SlideShare a Scribd company logo
1 of 43
COMMISSIONING & LOAD TESTING
5000 T CRANE
Gusto model E-5000-SBX-L
Location, Date
Schiedam, 17 January 2011
page 2
HLV Oleg Strashnov
page 3
Agenda
 Objectives
 Safety
 Organization
 Commissioning (A/B/C – scope)
 Load Testing
 Ballast procedure Vessel
 A-frame lowering/upending
 After load testing
 Clarifications
page 4
Objectives
Clarification of the presentation
The purpose of this presentation is to provide information and instructions on how
the CRANE will be commissioned and load tested in order to demonstrate the
CRANE complies with the requirements of the contract.
All the information and instructions together are bundled in a Commissioning & Load
Testing Book which will be the theme of this presentation.
The Commissioning & Load Testing Book comprises mainly of:
• Safety Plan
• Commissioning & Testing Manual
• Load Testing Manual
• Ballast Procedure Vessel
page 5
Safety
Safety issues:
• Control of access / Controlled Area
• Evacuation drill
• Define interface with DFDS, IHC (ERT room), Gusto, Muller, Traffic Control
of Port Authority
• Personal protective
• Weather (Conditions/Forecast)
• Emergency response
• Daily toolbox meeting
page 6
Organization
 Overall organization (IHC)
 Commissioning & Load Testing organization (Gusto)
 Overview members Commissioning & Load Testing team
 Chain of Command
page 7
Organization
Overall Organization (IHC)
Captain
Overall Vessel
Supervisor
(IHC)
Project Management
IHC
Oleg Strashnov
Port Authority
Port of Rotterdam
Ronald van Son Traffic Control
Vessel General
Team
(IHC)
Vessel Ballasting
Team
(IHC)
Crane
Commissioning &
Load Testing Team
Johan de Bruin Jelmer Gerdingh Arie van Dijken
page 8
Organization
Commissioning & Load Testing organization (Gusto)
Co-ordinator
Commissioning Team
Siemens
Rob Reddering
Sven Luessen
Test Pontoons
&
Tug Boat
Muller Transport
Crane driver
Kees Baggerman
Rigger Foreman
Test Pontoons &
Test Weights
Timo van Gils (Franklin)
Ballast Engineer
Test Pontoons
Jack Verzijl (Muller)
Co-ordinator
Commissioning Team
SAS
Martin de Bruin
Engineering
Commissioning
Co-ordinator
Scott Marpole
Arjo van Putten
Superintendent
Load Testing
Procedures
Cees de Heer
HSSE
Arie van Dijken
Ballast Co-ordinator
IHC
Oleg Strashnov
Jelmer Gerdingh
Overall
Co-ordinator
Crane Commissioning
&
Load Testing
page 9
Organization
Overview members Commissioning & Load Testing Team
Company Function / Discipline Name Telephone Substitution Telephone
Gusto Overall Co-ordinator Arie van Dijken 06-20246992 Rob Kloos 06-25004734
Gusto Co-ordinator Procedures Cees de Heer 06-15839461 Arjo van Putten 06-11392295
Gusto Expert Engineer Arjo van Putten 06-11392295 Wim Woldring 06-46613154
Gusto Superintendent Rob Reddering Arie van Dijken 06-20246992
Gusto Co-ordinator Commissioning Scott Marpole 06-55734093 Zeljko Karels 06-11626334
Gusto Construction Manager Rob Kloos 06-25004734 Arie van Dijken 06-20246992
Gusto Project Manager Michael Roosen 06-29349662 Rob Kloos 06-25004734
Siemens Co-ordinator Commissioning Sven Luessen +49(174)1591961 Willy Maas
SAS Co-ordinator Commissioning T.B.A. Martin de Bruin 06-51092561
Muller Captain Tugboat T.B.A. T.B.A.
Muller Ballast Engineer Jack Verzijl 06-51987564 T.B.A.
Franklin Rigger Foreman Timo van Gils 06-57568046 Jerry Bakx 06-57568042
IHC Captain T.B.A. T.B.A.
IHC Vessel Co-ordinator Johan de Bruin 06-14010513 Jaco van Vlaanderen 06-12720790
IHC Ballast Co-ordinator Jelmer Gerdigh 06-21224624 Jelte Buiteman 06-51987564
IHC Crane driver Kees Baggerman 06-22239126 No replacement
IHC Project Co-ordinator Marcel Smits 06-10429853 T.B.A.
IHC Project Manager Ronaldvan Son 06-12268400 T.B.A.
page 10
Commissioning A/B/C/ Scope
Based on report provided by Scott at end of Thursday
page 11
Load Testing
 Load Testing Manual
 Test Weights
 Sling Arrangements
 Load Testing Location
 Load Testing Arrangements
page 12
Load Testing
Load Testing Manual
The Load Testing Manual provides information and instructions on how the CRANE
will be load tested in order to demonstrate the CRANE complies with the
contractual requirements.
The tests described are in agreement with the applicable DNV standard for
Certification of Lifting Appliances January 2007, which is a reprint of the 1994
Rules.
The load testing comprises of loading the CRANE with loads at corresponding radii
as per load-radius curve. The loads at the breaking points in the curve have to be
applied as a minimum, completed with an intermediate load at corresponding
radius.
The test loads chosen are based on the different load cases as per document
GT264.CGG91010 5000 T Crane Loads on System Report showing the (high)
loaded components.
page 13
Load Testing
Test weights
Movable, certified weights will be used:
 Test pontoon 256-2 for loads from 35 t up to 250 t
 Test pontoon 5511 for loads from 250 t up to 1250 t
 Test pontoon 6619 for loads from 1250 t up to 5500 t
 Water bag for loads up to 35 t
Because of their size the weight of the test pontoons cannot be checked with a
separate load cell, therefore the test weight will be based on the certified own
weight and amount of water ballast multiplied by the measured water density.
The amount of water ballast will be based on the sounding tables of the ballast
tanks of the test pontoon.
The test weight including the weight of the required sling arrangement will be the
total weight suspended in the hook of the applicable hoisting system.
page 14
Load Testing
Test Pontoon 256-2
page 15
Load Testing
Test Pontoon 5511
page 16
Load Testing
Test Pontoon 6619
page 17
Load Testing
Water bags
page 18
Load Testing
Sling arrangements
 Sling arrangement for test pontoon 256-2
 Sling arrangement for test pontoon 5511
 Sling arrangement for test pontoon 6619
page 19
Load Testing
Sling arrangement for test pontoon 256-2
page 20
Load Testing
Sling arrangement for test pontoon 5511
page 21
Load Testing
Sling arrangement for test pontoon 6619
page 22
Load Testing
page 23
Load Testing
Location of Load testing at DFDS terminal
page 24
Load Testing
Load Testing Arrangements – Whiphoist 110t @ 118m
page 25
Load Testing
Load Testing Arrangements – Aux. Hoist 1 500 t @ 113 m
page 26
Load Testing
Load Testing Arrangements – Aux. Hoist 1 800 t @ 72 m
page 27
Load Testing
Load Testing Arrangements – Main Hoist 740 t @ 84.5 m
page 28
Load Testing
Load Testing Arrangements – Main Hoist 3800 t @ 43 m
page 29
Load Testing
Load Testing Arrangements – Main Hoist 5000 t @ 32 m
page 30
Ballast Procedure Vessel
 Refer to Ballast System Operation Philosophy
page 31
A-frame Lowering/Upending
Due to limited height when passing the bridge over the Bosporus, the CRANE has
the possibility to lower the A-frame to allow a safe passage.
For lowering /upending the procudere is as follows:
Lowering
1. Vessel must be even keel and preferably 1 - 2 trim (aft ship lower).⁰ ⁰
2. Boom must be in the boom rest. Sea fastening (anti-rotation pins, ballast
box support and safety clamp system) is not required to be engaged.
3. Lower blocks must be in the pockets and give slack wire till the load is on
the pocket and not in the wires. Give not more rope than required to. When
unexpected movements of the A-frame would occur, the weight of the blocks will
help to keep the boom down.
4. Park trolley in middle of boom and position hook halfway between boom
and deck.
5. Give rope of the boom winch till the rope load (indicated by the load pin at
A-frame aft leg) has dropped till about 15 t.
page 32
A-frame Lowering/Upending
6. Remove covers on boom hoist roof behind rope passage and make sure rope
passage can travel backwards.
7. Make sure that hydraulic jacks at hinge points of A-frame aft leg are not
pushing. Remove locking blocks at aft legs A-frame, two at each leg.
8. At both aft legs, two hydraulic jacks are mounted to push the A-frame. Both
systems have there own manual, local controls. First push all jacks with a
stroke of 50 mm. When at maximum pressure of 230 bar nothing happens,
the cause of that must be investigated.
9. Push all jacks more or less simultaneously with steps to 100 mm, 150 mm
and 200 mm. The maximum stroke is 250 mm. Make sure the A-frame can
move without pulling on the hydraulic hoses.
page 33
A-frame Lowering/Upending
10. Give boom rope with 5% speed until A-frame starts to lower or when rope
load (indicated by the load pin at A-frame aft leg) has dropped till 4.6 t.
Theoretically, it should start to move at 5.8 t. Rope pull at drum is then 4.5 t.
11. When A-frame didn’t start to move, push cylinder to maximum stroke.
12. When A-frame still doesn’t move, attach rope of both of load tuggers to the
pad-eyes on mini A-frame. Set load tuggers in CT mode and increase the
load until A-frame moves. Reduce the force to 1 t when A-frame is lowered
more than 10 .⁰
13. When hydraulic jacks are no more in contact with upper leg, pull in the jacks
completely and push them 1 or 2 mm to be sure that no pressure is on the
system. Now disconnect hydraulic hoses.
14. Give rope with the boom hoist until it’s final position is reached with a
maximum speed of 10%. In the mean time rope has to be given on the MH1,
MH2, AH1, AH2 and WH. This process has to be done in steps. After every
step of A-frame lowering, lower blocks need to be given some rope. Also the
rope force (indicated by the load pin at A-frame aft leg) has to be observed
during lowering. Theoretically, the value must be 16.8 t at the lowest position.
When it is exceeding 18.5 t, the operation has to be stopped to investigate the
cause.
page 34
A-frame Lowering/Upending
Upending
1. Start upending the A-frame by booming in with boom hoist at a speed of
maximum 10% until upper and lower leg are (almost) in line or rope load
(indicated by the load pin at A-frame aft leg) has increased till 15 t.
In the mean time rope has to be hauled in on the MH1, MH2, AH1, AH2 and
WH. This process has to be done in steps. After every step of A-frame
upending, the rope of the lower blocks need to be hauled in. Also the rope
force (indicated by the load pin at A-frame aft leg) has to be observed during
upending.
2. When gap at locking blocks is less than 15 mm, normal bolts can be installed
and by fastening the bolts, gap will be closed. When gap is too large for the
bolts, the force on the ropes can be increased till 20 t. It’s possible that the
boom will start to lift while the blocks are in the block pockets. If this doesn’t
help, threaded rods of 500 mm long can be used to pull upper and lower leg to
each other. It might be needed to decrease the rope load to 10-15 t to reduce
friction.
3. Bolts of locking blocks must be on the correct torque (2500 Nm).
4. Close covers on the boom hoist roof behind rope passage.
page 35
A-frame Lowering/Upending
page 36
After Load Testing
General
After execution of the load tests the CRANE, including gear accessories, has to be
examined to observe whether any part has been damaged or permanently
deformed by the test.
Special attention has to be paid to high stressed spots and/or components of the
CRANE which are indicated in so-called ‘ wolken tekeningen’ (clouds drawings).
Dismantling and/or non-destructive testing may be required if deemed
necessary by the Surveyor and/or SHL.
The above applies to the lower blocks and loose gear as well.
Any overload protection system and automatic safe load indicators that may have
been disconnected or by-passed during the load testing have to be re-
connected. Safety valves and or electrical circuit breakers have to be adjusted
accordingly and set points have to be verified and sealed by the Surveyor.
page 37
After Load Testing
Activities to be executed after Load Testing
The activities to be executed are, but not limited to, as follows:
 Examine crane components for (permanently) damages or distortion.
Components, location and method of examination as per so-called ‘ wolken
tekeningen’ and within the discretion of the Surveyor and/or SHL.
 Inspect all bolted or welded connections along with the boom, hoists and slew
transmission.
 Check and verify all bolting torques applied on main items.
 Take oil/grease samples to determine to check for damage or wear
 Check all components in systems for lubricating, air, hydraulic oil, etc. for
leakage or damages
page 38
After Load Testing
page 39
After Load Testing
page 40
After Load Testing
page 41
Clarifications
page 42
Meeting Closed
eeh…Biertje?
www.GustoMSC.com

More Related Content

What's hot

presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranesvipin balan
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brownBill Brown
 
Crane Incident Handbook, by R. John Phillips, P.E., CFEI
Crane Incident Handbook, by R. John Phillips, P.E., CFEICrane Incident Handbook, by R. John Phillips, P.E., CFEI
Crane Incident Handbook, by R. John Phillips, P.E., CFEIMattWarren37
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerTheodoros Dragonas
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soilsSravan Muguda
 
Lifting plan for bypass stack installation
Lifting plan for bypass stack installationLifting plan for bypass stack installation
Lifting plan for bypass stack installationShah Jalal
 
Barge Transportation Analysis & Load out activities in Modular Construction
Barge Transportation Analysis & Load out activities in Modular ConstructionBarge Transportation Analysis & Load out activities in Modular Construction
Barge Transportation Analysis & Load out activities in Modular ConstructionMrudul Thakar
 
Lifting plan for inlet duct removal
Lifting plan for inlet duct removalLifting plan for inlet duct removal
Lifting plan for inlet duct removalShah Jalal
 
Performance presentation 2013
Performance presentation 2013Performance presentation 2013
Performance presentation 2013alsats
 
Forklift training - refresher course
Forklift training - refresher courseForklift training - refresher course
Forklift training - refresher courseEric Lestock Kay
 
Crane Hoist Operations
Crane Hoist OperationsCrane Hoist Operations
Crane Hoist OperationsKJP Consulting
 
Take Off And Landing Performance
Take Off And Landing PerformanceTake Off And Landing Performance
Take Off And Landing Performanceahmad bassiouny
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook920728035348
 
Fork lift training on 21th sep 13
Fork lift training on 21th sep 13Fork lift training on 21th sep 13
Fork lift training on 21th sep 13PRAN-RFL Group
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 

What's hot (20)

Mobile crane
Mobile craneMobile crane
Mobile crane
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
 
2009 Face Conference Orosha Cranes Wooley
2009 Face Conference Orosha Cranes Wooley2009 Face Conference Orosha Cranes Wooley
2009 Face Conference Orosha Cranes Wooley
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
Crane Incident Handbook, by R. John Phillips, P.E., CFEI
Crane Incident Handbook, by R. John Phillips, P.E., CFEICrane Incident Handbook, by R. John Phillips, P.E., CFEI
Crane Incident Handbook, by R. John Phillips, P.E., CFEI
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 
Statnamic testing of soils
Statnamic testing of soilsStatnamic testing of soils
Statnamic testing of soils
 
Lifting plan for bypass stack installation
Lifting plan for bypass stack installationLifting plan for bypass stack installation
Lifting plan for bypass stack installation
 
Barge Transportation Analysis & Load out activities in Modular Construction
Barge Transportation Analysis & Load out activities in Modular ConstructionBarge Transportation Analysis & Load out activities in Modular Construction
Barge Transportation Analysis & Load out activities in Modular Construction
 
Types of crane
Types of craneTypes of crane
Types of crane
 
Lifting plan for inlet duct removal
Lifting plan for inlet duct removalLifting plan for inlet duct removal
Lifting plan for inlet duct removal
 
Performance presentation 2013
Performance presentation 2013Performance presentation 2013
Performance presentation 2013
 
Forklift training - refresher course
Forklift training - refresher courseForklift training - refresher course
Forklift training - refresher course
 
1. jar 25 speeds
1. jar 25 speeds1. jar 25 speeds
1. jar 25 speeds
 
Crane Hoist Operations
Crane Hoist OperationsCrane Hoist Operations
Crane Hoist Operations
 
Take Off And Landing Performance
Take Off And Landing PerformanceTake Off And Landing Performance
Take Off And Landing Performance
 
Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook
 
Fork lift training on 21th sep 13
Fork lift training on 21th sep 13Fork lift training on 21th sep 13
Fork lift training on 21th sep 13
 
Forllift safety
Forllift safetyForllift safety
Forllift safety
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 

Viewers also liked

SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...João Henrique Volpini Mattos
 
Vetter Material Handling Equipments - German Gulf Enterprises Ltd
Vetter Material Handling Equipments - German Gulf Enterprises LtdVetter Material Handling Equipments - German Gulf Enterprises Ltd
Vetter Material Handling Equipments - German Gulf Enterprises LtdGerman Gulf Enterprises Ltd
 
Check list for crane inspection, B C Das
Check list for crane inspection, B C DasCheck list for crane inspection, B C Das
Check list for crane inspection, B C DasBimal Chandra Das
 
Crane inspection
Crane inspectionCrane inspection
Crane inspectionAdnan Dar
 
Schillings crane inspection adelaide
Schillings crane inspection adelaideSchillings crane inspection adelaide
Schillings crane inspection adelaideSchilling s
 
İş kurma süreci
İş kurma süreciİş kurma süreci
İş kurma süreciGirişimTR
 
Crane safety by abidnadeemkhan
Crane safety by abidnadeemkhanCrane safety by abidnadeemkhan
Crane safety by abidnadeemkhanguest3d4fa4
 
EOT Crane Inspection Check list, helpful for safety officers during inspection
EOT Crane Inspection Check list, helpful for safety officers during inspectionEOT Crane Inspection Check list, helpful for safety officers during inspection
EOT Crane Inspection Check list, helpful for safety officers during inspectionBimal Chandra Das
 
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANES
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANESBs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANES
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANESANA ISABEL R.R.
 
Tower Crane Installation Work
Tower Crane Installation WorkTower Crane Installation Work
Tower Crane Installation Worknittipurohit
 
Crane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpCrane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpMounir Bassaid
 
Daily mobile crane inspection checklist
Daily mobile crane inspection checklist  Daily mobile crane inspection checklist
Daily mobile crane inspection checklist Rahmat Mohamed
 
Tower crane Basics
Tower crane BasicsTower crane Basics
Tower crane Basicsrama24x7
 

Viewers also liked (20)

SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
SUC Brasil 2012 : Engineering Study for Barge Lifting Weight on Crane Barge O...
 
Apresentação Nauticus Hull Rule Check
Apresentação Nauticus Hull Rule CheckApresentação Nauticus Hull Rule Check
Apresentação Nauticus Hull Rule Check
 
Crane received on site inspection log
Crane received on site inspection logCrane received on site inspection log
Crane received on site inspection log
 
Vetter Material Handling Equipments - German Gulf Enterprises Ltd
Vetter Material Handling Equipments - German Gulf Enterprises LtdVetter Material Handling Equipments - German Gulf Enterprises Ltd
Vetter Material Handling Equipments - German Gulf Enterprises Ltd
 
Check list for crane inspection, B C Das
Check list for crane inspection, B C DasCheck list for crane inspection, B C Das
Check list for crane inspection, B C Das
 
Crane inspection
Crane inspectionCrane inspection
Crane inspection
 
Schillings crane inspection adelaide
Schillings crane inspection adelaideSchillings crane inspection adelaide
Schillings crane inspection adelaide
 
Crane wire rope damage and inspection methods
Crane wire rope damage and inspection methodsCrane wire rope damage and inspection methods
Crane wire rope damage and inspection methods
 
İş kurma süreci
İş kurma süreciİş kurma süreci
İş kurma süreci
 
Crane safety by abidnadeemkhan
Crane safety by abidnadeemkhanCrane safety by abidnadeemkhan
Crane safety by abidnadeemkhan
 
2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection2016 CRW - Hands-on Crane Inspection
2016 CRW - Hands-on Crane Inspection
 
2014 CRW - Best Practices for Wire Rope Installation
2014 CRW - Best Practices for Wire Rope Installation2014 CRW - Best Practices for Wire Rope Installation
2014 CRW - Best Practices for Wire Rope Installation
 
EOT Crane Inspection Check list, helpful for safety officers during inspection
EOT Crane Inspection Check list, helpful for safety officers during inspectionEOT Crane Inspection Check list, helpful for safety officers during inspection
EOT Crane Inspection Check list, helpful for safety officers during inspection
 
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANES
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANESBs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANES
Bs 7121 2º INSPECTION, TESTING AND EXAMINATION-CRANES
 
Tower Crane Installation Work
Tower Crane Installation WorkTower Crane Installation Work
Tower Crane Installation Work
 
Crane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpCrane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttp
 
Daily mobile crane inspection checklist
Daily mobile crane inspection checklist  Daily mobile crane inspection checklist
Daily mobile crane inspection checklist
 
Wire rope
Wire ropeWire rope
Wire rope
 
Tower crane Basics
Tower crane BasicsTower crane Basics
Tower crane Basics
 
Overhead Crane
Overhead CraneOverhead Crane
Overhead Crane
 

Similar to 0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT

Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockSrinivasaRao Guduru
 
Design of Gantry Girders (1).pptx
Design of Gantry Girders (1).pptxDesign of Gantry Girders (1).pptx
Design of Gantry Girders (1).pptxNachiketKadlag1
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IAtlantic Training, LLC.
 
WAGON TEST EQUIPMENTS.pdf
WAGON TEST EQUIPMENTS.pdfWAGON TEST EQUIPMENTS.pdf
WAGON TEST EQUIPMENTS.pdfTCCW1
 
ESCORT TUG GIRTING ASSESSMENT
ESCORT TUG GIRTING ASSESSMENTESCORT TUG GIRTING ASSESSMENT
ESCORT TUG GIRTING ASSESSMENTLearnmarine
 
Liftingproedure
LiftingproedureLiftingproedure
LiftingproedureZhai Rull
 
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoist
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoistEnerpac shs-series-sync hoist-load-positioning-hydraulic-hoist
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoistHi Press Hydrualics Ltd
 
Mototok Radio-Controlled Aircraft/Helicopter Tug
Mototok Radio-Controlled Aircraft/Helicopter TugMototok Radio-Controlled Aircraft/Helicopter Tug
Mototok Radio-Controlled Aircraft/Helicopter TugAbdo Ali
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfssuseref23d3
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Flbs36 sf6 switch disconnector
Flbs36 sf6 switch disconnectorFlbs36 sf6 switch disconnector
Flbs36 sf6 switch disconnectorJoeChueng
 
Back-off Procedure.docx
Back-off Procedure.docxBack-off Procedure.docx
Back-off Procedure.docxJalal Neshat
 

Similar to 0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT (20)

Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stock
 
Design of Gantry Girders (1).pptx
Design of Gantry Girders (1).pptxDesign of Gantry Girders (1).pptx
Design of Gantry Girders (1).pptx
 
Crane 123
Crane 123Crane 123
Crane 123
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&I
 
WAGON TEST EQUIPMENTS.pdf
WAGON TEST EQUIPMENTS.pdfWAGON TEST EQUIPMENTS.pdf
WAGON TEST EQUIPMENTS.pdf
 
ESCORT TUG GIRTING ASSESSMENT
ESCORT TUG GIRTING ASSESSMENTESCORT TUG GIRTING ASSESSMENT
ESCORT TUG GIRTING ASSESSMENT
 
Engineered Spring Supports V.2
Engineered Spring Supports V.2Engineered Spring Supports V.2
Engineered Spring Supports V.2
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Bridge loading
Bridge loadingBridge loading
Bridge loading
 
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoist
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoistEnerpac shs-series-sync hoist-load-positioning-hydraulic-hoist
Enerpac shs-series-sync hoist-load-positioning-hydraulic-hoist
 
Mototok Radio-Controlled Aircraft/Helicopter Tug
Mototok Radio-Controlled Aircraft/Helicopter TugMototok Radio-Controlled Aircraft/Helicopter Tug
Mototok Radio-Controlled Aircraft/Helicopter Tug
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
6-CRANE-수정
6-CRANE-수정6-CRANE-수정
6-CRANE-수정
 
PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
LTM 11200
LTM 11200LTM 11200
LTM 11200
 
Flbs36 sf6 switch disconnector
Flbs36 sf6 switch disconnectorFlbs36 sf6 switch disconnector
Flbs36 sf6 switch disconnector
 
Back-off Procedure.docx
Back-off Procedure.docxBack-off Procedure.docx
Back-off Procedure.docx
 
Mech.pdf
Mech.pdfMech.pdf
Mech.pdf
 
Mech.pdf
Mech.pdfMech.pdf
Mech.pdf
 

0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT

  • 1. COMMISSIONING & LOAD TESTING 5000 T CRANE Gusto model E-5000-SBX-L Location, Date Schiedam, 17 January 2011
  • 2. page 2 HLV Oleg Strashnov
  • 3. page 3 Agenda  Objectives  Safety  Organization  Commissioning (A/B/C – scope)  Load Testing  Ballast procedure Vessel  A-frame lowering/upending  After load testing  Clarifications
  • 4. page 4 Objectives Clarification of the presentation The purpose of this presentation is to provide information and instructions on how the CRANE will be commissioned and load tested in order to demonstrate the CRANE complies with the requirements of the contract. All the information and instructions together are bundled in a Commissioning & Load Testing Book which will be the theme of this presentation. The Commissioning & Load Testing Book comprises mainly of: • Safety Plan • Commissioning & Testing Manual • Load Testing Manual • Ballast Procedure Vessel
  • 5. page 5 Safety Safety issues: • Control of access / Controlled Area • Evacuation drill • Define interface with DFDS, IHC (ERT room), Gusto, Muller, Traffic Control of Port Authority • Personal protective • Weather (Conditions/Forecast) • Emergency response • Daily toolbox meeting
  • 6. page 6 Organization  Overall organization (IHC)  Commissioning & Load Testing organization (Gusto)  Overview members Commissioning & Load Testing team  Chain of Command
  • 7. page 7 Organization Overall Organization (IHC) Captain Overall Vessel Supervisor (IHC) Project Management IHC Oleg Strashnov Port Authority Port of Rotterdam Ronald van Son Traffic Control Vessel General Team (IHC) Vessel Ballasting Team (IHC) Crane Commissioning & Load Testing Team Johan de Bruin Jelmer Gerdingh Arie van Dijken
  • 8. page 8 Organization Commissioning & Load Testing organization (Gusto) Co-ordinator Commissioning Team Siemens Rob Reddering Sven Luessen Test Pontoons & Tug Boat Muller Transport Crane driver Kees Baggerman Rigger Foreman Test Pontoons & Test Weights Timo van Gils (Franklin) Ballast Engineer Test Pontoons Jack Verzijl (Muller) Co-ordinator Commissioning Team SAS Martin de Bruin Engineering Commissioning Co-ordinator Scott Marpole Arjo van Putten Superintendent Load Testing Procedures Cees de Heer HSSE Arie van Dijken Ballast Co-ordinator IHC Oleg Strashnov Jelmer Gerdingh Overall Co-ordinator Crane Commissioning & Load Testing
  • 9. page 9 Organization Overview members Commissioning & Load Testing Team Company Function / Discipline Name Telephone Substitution Telephone Gusto Overall Co-ordinator Arie van Dijken 06-20246992 Rob Kloos 06-25004734 Gusto Co-ordinator Procedures Cees de Heer 06-15839461 Arjo van Putten 06-11392295 Gusto Expert Engineer Arjo van Putten 06-11392295 Wim Woldring 06-46613154 Gusto Superintendent Rob Reddering Arie van Dijken 06-20246992 Gusto Co-ordinator Commissioning Scott Marpole 06-55734093 Zeljko Karels 06-11626334 Gusto Construction Manager Rob Kloos 06-25004734 Arie van Dijken 06-20246992 Gusto Project Manager Michael Roosen 06-29349662 Rob Kloos 06-25004734 Siemens Co-ordinator Commissioning Sven Luessen +49(174)1591961 Willy Maas SAS Co-ordinator Commissioning T.B.A. Martin de Bruin 06-51092561 Muller Captain Tugboat T.B.A. T.B.A. Muller Ballast Engineer Jack Verzijl 06-51987564 T.B.A. Franklin Rigger Foreman Timo van Gils 06-57568046 Jerry Bakx 06-57568042 IHC Captain T.B.A. T.B.A. IHC Vessel Co-ordinator Johan de Bruin 06-14010513 Jaco van Vlaanderen 06-12720790 IHC Ballast Co-ordinator Jelmer Gerdigh 06-21224624 Jelte Buiteman 06-51987564 IHC Crane driver Kees Baggerman 06-22239126 No replacement IHC Project Co-ordinator Marcel Smits 06-10429853 T.B.A. IHC Project Manager Ronaldvan Son 06-12268400 T.B.A.
  • 10. page 10 Commissioning A/B/C/ Scope Based on report provided by Scott at end of Thursday
  • 11. page 11 Load Testing  Load Testing Manual  Test Weights  Sling Arrangements  Load Testing Location  Load Testing Arrangements
  • 12. page 12 Load Testing Load Testing Manual The Load Testing Manual provides information and instructions on how the CRANE will be load tested in order to demonstrate the CRANE complies with the contractual requirements. The tests described are in agreement with the applicable DNV standard for Certification of Lifting Appliances January 2007, which is a reprint of the 1994 Rules. The load testing comprises of loading the CRANE with loads at corresponding radii as per load-radius curve. The loads at the breaking points in the curve have to be applied as a minimum, completed with an intermediate load at corresponding radius. The test loads chosen are based on the different load cases as per document GT264.CGG91010 5000 T Crane Loads on System Report showing the (high) loaded components.
  • 13. page 13 Load Testing Test weights Movable, certified weights will be used:  Test pontoon 256-2 for loads from 35 t up to 250 t  Test pontoon 5511 for loads from 250 t up to 1250 t  Test pontoon 6619 for loads from 1250 t up to 5500 t  Water bag for loads up to 35 t Because of their size the weight of the test pontoons cannot be checked with a separate load cell, therefore the test weight will be based on the certified own weight and amount of water ballast multiplied by the measured water density. The amount of water ballast will be based on the sounding tables of the ballast tanks of the test pontoon. The test weight including the weight of the required sling arrangement will be the total weight suspended in the hook of the applicable hoisting system.
  • 14. page 14 Load Testing Test Pontoon 256-2
  • 18. page 18 Load Testing Sling arrangements  Sling arrangement for test pontoon 256-2  Sling arrangement for test pontoon 5511  Sling arrangement for test pontoon 6619
  • 19. page 19 Load Testing Sling arrangement for test pontoon 256-2
  • 20. page 20 Load Testing Sling arrangement for test pontoon 5511
  • 21. page 21 Load Testing Sling arrangement for test pontoon 6619
  • 23. page 23 Load Testing Location of Load testing at DFDS terminal
  • 24. page 24 Load Testing Load Testing Arrangements – Whiphoist 110t @ 118m
  • 25. page 25 Load Testing Load Testing Arrangements – Aux. Hoist 1 500 t @ 113 m
  • 26. page 26 Load Testing Load Testing Arrangements – Aux. Hoist 1 800 t @ 72 m
  • 27. page 27 Load Testing Load Testing Arrangements – Main Hoist 740 t @ 84.5 m
  • 28. page 28 Load Testing Load Testing Arrangements – Main Hoist 3800 t @ 43 m
  • 29. page 29 Load Testing Load Testing Arrangements – Main Hoist 5000 t @ 32 m
  • 30. page 30 Ballast Procedure Vessel  Refer to Ballast System Operation Philosophy
  • 31. page 31 A-frame Lowering/Upending Due to limited height when passing the bridge over the Bosporus, the CRANE has the possibility to lower the A-frame to allow a safe passage. For lowering /upending the procudere is as follows: Lowering 1. Vessel must be even keel and preferably 1 - 2 trim (aft ship lower).⁰ ⁰ 2. Boom must be in the boom rest. Sea fastening (anti-rotation pins, ballast box support and safety clamp system) is not required to be engaged. 3. Lower blocks must be in the pockets and give slack wire till the load is on the pocket and not in the wires. Give not more rope than required to. When unexpected movements of the A-frame would occur, the weight of the blocks will help to keep the boom down. 4. Park trolley in middle of boom and position hook halfway between boom and deck. 5. Give rope of the boom winch till the rope load (indicated by the load pin at A-frame aft leg) has dropped till about 15 t.
  • 32. page 32 A-frame Lowering/Upending 6. Remove covers on boom hoist roof behind rope passage and make sure rope passage can travel backwards. 7. Make sure that hydraulic jacks at hinge points of A-frame aft leg are not pushing. Remove locking blocks at aft legs A-frame, two at each leg. 8. At both aft legs, two hydraulic jacks are mounted to push the A-frame. Both systems have there own manual, local controls. First push all jacks with a stroke of 50 mm. When at maximum pressure of 230 bar nothing happens, the cause of that must be investigated. 9. Push all jacks more or less simultaneously with steps to 100 mm, 150 mm and 200 mm. The maximum stroke is 250 mm. Make sure the A-frame can move without pulling on the hydraulic hoses.
  • 33. page 33 A-frame Lowering/Upending 10. Give boom rope with 5% speed until A-frame starts to lower or when rope load (indicated by the load pin at A-frame aft leg) has dropped till 4.6 t. Theoretically, it should start to move at 5.8 t. Rope pull at drum is then 4.5 t. 11. When A-frame didn’t start to move, push cylinder to maximum stroke. 12. When A-frame still doesn’t move, attach rope of both of load tuggers to the pad-eyes on mini A-frame. Set load tuggers in CT mode and increase the load until A-frame moves. Reduce the force to 1 t when A-frame is lowered more than 10 .⁰ 13. When hydraulic jacks are no more in contact with upper leg, pull in the jacks completely and push them 1 or 2 mm to be sure that no pressure is on the system. Now disconnect hydraulic hoses. 14. Give rope with the boom hoist until it’s final position is reached with a maximum speed of 10%. In the mean time rope has to be given on the MH1, MH2, AH1, AH2 and WH. This process has to be done in steps. After every step of A-frame lowering, lower blocks need to be given some rope. Also the rope force (indicated by the load pin at A-frame aft leg) has to be observed during lowering. Theoretically, the value must be 16.8 t at the lowest position. When it is exceeding 18.5 t, the operation has to be stopped to investigate the cause.
  • 34. page 34 A-frame Lowering/Upending Upending 1. Start upending the A-frame by booming in with boom hoist at a speed of maximum 10% until upper and lower leg are (almost) in line or rope load (indicated by the load pin at A-frame aft leg) has increased till 15 t. In the mean time rope has to be hauled in on the MH1, MH2, AH1, AH2 and WH. This process has to be done in steps. After every step of A-frame upending, the rope of the lower blocks need to be hauled in. Also the rope force (indicated by the load pin at A-frame aft leg) has to be observed during upending. 2. When gap at locking blocks is less than 15 mm, normal bolts can be installed and by fastening the bolts, gap will be closed. When gap is too large for the bolts, the force on the ropes can be increased till 20 t. It’s possible that the boom will start to lift while the blocks are in the block pockets. If this doesn’t help, threaded rods of 500 mm long can be used to pull upper and lower leg to each other. It might be needed to decrease the rope load to 10-15 t to reduce friction. 3. Bolts of locking blocks must be on the correct torque (2500 Nm). 4. Close covers on the boom hoist roof behind rope passage.
  • 36. page 36 After Load Testing General After execution of the load tests the CRANE, including gear accessories, has to be examined to observe whether any part has been damaged or permanently deformed by the test. Special attention has to be paid to high stressed spots and/or components of the CRANE which are indicated in so-called ‘ wolken tekeningen’ (clouds drawings). Dismantling and/or non-destructive testing may be required if deemed necessary by the Surveyor and/or SHL. The above applies to the lower blocks and loose gear as well. Any overload protection system and automatic safe load indicators that may have been disconnected or by-passed during the load testing have to be re- connected. Safety valves and or electrical circuit breakers have to be adjusted accordingly and set points have to be verified and sealed by the Surveyor.
  • 37. page 37 After Load Testing Activities to be executed after Load Testing The activities to be executed are, but not limited to, as follows:  Examine crane components for (permanently) damages or distortion. Components, location and method of examination as per so-called ‘ wolken tekeningen’ and within the discretion of the Surveyor and/or SHL.  Inspect all bolted or welded connections along with the boom, hoists and slew transmission.  Check and verify all bolting torques applied on main items.  Take oil/grease samples to determine to check for damage or wear  Check all components in systems for lubricating, air, hydraulic oil, etc. for leakage or damages