SlideShare a Scribd company logo
1 of 17
18/11/2022 1
METHOD STATEMENT & ASSESSMENT FOR LOAD TEST
INJECTION PILING WORKS
LIPIDS TERMINAL SDN BHD
Jalan Kenanga 1, Kawasan Liquid Bulk Terminal
Westport, Pulau Indah
42009 Klang, Selangor Darul Ehsan
Tel : 03-31010011 / Fax : 03-31011800
LIPIDS TERMINAL SDN.BHD
18/11/2022 2
Proposed Extension Of Bulk Storage Facilities At Liquid Bulk Terminal Westports,
Pulau Indah Klang, Selangor Darul Ehsan For Lipids Terminal Sdn Bhd
1. Above Ground Tank Storage
2. Bund Wall
3. Weighbridge
4. Pipe Rack Crossing Road
5. Motorized Sliding Gate - Entrance
6. Guard House
7. Internal Road & Drainage
Consultant :-
Konsultant Proses Sdn Bhd
(Project Managers & Consulting Engineers)
Wisma Konpro
No 1, Persiaran Teknologi Subang,
Subang Hi Tech Industrial Park,
47500 Subang Jaya, Selangor Darul Ehsan
Project Information
18/11/2022 3
Foundation Illustration
18/11/2022 4
Load Influence Zone - Illustration
18/11/2022 5
1) INTRODUCTION
• Load Test involves measurement of pile head displacement in the response to a physically applied test
load. It is the most fundamental form of pile load tes and is considered as the bench mark of pile
performance
2) TYPE OF LOAD TEST
• Load Test will be carried out for the following configurations :
a) Compression
b) Tension
c) Lateral
3) INITIAL LOAD TERST ON PILES
This test is performed to confirm the design load calculations and to provide guidelines for setting up
the limits of acceptance for routine tests. It also gives an idea of the suitability of the piling system.
Initial Test on piles are to be carried out at one or more locations depending on the number of piles
required.
Load applied for the initial (cyclic) load test is 2.5 times the safe carrying capacity of the pile.
4) ROUTINE LOAD TEST ON PILES
Selection of piles for the Routine Test is done based on number of piles required subject to maximum
of total number of piles required. The number of tests may be increased depending on the nature /
type of structure. The test load applied is 1½ times the safe carrying capacity of the pile.
LOAD TEST PROCEDURE
18/11/2022 6
LOAD TEST PROCEDURE
18/11/2022 7
LOAD TEST PROCEDURE
18/11/2022 8
LOAD TEST PROCEDURE
18/11/2022 9
LOAD TEST PROCEDURE
18/11/2022 10
5) THIS TEST WILL BE PERFROMED FOR THE FOLLOWING PURPOSES.
• To ensure the safe load capacity of piles
• Detection of any unusual performance contrary to the findings of the Initial Test.
• The tests shall be performed at the cut-off level only.
• A detailed report for the test result is prepared.
6) VERTICAL LOAD TESTS ON PILES
Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable. The
reinforcement shall be cut and head levelled. A bearing plate with a hole shall be placed on the head
for the jack to rest.
Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor piles
(if required) shall be placed at a centre to centre distance of 3 times the pile diameter subject to a
minimum distance of 2 M.
Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm
sensitivity shall be used.
Application of load- It shall be applied as specified depending on the type of test (routine / initial).
Each load shall be maintained till the rate of displacement of the pile top is either 0.1 mm in the first
30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The next increment in
the load shall be applied on achieving the aforesaid criterion. (Instruction may vary by terminal
instructions)
The test load shall be maintained for 24 hours to 72 hours
LOAD TEST PROCEDURE
18/11/2022 11
LOAD TEST PROCEDURE
18/11/2022 12
LOAD TEST PROCEDURE
18/11/2022 13
Initial Tests– The safe load on a single pile shall be the least of the following:
• 2/3rd of the final load at which the total displacement attains a value of 12 mm unless otherwise
required in a given case on the basis of nature and type of structure in which case, the safe load
should be corresponding to the stated total displacement permissible.
• 50% of the final load at which the total displacement equals 10% of the pile diameter in case of
uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles.
Routine Tests – Acceptance
The maximum settlement at test load should not exceed 12 mm.
Lateral Load Tests on Piles
• The jack should be placed horizontally, between two piles. The load on the jack shall be the same
on both the piles. The load will be applied in increments of 20% of the estimated safe load and at
the cut off level. The load will be increased after the rate of displacement is nearer to 0.1 mm per
30 minutes. If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall
measure the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm
apart vertically, shall be set up and the lateral displacement of the cut-off level calculated by
similar triangles.
The safe load on the pile shall be the least of the following:
• 50% of the final load at which the total displacement increases to 12 mm.
• Final load at which the total displacement corresponds to 5 mm.
LOAD TEST PROCEDURE
18/11/2022 14
HIRARC - CRANE OPERATION
HIRARC - MACHINERIES
18/11/2022 15
HIRARC - LIFTING OPERATION
18/11/2022 16
HIRARC - TEMPORARY WORKS
HIRARC - HOT WORKS
18/11/2022 17
Date : 6th Jan 2021
For Internal Use Only
Prepared By;
Sri Shanmuganathan M Subramaniam
Safety, Security, Health & Environment
Dip (Mgmt), B.A.hons, B.Sc(Mgmt), M.Sc (OSH), Grad IOSH (UK), CMILT, IOW (BEM)
JKKP Registered Safety & Health Officer (SHO)
Maritime Safety Registered (Terminal, Longshoring & Shipyard) - National Safety Council (USA)
Registered IMDG Code Specific - Jabatan Laut Malaysia
Registered Inspector of Works, Board of Engineers (BEM)
HRDF & CIDB Registered Trainer

More Related Content

What's hot

LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1Sreenath Pokkadavath
 
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Muhammad Irfan
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methodsHalim Rahman
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedureAbdul Shukur
 
Pile foundation design
Pile foundation designPile foundation design
Pile foundation designUTHM
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationArbaz Kazi
 
Laboratory soil compaction test
Laboratory soil compaction testLaboratory soil compaction test
Laboratory soil compaction testAtul Hajong
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Muhammad Irfan
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
Lifting plan for bypass stack installation
Lifting plan for bypass stack installationLifting plan for bypass stack installation
Lifting plan for bypass stack installationShah Jalal
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement Suez Halder
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 

What's hot (20)

LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
 
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
 
Lecture 2 bearing capacity
Lecture 2 bearing capacityLecture 2 bearing capacity
Lecture 2 bearing capacity
 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
Pile foundation design
Pile foundation designPile foundation design
Pile foundation design
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow Foundation
 
Laboratory soil compaction test
Laboratory soil compaction testLaboratory soil compaction test
Laboratory soil compaction test
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Jkr Probe Test
Jkr Probe TestJkr Probe Test
Jkr Probe Test
 
Eccentric connections in steel structure
Eccentric connections in steel structureEccentric connections in steel structure
Eccentric connections in steel structure
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Micropile
MicropileMicropile
Micropile
 
Lifting plan for bypass stack installation
Lifting plan for bypass stack installationLifting plan for bypass stack installation
Lifting plan for bypass stack installation
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 

Similar to METHOD AND ASSESSMENT FOR LOAD TEST.ppt

publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdfPradeepPokhrel5
 
Turnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureTurnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureAlessandro Ciattaglia
 
California bearingratio test
California bearingratio testCalifornia bearingratio test
California bearingratio testAsok999
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 
FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480PRIYANSHU KUMAR
 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLift Events
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01anishdani
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEKaran Patel
 
Basic load out methodologies introduction
Basic load out methodologies introductionBasic load out methodologies introduction
Basic load out methodologies introductionBruce nguyen
 
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPTArie van Dijken
 
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptxCarlo882478
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
Abhishek sagar 121vc00235
Abhishek sagar 121vc00235Abhishek sagar 121vc00235
Abhishek sagar 121vc00235Abhishek sagar
 
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...IRJET Journal
 

Similar to METHOD AND ASSESSMENT FOR LOAD TEST.ppt (20)

publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Turnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage AquacultureTurnkey projects and services in Cage Aquaculture
Turnkey projects and services in Cage Aquaculture
 
California bearingratio test
California bearingratio testCalifornia bearingratio test
California bearingratio test
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
2905
29052905
2905
 
FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480
 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochure
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
 
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01Basicloadoutmethodologiesintroduction 130326020122-phpapp01
Basicloadoutmethodologiesintroduction 130326020122-phpapp01
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
 
Basic load out methodologies introduction
Basic load out methodologies introductionBasic load out methodologies introduction
Basic load out methodologies introduction
 
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
 
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx
487665348-PPT-on-FALLING-WEIGHT-DEFLECTOMETER.pptx
 
5816
58165816
5816
 
Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
Abhishek sagar 121vc00235
Abhishek sagar 121vc00235Abhishek sagar 121vc00235
Abhishek sagar 121vc00235
 
D1883.13825
D1883.13825D1883.13825
D1883.13825
 
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
 

Recently uploaded

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Recently uploaded (20)

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 

METHOD AND ASSESSMENT FOR LOAD TEST.ppt

  • 1. 18/11/2022 1 METHOD STATEMENT & ASSESSMENT FOR LOAD TEST INJECTION PILING WORKS LIPIDS TERMINAL SDN BHD Jalan Kenanga 1, Kawasan Liquid Bulk Terminal Westport, Pulau Indah 42009 Klang, Selangor Darul Ehsan Tel : 03-31010011 / Fax : 03-31011800 LIPIDS TERMINAL SDN.BHD
  • 2. 18/11/2022 2 Proposed Extension Of Bulk Storage Facilities At Liquid Bulk Terminal Westports, Pulau Indah Klang, Selangor Darul Ehsan For Lipids Terminal Sdn Bhd 1. Above Ground Tank Storage 2. Bund Wall 3. Weighbridge 4. Pipe Rack Crossing Road 5. Motorized Sliding Gate - Entrance 6. Guard House 7. Internal Road & Drainage Consultant :- Konsultant Proses Sdn Bhd (Project Managers & Consulting Engineers) Wisma Konpro No 1, Persiaran Teknologi Subang, Subang Hi Tech Industrial Park, 47500 Subang Jaya, Selangor Darul Ehsan Project Information
  • 4. 18/11/2022 4 Load Influence Zone - Illustration
  • 5. 18/11/2022 5 1) INTRODUCTION • Load Test involves measurement of pile head displacement in the response to a physically applied test load. It is the most fundamental form of pile load tes and is considered as the bench mark of pile performance 2) TYPE OF LOAD TEST • Load Test will be carried out for the following configurations : a) Compression b) Tension c) Lateral 3) INITIAL LOAD TERST ON PILES This test is performed to confirm the design load calculations and to provide guidelines for setting up the limits of acceptance for routine tests. It also gives an idea of the suitability of the piling system. Initial Test on piles are to be carried out at one or more locations depending on the number of piles required. Load applied for the initial (cyclic) load test is 2.5 times the safe carrying capacity of the pile. 4) ROUTINE LOAD TEST ON PILES Selection of piles for the Routine Test is done based on number of piles required subject to maximum of total number of piles required. The number of tests may be increased depending on the nature / type of structure. The test load applied is 1½ times the safe carrying capacity of the pile. LOAD TEST PROCEDURE
  • 10. 18/11/2022 10 5) THIS TEST WILL BE PERFROMED FOR THE FOLLOWING PURPOSES. • To ensure the safe load capacity of piles • Detection of any unusual performance contrary to the findings of the Initial Test. • The tests shall be performed at the cut-off level only. • A detailed report for the test result is prepared. 6) VERTICAL LOAD TESTS ON PILES Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable. The reinforcement shall be cut and head levelled. A bearing plate with a hole shall be placed on the head for the jack to rest. Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor piles (if required) shall be placed at a centre to centre distance of 3 times the pile diameter subject to a minimum distance of 2 M. Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm sensitivity shall be used. Application of load- It shall be applied as specified depending on the type of test (routine / initial). Each load shall be maintained till the rate of displacement of the pile top is either 0.1 mm in the first 30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The next increment in the load shall be applied on achieving the aforesaid criterion. (Instruction may vary by terminal instructions) The test load shall be maintained for 24 hours to 72 hours LOAD TEST PROCEDURE
  • 13. 18/11/2022 13 Initial Tests– The safe load on a single pile shall be the least of the following: • 2/3rd of the final load at which the total displacement attains a value of 12 mm unless otherwise required in a given case on the basis of nature and type of structure in which case, the safe load should be corresponding to the stated total displacement permissible. • 50% of the final load at which the total displacement equals 10% of the pile diameter in case of uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles. Routine Tests – Acceptance The maximum settlement at test load should not exceed 12 mm. Lateral Load Tests on Piles • The jack should be placed horizontally, between two piles. The load on the jack shall be the same on both the piles. The load will be applied in increments of 20% of the estimated safe load and at the cut off level. The load will be increased after the rate of displacement is nearer to 0.1 mm per 30 minutes. If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall measure the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm apart vertically, shall be set up and the lateral displacement of the cut-off level calculated by similar triangles. The safe load on the pile shall be the least of the following: • 50% of the final load at which the total displacement increases to 12 mm. • Final load at which the total displacement corresponds to 5 mm. LOAD TEST PROCEDURE
  • 14. 18/11/2022 14 HIRARC - CRANE OPERATION HIRARC - MACHINERIES
  • 15. 18/11/2022 15 HIRARC - LIFTING OPERATION
  • 16. 18/11/2022 16 HIRARC - TEMPORARY WORKS HIRARC - HOT WORKS
  • 17. 18/11/2022 17 Date : 6th Jan 2021 For Internal Use Only Prepared By; Sri Shanmuganathan M Subramaniam Safety, Security, Health & Environment Dip (Mgmt), B.A.hons, B.Sc(Mgmt), M.Sc (OSH), Grad IOSH (UK), CMILT, IOW (BEM) JKKP Registered Safety & Health Officer (SHO) Maritime Safety Registered (Terminal, Longshoring & Shipyard) - National Safety Council (USA) Registered IMDG Code Specific - Jabatan Laut Malaysia Registered Inspector of Works, Board of Engineers (BEM) HRDF & CIDB Registered Trainer