhara TrustOptim Associates LLP
 
Hospital sector 39
Hospital sector 39Hospital sector 39
Hospital sector 39Shyam Singh
 
Pearl Hospital Project
Pearl Hospital ProjectPearl Hospital Project
Pearl Hospital Projectawaitingeyes
 
Accident & emergency
Accident & emergencyAccident & emergency
Accident & emergencyvikastyagi
 
Pharmacy layout ppt
Pharmacy layout pptPharmacy layout ppt
Pharmacy layout pptMaham Shafiq
 
Reading floor plans
Reading floor plansReading floor plans
Reading floor plansjayneross
 
Final hospital planning and layout ppt
Final hospital planning and layout pptFinal hospital planning and layout ppt
Final hospital planning and layout pptSandeep Singh
 

Viewers also liked (13)

Project Of Rafah Central Hospital
Project Of Rafah Central HospitalProject Of Rafah Central Hospital
Project Of Rafah Central Hospital
 
ALL IN ONE MOCKUP ROOMS
ALL IN ONE MOCKUP ROOMS ALL IN ONE MOCKUP ROOMS
ALL IN ONE MOCKUP ROOMS
 
Sony hospital
Sony hospitalSony hospital
Sony hospital
 
Hospital Project by Vasundhara Trust
Hospital Project by Vasundhara TrustHospital Project by Vasundhara Trust
Hospital Project by Vasundhara Trust
 
Hospital sector 39
Hospital sector 39Hospital sector 39
Hospital sector 39
 
250 375 bed model hospital
250 375 bed model hospital250 375 bed model hospital
250 375 bed model hospital
 
apollo hospital
apollo hospitalapollo hospital
apollo hospital
 
Pearl Hospital Project
Pearl Hospital ProjectPearl Hospital Project
Pearl Hospital Project
 
Accident & emergency
Accident & emergencyAccident & emergency
Accident & emergency
 
Pharmacy layout ppt
Pharmacy layout pptPharmacy layout ppt
Pharmacy layout ppt
 
Case study
Case studyCase study
Case study
 
Reading floor plans
Reading floor plansReading floor plans
Reading floor plans
 
Final hospital planning and layout ppt
Final hospital planning and layout pptFinal hospital planning and layout ppt
Final hospital planning and layout ppt
 

Similar to THE INDUS HOSPITAL Construction Project Technical Proposal

Similar to THE INDUS HOSPITAL Construction Project Technical Proposal (20)

Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector  Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector
 
Cv.eslam elsnosy.update
Cv.eslam elsnosy.updateCv.eslam elsnosy.update
Cv.eslam elsnosy.update
 
CV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.updateCV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.update
 
Project Charter Completed
Project Charter CompletedProject Charter Completed
Project Charter Completed
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
Engineering
EngineeringEngineering
Engineering
 
RHI Capability Summary
RHI Capability SummaryRHI Capability Summary
RHI Capability Summary
 
Hisham C.V December 2014 C.C.M
Hisham C.V December 2014 C.C.MHisham C.V December 2014 C.C.M
Hisham C.V December 2014 C.C.M
 
Saeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer UtilitiesSaeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer Utilities
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
Eng Ahmed Afifi final CV
Eng Ahmed Afifi final CVEng Ahmed Afifi final CV
Eng Ahmed Afifi final CV
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
 
AH15019
AH15019AH15019
AH15019
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
wsa
wsawsa
wsa
 
Ahmed_c.v
Ahmed_c.vAhmed_c.v
Ahmed_c.v
 
vijay cv
vijay cvvijay cv
vijay cv
 
hidayath cv 2016
hidayath cv 2016hidayath cv 2016
hidayath cv 2016
 

THE INDUS HOSPITAL Construction Project Technical Proposal

  • 1.                                                                1    THE INDUS HOSPITAL Construction of Grey Structure (Core & Shell) Extension Phase 1 Technical Proposal Package
  • 2.                                                                2    CONTENT   SHEET NO  DESCRIPTION 01 ~ 04  PROJECT METHODOLOGY  05 ~ 08  PROJECT SCHEDULE   09  DEPLOYMENT SCHEDULE OF STAFF   10 ~ 11  DEPLOYMENT SCHEDULE OF EQUIPMENT  12   PROJECT ORGANOGRAM   13  TOWER CRANES WORKING ENVELOP  14  TOWER CRANES IN ELEVATION  15  SITE ESTABLISHMENT PLAN   16  PROPRIETARY RMD SYSTEM FORMWORK 
  • 3. 3 PROJECT METHODOLOGY SITE ESTABLISHMENT: SITE OFFICE, STORES, SITE WORKSHOPS: It is proposed to use three 20ft and two 40ft office containers to accommodate the Project Manager, Construction Managers, Site Engineers, Accounts and Other Officers. Two 40ft container will be used as tools and general items store as well as store office. Bulk items, scaffolding, timber, steel forms will be stored in an adjacent Open Store Area levelled and prepared for the purpose. Site workshop will comprise of scaffold frame and corrugated G.I. sheeting sheds with adjacent prepared open work areas. ELECTRIC POWER: Diesel generators, along with the requisite mains switches, cabling and distribution boards will be installed to supply electric power. WATER: Potable water acquired in 5000 gallon tankers, and stored in PVC or steel overhead tanks in the camp areas. The water will be distributed through PVC piping to toilets, showers and kitchens. The water will be filtered for drinking purposes. Also Water for earth fill works and concrete works will be obtained, in 5000 gallon tankers through water purchase agreements with the existing suppliers. MANAGEMENT PLAN SITE ORGANIZATION CHART: Please refer to attached Site Organization Chart. COMMUNICATION & COORDINATION PLAN: Site Coordinating Person: Project manager will be the key coordinating person for the project.
  • 4. 4 Highest Coordinating Person: For owner representative, contact reference will be the Project Director (Mr. Hamid Naqvi). Project Manager reports directly to the Project Director. In-house Communication: Telephone/ Internet facilities will be installed at the Site and will be used for voice / data communications.. INVOICES, SHOP DRAWINGS & SUBMITTALS: Invoice Raising: Quantity Surveyor will work on invoices and it will be raised by Project Manager to owner representative. Drawings & Documents / As Built Drawings: Drawings & Documents will be received at site by the Planning Engineer from the owner representative in accordance with a mutually agreed procedure. All data received will be distributed, filed, and periodically updated by the draftsman under the supervision of the Planning Engineer. "As built" drawings will be prepared by Draftsman working under Planning Engineer, who will report to Project Manager. Submittals: All submittals will be raised by Project Manager through the Planning Engineer. Planning Engineer will be responsible to handle the submittals. TRANSPORT: Well maintained vehicles will be used for site supervision, staff transport, and materials procurement duties. It is proposed to use owned / hired vehicles. All vehicles shall be driven only by licensed and trained drivers. CONSTRUCTION/SITE HEALTH & SAFETY: There will be a permanent health & safety supervisor on site. Safety facilities on site will include: 1. Personal protective equipment. 2. Firefighting equipment. 3. First aid facilities. 4. Arrangements for injury and other treatment with Indus Hospital. 5. Housekeeping facilities including waste drums, collection, and disposals in a safe manner. 6. Safe drinking water and sanitation facilities. CONSTRUCTION QUALITY CONTROL: There will be QA / QC supervisors to implement the Project Quality Control Plan. They will work under Project Manager. The project specific quality plan will be prepared prior to start of work at site. As a sample please refer to attach Construction Quality Control Plan.
  • 5. 5 SECURITY: Security for the work sites, site facilities area, and staff / labor camps will be provided through day and night watchmen, entry posts and adequate area lighting for night time use. WORK METHODOLOGY: Survey Control and Set-out: It is proposed to use four (4) survey teams, comprising one qualified senior surveyor and two survey assistants each, for the project works. The survey teams will establish and maintain survey monuments, temporary markers, property lines, reference base lines, and perform all survey work necessary to achieve the design formations, elevations and grades. Plant Maintenance: A workshop will be established for the purposes of servicing and routine maintenance of plant only. No major repairs shall be carried out on site. The workshop will be housed in a shed structure within the camp premises and equipped for lubrication, filter changes, tyre filling, and minor repairs. Diesel for the construction plant will be stored on site in a 15,00liters steel tank installed in accordance with the safety requirements for fuel storage. Material Handling & Lifting: 1) Tower Crane It is proposed to use three (3) static tower cranes The HUH is 35 m, jib length 50m, and lifting capacity is 10 ton with 2 ton Tip load whose seems to be adequate for Project. 2) Construction Passenger Hoist single cabin with 2 ton capacity – 2 Nos. 3) Construction Cargo Hoist single cabin with 2 ton capacity – 2 Nos. Concrete Pumps: Two stationary pumps 60 Cu-m/Hr are proposed for concrete placement in the floor slabs. The 125mm diameter delivery line shall be attached to the building structure (columns or lift core) through steel profiles and expansion bolts. It is also proposed to use a mobile pump during ground level and low level concreting. System Formwork: The proposed system formwork will comprise of: 1) Panel forms for internal walls and columns. 2) Panel forms for lift cores and stair walls. 3) Slab form systems for floor slabs, drop panels & beams. 4) Site fabricated forms for staircases and special shapes. It is proposed to use the RMD Kwikform system we already own and which has been successfully used on several high profile projects. All formwork and accessories shall be designed for the imposed loads of the concrete and for specified off-form finishes. Formwork for Slab, Drop Panels and Beams: We propose to have 80,000 Sft of proprietary RMD system formwork and 40,000 Sft of conventional formwork at site for Slab, Drop Panels & Beams. Form face would be 18mm thick quality plywood.
  • 6. 6 Formwork for Columns and Walls: We propose to have 45 sets of Columns Formwork. Other Equipment: Other equipment for building construction shall include excavation and backfill compaction machinery, material handling equipment, power generating sets , dewatering equipment, re-bar fabrication equipment and conventional scaffolding for access / miscellanies uses.. Manpower Deployment / Supervision: Efficient and productive deployment of labor and supervisory staff on building construction is achieved by: 1. Speedy transport to floor levels of personnel, tools, and materials. 2. An efficient communication system between ground facilities such as stores, laboratory, batch plants, workshops etc. 3. Easy access to facilities such as toilets and drinking water. For communication between the works crews on floor levels and the ground facilities hand-held radio sets shall be used. The above measures shall ensure quick deployment of work crews to floor levels, timely availability of tools and materials, and a minimum of non-productive labor time due to toilet breaks and water breaks. Plant & Equipment Proposed: Please refer to attach Equipment Deployment Plan. Material Procurement: Procurement of all permanent material will be the responsibility of the site management team. They will be responsible for submittals, approvals, ordering, delivery and warehousing. Concrete Batch Plant: Concrete will be delivered to the site from selected approved pre-mix concrete suppliers
  • 7. Activity Name Original Duration Start Finish Total 720d 02-Nov-2015 21-Oct-2017 Construction of Gery Structure (Core 720d 02-Nov-2015 21-Oct-2017 Mobilazation 720d 02-Nov-2015 21-Oct-2017 Start Of Work 0d 02-Nov-2015 Mobilazation and Site Set-Up /Approval of Mix Des 45d 02-Nov-2015 16-Dec-2015 Sub Structure Works 248d 07-Nov-2015 11-Jul-2016 Excavation Work 50d 07-Nov-2015 26-Dec-2015 Pile Bracking 30d 12-Nov-2015 11-Dec-2015 Pcc for Raft 45d 22-Nov-2015 05-Jan-2016 Pile Cap Reinf 45d 02-Dec-2015 15-Jan-2016 Pouring 45d 02-Dec-2015 15-Jan-2016 Retaining Wall & Columns 100d 05-Dec-2015 13-Mar-2016 Under Ground Water Tank 50d 24-Nov-2015 12-Jan-2016 Ground Floor Slab 160d 03-Feb-2016 11-Jul-2016 Ramp Slab from B-1 to Ground 25d 17-Jun-2016 11-Jul-2016 Water Proofing 90d 03-Feb-2016 02-May-2016 Package-A (Basment, Hospiatl Building & He 488d 23-May-2016 22-Sep-2017 F-1 & Meeznine 125d 23-May-2016 24-Sep-2016 Floor Column & Walls 40d 23-May-2016 01-Jul-2016 Floor Slabe 100d 17-Jun-2016 24-Sep-2016 F-2 100d 01-Aug-2016 08-Nov-2016 Floor Column & Walls 35d 01-Aug-2016 05-Sep-2016 Floor Slabe 80d 21-Aug-2016 08-Nov-2016 F-3 95d 10-Oct-2016 12-Jan-2017 Floor Column & Walls 30d 10-Oct-2016 08-Nov-2016 Floor Slabe 80d 25-Oct-2016 12-Jan-2017 F-4 95d 24-Nov-2016 26-Feb-2017 Floor Column & Walls 30d 24-Nov-2016 24-Dec-2016 Floor Slabe 80d 09-Dec-2016 26-Feb-2017 F-5 85d 08-Jan-2017 02-Apr-2017 Floor Column & Walls 30d 08-Jan-2017 07-Feb-2017 Floor Slabe 70d 23-Jan-2017 02-Apr-2017 F-6 70d 15-Feb-2017 25-Apr-2017 Floor Column & Walls 25d 15-Feb-2017 12-Mar-2017 Floor Slabe 60d 25-Feb-2017 25-Apr-2017 F-7 70d 12-Mar-2017 20-May-2017 Floor Column & Walls 25d 12-Mar-2017 06-Apr-2017 Floor Slabe 60d 22-Mar-2017 20-May-2017 F-8 70d 06-Apr-2017 14-Jun-2017 Floor Column & Walls 25d 06-Apr-2017 01-May-2017 Floor Slabe 60d 16-Apr-2017 14-Jun-2017 F-9 70d 01-May-2017 09-Jul-2017 Floor Column & Walls 25d 01-May-2017 26-May-2017 Floor Slabe 60d 11-May-2017 09-Jul-2017 F-10 70d 26-May-2017 03-Aug-2017 Floor Column & Walls 25d 26-May-2017 20-Jun-2017 Floor Slabe 60d 05-Jun-2017 03-Aug-2017 Roof 95d 20-Jun-2017 22-Sep-2017 Floor Column & Walls 25d 20-Jun-2017 15-Jul-2017 Floor Slabe 60d 30-Jun-2017 28-Aug-2017 O N D J F March April May June July A S O N D J F March April May June July A S O N D 2016 2017 -2015 21-Oct-2017 -2015 21-Oct-2017 -2015 21-Oct-2017 Start Of Work v-2015 11-Jul-2016 23-May-2016 22-Sep-2017 23-May-2016 24-Sep-2016 01-Aug-2016 08-Nov-2016 10-Oct-2016 12-Jan-2017 24-Nov-2016 26-Feb-2017 08-Jan-2017 02-Apr-2017 15-Feb-2017 25-Apr-2017 12-Mar-2017 20-May-2017 06-Apr-2017 14-Jun-2017 01-May-2017 09-Jul-2017 26-May-2017 03-Aug-2017 20-Jun-2017 22-Sep-2017 INDUS HOSPITAL EXTENSION PHASE-1 CONSTRUCTION OF GREY STRUCTURE (Package-A & B) Note:-Will be Review after Reciving of IFC Drawings Actual Work Remaining Work Critical Remaining Work Milestone % Co... Sum...
  • 8. Activity Name Original Duration Start Finish Upper Roof Slab Works 40d 14-Aug-2017 22-Sep-2017 Package-B ( ECOL Building) 338d 12-Jun-2016 15-May-2017 F-1 100d 12-Jun-2016 19-Sep-2016 Floor Column & Walls 30d 12-Jun-2016 11-Jul-2016 Floor Slabe 70d 27-Jun-2016 04-Sep-2016 Ramp GF to F-1 15d 05-Sep-2016 19-Sep-2016 F-2 85d 22-Jul-2016 14-Oct-2016 Floor Column & Walls 25d 22-Jul-2016 16-Aug-2016 Floor Slabe 60d 01-Aug-2016 29-Sep-2016 Ramp F-1 ~ F-2 15d 30-Sep-2016 14-Oct-2016 F-3 85d 16-Aug-2016 08-Nov-2016 Floor Column & Walls 25d 16-Aug-2016 10-Sep-2016 Floor Slabe 60d 26-Aug-2016 24-Oct-2016 Ramp F-2 ~ F-3 15d 25-Oct-2016 08-Nov-2016 F-4 85d 10-Sep-2016 03-Dec-2016 Floor Column & Walls 25d 10-Sep-2016 05-Oct-2016 Floor Slabe 60d 20-Sep-2016 18-Nov-2016 Ramp F-3 ~ F-4 15d 19-Nov-2016 03-Dec-2016 F-5 85d 05-Oct-2016 28-Dec-2016 Floor Column & Walls 25d 05-Oct-2016 30-Oct-2016 Floor Slabe 60d 15-Oct-2016 13-Dec-2016 Ramp F-4 ~ F-5 15d 14-Dec-2016 28-Dec-2016 F-6 85d 28-Oct-2016 20-Jan-2017 Floor Column & Walls 25d 28-Oct-2016 22-Nov-2016 Floor Slabe 60d 07-Nov-2016 05-Jan-2017 Ramp Slab F-5 ~ F-6 15d 06-Jan-2017 20-Jan-2017 F-7 85d 22-Nov-2016 14-Feb-2017 Floor Column & Walls 25d 22-Nov-2016 17-Dec-2016 Floor Slabe 60d 02-Dec-2016 30-Jan-2017 Ramp Slab F-6 ~ F-7 15d 31-Jan-2017 14-Feb-2017 F-8 70d 17-Dec-2016 24-Feb-2017 Floor Column & Walls 25d 17-Dec-2016 11-Jan-2017 Floor Slabe 60d 27-Dec-2016 24-Feb-2017 F-9 70d 11-Jan-2017 21-Mar-2017 Floor Column & Walls 25d 11-Jan-2017 05-Feb-2017 Floor Slabe 60d 21-Jan-2017 21-Mar-2017 Roof 95d 10-Feb-2017 15-May-2017 Floor Column & Walls 25d 10-Feb-2017 07-Mar-2017 Floor Slabe 60d 20-Feb-2017 20-Apr-2017 Upper Roof Slab Works 40d 06-Apr-2017 15-May-2017 Finishing Work 557d 13-Apr-2016 21-Oct-2017 Block Work 530d 13-Apr-2016 24-Sep-2017 Basment ( Hospital & ECOL) 120d 13-Apr-2016 10-Aug-2016 F-1 (Hospital & ECOL) 50d 23-May-2016 11-Jul-2016 F-2 (Hospital & ECOL) 50d 02-Jul-2016 20-Aug-2016 F-3 (Hospital & ECOL) 50d 11-Aug-2016 29-Sep-2016 F-3 (Hospital & ECOL) 50d 20-Sep-2016 08-Nov-2016 F-4 (Hospital & ECOL) 50d 30-Oct-2016 18-Dec-2016 F-5 (Hospital & ECOL) 50d 09-Dec-2016 27-Jan-2017 F-6 (Hospital & ECOL) 50d 18-Jan-2017 08-Mar-2017 F-7 (Hospital & ECOL) 50d 27-Feb-2017 17-Apr-2017 O N D J F March April May June July A S O N D J F March April May June July A S O N D 2016 2017 12-Jun-2016 15-May-2017 12-Jun-2016 19-Sep-2016 22-Jul-2016 14-Oct-2016 16-Aug-2016 08-Nov-2016 10-Sep-2016 03-Dec-2016 05-Oct-2016 28-Dec-2016 28-Oct-2016 20-Jan-2017 22-Nov-2016 14-Feb-2017 17-Dec-2016 24-Feb-2017 11-Jan-2017 21-Mar-2017 10-Feb-2017 15-May-2017 13-Apr-2016 21-Oct-2017 13-Apr-2016 24-Sep-2017 INDUS HOSPITAL EXTENSION PHASE-1 CONSTRUCTION OF GREY STRUCTURE (Package-A & B) Note:-Will be Review after Reciving of IFC Drawings Actual Work Remaining Work Critical Remaining Work Milestone % Co... Sum...
  • 9. Activity Name Original Duration Start Finish F-8 (Hospital & ECOL) 50d 08-Apr-2017 27-May-2017 F-9 (Hospital & ECOL) 50d 18-May-2017 06-Jul-2017 F-10 (Hospital & ECOL Roof) 50d 27-Jun-2017 15-Aug-2017 F-11 (Hospital Roof ) 50d 06-Aug-2017 24-Sep-2017 Plaster Work 527d 13-May-2016 21-Oct-2017 Basment ( Hospital & ECOL) 130d 13-May-2016 19-Sep-2016 F-1 (Hospital & ECOL) 50d 22-Jun-2016 10-Aug-2016 F-2 (Hospital & ECOL) 50d 01-Aug-2016 19-Sep-2016 F-3 (Hospital & ECOL) 50d 10-Sep-2016 29-Oct-2016 F-3 (Hospital & ECOL) 50d 20-Oct-2016 08-Dec-2016 F-4 (Hospital & ECOL) 50d 29-Nov-2016 17-Jan-2017 F-5 (Hospital & ECOL) 50d 08-Jan-2017 26-Feb-2017 F-6 (Hospital & ECOL) 50d 17-Feb-2017 07-Apr-2017 F-7 (Hospital & ECOL) 50d 29-Mar-2017 17-May-2017 F-8 (Hospital & ECOL) 50d 08-May-2017 26-Jun-2017 F-9 (Hospital & ECOL) 50d 17-Jun-2017 05-Aug-2017 F-10 (Hospital & ECOL Roof) 70d 27-Jul-2017 04-Oct-2017 F-11 (Hospital Roof ) 47d 05-Sep-2017 21-Oct-2017 Project Complate 0d 21-Oct-2017 O N D J F March April May June July A S O N D J F March April May June July A S O N D 2016 2017 13-May-2016 21-Oct-2017 Project Complat INDUS HOSPITAL EXTENSION PHASE-1 CONSTRUCTION OF GREY STRUCTURE (Package-A & B) Note:-Will be Review after Reciving of IFC Drawings Actual Work Remaining Work Critical Remaining Work Milestone % Co... Sum...
  • 10. Description M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 Man Hours Project Director (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760 Planning Engineer (H.O) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,760 Planning Engineer (Site) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,280 Quantity Surveyor 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 10,320 Ass.Q.S/Cad Operator - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,080 Plant /Mech Incharge 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520 Material Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,520 Lab Asst. 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 1 1 18,480 HSE Coordinator 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 1 19,920 Safety Inspector 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 - 19,200 Admin Officer - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - 5,280 Timekeeper/Payrool - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520 Camp /Housekeeping Supervisor - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040 Site Accountant - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520 Account Assistant 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 - 10,320 Procurement Manager - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 4,800 Site Purchaser - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - 5,040 StoreKeeper - 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,560 Construction Manager 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 10,320 Site Engineers 1 2 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 2 25,200 Asst.Site Engineers 2 4 4 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 8 4 2 48,000 Surveyor 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 11,040 Assistant Surveyor 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 21,120 Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5,520 Site Engineers 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 15,360 Asst.Site Engineers - 2 2 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 28,320 Surveyor - 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10,320 Assistant Surveyor - 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 1 19,440 TOTAL 20 40 52 66 69 71 71 71 71 71 71 71 71 71 71 71 71 71 71 69 68 57 39 19 358,320 FOR PACKAGE-A (BASMENT, HOSPITAL BUILDING, HEAD HOUSE WORKS) FOR PACKAGE-B (ECOL BUILDING WORKS) ASSOCIATED CONSTRUCTORS LIMITED DEPLOYMENT SCHEDULE OF STAFF FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT (FOR COMMON/SHARED WORKS ) Associated constructor Ltd
  • 11. M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 E.M. 1 Concrete Pump (Stationary) Owned 2 0 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 44 2 External Climbing Tower Crane Owned 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 23 3 Internal Climbing Tower Crane Owned 2 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 46 4 Hydraulic Mobile Crane Rental 2 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 36 5 Construction Hoist 6 Passenger Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32 7 Cargo Owned 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32 8 Generators (Diesel 250 ) Owned 3 0 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 62 9 Generators (Diesel 100 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 10 Generators (Diesel 80 KVA) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 11 Air Compressor Owned 3 1 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 59 12 Welding Plant Owned 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 46 13 Concrete Screeding / Floating Equipment for floors (Set) Owned 2 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 42 14 Power Tools (Drills, Grinders, Breakers, Scabblers) (Lots) Owned As Required A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. 15 Concrete Vibrators Owned As Required A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. 16 Total Station Owned 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 45 17 Surveyors Level Owned 6 2 2 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 124 19 Carpentery Shop (Set) Owned 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 20 Proprietary Formwork System (Sft) 80,000 40,000 60,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 60,000 50,000 A.R. 21 Conventional Formwork (Sft) 40,000 20,000 30,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 30,000 30,000 A.R. 22 Scaffolding Pipe & Joints for All-round & temporary works Owned As Required A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. A.R. 23 Columns (Nos.) Owned 45 30 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 1065 24 Re-Bar Bending Machine Owned 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 46 25 Re-Bar Cutting Owned 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 1 67 * Concrete will be delivered to the site from selected approved pre-mix concrete suppliers Steel Yard Formwork Max. Concrete Works Cranes, Access Equipment & Transport Air Compressor & Generator Small Power Tools & Plants Status ASSOCIATED CONSTRUCTORS LIMITED DEPLOYMENT SCHEDULE OF EQUIPMENT FOR INDUS HOSPITAL EXTENSION PHASE-1 PROJECT MONTHS S.N Description Carpentery & Fabrication Shop Associated constructor Ltd
  • 12. PROPOSED PROJECT ORGANOGRAM FOR CONSTRUCTION OF GREY STRUCTURE (Core & Shell) INDUS HOSPITAL EXTENSION PHASE‑1 PROJECTAssociated constructor Ltd PROJECT DIRECTOR +  PLANNING MANAGER CONSTRUCTION MANAGER                                             (FOR ECOL BUILDING ) SITE SUPERVISOR ASSISTANT SITE SUPERVISOR SURVEYORS ASSISTANT  SURVEYORS SURVEYOR  HELPERS UN‑SKILLED  WORKER  GANG  SKILLED WORKER  GANG  CARPENTER/ SCAFFOLDER/  MASON PLANNING  ENGINEER QUANTITY  SURVEYORS ASST  QUANTITY  SURVEYORS & AUTO  CAD OPERATOR ADMINISTRATI ON OFFICER CAMP / HOUSEKEEPING  SUPERVISOR TIME/PAYROLL  SUPERVISOR HSE  COORDINATOR MEDIC SAFETY  INSPECTORS QA/QC  SUPERVISOR MECH/PLANT INCHARGE MECHANICS/  OPERATOR/  ELECTRICIAN  PROCUREMENT  MANAGER   PURCHASERS ACCOUNTANT   OFFICER ASST    ACCOUNTANT STORE INCHARGE CONSTRUCTION MANAGER    (FOR  BASMENT,HOSPITAL BUILDING  & HEAD HOUSE) SITE SUPERVISOR ASST‑SITE  ENGINEERS SURVEYORS SURVEYOR  HELPERS UN‑SKILLED  WORKER  GANG  SKILLED  WORKER  GANG  CARPENTER/ SCAFFOLDER/  MASON SURVEYORS PROJECT  MANAGER LABORATORY  INCHARGE ASST‑ LABORATORY