Manufacturing
Manufacturing
Resource
Resource
Planning
Planning
Hierarchical Planning Process
Hierarchical Planning Process
Items
Items
Product lines
Product lines
or families
or families
Individual
Individual
products
products
Components
Components
Manufacturing
Manufacturing
operations
operations
Resource
Resource
Level
Level
Plants
Plants
Individual
Individual
machines
machines
Critical
Critical
work
work
centers
centers
Production
Production
Planning
Planning
Capacity
Capacity
Planning
Planning
Resource
requirements
plan
Rough-cut
capacity
plan
Capacity
requirements
plan
Input/
output
control
Aggregate
production
plan
Master
production
schedule
Material
requirements
plan
Shop
floor
schedule
All
All
work
work
centers
centers
Figure 9.5
Figure 9.5
Forecast
Forecast
Material Requirements
Material Requirements
Planning
Planning
 Computerized inventory control &
Computerized inventory control &
production planning system
production planning system
 Schedules component items when
Schedules component items when
they are needed - no earlier and no
they are needed - no earlier and no
later
later
STRUCTURE OF MRP
STRUCTURE OF MRP
Material
requirements
planning
Planned
order
releases
Work
orders
Purchase
orders
Rescheduling
notices
Item
master
file
Product
structure
file
Master
production
schedule
Figure 12.5
Figure 12.5
Master Production
Master Production
Schedule
Schedule
 Drives MRP process with a schedule of
Drives MRP process with a schedule of
finished products
finished products
 Quantities represent production not
Quantities represent production not
demand
demand
 Quantities may consist of a combination of
Quantities may consist of a combination of
customer orders & demand forecasts
customer orders & demand forecasts
 Quantities represent what needs to be
Quantities represent what needs to be
produced, not what can be produced
produced, not what can be produced
Master Production
Master Production
Schedule
Schedule
PERIOD
PERIOD
MPS ITEM
MPS ITEM 1
1 2
2 3
3 4
4 5
5
Clipboard
Clipboard 85
85 95
95 120
120 100
100 100
100
Lapdesk
Lapdesk 0
0 50
50 0
0 50
50 0
0
Lapboard
Lapboard 75
75 120
120 47
47 20
20 17
17
Pencil Case
Pencil Case 125
125 125
125 125
125 125
125 125
125
BILL OF MATERIAL
BILL OF MATERIAL
(BOM)
(BOM)
Top clip (1) Bottom clip (1)
Pivot (1) Spring (1)
Rivets (2)
Finished clipboard Pressboard (1)
Clipboard
Product Structure Tree
Product Structure Tree
Clipboard Level 0
Level 0
Level 1
Level 1
Level 2
Level 2
Spring
(1)
Bottom Clip
(1)
Top Clip
(1)
Pivot
(1)
Rivets
(2)
Clip Ass’y
(1)
Pressboard
(1)
INVENTORY RECORD FILE
INVENTORY RECORD FILE
DESCRIPTION
DESCRIPTION INVENTORY POLICY
INVENTORY POLICY
Item
Item Pressboard
Pressboard Lead time
Lead time 1
1
Item no.
Item no. 734
734 Annual demand
Annual demand 5000
5000
Item type
Item type Purch
Purch Holding cost
Holding cost 1
1
Product/sales class
Product/sales class Comp
Comp Ordering/setup cost
Ordering/setup cost 50
50
Value class
Value class B
B Safety stock
Safety stock 0
0
Buyer/planner
Buyer/planner RSR
RSR Reorder point
Reorder point 39
39
Vendor/drawing
Vendor/drawing 07142
07142 EOQ
EOQ 316
316
Phantom code
Phantom code N
N Minimum order qty
Minimum order qty 100
100
Unit price/cost
Unit price/cost 1.25
1.25 Maximum order qty
Maximum order qty 500
500
Pegging
Pegging Y
Y Multiple order qty
Multiple order qty
LLC
LLC 1
1 Policy code
Policy code 3
3
Table 12.4
Table 12.4
Item Master File
Item Master File
PHYSICAL INVENTORY
PHYSICAL INVENTORY USAGE/SALES
USAGE/SALES
CODES
CODES
On hand
On hand 100
100 YTD usage/sales
YTD usage/sales 1100
1100
Location
Location W142
W142 MTD usage/sales
MTD usage/sales 75
75
On order
On order 100
100 YTD receipts
YTD receipts 1200
1200
Allocated
Allocated 75
75 MTD receipts
MTD receipts 0
0
Cycle
Cycle 3
3 Last receipt
Last receipt 8/25
8/25
Last count
Last count 9/5
9/5 Last issue
Last issue 10/5
10/5
Difference
Difference -2
-2
Cost acct.
Cost acct. 00754
00754
Routing
Routing 00326
00326
Engr
Engr 07142
07142
Table 12.4
Table 12.4
Basic MRP
Basic MRP
Processes
Processes
1.
1. Exploding the bill of material
Exploding the bill of material
2.
2. Netting out inventory
Netting out inventory
3.
3. Lot sizing
Lot sizing
4.
4. Time-phasing requirements
Time-phasing requirements
The MRP Matrix
The MRP Matrix
Gross Requirements
Gross Requirements Derived from MPS or planned
Derived from MPS or planned
order releases of the parent
order releases of the parent
Scheduled Receipts
Scheduled Receipts On order and scheduled to be
On order and scheduled to be
received
received
Projected on Hand
Projected on Hand Beg Inv
Beg Inv Anticipated quantity on hand at
Anticipated quantity on hand at
the end of the period
the end of the period
Net Requirements
Net Requirements Gross requirements net of
Gross requirements net of
inventory and scheduled
inventory and scheduled
receipts
receipts
Planned Order Receipts
Planned Order Receipts When orders need to be
When orders need to be
received
received
Planned Order Releases
Planned Order Releases When orders need to be placed
When orders need to be placed
to be received on time
to be received on time
ITEM NAME OR NO.
ITEM NAME OR NO. LLC - LOW LEVEL CODE
LLC - LOW LEVEL CODE PERIOD
PERIOD
LOT SIZE QTY MADE IN
LOT SIZE QTY MADE IN LT - LEAD TIME
LT - LEAD TIME 1
1 2
2 3
3 4
4 5
5
Table 12.5
Table 12.5
Basic MRP formulas
Basic MRP formulas
• Net Requirements = Gross Requirements –
scheduled receipts – On-hand
Inventory(previous period)
• Planned Order Receipt = function (Net
Requirements, order policy)
• Planned Order Release = Planned Order
Receipt backed up by the lead time
– Planned Order Releasei-LT = Planned Order
Receipti
More formulas
More formulas
• On-hand inventoryi = on-hand
inventoryi-1 + scheduled receiptsi +
Planned Order Releasei – Gross
Requirementsi
• Gross Requirements for next level
down are determined from the
Planned Order Releases at the level
above
On-hand inventory
On-hand inventory
• Is always the amount of on-inventory
at the end of the period
• All other items (gross req., net req.,
scheduled receipts, planned order
receipts) are amounts at the
beginning of the period
MRP Outputs
MRP Outputs
 Planned orders
Planned orders
Work orders
Work orders
Purchase orders
Purchase orders
 Changes to previous plans or
Changes to previous plans or
existing schedules
existing schedules
Action notices
Action notices
Rescheduling notices
Rescheduling notices
Planned Order Report
Planned Order Report
Table 12.6
Table 12.6
Item
Item #2740
#2740 Date
Date 9 - 25 - 02
9 - 25 - 02
On hand
On hand 100
100 Lead time
Lead time 2 weeks
2 weeks
On order
On order 200
200 Lot size
Lot size 200
200
Allocated
Allocated 50
50 Safety stock
Safety stock 50
50
SCHEDULED
SCHEDULED PROJECTED
PROJECTED
DATE
DATE ORDER NO.
ORDER NO. GROSS REQS.
GROSS REQS. RECEIPTS
RECEIPTS ON HAND
ON HAND ACTION
ACTION
50
50
9-26
9-26 AL 4416
AL 4416 25
25 25
25
9-30
9-30 AL 4147
AL 4147 25
25 0
0
10-01
10-01 GR 6470
GR 6470 50
50 - 50
- 50
10-08
10-08 SR 7542
SR 7542 200
200 150
150 Expedite SR 10-01
Expedite SR 10-01
10-10
10-10 CO 4471
CO 4471 75
75 75
75
10-15
10-15 GR 6471
GR 6471 50
50 25
25
10-23
10-23 GR 6471
GR 6471 25
25 0
0
10-27
10-27 GR 6473
GR 6473 50
50 - 50
- 50 Release PO 10-13
Release PO 10-13
Key:
Key: AL
AL = allocated
= allocated WO
WO = work order
= work order
CO
CO = customer order
= customer order SR
SR = scheduled receipt
= scheduled receipt
PO
PO = purchase order
= purchase order GR
GR = gross requirement
= gross requirement
MRP Action Report
MRP Action Report
Table 12.7
Table 12.7
Current date 9-25-02
Current date 9-25-02
ITEM
ITEM DATE
DATE ORDER NO.
ORDER NO. QTY.
QTY. ACTION
ACTION
#2740
#2740 10-08
10-08 7542
7542 200
200 Expedite
Expedite SR
SR 10-01
10-01
#3616
#3616 10-09
10-09 Move forward
Move forward PO
PO 10-07
10-07
#2412
#2412 10-10
10-10 Move forward
Move forward PO
PO 10-05
10-05
#3427
#3427 10-15
10-15 Move backward
Move backward PO
PO 10-25
10-25
#2516
#2516 10-20
10-20 7648
7648 100
100 De-expedite
De-expedite SR
SR 10-30
10-30
#2740
#2740 10-27
10-27 200
200 Release
Release PO
PO 10-13
10-13
#3666
#3666 10-31
10-31 50
50 Release
Release WO
WO 10-24
10-24
Manufacturing
Manufacturing
Resource
Resource
Planning
Planning
(MRP II)
(MRP II)
DEFINITION OF MRP-II &
DEFINITION OF MRP-II &
ITS FUNCTIONING
ITS FUNCTIONING
• MRP II stands for Manufacturing Resources Planning, a
computer modelling technique for analysing and controlling
complicated Manufacturing operations
• When the manufacturing data has been collected (parts,
assemblies, resources) the lead time and cost of every
component can be predicted under any manufacturing
conditions.
• As soon as an order is received the workload on the
manufacturing organisation and the delivery time can be
calculated.
• MRP II systems also keep track of customers,
suppliers and accounting functions.
• Inventory can be purchased and assemblies made
"Just in Time". The records kept by an MRP system
highlight inadequacies such as overloaded
production centres and delays by suppliers.
• The effect of new orders, changes in capacity,
shortages, delays and a myriad of other
disturbances are calculated and tracked with
confidence.
HOW MRP-II WORKS
HOW MRP-II WORKS
Forecast Aggregate
production
plan
Customer
orders
Feasible?
Master production
schedule
Material requirements
planning
Capacity requirements
planning
Feasible?
Purchase
orders
Work
orders
Inventory
Shop floor
control
Manufacture
No
No
Yes
Yes
Feedback
Feedback
No
No
Yes
Yes
BENEFITS OF MRP-II
BENEFITS OF MRP-II
- Reduced inventory.
- Accurately predicted delivery times.
- Accurate costing at every stage of the
manufacturing process.
- Improved use of manufacturing facilities.
- Faster response to changing conditions.
- Control of every stage of production

MANUFACTURING RESOURCE PLANNING Basics and concepts

  • 1.
  • 2.
    Hierarchical Planning Process HierarchicalPlanning Process Items Items Product lines Product lines or families or families Individual Individual products products Components Components Manufacturing Manufacturing operations operations Resource Resource Level Level Plants Plants Individual Individual machines machines Critical Critical work work centers centers Production Production Planning Planning Capacity Capacity Planning Planning Resource requirements plan Rough-cut capacity plan Capacity requirements plan Input/ output control Aggregate production plan Master production schedule Material requirements plan Shop floor schedule All All work work centers centers Figure 9.5 Figure 9.5 Forecast Forecast
  • 3.
    Material Requirements Material Requirements Planning Planning Computerized inventory control & Computerized inventory control & production planning system production planning system  Schedules component items when Schedules component items when they are needed - no earlier and no they are needed - no earlier and no later later
  • 4.
    STRUCTURE OF MRP STRUCTUREOF MRP Material requirements planning Planned order releases Work orders Purchase orders Rescheduling notices Item master file Product structure file Master production schedule Figure 12.5 Figure 12.5
  • 5.
    Master Production Master Production Schedule Schedule Drives MRP process with a schedule of Drives MRP process with a schedule of finished products finished products  Quantities represent production not Quantities represent production not demand demand  Quantities may consist of a combination of Quantities may consist of a combination of customer orders & demand forecasts customer orders & demand forecasts  Quantities represent what needs to be Quantities represent what needs to be produced, not what can be produced produced, not what can be produced
  • 6.
    Master Production Master Production Schedule Schedule PERIOD PERIOD MPSITEM MPS ITEM 1 1 2 2 3 3 4 4 5 5 Clipboard Clipboard 85 85 95 95 120 120 100 100 100 100 Lapdesk Lapdesk 0 0 50 50 0 0 50 50 0 0 Lapboard Lapboard 75 75 120 120 47 47 20 20 17 17 Pencil Case Pencil Case 125 125 125 125 125 125 125 125 125 125
  • 7.
    BILL OF MATERIAL BILLOF MATERIAL (BOM) (BOM) Top clip (1) Bottom clip (1) Pivot (1) Spring (1) Rivets (2) Finished clipboard Pressboard (1) Clipboard
  • 8.
    Product Structure Tree ProductStructure Tree Clipboard Level 0 Level 0 Level 1 Level 1 Level 2 Level 2 Spring (1) Bottom Clip (1) Top Clip (1) Pivot (1) Rivets (2) Clip Ass’y (1) Pressboard (1)
  • 9.
    INVENTORY RECORD FILE INVENTORYRECORD FILE DESCRIPTION DESCRIPTION INVENTORY POLICY INVENTORY POLICY Item Item Pressboard Pressboard Lead time Lead time 1 1 Item no. Item no. 734 734 Annual demand Annual demand 5000 5000 Item type Item type Purch Purch Holding cost Holding cost 1 1 Product/sales class Product/sales class Comp Comp Ordering/setup cost Ordering/setup cost 50 50 Value class Value class B B Safety stock Safety stock 0 0 Buyer/planner Buyer/planner RSR RSR Reorder point Reorder point 39 39 Vendor/drawing Vendor/drawing 07142 07142 EOQ EOQ 316 316 Phantom code Phantom code N N Minimum order qty Minimum order qty 100 100 Unit price/cost Unit price/cost 1.25 1.25 Maximum order qty Maximum order qty 500 500 Pegging Pegging Y Y Multiple order qty Multiple order qty LLC LLC 1 1 Policy code Policy code 3 3 Table 12.4 Table 12.4
  • 10.
    Item Master File ItemMaster File PHYSICAL INVENTORY PHYSICAL INVENTORY USAGE/SALES USAGE/SALES CODES CODES On hand On hand 100 100 YTD usage/sales YTD usage/sales 1100 1100 Location Location W142 W142 MTD usage/sales MTD usage/sales 75 75 On order On order 100 100 YTD receipts YTD receipts 1200 1200 Allocated Allocated 75 75 MTD receipts MTD receipts 0 0 Cycle Cycle 3 3 Last receipt Last receipt 8/25 8/25 Last count Last count 9/5 9/5 Last issue Last issue 10/5 10/5 Difference Difference -2 -2 Cost acct. Cost acct. 00754 00754 Routing Routing 00326 00326 Engr Engr 07142 07142 Table 12.4 Table 12.4
  • 11.
    Basic MRP Basic MRP Processes Processes 1. 1.Exploding the bill of material Exploding the bill of material 2. 2. Netting out inventory Netting out inventory 3. 3. Lot sizing Lot sizing 4. 4. Time-phasing requirements Time-phasing requirements
  • 12.
    The MRP Matrix TheMRP Matrix Gross Requirements Gross Requirements Derived from MPS or planned Derived from MPS or planned order releases of the parent order releases of the parent Scheduled Receipts Scheduled Receipts On order and scheduled to be On order and scheduled to be received received Projected on Hand Projected on Hand Beg Inv Beg Inv Anticipated quantity on hand at Anticipated quantity on hand at the end of the period the end of the period Net Requirements Net Requirements Gross requirements net of Gross requirements net of inventory and scheduled inventory and scheduled receipts receipts Planned Order Receipts Planned Order Receipts When orders need to be When orders need to be received received Planned Order Releases Planned Order Releases When orders need to be placed When orders need to be placed to be received on time to be received on time ITEM NAME OR NO. ITEM NAME OR NO. LLC - LOW LEVEL CODE LLC - LOW LEVEL CODE PERIOD PERIOD LOT SIZE QTY MADE IN LOT SIZE QTY MADE IN LT - LEAD TIME LT - LEAD TIME 1 1 2 2 3 3 4 4 5 5 Table 12.5 Table 12.5
  • 13.
    Basic MRP formulas BasicMRP formulas • Net Requirements = Gross Requirements – scheduled receipts – On-hand Inventory(previous period) • Planned Order Receipt = function (Net Requirements, order policy) • Planned Order Release = Planned Order Receipt backed up by the lead time – Planned Order Releasei-LT = Planned Order Receipti
  • 14.
    More formulas More formulas •On-hand inventoryi = on-hand inventoryi-1 + scheduled receiptsi + Planned Order Releasei – Gross Requirementsi • Gross Requirements for next level down are determined from the Planned Order Releases at the level above
  • 15.
    On-hand inventory On-hand inventory •Is always the amount of on-inventory at the end of the period • All other items (gross req., net req., scheduled receipts, planned order receipts) are amounts at the beginning of the period
  • 16.
    MRP Outputs MRP Outputs Planned orders Planned orders Work orders Work orders Purchase orders Purchase orders  Changes to previous plans or Changes to previous plans or existing schedules existing schedules Action notices Action notices Rescheduling notices Rescheduling notices
  • 17.
    Planned Order Report PlannedOrder Report Table 12.6 Table 12.6 Item Item #2740 #2740 Date Date 9 - 25 - 02 9 - 25 - 02 On hand On hand 100 100 Lead time Lead time 2 weeks 2 weeks On order On order 200 200 Lot size Lot size 200 200 Allocated Allocated 50 50 Safety stock Safety stock 50 50 SCHEDULED SCHEDULED PROJECTED PROJECTED DATE DATE ORDER NO. ORDER NO. GROSS REQS. GROSS REQS. RECEIPTS RECEIPTS ON HAND ON HAND ACTION ACTION 50 50 9-26 9-26 AL 4416 AL 4416 25 25 25 25 9-30 9-30 AL 4147 AL 4147 25 25 0 0 10-01 10-01 GR 6470 GR 6470 50 50 - 50 - 50 10-08 10-08 SR 7542 SR 7542 200 200 150 150 Expedite SR 10-01 Expedite SR 10-01 10-10 10-10 CO 4471 CO 4471 75 75 75 75 10-15 10-15 GR 6471 GR 6471 50 50 25 25 10-23 10-23 GR 6471 GR 6471 25 25 0 0 10-27 10-27 GR 6473 GR 6473 50 50 - 50 - 50 Release PO 10-13 Release PO 10-13 Key: Key: AL AL = allocated = allocated WO WO = work order = work order CO CO = customer order = customer order SR SR = scheduled receipt = scheduled receipt PO PO = purchase order = purchase order GR GR = gross requirement = gross requirement
  • 18.
    MRP Action Report MRPAction Report Table 12.7 Table 12.7 Current date 9-25-02 Current date 9-25-02 ITEM ITEM DATE DATE ORDER NO. ORDER NO. QTY. QTY. ACTION ACTION #2740 #2740 10-08 10-08 7542 7542 200 200 Expedite Expedite SR SR 10-01 10-01 #3616 #3616 10-09 10-09 Move forward Move forward PO PO 10-07 10-07 #2412 #2412 10-10 10-10 Move forward Move forward PO PO 10-05 10-05 #3427 #3427 10-15 10-15 Move backward Move backward PO PO 10-25 10-25 #2516 #2516 10-20 10-20 7648 7648 100 100 De-expedite De-expedite SR SR 10-30 10-30 #2740 #2740 10-27 10-27 200 200 Release Release PO PO 10-13 10-13 #3666 #3666 10-31 10-31 50 50 Release Release WO WO 10-24 10-24
  • 19.
  • 20.
    DEFINITION OF MRP-II& DEFINITION OF MRP-II & ITS FUNCTIONING ITS FUNCTIONING • MRP II stands for Manufacturing Resources Planning, a computer modelling technique for analysing and controlling complicated Manufacturing operations • When the manufacturing data has been collected (parts, assemblies, resources) the lead time and cost of every component can be predicted under any manufacturing conditions. • As soon as an order is received the workload on the manufacturing organisation and the delivery time can be calculated.
  • 21.
    • MRP IIsystems also keep track of customers, suppliers and accounting functions. • Inventory can be purchased and assemblies made "Just in Time". The records kept by an MRP system highlight inadequacies such as overloaded production centres and delays by suppliers. • The effect of new orders, changes in capacity, shortages, delays and a myriad of other disturbances are calculated and tracked with confidence.
  • 22.
    HOW MRP-II WORKS HOWMRP-II WORKS Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Feasible? Purchase orders Work orders Inventory Shop floor control Manufacture No No Yes Yes Feedback Feedback No No Yes Yes
  • 23.
    BENEFITS OF MRP-II BENEFITSOF MRP-II - Reduced inventory. - Accurately predicted delivery times. - Accurate costing at every stage of the manufacturing process. - Improved use of manufacturing facilities. - Faster response to changing conditions. - Control of every stage of production